TOPIC : FACTOR IN SELECTION OF
GOOD ALIGNMENT IN RAILWAY
NAME : ABHIJIT SAHA
ROLL NO : 26901321038
REG NO :
212690101320001(2021-2022)
SEM :07
DEPT : CIVIL ENGINEERING
YEAR : 4TH SUB : RAILWAY &
AIRPORT
ENGINEERING (CE(PE)-705A)
ASSESMENT : CA :1
CONTENTS
Need for a
new railway
line
Track
Alignment
1.Importance of
a good alignment
2. Basic
Requirements
3.Selection of
good alignment
4.Mountain
Railways and
Rack railways
Conclusion
Introduction
INTRODUCTION
• Transportation is regarded as an index of
economic, social and commercial progress of
the country.
• Where, in various modes of transportation,
railways are cheap, fast, reliable and safe.
• To make the above advantages of railways to
be true, it is needed to align the railway track
with due consideration.
• The proper alignment of the tracks for the
above advantages are discussed here.
TRACK ALIGNMENT
• Giving direction and position to the centre line
of the proposed railway track on ground.
• Horizontal Alignment – straight path, its
width, deviations in width and horizontal
curves.
• Vertical Alignment – changes in gradients and
vertical curves
NEED FOR A NEW RAILWAY
LINE
• Strategic Reasons: for quick and easy
movement of defence forces in times of war
threat.
• Political Reasons: for political needs
• Development of backward areas: to develop
and foster development of under developed
and developing areas
Need for a new railway line
(Contd.,)
• To connect new trade centres: connecting new
trade centres helps in transfer of goods quicker and
facilitate their development.
• To shorten existing rail link: Short route is
economical, faster movement of goods and
passengers.
• To meet traffic requirements: doubling the
existing routes to meet heavy traffic (few cases)
• Conversion of Gauge: Recently all Meter Gauges
(MG) are converted to Broad Gauges (BG), which
may require new railway lines.
BASIC REQUIREMENTS OF
GOOD ALIGNMENT
An ideal alignment should fulfil the following
requirements:
Purpose of the track: In general railway
serves for the following purposes:
1. Transportation: to carry passenger and
goods traffic
2. Political and Strategic: for defence purpose
and political reasons
3. Linking of centres: linking two important
stations or trade centres
4. To open new tracks: new tracks for the land
whose resources are not yet tapped
5. Shortening of existing track: Short route is
economical, faster movement of goods and
passengers.
Feasibility: Proposed track should meet all the
technical requirements and general planning of the
country.
Economy: Economy of the track can be achieved by
considering the factors like shortest possible route,
minimum initial construction cost, minimum
maintenance cost and minimum operating cost.
Safety: Accidents should be minimum. This can be
achieved by having due considerations on curves,
gradients, stability of natural slopes and
embankments.
Aesthetic aspects: travel should be comfortable and
pleasant.
FACTORS IN SELECTION OF
A GOOD ALIGNMENT
• The direct route is the shortest route which is also
the most economical route. But practically it will be
impossible to connect two points by direct route.
• It may be due to intermediate obstructions, steep
gradients, etc.,
• An alignment may be economical in initial cost, but
maintenance and operational cost may increase.
• Hence the requirements cannot be satisfied
simultaneously.
For satisfying the requirements the following factors
are to be considered in selection of good track
alignment.
Obligatory points
Position, amount and type of traffic
Gauge selection
Geometric standards
Topography of the country
Economic considerations
Other considerations
FACTORS IN SELECTION OF
A GOOD ALIGNMENT
(Contd.,)
I. Obligatory Points
• They can be classified in to two categories:
points through which the track should pass
and points through which the track should
not pass.
Points through which the track should pass:
 Important cities and towns
 Major bridges and River Crossings
 Hill passes (or) saddles
 Site for tunnels
Points through which the track should not
pass:
 Acquisition of costly land – results in heavy
compensation
 Religious places – they are protected by law
 Areas liable to flooding – water logged areas,
marshy areas, cutting in snow fall, etc.
With the following figure these can be explained.
Obligatory Points
II. Traffic – its position,
nature and amount
• Position of traffic sources gives control points for
general alignment
• Nature of traffic and potential volume of traffic
(passenger and goods), govern the type of
construction. General considerations are:
• Traffic varies as square of population
• Freight earnings are more than passenger earnings
• For a new alignment – influence area up to width
of 15km on either side and increased to 25km
after few years.
III. Gauge Selection
What is Gauge?
Gauge of a railway track is defined as the clear
distance between the inner or running faces of the
two track rails.
The following are the types of gauges used in
India:
Types of Gauge Gauge Width
Standard Gauge/ Broad
Gauge (BG)
1.67m
Meter Gauge (MG) 1.00m
Narrow Gauge (NG) 0.762m
Feeder Track Gauge/ Light
Gauge (LG)
0.610m
How to select a gauge? – Factors governing
Gauge selection:
1. Cost of construction
2. Volume and nature of traffic
3. Development of the areas
4. Physical features of the country
5. Speed of movement
DISADVANTAGES OF MULTI GAUGE
SYSTEM:
🙧 Inconvenience to passengers
🙧 Difficulty in trans-shipment of goods
🙧 Inefficient use of rolling stock
🙧 Hindrance to fast movement of goods and passenger
traffic
🙧 Additional facilities at station yards
🙧 Difficulties in balanced economic growth
🙧 Difficulties in future gauge conversion projects
“The above difficulties can be overcome by adopting a
