SlideShare a Scribd company logo
1 of 51
DEBRE MARKOS UNIVERSITY
COLLEGE OF TECHNOLOGY
CIVIL ENGINEERING ACADAMIC PROGRAM
RAILWAY ENGINEERING
CHAPTER 3 RAILWAY TRACKSTRUCTURES
Biniyam A. January, 2022 1
Contents
1. Component and function of
track structure
2. Track loads
3. Track Analysis: Rail support;
sleepers/ties; ballast and
subballast
4. Ballasted and Slab track
5. Rail fastening system
6. Track modeling
3.1 Component and function of track structure
In contrast to road transport, where vehicles merely run on a prepared surface, rail
vehicles are also directionally guided by the tracks they run on. Track usually
consists of steel rails installed on sleepers/ties and ballast, on which the rolling stock,
usually fitted with metal wheels, moves.
The railway track has to fulfill two main functions:
 to guide the train with safety
 to carry the load of the train and to distribute the load to the
subgrade over an area that is as large as possible
Components of track structure
TRACK LOADS
The requirements for the bearing strength and quality of the track
depend to a large extent on the load parameters:
 axle load: static vertical load per axle;
 tonnage borne: sum of the axle loads;
 running speed
1. The static axle load level, to which the dynamic increment is
added, in principle determines the required strength of the track.
2. The accumulated tonnage is a measure that determines the
deterioration of the track quality and as such provides an
indication of when maintenance and renewal are necessary.
3. The dynamic load component which depends on speed and
horizontal and vertical track geometry also plays an essentialpart
here.
Forces on the Track
Those loads can be categorized into three
main groups:
• Vertical loads
• Lateral loads (transverse), and
• Longitudinal loads (parallel)
Depending on their nature, those loads can be divided into three groups:
 Static loads (normally caused by the vehicle body mass)
 Quasi-static loads (or dynamic ride loads),
 Dynamic (dynamic wheel/rail) loads, which are associated with
significant irregularities that may occur during the life of the track structure
and vehicle
• Irregularities of the track geometry
• Discontinuities on the running surface (switches, joints)
• Wear of the running surface of the rails
• Wear of the wheels (out-of-round wheels)
• Vehicle suspension and vehicle asymmetries
Dynamic wheel/rail forces are much higher in magnitude than quasi-static
(dynamic ride) forces.
Quasi-static (Dynamic Ride) Forces
Definition: the sum of the static load and the effect of the static load at
speed and they are classified in the frequency range between 0.5 and 30 Hz.
The load includes the effects of
• the geometrical roughness of the
track on vehicle response and
• unbalanced superelevation (the
effect of the train load not being
distributed evenly over both rails).
The quasi-static force has been
found to be typically between
1.4 and 1.6 times the static
wheel load before unbalanced
superelevation effects are
included4.
 which are associated with
vehicle movements: Vehicles
running on the track apply
certain forces on the track
structure due to the behavior
of the vehicle body, bogie
and other masses in reaction
to geometrical irregularities
in the track.
Dynamic Forces
The Dynamic Wheel /
Rail Forces
Dynamic forces come
in two categories:
– P1 Forces
– P2 Forces
The P1 Force
• P1 forces are classified in frequency range between 100 Hz and 2000
Hz. These forces are also called impact forces. They correspond to
surface irregularities or defects in rails and wheels and produce
strong impact to rail and wheel.
• P1 is a very high frequency force occurring ¼ - ½ ms after crossing
the angular discontinuity that occurs at the bottom of the dip and has
a very short duration
The P1 Force
Effect of P1 forces
 Rail hammering just after the joint gap and produces high
stresses in the rail web.
 It contributes to bolt hole failures in bolted joints by increasing
the stress range.
 contribute to the cracking of concrete sleepers.
 Its effects are largely filtered out by the rail and sleepers,
 do not directly affect ballast or subgrade settlement.
 they have a great influence on wheel/rail contact behavior.
The P2 Force
 P2 forces are classified in lower frequency range (30 Hz and 100Hz)
 They correspond to the movement of unsprung masses of the
vehicles.
 have a lower-amplitude and longer-duration than the P1 forces.
The peak force occurs in the area of the first running-off sleeper after
the joint. The wheel set mass and the rail/sleeper mass move down
together and compress the ballast beneath the sleeper.
 P2 forces therefore increase contact stresses, contribute to the total
stress range experienced by the rail web and at joint bolt holes
 Increase the loads on sleepers and ballast in the immediate
neighborhood of the joint.
 P2 forces are of great interest to the track designengineer.
 P2 forces contribute primarily to the degradation of trackgeometry.
Force Limits
Railway organizations around the world have set limits on the various
forces at the wheel / rail contact area.
Vertical Force Limits
In the vertical direction high forces can cause damage to the rails and
supporting structures and can cause rolling contact fatigue when
combined with high tangential forces such as occur during traction,
braking or curving.
Eg. UIC limits
– a maximum static load of 112.5 kN per wheel and
– a maximum dynamic vertical force per wheel of between 160 kN and 200
kN, depending on maximum speed (provided this values does not exceed
the static wheel load plus 90 kN).
– In small radius curves (less than 600 m) a limit of 145 kN for the quasi-
static vertical force.
Lateral Force Limits
• In the lateral direction high forces can cause distortion of the track
on ballast-bed.
• This is normally protected against by using the simple but widely
established Prud Homme limit for the track shifting force at one
wheel set, which can be calculated from the static load (Po force):
Where, Y and P0 are in kN.
Lateral forces of very short duration are less likely to shift the track
and therefore only forces that act for more than 2m of track length
are usually counted. In small radius curves (less than 600 m) UIC
sets a limit of 60 kN for the quasi-static lateral force.
Derailment
• Possibility of wheel climb derailment is indicated by the ratio of
the lateral force Y to vertical force V
• Nadal theory is used to establish limits for the Υ/V derailment ratio
with 0,8 as the limiting value.
Wheel Unloading
Very low vertical forces at the contact patch can indicate that a
vehicle is tending to derailment by rolling over or by failing to
follow twists in the track.
E.g. In the UK a lower limit of 60% of the static wheel load (i.e.,
unloading by over 40%) is set.
Track Components
The Principle:-
– Track Components do not function independently!
– Each component layer must protect the one below.
Main design components
1. Rail
2. Sleeper
3. Rail pad/plate
4. Ballast
Deflection Profile
Source: Selig and Waters, Track Geotechnology and Substructure Management, 1994
Static vs. Dynamic Loads
 Dynamic loads higher
– Acceleration from speed
– Downward rotation of wheel
– Smaller wheels, faster rotation, more acceleration
 Speed/wheel influence
– Pv= P + θP (AREMA)
Where, Pv= Vertical Dynamic Load (lbs)
D = Wheel diameter (in)
V = Speed (MPH)
P = Static Load (lbs)
–Larger wheels impose less influence
 Additional dynamic loads from impacts such as caused by wheel
flat spots, rail discontinuities (e.g. frog flange ways), track
transitions (e.g. bridge approaches), track condition, etc.
Typical Track Stiffness Values
Winkler Model of Rail Deflection
The deterioration process due
to variation in track stiffness
- Rail, fasteners, tie and ballast
Upper Structures
 The upper part consists of two parallel steel rails, anchored
perpendicular to members called ties (sleepers) of timber, concrete,
steel, or plastic to maintain a consistent distance apart, or gauge.
1. Rail
Rails are the longitudinal steel members that directly guide the train
wheels evenly and continuously.
Rail guides the conical, flanged wheels, keeping the vehicles on the
track without active steering and therefore allowing trains to be much
longer than road vehicles.
1. Rail
a) Characteristics b) Functions:
 Supports the loads of train and guides
their wheel movements
 The excellence of the track determines
the permissible wheel loads, speeds,
safety
 provide a surface with smaller
resistance
 bear the force of the wheels and spread
it to sleeper
 used as track circuit in electrified
railways and automatic block segments
• Rigidity
• Tenacity
• Hardness
• Roughness of top surface
Composition
Unlike other uses of iron and
steel, railway rails are subject to
very high stresses and have to
be made of very high quality
steel. Minor flaws in the steel
that pose no problems in
reinforcing rods for buildings,
can, however, lead to broken
rails and dangerous derailments
when used on railway tracks
C) Profile
The rail profile is the cross sectional shape of a
railway rail, perpendicular to the length of the
rail.
• A rail is hot rolled steel of a specific cross
sectional profile (an asymmetrical I-beam)
designed for use as the fundamental component
of railway track.
• Composed of rail head, rail web and rail base
• The rail head and base must be large and thick
rail head
rail web
rail base
1. Rail
• weight of a rail per length (Kg/m), such as
75, 60, 50, 43 kg/m.
• Standard rail length: 12.5m and 25m.
d) Types and length
The following rail forms are in use at present:
Vignoles rail (standard railway rail with head, web and foot),
Double-head rails with head, web and foot (obsolete)
Grooved rails for tram ways,
Switch rails and
Crane rails etc
1. Rail
Where,
δ- size of rail gap(mm)
L- length of track(m)
δq- structural joint gap, track of 38kg/m,
43kg/m, 50kg/m, 60kg/m, 75kg/m are 18mm
t0 - temperature of rail gap(oC)
e) Rail gap
To adapt to the needs of expanding with heat and contracting with cold,
the rail gap can not too big or too small.
2 0
2
q
  0 .0 11 8 L t  t 
1

