SlideShare a Scribd company logo
1 of 8
Download to read offline
marco.fleckenstein@de.abb.com
21, rue d’Artois, F-75008 PARIS CIGRE US National Committee
http://www.cigre.org 2019 Grid of the Future Symposium
Value Quantification of State-of-the-Art Condition Monitoring in
400kV Transmission System Substations
M. FLECKENSTEIN
ABB AG
Germany
L. ASGARIEH
ABB AG
Germany
C. ZEIDLER
ABB AG
Germany
SUMMARY
Digital substation and its monitoring systems is an “en vogue” topic again these days in the power
engineering community. Many system providers have put it back on the agenda and started their
promotion to sell their new holistic product offerings for substations. On the other hand, the
transmission system operators (TSO) are still not completely convinced to replace/retrofit substations
with "digital/sensored" equipment, because the added value is not visible on the first view and many
other subjects have a higher priority for TSO/DSO.
To determine the economic added value of monitoring systems within digital substations, a
Transmission Network Model (TNM) based on data from a German TSO was used in a grid
calculation tool with various scenarios of improved reliability and availability values. Based on these
values, the risk OPEX for the next 10 years will be calculated for all equipment in the 400 kV
switchgear. For the sake of simplification, this paper only illustrates the monitoring systems for power
transformers and circuit breakers in the 400 kV level.
A value-at-risk method is used to estimate the different risk costs of the assets. This methodology
considers repair, replacement and lost revenue costs by considering various occurrence moments of
the asset outages.
Based on the net present value with a 10-year period, it is determined, if a "digitization" of the
substations makes economic sense. Therefore, it is applied a variation of penalty fees for non-
delivered or feed-in electrical energy and span of prices for the sensor application. The results show a
strong dependency on the revenue losses due to energy not delivered, transferred or fed in, which are
also related to the penalty fees. Mission-critical substations always benefit from condition monitoring.
KEYWORDS
ASSET MANAGEMENT, CONDITION MONITORING, DIGITAL SUBSTATION, VALUE
QUANTIFICATION
2/8
1. Introduction
The German way against "global climate change" is unique. In 2011, directly after the Fukushima
disaster, the German government decided to accelerate the shutdown of nuclear power plants with the
last plant being out of service by 2022 [1]. Due to the public pressure the German government also
committed in 2019 to retire all lignite and hard coal power plants by 2038 [2]. Furthermore, the
regulation of network charges is tough to budgeting investments cost for the electrical transmission
and distribution systems and as a further side condition the feed-in of unregulated renewables is
further increasing [3]. Nevertheless, the TSO and DSO must adapt and expand the electrical network
for current feed-in modifications and future requirements. The application of sensors for monitoring
the equipment condition, has moved back to the agenda of many stakeholders of the power system
community after the price collapse of these various technologies within digital substations and its data
infrastructure [4]. This paper shows where and at what prices an added value exists for the operators of
such facilities. The methodology which was applied was already used for development of maintenance
strategies and other asset management tasks.
2. Basics for substation equipment risk determination
The benefits of digital substations are demonstrated with a transmission system model and an OPEX-
Risk cost assessment which is based on a Value-at-Risk Methodology by using Monte Carlo
Simulations to consider several equipment failure scenarios. The next subsections explain the
fundamental methodology to determine the risk associated with substation equipment [5].
2.1. Transmission System Model
The transmission network model (TNM) employed for this demonstration consists of three voltage
levels and is based on a subsection of the structure of a German TSO. It has been created within the
electrical power system software and contains 400 kV, 220 kV voltage level and ends with the vertical
feeding into the 110 kV network groups. These groups are summarized as an aggregated load, which
are used to simulate realistic load scenarios [6].
The highest voltage level is the 400 kV system and core of the TNM. The observed assets are in the
substations of this voltage level. TNM includes 60 substations, 23 power station connection points,
and ten coupling points to neighboring TSOs. The 400 kV network has a direct feed-in by 30 power
plant units with a net production of 18 GW [6].
Various types of substations are considered by modelling the network model. The structure of each
substation is reproduced in detail and is provided with the real switching settings which are important
for the reliability and availability calculations. TNM also considers the horizontal load. The
transmission capacities of the overhead lines are assumed as the only limiting boundary condition in
the regarded scenario. The voltage angles at the slack nodes, representing the neighboring
transmission system, are set to zero, which is the ideal case and has a transfer capacity to other TSOs
of around 29 GVA [7].
Age depended outage rates H are applied for the 400 kV assets within substations. An exception was
only made for the power plant connections. These are considered as ideal because these are on duty of
the power plant operators by German law.
Additionally, it should be noted that the outage rates of pantograph disconnectors are included in the
values of the bus bars, which are bay dependent. Figure 1 shows the age-dependent outage rates
of each busbar BB, circuit breaker (CB), disconnector (DIS), and power transformer (PTR).
A secondary axis for the power transformer is inserted on the left side. Each asset group consequently
has eight different failure rates. The individual financial characteristics of the assets are shown for
clarity in the results section.
3/8
Figure 1: Age distribution & dependent outage rates of the assets. [5][7].
The 220 kV transmission system is only modelled schematically and its assets’ outage impacts are not
simulated itself in reliability and availability calculations. But this level is necessary to get realistic
power flow conditions in the 400 kV transmission system. The 110 kV network groups are also partly
supplied by 220 kV/110 kV power transformers. In total 31 power plant units with a total net output of
10 GW are connected to the 220 kV network. It also has four coupling points to other TSOs, with a
total transmission capacity of around 4 GVA [5]. The 110 kV network groups represent the vertical
load of the transmission system model. These are supplied by the 220 kV and 400 kV networks
through power transformers. Power plants feeding directly into the 110 kV groups are not part of the
model. This voltage level is separated into 34 network groups and eight industrial network groups and
have a peak load of between 250 and 1200 MW.
The power plant units are implemented with different characteristics and their individual dynamic
performance in the model. Therefore, different power gradients inherent to the various types of power
plants, as well as their share of auxiliary power, are considered in the reliability and availability
calculations. The gross output of all power plant units is around 30 GW [8].
Ten typical load flow scenarios are used for these simulations with their different vertical load and
power plant scheduling, based on an analysis of the sorted annual vertical load curve of the
transmission system. The actual generation capacity of power plants always exceeds the consumption
of the 110 kV network groups. The surplus/shortfall of energy is imported/exported from the
neighboring transmission systems.
The schedules of the different types of power plants are determined by their typical operating hours.
For instance, gas power plants have fewer hours of operation, due to their high operating costs. A
portion of the gas power however remains constant at the power plants, as these are operated with
mine gas. These are promoted by the Renewal Energy Act (EEG) and may therefore always remain in
operation [8].
2.2. OPEX-risk costs determination of 400kV-Assets in substations
The determination of OPEX-risk costs contains the shortfall of revenue costs of individual assets,
which is based on the results of reliability and availability calculations multiplied with energy costs
and the typical follow-up costs e.g. repair/replacement costs KR.
An overview of the determination of OPEX-risk costs is illustrated in Figure 2. This process is
repeated many times within a Monte Carlo simulation. To clip out extreme values, which are
generated by the combination of variety of distribution functions, a Value at Risk (VaR) evaluation of
the data series is applied. Sorting the list of substations by their VaR then yields their priority list
[10][11]. The three green boxes illustrate the main input parameters: repair costs, reliability values
4/8
(Duration T of non-delivered or non-feed-in energy, Power P of non-delivered or non-feed-in energy)
and outage rate H. For every asset group a distribution function with repair costs is implemented. The
cost of repair for any asset is randomly re-drawn from this distribution for each simulation . The
characteristic values of the distribution functions of each asset groups are presented in the results
section. The green box “Reliability values” includes the database consisting of the reliability and
availability results under all load flow situations of the assets. By randomly re-drawing a value in each
simulation, different times of outage occurrence and the effects of the individual assets are considered.
i = 1 … N asset
Repair risk
RR = H * KR
Risik of non-delivered
energy
RND = H * TND * PND * KE
Risk of non-supplied
energy
RNS = H * TNS * PNS * KE
gND
gNS
∑
Asset risk R(i,s) of the
Asset i in simulation round s
H
KR
RND * gND
TND, PND
TNS, PNS
KE
RNS * gNS
Repair costs
Reliability
values
Outage Rate
Figure 2: Structure of asset risk determination [11].
The third green box is the outage rate. These outage rates of the assets are age dependent, as described
in subsection 2.1. Additionally, the outage rate is varied in each simulation according to a
normal distribution with a standard deviation of ten percent around the mean given by its age
dependent value.
Three further variables are required for the asset risk determination. The revenue loss by non-supplied
