SlideShare a Scribd company logo
1 of 17
Risk Factor
Identified, Quantified, and Build-In impacts in Schedule Risk Analysis
Commonpractice:ScheduleRiskAnalysis process
• All identified risks that have impact on schedule are basically assigned
into activities on schedule.
• Some risks may assigned to multiple activities, hence an activity can be
influenced by multiple risks. However, many users are not aware that
prior assigning process, risks need to be categorized either Risk Event or
Risk Factor.
• Ignoring Risk Factor is “risk” to schedule risk analysis process, that will
lead to distorted results.
• This paper intended to briefly shown how much the variance could
derived from the simulation output “with” and “without” Risk Factor
AND also hoping for feedback on how to improve the process.
• Primavera Risk Analysis is a tool used for this presentation and it is
assumed that the reader(s) has understanding and experiences of using
it.
RiskFactor VS RiskEvent
• Risk Event
Is an incident/occasion that may or may not happen, that affects through
impacts on particular activities in the project.
• Risk Factor
Is an unknown element that affects the project. It is expressed as % and
resulting from it, reduces or increases the activities it affects.
Examples
Risk Events Risk Factors
Unavailability of Resources Weather
Nobody is willing to do casting, hence
casting works shall delayed.
All Offshore installation activities will
prolonged 50% longer than planned
duration.
Land Subside Productivity Labor
Zone A1/D1 has weak ground, piling work
may get effected in case soil strengthening
not properly done.
Fabrication time will takes 20% longer than
initial planned.
Transportation Strike Vendor Performance
Delivery time of materials may extended by
2 weeks, due to strike attack planned by
workers union
LD Exposure will goes up by 50% if work
progressing continue on a flat line.
“Without”RiskFactor
Allrisksaretakenasriskevents.
SimulationonProjectA(dummy).
Constructionof 25Storey CeylonServiceApartment
All risks (Risk Factor + Risk Events) are assigned to activities in quantitative tab
49%
49%
49%
50%
50%
50%
53%
54%
54%
55%ELAEIS-RSRC LDD-A6680:012 - Landslide and Subside
ELAEIS-RSRC LDD-A6690:012 - Landslide and Subside
ELAEIS-RSRC LDD-A6680 - Water Reticulation
ELAEIS-RSRC LDD-A6690 - Road Work & Lighting
ELAEIS-RSRC LDD-A7530 - Formworkon Columns
ELAEIS-RSRC LDD-A6930 - Formworkon Columns
ELAEIS-RSRC LDD-A2370 - Formwork Pile Cap & Install Reinforcing
ELAEIS-RSRC LDD-A7230 - Formworkon Columns
ELAEIS-RSRC LDD-A2330 - Formwork on Column
ELAEIS-RSRC LDD-A2090 - Formwork Pile Cap & Install Reinforcing
Elaeis Condominium (Pre-mitigated)
Duration Sensitivity: Entire Plan - All tasks
Water Reticulation and Road Work
& Lighting tasks have highest duration
sensitivity. Noted these two activities
(Infrastructure) are planned at the last
quarter of project duration.
2%
-2%
3%
5%
-7%
9%
16%
16%
23%
25%006 - Availability of Resources
012 - Landslide and Subside
005 - Late drawing & Instructions
009 - Suitability of Materials
001 - Changes in Work
002 - Subsurfaces Geological
013 - Soil availability of Land Fill
001 - Changes in Work
001 - Changes in Work
014 - Insolvency of Subcontractor
Elaeis Condominium (Pre-mitigated)
Duration Sensitivity
Risk affects multiple activities. In
