NORTHProject Newsletter
September 2015
The Gateway Upgrade North project has progressed to the final design stage
following the announcement of a preferred contractor to design and construct the
$1.162 billion project.
Following a ten month tender process conducted
by the Department of Transport and Main
Roads and Transurban Queensland, Lend Lease
Engineering Pty Limited has been chosen to design
and construct the Gateway Upgrade North project.
The interactive tender process has ensured the
best value outcomes and the most innovative
solutions to provide maximum benefit to motorists
and the community.
The original Gateway Upgrade North Preferred
Plan was released to the public in October 2013.
As a result of the tender process, a number of
key innovations have been made to improve the
Preferred Plan, including:
`` 	Future proofing the motorway by making
allowance for the six lane upgrade to
be widened to eight lanes in the future,
accommodating forecasted traffic increases and
population growth.
`` Incorporating an off-road pedestrian and bicycle
path along the entire length of the project with
covered rest areas and a new pedestrian/cycle
connection over the Sandgate Road/Shorncliffe
rail line.
`` Constructing a new northbound bridge over
Sandgate Road and the Shorncliffe rail line to
replace the existing bridge and avoid long term
maintenance issues.
`` 	Improved outcomes for the Deagon Racecourse.
Under the Preferred Plan the racetrack had to
be realigned, however under the revised design
the track will be unaffected and only the starting
chute will be relocated.
`` 	Significantly reduced impact on the Deagon
Wetlands.
`` Relocation of the motorway ramps to and from
the upgraded Deagon Deviation to improve
safety outcomes and increase capacity.
`` Rehabilitation of the Gateway Motorway
between Bracken Ridge and the Bruce Highway
including pavement and safety improvements.
See map overleaf for further detail on the project’s
design
Early works update
The early works currently being undertaken by
contractor Fulton Hogan are well advanced. These
works are preparing the site for construction of
the major works and include earthworks and
drainage near the Nudgee Golf Course and north of
Nundah Creek.
These early works will be completed by October
2015 (weather permitting).
The relocation of several Energex towers is also
required to enable the widening of the motorway.
Preparatory works are underway just north of the
Nudgee interchange and will involve the construction
of new poles and removal of existing towers.
`` the Gateway Upgrade
North project is jointly
funded by the Australian
and Queensland
Governments
`` involves upgrading the
Gateway Motorway to six
lanes between Nudgee
and Bracken Ridge
`` will widen the Deagon
Deviation to provide two
lanes in each direction
between Depot Road and
Bracken Ridge Road
`` includes the construction
of a new, off-road shared
pedestrian and cycle
path between Nudgee
and Bracken Ridge
`` will enhance safety, ease
congestion and improve
freight movements on the
national network
`` installs Intelligent
Transport Systems such
as variable message
signs, CCTV cameras and
variable speed signs.
About the
project:
Safety improvements
Following completion of the project motorists will benefit from
significant safety improvements including:
`` upgrades to interchanges with the lengthening of on and off-ramps
`` installation of median and roadside barriers
`` extra lanes and wider shoulders
`` separation of local traffic using the Deagon Deviation from
motorway traffic
`` closure of northbound Sandgate Road on-ramp to eliminate
weaving and avoid the impact of local traffic using the motorway
for short local journeys
`` improved motorway alignment by easing curves
`` installation of Intelligent Transport Systems such as variable
message signs, CCTV cameras and variable speed signs.
Changes to Deagon Deviation
To improve motorists’ safety, a number of changes will be made to
the Deagon Deviation.
`` 	Two new northbound lanes will be constructed to separate
Redcliffe bound traffic from the Gateway Motorway - this means
motorists will travel along Sandgate Road and continue onto the
new Deagon Deviation without needing to use the motorway.
`` 	Through the interactive tender process, design improvements
have led to the relocation of the northbound off-ramp to the
Deagon Deviation – this means motorway traffic travelling north to
Redcliffe will now exit left off the motorway just before the Depot
Road off-ramp and travel over the Gateway Motorway on a new
overpass to seamlessly join with the new northbound Deagon
Deviation.
Constructing this new northbound Deagon Deviation connection
greatly improves safety outcomes by eliminating weaving on the
motorway, as well as increasing motorway capacity.
More detail about how these changes to the Deagon Deviation will
affect your journey are provided on the maps overleaf.
Active transport connections
The Gateway Upgrade North project will significantly improve active
transport infrastructure for pedestrians and cyclists. This includes
construction of a new, off-road shared pedestrian and cycle path
along the length of the project from Nudgee to Bracken Ridge, with
connections to existing local bicycle and pedestrian networks.