1
2
t2  tmax  tmin 
1. Rail
The 25 m rail are welded into 100-200m long
rail in factory, and then be welded again
into1000-2000m long rail in the laid place
Advantages:
smooth driving
low maintenance cost
long life
f) Continuous welded track (CWR)
 good weld ability,
 high degree of purity
 good surface quality
 evenness and observance of profile and
 low residual stress after manufacturing
g) Rail requirement
To be able to withstand manifold and high forces, the rails must meet
the following requirements:
 high resistance to wear,
 high resistance to compression,
 high resistance to fatigue
 high yield strength, tensile strength and hardness
 high resistance to brittle fracture
1. Rail
2. Sleeper
(a) Function
 bear the force of track
Act as elastic medium to absorb
blows & vibrations
 Longitudinal & lateral stability
spread the force to ballast bed and
roadbed
 keep the direction, position and
gauge of track
Supporting wheels and/or jacks
direct (in a derailment situation).
Acting as transverse beams when
sitting on temporary ‘way beams’.
Supporting signal engineering
and other safety related equipment
such as trip cocks and point
motors.
Supporting conductor rails,
electrical bonds and feeder cables.
 Reducing noise and vibration on
non-ballasted bridge decks
(b) Characteristic
It is solid, flexible, reasonably cost,
convenient for manufacturing
and maintenance.
2. Sleeper
2. Sleeper
• According to production material: reinforced concreted sleeper,
wooden sleeper, steel sleeper
• According to their usage: regular sleeper, switch sleeper and
bridge sleeper.
C) Requirements
Moderate weight- easy to handle
Fixing and removing of fastening should be easy
Sufficient bearing area and Able to resist shocks and
vibrations
Easy maintenance and gauge adjustment
Track circuiting must be possible
Minimum maintenance and initial cost
D)types
1. Wooden Sleeper
• Timber ties are usually of a variety of hardwoods, oak being a
popular material.
• They have the advantage of accepting treatment more readily, they
are more susceptible to wear. They are often heavily creosoted.
Creosote treating can reduce insect infestation and rot. However,
creosote is also carcinogenic and environmentally damaging.
• Less often, ties are treated with other preservatives, although some
timbers are durable enough that they can be used untreated.
2. Sleeper
2. Concrete Sleeper
• Concrete ties have become more common mainly due to greater
economy and better support of the rails under high speed and
heavy traffic than wooden ties
2. Sleeper
2. Sleeper
• In past times steel sleepers have suffered from poor design and
increased traffic loads over their normal long service life.
• The steel sleepers’cost benefits together with the ability to hold rail
gauge, lower long-term maintenance costs, increase the life of other
track components, reduce derailments and meet ever growing and
stricter environment standards provide railroad companies with
savings and capital to redirect to other areas of maintenance-of-way
and business projects.
3. Steel sleeper
Advantages:
• Long life, Better lateral rigidity
• Free from decay and fire hazards
• Good scrap value
• Lesser damage during handling
• Less maintenance problems
• Easy to maintain gauge
Disadvantages:
• Liable to corrosion
• Unsuitable to track
circuiting
• Becomes center bound due
to sloping ends
• Rail specific
 Concrete monoblock sleepers have also been produced in a wider
form (e.g. 57 cm (22 in))
 there is no ballast between the sleepers;
 wide sleeper increase lateral resistance and
 reduces ballast pressure.
Wide sleeper
2. Sleeper
2. Sleeper
Y-shaped sleepers
• An unusual form (developed in 1983)
• reduced ballast volume due to the load spreading characteristics
Compared to conventional sleepers.
• High Noise levels
• very good resistance to track movement.
• Three point contact curves means that an exact geometric fit cannot be
observed with a fixed attachment point.
Bi-block/Twin-block sleepers
• Bi-block sleepers consist of two concrete rail supports joined by steel
• Advantages include
 Increase lateral resistance
 lower weight than monoblock concrete sleepers
 eliminate damage from torsional forces on the sleeper centre due
the more flexible steel connections
 Bi-block sleepers are also used in ballastless track systems
2. Sleeper
Y-shaped sleepers
…Bi-block
Mono-block vs. twin block sleepers
The advantages of the twin-block sleeper
•Well-defined bearing surfaces in the
ballast bed;
• high lateral resistance in the ballast bed
The advantages of the
mono-block sleeper
• low price
• less susceptibility to
cracking
• can be pre-stressed
2. Sleeper
d)Arrangement
Configuration number at each kilometer is decided by volume, speed
and line level. The rule:
• wooden sleepers must no more than 1920 per 1km and no less
than 1440
• Reinforced concreted sleepers must no more than 1840 per 1km
and no less than 1440
1. Ballast- it is a layer of broken stones, gravel, moorum or any
other gritty material placed and packed below and around sleepers.
– for distributing the load from the sleepers to the formation and
– for providing drainage
– as well as giving longitudinal and lateral stability to the track.
3. Ballast and sub ballast
A layer of loose, coarse
grained material which, as a
result of internal friction
between the grains, can
absorb considerable
compressive stresses, but
not tensile stresses.
a) Functions
The six most important functions of ballast:
• To resist vertical & longitudinal forces
and hold the track in position
• To provide energy absorption for the track
• To provide voids for storage and
movement of fouling material in the
ballast
• To facilitate the adjustment of track
geometry
• To provide immediate drainage of water
falling on to the track
• To reduce pressures on underlying
materials by distributing loads
3. Ballast and sub ballast
b) Requirements
• Tough and resist wear
• Hard enough
• Cubical with sharp
edge
• Non porous, non-water
absorbent
• Resist attrition
• Durable
• Good drainage
• Cheap and economical
Ballast Analysis and Design(depth determination)
Source:-AREMA
3. Ballast and sub ballast
Ballast depth determination
(ballast and subballast combined) = f(applied stress, tie reaction,
and allowable subgrade stress)
–Talbot Equation, h = (16.8pa/pc)4/5
Where, h = Support ballast depth
pa= Stress at bottom of tie (top of ballast)
pc= Allowable subgrade stress
Note: Stress distribution independent of material
–Japanese National Railways Equation
pc= 50pa/(10+h1.25)
–Boussinesq Equation
pc= 6P/2h2 where P = wheel load (lbs)
–Love’s Formula
pc= pa{1-[1/(1+r2/h2)]3/2}
Where, r = Radius of a loaded circle whose area equals the effective
tie bearing area under one rail
3. Ballast and sub ballast
Minimum depth of ballast
Stress distribution is assumed as 45o
-Consider stress overlap area
-Provide adequate depth of ballast
-Thickness of ballast is a function of sleeper spacing, sleeper
size etc
3. Ballast and sub ballast
2. Sub ballast
-Is a layer of material between the top ballast and sub grade
with a gradation finer than the top ballast and coarser than the
sub grade
a) Function
• Used to reduce total ballast cost
• Provide a filter layer between the top ballast and a fine
grained sub grade
b) Application
A sub ballast layer is recommended for most new construction. In
addition to providing filter to keep sub grade particle from
working up in to and fouling the ballast, it provides a good mat to
distribute loads from the ballast and prevents ballast particles
from being pushed in to the sub grade.
3. Ballast and sub ballast
A sub ballast layer is required whenever:
i. The sub grade contains 85% or more (by weight) of silt and clay
sized particles or,
ii.The sub grade material has a plasticity index grater than 20
c) Material
hard, angular, non- cementing material,
d) Gradation
To function as a filter layer, the sub ballast size range from the smallest
ballast particles to the largest sub grade particles
e) Depth
i. During structural analysis, the sub ballast layer is considered as
part of the total ballast depth
ii. A sub ballast layer may comprise up to 40% of the total ballast
thickness on main running tracks and up to 50% on other tracks
3. Ballast and sub ballast
4. Rail fastening system/ Union piece
• A Rail fastening system is a means of fixing rails to railroad sleepers.
• The terms rail anchors, tie plates, chairs and track fasteners are used
to refer to parts or all of a rail fastening system. Various types of
fastening have been used over the years.
Union pieces are divided into
=> Rail joint fastenings
=> Middle joint fastenings.
a) Function:
The purpose of the rail fastenings:
 To maintain the track gauge
 Offer sufficient resistance in a vertical direction
 To transmit forces acting on and in the rails to the sleepers (cross,
longitudinal, concrete plates etc.)
 Electrically insulate the sleeper against the remaining track grid, to
minimize the loss of signals of the direct-current circuits
b) Types
(1) rail joint fastenings
Rail joint fastenings are used
at the end of the two tracks.
4. Rail fastening system/ Union piece
(2) Middle joint fastenings
• used to connect rail with the sleeper
• Based on sleeper type, (reinforced
concreted joint fastenings and
wooden joint fastenings)
5. Ballasted and slab track
a)Ballasted track
Advantages:
• Lower cost,
• small noise emission scope,
• short construction period,
• easy repair when failure
occurs,
• high efficiency of
maintenance work due to its
mechanization,
• easy to adjust its
geometrical unevenness
Disadvantages:
The tendency to “float”
(longitudinal and lateral direction)
Limited non-compensated lateral
acceleration in curves caused by the
limited lateral resistance provided by
ballast
Pulverization of the ballast grains in
the ballast bed resulting in particles
damaging the rail and wheels
Problems with ballast churning with
high speed
Reduced permeability due to
contamination, the wear of the
ballast, and intrusion of fine particles
from the sub grade
b) Slab track
In slab track, ballast is replaced by another stable load distributing
material such as concrete or asphalt.
The necessary elasticity has to be provided by inserting elastic
elements below the rail or the sleeper, as the concrete or asphalt
layer is very stiff.
In comparison to ballasted track, the advantages of slab track arein
general reduction of maintenance and a higher stability of the
track
 Less or free maintenance, costs 20%~30%
 better line evenness
 Increased service life, and possibility of almost full
replacement at the end of the service life
 Increased lateral resistance and stability
 Reduced structure height and weight
 The excess of super elevation and cant deficiency of
the track with mixed used of freight- and passenger
trains does not cause altering of the track position
 Track accessibility to road vehicles
 Preventing the release of dust from the ballast bed
into the environment
Slab track
Advantages:
 Higher construction costs and Higher airborne noise reflection
 Adaptability to larger sinkage in the embankment is relatively small
 Repair works take much more time and effort (in case of derailment)
 Transitions between ballasted track and slab track require attention
 Large attentions in track position and super elevation can only be
made possible by substantial amounts of work
 The application of slab track may require extensive measures
concerning the preparation of the foundation.
 The sub layers must be homogenous and capable of bearing the
imposed loads without significant settlements.
Slab track
• Metro, urban rail transit, Bridge
• Repair inconvenience, small space, traffic density
• Tunnels, subways, elevated crossing, stations & terminals
• High speed railway
Practical uses of slab track
Disadvantages
Main types of non-ballasted
track:
 Embedded in concrete
 Prefabricated slabs
 Monolithic slab
 AC(asphalt concrete)-road bed
 Embedded rail
Slab track (Japan)- prefabricated
Floating Slab Track on springs (Gerb Company)
LVT (Sonneville Company)
Rheda (Germany)- sleepers embedded in concrete
Slab Types
Comparison of ballasted and slab track
Track Modeling
Classic Modeling theories
Sprung/unsprung Mass
model DynamicAnalysis
…………
Track System
Wheel-rail contact
Vehicle System
Using FEA
software
ABAQUS
chapter-3  Track Stracture.pptx

