SlideShare a Scribd company logo
1 of 3
Download to read offline
6lectric
Wh;des
rssuE2| 2010
A I A
Ct r I C sFonreHroNcRrncArENERG'rssuEsg t g
Tke Pubf,co A
Yatr P-rects
Tratts(ortt Re8alofzns
fnfa Pafenfio,
)
Plorrshr;t[ Puter
firc Aix(or
tl.e Futwe
Prey.ent
ftrc Flost
S?t ^gerYi
L
LL
, - . - - : f -
'-5t -1-
'*,
: y,,rww_synyrvllett p/orrr
af fl.€ Tu,c;vln 6lectr;c_
Pa,te.(T6Fl p/ont;
* Synyrville,
ftriurw,
;s s(a,.,tr;n tk {reyatdt
n early 2006, it became apparent that the attempt to
extend the life of the 1,500 MW coal fired Mohave
Generating Station (MGS) would not be successful
(SRP's20"/" porrion of MGS equaled 300MW's)' SRP
then had to scrambleto add new coal fired power generatlon
to replacethat lost by Mohave's closing.The option selected
was to construct Unit 4 at the Tucson Electric Power (TEP)
plant site outside Springerville,Arizona. Unit 4 had received
all the necessarypermits when both Units 3 and 4 were
permitted. Tri-State'sUnit 3 was nearing completion.
SRP's Board approved moving forward with the
Sprir-rgerville4 project on May L, 2006. The 400MW
subcriticalplant would beessentiallyidenticalto Unit 3, with
the addition of various modifications intended to improve
plant operability and reduce maintenance costs. Unit 4
wor-rldalso have the benefit of "lessons learned" from the
constructionand initial operationof Unit 3. Unit 4 would be
owned by SRPand operated by TEP.
Detail Engineering commenced immediately as studies
and preliminary engineeringwere unnecessarydue to the
replication of Unit 3. The boiler, steam turbine, generator
and air quality control system were awarded to the same
suppliers who had provided the Unit 3 equipment. The
project schedule was 44 months from start to commercial
operation. (A typical coal plant scheduleis 60 months or
more.) The prolect had to be completed and placed into
commercial operation by the end of 2009. This was dictated
by the expiration of the Air Permiton December3L, 2009.
Fortunateln SRP had an in-houseteam of experienced
project management professionals who had recently
constructed 1,L00 MW's of gas fired, combined cycle
power generation. Little did they know that Springerville4
was headed into the "perfect storm" in terms of material,
equipment and construction labor cost escalationcoupled
with a scarcity of qualified suppliers and contractors. The
,'r"/t-.' ;ri
{b}
's
projectwould ultimatelycost one billion dollars.
Becauseof the short schedule,it was determinedthat the
substructures(concreteand underground)work would need
to be awardedon unit pricesbasedon preliminaryquantities.
The award was made at approximately 507" completion of
the substructuresengineering.This, in turn, led to extensive
revisionsin constnction drawings.Drawing revisionsof 15 to
20 becamecommonplace.In fact,therewere instanceswhere
concretepours were actually halted due to the last minute
receiptof a reviseddrawing. This was further exacerbatedby
the very late receipt of vendor drawings. The vendors were
overloadedand had no ability to staff-up with experienced
people to handle their 2006 -2007 workloads' Along with
other new power plants, SRP would also be competing for
resourceswith many "back-end" emissionscontrolsproiects
mandated by the EPA.
Structural steel erection needed to commence within
a yearof the project'snotice to proceed.This was another
challengeasChinawaslockingup worldwide steelproduction.
SRP immediately went to a trusted steel supplier they had
usedon previousproiects.They told the steelsupplierto get
started and the paperwork would follow. The steelsupplier
turned down much larger proiects just two weeks after SRP
contractedwith them becausethey had reachedtheir capacity
limit. In fact, they had to use their alliance agreementswith
other steelsuppliers to ensuretimely delivery of SRP'ssteel.
The steel was fast-tracked through mill rr-rns,fabrication
drawings, shop fabrication and jobsite delivery. However,
it still became necessaryto issuea cost-plus contract to an
industry renowned steel erector who did exceptionally well
under very difficult circumstances;performing any necessary
modifications to the steel in the field as drawing revisions
continuedup to the last minute.
Next, a boiler erectorneededto beselected.Unfortunatel5
there were no takers. Everyone was busy on other projects.
SpecializedTransmissionLine
Services:
. LiDARAcquisitionandMapping
Serviceswith Towill's Leading-
Edge Technology 200 KlIz LiDAR
System
. Re-rating and Re-conductoring
Surveys
. ClearanceSurveys
. Vegetation Management Support
. Engineering Surveys for
Construction
. High Dehnition Digital Video
. Large Area DTM's
. Corridor Design Suveys
. Horizontal and Vertical Proiect
Control
. CadastralSwveys for Rigfrts of Way
There'smoreatMerrick
Merrick'sclient-focusedprojectdeliveryteamshaveservedtheenergyindustrysincethe
firm'sfoundingin1955.Atthecoreofourservicesisanunderstandingofyourbusiness,
operations,industry,andmarketplaceconditions.Thatunderstandingiscombinedwiththe
expertiseofthefirm'stalentedprofessionalstodelivervitalsolutionsthatwork.
Whenyou'relookingformore,callMerrick.
Contact:ChrisBiondolilo,PE- ProjectManager
2450SouthPeoriaStreet
Aurora,C080014-5475
303-353-3876
DlstribuledGeneration
RenewableEnergy
BiomassUtrlazation
ControlandDataAcquisition
MERRICK"
E conApEFiV
Employee0wned
TOWI LL |:,1,1'sl{'B;$l,r,t'n
303.974.7270ext.401
John.Bloodgood@towill.com
www.towill.com