The new pathway will be 3.5m wide and will connect the Kedron
Brook Bikeway at Nudgee to the existing Gateway Motorway
pedestrian/cyclist underpass at Bracken Ridge, making use of any
existing shared paths adjacent to the Gateway Motorway.
The new pathway will provide safe and sustainable travel for
pedestrians and cyclists on the north side of Brisbane.
Grade separated crossings will be provided:
`` under Nudgee Road at Nudgee
`` over the Gateway Motorway at Nudgee Road
`` over Sandgate Road and the Shorncliffe rail line at Deagon
`` under Bicentennial Road at Boondall
`` under Deagon Deviation.
Five covered rest areas will also be provided along the new
shared pathway. These facilities will include lighting, seating and
drinking water for people and pets (at two locations), providing an
opportunity for pathway users to take a rest and enjoy the natural
surroundings.
Improvements to footpaths will also be made along:
`` Nudgee Road
`` Depot Road.
To improve traffic flow and pedestrian safety and access to the
North Boondall train station, the Sandgate Road and Holroyd Street
intersection will be signalised.
Over the coming months, Lend Lease will commence
detailed design and further preliminary investigative works.
This stage progresses the design ready for construction to
start in early 2016.
Activities expected to occur over the coming months include:
`` geotechnical and pavement condition investigations
`` surveying
`` inspections of existing structures and condition surveys
on existing roads
`` detailed final construction planning and approvals
`` set up of site office at Transport and Main Roads’ Depot
Road facility
`` set up of other construction compounds
`` preparation and early temporary works
`` water, electricity and communications services survey
and relocation.
What’s next
Artist impression of Nudgee Road interchange (looking south)
Sketch of rest area along shared pathway
Nudgee Service
Centre
Nudgee Golf Course
DeagonDeviation
BrackenRidgeRd
Deagon Wetlands
Deagon
Racecourse
Boondall
Wetlands
Brisbane
Entertainment
Centre
Sandgate Rd
Deagon
Station
North
Boondall
Station Boondall
Station
Nudgee
Station
Nudgee
Service
Centre
Nudgee Waterhole
Reserve
Nudgee
Golf Course
BCC
Transfer Centre
NudgeeRd
Station
Childs Rd
NudgeeRd
NundahCreek
Braun St
DepotRd
StanworthRd
BoardSt
Ca
bbage Tree
Creek
Bi
centennialRd
BarrettSt
Shorncliffe Rail Line
Gateway Upgrade North project revised design
How the upgraded Deagon Deviation will work
For a closer look at the Gateway Upgrade North project revised design visit www.gatewayupgradenorth.com.au
Travelling north to Gateway Motorway/Bruce Highway
	Sandgate Road to Gateway Motorway/Bruce Highway: access via the Depot Road on-ramp
(instead of the current Sandgate Road northbound on-ramp, which will be closed)
	Depot Road to Gateway Motorway/Bruce Highway: access via the existing Depot Road
northbound on-ramp
GATEWAY MOTORWAY
DEPOTROAD
BRAUN STREETDEAGON DEVIATION
SANDGATE ROAD
ON-RAMP
CLOSED
Bruce Highway
Redcliffe
Airport
Travelling south to Gateway Motorway and Depot/Sandgate Roads
	Redcliffe to the Gateway Motorway: access via the relocated on-ramp from the Deagon
Deviation - this ramp has been moved further south to combine with the existing
southbound on-ramp from Depot Road
	Depot Road to Gateway Motorway: access via the existing Depot Road southbound on-ramp
	Redcliffe to Depot Road/Sandgate Road: access via the upgraded Depot Road/Braun Street
intersection
GATEWAY MOTORWAY
DEPOTROAD
DEAGON DEVIATION
BRAUN STREET
Bruce Highway
Redcliffe
Airport
Bruce Highway
Redcliffe
Airport
Travelling north to Redcliffe
	Gateway Motorway to Redcliffe: access the Deagon Deviation by exiting left off the motorway
just before the Depot Road off-ramp and travel over the Gateway Motorway on an overpass to
join with the new northbound Deagon Deviation
	Sandgate Road to Redcliffe: continue onto the Deagon Deviation via the upgraded Depot
Road/Braun Street intersection to access Redcliffe without needing to use the motorway
(instead of the current Sandgate Road northbound on-ramp, which will be closed)
	Depot Road/Board Street to Redcliffe: access the Deagon Deviation via the upgraded Depot
Road/Braun Street intersection without needing to use the motorway (instead of the current
Depot Road on-ramp)
GATEWAY MOTORWAY
DEPOTROAD
BRAUN STREET
SANDGATE ROAD
DEAGON DEVIATION
ON-RAMP
CLOSED
Bruce Highway
Redcliffe
Airport
3
3
5
5
7
7
3
2
2
1
1
4
4 6
6
8
8
New signalised intersection
at Bracken Ridge Road/
Barfoot Street to replace
existing roundabout
Depot Road widened to
four lanes between Braun
Street and the Gateway
Motorway ramps
Access to Deagon Deviation via
upgraded Braun Street/Depot
Rd intersection
New northbound access
to Deagon Deviation and
Redcliffe via overpass from
the Gateway Motorway
New northbound bridge over
Sandgate Road/Shorncliffe
rail line, including new
shared pathway
Incorporation of already
completed works from Gateway
Additional Lane Project
Closure of Sandgate Road
northbound on-ramp
New signalised intersection
at Sandgate Road/Holroyd
Street for improved access to
North Boondall train station
Extended on and off-ramps at
Bicentennial Road interchange
New northbound Deagon
Deviation connection separate
from Gateway Motorway