uniform gauging system”
IV. Geometric Standards
The following geometric elements are to be considered
which would give economical combination of construction
and operating costs.
 Gradients, speed, loading and method of traction used
 Ruling gradient and minimum permissible radius of
curve
 Curve should have maximum possible radii – economical
 Reverse curves – long length of straight portion to be
provided (min. 36m)
 At stations and bridges – curves to be avoided
 Use of steep gradients – high operating costs
V. Topography of the
country
If the topography of the country is such a way
that, if steeper gradients are unavoidable, then
special ways to reduce the rate and cost of high
gradients are need to be adopted.
For alignment, topography can be classified as:
 Valley alignment
 Cross country alignment
 Mountain alignment
VALLEY ALIGNMENT
• Has no problems
• If two control points lie in the same valley, the engineer
should choose a straight line between the terminal
points with a uniform rate of gradient.
• The ends having steeper gradients can be further
negotiated by some other development.
CROSS COUNTRY ALIGNMENT
• This alignment crosses two or more streams/ water
sheds of different sizes.
• Uniform gradient is not possible, because the rail
levels are so high that there are no appreciable sags or
summits between the bridges.
• Hence the routes in this alignment have sags in
succession.
• Lowest saddles or tunnels form the obligatory points
MOUNTAIN ALIGNMENT
 It is best when accompanied by tunnelling.
 The length of the alignment is first increased between
the two extreme ends of elevation so as to limit the
gradient maximum up to the ruling gradient.
 This can be accomplished by the following special
ways:
 Zigzag development
 Switch Back development
 Spirals or complete loops development
Z
I
G
Z
A
G
A
L
I
G
N
M
E
N
T
SWITCH BACKALIGNMENT
BRIDGE SPIRALS
TUNNELSPIRAL
Mountain Alignment (Contd.,)
• If the gradients are less than 3%, then no problems
will arise and normal railways can be provided.
• But, if the gradients are more than 3%, special care
must be taken as said above.
• If the gradients are more than 6%, a central rack rail
has to be provided in between the two conventional
parallel rails.
Mountain Alignment (Contd.,)
RACK RAILS
• In case of very steep gradients, it becomes difficult for
the locomotive to pull the train load and hence the
train may slide down or slip back along the downward
gradient.
• The rack railway system consists of three rails, i.e.
two conventional rails and one extra toothed rail in
middle.
• There are various systems existing in the Indian
Railways like: Fell System, Riggenbach system and
Abt System.
THE FELL SYSTEM:
The Fell System was developed in 1860’s.
It uses a central raised toothed rail, in addition to the
two parallel rails.
These rails are braked by shoes pressing horizontally
on to the central rail, as well as by means of normal
running wheels.
For traction the locomotives are provided with
auxiliary engines powering the wheels that clamp onto
the third rail.
Brazil, France and New Zealand are the only countries
that have lines with the Fell System.
THE REIGGENBACH RACK SYSTEM:
• Invented by Niklaus Reiggenbach.
• It was given French patent in 1863.
• In this the gear teeth where in the form of rollers
arranged in the form of rungs of a ladder between two
L – shaped wrought iron rails.
• Fixed ladder rack was more complex and difficult to
build.
THE ABT SYSTEM:
• TheAbt System was devised by RomanAbt, a Swiss
Locomotive Engineer in early 1880’s.
• It overcame the limitations of The Reiggenbach system.
• Designed using solid bars having vertical teeth machined
to them.
• Two or three bars were placed in the middle of the rails.
They ensure that the pinions in the locomotive driving
wheels are constantly engaged with the track.
• First used in Harzbahn in Germany, opened in 1885.
• In India, a distance of about 20km from the ghat at Kallar
to Coonoor on Nigiri Railway, is constructed at a uniform
slope of 1 in 12 ½ and is being operated on the Abt
System
THEABT SYSTEM
Central Toothed Rail
RACK RAIL
ARRANGMENT
AFTER
KALLAR,
NILGIRI
RAILWAYS
VI. Economic Considerations
• Along with above factors, the alignment should be
economical also.
• The best alignment is the one which gives the
maximum annual return (r) which is given by the
formula:
r =
i.e. r = (R – E)/ l
This shows that for r to be maximum, proper selection
of route and increasing the annual returns by sound
track construction is to be considered.
VII. Other Considerations
1) Geological considerations Alignment
should be on good soil, free of slips or slides, not on
rocky soil.
2) Effect of flood and climate
Avoiding water logged areas.
Stations should be located on outside of the city or town
and on a level surface.
If possible track should pass through proximity of quarries
– source for ballasts are nearer.
If possible track should pass nearer to a village for cheap
labours.
CONCLUSION
• Giving direction and position to the centre line of the
proposed railway track on ground, is called as track
alignment.
• The need for new track may be due to strategic,
political reasons, to develop backward areas, to
connect new trade centres and to shorten existing
railway track.
• The factors affecting a good alignment are obligatory
points; amount, type and nature of traffic; topography
of the country; geometric; economic and other
considerations.
REFERENCES
1. Saxena, S.C and Arora, S.P. “A Text Book of
Railway Engineering”, Dhanpat Rai
Publications, New Delhi, 8th edition, 2015.
2. Chandra, Satish and Agarwal, M. M.
“Railway Engineering”, Oxford University
Press, New Delhi, 2nd edition, 2013.
3. Images from Google Images
Railway.pdf

