SlideShare a Scribd company logo
1 of 23
Hurricane Katrina, Sandy and the Boeing
             Dreamliner!!!
                 Part II.

                  By
             Dalip Raheja
          President and CEO
          The Mpower Group


                1/22/13
Dreamliner 787




© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.   2
Hot Off The Press
      key managerial wrong turning a decade ago. ..Boeing decided at the outset
      to rely on outsourcing for 70 percent of the plane’s manufactured content….
      greatly increased the managerial complexity of the project and almost certainly helps explain

      why the project ended up three years late …Boeing’s reputation ….contractual penalties.

      long-term cost in weakening Boeing’s competitiveness. …the wings and the wing-box. …
      most technologically advanced …Boeing’s secret wing-building know-how had to be
      transferred to Japan…Boeing workers …as vulgarly referring to Boeing’s technology-
      transfer

      deal as the “open kimono” policy. carbon fiber. The learning curve in putting this tricky new

      material to work has been climbed by Tokyo-based Toray and Mitsubishi, not by
      Boeing…left

      behind by its suppliers and cannot catch up .Airbus…Japanese-made carbon-fiber for the
      wings

       of its next major plane. ..Mitsubishi seems to be planning in the long run to enter the fray as
      a direct competitor to Boeing and Airbus
© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.   3
Hot Off The Press

 The right goal: add value for customers
 Overheating batteries – current focus

 “What we do know is that the cost-cutting way that Boeing went about
 outsourcing both in the US and beyond did not include steps to
 mitigate or eliminate the predicted costs and risks that have already materialized.”
                          The coordination risk                              The innovation risk

                          The outsourcing risk                               The risk of tiered
                                                                             outsourcing
                          The risk of partially                              The offshoring risk
                          The risk of communications                         The labor relations risk
                          by computer
                          The project management                             The risk of a disengaged C-
                          skills risk                                        suite


© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.   4
Hot Off The Press



  “….additional costs and risks of large-scale outsourcing. Outsourcing
  didn’t cut costs and increase profits, he wrote; instead, it drove
  profits and knowledge to suppliers while increasing costs for the
  mother company. “Not only is the work out-sourced; all of the profits
   associated with the work are out-sourced, too.”




                    Dr. L.J. Hart-Smith – Boeing, 2001

© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.   5
Value
                              Adoption is a process not an initiative
                               Solution                                  Adoption                Intended
                                                                           Introduced            Business
                                                                         Into the Market
                                                                                                 Results
  100                                                           22 %
                                                                                               Economic       • Only 8.8% of solution
UNITS OF                                                                                        Success         (product, process, etc.) will
“VALUE”                                                                                                         be successful
                                   60%
                                                                                                              • Change is hard and not
                                                                                                                easily adopted
                                                                                                              • Getting a new process /
                                                                18%                                             product adopted requires
                                                                            60%          40%
                                                                                                8.8% of All     investment (cost)
                                                                                                 Projects



                                 Technical         Stopped Because        Economic
                                  Failure            of Insufficient       Failure
                                                   Economic Success
                                                        Potential                                             Impact on project
 Innovation Process




                       100%
 % of total costs of




                                                                                                              funding
                                                                                                              •     Shift Investment
                                                                                                              •     Shift Resources
                       50%
                                                                                                              •     Longer Timeline
                                                                                                              •     “Customer” commitment

                        0%
                                                                                                                  Source: Maier, F. H.
© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.
                                                                         Time        6
Changing Value Drivers
                  Examples of Value Drivers

                            Critical to a CMO                                                    Others
           Brand                                                                               CMO
                                                           On Time       Differentiation
        Management


          Strategic                                       Sales          Relationship
          Planning                                       Support         Management


                                                         Competitive      Customer
           Lead
                                                          Analysis        Life Cycle
         Generation
                                                                         Management
                                                                                               CIO, CPO, CFO, ETC…
                                                            Industry
        Functional
                                                           Awareness     Under Budget
       Requirements




© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.      7
What do we mean by “Risk”

               Risk – From an industry training guide:
                           “The cumulative effect of the chances of an uncertain
                           occurrence that will adversely affect program or project
                           objectives. It is the degree of exposure to negative
                           events and probable consequences.”

                  Risk – The English Version:
                           “The net chance we have of stuff going wrong that could
                           screw up what we are trying to accomplish.”

                   Risk – The Mpower Group:
                           “The biggest risk a project can take is trying to eliminate
                           all risk – it can’t be done. Risk must be embraced and
                           effectively managed.”

© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.   8
Managing Risk
                 The Only Thing We Have to Fear…


                              Uncertainty                                             Risk
              Potential for negative                                         Potential for negative
              economic impact                                                economic impact
              Range of impacts                                               Range of impacts can be
              unknown / unclear                                              established
              Likelihood of occurrence                                       Likelihood of occurrence
              unknown / unclear                                              can be estimated
              Can only be worried                                            Can and should be
              about                                                          managed / mitigated

              Leads to paralysis                                             Leads to opportunities



                                      Goal: Transform Uncertainty into Risk
© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.   9
Direct vs. Systemic Causation!!

     Predictable & Inevitable!!

© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.
Managing Risk
                  Next we classify risk into four major risk types
          Market Risk →                                          Factors that would affect every supplier regardless of industry.

           Examples include: market drivers, new product introduction, interest rate
           sensitivity, currency changes, geographic risk, and political risk.

           Industry Risk →                                        Factors that would affect all suppliers in related businesses.

            Examples include: raw material price increases, shortages, environmental
            compliance, quotas, tariffs, innovation, and capacity issues.