or non-delivered energy is specified by energy costs in €/MWh. With correction factors and
penalty payments can be considered for non-delivered or non-supplied energy. The asset risk
of simulation round is finally determined as the sum of the repair risk , the risk of non-
delivered energy and the risk of non-supplied energy .
Due to the use of many distribution functions and randomly selected features a great number of
simulations are required to minimize the impact of exceptional combinations.
After the determination of all individual OPEX- risk costs in a simulation round, these values are
assigned to its substation and capture the overall substation risk of the round. The substation risks for
each substation are formed from the summarization of the risk of all assets that are associated with it.
The Monte Carlo Simulation repeats this process M times. The overall evaluation of the individual
simulation runs in the Monte Carlo simulation is performed again according to the VaR method. In
this method, risk values are sorted by their magnitude and the confidence area is determined using a
specified confidence interval. With this interval, the extremes are filtered which result from
unfortunate combinations of distribution functions. A confidence interval of 0.95 and 10,000
simulation rounds are used, which are standard values in VaR calculations [10].
2.3. Applied key figures of condition monitoring
To determine the value of condition monitoring in these 400 kV substations, some assumptions are
made. On the one hand, the impact of the monitoring, and on the other hand, the costs of monitoring
with its sensor application must be estimated.
5/8
Many significant publications were done within CIGRE, covering the topic asset monitoring for high
voltage equipment [12][13][14]. According to these documents, failure rates for power transformers
can be reduced significantly, as shown in Figure 3.
Figure 3: Standard failure probability tree for power transformer [12].
The reliability values, which are shown in Figure 3, are applied together with the age-dependent
outage rates for the power transformer of section 2.1, to show the impact on the OPEX-risk costs.
For determining the improvement of circuit breaker availability, the key parameter for monitoring are
gas density, motor drive current and cabinet heater supervision [15]. Increasing the reliability of the
circuit breaker with Condition Monitoring, no public figures are yet available. In this paper, the
assumption has been made that the outage rate will be halved.
As a basic assumption for the costs of condition monitoring, basic costs of 60k€ for the power
transformer and 15k€ for the circuit breaker were considered. These values relate only to the sensors
and does not include the data connection, engineering and other costs, which are heavily dependent on
the individual network operator. Due to the high skepticism about these technologies, the depreciation
period is set to ten years.
3. Execution of scenarios
For illustration of the results, the number of substations is reduced to twelve. Table 1 lists these
substations acronyms, along with their layout and numbers of power transformers (PTR) and circuit
breakers (CB).
Table 1: Substation key data
SUBSTATION
ACRONYM
LAYOUT PTR CB SUBSTATION
ACRONYM
LAYOUT PTR CB
BI H4 2 4 LB DBT 3 8
BU TBT 4 12 MB DBT 0 6
DT H3 1 3 SB ET 1 1
ED DBT 1 6 UC DBT 3 10
KO DB 1 4 UR DBT 8 3
KR DB 3 7 WT TBT 3 10
Layout Acronyms:
DBT Double Busbar with Transfer Busbar TBT Trible Busbar with Transfer Busbar
H4 H-Connection with 4-Breakers H3 H-Connection with 3-Breakers
DB Double Busbar ET External Transformer
6/8
The substation risk values regarding the age-depended outage rates of the assets for these 12
substations are considered with the methodology, which is presented in the second section. For the
application of monitoring systems, associated outage values (see subsection 2.3) are applied and the
risk determination of substation was performed with the modified values. Additional scenarios have
been developed, to show different investment strategies respectively to show the best case, if it is
decided to replace the whole substation and equip all PTR and CB with monitoring systems. The
applied scenarios are:
Regular Status Quo of current equipment
Intensive Improved behavior of equipment if all assets will be refurbished
NEW Replacement of primary equipment inside of the substation
Online Regular Retrofit of current CB’s and PTR’s in the substation with sensors
Online New Replacement of all CB’s and PTR’s in the substation and installation of
sensors
3.1. Annual OPEX-Substation risk costs comparison
This subsection shows the annual OPEX-substation risk costs for all five scenarios with 50€ per MWh
of non-delivered or non-feeded-in energy costs, per asset outages within specific substation. Figure 4
illustrates that risks for all described scenarios. The annual risks vary greatly among the regarded
substations. The number of equipment is an essential but is not the dominant reason for the massive
gap between the highest risk (260 k€) and the lowest one (6 k€). It can be seen the implementation of
sensors significantly mitigate the risk. For example, the annual risk of substation BU, which has the
highest risk, was reduced from 260 k€/a to 82 k€/a by a full refurbishment.
Figure 4: Annual substation risk costs by scenario
It is worth noting that in BU the substation has been renewed within the last five years. This explains
the result gap between NEW and the other OPEX Substation risk costs for this plant. For the
substation BI, DT, ED and SB the condition monitoring has no significant importance. These facilities
have a high redundancy and have only repair/replacement cost risk. The share of loss of revenue with
energy costs of 50 €/MWh is minimal. Due to that situation an investment for additional equipment
has a lower priority.
3.2. Net present value determination for a ten-year period.
The reduction of operational risks always has impact on the investment costs. In Figure 5, the
development of the total net present values (NPV) is shown for different loss of revenues. In this case
a variation of energy costs for non-delivered or non-feed-in energy was done between 50 €/MWh and
7/8
300 €/MWh. The results are shown accumulated from left to right. This means that the results of WT
include the results of BU for all scenarios. Thus, the results could be considered for high price areas,
or for countries which have high penalties; e.g., non-services of power purchase agreements (PPA) or
any other non-delivery.
The order of importance of the substation was used for the sequence of condition monitoring and
respectively for the investment. The diagram shows that the total NPV is strongly depended on the
penalty fee for non-delivered and supplied energy. Assuming low penalties the investment in sensors
can only be recommended for the most important substations. For energy costs of 100 €/MWh and
higher, investment can however be recommended for all substations.
Figure 5: Net present value of the substations.
4. Conclusion
The use of sensors for switchgear is an excellent opportunity to increase the availability and the
service life. Even with minor penalties, a return of investment for the major switchgear can be
achieved within 10 years. This result is very impressive, since redundancy is very high within the
maximum voltage level compared to the lower levels.
The reduction of operational risk is only a partial aspect. Other options such as the adjustment of the
maintenance, which is not shown in this paper, or the extended life of the equipment and the resulting
shift of investment costs are not considered here.
In this paper, only figures with the state of the art are used in terms of condition monitoring. New
publications show that even more will be possible in the area of circuit breakers and power
transformers soon [15][16]. Furthermore, a condition monitoring for surge arresters promises
additional advantages. Although this component is considered one of the cheaper components in a
substation, its failure has a significant impact on the "valuable" assets [17].
8/8
BIBLIOGRAPHY
[1] Printed matter of the German Bundestag: Entwurf eines Dreizehnten Gesetzes zur Änderung des
Atomgesetzes, Drucksache 17/6070, Berlin, 6th
June 2011.
[2] BMWi: Eckpunkte zur Umsetzung der strukturpolitischen Empfehlungen der Kommission
„Wachstum, Struktur wandel und Beschäftigung“ für ein „Strukturstärkungsgesetz
Kohleregionen“, Berlin, 22nd
May 2019
[3] Diekmann J.: Regulierung der Stromnetze in Deutschland, Düsseldorf, 2007.
[4] Lopez J.: GE’s Journey toward Intelligent Digital Substations, Paris, 2016.
[5] Fleckenstein, M.; Neumann, C.; Balzer G.: Bay oriented & risk based maintenance for
transmission networks. 2014 CIGRE Conference on Power Systems, rep. 226, Bruessels,
Belgium, March 12th-14th, 2014.
[6] Fleckenstein, M.; Neumann, C.; Balzer, G.: Risk-oriented asset replacement within substations
in EHV transmission networks. 20th Conference of the electric power supply industry, Jeju,
Südkorea, October 26th – 30th, 2014.
[7] Schwan M.: Using the VDN Statistic on Incidents to Derive Component Reliability Data for
Probabilistic Reliability Analyses, 2005.
[8] Balzer G., Schorn C.: Life Cycle Costs Analysis of a Complete Air Insulated Substation, CIGRE
SC B3 Berlin 2007.
[9] Fleckenstein, M.; Neumann, C.; Balzer, G.: Risk assessment of aging power transformers in the
transmission network. Grid of the Future, Houston, USA, October 20th -21st, 2014
[10] Jorion P.: Value at Risk – The new Benchmark for controlling derivatives Risk, 3. Edition, New
York 2006.
[11] Fleckenstein, M.: Risikoorientierte Instandhaltung auf der Basis der Value-at-Risk Methode im
Übertragungsnetz, Technische Universität Darmstadt, Dissertation, 2015.
[12] WG A3.29: Economics of Transformer Management, CIGRE, document no. 248, 2004.
[13] WG A3.06: Final Report of the 2004-2007 International Enquiry on Reliability of High Voltage
Equipment, CIGRE, document no. 514, 2012.
[14] WG A3.29: Ageing High Voltage Substation Equipment and possible mitigation techniques,
CIGRE, document no. 725, 2018.
[15] WG A3.32: Non-Intrusive methods for condition assessment of distribution and transmission
switchgear, CIGRE, 2018
[16] Laitinen, T., Albrecht, R.: Wireless sensor units for acoustic monitoring of switching devices,
CIGRE Session, Paris, 2018.
[17] I. A. Metwally, M. Eladawy and E. A. Feilat, "Online condition monitoring of surge arresters
based on third-harmonic analysis of leakage current," in IEEE Transactions on Dielectrics and
Electrical Insulation, vol. 24, no. 4, pp. 2274-2281, 2017.

