SlideShare a Scribd company logo
1 of 2
Download to read offline
Patrick D. Calder
25 Stepping Stone Ln
Portland, ME 04103
(207)232-0944
patrickcalder@hotmail.com
Summary of Significant Engineering Project and Management Experience
1) Overhauls for power plant diesel generators
a) Six units at 12,000 running hours, 18,000 running hours, and 24,000 hrs each
b) Total cost per unit: $750,000 at each overhaul
c) Duration of project: up to six months prior preparation, work completed at each phase in 14-40
days.
d) Coordinated ordering and delivery of parts, scheduling of labor, scope of work performed, and
impact on overall plant operation including outages
e) Budgeted for repair of individual components for off-site refurbishment by third party vendors,
directed scope of repair work
2) Repair, Refit, and Regulatory Inspection of Steam Boilers and Generators
a) Two units twice each major overhaul, once each regulatory inspection
b) Total cost per unit: $50,000; overall cost $200,000
c) Duration of project: one month prior preparation, work completed in 7 days
d) Coordinated ordering, delivery, and supply of parts; oversaw rebuilding of fittings, parts, and
associated components in onboard facility
e) Interfaced with regulatory agencies for inspection and compliance with federal regulations on
condition, repair, and reinstallation
3) Redesign, reinstall main engineering power plant cooling water systems to repair damage and
failures and facilitate upgrades
a) Design temporary workaround for work on main systems, purchase raw materials needed,
coordinate and interface with maintenance crew(s) for work.
b) Direct and organize two multi-disciplined vendor teams made up of more than a dozen individual
contractors: one for construction of secondary cooling system, one for internal repair of primary
system, both with minimal impact on normal operations of vessel power production and air
conditioning services
c) Liaison with contractors and subcontractors and reconcile problems in scope of work gaps and
overlaps
d) Construction of additional systems to support primary system and return of primary system to
service upon completion of repairs; removal of secondary system upon completion of work
e) Total cost (labor and materials): approximately $400,000
4) Redesign, construction, and installation of auxiliary cooling and water production systems
a) Research, coordinate with vendors, and purchase new equipment to replace or modify substandard
equipment already installed.
b) Plan and oversee installation of equipment, including labor and operational cost management.
c) Total cost (labor and materials): approximately $100,000
5) Major Shutdown of Power Plant (Drydock)
a) Capital improvement and maintenance projects for all equipment, including power generation,
water production, inspections by regulatory agencies, and major overhauls. Total cost
approximately $1 million at each event.
b) Liaison with US Naval and military officers for facilities operations
6) Follow-up of problems related to installations of previously constructed propulsion, electrical,
and automation systems
a) Scheduling of inspections, budgeting and tracking costs of repairs, devising plan for repairs to
minimize operational impact
b) Total cost approximately $250,000
c) Budgeted for repair of individual components for off-site refurbishment by third party vendors and
subcontractors, directed scope of repair work
7) Miscellaneous repair, maintenance, and refurbishment projects
a) Examples: seal replacement on stabilizing fins, manufacturer inspection of major equipment,
replacement of desalination plant equipment, replacement of generators, rerouting of cabling and
wiring on massive scale, installation of new system components
b) Projects range from maintenance repaired within one day, to projects involving redesign,
improvement, or overhaul lasting months
c) Total cost: $3 million annual operating budget for materials, $1.5 million for labor including overtime
costs, both independent of other projects
8) Environmental Improvements and Designs, Malin International Ship Repair and Drydock
a) Project and Consultant development for installation of water purification systems and other
environmental initiatives
b) Directed purchase of materials, designs of systems, and construction and installation of shipboard
oil and water separation systems
c) Total cost: approximately $150,000
9) Refit of Rolls Royce/Alstom Electrical Propulsion Units
a) Coordination with vendors for purchase, installation, and labor cost of all associated equipment
including bearings, pumps, electrical cabling and wiring, automation controls, and regulatory
approval
b) Total cost approximately $1.5 million
10) Installation of Carbon Emissions Scrubber System
a) Determine locations for major retrofit piping, electrical components, pumps, and auxiliary equipment
onboard vessel and review and approve designs proposed by vendor/system designer.
b) Direct onboard construction team for placement and modification as necessary of proposed system
c) Coordinate purchase of materials, and shipment to location as they are needed
d) Review environmental regulations vs planned installation model; adjust accordingly
e) Total cost: $10 million+
11) Complete overhaul of engineering power-plant and facility and associated systems,
accommodations, and ancillary equipment (refrigeration, water treatment, oil purification, waste
water treatment)
a) Construction of new facilities, including electrical, water, and other utilities
b) Interface with regulatory agencies to ensure compliance with construction designs, practices, and
installation
c) Further planning for next evolution in 2016
d) Total cost: approximately $25 million