                                                                  Factors that would prevent a single supplier from fulfilling its
           Supplier Risk →
                                                                  contractual obligation to Your Company.
            Examples include: time or production delays, quality defects, stock-outs, change in
            ownership, bankruptcy, and missed or broken promises.

            Internal Risk →                                       Factors that are internal to Your Company
             Examples include: using a single source of supply, incorrect lead-times in an
              internal system, schedule risk, exposure for stock consignment, obsolete
              inventory and transportation/logistics risk, engineering changes, errors in
              demand forecast, data integrity, BOM version control, Business Unit friction, and
              information silos.
                This assists in determining how controllable the risk is
                and our potential responses.11
© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.
Managing Risk
                  Lastly we assess the likelihood, impact, and level of
                  control for each risk.

                                                                         Severity of Effect
                                                                         (Impact)

  Manufacturing
                                                                                                         Customers
  & Suppliers

                                                                            Your
                                                                          Company
                                                    Probability of                     Level of
                                                    Occurrence                         Control
                                                    (Likelyhood)                       (Influence)

                 This helps us understand and focus on the actual magnitude of the
                 risk, and in prioritizing mitigating activities and responses.

© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.        12
Managing Risk
                  In assessing risk, it is useful to have a consistent
                  scoring methodology
                                    Likelihood                                           Impact                          Controllability
                     (The probability the risk will                           (The severity of outcomes if the   (The level of control we can exert
                        occur if unmitigated)                                         risk occurred)                    over the likelihood)
                Very unlikely                                            1   Moderate, progress           1      Total direct control         1
                                                                             disrupted with                      through project actions
                                                                             manageable extensions
                                                                             to short-mid term
                                                                             schedule and cost
                Somewhat unlikely                                        2   Medium; progress             2      Highly controllable          2
                                                                             disrupted with large                through project actions
                                                                             extensions to mid term
                                                                             schedule and cost
                50/50                                                    3   High, significant            3      Moderately controllable      3
                                                                             disruption to schedule,             through project actions
                                                                             cost, and products over
                                                                             the mid-long terms
                Highly likely                                            4   Extreme, significant         4      Minimal control              4
                                                                             disruption to successful
                                                                             delivery of objectives,
                                                                             products, and benefits
                Nearly certain                                           5   Critical, threatens          5      No control                   5
                                                                             success of program


© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.                    13
Managing Risk
                  Once this first step is complete we analyze and
                  mitigate risk
         Review the identified risks and their quantified assessments from the
          preceding steps.
         Risk analysis and mitigation develops specific, discrete, and measurable
          responses to each identified risk.
         Identify and record actions that could be taken to avoid or mitigate the
          individual risks based on their level of controllability.
                       Controllability                                                  Type of Mitigation
                                High (1)                        Actions which should be immediately incorporated into the
                                                                project plan.

                                       2

                            Medium (3)                          Actions which are contingent risk responses to be incorporated
                                                                in the project plan if the risk occurs.

                                       4

                                Low (5)                         None. By definition, such risks cannot be avoided or mitigated.

© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.             14
Managing Risk
                  Lastly we begin the process to manage and report
                  risk

               Risk Management does not end with the identification and
               implementation of mitigating strategies or potential responses

                Risk Management must monitor the effectiveness of the Risk
                Mitigation Plan
                • Tracking measurable reductions in the likelihood
                • Tracking measurable reductions in the impact of each risk


               Review the Risk Mitigation Plan on a monthly basis
                           • Discuss the status and movement of each risk reviewed
                           • Establish a Risk Watch List

                                                                         Remember Portfolio Risk
© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.            15
Most Projects needs to focus on an expanded “When”
                  and “What”
                          Projects
             typically END HERE (Deployment)

                                                      The Value to the User starts here (Adoption)                When


                  2012                                           2013      2014    2015 2016       ……………………
    ……….IProjects……….



                                                                 Attracting and
                                                                                     Risk               Market
  Traditional Focus:                                             retaining new
                                                                                  Management           position
                                                                   customers
  Cost                                                                                                              What –
     Time                                                                                                         Value Focus
       Scope                                                       Operational      Demand             Business
                                                                   Advantage        Planning            growth
          Quality



                                                                         Business Drivers of “Users”




© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.               16
Focus on Proactive Value Creation


                                                 Maximum Designed Value of “software”(solution)




                                                                         Customer A
                                                                          Value Gap




                                                                                                 Customer B
                                                                                                  Value Gap




                                                                                                              Customer C
                                                                                                               Value Gap
                                                                                             A


                                                                                             B


                                                                                             C




                                                                                             2 YEARS



© 2013 The Mpower Group, Inc. All Rights Reserved.
                                                                                      Time
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.                17
Increasing Perceived Value and lowering Perceived Cost
                 leads to increased Actual Realized Value



       Perceived “Value” > Perceived “Cost” =
  Increased Adoption       Actual Realized Value



                                     “Value” and “Costs” extend beyond Financials




© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.   18
What is Value?
                   Fundamentals of Value (Sawhney)


             Customer Defined                                            • Non-Negotiable

             Opaque                                                      • Non-Quantifiable

             Multi Dimensional                                           • Functional, Economic, Psychological

             Trade Off                                                   • Cost - Value

              Contextual                                                  Defined by How it is Used

              Relative                                                    Compared to Alternatives

              Mind Set                                                    Based on a Belief

© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.      19
What is Value?
                   IT Business Value Program – “Cost Center to Value Center”
                      (Fortune 100 Company)