This presentation, Risk Availability
of resources and Landslide &
Subside gives effect most.
P80 stands at 17 April 2015
“With”RiskFactor
Impactplanmodelisacombinationofriskevents
andriskfactors.
SimulationonProjectA(dummy).
Constructionof 25Storey CeylonServiceApartment
DetermineRiskFactor
Take out Risk Events (Risk Factor )from
Quantitative tab. Edit Risk Factor
dialogue box.
Set 3 point estimates in %
ranges and % likelihood.
In this example, we
set zero likelihood
of correlation
Assigning Risk Factor to task. In this example, we apply risk to entire section of the
WBS (Summaries). Indirectly it reflects correlation due to common cause.
Important Notes to understand. Sources from Primavera Risk Analysis Help.
04/04/2015 17:00 27/06/2015 01:00 18/09/2015 09:00
Distribution (start of interval)
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
Hits
0% 18/02/2015 16:00
5% 17/03/2015 17:00
10% 02/04/2015 09:00
15% 13/04/2015 09:00
20% 20/04/2015 09:00
25% 27/04/2015 09:00
30% 01/05/2015 11:00
35% 08/05/2015 09:00
40% 13/05/2015 17:00
45% 18/05/2015 17:00
50% 25/05/2015 09:00
55% 01/06/2015 09:00
60% 05/06/2015 14:00
65% 11/06/2015 14:00
70% 18/06/2015 14:00
75% 24/06/2015 15:00
80% 01/07/2015 16:00
85% 13/07/2015 09:00
90% 29/07/2015 14:00
95% 24/08/2015 09:00
100% 30/11/2015 10:00
CumulativeFrequency
Elaeis Condominium (Pre-mitigated)
EntirePlan: FinishDate
P80 now stands at 1 July 2015
72%
72%
72%
72%
72%
72%
73%
73%
73%
74%ELAEIS-RSRC LDD-A7080 - Reinforcement for Beam/Slab
ELAEIS-RSRC LDD-A7040 - Reinforcement works on Column
ELAEIS-RSRC LDD-A7190 - Formwork for Beam/Slab
ELAEIS-RSRC LDD-A7100 - Reinforcement works on Column
ELAEIS-RSRC LDD-A7010 - Formwork for Beam/Slab
ELAEIS-RSRC LDD-A7110 - Formwork on Column
ELAEIS-RSRC LDD-A7000 - Concrete for Column
ELAEIS-RSRC LDD-A7020 - Reinforcement for Beam/Slab
ELAEIS-RSRC LDD-A7050 - Formwork for Column
ELAEIS-RSRC LDD-A7030 - Concrete for Beam/Slab
Elaeis Condominium (Pre-mitigated)
Duration Sensitivity: Entire Plan - All tasks
2%
-2%
3%
5%
-7%
9%
16%
16%
23%
25%006- Availabilityof Resources
012- LandslideandSubside
005- Latedrawing& Instructions
009- Suitabilityof Materials
001- Changes inWork
002- Subsurfaces Geological
013- Soilavailabilityof LandFill
001- Changes inWork
001- Changes inWork
014- Insolvencyof Subcontractor
4-Storey Elaeis Condominium for Sime Darby Development(Pre-mitigated)
Duration Sensitivity
Not much changes as observed
on the criticality rank
More activities are sensitive to the risk
Impact. Noted at this time,
that they are those activities (Structure)
that planned at earlier stage of construction
Risk: Availability of Resources confirmed “driving” project schedule.
Pull out from Risk Factor menu – Show Tornado
Conclusions.
• P80 for both models have different suggestion dates
“With” Risk Factor = 17 April 2015
“Without” Risk Factor = 1 July 2015
Variance = 75 days
• The output of Risk Factor model had indicated that, Major Construction
Works are critical to manage properly with Risk: Availability Resources
and Risk: Productivity Labor tagged along with, rather than having
Infrastructure works as crucial.
• Incorporating Risk Factor would enabling The User to bring true reality
of the project environment into the model AND give some excellent
reflection of risk exposure.
ThankYou