More Related Content

What's hot

Design and Experimental Results of Universal Electric Vehicle Charger Using DSP
Design and Experimental Results of Universal Electric Vehicle Charger Using DSPDesign and Experimental Results of Universal Electric Vehicle Charger Using DSP
Design and Experimental Results of Universal Electric Vehicle Charger Using DSPTELKOMNIKA JOURNAL
 
Cost Allocation of Reactive Power Using Matrix Methodology in Transmission Ne...
Cost Allocation of Reactive Power Using Matrix Methodology in Transmission Ne...Cost Allocation of Reactive Power Using Matrix Methodology in Transmission Ne...
Cost Allocation of Reactive Power Using Matrix Methodology in Transmission Ne...IJAAS Team
 
International Refereed Journal of Engineering and Science (IRJES)
International Refereed Journal of Engineering and Science (IRJES)International Refereed Journal of Engineering and Science (IRJES)
International Refereed Journal of Engineering and Science (IRJES)irjes
 
A Single-Phase Dual-Stage PV-Grid System with Active Filtering
A Single-Phase Dual-Stage PV-Grid System with Active FilteringA Single-Phase Dual-Stage PV-Grid System with Active Filtering
A Single-Phase Dual-Stage PV-Grid System with Active FilteringIAES-IJPEDS
 
An Improved UPQC Controller to Provide Grid-Voltage Regulation
An Improved UPQC Controller to Provide Grid-Voltage RegulationAn Improved UPQC Controller to Provide Grid-Voltage Regulation
An Improved UPQC Controller to Provide Grid-Voltage RegulationIJMTST Journal
 
Energy Storage | Fuel Security , Presented at Energy Institute, London
Energy Storage | Fuel Security , Presented at Energy Institute, LondonEnergy Storage | Fuel Security , Presented at Energy Institute, London
Energy Storage | Fuel Security , Presented at Energy Institute, LondonRebecca Markillie
 
Load types, estimation, grwoth, forecasting and duration curves
Load types, estimation, grwoth, forecasting and duration curvesLoad types, estimation, grwoth, forecasting and duration curves
Load types, estimation, grwoth, forecasting and duration curvesAzfar Rasool
 
Ifedi.Seminar Presenatation
Ifedi.Seminar PresenatationIfedi.Seminar Presenatation
Ifedi.Seminar PresenatationIfedi
 
CONTROL OF BATTERY OPERATED SYSTEM WITH A DC-DC BOOSTCONVERTER FED DSTATCOM U...
CONTROL OF BATTERY OPERATED SYSTEM WITH A DC-DC BOOSTCONVERTER FED DSTATCOM U...CONTROL OF BATTERY OPERATED SYSTEM WITH A DC-DC BOOSTCONVERTER FED DSTATCOM U...
CONTROL OF BATTERY OPERATED SYSTEM WITH A DC-DC BOOSTCONVERTER FED DSTATCOM U...ijiert bestjournal
 
T04201162168Optimal Allocation of FACTS Device with Multiple Objectives Using...
T04201162168Optimal Allocation of FACTS Device with Multiple Objectives Using...T04201162168Optimal Allocation of FACTS Device with Multiple Objectives Using...
T04201162168Optimal Allocation of FACTS Device with Multiple Objectives Using...IJMER
 
212741860 assignment
212741860 assignment212741860 assignment
212741860 assignmenthomeworkping8
 
Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...
Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...
Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...Power System Operation
 
Profitability of frequency_regulation_by_electric_car
Profitability of frequency_regulation_by_electric_carProfitability of frequency_regulation_by_electric_car
Profitability of frequency_regulation_by_electric_carZedrickKhan2
 
roy_emmerich-eurec_dissertation-summary_paper-final
roy_emmerich-eurec_dissertation-summary_paper-finalroy_emmerich-eurec_dissertation-summary_paper-final
roy_emmerich-eurec_dissertation-summary_paper-finalRoy Emmerich
 
USAGE BASED COST ALLOCATION TECHNIQUE FOR EHV NETWORKS USING NON-LINEAR UTILI...
USAGE BASED COST ALLOCATION TECHNIQUE FOR EHV NETWORKS USING NON-LINEAR UTILI...USAGE BASED COST ALLOCATION TECHNIQUE FOR EHV NETWORKS USING NON-LINEAR UTILI...
USAGE BASED COST ALLOCATION TECHNIQUE FOR EHV NETWORKS USING NON-LINEAR UTILI...ELELIJ
 
E021203026035
E021203026035E021203026035
E021203026035theijes
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
Fuzzy and predictive control of a photovoltaic pumping system based on three-...
Fuzzy and predictive control of a photovoltaic pumping system based on three-...Fuzzy and predictive control of a photovoltaic pumping system based on three-...
Fuzzy and predictive control of a photovoltaic pumping system based on three-...journalBEEI
 

What's hot (20)

Design and Experimental Results of Universal Electric Vehicle Charger Using DSP
Design and Experimental Results of Universal Electric Vehicle Charger Using DSPDesign and Experimental Results of Universal Electric Vehicle Charger Using DSP
Design and Experimental Results of Universal Electric Vehicle Charger Using DSP
 
Cost Allocation of Reactive Power Using Matrix Methodology in Transmission Ne...
Cost Allocation of Reactive Power Using Matrix Methodology in Transmission Ne...Cost Allocation of Reactive Power Using Matrix Methodology in Transmission Ne...
Cost Allocation of Reactive Power Using Matrix Methodology in Transmission Ne...
 
