SlideShare a Scribd company logo
1 of 1
Max measured length is 200', max equivalent length is 250'
Liquid Lines
Velocity
This should be between 100 fpm and 400 fpm for either R-
410A or R-22.Exceeding 400 fpm is acceptable, but may lead
to refrigerant noise issues. 5 ton units using 3/8" lines will be
405 fpm for R-22 or 483 fpm for R-410A. While acceptable,
the possibility of noise must be understood and explained to
the owner Avoid placing lines inside walls or directly above
sleeping areas whenever possible
Pressure Drop
This can be no more than 35 psi for R-22 or 60 psi for R-
410A. Exceeding those parameters is NOT ALLOWED as it
would cause a loss of subcooling which leads to capacity loss
and/or failed components. If a HP system has both vertical
rise and vertical drop in the liquid line, enter the NET value
as a rise. In an A/C system enter the net rise OR net drop as
appropriate.
Suction Lines
Velocity
This should be between 1000 fpm and 3000 fpm for either R-
410A or R-22. Less than 1000 fpm on vertical risers may not
allow oil to be returned to the compressor and exceeding
3000 fpm will cause noise and vibration problems. Velocity
on horizontal runs is allowed to be as low as 800 fpm.
Pressure Drop
This should be no more than 3 psi for R-22 or 5 psi for R-
410A Exceeding these values is not recommended but is
allowed. However it results in capacity loss at a rate of 1%
for every psi on R-22 and .7% for every psi on R-410A
Long Line Sets
A long line set is defined as exceeding 75 Feet in length and
MUST include a:
1. crankcase heater if one is not factory installed.
2. normally closed solenoid valve installed in the liquid line
near the condensing unit.
3. Non Bleed TXV (standard requirement on most units at
13 SEER and higher).
4. hard start kit (single phase units only).
5. Install Schrader access valves at the indoor unit for both
the suction and liquid lines. These are optional, but
recommended to aid in troubleshooting pressure drops,
subcooling and TXV operation
Using Receivers to overcome loss of subcooling
When using a receiver it must be understood that subcooling
measurements cannot be attempted in the field as the receiver contents
are in a saturated state. No hydrolic or hydorstatic seal exists so
subcooling cannot be measured. A sight glass between the receiver and
TXV must be used to charge the system by adding refrigerant until
bubbles are gone, then adding 1/2 the pump down capacity of the
receiver. Use of receivers is not supported by the factory because the
application typically does not fall within their published guidelines.
NOTES:
1. If on a long line set the liquid line will be exposed to direct
sunlight, or very high ambient conditions, it should be
insulated
2. If the unit contains a rotary compressor the MAXIMUM
line length is 100'
3. If more than 5 feet of underground piping is installed on a
cooling only system, install an accumulator with volume
equal to 1/2 the system's refrigerant volume.
4. If a long line set application uses a two stage system,
meaning a single refrigerant circuit with either two
compressors or a single compressor that reduces capacity,
consider decreasing the vertical suction riser (if one exists)
by one line size.
5. Noise from lines running through basements and/or attics
can often be avoided by adhearing to the velocity
guidelines and taking care use non metalic hangers such as
mesh strap which insulates the refrigerant lines from the
joists. Overcharging will also contribute to noise.
Discharge or vapor line mufflers can eliminate harmonic
noises sometimes encountered in otherwise properly sized
and charged systems.
6. For addtional information consult the most recent
Application Guidlines for Refrigeration Piping as
published by UPG. If your application exceeds
theseparameters, you must contact Jack Bartell or the
factory for assistance
REMEMBER: With 2 stage units you must look at the suction line
velocity at reduced capacity to insure velocity remains above 1000fpm
on suction risers. If it does not, reducing the riser size by one size will
correct the problem
1. Slope horizontal suction lines on cooling only systems approximately
1 inch every 20 feet toward the outdoor unit to facilitate proper oil
return. Since the flow of refrigerant is bidirectional on heat pumps,
all horizontal vapor lines should be level. Pre-charged lines with
excess tubing should be coiled horizontally in an inconspicuous
location to avoid oil trapping. Never coil excess tubing vertically.
2. Use long radius elbows wherever possible
3. Use PVC piping as a conduit for all underground installations.See
Figure 2. Buried lines must be kept as short as possible to minimize
the build up of liquid refrigerant in the vapor line during long
periods of shutdown.
TRAPS
Traps are not required if the piping is properly sized.
Traps will only add pressure drop to the system, further
reducing capacity
INDOOR UNIT ABOVE OUTDOOR UNIT
a common problem with the cooling cycle (air conditioning or heat
pump) is that the amount of liquid sub-cooling varies as operating
conditions change (such as outdoor ambient). Under some conditions, it
is possible that flashing will actually occur in the liquid riser. As long as
only liquid is present in the liquid riser, the liquid static pressure loss
can be calculated at 1/2 psi per foot of rise. However, as soon as flashing
starts, the rate of pressure loss increases and continues to increase as
the amount of gas increases. For this reason, the restrictions on
elevation differences for this configuration must be based on
the entire range of operating conditions. When the indoor
unit is above the outdoor unit, the pressure loss in the liquid
line during the cooling cycle will limit the amount of elevation
difference allowed. Since both friction and static head
contribute to pressure loss, it can be stated that the elevation
difference allowed decreases as the total equivalent line
length (horizontal plus vertical) increases.
OUTDOOR UNIT ABOVE INDOOR UNIT
When the outdoor unit is above the indoor unit, the static pressure
gain in the liquid line vertical drop (1/2 psi per foot) may overcome the
frictional pressure loss resulting in a total pressure gain. A pressure
gain in the liquid line is not detrimental to the performance of the
system. On cooling only systems where the outdoor unit is located high
above the indoor coil, it may even be possible to reduce the size of the
liquid line. The static gain in the vertical drop will offset the increased
friction loss caused by smaller tubing. In addition, the reduction in the
total system charge due to the smaller liquid line will enhance the
reliability of the system. With this configuration, gas velocity in the
vapor riser must be kept above 1000 feet per minute for proper oil
return and below 3000 feet per minute to avoid noise and vibration
problems.