             •        Behavioral change across IT – Business Value focus
             •        Uptime, service calls etc. – TTM, Increased revenue
             •        Changed relationship with customers – support to business partner
             •        New measurements, New alliances
             •        Common language, based on needs of customers
             •        Value defined by customers
             •        Standard measurement, valuation, training – evangelism!
             •        Changing corporate attitude value of IT investments
             •        Getting “customer” to accept accountability increases success
             •        Linking Business value to IT processes was critical

© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.   20
What’s Different? Example: New measures for project
                  success and completion

                     Is it patch/upgrade
                      stable?                                                           Did it reduce cost?
                     Is testing done?                                                  Did it improve service?
  Traditional




                                                                                        Are people aware of the new features?
                     Did we meet the budget?                                           Are people using the new features?
                     Did we do initial                                                 Did the business change their
                      training?                                                          processes
                                                                                         or are we repeating old mistakes?
                     Do we have a support
                                                                                        What open issues still exist?
                      person/super-user                                                 Is it better than what we had?
                      identified?                                                       What users are most displeased?
                                                                                         Why…
                                                                                        What users are most excited? Why…
                                                                         Expanded       What do our customers think?
                                                                                        What do our suppliers think?
                                                                         Thinking       How does this compare to what our
                                                                                         competitors have?
                                                                                        What process steps were automated?

© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.          21
TMG’s Approach
                Competency Model Framework
                                                                                                                                                              Illustrative


                                   Business, Industry, & Enterprise Knowledge
                                                                                                          Change
                                                                                                         Management
                                                                                Operational Management
                                                                                                         Consulting &         Functional
                                                                                                          Facilitation        Core Processes
                                                                                                                              • Engineering
                                                                                                                              • Finance         Competency Exceptional
                                                                                                         Information          • HR
                                                                                                                                                  Based     Business
                                                                                                                              • IT
                                                                                                         Technology           • Manufacturing     Talent     Results
                                                                                                                              • Operations      Management
                                                                                                                              • Quality
                                                                                                           Project            • Sales
                                                                                                         Management           • Supply Chain
                                                                                                                                                           Business Context /
                                                                                                                                                             Organizational
                                                                                                          Teamwork                                           Competencies

                                                                                                                                                              Strategic
                                                                                                                                                            Competencies

                                                                                                                                                             Functional
                                                                                                                                                            Competencies
© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.                                                   22
THANK YOU FOR ATTENDING!



                                                                                By
                                                                            Dalip Raheja
                                                                         President and CEO
                                                                         The Mpower Group
                                                                           (630) 268-8963
                                                                    www.thempowergroup.com
                                                                 http://blog.thempowergroup.com

© 2013 The Mpower Group, Inc. All Rights Reserved.
Unauthorized Duplication, Storage or Transmission Strictly Prohibited.         23

More Related Content

What's hot

4th Annual Wind Operations and Maintenance Summit USA 2012
4th Annual Wind Operations and Maintenance Summit USA 20124th Annual Wind Operations and Maintenance Summit USA 2012
4th Annual Wind Operations and Maintenance Summit USA 2012Jon Harman, Wind Energy Update
 
The Digital Oobeya at the European Lean IT Summit
The Digital Oobeya at the European Lean IT SummitThe Digital Oobeya at the European Lean IT Summit
The Digital Oobeya at the European Lean IT SummitInstitut Lean France
 
Allied Reliability Phase II EMP Development Overview (March 2009)
Allied Reliability Phase II EMP Development Overview (March 2009)Allied Reliability Phase II EMP Development Overview (March 2009)
Allied Reliability Phase II EMP Development Overview (March 2009)Chris Colson
 
"Information needs for the lean organization" by Jean Cunningham
"Information needs for the lean organization" by Jean Cunningham"Information needs for the lean organization" by Jean Cunningham
"Information needs for the lean organization" by Jean CunninghamOperae Partners
 
O509 esbge gas
O509 esbge gasO509 esbge gas
O509 esbge gasrcparkin
 
"The myth of Certainty - Is implementation a naughty word?" by Steve Bell
"The myth of Certainty - Is implementation a naughty word?" by Steve Bell"The myth of Certainty - Is implementation a naughty word?" by Steve Bell
"The myth of Certainty - Is implementation a naughty word?" by Steve BellOperae Partners
 
"Lean IT practices, from theory to application" by Mike Orzen
"Lean IT practices, from theory to application" by Mike Orzen"Lean IT practices, from theory to application" by Mike Orzen
"Lean IT practices, from theory to application" by Mike OrzenOperae Partners
 
Best Practice Transfer: An approach to the organizational adoption of best pr...
Best Practice Transfer: An approach to the organizational adoption of best pr...Best Practice Transfer: An approach to the organizational adoption of best pr...
Best Practice Transfer: An approach to the organizational adoption of best pr...ITSM Academy, Inc.
 