More Related Content

What's hot

05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...
05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...
05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...Hossam Shafiq I
 
Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)sharda university
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)RAMPRASAD KUMAWAT
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossingshiranrathva
 
Railway engineering (CIVIL ENGINEERING)
Railway engineering (CIVIL ENGINEERING)Railway engineering (CIVIL ENGINEERING)
Railway engineering (CIVIL ENGINEERING)comsats
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackKHUSHBU SHAH
 
Geometric design of track
Geometric design of trackGeometric design of track
Geometric design of trackJOYCHENKENGLANG
 
Railway track construction, drainage & maintenence
Railway track  construction, drainage & maintenenceRailway track  construction, drainage & maintenence
Railway track construction, drainage & maintenenceGhanashyam Prajapati
 
modern methods of railway track maintanence
modern methods of railway track maintanencemodern methods of railway track maintanence
modern methods of railway track maintanencekrishnacp
 
Railway engineering By T.Ravi Prakash/Kongu Engineering College
Railway engineering By T.Ravi Prakash/Kongu Engineering CollegeRailway engineering By T.Ravi Prakash/Kongu Engineering College
Railway engineering By T.Ravi Prakash/Kongu Engineering Collegeravicivil
 
About Bridge pier.
About Bridge pier.About Bridge pier.
About Bridge pier.Tajul Islam
 
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...Hossam Shafiq I
 
Railway and Airport Engineering
Railway and Airport EngineeringRailway and Airport Engineering
Railway and Airport EngineeringEmaan Sharma
 
Geometric design of the track
Geometric design of the trackGeometric design of the track
Geometric design of the trackT.Naga Anusha
 
BANGLADESH RAILWAY COMUNICATION
BANGLADESH RAILWAY COMUNICATIONBANGLADESH RAILWAY COMUNICATION
BANGLADESH RAILWAY COMUNICATIONMasudul Robin
 
Introduction to railway engineering
Introduction to railway engineeringIntroduction to railway engineering
Introduction to railway engineeringSatyapal Singh
 
Chapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yardsChapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yardsKHUSHBU SHAH
 

What's hot (20)

05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...
05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...
05 Rails (Railway Engineering Lectures هندسة السكك الحديدية & Dr. Walied A. E...
 
Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
 
Railway engineering (CIVIL ENGINEERING)
Railway engineering (CIVIL ENGINEERING)Railway engineering (CIVIL ENGINEERING)
Railway engineering (CIVIL ENGINEERING)
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway track
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Geometric design of track
Geometric design of trackGeometric design of track
Geometric design of track
 
Railway track construction, drainage & maintenence
Railway track  construction, drainage & maintenenceRailway track  construction, drainage & maintenence
Railway track construction, drainage & maintenence
 
modern methods of railway track maintanence
modern methods of railway track maintanencemodern methods of railway track maintanence
modern methods of railway track maintanence
 
Railway engineering By T.Ravi Prakash/Kongu Engineering College
Railway engineering By T.Ravi Prakash/Kongu Engineering CollegeRailway engineering By T.Ravi Prakash/Kongu Engineering College
Railway engineering By T.Ravi Prakash/Kongu Engineering College
 
About Bridge pier.
About Bridge pier.About Bridge pier.
About Bridge pier.
 
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
02 Railway Terminology (Railway Engineering Lectures هندسة السكك الحديدية & D...
 
Railway and Airport Engineering
Railway and Airport EngineeringRailway and Airport Engineering
Railway and Airport Engineering
 
Railway track:An Introduction
Railway track:An IntroductionRailway track:An Introduction
Railway track:An Introduction
 
Geometric design of the track
Geometric design of the trackGeometric design of the track
Geometric design of the track
 
BANGLADESH RAILWAY COMUNICATION
BANGLADESH RAILWAY COMUNICATIONBANGLADESH RAILWAY COMUNICATION
BANGLADESH RAILWAY COMUNICATION
 
Introduction to railway engineering
Introduction to railway engineeringIntroduction to railway engineering
Introduction to railway engineering
 
Chapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yardsChapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yards
 

Similar to chapter-3 Track Stracture.pptx

lecturenote_1888016911chapter-3 track.pdf
lecturenote_1888016911chapter-3 track.pdflecturenote_1888016911chapter-3 track.pdf
lecturenote_1888016911chapter-3 track.pdfssuser75acc8
 
Defects in a Railway Track & their maintenance.pptx
Defects in a Railway Track & their maintenance.pptxDefects in a Railway Track & their maintenance.pptx
Defects in a Railway Track & their maintenance.pptxSuhasR37
 
CE 533 Chapter 15.pptx
CE 533 Chapter 15.pptxCE 533 Chapter 15.pptx
CE 533 Chapter 15.pptxMarcWorld
 
Axle load for Rail way - linkedin
Axle load for Rail way - linkedinAxle load for Rail way - linkedin
Axle load for Rail way - linkedinHamad Al-oqayli
 
ANALYSIS AND DESIGN OF PRESTRESSED SLEEPERS
ANALYSIS AND DESIGN OF PRESTRESSED SLEEPERSANALYSIS AND DESIGN OF PRESTRESSED SLEEPERS
ANALYSIS AND DESIGN OF PRESTRESSED SLEEPERSAbba Hassan Musa
 
Design consideration for frame
Design consideration for frameDesign consideration for frame
Design consideration for frameaman1312
 
Introduction railway engineering
Introduction railway engineeringIntroduction railway engineering
Introduction railway engineeringDnyaneshwar More
 
Project_midas[1].pptx
Project_midas[1].pptxProject_midas[1].pptx
Project_midas[1].pptxMRVOLDEMORT1
 
Chenab River Bridge
Chenab River BridgeChenab River Bridge
Chenab River BridgeHitesh Sahu
 
1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptxMayuriPatel90
 
Trucks/Buses Chassis Static Structural Analysis with respect to different mat...
Trucks/Buses Chassis Static Structural Analysis with respect to different mat...Trucks/Buses Chassis Static Structural Analysis with respect to different mat...
Trucks/Buses Chassis Static Structural Analysis with respect to different mat...Vinay Tiwari
 
W-6-7-Ch-5-Tank Suspension system.pptx
W-6-7-Ch-5-Tank Suspension system.pptxW-6-7-Ch-5-Tank Suspension system.pptx
W-6-7-Ch-5-Tank Suspension system.pptxvishnoo7
 
introductiontobridges07-08-090507223401-phpapp02.pdf
introductiontobridges07-08-090507223401-phpapp02.pdfintroductiontobridges07-08-090507223401-phpapp02.pdf
introductiontobridges07-08-090507223401-phpapp02.pdfabhinavbharat9
 
introductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptintroductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptJoeBankerS1
 
introductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptintroductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptJoeBankerS1
 
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...Hossam Shafiq I
 
IRJET-Design and Development of Three Link Suspension System for a Quad Bike
IRJET-Design and Development of Three Link Suspension System for a Quad BikeIRJET-Design and Development of Three Link Suspension System for a Quad Bike
IRJET-Design and Development of Three Link Suspension System for a Quad BikeIRJET Journal
 

Similar to chapter-3 Track Stracture.pptx (20)

lecturenote_1888016911chapter-3 track.pdf
lecturenote_1888016911chapter-3 track.pdflecturenote_1888016911chapter-3 track.pdf
lecturenote_1888016911chapter-3 track.pdf
 