International Refereed Journal of Engineering and Science (IRJES)
International Refereed Journal of Engineering and Science (IRJES)International Refereed Journal of Engineering and Science (IRJES)
International Refereed Journal of Engineering and Science (IRJES)
 
A Single-Phase Dual-Stage PV-Grid System with Active Filtering
A Single-Phase Dual-Stage PV-Grid System with Active FilteringA Single-Phase Dual-Stage PV-Grid System with Active Filtering
A Single-Phase Dual-Stage PV-Grid System with Active Filtering
 
An Improved UPQC Controller to Provide Grid-Voltage Regulation
An Improved UPQC Controller to Provide Grid-Voltage RegulationAn Improved UPQC Controller to Provide Grid-Voltage Regulation
An Improved UPQC Controller to Provide Grid-Voltage Regulation
 
Tie.2007.894713
Tie.2007.894713Tie.2007.894713
Tie.2007.894713
 
Energy Storage | Fuel Security , Presented at Energy Institute, London
Energy Storage | Fuel Security , Presented at Energy Institute, LondonEnergy Storage | Fuel Security , Presented at Energy Institute, London
Energy Storage | Fuel Security , Presented at Energy Institute, London
 
Load types, estimation, grwoth, forecasting and duration curves
Load types, estimation, grwoth, forecasting and duration curvesLoad types, estimation, grwoth, forecasting and duration curves
Load types, estimation, grwoth, forecasting and duration curves
 
Ifedi.Seminar Presenatation
Ifedi.Seminar PresenatationIfedi.Seminar Presenatation
Ifedi.Seminar Presenatation
 
CONTROL OF BATTERY OPERATED SYSTEM WITH A DC-DC BOOSTCONVERTER FED DSTATCOM U...
CONTROL OF BATTERY OPERATED SYSTEM WITH A DC-DC BOOSTCONVERTER FED DSTATCOM U...CONTROL OF BATTERY OPERATED SYSTEM WITH A DC-DC BOOSTCONVERTER FED DSTATCOM U...
CONTROL OF BATTERY OPERATED SYSTEM WITH A DC-DC BOOSTCONVERTER FED DSTATCOM U...
 
Newdd
NewddNewdd
Newdd
 
T04201162168Optimal Allocation of FACTS Device with Multiple Objectives Using...
T04201162168Optimal Allocation of FACTS Device with Multiple Objectives Using...T04201162168Optimal Allocation of FACTS Device with Multiple Objectives Using...
T04201162168Optimal Allocation of FACTS Device with Multiple Objectives Using...
 
212741860 assignment
212741860 assignment212741860 assignment
212741860 assignment
 
Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...
Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...
Economic Impacts of Behind the Meter Distributed Energy Resources on Transmis...
 
Profitability of frequency_regulation_by_electric_car
Profitability of frequency_regulation_by_electric_carProfitability of frequency_regulation_by_electric_car
Profitability of frequency_regulation_by_electric_car
 
roy_emmerich-eurec_dissertation-summary_paper-final
roy_emmerich-eurec_dissertation-summary_paper-finalroy_emmerich-eurec_dissertation-summary_paper-final
roy_emmerich-eurec_dissertation-summary_paper-final
 
USAGE BASED COST ALLOCATION TECHNIQUE FOR EHV NETWORKS USING NON-LINEAR UTILI...
USAGE BASED COST ALLOCATION TECHNIQUE FOR EHV NETWORKS USING NON-LINEAR UTILI...USAGE BASED COST ALLOCATION TECHNIQUE FOR EHV NETWORKS USING NON-LINEAR UTILI...
USAGE BASED COST ALLOCATION TECHNIQUE FOR EHV NETWORKS USING NON-LINEAR UTILI...
 
E021203026035
E021203026035E021203026035
E021203026035
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
Fuzzy and predictive control of a photovoltaic pumping system based on three-...
Fuzzy and predictive control of a photovoltaic pumping system based on three-...Fuzzy and predictive control of a photovoltaic pumping system based on three-...
Fuzzy and predictive control of a photovoltaic pumping system based on three-...
 

Similar to Value Quantification of State-of-the-Art Condition Monitoring in 400kV Transmission System Substations

Congestion Management in Deregulated Power System by Using FACTS Devices
Congestion Management in Deregulated Power System by Using FACTS DevicesCongestion Management in Deregulated Power System by Using FACTS Devices
Congestion Management in Deregulated Power System by Using FACTS DevicesIRJET Journal
 
IRJET- High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...
IRJET-  	  High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...IRJET-  	  High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...
IRJET- High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...IRJET Journal
 
IRJET- An Optimal and Capacitor Placement for Loss Reduction in Electrica...
IRJET-  	  An Optimal and Capacitor Placement for Loss Reduction in Electrica...IRJET-  	  An Optimal and Capacitor Placement for Loss Reduction in Electrica...
IRJET- An Optimal and Capacitor Placement for Loss Reduction in Electrica...IRJET Journal
 
Fuzzy logic controller for synchronous generators in a stand-alone multi-mac...
Fuzzy logic controller for  synchronous generators in a stand-alone multi-mac...Fuzzy logic controller for  synchronous generators in a stand-alone multi-mac...
Fuzzy logic controller for synchronous generators in a stand-alone multi-mac...IRJET Journal
 
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...IRJET Journal
 
IRJET- A Comparative Study of Control Algorithms for DSTATCOM for Harmonic El...
IRJET- A Comparative Study of Control Algorithms for DSTATCOM for Harmonic El...IRJET- A Comparative Study of Control Algorithms for DSTATCOM for Harmonic El...
IRJET- A Comparative Study of Control Algorithms for DSTATCOM for Harmonic El...IRJET Journal
 
IRJET- A Comparative Study of Control Algorithms for DSTATCOM for Harmonic El...
IRJET- A Comparative Study of Control Algorithms for DSTATCOM for Harmonic El...IRJET- A Comparative Study of Control Algorithms for DSTATCOM for Harmonic El...
IRJET- A Comparative Study of Control Algorithms for DSTATCOM for Harmonic El...IRJET Journal
 
Improved Nine-Level Transformerless Inverter with Reduced Part Count
Improved Nine-Level Transformerless Inverter with Reduced Part CountImproved Nine-Level Transformerless Inverter with Reduced Part Count
Improved Nine-Level Transformerless Inverter with Reduced Part CountIRJET Journal
 