More Related Content

What's hot

Cbems 149 b senior design poster
Cbems 149 b senior design posterCbems 149 b senior design poster
Cbems 149 b senior design posterMathew Shum
 
12160 power plant engineering
12160   power plant engineering12160   power plant engineering
12160 power plant engineeringOnkar768
 
Ronan Kerr: Exploring the Debris Disk Around Beta Pictoris
Ronan Kerr: Exploring the Debris Disk Around Beta PictorisRonan Kerr: Exploring the Debris Disk Around Beta Pictoris
Ronan Kerr: Exploring the Debris Disk Around Beta PictorisJeremyHeyl
 
Selected achievements - Operations machinery engineer
Selected achievements - Operations machinery engineerSelected achievements - Operations machinery engineer
Selected achievements - Operations machinery engineerChris Owen
 

What's hot (9)

Gas CCS in the UK - Tom Snow at the UKCCSRC Gas CCS Meeting, University of Su...
Gas CCS in the UK - Tom Snow at the UKCCSRC Gas CCS Meeting, University of Su...Gas CCS in the UK - Tom Snow at the UKCCSRC Gas CCS Meeting, University of Su...
Gas CCS in the UK - Tom Snow at the UKCCSRC Gas CCS Meeting, University of Su...
 
Kvaerner topsides
Kvaerner topsidesKvaerner topsides
Kvaerner topsides
 
Cbems 149 b senior design poster
Cbems 149 b senior design posterCbems 149 b senior design poster
Cbems 149 b senior design poster
 
Emdrive
EmdriveEmdrive
Emdrive
 
Orbital ATK Update WIRA Q2 April 12 2016
Orbital ATK Update WIRA Q2 April 12 2016Orbital ATK Update WIRA Q2 April 12 2016
Orbital ATK Update WIRA Q2 April 12 2016
 
12160 power plant engineering
12160   power plant engineering12160   power plant engineering
12160 power plant engineering
 
[Belle] Resume
[Belle] Resume[Belle] Resume
[Belle] Resume
 
Ronan Kerr: Exploring the Debris Disk Around Beta Pictoris
Ronan Kerr: Exploring the Debris Disk Around Beta PictorisRonan Kerr: Exploring the Debris Disk Around Beta Pictoris
Ronan Kerr: Exploring the Debris Disk Around Beta Pictoris
 
Selected achievements - Operations machinery engineer
Selected achievements - Operations machinery engineerSelected achievements - Operations machinery engineer
Selected achievements - Operations machinery engineer
 

Viewers also liked

16 04 19- WPC Webinar
16 04 19- WPC Webinar16 04 19- WPC Webinar
16 04 19- WPC WebinarRay Jussila
 
AACEI WPC Project Control Webinar Apr 19, 2016
AACEI WPC Project Control Webinar Apr 19, 2016AACEI WPC Project Control Webinar Apr 19, 2016
AACEI WPC Project Control Webinar Apr 19, 2016Ray Jussila
 