Defects in a Railway Track & their maintenance.pptx
Defects in a Railway Track & their maintenance.pptxDefects in a Railway Track & their maintenance.pptx
Defects in a Railway Track & their maintenance.pptx
 
CE 533 Chapter 15.pptx
CE 533 Chapter 15.pptxCE 533 Chapter 15.pptx
CE 533 Chapter 15.pptx
 
Axle load for Rail way - linkedin
Axle load for Rail way - linkedinAxle load for Rail way - linkedin
Axle load for Rail way - linkedin
 
ANALYSIS AND DESIGN OF PRESTRESSED SLEEPERS
ANALYSIS AND DESIGN OF PRESTRESSED SLEEPERSANALYSIS AND DESIGN OF PRESTRESSED SLEEPERS
ANALYSIS AND DESIGN OF PRESTRESSED SLEEPERS
 
3rd unit
3rd unit3rd unit
3rd unit
 
Design consideration for frame
Design consideration for frameDesign consideration for frame
Design consideration for frame
 
Introduction railway engineering
Introduction railway engineeringIntroduction railway engineering
Introduction railway engineering
 
Rail bridge and composite girder bridge analysis
Rail bridge and composite girder bridge analysisRail bridge and composite girder bridge analysis
Rail bridge and composite girder bridge analysis
 
Project_midas[1].pptx
Project_midas[1].pptxProject_midas[1].pptx
Project_midas[1].pptx
 
Chenab River Bridge
Chenab River BridgeChenab River Bridge
Chenab River Bridge
 
1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx
 
Trucks/Buses Chassis Static Structural Analysis with respect to different mat...
Trucks/Buses Chassis Static Structural Analysis with respect to different mat...Trucks/Buses Chassis Static Structural Analysis with respect to different mat...
Trucks/Buses Chassis Static Structural Analysis with respect to different mat...
 
W-6-7-Ch-5-Tank Suspension system.pptx
W-6-7-Ch-5-Tank Suspension system.pptxW-6-7-Ch-5-Tank Suspension system.pptx
W-6-7-Ch-5-Tank Suspension system.pptx
 
introductiontobridges07-08-090507223401-phpapp02.pdf
introductiontobridges07-08-090507223401-phpapp02.pdfintroductiontobridges07-08-090507223401-phpapp02.pdf
introductiontobridges07-08-090507223401-phpapp02.pdf
 
introductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptintroductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.ppt
 
introductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptintroductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.ppt
 
Unit 1 gauge creep
Unit 1 gauge creepUnit 1 gauge creep
Unit 1 gauge creep
 
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
 
IRJET-Design and Development of Three Link Suspension System for a Quad Bike
IRJET-Design and Development of Three Link Suspension System for a Quad BikeIRJET-Design and Development of Three Link Suspension System for a Quad Bike
IRJET-Design and Development of Three Link Suspension System for a Quad Bike
 

More from MamushLeta

Chapter Two.pdf
Chapter Two.pdfChapter Two.pdf
Chapter Two.pdfMamushLeta
 
CHAPTER 3 (part 2) Earth Quake Load and procedure.pptx
CHAPTER 3 (part 2) Earth Quake Load and procedure.pptxCHAPTER 3 (part 2) Earth Quake Load and procedure.pptx
CHAPTER 3 (part 2) Earth Quake Load and procedure.pptxMamushLeta
 
Cha 1 powerpoint.pdf
Cha 1 powerpoint.pdfCha 1 powerpoint.pdf
Cha 1 powerpoint.pdfMamushLeta
 
CHAPTER 3 (part 1) Wind Load and procedure.pptx
CHAPTER 3 (part 1) Wind Load and procedure.pptxCHAPTER 3 (part 1) Wind Load and procedure.pptx
CHAPTER 3 (part 1) Wind Load and procedure.pptxMamushLeta
 
Chapter 4.pptx
Chapter 4.pptxChapter 4.pptx
Chapter 4.pptxMamushLeta
 
chapter 5.pptx
chapter 5.pptxchapter 5.pptx
chapter 5.pptxMamushLeta
 
Chapter 1.pptx
Chapter 1.pptxChapter 1.pptx
Chapter 1.pptxMamushLeta
 
Chapter 2 Track Geometry.pptx
Chapter 2 Track Geometry.pptxChapter 2 Track Geometry.pptx
Chapter 2 Track Geometry.pptxMamushLeta
 
Chapter 1.2 Railway Track Gauge and Train Guidance.pptx
Chapter 1.2 Railway Track Gauge and Train Guidance.pptxChapter 1.2 Railway Track Gauge and Train Guidance.pptx
Chapter 1.2 Railway Track Gauge and Train Guidance.pptxMamushLeta
 
chapter-4 Railway Station.pptx
chapter-4   Railway Station.pptxchapter-4   Railway Station.pptx
chapter-4 Railway Station.pptxMamushLeta
 
Chapter 4 -Irrigation Methods.pptx
Chapter 4  -Irrigation Methods.pptxChapter 4  -Irrigation Methods.pptx
Chapter 4 -Irrigation Methods.pptxMamushLeta
 
CHAPTER 5- Water Conveynance and Control-1.pptx
CHAPTER  5- Water Conveynance and Control-1.pptxCHAPTER  5- Water Conveynance and Control-1.pptx
CHAPTER 5- Water Conveynance and Control-1.pptxMamushLeta
 
Chapter 1.pptx
Chapter 1.pptxChapter 1.pptx
Chapter 1.pptxMamushLeta
 
Debre Markos university 4th year sewage project.pptx
Debre Markos university 4th year sewage project.pptxDebre Markos university 4th year sewage project.pptx
Debre Markos university 4th year sewage project.pptxMamushLeta
 

More from MamushLeta (15)

Chapter Two.pdf
Chapter Two.pdfChapter Two.pdf
Chapter Two.pdf
 
CHAPTER 3 (part 2) Earth Quake Load and procedure.pptx
CHAPTER 3 (part 2) Earth Quake Load and procedure.pptxCHAPTER 3 (part 2) Earth Quake Load and procedure.pptx
CHAPTER 3 (part 2) Earth Quake Load and procedure.pptx
 
Cha 1 powerpoint.pdf
Cha 1 powerpoint.pdfCha 1 powerpoint.pdf
Cha 1 powerpoint.pdf
 
CHAPTER 3 (part 1) Wind Load and procedure.pptx
CHAPTER 3 (part 1) Wind Load and procedure.pptxCHAPTER 3 (part 1) Wind Load and procedure.pptx
CHAPTER 3 (part 1) Wind Load and procedure.pptx
 
Chapter 4.pptx
Chapter 4.pptxChapter 4.pptx
Chapter 4.pptx
 
chapter 5.pptx
chapter 5.pptxchapter 5.pptx
chapter 5.pptx
 
Chapter 1.pptx
Chapter 1.pptxChapter 1.pptx
Chapter 1.pptx
 
CH 1.pptx
CH 1.pptxCH 1.pptx
CH 1.pptx
 
Chapter 2 Track Geometry.pptx
Chapter 2 Track Geometry.pptxChapter 2 Track Geometry.pptx
Chapter 2 Track Geometry.pptx
 