Mand a toolkit pmi project management
Mand a toolkit   pmi project managementMand a toolkit   pmi project management
Mand a toolkit pmi project managementchrisdoran
 
1 maintenance-strategystrategy
1  maintenance-strategystrategy1  maintenance-strategystrategy
1 maintenance-strategystrategyNgoc Dep
 
Softtek Break Through Savings No Need Offshore 2011 Asug Final
Softtek Break Through Savings No Need Offshore 2011 Asug FinalSofttek Break Through Savings No Need Offshore 2011 Asug Final
Softtek Break Through Savings No Need Offshore 2011 Asug FinalMauro Okamoto
 
Successful Outage Management Lessons Learned From Global Generation Leaders
Successful Outage Management   Lessons Learned From Global Generation LeadersSuccessful Outage Management   Lessons Learned From Global Generation Leaders
Successful Outage Management Lessons Learned From Global Generation LeadersTedLemmers
 
3rd party independant reviews
3rd party independant reviews3rd party independant reviews
3rd party independant reviewsNick Pelham
 
Recipe for a Lean IT Service by Tata Consultancy Services - European Lean IT ...
Recipe for a Lean IT Service by Tata Consultancy Services - European Lean IT ...Recipe for a Lean IT Service by Tata Consultancy Services - European Lean IT ...
Recipe for a Lean IT Service by Tata Consultancy Services - European Lean IT ...Institut Lean France
 
The Analysis and Valuation of Disruption
The Analysis and Valuation of DisruptionThe Analysis and Valuation of Disruption
The Analysis and Valuation of DisruptionHKA
 
Risk leadership perspectives Risk Manager of the Year
Risk leadership perspectives Risk Manager of the YearRisk leadership perspectives Risk Manager of the Year
Risk leadership perspectives Risk Manager of the YearKarl Davey
 

What's hot (20)

4th Annual Wind Operations and Maintenance Summit USA 2012
4th Annual Wind Operations and Maintenance Summit USA 20124th Annual Wind Operations and Maintenance Summit USA 2012
4th Annual Wind Operations and Maintenance Summit USA 2012
 
The Digital Oobeya at the European Lean IT Summit
The Digital Oobeya at the European Lean IT SummitThe Digital Oobeya at the European Lean IT Summit
The Digital Oobeya at the European Lean IT Summit
 
Allied Reliability Phase II EMP Development Overview (March 2009)
Allied Reliability Phase II EMP Development Overview (March 2009)Allied Reliability Phase II EMP Development Overview (March 2009)
Allied Reliability Phase II EMP Development Overview (March 2009)
 
"Information needs for the lean organization" by Jean Cunningham
"Information needs for the lean organization" by Jean Cunningham"Information needs for the lean organization" by Jean Cunningham
"Information needs for the lean organization" by Jean Cunningham
 
O509 esbge gas
O509 esbge gasO509 esbge gas
O509 esbge gas
 
"The myth of Certainty - Is implementation a naughty word?" by Steve Bell
"The myth of Certainty - Is implementation a naughty word?" by Steve Bell"The myth of Certainty - Is implementation a naughty word?" by Steve Bell
"The myth of Certainty - Is implementation a naughty word?" by Steve Bell
 
Ch14
Ch14Ch14
Ch14
 
Knut Samset
Knut SamsetKnut Samset
Knut Samset
 
"Lean IT practices, from theory to application" by Mike Orzen
"Lean IT practices, from theory to application" by Mike Orzen"Lean IT practices, from theory to application" by Mike Orzen
"Lean IT practices, from theory to application" by Mike Orzen
 
Best Practice Transfer: An approach to the organizational adoption of best pr...
Best Practice Transfer: An approach to the organizational adoption of best pr...Best Practice Transfer: An approach to the organizational adoption of best pr...
Best Practice Transfer: An approach to the organizational adoption of best pr...
 
Mand a toolkit pmi project management
Mand a toolkit   pmi project managementMand a toolkit   pmi project management
Mand a toolkit pmi project management
 
1 maintenance-strategystrategy
1  maintenance-strategystrategy1  maintenance-strategystrategy
1 maintenance-strategystrategy
 
Softtek Break Through Savings No Need Offshore 2011 Asug Final
Softtek Break Through Savings No Need Offshore 2011 Asug FinalSofttek Break Through Savings No Need Offshore 2011 Asug Final
Softtek Break Through Savings No Need Offshore 2011 Asug Final
 
MT-C - company presentation
MT-C - company presentationMT-C - company presentation
MT-C - company presentation
 
MGT 371 Chapter 1
MGT 371 Chapter 1MGT 371 Chapter 1
MGT 371 Chapter 1
 
Successful Outage Management Lessons Learned From Global Generation Leaders
Successful Outage Management   Lessons Learned From Global Generation LeadersSuccessful Outage Management   Lessons Learned From Global Generation Leaders
Successful Outage Management Lessons Learned From Global Generation Leaders
 
3rd party independant reviews
3rd party independant reviews3rd party independant reviews
3rd party independant reviews
 
Recipe for a Lean IT Service by Tata Consultancy Services - European Lean IT ...
Recipe for a Lean IT Service by Tata Consultancy Services - European Lean IT ...Recipe for a Lean IT Service by Tata Consultancy Services - European Lean IT ...
Recipe for a Lean IT Service by Tata Consultancy Services - European Lean IT ...
 
The Analysis and Valuation of Disruption
The Analysis and Valuation of DisruptionThe Analysis and Valuation of Disruption
The Analysis and Valuation of Disruption
 
Risk leadership perspectives Risk Manager of the Year
Risk leadership perspectives Risk Manager of the YearRisk leadership perspectives Risk Manager of the Year
Risk leadership perspectives Risk Manager of the Year
 

Viewers also liked

21 high-quality programming code construction part-i
21 high-quality programming code construction part-i21 high-quality programming code construction part-i
21 high-quality programming code construction part-imaznabili
 
Surfing Legends Final
Surfing Legends FinalSurfing Legends Final
Surfing Legends Finalgestrine
 
Surfing Legends Final
Surfing Legends FinalSurfing Legends Final
Surfing Legends Finalgestrine
 