More Related Content

What's hot

Thermocompressors us
Thermocompressors usThermocompressors us
Thermocompressors ushung do
 
Rail Hose Selection Guide - Transportation - Parker Hannifin
Rail Hose Selection Guide - Transportation - Parker HannifinRail Hose Selection Guide - Transportation - Parker Hannifin
Rail Hose Selection Guide - Transportation - Parker HannifinParker Hannifin Corporation
 
Flow, Pressure & Vapor Instrumentation
Flow, Pressure & Vapor InstrumentationFlow, Pressure & Vapor Instrumentation
Flow, Pressure & Vapor InstrumentationMiller Energy, Inc.
 
Yokogawa Differential Pressure Transmitter
Yokogawa Differential Pressure TransmitterYokogawa Differential Pressure Transmitter
Yokogawa Differential Pressure TransmitterMiller Energy, Inc.
 
Hvac duct construction wasilewski
Hvac duct construction   wasilewskiHvac duct construction   wasilewski
Hvac duct construction wasilewskiIyan Gutierrez
 
Vortex Flow Meters- Badger Meter
Vortex Flow Meters- Badger MeterVortex Flow Meters- Badger Meter
Vortex Flow Meters- Badger MeterBell Flow Systems
 
F500 series floco positive displacement meters
F500 series floco positive displacement metersF500 series floco positive displacement meters
F500 series floco positive displacement metersWilly Orosco Mariscal
 
Liquid Level Measurement Using the Bubbler Method
Liquid Level Measurement Using the Bubbler MethodLiquid Level Measurement Using the Bubbler Method
Liquid Level Measurement Using the Bubbler MethodMiller Energy, Inc.
 
