HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
B.Tech Project Report on MINIATURE ACTIVE MODEL SUBSTATION
1. MINIATURE ACTIVE MODEL SUBSTATION
A Project Work Submitted in Partial Fulfilment of the requirements for the
Degree of
BACHELOR OF TECHNOLOGY IN ELECTRICAL ENGINEERING
OF
MAULANA ABUL KALAM AZAD UNIVERSITY OF TECHNOLOGY
By
Sushil Kumar Bharti (EE/14/64, 10701614058)
Sougata Bera (EE/14/65, 10701614038)
Mainak Singha Barma (EE/14/21, 10701614024)
Kousik Das (EE/14/17, 10701614018)
Under the supervision of
Prof. Shibaji Mondal
(Department of Electrical Engineering)
DEPARTMENT OF ELECTRICAL ENGINEERING
COLLEGE OF ENGINEERING AND MANAGEMENT, KOLAGHAT
Affiliated to MAKAUT, formerly known as WBUT
Approved By AICTE
Kolaghat-721171, West Bengal, India
MAY 2018
2. COLLEGE OF ENGINEERING AND MANAGEMENT, KOLAGHAT
Department of Electrical Engineering
SUSHIL KUMAR BHARTI (EE/14/64, 10701614058)
SOUGATA BERA (EE/14/65, 10701614038)
MAINAK SINGHA BARMA (EE/14/21, 10701614024)
KOUSIK DAS (EE/14/17, 10701614018)
CERTIFICATE OF RECOMMENDATION
Under my guidance for the fulfilment of the B.Tech degree in Electrical Engineering under
Maulana Abul Kalam Azad University of Technology, is a bonafide record of the carried by them
and that neither his/her project nor any part of the project has been submitted for any
Degree/Diploma or any other academic award anywhere before.
Prof. Shibaji Mondal
(Department of Electrical Engineering)
College of Engineering and Management, Kolaghat
_________________
Prof. Shobha Gupta
(H.O.D of Department of Electrical Engineering)
College of Engineering and Management, Kolaghat
_________________
This to certify that the dissertation work entitles “MINIATURE ACTIVE MODEL SUBSTATION”
was done by
3. CERTIFICATE OF APPROVAL
The foregoing project entitled “MINIATURE ACTIVE MODEL SUBSTATION” is
hereby approved as a creditable study of B.Tech in Electrical Engineering and presented in
a manner satisfactory to warrant its acceptance as a prerequisite to the degree for which it
has been submitted. It is understood that by this approval the undersigned do not
necessarily endorse or approve any statement made, opinion expressed or conclusion there
in but approve this thesis only for the purpose for which it is submitted.
Committee for
Evaluation of the Project
: _________________________________
: ________________________________
: _________________________________
4. ACKNOWLEDGEMENT
We would like to thank College of Engineering and Management, Kolaghat for giving us the
opportunity to use their resources and work in a challenging environment.
First and foremost we take this opportunity to express our deepest sense of gratitude to our
guide Prof. Shibaji Mondal for his able guidance during my protest work. This project would
not have been possible without his help and the valuable time he has given us amidst his busy
schedule. We would also like to extend our gratitude to our H.O.D Prof. Shobha Gupta and
Prof. Shankar Prasad Ghosh who have always encouraged and supported us in completing
our project. Last but not the least we would like to thank all the staff members of Department
of Electrical Engineering who have been very cooperative with us.
____________________
SUSHIL KUMAR BHARTI
____________________
SOUGATA BERA
_____________________
MAINAK SINGHA BARMA
_____________________
KOUSIK DAS
DATE-
5. CONTENTS
TOPICS
1) Introduction
2) Layout of the Substation
3) Main Elements and Modification
4) E.H.V. Transmission Tower
5) Insulators
6) Isolators
7) P.F. Improvement
8) Busbar
9) Instrument Transformer
10) Circuit Breaker
11) Power Transformer
12) Wires & Cables
13) Internal Wiring
14) Project Work Pictures
15) Conclusion
16) References
PAGE NO
1
2
3
4
6
9
10
13
16
17
19
20
21
22
26
27
6. Substation is an intermediate station between generating station and consumer. The assembly
of apparatus which is used to change some characteristic (e.g. voltage, current, power factor,
frequency etc) of supply system is known as substation. Now a days electrical power is
generated, transmitted and distributed in the form of alternating quantity. The power stations
are actually far away from the consumers through installed within the load centre. It delivers
power to consumers through a large network. The assembly of apparatus (e.g. transformer,
isolator, fuse etc) is required to use for this purpose. It may be desirable to convert large
quantity of A.C. power to D.C. power for (special single phase A.C. case) traction system,
electroplating D.C. motor etc. It is clear that type of requirement needed in a substation will
depend upon the service requirement and different voltage levels.