Chapter 1.2 Railway Track Gauge and Train Guidance.pptx
Chapter 1.2 Railway Track Gauge and Train Guidance.pptxChapter 1.2 Railway Track Gauge and Train Guidance.pptx
Chapter 1.2 Railway Track Gauge and Train Guidance.pptx
 
chapter-4 Railway Station.pptx
chapter-4   Railway Station.pptxchapter-4   Railway Station.pptx
chapter-4 Railway Station.pptx
 
Chapter 4 -Irrigation Methods.pptx
Chapter 4  -Irrigation Methods.pptxChapter 4  -Irrigation Methods.pptx
Chapter 4 -Irrigation Methods.pptx
 
CHAPTER 5- Water Conveynance and Control-1.pptx
CHAPTER  5- Water Conveynance and Control-1.pptxCHAPTER  5- Water Conveynance and Control-1.pptx
CHAPTER 5- Water Conveynance and Control-1.pptx
 
Chapter 1.pptx
Chapter 1.pptxChapter 1.pptx
Chapter 1.pptx
 
Debre Markos university 4th year sewage project.pptx
Debre Markos university 4th year sewage project.pptxDebre Markos university 4th year sewage project.pptx
Debre Markos university 4th year sewage project.pptx
 

Recently uploaded

High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 

Recently uploaded (20)