Film315 presentation
Film315 presentationFilm315 presentation
Film315 presentation8emc
 
Surfing legends power point
Surfing legends power pointSurfing legends power point
Surfing legends power pointgestrine
 
Surfing legends final
Surfing legends finalSurfing legends final
Surfing legends finalgestrine
 
Surfing legends final
Surfing legends finalSurfing legends final
Surfing legends finalgestrine
 
Surfing legends
Surfing legendsSurfing legends
Surfing legendsgestrine
 
Andrews presentation 2.pptx
Andrews presentation 2.pptxAndrews presentation 2.pptx
Andrews presentation 2.pptxgestrine
 
Introduction to dot search
Introduction to dot searchIntroduction to dot search
Introduction to dot searchmigueldelarocha2
 
Surfing Legends Final
Surfing Legends FinalSurfing Legends Final
Surfing Legends Finalgestrine
 
How to Build High Value Relationships Under Theory Z
How to Build High Value Relationships Under Theory ZHow to Build High Value Relationships Under Theory Z
How to Build High Value Relationships Under Theory ZAnne Kohler
 
14 Defining classes
14 Defining classes14 Defining classes
14 Defining classesmaznabili
 
FILM315
FILM315FILM315
FILM3158emc
 
Reu13 orientation
Reu13 orientationReu13 orientation
Reu13 orientationgestrine
 
22 Methodology of problem solving
22 Methodology of problem solving22 Methodology of problem solving
22 Methodology of problem solvingmaznabili
 
04 Console input output-
04 Console input output-04 Console input output-
04 Console input output-maznabili
 
Hurricane Katrina, Sandy and the Boeing Dreamliner!!! PT 1
Hurricane Katrina, Sandy and the Boeing Dreamliner!!! PT 1Hurricane Katrina, Sandy and the Boeing Dreamliner!!! PT 1
Hurricane Katrina, Sandy and the Boeing Dreamliner!!! PT 1MpowerGroup
 
Executive Webinar- The How – What Does Contracting Need to Change and How?
Executive Webinar- The How – What Does Contracting Need to Change and How?Executive Webinar- The How – What Does Contracting Need to Change and How?
Executive Webinar- The How – What Does Contracting Need to Change and How?thempowergroup
 

Viewers also liked (20)

21 high-quality programming code construction part-i
21 high-quality programming code construction part-i21 high-quality programming code construction part-i
21 high-quality programming code construction part-i
 
Surfing Legends Final
Surfing Legends FinalSurfing Legends Final
Surfing Legends Final
 
Surfing Legends Final
Surfing Legends FinalSurfing Legends Final
Surfing Legends Final
 
Film315 presentation
Film315 presentationFilm315 presentation
Film315 presentation
 
Surfing legends power point
Surfing legends power pointSurfing legends power point
Surfing legends power point
 
Surfing legends final
Surfing legends finalSurfing legends final
Surfing legends final
 
Surfing legends final
Surfing legends finalSurfing legends final
Surfing legends final
 
Surfing legends
Surfing legendsSurfing legends
Surfing legends
 
Andrews presentation 2.pptx
Andrews presentation 2.pptxAndrews presentation 2.pptx
Andrews presentation 2.pptx
 
Introduction to dot search
Introduction to dot searchIntroduction to dot search
Introduction to dot search
 
Surfing Legends Final
Surfing Legends FinalSurfing Legends Final
Surfing Legends Final
 
How to Build High Value Relationships Under Theory Z
How to Build High Value Relationships Under Theory ZHow to Build High Value Relationships Under Theory Z
How to Build High Value Relationships Under Theory Z
 
14 Defining classes
14 Defining classes14 Defining classes
14 Defining classes
 
06 Loops
06 Loops06 Loops
06 Loops
 
FILM315
FILM315FILM315
FILM315
 
Reu13 orientation
Reu13 orientationReu13 orientation
Reu13 orientation
 
22 Methodology of problem solving
22 Methodology of problem solving22 Methodology of problem solving
22 Methodology of problem solving
 
04 Console input output-
04 Console input output-04 Console input output-
04 Console input output-
 
Hurricane Katrina, Sandy and the Boeing Dreamliner!!! PT 1
Hurricane Katrina, Sandy and the Boeing Dreamliner!!! PT 1Hurricane Katrina, Sandy and the Boeing Dreamliner!!! PT 1
Hurricane Katrina, Sandy and the Boeing Dreamliner!!! PT 1
 
Executive Webinar- The How – What Does Contracting Need to Change and How?
Executive Webinar- The How – What Does Contracting Need to Change and How?Executive Webinar- The How – What Does Contracting Need to Change and How?
Executive Webinar- The How – What Does Contracting Need to Change and How?
 

Similar to Iaccm jan2013 part ii finalss

E&C Industry Review By Scott Boutwell Jan09
E&C Industry Review By Scott Boutwell Jan09E&C Industry Review By Scott Boutwell Jan09
E&C Industry Review By Scott Boutwell Jan09Scott Boutwell, LEED AP
 
2.0 Adoption in the Enterprise - The Before
2.0 Adoption in the Enterprise - The Before2.0 Adoption in the Enterprise - The Before
2.0 Adoption in the Enterprise - The BeforeThe 2.0 Adoption Council
 
Future Africa
Future AfricaFuture Africa
Future AfricaLarsStork
 
Why Projects Fail: Obstacles and Solutions
Why Projects Fail: Obstacles and SolutionsWhy Projects Fail: Obstacles and Solutions
Why Projects Fail: Obstacles and SolutionsMichael Krigsman
 