AJA ATC-2200-UHV deposition system sputtering system system in San Jose CA
AJA ATC-2200-UHV deposition system sputtering system system in San Jose CAAJA ATC-2200-UHV deposition system sputtering system system in San Jose CA
AJA ATC-2200-UHV deposition system sputtering system system in San Jose CAEmily Tan
 
Transformer_Cooling 2015 Doble LOAT Conference
Transformer_Cooling 2015 Doble LOAT ConferenceTransformer_Cooling 2015 Doble LOAT Conference
Transformer_Cooling 2015 Doble LOAT ConferenceKevin Riley
 
Cem 350 hvac distribution systems sizing 10 2016
Cem  350 hvac distribution systems sizing 10 2016Cem  350 hvac distribution systems sizing 10 2016
Cem 350 hvac distribution systems sizing 10 2016miresmaeil
 
Instrumentation & Control For Thermal Power Plant
Instrumentation & Control For Thermal Power PlantInstrumentation & Control For Thermal Power Plant
Instrumentation & Control For Thermal Power PlantSHIVAJI CHOUDHURY
 
Rosemount Analytical Hagan Pneumatic Power Positioners
Rosemount Analytical Hagan Pneumatic Power PositionersRosemount Analytical Hagan Pneumatic Power Positioners
Rosemount Analytical Hagan Pneumatic Power PositionersHile Controls of Alabama, Inc.
 

What's hot (20)

Thermocompressors us
Thermocompressors usThermocompressors us
Thermocompressors us
 
Control Dampers
Control DampersControl Dampers
Control Dampers
 
Damper Actuators
Damper ActuatorsDamper Actuators
Damper Actuators
 
Rail Hose Selection Guide - Transportation - Parker Hannifin
Rail Hose Selection Guide - Transportation - Parker HannifinRail Hose Selection Guide - Transportation - Parker Hannifin
Rail Hose Selection Guide - Transportation - Parker Hannifin
 
Flow, Pressure & Vapor Instrumentation
Flow, Pressure & Vapor InstrumentationFlow, Pressure & Vapor Instrumentation
Flow, Pressure & Vapor Instrumentation
 
Yokogawa Differential Pressure Transmitter
Yokogawa Differential Pressure TransmitterYokogawa Differential Pressure Transmitter
Yokogawa Differential Pressure Transmitter
 
Hvac duct construction wasilewski
Hvac duct construction   wasilewskiHvac duct construction   wasilewski
Hvac duct construction wasilewski
 
Vortex Flow Meters- Badger Meter
Vortex Flow Meters- Badger MeterVortex Flow Meters- Badger Meter
Vortex Flow Meters- Badger Meter
 
F500 series floco positive displacement meters
F500 series floco positive displacement metersF500 series floco positive displacement meters
F500 series floco positive displacement meters
 
Liquid Level Measurement Using the Bubbler Method
Liquid Level Measurement Using the Bubbler MethodLiquid Level Measurement Using the Bubbler Method
Liquid Level Measurement Using the Bubbler Method
 
Steam blowing procedure
Steam blowing procedure Steam blowing procedure
Steam blowing procedure
 
AJA ATC-2200-UHV deposition system sputtering system system in San Jose CA
AJA ATC-2200-UHV deposition system sputtering system system in San Jose CAAJA ATC-2200-UHV deposition system sputtering system system in San Jose CA
AJA ATC-2200-UHV deposition system sputtering system system in San Jose CA
 
Transformer_Cooling 2015 Doble LOAT Conference
Transformer_Cooling 2015 Doble LOAT ConferenceTransformer_Cooling 2015 Doble LOAT Conference
Transformer_Cooling 2015 Doble LOAT Conference
 
Cem 350 hvac distribution systems sizing 10 2016
Cem  350 hvac distribution systems sizing 10 2016Cem  350 hvac distribution systems sizing 10 2016
Cem 350 hvac distribution systems sizing 10 2016
 