AACEI WPC Project Control Webinar Apr 19, 2016
AACEI WPC Project Control Webinar Apr 19, 2016AACEI WPC Project Control Webinar Apr 19, 2016
AACEI WPC Project Control Webinar Apr 19, 2016Ray Jussila
 
Prematurez
PrematurezPrematurez
PrematurezDharinka
 
2013 designsbyonye_look_book
2013 designsbyonye_look_book2013 designsbyonye_look_book
2013 designsbyonye_look_bookOnye Ndika
 
What is (and isn't) a lean startup
What is (and isn't) a lean startupWhat is (and isn't) a lean startup
What is (and isn't) a lean startup"Alan "Al"" Davis
 
Compass-DI-Brochure-2016-Web
Compass-DI-Brochure-2016-WebCompass-DI-Brochure-2016-Web
Compass-DI-Brochure-2016-WebPaul Rebeil, SPHR
 
What is (and isn't) a lean startup
What is (and isn't) a lean startupWhat is (and isn't) a lean startup
What is (and isn't) a lean startup"Alan "Al"" Davis
 
Výukové investiční balíčky Finlord
Výukové investiční balíčky FinlordVýukové investiční balíčky Finlord
Výukové investiční balíčky Finlord♛ Eva Mahdalová
 

Viewers also liked (16)

16 04 19- WPC Webinar
16 04 19- WPC Webinar16 04 19- WPC Webinar
16 04 19- WPC Webinar
 
AACEI WPC Project Control Webinar Apr 19, 2016
AACEI WPC Project Control Webinar Apr 19, 2016AACEI WPC Project Control Webinar Apr 19, 2016
AACEI WPC Project Control Webinar Apr 19, 2016
 
AACEI WPC Project Control Webinar Apr 19, 2016
AACEI WPC Project Control Webinar Apr 19, 2016AACEI WPC Project Control Webinar Apr 19, 2016
AACEI WPC Project Control Webinar Apr 19, 2016
 
Prematurez
PrematurezPrematurez
Prematurez
 
Mapas conceptuales planteamiento del problema
Mapas conceptuales planteamiento del problemaMapas conceptuales planteamiento del problema
Mapas conceptuales planteamiento del problema
 
research preliminary data
research preliminary dataresearch preliminary data
research preliminary data
 
2013 designsbyonye_look_book
2013 designsbyonye_look_book2013 designsbyonye_look_book
2013 designsbyonye_look_book
 
P2P PŮJČKY A INVESTICE
P2P PŮJČKY A INVESTICEP2P PŮJČKY A INVESTICE
P2P PŮJČKY A INVESTICE
 
Spoření
Spoření Spoření
Spoření
 
Resume
ResumeResume
Resume
 
What is (and isn't) a lean startup
What is (and isn't) a lean startupWhat is (and isn't) a lean startup
What is (and isn't) a lean startup
 
Compass-DI-Brochure-2016-Web
Compass-DI-Brochure-2016-WebCompass-DI-Brochure-2016-Web
Compass-DI-Brochure-2016-Web
 
What is (and isn't) a lean startup
What is (and isn't) a lean startupWhat is (and isn't) a lean startup
What is (and isn't) a lean startup
 
Úvěry
ÚvěryÚvěry
Úvěry
 
Pojištění
PojištěníPojištění
Pojištění
 
Výukové investiční balíčky Finlord
Výukové investiční balíčky FinlordVýukové investiční balíčky Finlord
Výukové investiční balíčky Finlord
 

Similar to SRP's Springerville Electric Unit 4: Overcoming Challenges

AISI Direct Steelmaking Final Report
AISI Direct Steelmaking Final ReportAISI Direct Steelmaking Final Report
AISI Direct Steelmaking Final ReportRobert Meegan
 
Steel Plant Layout: Civil Engineering perspective
Steel Plant Layout: Civil Engineering perspectiveSteel Plant Layout: Civil Engineering perspective
Steel Plant Layout: Civil Engineering perspectiveIRJET Journal
 
THE USE OF 700 C FOR CARBON FREE
THE USE OF 700 C FOR CARBON FREETHE USE OF 700 C FOR CARBON FREE
THE USE OF 700 C FOR CARBON FREERAVI PRAJAPATI
 