Effective Change Management
Effective Change ManagementEffective Change Management
Effective Change Managementdeboeck11
 
Venture Incubation
Venture IncubationVenture Incubation
Venture Incubationjagan339
 
Organize and Justify Your EMI Initiative
Organize and Justify Your EMI InitiativeOrganize and Justify Your EMI Initiative
Organize and Justify Your EMI InitiativeNorthwest Analytics
 
New Product Introduction - Launching Success!
New Product Introduction - Launching Success! New Product Introduction - Launching Success!
New Product Introduction - Launching Success! Product Realization Group
 
What's Slowing You Down? Unlocking Strategic Speed in Your Learning Organization
What's Slowing You Down? Unlocking Strategic Speed in Your Learning OrganizationWhat's Slowing You Down? Unlocking Strategic Speed in Your Learning Organization
What's Slowing You Down? Unlocking Strategic Speed in Your Learning OrganizationHuman Capital Media
 
Consequences of a Failed ECM Implementation
Consequences of a Failed ECM ImplementationConsequences of a Failed ECM Implementation
Consequences of a Failed ECM ImplementationiDatix
 
Content Scenarios New Information Products
Content Scenarios New Information ProductsContent Scenarios New Information Products
Content Scenarios New Information ProductsMaxwell Hoffmann
 
Stream 1- Enhanced Business Performance
Stream 1- Enhanced Business PerformanceStream 1- Enhanced Business Performance
Stream 1- Enhanced Business PerformanceIBM Business Insight
 
Agile User Experience
Agile User ExperienceAgile User Experience
Agile User ExperienceACM
 
Cognizant Lunch First
Cognizant   Lunch FirstCognizant   Lunch First
Cognizant Lunch Firsttechcouncil
 
Ems11 Programme
Ems11 ProgrammeEms11 Programme
Ems11 ProgrammeMandy_Long
 

Similar to Iaccm jan2013 part ii finalss (20)

E&C Industry Review By Scott Boutwell Jan09
E&C Industry Review By Scott Boutwell Jan09E&C Industry Review By Scott Boutwell Jan09
E&C Industry Review By Scott Boutwell Jan09
 
ITW Rocol - Case Study
ITW Rocol - Case StudyITW Rocol - Case Study
ITW Rocol - Case Study
 
IT Failure and Waste
IT Failure and WasteIT Failure and Waste
IT Failure and Waste
 
2.0 Adoption in the Enterprise - The Before
2.0 Adoption in the Enterprise - The Before2.0 Adoption in the Enterprise - The Before
2.0 Adoption in the Enterprise - The Before
 
Future Africa
Future AfricaFuture Africa
Future Africa
 
Why Projects Fail: Obstacles and Solutions
Why Projects Fail: Obstacles and SolutionsWhy Projects Fail: Obstacles and Solutions
Why Projects Fail: Obstacles and Solutions
 
Icon ecpma09
Icon ecpma09Icon ecpma09
Icon ecpma09
 
Effective Change Management
Effective Change ManagementEffective Change Management
Effective Change Management
 
Venture Incubation
Venture IncubationVenture Incubation
Venture Incubation
 
Organize and Justify Your EMI Initiative
Organize and Justify Your EMI InitiativeOrganize and Justify Your EMI Initiative
Organize and Justify Your EMI Initiative
 
New Product Introduction - Launching Success!
New Product Introduction - Launching Success! New Product Introduction - Launching Success!
New Product Introduction - Launching Success!
 
What's Slowing You Down? Unlocking Strategic Speed in Your Learning Organization
What's Slowing You Down? Unlocking Strategic Speed in Your Learning OrganizationWhat's Slowing You Down? Unlocking Strategic Speed in Your Learning Organization
What's Slowing You Down? Unlocking Strategic Speed in Your Learning Organization
 
Consequences of a Failed ECM Implementation
Consequences of a Failed ECM ImplementationConsequences of a Failed ECM Implementation
Consequences of a Failed ECM Implementation
 
Managing Television Advertising Production Costs
Managing Television Advertising Production CostsManaging Television Advertising Production Costs
Managing Television Advertising Production Costs
 
Managing The 80% Problem
Managing The 80% ProblemManaging The 80% Problem
Managing The 80% Problem
 
Content Scenarios New Information Products
Content Scenarios New Information ProductsContent Scenarios New Information Products
Content Scenarios New Information Products
 
Stream 1- Enhanced Business Performance
Stream 1- Enhanced Business PerformanceStream 1- Enhanced Business Performance
Stream 1- Enhanced Business Performance
 
Agile User Experience
Agile User ExperienceAgile User Experience
Agile User Experience
 
Cognizant Lunch First
Cognizant   Lunch FirstCognizant   Lunch First
Cognizant Lunch First
 