More Related Content

What's hot

Navy: Hangar One Detailed Cost Estimate
Navy: Hangar One Detailed Cost EstimateNavy: Hangar One Detailed Cost Estimate
Navy: Hangar One Detailed Cost EstimateSteve Williams
 
Cement Australia - Energy Efficiency Opportunities Public Report 2010
Cement Australia - Energy Efficiency Opportunities Public Report 2010Cement Australia - Energy Efficiency Opportunities Public Report 2010
Cement Australia - Energy Efficiency Opportunities Public Report 2010girlfoster10
 
Cement Australia - Energy Efficiency Opportunities Public Report 2010
Cement Australia - Energy Efficiency Opportunities Public Report 2010Cement Australia - Energy Efficiency Opportunities Public Report 2010
Cement Australia - Energy Efficiency Opportunities Public Report 2010girlfoster10
 
Cement Australia - Energy Efficiency Opportunities Public Report 2010
Cement Australia - Energy Efficiency Opportunities Public Report 2010Cement Australia - Energy Efficiency Opportunities Public Report 2010
Cement Australia - Energy Efficiency Opportunities Public Report 2010hong8reason
 
Final Presentation (Jesse Columbus)
Final Presentation (Jesse Columbus)Final Presentation (Jesse Columbus)
Final Presentation (Jesse Columbus)colum006
 
Probabilistic & Source Characterization Techniques in AERMOD Compliance
Probabilistic & Source Characterization Techniques in AERMOD ComplianceProbabilistic & Source Characterization Techniques in AERMOD Compliance
Probabilistic & Source Characterization Techniques in AERMOD ComplianceSergio A. Guerra
 
Lcoe offshore
Lcoe offshoreLcoe offshore
Lcoe offshoreinesgs
 
Cost Reduction Pivotal for Offshore Turbine Blades
Cost Reduction Pivotal for Offshore Turbine BladesCost Reduction Pivotal for Offshore Turbine Blades
Cost Reduction Pivotal for Offshore Turbine BladesTorben Haagh
 
Diminishing Options For Pm10 Er Cs
Diminishing Options For Pm10 Er CsDiminishing Options For Pm10 Er Cs
Diminishing Options For Pm10 Er CsJoel Reisman
 
Evaluation of the Theoretical Problems with Building Downwash Using A New Met...
Evaluation of the Theoretical Problems with Building Downwash Using A New Met...Evaluation of the Theoretical Problems with Building Downwash Using A New Met...
Evaluation of the Theoretical Problems with Building Downwash Using A New Met...Sergio A. Guerra
 
Drilling economics drilling engineering
Drilling economics drilling engineeringDrilling economics drilling engineering
Drilling economics drilling engineeringSafen D Taha
 
David Mortimer – Summary ‘09
David Mortimer – Summary ‘09David Mortimer – Summary ‘09
David Mortimer – Summary ‘09DavidMortimer
 
DGCA AME EXAM MODULE - 10 AVIATION LEGISLATION
DGCA AME EXAM MODULE - 10 AVIATION LEGISLATIONDGCA AME EXAM MODULE - 10 AVIATION LEGISLATION
DGCA AME EXAM MODULE - 10 AVIATION LEGISLATIONNisarg Mistry
 

What's hot (20)

Experience
ExperienceExperience
Experience
 
Navy: Hangar One Detailed Cost Estimate
Navy: Hangar One Detailed Cost EstimateNavy: Hangar One Detailed Cost Estimate
Navy: Hangar One Detailed Cost Estimate
 
Cement Australia - Energy Efficiency Opportunities Public Report 2010
Cement Australia - Energy Efficiency Opportunities Public Report 2010Cement Australia - Energy Efficiency Opportunities Public Report 2010
Cement Australia - Energy Efficiency Opportunities Public Report 2010
 
Cement Australia - Energy Efficiency Opportunities Public Report 2010
Cement Australia - Energy Efficiency Opportunities Public Report 2010Cement Australia - Energy Efficiency Opportunities Public Report 2010
Cement Australia - Energy Efficiency Opportunities Public Report 2010
 