SAG 2011 paper #144
SAG 2011 paper #144SAG 2011 paper #144
SAG 2011 paper #144John Hadaway
 
CV Yoseph Prakosa Senior Elec Eng
CV Yoseph Prakosa Senior Elec EngCV Yoseph Prakosa Senior Elec Eng
CV Yoseph Prakosa Senior Elec Engyoseph prakosa S
 
Adoption of supercritical technology (1)
Adoption of supercritical technology (1)Adoption of supercritical technology (1)
Adoption of supercritical technology (1)HARSHIT GUPTA
 
Parabolic trough collectors comparison
Parabolic trough collectors comparisonParabolic trough collectors comparison
Parabolic trough collectors comparisonSolarReference
 
Ibrahim Nabawy CV 3 .2017
Ibrahim Nabawy CV 3 .2017Ibrahim Nabawy CV 3 .2017
Ibrahim Nabawy CV 3 .2017Ibrahim Nabawy
 
01-Turchi - sCO2 Power Cycle for CSP SunShot Summit 2016-04-19 Rev5.pptx
01-Turchi - sCO2 Power Cycle for CSP SunShot Summit 2016-04-19 Rev5.pptx01-Turchi - sCO2 Power Cycle for CSP SunShot Summit 2016-04-19 Rev5.pptx
01-Turchi - sCO2 Power Cycle for CSP SunShot Summit 2016-04-19 Rev5.pptxlalitkhekswani
 
Sam Sun_Sr. Mechanical Engineer
Sam Sun_Sr. Mechanical EngineerSam Sun_Sr. Mechanical Engineer
Sam Sun_Sr. Mechanical EngineerSam Sun
 
Ultra super critical power plant materials
Ultra super critical power plant materialsUltra super critical power plant materials
Ultra super critical power plant materialsS S Ananthan Ananthan
 
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...Global CCS Institute
 
Partial List of Past SAVvy Engineering Projects
Partial List of Past SAVvy Engineering ProjectsPartial List of Past SAVvy Engineering Projects
Partial List of Past SAVvy Engineering ProjectsScott Vierstra
 
'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...
'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...
'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...Global CCS Institute
 
Overview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _VhoraOverview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _VhoraProSIM R & D Pvt. Ltd.
 
Coherent_Jets_in_Steelmaking_Principles_and_Learni.pdf
Coherent_Jets_in_Steelmaking_Principles_and_Learni.pdfCoherent_Jets_in_Steelmaking_Principles_and_Learni.pdf
Coherent_Jets_in_Steelmaking_Principles_and_Learni.pdfOmarCuts
 
Breaking Paradigms in old Fields. Finding “the reservoir key” for Mature Fiel...
Breaking Paradigms in old Fields. Finding “the reservoir key” for Mature Fiel...Breaking Paradigms in old Fields. Finding “the reservoir key” for Mature Fiel...
Breaking Paradigms in old Fields. Finding “the reservoir key” for Mature Fiel...Juan Diego Suarez Fromm
 
Time dependent behaviour of a class f fly ash-based geopolymer concrete
Time dependent behaviour of a class f fly ash-based geopolymer concreteTime dependent behaviour of a class f fly ash-based geopolymer concrete
Time dependent behaviour of a class f fly ash-based geopolymer concreteeSAT Publishing House
 

Similar to SRP's Springerville Electric Unit 4: Overcoming Challenges (20)

AISI Direct Steelmaking Final Report
AISI Direct Steelmaking Final ReportAISI Direct Steelmaking Final Report
AISI Direct Steelmaking Final Report
 
Steel Plant Layout: Civil Engineering perspective
Steel Plant Layout: Civil Engineering perspectiveSteel Plant Layout: Civil Engineering perspective
Steel Plant Layout: Civil Engineering perspective
 
THE USE OF 700 C FOR CARBON FREE
THE USE OF 700 C FOR CARBON FREETHE USE OF 700 C FOR CARBON FREE
THE USE OF 700 C FOR CARBON FREE
 
SAG 2011 paper #144
SAG 2011 paper #144SAG 2011 paper #144
SAG 2011 paper #144
 
CV Yoseph Prakosa Senior Elec Eng
CV Yoseph Prakosa Senior Elec EngCV Yoseph Prakosa Senior Elec Eng
CV Yoseph Prakosa Senior Elec Eng
 
