SlideShare a Scribd company logo
1 of 28
MINISTRY OF CITY PLANNING & WATER SUPPLY
Pathma Gunawardana
Project Director
PROJECT DETAILS
Project Name : Anamaduwa Integrated Water Supply Project
Project Period : 07/02/2017 - 06/02/2020 ( 36 months)
Covered Area : 125 GND’s including Anamaduwa ,
Kotawehara,Nawagaththegama,Part of
Galgamuwa,Puttalama,Mundalama and
Mahakumbukkadawala Devisions
Funding Source : Spanish Government & HNB
No of Beneficiaries : 81741
Total Estimated Cost : Local Component - 1941.9 Rs.Mn
Foreign Component - 6683.27 Rs.Mn
Contract Agreement signed :27.05.2015
Loan Effective Date :16.02.2016 (ICO Bank)
19.02.2016 (HNB Bank)
Intake & Treatment Plant
• Intake Source - Inginimitiya Resourvoir,
• Capacity - 12,500 m3/day
• Treatment Plant at Inginimitiya
• Capacity -11,000 m3/day
• Raw water transmission line - 1.0 km
• Clear water transmission line - 61 km
• Distribution Line - 328 km
PROJECT SCOPE
Water Towers
Water Tower Capacity (m3)
Anamaduwa Tower 1000
Mahakubukkadawala Tower 1500
Nawagattegama Tower
(at Mulllegama Temple)
300
Kotawehera
( Halmillewa)
300
Treatement Plant
(Iginimitiya)
100
5
Progress of construction of structures
No. Structure Current Status Planned Progress
01. Kotawehera Tower
(300m3)
Tower shaft construction in progress 100% 12%
02. Nawagaththegama
Tower (300m3)
Construction started and foundation
excavation in progress
100% 12%
03. Anamaduwa Tower
(1000m3)
Construction will be started on 7th May
2018.
11% 14%
04. Mahakumbukkadawala
Tower (1500m3)
Construction will be started at end of
May 2018.
12% 2%
05. Water Treatment Plant Construction not yet started
(Design works in progress)
33% 0%
06. Intake at Inginimitiya
reservoir
Construction not yet started
(Comments are pending from Irri.Dept
and Design works in progress )
28% 0%
6
Progress of Network Modelling
No. Pipe line Current Status Planned Progress
01. Raw Water Transmission (1.0 km) Network modelling finalized 100% 100%
02. Clear Water Transmission (61 Km) Network modelling finalized 100% 100%
03.
Clear Water Distribution (328 Km)
a) Nawagaththegama Zone
b) Kotawehera Zone
c) Anamaduwa Zone
d) Mahakumbukkadawala Zone
Network modelling finalized
100%
100%
100%
100%
100%
100%
100%
90%
Financial Progress
7
TEC
Cumulative Expenditure
as at 31st August %
Foreign 6683.27 1722.98 25.78
GOSL 1941.90 196.37 10.11
Total 8625.17 1919.35 22.25
Physical Progress
Major Activities
Targeted
Completion
Date
Physical Progress (%) 31st August
Target Actual
Preliminary surveying works 31/7/17 100% 100%
Geotechnical Investigations 31/7/17 100% 100%
Raw water test 6/2/18 100% 100%
Design of Transmission line 1/9/17 100% 100%
Design of Distribution line 30/9/17 100% 97%
Design of Towers 31/8/17 100% 90%
Design of Water Treatment Plant +
Intake
9/11/17 100% 39%
Construction of Towers 17/09/19 48% 10%
Physical Progress- 23%
Tower at
Kotawehera
10
Tower at
Anamaduwa
11
Work In Progress
Tower at
Nawagaththegama
12
Road Crossings
All numbers of crossings along with i-road
project - Completed
Major Issues
13
• Road Crossings ( Micro tunneling)
• Comments on Irrigation Structures-
• Project Management Unit
• VAT & NBT Payment to Contractor
• Pipe supply
• Progress reporting Formats
ISSUE No 01 - Irrigation Department
Issue
Current Situation
Issue Description:
Action Taken
•Irrigation Dept, comments on drawings of
Intake structures
Impact:
Propose Plan of Action:
Option 1
•Delay in finalizing the design & starting construction
Quick response on Drawings for comments
• Requested to change the location of intake ???
•Discussed with them and not yet received.
Intake Location Details
15
Issue
Current Situation
Issue Description:
Action Taken
•Irrigation Dept, comments on drawings of
Intake structures
Impact:
Propose Plan of Action:
Option 1
•Delay in finalizing the design & starting construction
Quick response on Drawings for comments
• Requested to change the location of intake ???
•Discussed with them and not yet received.
Issue
Current Situation
Issue Description:
Action Taken
•Irrigation Dept, comments on drawings of
Intake structures
Impact:
Propose Plan of Action:
Option 1
•Delay in finalizing the design & starting construction
Quick response on Drawings for comments
• Requested to change the location of intake ???
•Discussed with them and not yet received.
ISSUE No 2 – Road Crossings
Issue
Current Situation
Issue Description:
Action Taken