More Related Content

Viewers also liked

Gerrit Mets, Cyber Insurance Expert, on corporate cyber risks
Gerrit Mets, Cyber Insurance Expert, on corporate cyber risksGerrit Mets, Cyber Insurance Expert, on corporate cyber risks
Gerrit Mets, Cyber Insurance Expert, on corporate cyber risksVanbreda Risk & Benefits
 
Panda Adaptive Defense 360 - Cyber Extortion Guide
Panda Adaptive Defense 360 - Cyber Extortion GuidePanda Adaptive Defense 360 - Cyber Extortion Guide
Panda Adaptive Defense 360 - Cyber Extortion GuidePanda Security
 
Panda Adaptive Defense - The evolution of malware
Panda Adaptive Defense - The evolution of malwarePanda Adaptive Defense - The evolution of malware
Panda Adaptive Defense - The evolution of malwarePanda Security
 
CS3: Cybersecurity Extortion & Fraud
CS3: Cybersecurity Extortion & FraudCS3: Cybersecurity Extortion & Fraud
CS3: Cybersecurity Extortion & FraudPaige Rasid
 
risk management presentation
risk management presentationrisk management presentation
risk management presentationJonathan Gubler
 
MHA Stalking Presentation for Clery Center 25th Anniversary Program
MHA Stalking Presentation for Clery Center 25th Anniversary ProgramMHA Stalking Presentation for Clery Center 25th Anniversary Program
MHA Stalking Presentation for Clery Center 25th Anniversary ProgramMargolis Healy
 
Effects of Domestic Violence in Children
Effects of Domestic Violence in ChildrenEffects of Domestic Violence in Children
Effects of Domestic Violence in Childrentherapistfinder com
 
Domestic violence
Domestic violence Domestic violence
Domestic violence albireno
 
Tips on mugging,extortion and kidnapping
Tips on mugging,extortion and kidnappingTips on mugging,extortion and kidnapping
Tips on mugging,extortion and kidnappingUsman Farooq
 
Improving outcomes for young people in Counties Manukau - Carl Crafar (Minist...
Improving outcomes for young people in Counties Manukau - Carl Crafar (Minist...Improving outcomes for young people in Counties Manukau - Carl Crafar (Minist...
Improving outcomes for young people in Counties Manukau - Carl Crafar (Minist...robine
 
Read 142 presentation 2 homeboy industries
Read 142 presentation 2 homeboy industriesRead 142 presentation 2 homeboy industries
Read 142 presentation 2 homeboy industriesGabeochoa
 
Negative emotions and health: Why do we keep stalking bears.ehps
Negative emotions and health: Why do we keep stalking bears.ehpsNegative emotions and health: Why do we keep stalking bears.ehps
Negative emotions and health: Why do we keep stalking bears.ehpsJames Coyne
 
Society for Risk Analysis On Transnational Risk & Terrorism
Society for Risk Analysis  On Transnational Risk & TerrorismSociety for Risk Analysis  On Transnational Risk & Terrorism
Society for Risk Analysis On Transnational Risk & TerrorismJohn Marke
 
Girls, Gangs, & Sex
Girls, Gangs, & SexGirls, Gangs, & Sex
Girls, Gangs, & Sexrisat528
 
Negative emotion and health why do we keep stalking bears, when we only find ...
Negative emotion and health why do we keep stalking bears, when we only find ...Negative emotion and health why do we keep stalking bears, when we only find ...
Negative emotion and health why do we keep stalking bears, when we only find ...James Coyne
 
e-Extortion Trends and Defense
e-Extortion Trends and Defensee-Extortion Trends and Defense
e-Extortion Trends and DefenseErik Iker
 
Hotels restaurants security
Hotels restaurants securityHotels restaurants security
Hotels restaurants securityzaffar abbasi
 

Viewers also liked (20)

Gerrit Mets, Cyber Insurance Expert, on corporate cyber risks
Gerrit Mets, Cyber Insurance Expert, on corporate cyber risksGerrit Mets, Cyber Insurance Expert, on corporate cyber risks
Gerrit Mets, Cyber Insurance Expert, on corporate cyber risks
 
Plep inteligencia humana
Plep inteligencia humanaPlep inteligencia humana
Plep inteligencia humana
 
Panda Adaptive Defense 360 - Cyber Extortion Guide
Panda Adaptive Defense 360 - Cyber Extortion GuidePanda Adaptive Defense 360 - Cyber Extortion Guide
Panda Adaptive Defense 360 - Cyber Extortion Guide
 
Panda Adaptive Defense - The evolution of malware
Panda Adaptive Defense - The evolution of malwarePanda Adaptive Defense - The evolution of malware
Panda Adaptive Defense - The evolution of malware
 
CS3: Cybersecurity Extortion & Fraud
CS3: Cybersecurity Extortion & FraudCS3: Cybersecurity Extortion & Fraud
CS3: Cybersecurity Extortion & Fraud
 
risk management presentation
risk management presentationrisk management presentation
risk management presentation
 