More Related Content

Similar to Railway.pdf

Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptxashish502848
 
ALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERING
ALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERINGALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERING
ALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERINGEduHUBOnline
 
Chapter 5 Introduction to railway
Chapter 5 Introduction to railwayChapter 5 Introduction to railway
Chapter 5 Introduction to railwayKHUSHBU SHAH
 
1_Highway Engg-Ch.1 Introduction_full.pdf
1_Highway Engg-Ch.1 Introduction_full.pdf1_Highway Engg-Ch.1 Introduction_full.pdf
1_Highway Engg-Ch.1 Introduction_full.pdfShivamKumar423966
 
VTU exam Question Paper with Solution of 18CV56 HIGHWAY ENGINEERING Jan-2021-...
VTU exam Question Paper with Solution of 18CV56 HIGHWAY ENGINEERING Jan-2021-...VTU exam Question Paper with Solution of 18CV56 HIGHWAY ENGINEERING Jan-2021-...
VTU exam Question Paper with Solution of 18CV56 HIGHWAY ENGINEERING Jan-2021-...pogeto1115
 
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdfEr. Bam Bhandari
 
Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)Saksham Bhutani
 
Highway Geometric Design.pptx
Highway Geometric Design.pptxHighway Geometric Design.pptx
Highway Geometric Design.pptxPriya Sarita Mane
 