In our technical project work we have decided to make a Model Active Substation under Prof.
Shivaji Mondal. The main motto of our project is to reduce the overall complexity of a
substation by using M.C.B (Miniature Circuit Breaker).
INTRODUCTION
1
8. MAIN ELEMENTS AND MODIFICATIONS
OF OUR SUBSTATION
MAIN ELEMENTS EQUIVALENT ELEMENTS
Working Surface Ply Board; Dimension- 4ftx3ft
EHV T.L.Tower Iron Bar; Height- 8”,Top Width- 5”
Insulator Wooden Blocks; Height- 2”
Isolator Toggle Switch
Circuit Breaker MCB--16 amps,10 amps,6 amps
Connection Wire Normal Plastic Insulated Wire
Extension Wire Insulated Silver Wire
Transformer 220/132 V, 1 phase
220/66 V, 1 phase
P.T 220/12 V
Voltmeter 0-300 V
Indicator 15x22 mm AC/DC LED Indicator
Buzzer 22 mm 12V LED Flashing Buzzer
3
31. CONCLUSION
So, finally it can be concluded that the report here contains the respective
theorem along with the schematic arrangement for our project and thus contain a
complete report on “ MINIATURE ACTIVE SUBSTATION MODEL”
26
32. REFERENCES
1. "Joint Consultation Paper: Western Metropolitan Melbourne Transmission Connection
and Subtransmission Capacity". Jemena. Powercor Australia, Jemena, Australian Energy
Market Operator. Retrieved 4 February 2016.
2. Stockton, Blaine. "Design Guide for Rural Substation". USDA Rural Development.
United States Department of Agriculture. Retrieved 4 February 2016.
3.Steinberg, Neil. "Lights On but Nobody Home: Behind the Fake Buildings that Power
Chicago". Retrieved 14 December 2013.
4."Transformer Fire Video". metacafe. User Eagle Eye. Retrieved 4 February 2016.
5. Boyd, Dan; Rampaul, Glen. "Mobile Substations". IEEE Winnipeg PES Chapter. IEEE
Power and Energy Society. Retrieved 11 October 2017.
6. John, Alvin. "EE35T - Substation Design and Layout". The University Of The West
Indies at St. Augustine, Trinidad And Tobago. Retrieved 4 February 2016.
7. Donald G. Fink, H. Wayne Beatty Standard Handbook for Electrical Engineers
Eleventh Edition, McGraw Hill 1978 ISBN 0-07-020974-X Chapter 17 Substation
Design
8. Baker, Joseph W,. "Eliminating Hurricane Induced Storm Surge Damage To Electric
Utilities Via In-place Elevation Of Substation Structures And Equipment". DIS-TRAN
Packaged Substations. Crest Industries. Archived from the original on 5 February 2016.
Retrieved 4 February 2016.
9.R. M. S. de Oliveira and C. L. S. S. Sobrinho (2009). "Computational Environment for
Simulating Lightning Strokes in a Power Substation by Finite-Difference Time-Domain
Method". IEEE Transactions on Electromagnetic Compatibility. 51 (4): 995–
1000. doi:10.1109/TEMC.2009.2028879.
27
Editor's Notes
A Project Work Submitted in Partial Fulfillment of the requirements for the Degree of
BACHELOR OF TECHNOLOGY IN ELECTRICAL ENGINEERING
OF
MAULANA ABUL KALAM AZAD UNIVERSITY OF TECHNOLOGY
This to certify that the dissertation work entitles “ACTIVE MODEL ON 132 KV SUBSTATION” was done by