New bridges over
Nundah Creek
Extended on and
off-ramps at Nudgee
Road interchange
New Nudgee Road
bridge over Gateway
Motorway
Realignment of
motorway to ease curves
and improve safety
Connect to existing
bikeway bridge
Connect to existing
bikeways
Connect to existing bikeways
Connect to existing
Jim Soorley Bikeway
Realignment of motorway to
ease curves and improve safety
See below for details
on how the Deagon
Deviation will work
	 Main alignment – 3 lanes minimum
	 in each direction
	Off-ramp
	On-ramp
	 Modifications to local road
	 Bridge structure
	 New shared cycle/pedestrian pathway
	Access to shared cycle/pedestrian pathway
Pedestrian overpass
Pedestrian underpass
	 Rest area along shared pathway
	Fauna underpass
	 Fauna overpass (rope ladders)
Legend
Taoist Temple
Deagon Racecourse
Artist impression of Gateway Motorway interchange just north of Depot Road (looking north)
BRACKEN RIDGE ROAD
Environmental management
The project team is dedicated to positive environmental outcomes
throughout the design and construction of the project.
Through innovative changes to the original Preferred Plan, the design
now demonstrates a reduced footprint, particularly around the
Deagon Wetlands and Deagon Racecourse. This has resulted in an
overall reduction in the amount of vegetation clearing required.
Six fauna crossings have been included in the design at key locations
along the project corridor to provide safe locations for animals to
cross from one side of the motorway to the other. Fauna underpasses
and overhead rope ladders will be provided, with overhead crossings
designed specifically for squirrel gliders. Fauna fencing will also
be installed to to direct animals to the fauna crossing locations
preventing them from accessing the motorway.
Noise barriers
Construction of new noise barriers and improvements to existing
noise barriers will be undertaken where required. The final design
will identify any sites requiring new or upgraded noise barriers. The
project is required to comply with the road traffic noise criteria set by
Transport and Main Roads. Further detail will be provided on noise
barrier locations in the coming months.
Traffic management
All construction works will be scheduled to minimise traffic
disruption to motorists and impacts on neighbours.
To minimise motorist delays, four lanes will be maintained on the
motorway during daylight hours at reduced speeds of 80km/h to
ensure motorists’ safety. Any works expected to have an impact on
traffic, such as single lane closures, will be conducted at night when
traffic volumes are lower.
Advance notification will be provided to motorists prior to significant
traffic changes via social media, email, 13 19 40, letterbox drops and
the project website.
Contact details
The project team is committed to working with the
community to better understand your views and ensure the
successful delivery of the Gateway Upgrade North project.
You can contact the project team via:
contactus@gatewayupgradenorth.com.au
1800 607 755 (freecall)
www.gatewayupgradenorth.com.au
*Free call from anywhere in Australia, call charges apply for mobile phones and payphones. Check with
your service provider for call costs.
JULY 2015
Contract
award
AUGUST 2015
Start of final
design phase
OCTOBER 2015
Current early
works completed
LATE 2015
Preliminary
works for major
construction
underway
LATE 2015
Site office
establishment
EARLY 2016
Start of major
construction
LATE 2017
Completion
of Deagon
Deviation
duplication
LATE 2018
Completion of
construction
Project timeline
Sustainability
Sustainable outcomes including considering the motorway’s
neighbours, reducing waste and thinking long term will be a focus for
the project during design and construction.
To achieve these outcomes, the project is aiming to meet the
Infrastructure Sustainability Council of Australia (ISCA) rating of
‘excellent’ – the first major road project in Queensland to seek an
ISCA rating.
To gain the excellent rating, the project has to prove its achievements
in how it has been managed including how it uses construction
materials, controls pollution, protects ecology, delivers community
benefits and incorporates innovation.
Transurban Queensland and Transport and Main Roads will work
with the project contractor to investigate the use of innovative
methodologies and sustainable materials throughout the project’s
design and construction. This will ensure the benefits of the project
will continue to be realised long after its completion.
Impacts to North Boondall train station
carpark
Construction of the new northbound bridges over Sandgate Road and
the Shorncliffe rail line, will require significant works in the vicinity
of the North Boondall train station carpark. These works will have an
impact on the number of parks available during construction.
The project team is working closely with TransLink to minimise the
impacts to commuters. This will include the provision of a new off-
street carpark to compensate for the majority of carparks affected
during construction. This new carpark will be located closer to the
train station and will increase the total number of available carparks
on completion of construction. Early notification will be provided to
train commuters prior to any carparking changes.