Adoption of supercritical technology (1)
Adoption of supercritical technology (1)Adoption of supercritical technology (1)
Adoption of supercritical technology (1)
 
Parabolic trough collectors comparison
Parabolic trough collectors comparisonParabolic trough collectors comparison
Parabolic trough collectors comparison
 
Ibrahim Nabawy CV 3 .2017
Ibrahim Nabawy CV 3 .2017Ibrahim Nabawy CV 3 .2017
Ibrahim Nabawy CV 3 .2017
 
01-Turchi - sCO2 Power Cycle for CSP SunShot Summit 2016-04-19 Rev5.pptx
01-Turchi - sCO2 Power Cycle for CSP SunShot Summit 2016-04-19 Rev5.pptx01-Turchi - sCO2 Power Cycle for CSP SunShot Summit 2016-04-19 Rev5.pptx
01-Turchi - sCO2 Power Cycle for CSP SunShot Summit 2016-04-19 Rev5.pptx
 
Sam Sun_Sr. Mechanical Engineer
Sam Sun_Sr. Mechanical EngineerSam Sun_Sr. Mechanical Engineer
Sam Sun_Sr. Mechanical Engineer
 
Ultra super critical power plant materials
Ultra super critical power plant materialsUltra super critical power plant materials
Ultra super critical power plant materials
 
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
Webinar: 'Applying carbon capture and storage to a Chinese steel plant.' Feas...
 
Partial List of Past SAVvy Engineering Projects
Partial List of Past SAVvy Engineering ProjectsPartial List of Past SAVvy Engineering Projects
Partial List of Past SAVvy Engineering Projects
 
'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...
'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...
'Applying carbon capture and storage to a Chinese steel plant.' Feasibility s...
 
Overview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _VhoraOverview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _Vhora
 
Coherent_Jets_in_Steelmaking_Principles_and_Learni.pdf
Coherent_Jets_in_Steelmaking_Principles_and_Learni.pdfCoherent_Jets_in_Steelmaking_Principles_and_Learni.pdf
Coherent_Jets_in_Steelmaking_Principles_and_Learni.pdf
 
Breaking Paradigms in old Fields. Finding “the reservoir key” for Mature Fiel...
Breaking Paradigms in old Fields. Finding “the reservoir key” for Mature Fiel...Breaking Paradigms in old Fields. Finding “the reservoir key” for Mature Fiel...
Breaking Paradigms in old Fields. Finding “the reservoir key” for Mature Fiel...
 
ge turbine
 ge  turbine ge  turbine
ge turbine
 
Time dependent behaviour of a class f fly ash-based geopolymer concrete
Time dependent behaviour of a class f fly ash-based geopolymer concreteTime dependent behaviour of a class f fly ash-based geopolymer concrete
Time dependent behaviour of a class f fly ash-based geopolymer concrete
 
The Peterhead Carbon Capture and Storage Project - plenary presentation given...
The Peterhead Carbon Capture and Storage Project - plenary presentation given...The Peterhead Carbon Capture and Storage Project - plenary presentation given...
The Peterhead Carbon Capture and Storage Project - plenary presentation given...
 