Cement Australia - Energy Efficiency Opportunities Public Report 2010
Cement Australia - Energy Efficiency Opportunities Public Report 2010Cement Australia - Energy Efficiency Opportunities Public Report 2010
Cement Australia - Energy Efficiency Opportunities Public Report 2010
 
Record of Environmental Consideration for the PCAPP Demilitarization Activi...
Record of Environmental Consideration for the PCAPP Demilitarization Activi...Record of Environmental Consideration for the PCAPP Demilitarization Activi...
Record of Environmental Consideration for the PCAPP Demilitarization Activi...
 
Final Presentation (Jesse Columbus)
Final Presentation (Jesse Columbus)Final Presentation (Jesse Columbus)
Final Presentation (Jesse Columbus)
 
Probabilistic & Source Characterization Techniques in AERMOD Compliance
Probabilistic & Source Characterization Techniques in AERMOD ComplianceProbabilistic & Source Characterization Techniques in AERMOD Compliance
Probabilistic & Source Characterization Techniques in AERMOD Compliance
 
2014 Q4 RB slides
2014 Q4 RB slides2014 Q4 RB slides
2014 Q4 RB slides
 
Lcoe offshore
Lcoe offshoreLcoe offshore
Lcoe offshore
 
Cost Reduction Pivotal for Offshore Turbine Blades
Cost Reduction Pivotal for Offshore Turbine BladesCost Reduction Pivotal for Offshore Turbine Blades
Cost Reduction Pivotal for Offshore Turbine Blades
 
Diminishing Options For Pm10 Er Cs
Diminishing Options For Pm10 Er CsDiminishing Options For Pm10 Er Cs
Diminishing Options For Pm10 Er Cs
 
Sustaining energy performance
Sustaining energy performanceSustaining energy performance
Sustaining energy performance
 
Senior
SeniorSenior
Senior
 
Evaluation of the Theoretical Problems with Building Downwash Using A New Met...
Evaluation of the Theoretical Problems with Building Downwash Using A New Met...Evaluation of the Theoretical Problems with Building Downwash Using A New Met...
Evaluation of the Theoretical Problems with Building Downwash Using A New Met...
 
Drilling economics drilling engineering
Drilling economics drilling engineeringDrilling economics drilling engineering
Drilling economics drilling engineering
 
David Mortimer – Summary ‘09
David Mortimer – Summary ‘09David Mortimer – Summary ‘09
David Mortimer – Summary ‘09
 
DGCA AME EXAM MODULE - 10 AVIATION LEGISLATION
DGCA AME EXAM MODULE - 10 AVIATION LEGISLATIONDGCA AME EXAM MODULE - 10 AVIATION LEGISLATION
DGCA AME EXAM MODULE - 10 AVIATION LEGISLATION
 
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
 
PPT
PPTPPT
PPT
 

Similar to Patrick Calder Experience Summary

Natural Gas Storage Sample Memo
Natural Gas Storage Sample MemoNatural Gas Storage Sample Memo
Natural Gas Storage Sample MemoChad Colton
 
FINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
FINAL The Owens Lake Turnout Facility End Cap Budget and ScheduleFINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
FINAL The Owens Lake Turnout Facility End Cap Budget and ScheduleKook Dean
 
Chapter 7 capital cost estimation
Chapter 7 capital cost estimationChapter 7 capital cost estimation
Chapter 7 capital cost estimationjose2424
 
DesignCriteriaManual DesignCriteriaManual.pdf
DesignCriteriaManual DesignCriteriaManual.pdfDesignCriteriaManual DesignCriteriaManual.pdf
DesignCriteriaManual DesignCriteriaManual.pdfkahlaoui1
 
CEC_Carbon_Removal_Activities_8_15_2023_English.pptx
CEC_Carbon_Removal_Activities_8_15_2023_English.pptxCEC_Carbon_Removal_Activities_8_15_2023_English.pptx
CEC_Carbon_Removal_Activities_8_15_2023_English.pptxrammanav3101
 
Working plan guidance_wwtp
Working plan guidance_wwtpWorking plan guidance_wwtp
Working plan guidance_wwtpmedongonu
 
Working plan guidance_wwtp
Working plan guidance_wwtpWorking plan guidance_wwtp
Working plan guidance_wwtpmedongonu
 