★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 

chapter-3 Track Stracture.pptx

  • 1. DEBRE MARKOS UNIVERSITY COLLEGE OF TECHNOLOGY CIVIL ENGINEERING ACADAMIC PROGRAM RAILWAY ENGINEERING CHAPTER 3 RAILWAY TRACKSTRUCTURES Biniyam A. January, 2022 1
  • 2. Contents 1. Component and function of track structure 2. Track loads 3. Track Analysis: Rail support; sleepers/ties; ballast and subballast 4. Ballasted and Slab track 5. Rail fastening system 6. Track modeling
  • 3. 3.1 Component and function of track structure In contrast to road transport, where vehicles merely run on a prepared surface, rail vehicles are also directionally guided by the tracks they run on. Track usually consists of steel rails installed on sleepers/ties and ballast, on which the rolling stock, usually fitted with metal wheels, moves. The railway track has to fulfill two main functions:  to guide the train with safety  to carry the load of the train and to distribute the load to the subgrade over an area that is as large as possible
  • 5. TRACK LOADS The requirements for the bearing strength and quality of the track depend to a large extent on the load parameters:  axle load: static vertical load per axle;  tonnage borne: sum of the axle loads;  running speed 1. The static axle load level, to which the dynamic increment is added, in principle determines the required strength of the track. 2. The accumulated tonnage is a measure that determines the deterioration of the track quality and as such provides an indication of when maintenance and renewal are necessary. 3. The dynamic load component which depends on speed and horizontal and vertical track geometry also plays an essentialpart here.
  • 6. Forces on the Track Those loads can be categorized into three main groups: • Vertical loads • Lateral loads (transverse), and • Longitudinal loads (parallel) Depending on their nature, those loads can be divided into three groups:  Static loads (normally caused by the vehicle body mass)  Quasi-static loads (or dynamic ride loads),  Dynamic (dynamic wheel/rail) loads, which are associated with significant irregularities that may occur during the life of the track structure and vehicle • Irregularities of the track geometry • Discontinuities on the running surface (switches, joints) • Wear of the running surface of the rails • Wear of the wheels (out-of-round wheels) • Vehicle suspension and vehicle asymmetries Dynamic wheel/rail forces are much higher in magnitude than quasi-static (dynamic ride) forces.
  • 7. Quasi-static (Dynamic Ride) Forces Definition: the sum of the static load and the effect of the static load at speed and they are classified in the frequency range between 0.5 and 30 Hz. The load includes the effects of • the geometrical roughness of the track on vehicle response and • unbalanced superelevation (the effect of the train load not being distributed evenly over both rails). The quasi-static force has been found to be typically between 1.4 and 1.6 times the static wheel load before unbalanced superelevation effects are included4.  which are associated with vehicle movements: Vehicles running on the track apply certain forces on the track structure due to the behavior of the vehicle body, bogie and other masses in reaction to geometrical irregularities in the track.
  • 8. Dynamic Forces The Dynamic Wheel / Rail Forces Dynamic forces come in two categories: – P1 Forces – P2 Forces The P1 Force • P1 forces are classified in frequency range between 100 Hz and 2000 Hz. These forces are also called impact forces. They correspond to surface irregularities or defects in rails and wheels and produce strong impact to rail and wheel. • P1 is a very high frequency force occurring ¼ - ½ ms after crossing the angular discontinuity that occurs at the bottom of the dip and has a very short duration
  • 9. The P1 Force Effect of P1 forces  Rail hammering just after the joint gap and produces high stresses in the rail web.  It contributes to bolt hole failures in bolted joints by increasing the stress range.  contribute to the cracking of concrete sleepers.  Its effects are largely filtered out by the rail and sleepers,  do not directly affect ballast or subgrade settlement.  they have a great influence on wheel/rail contact behavior.
  • 10. The P2 Force  P2 forces are classified in lower frequency range (30 Hz and 100Hz)  They correspond to the movement of unsprung masses of the vehicles.  have a lower-amplitude and longer-duration than the P1 forces. The peak force occurs in the area of the first running-off sleeper after the joint. The wheel set mass and the rail/sleeper mass move down together and compress the ballast beneath the sleeper.  P2 forces therefore increase contact stresses, contribute to the total stress range experienced by the rail web and at joint bolt holes  Increase the loads on sleepers and ballast in the immediate neighborhood of the joint.  P2 forces are of great interest to the track designengineer.  P2 forces contribute primarily to the degradation of trackgeometry.
  • 11. Force Limits Railway organizations around the world have set limits on the various forces at the wheel / rail contact area. Vertical Force Limits In the vertical direction high forces can cause damage to the rails and supporting structures and can cause rolling contact fatigue when combined with high tangential forces such as occur during traction, braking or curving. Eg. UIC limits – a maximum static load of 112.5 kN per wheel and – a maximum dynamic vertical force per wheel of between 160 kN and 200 kN, depending on maximum speed (provided this values does not exceed the static wheel load plus 90 kN). – In small radius curves (less than 600 m) a limit of 145 kN for the quasi- static vertical force.
  • 12. Lateral Force Limits • In the lateral direction high forces can cause distortion of the track on ballast-bed. • This is normally protected against by using the simple but widely established Prud Homme limit for the track shifting force at one wheel set, which can be calculated from the static load (Po force): Where, Y and P0 are in kN. Lateral forces of very short duration are less likely to shift the track and therefore only forces that act for more than 2m of track length are usually counted. In small radius curves (less than 600 m) UIC sets a limit of 60 kN for the quasi-static lateral force.
  • 13. Derailment • Possibility of wheel climb derailment is indicated by the ratio of the lateral force Y to vertical force V • Nadal theory is used to establish limits for the Υ/V derailment ratio with 0,8 as the limiting value. Wheel Unloading Very low vertical forces at the contact patch can indicate that a vehicle is tending to derailment by rolling over or by failing to follow twists in the track. E.g. In the UK a lower limit of 60% of the static wheel load (i.e., unloading by over 40%) is set.
  • 14. Track Components The Principle:- – Track Components do not function independently! – Each component layer must protect the one below. Main design components 1. Rail 2. Sleeper 3. Rail pad/plate 4. Ballast
  • 15. Deflection Profile Source: Selig and Waters, Track Geotechnology and Substructure Management, 1994
  • 16. Static vs. Dynamic Loads  Dynamic loads higher – Acceleration from speed – Downward rotation of wheel – Smaller wheels, faster rotation, more acceleration  Speed/wheel influence – Pv= P + θP (AREMA) Where, Pv= Vertical Dynamic Load (lbs) D = Wheel diameter (in) V = Speed (MPH) P = Static Load (lbs) –Larger wheels impose less influence  Additional dynamic loads from impacts such as caused by wheel flat spots, rail discontinuities (e.g. frog flange ways), track transitions (e.g. bridge approaches), track condition, etc.