1. railway track gauge
1. railway track gauge1. railway track gauge
1. railway track gaugeGaurav Jagad
 
transportation Engineering.Highway planning,alignment and geometry.
transportation Engineering.Highway planning,alignment and geometry.transportation Engineering.Highway planning,alignment and geometry.
transportation Engineering.Highway planning,alignment and geometry.ayudge
 
Corridor Identification UTS
Corridor Identification UTSCorridor Identification UTS
Corridor Identification UTSfreshwoody patel
 
1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptxMayuriPatel90
 
Modes of transportation
Modes of transportationModes of transportation
Modes of transportationJAYDEV PATEL
 
Surveys & alignment of Railway Engineering
Surveys & alignment of Railway EngineeringSurveys & alignment of Railway Engineering
Surveys & alignment of Railway EngineeringLatif Hyder Wadho
 

Similar to Railway.pdf (20)

Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptx
 
ALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERING
ALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERINGALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERING
ALIGNMENT OF RAILWAY LINE |ALIGNMENT OF RAILWAY TRACK |RAILWAY ENGINEERING
 
Chapter 5 Introduction to railway
Chapter 5 Introduction to railwayChapter 5 Introduction to railway
Chapter 5 Introduction to railway
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
1_Highway Engg-Ch.1 Introduction_full.pdf
1_Highway Engg-Ch.1 Introduction_full.pdf1_Highway Engg-Ch.1 Introduction_full.pdf
1_Highway Engg-Ch.1 Introduction_full.pdf
 
VTU exam Question Paper with Solution of 18CV56 HIGHWAY ENGINEERING Jan-2021-...
VTU exam Question Paper with Solution of 18CV56 HIGHWAY ENGINEERING Jan-2021-...VTU exam Question Paper with Solution of 18CV56 HIGHWAY ENGINEERING Jan-2021-...
VTU exam Question Paper with Solution of 18CV56 HIGHWAY ENGINEERING Jan-2021-...
 
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
 
Mumbai-Nagpur.pdf
Mumbai-Nagpur.pdfMumbai-Nagpur.pdf
Mumbai-Nagpur.pdf
 
Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)
 
Railway engineering part2
Railway engineering part2Railway engineering part2
Railway engineering part2
 
Highway Geometric Design.pptx
Highway Geometric Design.pptxHighway Geometric Design.pptx
Highway Geometric Design.pptx
 
1. railway track gauge
1. railway track gauge1. railway track gauge
1. railway track gauge
 
transportation Engineering.Highway planning,alignment and geometry.
transportation Engineering.Highway planning,alignment and geometry.transportation Engineering.Highway planning,alignment and geometry.
transportation Engineering.Highway planning,alignment and geometry.
 
Corridor Identification UTS
Corridor Identification UTSCorridor Identification UTS
Corridor Identification UTS
 
transportation
transportationtransportation
transportation
 
1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx
 
Modes of transportation
Modes of transportationModes of transportation
Modes of transportation
 
R E T 565construction Technology Infrastructure
R E T 565construction Technology InfrastructureR E T 565construction Technology Infrastructure
R E T 565construction Technology Infrastructure
 
Construction Technology
Construction TechnologyConstruction Technology
Construction Technology
 
Surveys & alignment of Railway Engineering
Surveys & alignment of Railway EngineeringSurveys & alignment of Railway Engineering
Surveys & alignment of Railway Engineering
 

More from abhijitsaha99

26901321038_CE(OE)701C.pdf
26901321038_CE(OE)701C.pdf26901321038_CE(OE)701C.pdf
26901321038_CE(OE)701C.pdfabhijitsaha99
 
damandtypesofdamwithsiteselection-170403160723 (1) (1).pptx
damandtypesofdamwithsiteselection-170403160723 (1) (1).pptxdamandtypesofdamwithsiteselection-170403160723 (1) (1).pptx
damandtypesofdamwithsiteselection-170403160723 (1) (1).pptxabhijitsaha99
 