•Road Crossing Open trench pipe laying
Impact:
Propose Plan of Action:
Option 1
Option 2
•Discussion had with PD –RDA NW)
•Town center 4 nos crossings – agreed
•Other Places?????
•Difficulties in Micro tunneling pipe laying of DI pipes and
• large diameters of PE Pipes
Approval for open trench pipe laying Required
Road crossing- Open Trench
19
PIPE LINE PLACE DETAILS OF PIPE
Transmission
Line
Mullegama Junction 500mm -HDPE
Kottukachchiya Junction 350 mm - DI
Distribution Line Madurankuliya Town 250 mm -DI
Town Center
4 nos. Crossings
225mm - HDPE
Road crossing
ISSUE No 03 - PMU
Issue
Current Situation
Issue Description:
Action Taken
Recruiting of PMU
Impact:
Propose Plan of Action:
Option 1
Conducted interviews for short listed
candidates
Basic salary of permanent employee in same category × (a factor of
1.25 or 1.5)as per the previous project staff recruitment procedure
Names of the qualified candidates were sent for
approval
•Difficulties in work without Engineers & Eng. Assistants.
The experience requirement for these positions is high. Refer next slide
The salary based on the project cost is proposed to change
for a unique salary scale for all projects.
Option 2
Low experienced personnel are proposed to recruit while
keeping the salary to the Basic salary of parallel permanent
employees
Option 3
22
Action Taken & Current situation
Vacancy
No. of
vacancies
No.
Applied
No. of
candidates
called for
the
interview
No.Of
candidate
s
presented
for the
interview
No. of
qualified
candidate
s
Engineers - Civil 01 57 05 02 02
Engineers -
Mechanical
01 59 11 08 04
Engineers - Electrical 01 32 02 01 01
Engineer Assistants-
Civil
09 176 29 15 10
Engineer Assistants -
Mechanical
01 44 04 04 04
Engineer Assistants -
Electronic
01 43 08 02 00
ISSUE No 04- VAT & NBT Payment
Issue
Current Situation
Issue Description:
Action Taken
•VAT & NBT payment for IPC No. 1 & IPC No.2
Impact:
Propose Plan of Action:
Option 1
•Contractor has paid NBT for IPC No. 1 , and
requested to reimburse. VAT amount for payment
•Contractor wants to submit the VAT return documents. So
requested the VAT Payment of IPC No 1 & IPC 2
To be reimbursed the NBT payment
 If vote ledger VAT payment done, VAT return
facility contractor.
Handed over the invoice to reimburse the NBT payment
VAT payment ?????
24
Payment No IPC 01 (Mn) IPC 02 (Mn)
Payment
Foreign Foreign Local
1,512,651.62 Euro 1,494,989.16 Euro Rs. 6,620,201.28
TAX
NBT
Rs. 5,384,132.17 Rs. 5,787,350.01
* Paid by the Contractor. Needs to
be reimbursed
*Contractor informed that NBT shall not
be paid and penalties on late payment
of tax shall be boned by NWSDB.
VAT
Rs. 41,188,611.14 Rs. 44,273,227.66
*Paid by Vote basis by NWSDB .
*Tax refund problem to Contractor
*Not Finalized
ISSUE No 05- Pipe Supply
Issue
Current Situation
Issue Description:
Action Taken
Impact:
Propose Plan of Action:
•Requested instructions from Addl.GM(WSP)/
GM on the colour of PE pipes
•Delay of purchasing pipes
•Decision pending from the committee.
•Approval for PE pipes
•Decision shall be given to contractor
Option 1
ISSUE No 06- Progress Reporting
Issue
Current Situation
Issue Description:
Action Taken
•Progress Reporting
Impact:
Propose Plan of Action:
Option 1
•There are more reports requested by many sections
with different formats
No of formats in next slide
•Difficulties in reserving engineer for that work as only two
engineers are available.
One or two formats to be finalized
•One Engineer is reserved for that
27
Title of the Report
Needs to be submitted
Monthly Quarterly Annualy
As per
Request
1 Quarterly progress report for Ministry ✔
2 Capital budget report for Ministry ✔
3 Report for President Secretariat ✔
4 Quarterly progress report for GM ✔
5 2A Quarterly progress report for DGM (PC) ✔
6
1A - Action physical plan for Budget Review
Implementation Committee ✔
7
1B- Action financial plan for Budget Review
Implementation Committee ✔
8 2B monthly financial progress report for WSP ✔
9 Monthly physical & financial progress reports for PMU ✔
10
Report for Department of Project Management and
Monitoring(Ms.Chandra Kumari) ✔
11 Annual report for WSP ✔
12 Physical & financial action plan for GM ✔
13 Report for Finance Division (42 list of projects) ✔
14 Reports for ERD ✔
15
Report for Progress of Development Initiatives for
Director(Planning) ✔
16
Report for Assistant Director P&M (Ms.Anoma Ilukwatta)
✔
28