More Related Content

What's hot

Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open HouseCrosstown TO
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCrosstown TO
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Crosstown TO
 
Laird Station Open House
Laird Station Open HouseLaird Station Open House
Laird Station Open HouseCrosstown TO
 
Mount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design ReviewMount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design ReviewCrosstown TO
 
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016VDOT Northern Virginia
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018Crosstown TO
 
Major Contracts Undertaken 03 07 11[1]
Major Contracts Undertaken 03 07 11[1]Major Contracts Undertaken 03 07 11[1]
Major Contracts Undertaken 03 07 11[1]Rob_Borland
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Crosstown TO
 
Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation Crosstown TO
 
Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Crosstown TO
 
North Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsNorth Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsFairfax County
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2Crosstown TO
 
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
1604 Syd City Centre COMMUNITY UPDATE project update_FINALCandice Spiroski
 
Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Crosstown TO
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCrosstown TO
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Crosstown TO
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017Crosstown TO
 

What's hot (20)

Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open House
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017
 
Laird Station Open House
Laird Station Open HouseLaird Station Open House
Laird Station Open House
 
Mount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design ReviewMount Dennis Mobility Hub Update and Station Design Review
Mount Dennis Mobility Hub Update and Station Design Review
 
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
 
Major Contracts Undertaken 03 07 11[1]
Major Contracts Undertaken 03 07 11[1]Major Contracts Undertaken 03 07 11[1]
Major Contracts Undertaken 03 07 11[1]
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
 
Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation
 
Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017
 
Quander Road Walkway
Quander Road WalkwayQuander Road Walkway
Quander Road Walkway
 
North Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsNorth Shore Sidewalk Improvements
North Shore Sidewalk Improvements
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2
 
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
1604 Syd City Centre COMMUNITY UPDATE project update_FINAL
 
Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017
 

Viewers also liked

Fuentes de Informacion
Fuentes de InformacionFuentes de Informacion
Fuentes de InformacionAna Mariiaa M
 
Microsoft word proyecto-de-vida-angie-chuquitarco
Microsoft word   proyecto-de-vida-angie-chuquitarcoMicrosoft word   proyecto-de-vida-angie-chuquitarco
Microsoft word proyecto-de-vida-angie-chuquitarcoSteven Chacha
 
Excelling in Exhibitions Training Prospectus 2017
Excelling in Exhibitions Training Prospectus 2017Excelling in Exhibitions Training Prospectus 2017
Excelling in Exhibitions Training Prospectus 2017Kathy Herd
 
Group- Emotions Kids group FINAL*
Group- Emotions Kids group FINAL*Group- Emotions Kids group FINAL*
Group- Emotions Kids group FINAL*Morgan Pearson, LSW
 
Medical Records 2 004.Jpg
Medical Records 2 004.JpgMedical Records 2 004.Jpg
Medical Records 2 004.Jpgfisher_andrea
 
презентация "Зимнее время года"
 презентация "Зимнее время года" презентация "Зимнее время года"
презентация "Зимнее время года"презентация
 
Aparato Repoductor Masculino
Aparato Repoductor Masculino Aparato Repoductor Masculino
Aparato Repoductor Masculino Aletx Marroquin
 
LinDexia Mullen Personal Persona Slide Show
LinDexia Mullen Personal Persona Slide ShowLinDexia Mullen Personal Persona Slide Show
LinDexia Mullen Personal Persona Slide ShowLinDexia Mullen
 
Proyecto de-vida-domenica-herrera
Proyecto de-vida-domenica-herreraProyecto de-vida-domenica-herrera
Proyecto de-vida-domenica-herreraLeonardo Ramón
 

Viewers also liked (14)

Catalogo T'inka
Catalogo T'inkaCatalogo T'inka
Catalogo T'inka
 
Fuentes de Informacion
Fuentes de InformacionFuentes de Informacion
Fuentes de Informacion
 
Microsoft word proyecto-de-vida-angie-chuquitarco
Microsoft word   proyecto-de-vida-angie-chuquitarcoMicrosoft word   proyecto-de-vida-angie-chuquitarco
Microsoft word proyecto-de-vida-angie-chuquitarco
 
Veronica hect yeneRIA
Veronica hect yeneRIAVeronica hect yeneRIA
Veronica hect yeneRIA
 
File ripristinato 1
File ripristinato 1File ripristinato 1
File ripristinato 1
 
Excelling in Exhibitions Training Prospectus 2017
Excelling in Exhibitions Training Prospectus 2017Excelling in Exhibitions Training Prospectus 2017
Excelling in Exhibitions Training Prospectus 2017
 
Group- Emotions Kids group FINAL*
Group- Emotions Kids group FINAL*Group- Emotions Kids group FINAL*
Group- Emotions Kids group FINAL*
 
Matriz
MatrizMatriz
Matriz
 
Medical Records 2 004.Jpg
Medical Records 2 004.JpgMedical Records 2 004.Jpg
Medical Records 2 004.Jpg
 
презентация "Зимнее время года"
 презентация "Зимнее время года" презентация "Зимнее время года"
презентация "Зимнее время года"
 
Modulo 7-ubv
Modulo 7-ubvModulo 7-ubv
Modulo 7-ubv
 
Aparato Repoductor Masculino
Aparato Repoductor Masculino Aparato Repoductor Masculino
Aparato Repoductor Masculino
 