MHA Stalking Presentation for Clery Center 25th Anniversary Program
MHA Stalking Presentation for Clery Center 25th Anniversary ProgramMHA Stalking Presentation for Clery Center 25th Anniversary Program
MHA Stalking Presentation for Clery Center 25th Anniversary Program
 
Effects of Domestic Violence in Children
Effects of Domestic Violence in ChildrenEffects of Domestic Violence in Children
Effects of Domestic Violence in Children
 
Domestic violence
Domestic violence Domestic violence
Domestic violence
 
Tips on mugging,extortion and kidnapping
Tips on mugging,extortion and kidnappingTips on mugging,extortion and kidnapping
Tips on mugging,extortion and kidnapping
 
IDRC14-ppp-Stanciugelu-PEP-session-2708
IDRC14-ppp-Stanciugelu-PEP-session-2708IDRC14-ppp-Stanciugelu-PEP-session-2708
IDRC14-ppp-Stanciugelu-PEP-session-2708
 
Improving outcomes for young people in Counties Manukau - Carl Crafar (Minist...
Improving outcomes for young people in Counties Manukau - Carl Crafar (Minist...Improving outcomes for young people in Counties Manukau - Carl Crafar (Minist...
Improving outcomes for young people in Counties Manukau - Carl Crafar (Minist...
 
Read 142 presentation 2 homeboy industries
Read 142 presentation 2 homeboy industriesRead 142 presentation 2 homeboy industries
Read 142 presentation 2 homeboy industries
 
Negative emotions and health: Why do we keep stalking bears.ehps
Negative emotions and health: Why do we keep stalking bears.ehpsNegative emotions and health: Why do we keep stalking bears.ehps
Negative emotions and health: Why do we keep stalking bears.ehps
 
Society for Risk Analysis On Transnational Risk & Terrorism
Society for Risk Analysis  On Transnational Risk & TerrorismSociety for Risk Analysis  On Transnational Risk & Terrorism
Society for Risk Analysis On Transnational Risk & Terrorism
 
The Marsh Report-Terrorism Risk Insurance 2010
The Marsh Report-Terrorism Risk Insurance 2010 The Marsh Report-Terrorism Risk Insurance 2010
The Marsh Report-Terrorism Risk Insurance 2010
 
Girls, Gangs, & Sex
Girls, Gangs, & SexGirls, Gangs, & Sex
Girls, Gangs, & Sex
 
Negative emotion and health why do we keep stalking bears, when we only find ...
Negative emotion and health why do we keep stalking bears, when we only find ...Negative emotion and health why do we keep stalking bears, when we only find ...
Negative emotion and health why do we keep stalking bears, when we only find ...
 
e-Extortion Trends and Defense
e-Extortion Trends and Defensee-Extortion Trends and Defense
e-Extortion Trends and Defense
 
Hotels restaurants security
Hotels restaurants securityHotels restaurants security
Hotels restaurants security
 

Similar to Risk factor

APRIL -23 TO Feb 24 FINAL PPT (3).pptx
APRIL  -23 TO  Feb 24 FINAL PPT (3).pptxAPRIL  -23 TO  Feb 24 FINAL PPT (3).pptx
APRIL -23 TO Feb 24 FINAL PPT (3).pptxnkarthik21
 
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
APRIL  -23 TO  Feb 24 FINAL PPT (3).pptxAPRIL  -23 TO  Feb 24 FINAL PPT (3).pptx
APRIL -23 TO Feb 24 FINAL PPT (3).pptxnkarthik21
 
Management Of Business Operation Components PowerPoint Presentation Slides
Management Of Business Operation Components PowerPoint Presentation SlidesManagement Of Business Operation Components PowerPoint Presentation Slides
Management Of Business Operation Components PowerPoint Presentation SlidesSlideTeam
 
Concept Of Risk Management PowerPoint presentation Slides
Concept Of Risk Management PowerPoint presentation SlidesConcept Of Risk Management PowerPoint presentation Slides
Concept Of Risk Management PowerPoint presentation SlidesSlideTeam
 
Quality Assurance Tools PowerPoint Presentation Slides
Quality Assurance Tools PowerPoint Presentation Slides Quality Assurance Tools PowerPoint Presentation Slides
Quality Assurance Tools PowerPoint Presentation Slides SlideTeam
 
Turag Presentation
Turag PresentationTurag Presentation
Turag PresentationSourav Das
 