Lecture 9 plant economics
Lecture 9 plant economicsLecture 9 plant economics
Lecture 9 plant economicsSwapnil Gadgune
 
Boo wind power in egypt
Boo wind power in egyptBoo wind power in egypt
Boo wind power in egyptRCREEE
 
Lecture 10 plant economics
Lecture 10 plant economicsLecture 10 plant economics
Lecture 10 plant economicsSwapnil Gadgune
 
Current Fluor Resume
Current Fluor ResumeCurrent Fluor Resume
Current Fluor ResumeRoy Firtha
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1Dan Caouette
 
Afaq CV (April 17, 2016)
Afaq CV (April 17, 2016)Afaq CV (April 17, 2016)
Afaq CV (April 17, 2016)Afaq Ahmad
 
John Charles Snyder Lead Engineer resume
John Charles Snyder Lead Engineer resumeJohn Charles Snyder Lead Engineer resume
John Charles Snyder Lead Engineer resumeJohn Snyder
 
Co Gen Presentation Final
Co Gen Presentation FinalCo Gen Presentation Final
Co Gen Presentation Finalsilverwolf_4_u
 

Similar to Patrick Calder Experience Summary (20)

projects
projectsprojects
projects
 
Natural Gas Storage Sample Memo
Natural Gas Storage Sample MemoNatural Gas Storage Sample Memo
Natural Gas Storage Sample Memo
 
FINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
FINAL The Owens Lake Turnout Facility End Cap Budget and ScheduleFINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
FINAL The Owens Lake Turnout Facility End Cap Budget and Schedule
 
Chapter 7 capital cost estimation
Chapter 7 capital cost estimationChapter 7 capital cost estimation
Chapter 7 capital cost estimation
 
Hossam CV-FEB2016
Hossam CV-FEB2016Hossam CV-FEB2016
Hossam CV-FEB2016
 
DesignCriteriaManual DesignCriteriaManual.pdf
DesignCriteriaManual DesignCriteriaManual.pdfDesignCriteriaManual DesignCriteriaManual.pdf
DesignCriteriaManual DesignCriteriaManual.pdf
 
CEC_Carbon_Removal_Activities_8_15_2023_English.pptx
CEC_Carbon_Removal_Activities_8_15_2023_English.pptxCEC_Carbon_Removal_Activities_8_15_2023_English.pptx
CEC_Carbon_Removal_Activities_8_15_2023_English.pptx
 
Donnie Belloit_Reume
Donnie Belloit_ReumeDonnie Belloit_Reume
Donnie Belloit_Reume
 
Working plan guidance_wwtp
Working plan guidance_wwtpWorking plan guidance_wwtp
Working plan guidance_wwtp
 
Working plan guidance_wwtp
Working plan guidance_wwtpWorking plan guidance_wwtp
Working plan guidance_wwtp
 
ERICK RENALDI REZAL CV
ERICK RENALDI REZAL CVERICK RENALDI REZAL CV
ERICK RENALDI REZAL CV
 
Lecture 9 plant economics
Lecture 9 plant economicsLecture 9 plant economics
Lecture 9 plant economics
 
Work Experience
Work ExperienceWork Experience
Work Experience
 
Boo wind power in egypt
Boo wind power in egyptBoo wind power in egypt
Boo wind power in egypt
 
Lecture 10 plant economics
Lecture 10 plant economicsLecture 10 plant economics
Lecture 10 plant economics
 
Current Fluor Resume
Current Fluor ResumeCurrent Fluor Resume
Current Fluor Resume
 
CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1CARGILLPROJOVERVIEW_rev1
CARGILLPROJOVERVIEW_rev1
 
Afaq CV (April 17, 2016)
Afaq CV (April 17, 2016)Afaq CV (April 17, 2016)
Afaq CV (April 17, 2016)
 
John Charles Snyder Lead Engineer resume
John Charles Snyder Lead Engineer resumeJohn Charles Snyder Lead Engineer resume
John Charles Snyder Lead Engineer resume
 
Co Gen Presentation Final
Co Gen Presentation FinalCo Gen Presentation Final
Co Gen Presentation Final
 