IRJET- Design and Simulation of Solar PV DC Microgrid for Rural Electrification
IRJET- Design and Simulation of Solar PV DC Microgrid for Rural ElectrificationIRJET- Design and Simulation of Solar PV DC Microgrid for Rural Electrification
IRJET- Design and Simulation of Solar PV DC Microgrid for Rural ElectrificationIRJET Journal
 
Performance Analysis of DC Micro Grid with PV-Fuel Cell Hybrid Generation
Performance Analysis of DC Micro Grid with PV-Fuel Cell Hybrid GenerationPerformance Analysis of DC Micro Grid with PV-Fuel Cell Hybrid Generation
Performance Analysis of DC Micro Grid with PV-Fuel Cell Hybrid GenerationIJMREMJournal
 
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...IRJET Journal
 
Investigation Effect of Outage Line on the Transmission Line for Karbalaa-132...
Investigation Effect of Outage Line on the Transmission Line for Karbalaa-132...Investigation Effect of Outage Line on the Transmission Line for Karbalaa-132...
Investigation Effect of Outage Line on the Transmission Line for Karbalaa-132...IRJET Journal
 
IRJET- Electrical Simulation Model of IEC 61400-27-1 Doubly-Fed Induction...
IRJET-  	  Electrical Simulation Model of IEC 61400-27-1 Doubly-Fed Induction...IRJET-  	  Electrical Simulation Model of IEC 61400-27-1 Doubly-Fed Induction...
IRJET- Electrical Simulation Model of IEC 61400-27-1 Doubly-Fed Induction...IRJET Journal
 
IRJET- Electrical Simulation Model of IEC 61400-27-1 Doubly-Fed Induction Gen...
IRJET- Electrical Simulation Model of IEC 61400-27-1 Doubly-Fed Induction Gen...IRJET- Electrical Simulation Model of IEC 61400-27-1 Doubly-Fed Induction Gen...
IRJET- Electrical Simulation Model of IEC 61400-27-1 Doubly-Fed Induction Gen...IRJET Journal
 
Influence choice of the injection nodes of energy source on on-line losses of...
Influence choice of the injection nodes of energy source on on-line losses of...Influence choice of the injection nodes of energy source on on-line losses of...
Influence choice of the injection nodes of energy source on on-line losses of...IJMER
 
Analysis of harmonics and resonances in hvdc mmc link connected to AC grid
Analysis of harmonics and resonances in hvdc mmc link connected to AC gridAnalysis of harmonics and resonances in hvdc mmc link connected to AC grid
Analysis of harmonics and resonances in hvdc mmc link connected to AC gridBérengère VIGNAUX
 
HVDC- Final mustapha.ppt - Copy.pptx
HVDC- Final mustapha.ppt - Copy.pptxHVDC- Final mustapha.ppt - Copy.pptx
HVDC- Final mustapha.ppt - Copy.pptxSherAli260123
 
An Efficient Wireless Power Transfer Methodology for Electric Vehicle Battery...
An Efficient Wireless Power Transfer Methodology for Electric Vehicle Battery...An Efficient Wireless Power Transfer Methodology for Electric Vehicle Battery...
An Efficient Wireless Power Transfer Methodology for Electric Vehicle Battery...IRJET Journal
 
Impact of Electric Vehicle Integration on Grid
Impact of Electric Vehicle Integration on GridImpact of Electric Vehicle Integration on Grid
Impact of Electric Vehicle Integration on Gridvivatechijri
 

Similar to Value Quantification of State-of-the-Art Condition Monitoring in 400kV Transmission System Substations (20)

Congestion Management in Deregulated Power System by Using FACTS Devices
Congestion Management in Deregulated Power System by Using FACTS DevicesCongestion Management in Deregulated Power System by Using FACTS Devices
Congestion Management in Deregulated Power System by Using FACTS Devices
 
IRJET- High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...
IRJET-  	  High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...IRJET-  	  High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...
IRJET- High-Efficiency Three-Level Stacked-Neutral-Point-Clamped Grid-Tie...
 
IRJET- An Optimal and Capacitor Placement for Loss Reduction in Electrica...
IRJET-  	  An Optimal and Capacitor Placement for Loss Reduction in Electrica...IRJET-  	  An Optimal and Capacitor Placement for Loss Reduction in Electrica...
IRJET- An Optimal and Capacitor Placement for Loss Reduction in Electrica...
 
Fuzzy logic controller for synchronous generators in a stand-alone multi-mac...
Fuzzy logic controller for  synchronous generators in a stand-alone multi-mac...Fuzzy logic controller for  synchronous generators in a stand-alone multi-mac...
Fuzzy logic controller for synchronous generators in a stand-alone multi-mac...
 
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...
IRJET- Frequency Control of Distributed Generators in Microgrid with ANFIS Co...
 
IRJET- A Comparative Study of Control Algorithms for DSTATCOM for Harmonic El...
IRJET- A Comparative Study of Control Algorithms for DSTATCOM for Harmonic El...IRJET- A Comparative Study of Control Algorithms for DSTATCOM for Harmonic El...
IRJET- A Comparative Study of Control Algorithms for DSTATCOM for Harmonic El...
 
IRJET- A Comparative Study of Control Algorithms for DSTATCOM for Harmonic El...
IRJET- A Comparative Study of Control Algorithms for DSTATCOM for Harmonic El...IRJET- A Comparative Study of Control Algorithms for DSTATCOM for Harmonic El...
IRJET- A Comparative Study of Control Algorithms for DSTATCOM for Harmonic El...
 
Improved Nine-Level Transformerless Inverter with Reduced Part Count
Improved Nine-Level Transformerless Inverter with Reduced Part CountImproved Nine-Level Transformerless Inverter with Reduced Part Count
Improved Nine-Level Transformerless Inverter with Reduced Part Count
 
IRJET- Design and Simulation of Solar PV DC Microgrid for Rural Electrification
IRJET- Design and Simulation of Solar PV DC Microgrid for Rural ElectrificationIRJET- Design and Simulation of Solar PV DC Microgrid for Rural Electrification
IRJET- Design and Simulation of Solar PV DC Microgrid for Rural Electrification
 
Performance Analysis of DC Micro Grid with PV-Fuel Cell Hybrid Generation
Performance Analysis of DC Micro Grid with PV-Fuel Cell Hybrid GenerationPerformance Analysis of DC Micro Grid with PV-Fuel Cell Hybrid Generation
Performance Analysis of DC Micro Grid with PV-Fuel Cell Hybrid Generation
 
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
 
Investigation Effect of Outage Line on the Transmission Line for Karbalaa-132...
Investigation Effect of Outage Line on the Transmission Line for Karbalaa-132...Investigation Effect of Outage Line on the Transmission Line for Karbalaa-132...
Investigation Effect of Outage Line on the Transmission Line for Karbalaa-132...
 
36 p vplant-modeling-gorgan
36 p vplant-modeling-gorgan36 p vplant-modeling-gorgan
36 p vplant-modeling-gorgan
 
IRJET- Electrical Simulation Model of IEC 61400-27-1 Doubly-Fed Induction...
IRJET-  	  Electrical Simulation Model of IEC 61400-27-1 Doubly-Fed Induction...IRJET-  	  Electrical Simulation Model of IEC 61400-27-1 Doubly-Fed Induction...
IRJET- Electrical Simulation Model of IEC 61400-27-1 Doubly-Fed Induction...
 
IRJET- Electrical Simulation Model of IEC 61400-27-1 Doubly-Fed Induction Gen...
IRJET- Electrical Simulation Model of IEC 61400-27-1 Doubly-Fed Induction Gen...IRJET- Electrical Simulation Model of IEC 61400-27-1 Doubly-Fed Induction Gen...
IRJET- Electrical Simulation Model of IEC 61400-27-1 Doubly-Fed Induction Gen...
 