Sce guide trainer_pakete_en_without_prices
Sce guide trainer_pakete_en_without_pricesSce guide trainer_pakete_en_without_prices
Sce guide trainer_pakete_en_without_pricesCharles Santos
 
Operational Infrastructure Management PowerPoint Presentation Slides
Operational Infrastructure Management PowerPoint Presentation SlidesOperational Infrastructure Management PowerPoint Presentation Slides
Operational Infrastructure Management PowerPoint Presentation SlidesSlideTeam
 
Capacity Planning PowerPoint Presentation Slides
Capacity Planning PowerPoint Presentation SlidesCapacity Planning PowerPoint Presentation Slides
Capacity Planning PowerPoint Presentation SlidesSlideTeam
 
Enterprise Risk Management Overview PowerPoint Presentation Slides
Enterprise Risk Management Overview PowerPoint Presentation SlidesEnterprise Risk Management Overview PowerPoint Presentation Slides
Enterprise Risk Management Overview PowerPoint Presentation SlidesSlideTeam
 
When is a SIL Rating of a Valve Required?
When is a SIL Rating of a Valve Required?When is a SIL Rating of a Valve Required?
When is a SIL Rating of a Valve Required?ISA Interchange
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoignitetribes
 
Detailed Infrastructure Analysis PowerPoint Presentation Slides
Detailed Infrastructure Analysis PowerPoint Presentation SlidesDetailed Infrastructure Analysis PowerPoint Presentation Slides
Detailed Infrastructure Analysis PowerPoint Presentation SlidesSlideTeam
 
Security Operational Scorecard EX2
Security Operational Scorecard EX2Security Operational Scorecard EX2
Security Operational Scorecard EX2Alice E. Nordwall
 
Project Risk Management Overview PowerPoint Presentation Slides
Project Risk Management Overview PowerPoint Presentation SlidesProject Risk Management Overview PowerPoint Presentation Slides
Project Risk Management Overview PowerPoint Presentation SlidesSlideTeam
 

Similar to Risk factor (20)

SIP PPT
SIP PPTSIP PPT
SIP PPT
 
JTP - EV Presentation
JTP - EV PresentationJTP - EV Presentation
JTP - EV Presentation
 
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
APRIL  -23 TO  Feb 24 FINAL PPT (3).pptxAPRIL  -23 TO  Feb 24 FINAL PPT (3).pptx
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
 
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
APRIL  -23 TO  Feb 24 FINAL PPT (3).pptxAPRIL  -23 TO  Feb 24 FINAL PPT (3).pptx
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
 
Management Of Business Operation Components PowerPoint Presentation Slides
Management Of Business Operation Components PowerPoint Presentation SlidesManagement Of Business Operation Components PowerPoint Presentation Slides
Management Of Business Operation Components PowerPoint Presentation Slides
 
Network Diagram
Network DiagramNetwork Diagram
Network Diagram
 
Concept Of Risk Management PowerPoint presentation Slides
Concept Of Risk Management PowerPoint presentation SlidesConcept Of Risk Management PowerPoint presentation Slides
Concept Of Risk Management PowerPoint presentation Slides
 
Quality Assurance Tools PowerPoint Presentation Slides
Quality Assurance Tools PowerPoint Presentation Slides Quality Assurance Tools PowerPoint Presentation Slides
Quality Assurance Tools PowerPoint Presentation Slides
 
Turag Presentation
Turag PresentationTurag Presentation
Turag Presentation
 
Sce guide trainer_pakete_en_without_prices
Sce guide trainer_pakete_en_without_pricesSce guide trainer_pakete_en_without_prices
Sce guide trainer_pakete_en_without_prices
 
Operational Infrastructure Management PowerPoint Presentation Slides
Operational Infrastructure Management PowerPoint Presentation SlidesOperational Infrastructure Management PowerPoint Presentation Slides
Operational Infrastructure Management PowerPoint Presentation Slides
 
Capacity Planning PowerPoint Presentation Slides
Capacity Planning PowerPoint Presentation SlidesCapacity Planning PowerPoint Presentation Slides
Capacity Planning PowerPoint Presentation Slides
 
Enterprise Risk Management Overview PowerPoint Presentation Slides
Enterprise Risk Management Overview PowerPoint Presentation SlidesEnterprise Risk Management Overview PowerPoint Presentation Slides
Enterprise Risk Management Overview PowerPoint Presentation Slides
 
When is a SIL Rating of a Valve Required?
When is a SIL Rating of a Valve Required?When is a SIL Rating of a Valve Required?
When is a SIL Rating of a Valve Required?
 