LinDexia Mullen Personal Persona Slide Show
LinDexia Mullen Personal Persona Slide ShowLinDexia Mullen Personal Persona Slide Show
LinDexia Mullen Personal Persona Slide Show
 
Proyecto de-vida-domenica-herrera
Proyecto de-vida-domenica-herreraProyecto de-vida-domenica-herrera
Proyecto de-vida-domenica-herrera
 

Similar to GUN-newsletter-2_270815_web

Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdfChaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdfCrosstown TO
 
BLASE TOWNSING CV 2015
BLASE TOWNSING CV 2015BLASE TOWNSING CV 2015
BLASE TOWNSING CV 2015Blase Townsing
 
Interim Shuttle Association Service Project Project.docx
Interim Shuttle Association Service Project          Project.docxInterim Shuttle Association Service Project          Project.docx
Interim Shuttle Association Service Project Project.docxnormanibarber20063
 
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...Maureen Kenney
 
I-285-SR400InterchangeReconstruction
I-285-SR400InterchangeReconstructionI-285-SR400InterchangeReconstruction
I-285-SR400InterchangeReconstructionAlain Gonzalez
 
20160704 Carline_Andrew
20160704 Carline_Andrew20160704 Carline_Andrew
20160704 Carline_AndrewAndrew Carline
 
The 3068 Group - Presentation to East West Link Assessment Panel
The 3068 Group - Presentation to East West Link Assessment PanelThe 3068 Group - Presentation to East West Link Assessment Panel
The 3068 Group - Presentation to East West Link Assessment PanelChris Goodman
 
Sr 826 (palmetto expressway)interchange reconstruction
Sr 826 (palmetto expressway)interchange reconstructionSr 826 (palmetto expressway)interchange reconstruction
Sr 826 (palmetto expressway)interchange reconstructiongbfengineering
 
Eastern Works Open House - October 24, 2019
Eastern Works Open House  - October 24, 2019Eastern Works Open House  - October 24, 2019
Eastern Works Open House - October 24, 2019Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCrosstown TO
 
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCrosstown TO
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022Crosstown TO
 
Chaplin-Avenue CLC - Sept 14, 2022 compressed .pptx
Chaplin-Avenue CLC - Sept 14, 2022 compressed .pptxChaplin-Avenue CLC - Sept 14, 2022 compressed .pptx
Chaplin-Avenue CLC - Sept 14, 2022 compressed .pptxCrosstown TO
 
Braddock Road Walkway - Carlbern Drive to Clubside Lane
Braddock Road Walkway - Carlbern Drive to Clubside LaneBraddock Road Walkway - Carlbern Drive to Clubside Lane
Braddock Road Walkway - Carlbern Drive to Clubside LaneFairfax County
 
Silverbrook Road & Southrun Road Intersection Improvements
Silverbrook Road & Southrun Road Intersection ImprovementsSilverbrook Road & Southrun Road Intersection Improvements
Silverbrook Road & Southrun Road Intersection ImprovementsFairfax County
 
Practical Work Report - Fletcher
Practical Work Report - FletcherPractical Work Report - Fletcher
Practical Work Report - FletcherJade Keswick
 

Similar to GUN-newsletter-2_270815_web (20)

Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdfChaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
 
BLASE TOWNSING CV 2015
BLASE TOWNSING CV 2015BLASE TOWNSING CV 2015
BLASE TOWNSING CV 2015
 
Paquette, Jason 2016 CV
Paquette, Jason 2016 CVPaquette, Jason 2016 CV
Paquette, Jason 2016 CV
 
Interim Shuttle Association Service Project Project.docx
Interim Shuttle Association Service Project          Project.docxInterim Shuttle Association Service Project          Project.docx
Interim Shuttle Association Service Project Project.docx
 
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
Bridge Construction, Pedestrian Safety Upgrades, Tree-Plantings and Road Impr...
 
CV - Dsouza UPDATED 03-04-2016
CV - Dsouza UPDATED 03-04-2016CV - Dsouza UPDATED 03-04-2016
CV - Dsouza UPDATED 03-04-2016
 
I-285-SR400InterchangeReconstruction
I-285-SR400InterchangeReconstructionI-285-SR400InterchangeReconstruction
I-285-SR400InterchangeReconstruction
 
Wellborn Community Plan
Wellborn Community PlanWellborn Community Plan
Wellborn Community Plan
 
20160704 Carline_Andrew
20160704 Carline_Andrew20160704 Carline_Andrew
20160704 Carline_Andrew
 
The 3068 Group - Presentation to East West Link Assessment Panel
The 3068 Group - Presentation to East West Link Assessment PanelThe 3068 Group - Presentation to East West Link Assessment Panel
The 3068 Group - Presentation to East West Link Assessment Panel
 
Sr 826 (palmetto expressway)interchange reconstruction
Sr 826 (palmetto expressway)interchange reconstructionSr 826 (palmetto expressway)interchange reconstruction
Sr 826 (palmetto expressway)interchange reconstruction
 
Eastern Works Open House - October 24, 2019
Eastern Works Open House  - October 24, 2019Eastern Works Open House  - October 24, 2019
Eastern Works Open House - October 24, 2019
 