  • 17. Typical Track Stiffness Values Winkler Model of Rail Deflection The deterioration process due to variation in track stiffness
  • 18. - Rail, fasteners, tie and ballast Upper Structures  The upper part consists of two parallel steel rails, anchored perpendicular to members called ties (sleepers) of timber, concrete, steel, or plastic to maintain a consistent distance apart, or gauge. 1. Rail Rails are the longitudinal steel members that directly guide the train wheels evenly and continuously. Rail guides the conical, flanged wheels, keeping the vehicles on the track without active steering and therefore allowing trains to be much longer than road vehicles.
  • 19. 1. Rail a) Characteristics b) Functions:  Supports the loads of train and guides their wheel movements  The excellence of the track determines the permissible wheel loads, speeds, safety  provide a surface with smaller resistance  bear the force of the wheels and spread it to sleeper  used as track circuit in electrified railways and automatic block segments • Rigidity • Tenacity • Hardness • Roughness of top surface Composition Unlike other uses of iron and steel, railway rails are subject to very high stresses and have to be made of very high quality steel. Minor flaws in the steel that pose no problems in reinforcing rods for buildings, can, however, lead to broken rails and dangerous derailments when used on railway tracks
  • 20. C) Profile The rail profile is the cross sectional shape of a railway rail, perpendicular to the length of the rail. • A rail is hot rolled steel of a specific cross sectional profile (an asymmetrical I-beam) designed for use as the fundamental component of railway track. • Composed of rail head, rail web and rail base • The rail head and base must be large and thick rail head rail web rail base 1. Rail • weight of a rail per length (Kg/m), such as 75, 60, 50, 43 kg/m. • Standard rail length: 12.5m and 25m. d) Types and length
  • 21. The following rail forms are in use at present: Vignoles rail (standard railway rail with head, web and foot), Double-head rails with head, web and foot (obsolete) Grooved rails for tram ways, Switch rails and Crane rails etc 1. Rail
  • 22. Where, δ- size of rail gap(mm) L- length of track(m) δq- structural joint gap, track of 38kg/m, 43kg/m, 50kg/m, 60kg/m, 75kg/m are 18mm t0 - temperature of rail gap(oC) e) Rail gap To adapt to the needs of expanding with heat and contracting with cold, the rail gap can not too big or too small. 2 0 2 q   0 .0 11 8 L t  t  1  1 2 t2  tmax  tmin  1. Rail The 25 m rail are welded into 100-200m long rail in factory, and then be welded again into1000-2000m long rail in the laid place Advantages: smooth driving low maintenance cost long life f) Continuous welded track (CWR)
  • 23.  good weld ability,  high degree of purity  good surface quality  evenness and observance of profile and  low residual stress after manufacturing g) Rail requirement To be able to withstand manifold and high forces, the rails must meet the following requirements:  high resistance to wear,  high resistance to compression,  high resistance to fatigue  high yield strength, tensile strength and hardness  high resistance to brittle fracture 1. Rail
  • 24. 2. Sleeper (a) Function  bear the force of track Act as elastic medium to absorb blows & vibrations  Longitudinal & lateral stability spread the force to ballast bed and roadbed  keep the direction, position and gauge of track Supporting wheels and/or jacks direct (in a derailment situation). Acting as transverse beams when sitting on temporary ‘way beams’. Supporting signal engineering and other safety related equipment such as trip cocks and point motors. Supporting conductor rails, electrical bonds and feeder cables.  Reducing noise and vibration on non-ballasted bridge decks
  • 25. (b) Characteristic It is solid, flexible, reasonably cost, convenient for manufacturing and maintenance. 2. Sleeper
  • 26. 2. Sleeper • According to production material: reinforced concreted sleeper, wooden sleeper, steel sleeper • According to their usage: regular sleeper, switch sleeper and bridge sleeper. C) Requirements Moderate weight- easy to handle Fixing and removing of fastening should be easy Sufficient bearing area and Able to resist shocks and vibrations Easy maintenance and gauge adjustment Track circuiting must be possible Minimum maintenance and initial cost D)types
  • 27. 1. Wooden Sleeper • Timber ties are usually of a variety of hardwoods, oak being a popular material. • They have the advantage of accepting treatment more readily, they are more susceptible to wear. They are often heavily creosoted. Creosote treating can reduce insect infestation and rot. However, creosote is also carcinogenic and environmentally damaging. • Less often, ties are treated with other preservatives, although some timbers are durable enough that they can be used untreated. 2. Sleeper
  • 28. 2. Concrete Sleeper • Concrete ties have become more common mainly due to greater economy and better support of the rails under high speed and heavy traffic than wooden ties 2. Sleeper
  • 30. • In past times steel sleepers have suffered from poor design and increased traffic loads over their normal long service life. • The steel sleepers’cost benefits together with the ability to hold rail gauge, lower long-term maintenance costs, increase the life of other track components, reduce derailments and meet ever growing and stricter environment standards provide railroad companies with savings and capital to redirect to other areas of maintenance-of-way and business projects. 3. Steel sleeper Advantages: • Long life, Better lateral rigidity • Free from decay and fire hazards • Good scrap value • Lesser damage during handling • Less maintenance problems • Easy to maintain gauge Disadvantages: • Liable to corrosion • Unsuitable to track circuiting • Becomes center bound due to sloping ends • Rail specific
  • 31.  Concrete monoblock sleepers have also been produced in a wider form (e.g. 57 cm (22 in))  there is no ballast between the sleepers;  wide sleeper increase lateral resistance and  reduces ballast pressure. Wide sleeper 2. Sleeper
  • 32. 2. Sleeper Y-shaped sleepers • An unusual form (developed in 1983) • reduced ballast volume due to the load spreading characteristics Compared to conventional sleepers. • High Noise levels • very good resistance to track movement. • Three point contact curves means that an exact geometric fit cannot be observed with a fixed attachment point. Bi-block/Twin-block sleepers • Bi-block sleepers consist of two concrete rail supports joined by steel • Advantages include  Increase lateral resistance  lower weight than monoblock concrete sleepers  eliminate damage from torsional forces on the sleeper centre due the more flexible steel connections  Bi-block sleepers are also used in ballastless track systems
  • 34. Mono-block vs. twin block sleepers The advantages of the twin-block sleeper •Well-defined bearing surfaces in the ballast bed; • high lateral resistance in the ballast bed The advantages of the mono-block sleeper • low price • less susceptibility to cracking • can be pre-stressed 2. Sleeper d)Arrangement Configuration number at each kilometer is decided by volume, speed and line level. The rule: • wooden sleepers must no more than 1920 per 1km and no less than 1440 • Reinforced concreted sleepers must no more than 1840 per 1km and no less than 1440