Project Controls Overview - R2
Project Controls Overview - R2Project Controls Overview - R2
Project Controls Overview - R2
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promo
 
Detailed Infrastructure Analysis PowerPoint Presentation Slides
Detailed Infrastructure Analysis PowerPoint Presentation SlidesDetailed Infrastructure Analysis PowerPoint Presentation Slides
Detailed Infrastructure Analysis PowerPoint Presentation Slides
 
Session B2 - Project Cost Control
Session B2 - Project Cost ControlSession B2 - Project Cost Control
Session B2 - Project Cost Control
 
Security Operational Scorecard EX2
Security Operational Scorecard EX2Security Operational Scorecard EX2
Security Operational Scorecard EX2
 
Project Risk Management Overview PowerPoint Presentation Slides
Project Risk Management Overview PowerPoint Presentation SlidesProject Risk Management Overview PowerPoint Presentation Slides
Project Risk Management Overview PowerPoint Presentation Slides
 

Recently uploaded

Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 

Recently uploaded (20)

Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 

Risk factor

  • 1. Risk Factor Identified, Quantified, and Build-In impacts in Schedule Risk Analysis
  • 2. Commonpractice:ScheduleRiskAnalysis process • All identified risks that have impact on schedule are basically assigned into activities on schedule. • Some risks may assigned to multiple activities, hence an activity can be influenced by multiple risks. However, many users are not aware that prior assigning process, risks need to be categorized either Risk Event or Risk Factor. • Ignoring Risk Factor is “risk” to schedule risk analysis process, that will lead to distorted results. • This paper intended to briefly shown how much the variance could derived from the simulation output “with” and “without” Risk Factor AND also hoping for feedback on how to improve the process. • Primavera Risk Analysis is a tool used for this presentation and it is assumed that the reader(s) has understanding and experiences of using it.
  • 3. RiskFactor VS RiskEvent • Risk Event Is an incident/occasion that may or may not happen, that affects through impacts on particular activities in the project. • Risk Factor Is an unknown element that affects the project. It is expressed as % and resulting from it, reduces or increases the activities it affects.
  • 4. Examples Risk Events Risk Factors Unavailability of Resources Weather Nobody is willing to do casting, hence casting works shall delayed. All Offshore installation activities will prolonged 50% longer than planned duration. Land Subside Productivity Labor Zone A1/D1 has weak ground, piling work may get effected in case soil strengthening not properly done. Fabrication time will takes 20% longer than initial planned. Transportation Strike Vendor Performance Delivery time of materials may extended by 2 weeks, due to strike attack planned by workers union LD Exposure will goes up by 50% if work progressing continue on a flat line.
  • 6. All risks (Risk Factor + Risk Events) are assigned to activities in quantitative tab
  • 7. 49% 49% 49% 50% 50% 50% 53% 54% 54% 55%ELAEIS-RSRC LDD-A6680:012 - Landslide and Subside ELAEIS-RSRC LDD-A6690:012 - Landslide and Subside ELAEIS-RSRC LDD-A6680 - Water Reticulation ELAEIS-RSRC LDD-A6690 - Road Work & Lighting ELAEIS-RSRC LDD-A7530 - Formworkon Columns ELAEIS-RSRC LDD-A6930 - Formworkon Columns ELAEIS-RSRC LDD-A2370 - Formwork Pile Cap & Install Reinforcing ELAEIS-RSRC LDD-A7230 - Formworkon Columns ELAEIS-RSRC LDD-A2330 - Formwork on Column ELAEIS-RSRC LDD-A2090 - Formwork Pile Cap & Install Reinforcing Elaeis Condominium (Pre-mitigated) Duration Sensitivity: Entire Plan - All tasks Water Reticulation and Road Work & Lighting tasks have highest duration sensitivity. Noted these two activities (Infrastructure) are planned at the last quarter of project duration. 