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
 
Perth Stadium community briefing presentation
Perth Stadium community briefing presentationPerth Stadium community briefing presentation
Perth Stadium community briefing presentation
 
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
Brentcliffe to Victoria Park CLC Meeting - Presentation - Jan 13, 2022
 
Chaplin-Avenue CLC - Sept 14, 2022 compressed .pptx
Chaplin-Avenue CLC - Sept 14, 2022 compressed .pptxChaplin-Avenue CLC - Sept 14, 2022 compressed .pptx
Chaplin-Avenue CLC - Sept 14, 2022 compressed .pptx
 
Braddock Road Walkway - Carlbern Drive to Clubside Lane
Braddock Road Walkway - Carlbern Drive to Clubside LaneBraddock Road Walkway - Carlbern Drive to Clubside Lane
Braddock Road Walkway - Carlbern Drive to Clubside Lane
 
Silverbrook Road & Southrun Road Intersection Improvements
Silverbrook Road & Southrun Road Intersection ImprovementsSilverbrook Road & Southrun Road Intersection Improvements
Silverbrook Road & Southrun Road Intersection Improvements
 
Practical Work Report - Fletcher
Practical Work Report - FletcherPractical Work Report - Fletcher
Practical Work Report - Fletcher
 

GUN-newsletter-2_270815_web

  • 1. DEPOT ROAD BICENTENNIALROAD SANDGATE ROAD NUDGEEROADNUDGEEROAD BRAUN STREET Gateway UPGRADE NORTHProject Newsletter September 2015 The Gateway Upgrade North project has progressed to the final design stage following the announcement of a preferred contractor to design and construct the $1.162 billion project. Following a ten month tender process conducted by the Department of Transport and Main Roads and Transurban Queensland, Lend Lease Engineering Pty Limited has been chosen to design and construct the Gateway Upgrade North project. The interactive tender process has ensured the best value outcomes and the most innovative solutions to provide maximum benefit to motorists and the community. The original Gateway Upgrade North Preferred Plan was released to the public in October 2013. As a result of the tender process, a number of key innovations have been made to improve the Preferred Plan, including: `` Future proofing the motorway by making allowance for the six lane upgrade to be widened to eight lanes in the future, accommodating forecasted traffic increases and population growth. `` Incorporating an off-road pedestrian and bicycle path along the entire length of the project with covered rest areas and a new pedestrian/cycle connection over the Sandgate Road/Shorncliffe rail line. `` Constructing a new northbound bridge over Sandgate Road and the Shorncliffe rail line to replace the existing bridge and avoid long term maintenance issues. `` Improved outcomes for the Deagon Racecourse. Under the Preferred Plan the racetrack had to be realigned, however under the revised design the track will be unaffected and only the starting chute will be relocated. `` Significantly reduced impact on the Deagon Wetlands. `` Relocation of the motorway ramps to and from the upgraded Deagon Deviation to improve safety outcomes and increase capacity. `` Rehabilitation of the Gateway Motorway between Bracken Ridge and the Bruce Highway including pavement and safety improvements. See map overleaf for further detail on the project’s design Early works update The early works currently being undertaken by contractor Fulton Hogan are well advanced. These works are preparing the site for construction of the major works and include earthworks and drainage near the Nudgee Golf Course and north of Nundah Creek. These early works will be completed by October 2015 (weather permitting). The relocation of several Energex towers is also required to enable the widening of the motorway. Preparatory works are underway just north of the Nudgee interchange and will involve the construction of new poles and removal of existing towers. `` the Gateway Upgrade North project is jointly funded by the Australian and Queensland Governments `` involves upgrading the Gateway Motorway to six lanes between Nudgee and Bracken Ridge `` will widen the Deagon Deviation to provide two lanes in each direction between Depot Road and Bracken Ridge Road `` includes the construction of a new, off-road shared pedestrian and cycle path between Nudgee and Bracken Ridge `` will enhance safety, ease congestion and improve freight movements on the national network `` installs Intelligent Transport Systems such as variable message signs, CCTV cameras and variable speed signs. About the project:
  • 2. Safety improvements Following completion of the project motorists will benefit from significant safety improvements including: `` upgrades to interchanges with the lengthening of on and off-ramps `` installation of median and roadside barriers `` extra lanes and wider shoulders `` separation of local traffic using the Deagon Deviation from motorway traffic `` closure of northbound Sandgate Road on-ramp to eliminate weaving and avoid the impact of local traffic using the motorway for short local journeys `` improved motorway alignment by easing curves `` installation of Intelligent Transport Systems such as variable message signs, CCTV cameras and variable speed signs. Changes to Deagon Deviation To improve motorists’ safety, a number of changes will be made to the Deagon Deviation. `` Two new northbound lanes will be constructed to separate Redcliffe bound traffic from the Gateway Motorway - this means motorists will travel along Sandgate Road and continue onto the new Deagon Deviation without needing to use the motorway. `` Through the interactive tender process, design improvements have led to the relocation of the northbound off-ramp to the Deagon Deviation – this means motorway traffic