Environment green house effect .pdf
Environment green house effect .pdfEnvironment green house effect .pdf
Environment green house effect .pdfabhijitsaha99
 
gravity dam elementary profile.pdf
gravity dam elementary profile.pdfgravity dam elementary profile.pdf
gravity dam elementary profile.pdfabhijitsaha99
 
lec3principlevirtualworkmethod-191007114659.pptx
lec3principlevirtualworkmethod-191007114659.pptxlec3principlevirtualworkmethod-191007114659.pptx
lec3principlevirtualworkmethod-191007114659.pptxabhijitsaha99
 

More from abhijitsaha99 (7)

Hbe .pdf
Hbe .pdfHbe .pdf
Hbe .pdf
 
26901321038_CE(OE)701C.pdf
26901321038_CE(OE)701C.pdf26901321038_CE(OE)701C.pdf
26901321038_CE(OE)701C.pdf
 
damandtypesofdamwithsiteselection-170403160723 (1) (1).pptx
damandtypesofdamwithsiteselection-170403160723 (1) (1).pptxdamandtypesofdamwithsiteselection-170403160723 (1) (1).pptx
damandtypesofdamwithsiteselection-170403160723 (1) (1).pptx
 
Environment green house effect .pdf
Environment green house effect .pdfEnvironment green house effect .pdf
Environment green house effect .pdf
 
Numericals.pdf
Numericals.pdfNumericals.pdf
Numericals.pdf
 
gravity dam elementary profile.pdf
gravity dam elementary profile.pdfgravity dam elementary profile.pdf
gravity dam elementary profile.pdf
 
lec3principlevirtualworkmethod-191007114659.pptx
lec3principlevirtualworkmethod-191007114659.pptxlec3principlevirtualworkmethod-191007114659.pptx
lec3principlevirtualworkmethod-191007114659.pptx
 

Recently uploaded

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 

Recently uploaded (20)