More Related Content

Similar to AIWSP presentation SCM 3 11.09.2018 (1).ppt

Final Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptxFinal Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptxIESGATEWiz
 
Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017Pont Samuel-De Champlain Bridge
 
PROJECT MGT. PRESENTATION
PROJECT MGT. PRESENTATIONPROJECT MGT. PRESENTATION
PROJECT MGT. PRESENTATIONmaheshvkat1972
 
Neelum Jhelum Hydropower Project (NJHP)
Neelum Jhelum Hydropower Project (NJHP)Neelum Jhelum Hydropower Project (NJHP)
Neelum Jhelum Hydropower Project (NJHP)IRFAN UR REHMAN
 
Graham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairGraham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairFairfax County
 
Fast track projects experiences and overview by Rajesh Prasad
Fast track projects   experiences and overview by Rajesh PrasadFast track projects   experiences and overview by Rajesh Prasad
Fast track projects experiences and overview by Rajesh PrasadRajesh Prasad
 
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014San Diego County Water Authority
 
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017Pont Samuel-De Champlain Bridge
 
Bay Delta Conservation Plan - Infrastructure Review - Feb. 13, 2014
Bay Delta Conservation Plan - Infrastructure Review - Feb. 13, 2014Bay Delta Conservation Plan - Infrastructure Review - Feb. 13, 2014
Bay Delta Conservation Plan - Infrastructure Review - Feb. 13, 2014San Diego County Water Authority
 
James Hele CV 26th May 2016 (1)
James Hele CV 26th May 2016 (1)James Hele CV 26th May 2016 (1)
James Hele CV 26th May 2016 (1)James Hele
 

Similar to AIWSP presentation SCM 3 11.09.2018 (1).ppt (20)

Final Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptxFinal Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
 
summer internship
summer internshipsummer internship
summer internship
 
PPT_Final_18-02-15
PPT_Final_18-02-15PPT_Final_18-02-15
PPT_Final_18-02-15
 
ramakant_23.9.2016 (1)
ramakant_23.9.2016 (1)ramakant_23.9.2016 (1)
ramakant_23.9.2016 (1)
 
Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017
 
PROJECT MGT. PRESENTATION
PROJECT MGT. PRESENTATIONPROJECT MGT. PRESENTATION
PROJECT MGT. PRESENTATION
 
Water Management Financing in the Caribbean - Part 2
Water Management Financing in the Caribbean - Part 2Water Management Financing in the Caribbean - Part 2
Water Management Financing in the Caribbean - Part 2
 
Neelum Jhelum Hydropower Project (NJHP)
Neelum Jhelum Hydropower Project (NJHP)Neelum Jhelum Hydropower Project (NJHP)
Neelum Jhelum Hydropower Project (NJHP)
 
Graham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairGraham Port Plaza Emergency Repair
Graham Port Plaza Emergency Repair
 
AMT CV (3)
AMT CV (3)AMT CV (3)
AMT CV (3)
 
Fast track projects experiences and overview by Rajesh Prasad
Fast track projects   experiences and overview by Rajesh PrasadFast track projects   experiences and overview by Rajesh Prasad
Fast track projects experiences and overview by Rajesh Prasad
 
Project Quality control Progress .pptx
Project Quality control  Progress .pptxProject Quality control  Progress .pptx
Project Quality control Progress .pptx
 
NEDA
NEDANEDA
NEDA
 
Resume
ResumeResume
Resume
 
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
 
CV - Dsouza UPDATED 03-04-2016
CV - Dsouza UPDATED 03-04-2016CV - Dsouza UPDATED 03-04-2016
CV - Dsouza UPDATED 03-04-2016
 
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
 
AMIT 17357.pptx
AMIT 17357.pptxAMIT 17357.pptx
AMIT 17357.pptx
 
Bay Delta Conservation Plan - Infrastructure Review - Feb. 13, 2014
Bay Delta Conservation Plan - Infrastructure Review - Feb. 13, 2014Bay Delta Conservation Plan - Infrastructure Review - Feb. 13, 2014
Bay Delta Conservation Plan - Infrastructure Review - Feb. 13, 2014
 
James Hele CV 26th May 2016 (1)
James Hele CV 26th May 2016 (1)James Hele CV 26th May 2016 (1)
James Hele CV 26th May 2016 (1)
 

Recently uploaded

High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...Call girls in Ahmedabad High profile
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 