Influence choice of the injection nodes of energy source on on-line losses of...
Influence choice of the injection nodes of energy source on on-line losses of...Influence choice of the injection nodes of energy source on on-line losses of...
Influence choice of the injection nodes of energy source on on-line losses of...
 
Analysis of harmonics and resonances in hvdc mmc link connected to AC grid
Analysis of harmonics and resonances in hvdc mmc link connected to AC gridAnalysis of harmonics and resonances in hvdc mmc link connected to AC grid
Analysis of harmonics and resonances in hvdc mmc link connected to AC grid
 
HVDC- Final mustapha.ppt - Copy.pptx
HVDC- Final mustapha.ppt - Copy.pptxHVDC- Final mustapha.ppt - Copy.pptx
HVDC- Final mustapha.ppt - Copy.pptx
 
An Efficient Wireless Power Transfer Methodology for Electric Vehicle Battery...
An Efficient Wireless Power Transfer Methodology for Electric Vehicle Battery...An Efficient Wireless Power Transfer Methodology for Electric Vehicle Battery...
An Efficient Wireless Power Transfer Methodology for Electric Vehicle Battery...
 
Impact of Electric Vehicle Integration on Grid
Impact of Electric Vehicle Integration on GridImpact of Electric Vehicle Integration on Grid
Impact of Electric Vehicle Integration on Grid
 

More from Power System Operation

Thermography test of electrical panels
Thermography test of electrical panelsThermography test of electrical panels
Thermography test of electrical panelsPower System Operation
 
Big Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsBig Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsPower System Operation
 
SPS to RAS Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme  Remedial Action SchemeSPS to RAS Special Protection Scheme  Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action SchemePower System Operation
 
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...Power System Operation
 
Principles & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePrinciples & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePower System Operation
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)Power System Operation
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & PartsPower System Operation
 
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools
The Need for Enhanced Power System Modelling Techniques & Simulation Tools Power System Operation
 
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
Power Quality  Trends in the Transition to  Carbon-Free Electrical Energy SystemPower Quality  Trends in the Transition to  Carbon-Free Electrical Energy System
Power Quality Trends in the Transition to Carbon-Free Electrical Energy SystemPower System Operation
 

More from Power System Operation (20)

ENERGY TRANSITION OUTLOOK 2021
ENERGY TRANSITION OUTLOOK  2021ENERGY TRANSITION OUTLOOK  2021
ENERGY TRANSITION OUTLOOK 2021
 
Thermography test of electrical panels
Thermography test of electrical panelsThermography test of electrical panels
Thermography test of electrical panels
 
What does peak shaving mean
What does peak shaving meanWhat does peak shaving mean
What does peak shaving mean
 
What's short circuit level
What's short circuit levelWhat's short circuit level
What's short circuit level
 
Power System Restoration Guide
Power System Restoration Guide  Power System Restoration Guide
Power System Restoration Guide
 
Big Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid OperationsBig Data Analytics for Power Grid Operations
Big Data Analytics for Power Grid Operations
 
SPS to RAS Special Protection Scheme Remedial Action Scheme
SPS to RAS Special Protection Scheme  Remedial Action SchemeSPS to RAS Special Protection Scheme  Remedial Action Scheme
SPS to RAS Special Protection Scheme Remedial Action Scheme
 
Substation Neutral Earthing
Substation Neutral EarthingSubstation Neutral Earthing
Substation Neutral Earthing
 
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...SVC PLUS Frequency Stabilizer Frequency and voltage support for  dynamic grid...
SVC PLUS Frequency Stabilizer Frequency and voltage support for dynamic grid...
 
Principles & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePrinciples & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground Resistance
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & Parts
 
What is load management
What is load managementWhat is load management
What is load management
 
What does merit order mean
What does merit order meanWhat does merit order mean
What does merit order mean
 
What are Balancing Services ?
What are  Balancing Services ?What are  Balancing Services ?
What are Balancing Services ?
 
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools The Need for Enhanced  Power System  Modelling Techniques  &  Simulation Tools
The Need for Enhanced Power System Modelling Techniques & Simulation Tools
 
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
Power Quality  Trends in the Transition to  Carbon-Free Electrical Energy SystemPower Quality  Trends in the Transition to  Carbon-Free Electrical Energy System
Power Quality Trends in the Transition to Carbon-Free Electrical Energy System
 
Power Purchase Agreement PPA
Power Purchase Agreement PPA Power Purchase Agreement PPA
Power Purchase Agreement PPA
 
Harmonic study and analysis
Harmonic study and analysisHarmonic study and analysis
Harmonic study and analysis
 
What is leakage current testing
What is leakage current testingWhat is leakage current testing
What is leakage current testing
 

Recently uploaded

Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 

Recently uploaded (20)

Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 

Value Quantification of State-of-the-Art Condition Monitoring in 400kV Transmission System Substations