travelling north to Redcliffe will now exit left off the motorway just before the Depot Road off-ramp and travel over the Gateway Motorway on a new overpass to seamlessly join with the new northbound Deagon Deviation. Constructing this new northbound Deagon Deviation connection greatly improves safety outcomes by eliminating weaving on the motorway, as well as increasing motorway capacity. More detail about how these changes to the Deagon Deviation will affect your journey are provided on the maps overleaf. Active transport connections The Gateway Upgrade North project will significantly improve active transport infrastructure for pedestrians and cyclists. This includes construction of a new, off-road shared pedestrian and cycle path along the length of the project from Nudgee to Bracken Ridge, with connections to existing local bicycle and pedestrian networks. The new pathway will be 3.5m wide and will connect the Kedron Brook Bikeway at Nudgee to the existing Gateway Motorway pedestrian/cyclist underpass at Bracken Ridge, making use of any existing shared paths adjacent to the Gateway Motorway. The new pathway will provide safe and sustainable travel for pedestrians and cyclists on the north side of Brisbane. Grade separated crossings will be provided: `` under Nudgee Road at Nudgee `` over the Gateway Motorway at Nudgee Road `` over Sandgate Road and the Shorncliffe rail line at Deagon `` under Bicentennial Road at Boondall `` under Deagon Deviation. Five covered rest areas will also be provided along the new shared pathway. These facilities will include lighting, seating and drinking water for people and pets (at two locations), providing an opportunity for pathway users to take a rest and enjoy the natural surroundings. Improvements to footpaths will also be made along: `` Nudgee Road `` Depot Road. To improve traffic flow and pedestrian safety and access to the North Boondall train station, the Sandgate Road and Holroyd Street intersection will be signalised. Over the coming months, Lend Lease will commence detailed design and further preliminary investigative works. This stage progresses the design ready for construction to start in early 2016. Activities expected to occur over the coming months include: `` geotechnical and pavement condition investigations `` surveying `` inspections of existing structures and condition surveys on existing roads `` detailed final construction planning and approvals `` set up of site office at Transport and Main Roads’ Depot Road facility `` set up of other construction compounds `` preparation and early temporary works `` water, electricity and communications services survey and relocation. What’s next Artist impression of Nudgee Road interchange (looking south) Sketch of rest area along shared pathway Nudgee Service Centre Nudgee Golf Course
  • 3. DeagonDeviation BrackenRidgeRd Deagon Wetlands Deagon Racecourse Boondall Wetlands Brisbane Entertainment Centre Sandgate Rd Deagon Station North Boondall Station Boondall Station Nudgee Station Nudgee Service Centre Nudgee Waterhole Reserve Nudgee Golf Course BCC Transfer Centre NudgeeRd Station Childs Rd NudgeeRd NundahCreek Braun St DepotRd StanworthRd BoardSt Ca bbage Tree Creek Bi centennialRd BarrettSt Shorncliffe Rail Line Gateway Upgrade North project revised design How the upgraded Deagon Deviation will work For a closer look at the Gateway Upgrade North project revised design visit www.gatewayupgradenorth.com.au Travelling north to Gateway Motorway/Bruce Highway Sandgate Road to Gateway Motorway/Bruce Highway: access via the Depot Road on-ramp (instead of the current Sandgate Road northbound on-ramp, which will be closed) Depot Road to Gateway Motorway/Bruce Highway: access via the existing Depot Road northbound on-ramp GATEWAY MOTORWAY DEPOTROAD BRAUN STREETDEAGON DEVIATION SANDGATE ROAD ON-RAMP CLOSED Bruce Highway Redcliffe Airport Travelling south to Gateway Motorway and Depot/Sandgate Roads Redcliffe to the Gateway Motorway: access via the relocated on-ramp from the Deagon Deviation - this ramp has been moved further south to combine with the existing southbound on-ramp from Depot Road Depot Road to Gateway Motorway: access via the existing Depot Road southbound on-ramp Redcliffe to Depot Road/Sandgate Road: access via the upgraded Depot Road/Braun Street intersection GATEWAY MOTORWAY DEPOTROAD DEAGON DEVIATION BRAUN STREET Bruce Highway Redcliffe Airport Bruce Highway Redcliffe Airport Travelling north to Redcliffe Gateway Motorway to Redcliffe: access the Deagon Deviation by exiting left off the motorway just before the Depot Road off-ramp and travel over the Gateway Motorway on an overpass to join with the new northbound Deagon Deviation Sandgate Road to Redcliffe: continue onto the Deagon Deviation via the upgraded Depot Road/Braun Street intersection to access Redcliffe without needing to use the motorway (instead of the current Sandgate Road northbound on-ramp, which will be closed) Depot Road/Board Street to Redcliffe: access the Deagon Deviation via the upgraded Depot Road/Braun Street intersection without needing to use the motorway (instead of the current Depot Road on-ramp) GATEWAY MOTORWAY DEPOTROAD BRAUN STREET SANDGATE ROAD DEAGON DEVIATION ON-RAMP CLOSED Bruce Highway Redcliffe Airport 3 3 5 5 7 7 3 2 2 1 1 4 4 6 6 8 8 New signalised intersection at Bracken Ridge Road/ Barfoot Street to replace existing roundabout Depot Road widened to four lanes between Braun Street and the Gateway Motorway ramps Access to Deagon Deviation via upgraded Braun Street/Depot Rd intersection New northbound access to Deagon Deviation and Redcliffe via overpass from the Gateway Motorway New northbound bridge