AIWSP presentation SCM 3 11.09.2018 (1).ppt

  • 1. MINISTRY OF CITY PLANNING & WATER SUPPLY Pathma Gunawardana Project Director
  • 2. PROJECT DETAILS Project Name : Anamaduwa Integrated Water Supply Project Project Period : 07/02/2017 - 06/02/2020 ( 36 months) Covered Area : 125 GND’s including Anamaduwa , Kotawehara,Nawagaththegama,Part of Galgamuwa,Puttalama,Mundalama and Mahakumbukkadawala Devisions Funding Source : Spanish Government & HNB No of Beneficiaries : 81741 Total Estimated Cost : Local Component - 1941.9 Rs.Mn Foreign Component - 6683.27 Rs.Mn Contract Agreement signed :27.05.2015 Loan Effective Date :16.02.2016 (ICO Bank) 19.02.2016 (HNB Bank)
  • 3. Intake & Treatment Plant • Intake Source - Inginimitiya Resourvoir, • Capacity - 12,500 m3/day • Treatment Plant at Inginimitiya • Capacity -11,000 m3/day • Raw water transmission line - 1.0 km • Clear water transmission line - 61 km • Distribution Line - 328 km PROJECT SCOPE
  • 4. Water Towers Water Tower Capacity (m3) Anamaduwa Tower 1000 Mahakubukkadawala Tower 1500 Nawagattegama Tower (at Mulllegama Temple) 300 Kotawehera ( Halmillewa) 300 Treatement Plant (Iginimitiya) 100
  • 5. 5 Progress of construction of structures No. Structure Current Status Planned Progress 01. Kotawehera Tower (300m3) Tower shaft construction in progress 100% 12% 02. Nawagaththegama Tower (300m3) Construction started and foundation excavation in progress 100% 12% 03. Anamaduwa Tower (1000m3) Construction will be started on 7th May 2018. 11% 14% 04. Mahakumbukkadawala Tower (1500m3) Construction will be started at end of May 2018. 12% 2% 05. Water Treatment Plant Construction not yet started (Design works in progress) 33% 0% 06. Intake at Inginimitiya reservoir Construction not yet started (Comments are pending from Irri.Dept and Design works in progress ) 28% 0%
  • 6. 6 Progress of Network Modelling No. Pipe line Current Status Planned Progress 01. Raw Water Transmission (1.0 km) Network modelling finalized 100% 100% 02. Clear Water Transmission (61 Km) Network modelling finalized 100% 100% 03. Clear Water Distribution (328 Km) a) Nawagaththegama Zone b) Kotawehera Zone c) Anamaduwa Zone d) Mahakumbukkadawala Zone Network modelling finalized 100% 100% 100% 100% 100% 100% 100% 90%
  • 7. Financial Progress 7 TEC Cumulative Expenditure as at 31st August % Foreign 6683.27 1722.98 25.78 GOSL 1941.90 196.37 10.11 Total 8625.17 1919.35 22.25
  • 8. Physical Progress Major Activities Targeted Completion Date Physical Progress (%) 31st August Target Actual Preliminary surveying works 31/7/17 100% 100% Geotechnical Investigations 31/7/17 100% 100% Raw water test 6/2/18 100% 100% Design of Transmission line 1/9/17 100% 100% Design of Distribution line 30/9/17 100% 97% Design of Towers 31/8/17 100% 90% Design of Water Treatment Plant + Intake 9/11/17 100% 39% Construction of Towers 17/09/19 48% 10% Physical Progress- 23%
  • 11. 11 Work In Progress Tower at Nawagaththegama
  • 12. 12 Road Crossings All numbers of crossings along with i-road project - Completed
  • 13. Major Issues 13 • Road Crossings ( Micro tunneling) • Comments on Irrigation Structures- • Project Management Unit • VAT & NBT Payment to Contractor • Pipe supply • Progress reporting Formats
  • 14. ISSUE No 01 - Irrigation Department Issue Current Situation Issue Description: Action Taken •Irrigation Dept, comments on drawings of Intake structures Impact: Propose Plan of Action: Option 1 •Delay in finalizing the design & starting construction Quick response on Drawings for comments • Requested to change the location of intake ??? •Discussed with them and not yet received.
  • 16. Issue Current Situation Issue Description: Action Taken •Irrigation Dept, comments on drawings of Intake structures Impact: Propose Plan of Action: Option 1 •Delay in finalizing the design & starting construction Quick response on Drawings for comments • Requested to change the location of intake ??? •Discussed with them and not yet received.
  • 17. Issue Current Situation Issue Description: Action Taken •Irrigation Dept, comments on drawings of Intake structures Impact: Propose Plan of Action: Option 1 •Delay in finalizing the design & starting construction Quick response on Drawings for comments • Requested to change the location of intake ??? •Discussed with them and not yet received.