  • 1. marco.fleckenstein@de.abb.com 21, rue d’Artois, F-75008 PARIS CIGRE US National Committee http://www.cigre.org 2019 Grid of the Future Symposium Value Quantification of State-of-the-Art Condition Monitoring in 400kV Transmission System Substations M. FLECKENSTEIN ABB AG Germany L. ASGARIEH ABB AG Germany C. ZEIDLER ABB AG Germany SUMMARY Digital substation and its monitoring systems is an “en vogue” topic again these days in the power engineering community. Many system providers have put it back on the agenda and started their promotion to sell their new holistic product offerings for substations. On the other hand, the transmission system operators (TSO) are still not completely convinced to replace/retrofit substations with "digital/sensored" equipment, because the added value is not visible on the first view and many other subjects have a higher priority for TSO/DSO. To determine the economic added value of monitoring systems within digital substations, a Transmission Network Model (TNM) based on data from a German TSO was used in a grid calculation tool with various scenarios of improved reliability and availability values. Based on these values, the risk OPEX for the next 10 years will be calculated for all equipment in the 400 kV switchgear. For the sake of simplification, this paper only illustrates the monitoring systems for power transformers and circuit breakers in the 400 kV level. A value-at-risk method is used to estimate the different risk costs of the assets. This methodology considers repair, replacement and lost revenue costs by considering various occurrence moments of the asset outages. Based on the net present value with a 10-year period, it is determined, if a "digitization" of the substations makes economic sense. Therefore, it is applied a variation of penalty fees for non- delivered or feed-in electrical energy and span of prices for the sensor application. The results show a strong dependency on the revenue losses due to energy not delivered, transferred or fed in, which are also related to the penalty fees. Mission-critical substations always benefit from condition monitoring. KEYWORDS ASSET MANAGEMENT, CONDITION MONITORING, DIGITAL SUBSTATION, VALUE QUANTIFICATION
  • 2. 2/8 1. Introduction The German way against "global climate change" is unique. In 2011, directly after the Fukushima disaster, the German government decided to accelerate the shutdown of nuclear power plants with the last plant being out of service by 2022 [1]. Due to the public pressure the German government also committed in 2019 to retire all lignite and hard coal power plants by 2038 [2]. Furthermore, the regulation of network charges is tough to budgeting investments cost for the electrical transmission and distribution systems and as a further side condition the feed-in of unregulated renewables is further increasing [3]. Nevertheless, the TSO and DSO must adapt and expand the electrical network for current feed-in modifications and future requirements. The application of sensors for monitoring the equipment condition, has moved back to the agenda of many stakeholders of the power system community after the price collapse of these various technologies within digital substations and its data infrastructure [4]. This paper shows where and at what prices an added value exists for the operators of such facilities. The methodology which was applied was already used for development of maintenance strategies and other asset management tasks. 2. Basics for substation equipment risk determination The benefits of digital substations are demonstrated with a transmission system model and an OPEX- Risk cost assessment which is based on a Value-at-Risk Methodology by using Monte Carlo Simulations to consider several equipment failure scenarios. The next subsections explain the fundamental methodology to determine the risk associated with substation equipment [5]. 2.1. Transmission System Model The transmission network model (TNM) employed for this demonstration consists of three voltage levels and is based on a subsection of the structure of a German TSO. It has been created within the electrical power system software and contains 400 kV, 220 kV voltage level and ends with the vertical feeding into the 110 kV network groups. These groups are summarized as an aggregated load, which are used to simulate realistic load scenarios [6]. The highest voltage level is the 400 kV system and core of the TNM. The observed assets are in the substations of this voltage level. TNM includes 60 substations, 23 power station connection points, and ten coupling points to neighboring TSOs. The 400 kV network has a direct feed-in by 30 power plant units with a net production of 18 GW [6]. Various types of substations are considered by modelling the network model. The structure of each substation is reproduced in detail and is provided with the real switching settings which are important for the reliability and availability calculations. TNM also considers the horizontal load. The transmission capacities of the overhead lines are assumed as the only limiting boundary condition in the regarded scenario. The voltage angles at the slack nodes, representing the neighboring transmission system, are set to zero, which is the ideal case and has a transfer capacity to other TSOs of around 29 GVA [7]. Age depended outage rates H are applied for the 400 kV assets within substations. An exception was only made for the power plant connections. These are considered as ideal because these are on duty of the power plant operators by German law. Additionally, it should be noted that the outage rates of pantograph disconnectors are included in the values of the bus bars, which are bay dependent. Figure 1 shows the age-dependent outage rates of each busbar BB, circuit breaker (CB), disconnector (DIS), and power transformer (PTR). A secondary axis for the power transformer is inserted on the left side. Each asset group consequently has eight different failure rates. The individual financial characteristics of the assets are shown for clarity in the results section.
  • 3. 3/8 Figure 1: Age distribution & dependent outage rates of the assets. [5][7]. The 220 kV transmission system is only modelled schematically and its assets’ outage impacts are not simulated itself in reliability and availability calculations. But this level is necessary to get realistic power flow conditions in the 400 kV transmission system. The 110 kV network groups are also partly supplied by 220 kV/110 kV power transformers. In total 31 power plant units with a total net output of 10 GW are connected to the 220 kV network. It also has four coupling points to other TSOs, with a total transmission capacity of around 4 GVA [5]. The 110 kV network groups represent the vertical load of the transmission system model. These are supplied by the 220 kV and 400 kV networks through power transformers. Power plants feeding directly into the 110 kV groups are not part of the model. This voltage level is separated into 34 network groups and eight industrial network groups and have a peak load of between 250 and 1200 MW. The power plant units are implemented with different characteristics and their individual dynamic performance in the model. Therefore, different power gradients inherent to the various types of power plants, as well as their share of auxiliary power, are considered in the reliability and availability calculations. The gross output of all power plant units is around 30 GW [8]. Ten typical load flow scenarios are used for these simulations with their different vertical load and power plant scheduling, based on an analysis of the sorted annual vertical load curve of the transmission system. The actual generation capacity of power plants always exceeds the consumption of the 110 kV network groups. The surplus/shortfall of energy is imported/exported from the neighboring transmission systems. The schedules of the different types of power plants are determined by their typical operating hours. For instance, gas power plants have fewer hours of operation, due to their high operating costs. A portion of the gas power however remains constant at the power plants, as these are operated with mine gas. These are promoted by the Renewal Energy Act (EEG) and may therefore always remain in operation [8]. 2.2. OPEX-risk costs determination of 400kV-Assets in substations The determination of OPEX-risk costs contains the shortfall of revenue costs of individual assets, which is based on the results of reliability and availability calculations multiplied with energy costs and the typical follow-up costs e.g. repair/replacement costs KR. An overview of the determination of OPEX-risk costs is illustrated in Figure 2. This process is repeated many times within a Monte Carlo simulation. To clip out extreme values, which are generated by the combination of variety of distribution functions, a Value at Risk (VaR) evaluation of the data series is applied. Sorting the list of substations by their VaR then yields their priority list [10][11]. The three green boxes illustrate the main input parameters: repair costs, reliability values