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 

Railway.pdf

  • 1. TOPIC : FACTOR IN SELECTION OF GOOD ALIGNMENT IN RAILWAY NAME : ABHIJIT SAHA ROLL NO : 26901321038 REG NO : 212690101320001(2021-2022) SEM :07 DEPT : CIVIL ENGINEERING YEAR : 4TH SUB : RAILWAY & AIRPORT ENGINEERING (CE(PE)-705A) ASSESMENT : CA :1
  • 2. CONTENTS Need for a new railway line Track Alignment 1.Importance of a good alignment 2. Basic Requirements 3.Selection of good alignment 4.Mountain Railways and Rack railways Conclusion Introduction
  • 3. INTRODUCTION • Transportation is regarded as an index of economic, social and commercial progress of the country. • Where, in various modes of transportation, railways are cheap, fast, reliable and safe. • To make the above advantages of railways to be true, it is needed to align the railway track with due consideration. • The proper alignment of the tracks for the above advantages are discussed here.
  • 4. TRACK ALIGNMENT • Giving direction and position to the centre line of the proposed railway track on ground. • Horizontal Alignment – straight path, its width, deviations in width and horizontal curves. • Vertical Alignment – changes in gradients and vertical curves
  • 5. NEED FOR A NEW RAILWAY LINE • Strategic Reasons: for quick and easy movement of defence forces in times of war threat. • Political Reasons: for political needs • Development of backward areas: to develop and foster development of under developed and developing areas
  • 6. Need for a new railway line (Contd.,) • To connect new trade centres: connecting new trade centres helps in transfer of goods quicker and facilitate their development. • To shorten existing rail link: Short route is economical, faster movement of goods and passengers. • To meet traffic requirements: doubling the existing routes to meet heavy traffic (few cases) • Conversion of Gauge: Recently all Meter Gauges (MG) are converted to Broad Gauges (BG), which may require new railway lines.
  • 7. BASIC REQUIREMENTS OF GOOD ALIGNMENT An ideal alignment should fulfil the following requirements: Purpose of the track: In general railway serves for the following purposes: 1. Transportation: to carry passenger and goods traffic 2. Political and Strategic: for defence purpose and political reasons
  • 8. 3. Linking of centres: linking two important stations or trade centres 4. To open new tracks: new tracks for the land whose resources are not yet tapped 5. Shortening of existing track: Short route is economical, faster movement of goods and passengers.
  • 9. Feasibility: Proposed track should meet all the technical requirements and general planning of the country. Economy: Economy of the track can be achieved by considering the factors like shortest possible route, minimum initial construction cost, minimum maintenance cost and minimum operating cost. Safety: Accidents should be minimum. This can be achieved by having due considerations on curves, gradients, stability of natural slopes and embankments. Aesthetic aspects: travel should be comfortable and pleasant.
  • 10. FACTORS IN SELECTION OF A GOOD ALIGNMENT • The direct route is the shortest route which is also the most economical route. But practically it will be impossible to connect two points by direct route. • It may be due to intermediate obstructions, steep gradients, etc., • An alignment may be economical in initial cost, but maintenance and operational cost may increase. • Hence the requirements cannot be satisfied simultaneously.
  • 11. For satisfying the requirements the following factors are to be considered in selection of good track alignment. Obligatory points Position, amount and type of traffic Gauge selection Geometric standards Topography of the country Economic considerations Other considerations FACTORS IN SELECTION OF A GOOD ALIGNMENT (Contd.,)
  • 12. I. Obligatory Points • They can be classified in to two categories: points through which the track should pass and points through which the track should not pass. Points through which the track should pass:  Important cities and towns  Major bridges and River Crossings  Hill passes (or) saddles  Site for tunnels
  • 13. Points through which the track should not pass:  Acquisition of costly land – results in heavy compensation  Religious places – they are protected by law  Areas liable to flooding – water logged areas, marshy areas, cutting in snow fall, etc. With the following figure these can be explained.
  • 15. II. Traffic – its position, nature and amount • Position of traffic sources gives control points for general alignment • Nature of traffic and potential volume of traffic (passenger and goods), govern the type of construction. General considerations are: • Traffic varies as square of population • Freight earnings are more than passenger earnings • For a new alignment – influence area up to width of 15km on either side and increased to 25km after few years.
  • 16. III. Gauge Selection What is Gauge? Gauge of a railway track is defined as the clear distance between the inner or running faces of the two track rails.
  • 17. The following are the types of gauges used in India: Types of Gauge Gauge Width Standard Gauge/ Broad Gauge (BG) 1.67m Meter Gauge (MG) 1.00m Narrow Gauge (NG) 0.762m Feeder Track Gauge/ Light Gauge (LG) 0.610m
  • 18. How to select a gauge? – Factors governing Gauge selection: 1. Cost of construction 2. Volume and nature of traffic 3. Development of the areas 4. Physical features of the country 5. Speed of movement
  • 19. DISADVANTAGES OF MULTI GAUGE SYSTEM: 🙧 Inconvenience to passengers 🙧 Difficulty in trans-shipment of goods 🙧 Inefficient use of rolling stock 🙧 Hindrance to fast movement of goods and passenger traffic 🙧 Additional facilities at station yards 🙧 Difficulties in balanced economic growth 🙧 Difficulties in future gauge conversion projects “The above difficulties can be overcome by adopting a uniform gauging system”