  • 18. ISSUE No 2 – Road Crossings Issue Current Situation Issue Description: Action Taken •Road Crossing Open trench pipe laying Impact: Propose Plan of Action: Option 1 Option 2 •Discussion had with PD –RDA NW) •Town center 4 nos crossings – agreed •Other Places????? •Difficulties in Micro tunneling pipe laying of DI pipes and • large diameters of PE Pipes Approval for open trench pipe laying Required
  • 19. Road crossing- Open Trench 19 PIPE LINE PLACE DETAILS OF PIPE Transmission Line Mullegama Junction 500mm -HDPE Kottukachchiya Junction 350 mm - DI Distribution Line Madurankuliya Town 250 mm -DI Town Center 4 nos. Crossings 225mm - HDPE
  • 21. ISSUE No 03 - PMU Issue Current Situation Issue Description: Action Taken Recruiting of PMU Impact: Propose Plan of Action: Option 1 Conducted interviews for short listed candidates Basic salary of permanent employee in same category × (a factor of 1.25 or 1.5)as per the previous project staff recruitment procedure Names of the qualified candidates were sent for approval •Difficulties in work without Engineers & Eng. Assistants. The experience requirement for these positions is high. Refer next slide The salary based on the project cost is proposed to change for a unique salary scale for all projects. Option 2 Low experienced personnel are proposed to recruit while keeping the salary to the Basic salary of parallel permanent employees Option 3
  • 22. 22 Action Taken & Current situation Vacancy No. of vacancies No. Applied No. of candidates called for the interview No.Of candidate s presented for the interview No. of qualified candidate s Engineers - Civil 01 57 05 02 02 Engineers - Mechanical 01 59 11 08 04 Engineers - Electrical 01 32 02 01 01 Engineer Assistants- Civil 09 176 29 15 10 Engineer Assistants - Mechanical 01 44 04 04 04 Engineer Assistants - Electronic 01 43 08 02 00
  • 23. ISSUE No 04- VAT & NBT Payment Issue Current Situation Issue Description: Action Taken •VAT & NBT payment for IPC No. 1 & IPC No.2 Impact: Propose Plan of Action: Option 1 •Contractor has paid NBT for IPC No. 1 , and requested to reimburse. VAT amount for payment •Contractor wants to submit the VAT return documents. So requested the VAT Payment of IPC No 1 & IPC 2 To be reimbursed the NBT payment  If vote ledger VAT payment done, VAT return facility contractor. Handed over the invoice to reimburse the NBT payment VAT payment ?????
  • 24. 24 Payment No IPC 01 (Mn) IPC 02 (Mn) Payment Foreign Foreign Local 1,512,651.62 Euro 1,494,989.16 Euro Rs. 6,620,201.28 TAX NBT Rs. 5,384,132.17 Rs. 5,787,350.01 * Paid by the Contractor. Needs to be reimbursed *Contractor informed that NBT shall not be paid and penalties on late payment of tax shall be boned by NWSDB. VAT Rs. 41,188,611.14 Rs. 44,273,227.66 *Paid by Vote basis by NWSDB . *Tax refund problem to Contractor *Not Finalized
  • 25. ISSUE No 05- Pipe Supply Issue Current Situation Issue Description: Action Taken Impact: Propose Plan of Action: •Requested instructions from Addl.GM(WSP)/ GM on the colour of PE pipes •Delay of purchasing pipes •Decision pending from the committee. •Approval for PE pipes •Decision shall be given to contractor Option 1
  • 26. ISSUE No 06- Progress Reporting Issue Current Situation Issue Description: Action Taken •Progress Reporting Impact: Propose Plan of Action: Option 1 •There are more reports requested by many sections with different formats No of formats in next slide •Difficulties in reserving engineer for that work as only two engineers are available. One or two formats to be finalized •One Engineer is reserved for that
  • 27. 27 Title of the Report Needs to be submitted Monthly Quarterly Annualy As per Request 1 Quarterly progress report for Ministry ✔ 2 Capital budget report for Ministry ✔ 3 Report for President Secretariat ✔ 4 Quarterly progress report for GM ✔ 5 2A Quarterly progress report for DGM (PC) ✔ 6 1A - Action physical plan for Budget Review Implementation Committee ✔ 7 1B- Action financial plan for Budget Review Implementation Committee ✔ 8 2B monthly financial progress report for WSP ✔ 9 Monthly physical & financial progress reports for PMU ✔ 10 Report for Department of Project Management and Monitoring(Ms.Chandra Kumari) ✔ 11 Annual report for WSP ✔ 12 Physical & financial action plan for GM ✔ 13 Report for Finance Division (42 list of projects) ✔ 14 Reports for ERD ✔ 15 Report for Progress of Development Initiatives for Director(Planning) ✔ 16 Report for Assistant Director P&M (Ms.Anoma Ilukwatta) ✔
  • 28. 28