SRP's Springerville Electric Unit 4: Overcoming Challenges

  • 1. 6lectric Wh;des rssuE2| 2010 A I A Ct r I C sFonreHroNcRrncArENERG'rssuEsg t g Tke Pubf,co A Yatr P-rects Tratts(ortt Re8alofzns fnfa Pafenfio, ) Plorrshr;t[ Puter firc Aix(or tl.e Futwe Prey.ent ftrc Flost S?t ^gerYi
  • 2. L LL , - . - - : f - '-5t -1- '*, : y,,rww_synyrvllett p/orrr af fl.€ Tu,c;vln 6lectr;c_ Pa,te.(T6Fl p/ont; * Synyrville, ftriurw, ;s s(a,.,tr;n tk {reyatdt n early 2006, it became apparent that the attempt to extend the life of the 1,500 MW coal fired Mohave Generating Station (MGS) would not be successful (SRP's20"/" porrion of MGS equaled 300MW's)' SRP then had to scrambleto add new coal fired power generatlon to replacethat lost by Mohave's closing.The option selected was to construct Unit 4 at the Tucson Electric Power (TEP) plant site outside Springerville,Arizona. Unit 4 had received all the necessarypermits when both Units 3 and 4 were permitted. Tri-State'sUnit 3 was nearing completion. SRP's Board approved moving forward with the Sprir-rgerville4 project on May L, 2006. The 400MW subcriticalplant would beessentiallyidenticalto Unit 3, with the addition of various modifications intended to improve plant operability and reduce maintenance costs. Unit 4 wor-rldalso have the benefit of "lessons learned" from the constructionand initial operationof Unit 3. Unit 4 would be owned by SRPand operated by TEP. Detail Engineering commenced immediately as studies and preliminary engineeringwere unnecessarydue to the replication of Unit 3. The boiler, steam turbine, generator and air quality control system were awarded to the same suppliers who had provided the Unit 3 equipment. The project schedule was 44 months from start to commercial operation. (A typical coal plant scheduleis 60 months or more.) The prolect had to be completed and placed into commercial operation by the end of 2009. This was dictated by the expiration of the Air Permiton December3L, 2009. Fortunateln SRP had an in-houseteam of experienced project management professionals who had recently constructed 1,L00 MW's of gas fired, combined cycle power generation. Little did they know that Springerville4 was headed into the "perfect storm" in terms of material, equipment and construction labor cost escalationcoupled with a scarcity of qualified suppliers and contractors. The ,'r"/t-.' ;ri {b} 's projectwould ultimatelycost one billion dollars. Becauseof the short schedule,it was determinedthat the substructures(concreteand underground)work would need to be awardedon unit pricesbasedon preliminaryquantities. The award was made at approximately 507" completion of the substructuresengineering.This, in turn, led to extensive revisionsin constnction drawings.Drawing revisionsof 15 to 20 becamecommonplace.In fact,therewere instanceswhere concretepours were actually halted due to the last minute receiptof a reviseddrawing. This was further exacerbatedby the very late receipt of vendor drawings. The vendors were overloadedand had no ability to staff-up with experienced people to handle their 2006 -2007 workloads' Along with other new power plants, SRP would also be competing for resourceswith many "back-end" emissionscontrolsproiects mandated by the EPA. Structural steel erection needed to commence within a yearof the project'snotice to proceed.This was another challengeasChinawaslockingup worldwide steelproduction. SRP immediately went to a trusted steel supplier they had usedon previousproiects.They told the steelsupplierto get started and the paperwork would follow. The steelsupplier turned down much larger proiects just two weeks after SRP contractedwith them becausethey had reachedtheir capacity limit. In fact, they had to use their alliance agreementswith other steelsuppliers to ensuretimely delivery of SRP'ssteel. The steel was fast-tracked through mill rr-rns,fabrication drawings, shop fabrication and jobsite delivery. However, it still became necessaryto issuea cost-plus contract to an industry renowned steel erector who did exceptionally well under very difficult circumstances;performing any necessary modifications to the steel in the field as drawing revisions continuedup to the last minute. Next, a boiler erectorneededto beselected.Unfortunatel5 there were no takers. Everyone was busy on other projects.
  • 3. SpecializedTransmissionLine Services: . LiDARAcquisitionandMapping Serviceswith Towill's Leading- Edge Technology 200 KlIz LiDAR System . Re-rating and Re-conductoring Surveys . ClearanceSurveys . Vegetation Management Support . Engineering Surveys for Construction . High Dehnition Digital Video . Large Area DTM's . Corridor Design Suveys . Horizontal and Vertical Proiect Control . CadastralSwveys for Rigfrts of Way There'smoreatMerrick Merrick'sclient-focusedprojectdeliveryteamshaveservedtheenergyindustrysincethe firm'sfoundingin1955.Atthecoreofourservicesisanunderstandingofyourbusiness, operations,industry,andmarketplaceconditions.Thatunderstandingiscombinedwiththe expertiseofthefirm'stalentedprofessionalstodelivervitalsolutionsthatwork. Whenyou'relookingformore,callMerrick. Contact:ChrisBiondolilo,PE- ProjectManager 2450SouthPeoriaStreet Aurora,C080014-5475 303-353-3876 DlstribuledGeneration RenewableEnergy BiomassUtrlazation ControlandDataAcquisition MERRICK" E conApEFiV Employee0wned TOWI LL |:,1,1'sl{'B;$l,r,t'n 303.974.7270ext.401 John.Bloodgood@towill.com www.towill.com