Ems11 Programme
Ems11 ProgrammeEms11 Programme
Ems11 Programme
 

Iaccm jan2013 part ii finalss

  • 1. Hurricane Katrina, Sandy and the Boeing Dreamliner!!! Part II. By Dalip Raheja President and CEO The Mpower Group 1/22/13
  • 2. Dreamliner 787 © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited. 2
  • 3. Hot Off The Press key managerial wrong turning a decade ago. ..Boeing decided at the outset to rely on outsourcing for 70 percent of the plane’s manufactured content…. greatly increased the managerial complexity of the project and almost certainly helps explain why the project ended up three years late …Boeing’s reputation ….contractual penalties. long-term cost in weakening Boeing’s competitiveness. …the wings and the wing-box. … most technologically advanced …Boeing’s secret wing-building know-how had to be transferred to Japan…Boeing workers …as vulgarly referring to Boeing’s technology- transfer deal as the “open kimono” policy. carbon fiber. The learning curve in putting this tricky new material to work has been climbed by Tokyo-based Toray and Mitsubishi, not by Boeing…left behind by its suppliers and cannot catch up .Airbus…Japanese-made carbon-fiber for the wings of its next major plane. ..Mitsubishi seems to be planning in the long run to enter the fray as a direct competitor to Boeing and Airbus © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited. 3
  • 4. Hot Off The Press The right goal: add value for customers Overheating batteries – current focus “What we do know is that the cost-cutting way that Boeing went about outsourcing both in the US and beyond did not include steps to mitigate or eliminate the predicted costs and risks that have already materialized.” The coordination risk The innovation risk The outsourcing risk The risk of tiered outsourcing The risk of partially The offshoring risk The risk of communications The labor relations risk by computer The project management The risk of a disengaged C- skills risk suite © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited. 4
  • 5. Hot Off The Press “….additional costs and risks of large-scale outsourcing. Outsourcing didn’t cut costs and increase profits, he wrote; instead, it drove profits and knowledge to suppliers while increasing costs for the mother company. “Not only is the work out-sourced; all of the profits associated with the work are out-sourced, too.” Dr. L.J. Hart-Smith – Boeing, 2001 © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited. 5
  • 6. Value Adoption is a process not an initiative Solution Adoption Intended Introduced Business Into the Market Results 100 22 % Economic • Only 8.8% of solution UNITS OF Success (product, process, etc.) will “VALUE” be successful 60% • Change is hard and not easily adopted • Getting a new process / 18% product adopted requires 60% 40% 8.8% of All investment (cost) Projects Technical Stopped Because Economic Failure of Insufficient Failure Economic Success Potential Impact on project Innovation Process 100% % of total costs of funding • Shift Investment • Shift Resources 50% • Longer Timeline • “Customer” commitment 0% Source: Maier, F. H. © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited. Time 6
  • 7. Changing Value Drivers Examples of Value Drivers Critical to a CMO Others Brand CMO On Time Differentiation Management Strategic Sales Relationship Planning Support Management Competitive Customer Lead Analysis Life Cycle Generation Management CIO, CPO, CFO, ETC… Industry Functional Awareness Under Budget Requirements © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited. 7
  • 8. What do we mean by “Risk” Risk – From an industry training guide: “The cumulative effect of the chances of an uncertain occurrence that will adversely affect program or project objectives. It is the degree of exposure to negative events and probable consequences.” Risk – The English Version: “The net chance we have of stuff going wrong that could screw up what we are trying to accomplish.” Risk – The Mpower Group: “The biggest risk a project can take is trying to eliminate all risk – it can’t be done. Risk must be embraced and effectively managed.” © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited. 8
  • 9. Managing Risk The Only Thing We Have to Fear… Uncertainty Risk Potential for negative Potential for negative economic impact economic impact Range of impacts Range of impacts can be unknown / unclear established Likelihood of occurrence Likelihood of occurrence unknown / unclear can be estimated Can only be worried Can and should be about managed / mitigated Leads to paralysis Leads to opportunities Goal: Transform Uncertainty into Risk © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited. 9
  • 10. Direct vs. Systemic Causation!! Predictable & Inevitable!! © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited.
  • 11. Managing Risk Next we classify risk into four major risk types Market Risk → Factors that would affect every supplier regardless of industry. Examples include: market drivers, new product introduction, interest rate sensitivity, currency changes, geographic risk, and political risk. Industry Risk → Factors that would affect all suppliers in related businesses. Examples include: raw material price increases, shortages, environmental compliance, quotas, tariffs, innovation, and capacity issues. Factors that would prevent a single supplier from fulfilling its Supplier Risk → contractual obligation to Your Company. Examples include: time or production delays, quality defects, stock-outs, change in ownership, bankruptcy, and missed or broken promises. Internal Risk → Factors that are internal to Your Company Examples include: using a single source of supply, incorrect lead-times in an internal system, schedule risk, exposure for stock consignment, obsolete inventory and transportation/logistics risk, engineering changes, errors in demand forecast, data integrity, BOM version control, Business Unit friction, and information silos. This assists in determining how controllable the risk is and our potential responses.11 © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited.
  • 12. Managing Risk Lastly we assess the likelihood, impact, and level of control for each risk. Severity of Effect (Impact) Manufacturing Customers & Suppliers Your Company Probability of Level of Occurrence Control (Likelyhood) (Influence) This helps us understand and focus on the actual magnitude of the risk, and in prioritizing mitigating activities and responses. © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited. 12