  • 35. 1. Ballast- it is a layer of broken stones, gravel, moorum or any other gritty material placed and packed below and around sleepers. – for distributing the load from the sleepers to the formation and – for providing drainage – as well as giving longitudinal and lateral stability to the track. 3. Ballast and sub ballast A layer of loose, coarse grained material which, as a result of internal friction between the grains, can absorb considerable compressive stresses, but not tensile stresses.
  • 36. a) Functions The six most important functions of ballast: • To resist vertical & longitudinal forces and hold the track in position • To provide energy absorption for the track • To provide voids for storage and movement of fouling material in the ballast • To facilitate the adjustment of track geometry • To provide immediate drainage of water falling on to the track • To reduce pressures on underlying materials by distributing loads 3. Ballast and sub ballast b) Requirements • Tough and resist wear • Hard enough • Cubical with sharp edge • Non porous, non-water absorbent • Resist attrition • Durable • Good drainage • Cheap and economical
  • 37. Ballast Analysis and Design(depth determination) Source:-AREMA 3. Ballast and sub ballast
  • 38. Ballast depth determination (ballast and subballast combined) = f(applied stress, tie reaction, and allowable subgrade stress) –Talbot Equation, h = (16.8pa/pc)4/5 Where, h = Support ballast depth pa= Stress at bottom of tie (top of ballast) pc= Allowable subgrade stress Note: Stress distribution independent of material –Japanese National Railways Equation pc= 50pa/(10+h1.25) –Boussinesq Equation pc= 6P/2h2 where P = wheel load (lbs) –Love’s Formula pc= pa{1-[1/(1+r2/h2)]3/2} Where, r = Radius of a loaded circle whose area equals the effective tie bearing area under one rail 3. Ballast and sub ballast
  • 39. Minimum depth of ballast Stress distribution is assumed as 45o -Consider stress overlap area -Provide adequate depth of ballast -Thickness of ballast is a function of sleeper spacing, sleeper size etc 3. Ballast and sub ballast
  • 40. 2. Sub ballast -Is a layer of material between the top ballast and sub grade with a gradation finer than the top ballast and coarser than the sub grade a) Function • Used to reduce total ballast cost • Provide a filter layer between the top ballast and a fine grained sub grade b) Application A sub ballast layer is recommended for most new construction. In addition to providing filter to keep sub grade particle from working up in to and fouling the ballast, it provides a good mat to distribute loads from the ballast and prevents ballast particles from being pushed in to the sub grade. 3. Ballast and sub ballast
  • 41. A sub ballast layer is required whenever: i. The sub grade contains 85% or more (by weight) of silt and clay sized particles or, ii.The sub grade material has a plasticity index grater than 20 c) Material hard, angular, non- cementing material, d) Gradation To function as a filter layer, the sub ballast size range from the smallest ballast particles to the largest sub grade particles e) Depth i. During structural analysis, the sub ballast layer is considered as part of the total ballast depth ii. A sub ballast layer may comprise up to 40% of the total ballast thickness on main running tracks and up to 50% on other tracks 3. Ballast and sub ballast
  • 42. 4. Rail fastening system/ Union piece • A Rail fastening system is a means of fixing rails to railroad sleepers. • The terms rail anchors, tie plates, chairs and track fasteners are used to refer to parts or all of a rail fastening system. Various types of fastening have been used over the years. Union pieces are divided into => Rail joint fastenings => Middle joint fastenings. a) Function: The purpose of the rail fastenings:  To maintain the track gauge  Offer sufficient resistance in a vertical direction  To transmit forces acting on and in the rails to the sleepers (cross, longitudinal, concrete plates etc.)  Electrically insulate the sleeper against the remaining track grid, to minimize the loss of signals of the direct-current circuits
  • 43. b) Types (1) rail joint fastenings Rail joint fastenings are used at the end of the two tracks. 4. Rail fastening system/ Union piece (2) Middle joint fastenings • used to connect rail with the sleeper • Based on sleeper type, (reinforced concreted joint fastenings and wooden joint fastenings)
  • 44. 5. Ballasted and slab track a)Ballasted track Advantages: • Lower cost, • small noise emission scope, • short construction period, • easy repair when failure occurs, • high efficiency of maintenance work due to its mechanization, • easy to adjust its geometrical unevenness Disadvantages: The tendency to “float” (longitudinal and lateral direction) Limited non-compensated lateral acceleration in curves caused by the limited lateral resistance provided by ballast Pulverization of the ballast grains in the ballast bed resulting in particles damaging the rail and wheels Problems with ballast churning with high speed Reduced permeability due to contamination, the wear of the ballast, and intrusion of fine particles from the sub grade
  • 45. b) Slab track In slab track, ballast is replaced by another stable load distributing material such as concrete or asphalt. The necessary elasticity has to be provided by inserting elastic elements below the rail or the sleeper, as the concrete or asphalt layer is very stiff. In comparison to ballasted track, the advantages of slab track arein general reduction of maintenance and a higher stability of the track
  • 46.  Less or free maintenance, costs 20%~30%  better line evenness  Increased service life, and possibility of almost full replacement at the end of the service life  Increased lateral resistance and stability  Reduced structure height and weight  The excess of super elevation and cant deficiency of the track with mixed used of freight- and passenger trains does not cause altering of the track position  Track accessibility to road vehicles  Preventing the release of dust from the ballast bed into the environment Slab track Advantages:
  • 47.  Higher construction costs and Higher airborne noise reflection  Adaptability to larger sinkage in the embankment is relatively small  Repair works take much more time and effort (in case of derailment)  Transitions between ballasted track and slab track require attention  Large attentions in track position and super elevation can only be made possible by substantial amounts of work  The application of slab track may require extensive measures concerning the preparation of the foundation.  The sub layers must be homogenous and capable of bearing the imposed loads without significant settlements. Slab track • Metro, urban rail transit, Bridge • Repair inconvenience, small space, traffic density • Tunnels, subways, elevated crossing, stations & terminals • High speed railway Practical uses of slab track Disadvantages
  • 48. Main types of non-ballasted track:  Embedded in concrete  Prefabricated slabs  Monolithic slab  AC(asphalt concrete)-road bed  Embedded rail Slab track (Japan)- prefabricated Floating Slab Track on springs (Gerb Company) LVT (Sonneville Company) Rheda (Germany)- sleepers embedded in concrete Slab Types
  • 49. Comparison of ballasted and slab track
  • 50. Track Modeling Classic Modeling theories Sprung/unsprung Mass model DynamicAnalysis ………… Track System Wheel-rail contact Vehicle System Using FEA software ABAQUS