Patrick Calder Experience Summary

  • 1. Patrick D. Calder 25 Stepping Stone Ln Portland, ME 04103 (207)232-0944 patrickcalder@hotmail.com Summary of Significant Engineering Project and Management Experience 1) Overhauls for power plant diesel generators a) Six units at 12,000 running hours, 18,000 running hours, and 24,000 hrs each b) Total cost per unit: $750,000 at each overhaul c) Duration of project: up to six months prior preparation, work completed at each phase in 14-40 days. d) Coordinated ordering and delivery of parts, scheduling of labor, scope of work performed, and impact on overall plant operation including outages e) Budgeted for repair of individual components for off-site refurbishment by third party vendors, directed scope of repair work 2) Repair, Refit, and Regulatory Inspection of Steam Boilers and Generators a) Two units twice each major overhaul, once each regulatory inspection b) Total cost per unit: $50,000; overall cost $200,000 c) Duration of project: one month prior preparation, work completed in 7 days d) Coordinated ordering, delivery, and supply of parts; oversaw rebuilding of fittings, parts, and associated components in onboard facility e) Interfaced with regulatory agencies for inspection and compliance with federal regulations on condition, repair, and reinstallation 3) Redesign, reinstall main engineering power plant cooling water systems to repair damage and failures and facilitate upgrades a) Design temporary workaround for work on main systems, purchase raw materials needed, coordinate and interface with maintenance crew(s) for work. b) Direct and organize two multi-disciplined vendor teams made up of more than a dozen individual contractors: one for construction of secondary cooling system, one for internal repair of primary system, both with minimal impact on normal operations of vessel power production and air conditioning services c) Liaison with contractors and subcontractors and reconcile problems in scope of work gaps and overlaps d) Construction of additional systems to support primary system and return of primary system to service upon completion of repairs; removal of secondary system upon completion of work e) Total cost (labor and materials): approximately $400,000 4) Redesign, construction, and installation of auxiliary cooling and water production systems a) Research, coordinate with vendors, and purchase new equipment to replace or modify substandard equipment already installed. b) Plan and oversee installation of equipment, including labor and operational cost management. c) Total cost (labor and materials): approximately $100,000 5) Major Shutdown of Power Plant (Drydock) a) Capital improvement and maintenance projects for all equipment, including power generation, water production, inspections by regulatory agencies, and major overhauls. Total cost
  • 2. approximately $1 million at each event. b) Liaison with US Naval and military officers for facilities operations 6) Follow-up of problems related to installations of previously constructed propulsion, electrical, and automation systems a) Scheduling of inspections, budgeting and tracking costs of repairs, devising plan for repairs to minimize operational impact b) Total cost approximately $250,000 c) Budgeted for repair of individual components for off-site refurbishment by third party vendors and subcontractors, directed scope of repair work 7) Miscellaneous repair, maintenance, and refurbishment projects a) Examples: seal replacement on stabilizing fins, manufacturer inspection of major equipment, replacement of desalination plant equipment, replacement of generators, rerouting of cabling and wiring on massive scale, installation of new system components b) Projects range from maintenance repaired within one day, to projects involving redesign, improvement, or overhaul lasting months c) Total cost: $3 million annual operating budget for materials, $1.5 million for labor including overtime costs, both independent of other projects 8) Environmental Improvements and Designs, Malin International Ship Repair and Drydock a) Project and Consultant development for installation of water purification systems and other environmental initiatives b) Directed purchase of materials, designs of systems, and construction and installation of shipboard oil and water separation systems c) Total cost: approximately $150,000 9) Refit of Rolls Royce/Alstom Electrical Propulsion Units a) Coordination with vendors for purchase, installation, and labor cost of all associated equipment including bearings, pumps, electrical cabling and wiring, automation controls, and regulatory approval b) Total cost approximately $1.5 million 10) Installation of Carbon Emissions Scrubber System a) Determine locations for major retrofit piping, electrical components, pumps, and auxiliary equipment onboard vessel and review and approve designs proposed by vendor/system designer. b) Direct onboard construction team for placement and modification as necessary of proposed system c) Coordinate purchase of materials, and shipment to location as they are needed d) Review environmental regulations vs planned installation model; adjust accordingly e) Total cost: $10 million+ 11) Complete overhaul of engineering power-plant and facility and associated systems, accommodations, and ancillary equipment (refrigeration, water treatment, oil purification, waste water treatment) a) Construction of new facilities, including electrical, water, and other utilities b) Interface with regulatory agencies to ensure compliance with construction designs, practices, and installation c) Further planning for next evolution in 2016 d) Total cost: approximately $25 million