  • 13. Managing Risk In assessing risk, it is useful to have a consistent scoring methodology Likelihood Impact Controllability (The probability the risk will (The severity of outcomes if the (The level of control we can exert occur if unmitigated) risk occurred) over the likelihood) Very unlikely 1 Moderate, progress 1 Total direct control 1 disrupted with through project actions manageable extensions to short-mid term schedule and cost Somewhat unlikely 2 Medium; progress 2 Highly controllable 2 disrupted with large through project actions extensions to mid term schedule and cost 50/50 3 High, significant 3 Moderately controllable 3 disruption to schedule, through project actions cost, and products over the mid-long terms Highly likely 4 Extreme, significant 4 Minimal control 4 disruption to successful delivery of objectives, products, and benefits Nearly certain 5 Critical, threatens 5 No control 5 success of program © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited. 13
  • 14. Managing Risk Once this first step is complete we analyze and mitigate risk Review the identified risks and their quantified assessments from the preceding steps. Risk analysis and mitigation develops specific, discrete, and measurable responses to each identified risk. Identify and record actions that could be taken to avoid or mitigate the individual risks based on their level of controllability. Controllability Type of Mitigation High (1) Actions which should be immediately incorporated into the project plan. 2 Medium (3) Actions which are contingent risk responses to be incorporated in the project plan if the risk occurs. 4 Low (5) None. By definition, such risks cannot be avoided or mitigated. © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited. 14
  • 15. Managing Risk Lastly we begin the process to manage and report risk Risk Management does not end with the identification and implementation of mitigating strategies or potential responses Risk Management must monitor the effectiveness of the Risk Mitigation Plan • Tracking measurable reductions in the likelihood • Tracking measurable reductions in the impact of each risk Review the Risk Mitigation Plan on a monthly basis • Discuss the status and movement of each risk reviewed • Establish a Risk Watch List Remember Portfolio Risk © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited. 15
  • 16. Most Projects needs to focus on an expanded “When” and “What” Projects typically END HERE (Deployment) The Value to the User starts here (Adoption) When 2012 2013 2014 2015 2016 …………………… ……….IProjects………. Attracting and Risk Market Traditional Focus: retaining new Management position customers Cost What – Time Value Focus Scope Operational Demand Business Advantage Planning growth Quality Business Drivers of “Users” © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited. 16
  • 17. Focus on Proactive Value Creation Maximum Designed Value of “software”(solution) Customer A Value Gap Customer B Value Gap Customer C Value Gap A B C 2 YEARS © 2013 The Mpower Group, Inc. All Rights Reserved. Time Unauthorized Duplication, Storage or Transmission Strictly Prohibited. 17
  • 18. Increasing Perceived Value and lowering Perceived Cost leads to increased Actual Realized Value Perceived “Value” > Perceived “Cost” = Increased Adoption Actual Realized Value “Value” and “Costs” extend beyond Financials © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited. 18
  • 19. What is Value? Fundamentals of Value (Sawhney) Customer Defined • Non-Negotiable Opaque • Non-Quantifiable Multi Dimensional • Functional, Economic, Psychological Trade Off • Cost - Value Contextual Defined by How it is Used Relative Compared to Alternatives Mind Set Based on a Belief © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited. 19
  • 20. What is Value? IT Business Value Program – “Cost Center to Value Center” (Fortune 100 Company) • Behavioral change across IT – Business Value focus • Uptime, service calls etc. – TTM, Increased revenue • Changed relationship with customers – support to business partner • New measurements, New alliances • Common language, based on needs of customers • Value defined by customers • Standard measurement, valuation, training – evangelism! • Changing corporate attitude value of IT investments • Getting “customer” to accept accountability increases success • Linking Business value to IT processes was critical © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited. 20
  • 21. What’s Different? Example: New measures for project success and completion  Is it patch/upgrade stable?  Did it reduce cost?  Is testing done?  Did it improve service? Traditional  Are people aware of the new features?  Did we meet the budget?  Are people using the new features?  Did we do initial  Did the business change their training? processes or are we repeating old mistakes?  Do we have a support  What open issues still exist? person/super-user  Is it better than what we had? identified?  What users are most displeased? Why…  What users are most excited? Why… Expanded  What do our customers think?  What do our suppliers think? Thinking  How does this compare to what our competitors have?  What process steps were automated? © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited. 21
  • 22. TMG’s Approach Competency Model Framework Illustrative Business, Industry, & Enterprise Knowledge Change Management Operational Management Consulting & Functional Facilitation Core Processes • Engineering • Finance Competency Exceptional Information • HR Based Business • IT Technology • Manufacturing Talent Results • Operations Management • Quality Project • Sales Management • Supply Chain Business Context / Organizational Teamwork Competencies Strategic Competencies Functional Competencies © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited. 22
  • 23. THANK YOU FOR ATTENDING! By Dalip Raheja President and CEO The Mpower Group (630) 268-8963 www.thempowergroup.com http://blog.thempowergroup.com © 2013 The Mpower Group, Inc. All Rights Reserved. Unauthorized Duplication, Storage or Transmission Strictly Prohibited. 23

Editor's Notes

  1. This is an example of IT providing a software solution for a CMO Need to get beyond what IT thinks creates VALUEB, C - Identified value drivers for CMO If IT is focusing on Cost and ROI you have missed the boatHas a CMO ever been fired for NOT meeting their budget? So when IT or SC or Finance approaches VAUE from a cost perspective they have LOST the customer
  2. MUST be defined by the Customer Not always quantifiable – lets look at the hamburger example Recruiting QOWL Employee RetentionEven if you could measure it – it is difficult to find a causual link to the “Kobe” beefMulti-Dimensional – we tend to think of functional, or economic but psychological (emotional benefits) is just as important (designer purse) Trade-off - PERCEIVED worth as compared to the costContextual - HamburgerMind Set – Outside IN perspective (value should revolve around the CUSTOMER
  3. Companies have tried to move from Cost to Value with limited successKey points:Requires a change in both DECISIONS and BEHAVIORSRequired new metricsLanguage change – needs to be in discussed in terms of the benefit to the customerGetting the CUSTOMER to ACCEPT ACCOUNTABILITYThis is a work is process – this company is not there YET
  4. You can see that when you change the context it changes the thinking and therefore the decisions that get made and the behaviors change