over Sandgate Road/Shorncliffe rail line, including new shared pathway Incorporation of already completed works from Gateway Additional Lane Project Closure of Sandgate Road northbound on-ramp New signalised intersection at Sandgate Road/Holroyd Street for improved access to North Boondall train station Extended on and off-ramps at Bicentennial Road interchange New northbound Deagon Deviation connection separate from Gateway Motorway New bridges over Nundah Creek Extended on and off-ramps at Nudgee Road interchange New Nudgee Road bridge over Gateway Motorway Realignment of motorway to ease curves and improve safety Connect to existing bikeway bridge Connect to existing bikeways Connect to existing bikeways Connect to existing Jim Soorley Bikeway Realignment of motorway to ease curves and improve safety See below for details on how the Deagon Deviation will work Main alignment – 3 lanes minimum in each direction Off-ramp On-ramp Modifications to local road Bridge structure New shared cycle/pedestrian pathway Access to shared cycle/pedestrian pathway Pedestrian overpass Pedestrian underpass Rest area along shared pathway Fauna underpass Fauna overpass (rope ladders) Legend Taoist Temple Deagon Racecourse Artist impression of Gateway Motorway interchange just north of Depot Road (looking north)
  • 4. BRACKEN RIDGE ROAD Environmental management The project team is dedicated to positive environmental outcomes throughout the design and construction of the project. Through innovative changes to the original Preferred Plan, the design now demonstrates a reduced footprint, particularly around the Deagon Wetlands and Deagon Racecourse. This has resulted in an overall reduction in the amount of vegetation clearing required. Six fauna crossings have been included in the design at key locations along the project corridor to provide safe locations for animals to cross from one side of the motorway to the other. Fauna underpasses and overhead rope ladders will be provided, with overhead crossings designed specifically for squirrel gliders. Fauna fencing will also be installed to to direct animals to the fauna crossing locations preventing them from accessing the motorway. Noise barriers Construction of new noise barriers and improvements to existing noise barriers will be undertaken where required. The final design will identify any sites requiring new or upgraded noise barriers. The project is required to comply with the road traffic noise criteria set by Transport and Main Roads. Further detail will be provided on noise barrier locations in the coming months. Traffic management All construction works will be scheduled to minimise traffic disruption to motorists and impacts on neighbours. To minimise motorist delays, four lanes will be maintained on the motorway during daylight hours at reduced speeds of 80km/h to ensure motorists’ safety. Any works expected to have an impact on traffic, such as single lane closures, will be conducted at night when traffic volumes are lower. Advance notification will be provided to motorists prior to significant traffic changes via social media, email, 13 19 40, letterbox drops and the project website. Contact details The project team is committed to working with the community to better understand your views and ensure the successful delivery of the Gateway Upgrade North project. You can contact the project team via: contactus@gatewayupgradenorth.com.au 1800 607 755 (freecall) www.gatewayupgradenorth.com.au *Free call from anywhere in Australia, call charges apply for mobile phones and payphones. Check with your service provider for call costs. JULY 2015 Contract award AUGUST 2015 Start of final design phase OCTOBER 2015 Current early works completed LATE 2015 Preliminary works for major construction underway LATE 2015 Site office establishment EARLY 2016 Start of major construction LATE 2017 Completion of Deagon Deviation duplication LATE 2018 Completion of construction Project timeline Sustainability Sustainable outcomes including considering the motorway’s neighbours, reducing waste and thinking long term will be a focus for the project during design and construction. To achieve these outcomes, the project is aiming to meet the Infrastructure Sustainability Council of Australia (ISCA) rating of ‘excellent’ – the first major road project in Queensland to seek an ISCA rating. To gain the excellent rating, the project has to prove its achievements in how it has been managed including how it uses construction materials, controls pollution, protects ecology, delivers community benefits and incorporates innovation. Transurban Queensland and Transport and Main Roads will work with the project contractor to investigate the use of innovative methodologies and sustainable materials throughout the project’s design and construction. This will ensure the benefits of the project will continue to be realised long after its completion. Impacts to North Boondall train station carpark Construction of the new northbound bridges over Sandgate Road and the Shorncliffe rail line, will require significant works in the vicinity of the North Boondall train station carpark. These works will have an impact on the number of parks available during construction. The project team is working closely with TransLink to minimise the impacts to commuters. This will include the provision of a new off- street carpark to compensate for the majority of carparks affected during construction. This new carpark will be located closer to the train station and will increase the total number of available carparks on completion of construction. Early notification will be provided to train commuters prior to any carparking changes.