  • 4. 4/8 (Duration T of non-delivered or non-feed-in energy, Power P of non-delivered or non-feed-in energy) and outage rate H. For every asset group a distribution function with repair costs is implemented. The cost of repair for any asset is randomly re-drawn from this distribution for each simulation . The characteristic values of the distribution functions of each asset groups are presented in the results section. The green box “Reliability values” includes the database consisting of the reliability and availability results under all load flow situations of the assets. By randomly re-drawing a value in each simulation, different times of outage occurrence and the effects of the individual assets are considered. i = 1 … N asset Repair risk RR = H * KR Risik of non-delivered energy RND = H * TND * PND * KE Risk of non-supplied energy RNS = H * TNS * PNS * KE gND gNS ∑ Asset risk R(i,s) of the Asset i in simulation round s H KR RND * gND TND, PND TNS, PNS KE RNS * gNS Repair costs Reliability values Outage Rate Figure 2: Structure of asset risk determination [11]. The third green box is the outage rate. These outage rates of the assets are age dependent, as described in subsection 2.1. Additionally, the outage rate is varied in each simulation according to a normal distribution with a standard deviation of ten percent around the mean given by its age dependent value. Three further variables are required for the asset risk determination. The revenue loss by non-supplied or non-delivered energy is specified by energy costs in €/MWh. With correction factors and penalty payments can be considered for non-delivered or non-supplied energy. The asset risk of simulation round is finally determined as the sum of the repair risk , the risk of non- delivered energy and the risk of non-supplied energy . Due to the use of many distribution functions and randomly selected features a great number of simulations are required to minimize the impact of exceptional combinations. After the determination of all individual OPEX- risk costs in a simulation round, these values are assigned to its substation and capture the overall substation risk of the round. The substation risks for each substation are formed from the summarization of the risk of all assets that are associated with it. The Monte Carlo Simulation repeats this process M times. The overall evaluation of the individual simulation runs in the Monte Carlo simulation is performed again according to the VaR method. In this method, risk values are sorted by their magnitude and the confidence area is determined using a specified confidence interval. With this interval, the extremes are filtered which result from unfortunate combinations of distribution functions. A confidence interval of 0.95 and 10,000 simulation rounds are used, which are standard values in VaR calculations [10]. 2.3. Applied key figures of condition monitoring To determine the value of condition monitoring in these 400 kV substations, some assumptions are made. On the one hand, the impact of the monitoring, and on the other hand, the costs of monitoring with its sensor application must be estimated.
  • 5. 5/8 Many significant publications were done within CIGRE, covering the topic asset monitoring for high voltage equipment [12][13][14]. According to these documents, failure rates for power transformers can be reduced significantly, as shown in Figure 3. Figure 3: Standard failure probability tree for power transformer [12]. The reliability values, which are shown in Figure 3, are applied together with the age-dependent outage rates for the power transformer of section 2.1, to show the impact on the OPEX-risk costs. For determining the improvement of circuit breaker availability, the key parameter for monitoring are gas density, motor drive current and cabinet heater supervision [15]. Increasing the reliability of the circuit breaker with Condition Monitoring, no public figures are yet available. In this paper, the assumption has been made that the outage rate will be halved. As a basic assumption for the costs of condition monitoring, basic costs of 60k€ for the power transformer and 15k€ for the circuit breaker were considered. These values relate only to the sensors and does not include the data connection, engineering and other costs, which are heavily dependent on the individual network operator. Due to the high skepticism about these technologies, the depreciation period is set to ten years. 3. Execution of scenarios For illustration of the results, the number of substations is reduced to twelve. Table 1 lists these substations acronyms, along with their layout and numbers of power transformers (PTR) and circuit breakers (CB). Table 1: Substation key data SUBSTATION ACRONYM LAYOUT PTR CB SUBSTATION ACRONYM LAYOUT PTR CB BI H4 2 4 LB DBT 3 8 BU TBT 4 12 MB DBT 0 6 DT H3 1 3 SB ET 1 1 ED DBT 1 6 UC DBT 3 10 KO DB 1 4 UR DBT 8 3 KR DB 3 7 WT TBT 3 10 Layout Acronyms: DBT Double Busbar with Transfer Busbar TBT Trible Busbar with Transfer Busbar H4 H-Connection with 4-Breakers H3 H-Connection with 3-Breakers DB Double Busbar ET External Transformer
  • 6. 6/8 The substation risk values regarding the age-depended outage rates of the assets for these 12 substations are considered with the methodology, which is presented in the second section. For the application of monitoring systems, associated outage values (see subsection 2.3) are applied and the risk determination of substation was performed with the modified values. Additional scenarios have been developed, to show different investment strategies respectively to show the best case, if it is decided to replace the whole substation and equip all PTR and CB with monitoring systems. The applied scenarios are: Regular Status Quo of current equipment Intensive Improved behavior of equipment if all assets will be refurbished NEW Replacement of primary equipment inside of the substation Online Regular Retrofit of current CB’s and PTR’s in the substation with sensors Online New Replacement of all CB’s and PTR’s in the substation and installation of sensors 3.1. Annual OPEX-Substation risk costs comparison This subsection shows the annual OPEX-substation risk costs for all five scenarios with 50€ per MWh of non-delivered or non-feeded-in energy costs, per asset outages within specific substation. Figure 4 illustrates that risks for all described scenarios. The annual risks vary greatly among the regarded substations. The number of equipment is an essential but is not the dominant reason for the massive gap between the highest risk (260 k€) and the lowest one (6 k€). It can be seen the implementation of sensors significantly mitigate the risk. For example, the annual risk of substation BU, which has the highest risk, was reduced from 260 k€/a to 82 k€/a by a full refurbishment. Figure 4: Annual substation risk costs by scenario It is worth noting that in BU the substation has been renewed within the last five years. This explains the result gap between NEW and the other OPEX Substation risk costs for this plant. For the substation BI, DT, ED and SB the condition monitoring has no significant importance. These facilities have a high redundancy and have only repair/replacement cost risk. The share of loss of revenue with energy costs of 50 €/MWh is minimal. Due to that situation an investment for additional equipment has a lower priority. 3.2. Net present value determination for a ten-year period. The reduction of operational risks always has impact on the investment costs. In Figure 5, the development of the total net present values (NPV) is shown for different loss of revenues. In this case a variation of energy costs for non-delivered or non-feed-in energy was done between 50 €/MWh and
  • 7. 7/8 300 €/MWh. The results are shown accumulated from left to right. This means that the results of WT include the results of BU for all scenarios. Thus, the results could be considered for high price areas, or for countries which have high penalties; e.g., non-services of power purchase agreements (PPA) or any other non-delivery. The order of importance of the substation was used for the sequence of condition monitoring and respectively for the investment. The diagram shows that the total NPV is strongly depended on the penalty fee for non-delivered and supplied energy. Assuming low penalties the investment in sensors can only be recommended for the most important substations. For energy costs of 100 €/MWh and higher, investment can however be recommended for all substations. Figure 5: Net present value of the substations. 4. Conclusion The use of sensors for switchgear is an excellent opportunity to increase the availability and the service life. Even with minor penalties, a return of investment for the major switchgear can be achieved within 10 years. This result is very impressive, since redundancy is very high within the maximum voltage level compared to the lower levels. The reduction of operational risk is only a partial aspect. Other options such as the adjustment of the maintenance, which is not shown in this paper, or the extended life of the equipment and the resulting shift of investment costs are not considered here. In this paper, only figures with the state of the art are used in terms of condition monitoring. New publications show that even more will be possible in the area of circuit breakers and power transformers soon [15][16]. Furthermore, a condition monitoring for surge arresters promises additional advantages. Although this component is considered one of the cheaper components in a substation, its failure has a significant impact on the "valuable" assets [17].
  • 8. 8/8 BIBLIOGRAPHY [1] Printed matter of the German Bundestag: Entwurf eines Dreizehnten Gesetzes zur Änderung des Atomgesetzes, Drucksache 17/6070, Berlin, 6th June 2011. [2] BMWi: Eckpunkte zur Umsetzung der strukturpolitischen Empfehlungen der Kommission „Wachstum, Struktur wandel und Beschäftigung“ für ein „Strukturstärkungsgesetz Kohleregionen“, Berlin, 22nd May 2019 [3] Diekmann J.: Regulierung der Stromnetze in Deutschland, Düsseldorf, 2007. [4] Lopez J.: GE’s Journey toward Intelligent Digital Substations, Paris, 2016. [5] Fleckenstein, M.; Neumann, C.; Balzer G.: Bay oriented & risk based maintenance for transmission networks. 2014 CIGRE Conference on Power Systems, rep. 226, Bruessels, Belgium, March 12th-14th, 2014. [6] Fleckenstein, M.; Neumann, C.; Balzer, G.: Risk-oriented asset replacement within substations in EHV transmission networks. 20th Conference of the electric power supply industry, Jeju, Südkorea, October 26th – 30th, 2014. [7] Schwan M.: Using the VDN Statistic on Incidents to Derive Component Reliability Data for Probabilistic Reliability Analyses, 2005. [8] Balzer G., Schorn C.: Life Cycle Costs Analysis of a Complete Air Insulated Substation, CIGRE SC B3 Berlin 2007. [9] Fleckenstein, M.; Neumann, C.; Balzer, G.: Risk assessment of aging power transformers in the transmission network. Grid of the Future, Houston, USA, October 20th -21st, 2014 [10] Jorion P.: Value at Risk – The new Benchmark for controlling derivatives Risk, 3. Edition, New York 2006. [11] Fleckenstein, M.: Risikoorientierte Instandhaltung auf der Basis der Value-at-Risk Methode im Übertragungsnetz, Technische Universität Darmstadt, Dissertation, 2015. [12] WG A3.29: Economics of Transformer Management, CIGRE, document no. 248, 2004. [13] WG A3.06: Final Report of the 2004-2007 International Enquiry on Reliability of High Voltage Equipment, CIGRE, document no. 514, 2012. [14] WG A3.29: Ageing High Voltage Substation Equipment and possible mitigation techniques, CIGRE, document no. 725, 2018. [15] WG A3.32: Non-Intrusive methods for condition assessment of distribution and transmission switchgear, CIGRE, 2018 [16] Laitinen, T., Albrecht, R.: Wireless sensor units for acoustic monitoring of switching devices, CIGRE Session, Paris, 2018. [17] I. A. Metwally, M. Eladawy and E. A. Feilat, "Online condition monitoring of surge arresters based on third-harmonic analysis of leakage current," in IEEE Transactions on Dielectrics and Electrical Insulation, vol. 24, no. 4, pp. 2274-2281, 2017.