2% -2% 3% 5% -7% 9% 16% 16% 23% 25%006 - Availability of Resources 012 - Landslide and Subside 005 - Late drawing & Instructions 009 - Suitability of Materials 001 - Changes in Work 002 - Subsurfaces Geological 013 - Soil availability of Land Fill 001 - Changes in Work 001 - Changes in Work 014 - Insolvency of Subcontractor Elaeis Condominium (Pre-mitigated) Duration Sensitivity Risk affects multiple activities. In This presentation, Risk Availability of resources and Landslide & Subside gives effect most.
  • 8. P80 stands at 17 April 2015
  • 10. DetermineRiskFactor Take out Risk Events (Risk Factor )from Quantitative tab. Edit Risk Factor dialogue box. Set 3 point estimates in % ranges and % likelihood. In this example, we set zero likelihood of correlation
  • 11. Assigning Risk Factor to task. In this example, we apply risk to entire section of the WBS (Summaries). Indirectly it reflects correlation due to common cause.
  • 12. Important Notes to understand. Sources from Primavera Risk Analysis Help.
  • 13. 04/04/2015 17:00 27/06/2015 01:00 18/09/2015 09:00 Distribution (start of interval) 0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 Hits 0% 18/02/2015 16:00 5% 17/03/2015 17:00 10% 02/04/2015 09:00 15% 13/04/2015 09:00 20% 20/04/2015 09:00 25% 27/04/2015 09:00 30% 01/05/2015 11:00 35% 08/05/2015 09:00 40% 13/05/2015 17:00 45% 18/05/2015 17:00 50% 25/05/2015 09:00 55% 01/06/2015 09:00 60% 05/06/2015 14:00 65% 11/06/2015 14:00 70% 18/06/2015 14:00 75% 24/06/2015 15:00 80% 01/07/2015 16:00 85% 13/07/2015 09:00 90% 29/07/2015 14:00 95% 24/08/2015 09:00 100% 30/11/2015 10:00 CumulativeFrequency Elaeis Condominium (Pre-mitigated) EntirePlan: FinishDate P80 now stands at 1 July 2015
  • 14. 72% 72% 72% 72% 72% 72% 73% 73% 73% 74%ELAEIS-RSRC LDD-A7080 - Reinforcement for Beam/Slab ELAEIS-RSRC LDD-A7040 - Reinforcement works on Column ELAEIS-RSRC LDD-A7190 - Formwork for Beam/Slab ELAEIS-RSRC LDD-A7100 - Reinforcement works on Column ELAEIS-RSRC LDD-A7010 - Formwork for Beam/Slab ELAEIS-RSRC LDD-A7110 - Formwork on Column ELAEIS-RSRC LDD-A7000 - Concrete for Column ELAEIS-RSRC LDD-A7020 - Reinforcement for Beam/Slab ELAEIS-RSRC LDD-A7050 - Formwork for Column ELAEIS-RSRC LDD-A7030 - Concrete for Beam/Slab Elaeis Condominium (Pre-mitigated) Duration Sensitivity: Entire Plan - All tasks 2% -2% 3% 5% -7% 9% 16% 16% 23% 25%006- Availabilityof Resources 012- LandslideandSubside 005- Latedrawing& Instructions 009- Suitabilityof Materials 001- Changes inWork 002- Subsurfaces Geological 013- Soilavailabilityof LandFill 001- Changes inWork 001- Changes inWork 014- Insolvencyof Subcontractor 4-Storey Elaeis Condominium for Sime Darby Development(Pre-mitigated) Duration Sensitivity Not much changes as observed on the criticality rank More activities are sensitive to the risk Impact. Noted at this time, that they are those activities (Structure) that planned at earlier stage of construction
  • 15. Risk: Availability of Resources confirmed “driving” project schedule. Pull out from Risk Factor menu – Show Tornado
  • 16. Conclusions. • P80 for both models have different suggestion dates “With” Risk Factor = 17 April 2015 “Without” Risk Factor = 1 July 2015 Variance = 75 days • The output of Risk Factor model had indicated that, Major Construction Works are critical to manage properly with Risk: Availability Resources and Risk: Productivity Labor tagged along with, rather than having Infrastructure works as crucial. • Incorporating Risk Factor would enabling The User to bring true reality of the project environment into the model AND give some excellent reflection of risk exposure.