  • 20. IV. Geometric Standards The following geometric elements are to be considered which would give economical combination of construction and operating costs.  Gradients, speed, loading and method of traction used  Ruling gradient and minimum permissible radius of curve  Curve should have maximum possible radii – economical  Reverse curves – long length of straight portion to be provided (min. 36m)  At stations and bridges – curves to be avoided  Use of steep gradients – high operating costs
  • 21. V. Topography of the country If the topography of the country is such a way that, if steeper gradients are unavoidable, then special ways to reduce the rate and cost of high gradients are need to be adopted. For alignment, topography can be classified as:  Valley alignment  Cross country alignment  Mountain alignment
  • 22. VALLEY ALIGNMENT • Has no problems • If two control points lie in the same valley, the engineer should choose a straight line between the terminal points with a uniform rate of gradient. • The ends having steeper gradients can be further negotiated by some other development.
  • 23. CROSS COUNTRY ALIGNMENT • This alignment crosses two or more streams/ water sheds of different sizes. • Uniform gradient is not possible, because the rail levels are so high that there are no appreciable sags or summits between the bridges. • Hence the routes in this alignment have sags in succession. • Lowest saddles or tunnels form the obligatory points
  • 24. MOUNTAIN ALIGNMENT  It is best when accompanied by tunnelling.  The length of the alignment is first increased between the two extreme ends of elevation so as to limit the gradient maximum up to the ruling gradient.  This can be accomplished by the following special ways:  Zigzag development  Switch Back development  Spirals or complete loops development
  • 29. Mountain Alignment (Contd.,) • If the gradients are less than 3%, then no problems will arise and normal railways can be provided. • But, if the gradients are more than 3%, special care must be taken as said above. • If the gradients are more than 6%, a central rack rail has to be provided in between the two conventional parallel rails.
  • 30. Mountain Alignment (Contd.,) RACK RAILS • In case of very steep gradients, it becomes difficult for the locomotive to pull the train load and hence the train may slide down or slip back along the downward gradient. • The rack railway system consists of three rails, i.e. two conventional rails and one extra toothed rail in middle. • There are various systems existing in the Indian Railways like: Fell System, Riggenbach system and Abt System.
  • 31. THE FELL SYSTEM: The Fell System was developed in 1860’s. It uses a central raised toothed rail, in addition to the two parallel rails. These rails are braked by shoes pressing horizontally on to the central rail, as well as by means of normal running wheels. For traction the locomotives are provided with auxiliary engines powering the wheels that clamp onto the third rail. Brazil, France and New Zealand are the only countries that have lines with the Fell System.
  • 32. THE REIGGENBACH RACK SYSTEM: • Invented by Niklaus Reiggenbach. • It was given French patent in 1863. • In this the gear teeth where in the form of rollers arranged in the form of rungs of a ladder between two L – shaped wrought iron rails. • Fixed ladder rack was more complex and difficult to build.
  • 33. THE ABT SYSTEM: • TheAbt System was devised by RomanAbt, a Swiss Locomotive Engineer in early 1880’s. • It overcame the limitations of The Reiggenbach system. • Designed using solid bars having vertical teeth machined to them. • Two or three bars were placed in the middle of the rails. They ensure that the pinions in the locomotive driving wheels are constantly engaged with the track. • First used in Harzbahn in Germany, opened in 1885. • In India, a distance of about 20km from the ghat at Kallar to Coonoor on Nigiri Railway, is constructed at a uniform slope of 1 in 12 ½ and is being operated on the Abt System
  • 37. VI. Economic Considerations • Along with above factors, the alignment should be economical also. • The best alignment is the one which gives the maximum annual return (r) which is given by the formula: r = i.e. r = (R – E)/ l This shows that for r to be maximum, proper selection of route and increasing the annual returns by sound track construction is to be considered.
  • 38. VII. Other Considerations 1) Geological considerations Alignment should be on good soil, free of slips or slides, not on rocky soil. 2) Effect of flood and climate Avoiding water logged areas. Stations should be located on outside of the city or town and on a level surface. If possible track should pass through proximity of quarries – source for ballasts are nearer. If possible track should pass nearer to a village for cheap labours.
  • 39. CONCLUSION • Giving direction and position to the centre line of the proposed railway track on ground, is called as track alignment. • The need for new track may be due to strategic, political reasons, to develop backward areas, to connect new trade centres and to shorten existing railway track. • The factors affecting a good alignment are obligatory points; amount, type and nature of traffic; topography of the country; geometric; economic and other considerations.
  • 40. REFERENCES 1. Saxena, S.C and Arora, S.P. “A Text Book of Railway Engineering”, Dhanpat Rai Publications, New Delhi, 8th edition, 2015. 2. Chandra, Satish and Agarwal, M. M. “Railway Engineering”, Oxford University Press, New Delhi, 2nd edition, 2013. 3. Images from Google Images