Instrumentation & Control For Thermal Power Plant
Instrumentation & Control For Thermal Power PlantInstrumentation & Control For Thermal Power Plant
Instrumentation & Control For Thermal Power Plant
 
Rosemount Analytical Hagan Pneumatic Power Positioners
Rosemount Analytical Hagan Pneumatic Power PositionersRosemount Analytical Hagan Pneumatic Power Positioners
Rosemount Analytical Hagan Pneumatic Power Positioners
 
Ins and Outs of I/P Transducers
Ins and Outs of I/P TransducersIns and Outs of I/P Transducers
Ins and Outs of I/P Transducers
 
Industrial Boiler Optimization Toolkit
Industrial Boiler Optimization ToolkitIndustrial Boiler Optimization Toolkit
Industrial Boiler Optimization Toolkit
 
HVAC
HVACHVAC
HVAC
 
Air Duct Leakage
Air Duct LeakageAir Duct Leakage
Air Duct Leakage
 

Similar to hvac refragration Pipes size and table

Understanding & Solving Heat Transfer Equipment Stall
Understanding & Solving Heat Transfer Equipment StallUnderstanding & Solving Heat Transfer Equipment Stall
Understanding & Solving Heat Transfer Equipment StallMead O'Brien, Inc.
 
Boiler doc 08 control application
Boiler doc 08   control applicationBoiler doc 08   control application
Boiler doc 08 control applicationMars Tsani
 
Energy efficiency improvement opportunities in compressed air systems
Energy efficiency improvement opportunities in compressed air systemsEnergy efficiency improvement opportunities in compressed air systems
Energy efficiency improvement opportunities in compressed air systemsPratik Bhoir
 
A Guide To Fume Extraction Systems & Components
A Guide To Fume Extraction Systems & ComponentsA Guide To Fume Extraction Systems & Components
A Guide To Fume Extraction Systems & ComponentsAxair Fan (UK) Ltd.
 
Control valves for thermal power plants
Control valves for thermal power plantsControl valves for thermal power plants
Control valves for thermal power plantsSHIVAJI CHOUDHURY
 
Refrigeration and Air Conditioning
Refrigeration and Air ConditioningRefrigeration and Air Conditioning
Refrigeration and Air Conditioningfahrenheit
 
heat exchangers | column components | couplings
heat exchangers | column components | couplingsheat exchangers | column components | couplings
heat exchangers | column components | couplingsGoel Scientific
 
FIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPT
FIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPTFIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPT
FIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPTMEP ENGINEER'S SERVICES
 
Catálogo Williams _ X series
Catálogo Williams _ X series Catálogo Williams _ X series
Catálogo Williams _ X series Vibropac
 
Compressed Coalescing Filters for Industrial Use
Compressed Coalescing Filters for Industrial UseCompressed Coalescing Filters for Industrial Use
Compressed Coalescing Filters for Industrial UseClassic Controls, Inc.
 

Similar to hvac refragration Pipes size and table (20)

Understanding & Solving Heat Transfer Equipment Stall
Understanding & Solving Heat Transfer Equipment StallUnderstanding & Solving Heat Transfer Equipment Stall
Understanding & Solving Heat Transfer Equipment Stall
 
Boiler doc 08 control application
Boiler doc 08   control applicationBoiler doc 08   control application
Boiler doc 08 control application
 
Model 8.1-pressure control
Model 8.1-pressure controlModel 8.1-pressure control
Model 8.1-pressure control
 
QX1402 VDL(H) spec.
QX1402 VDL(H) spec.QX1402 VDL(H) spec.
QX1402 VDL(H) spec.
 
Energy efficiency improvement opportunities in compressed air systems
Energy efficiency improvement opportunities in compressed air systemsEnergy efficiency improvement opportunities in compressed air systems
Energy efficiency improvement opportunities in compressed air systems
 
A Guide To Fume Extraction Systems & Components
A Guide To Fume Extraction Systems & ComponentsA Guide To Fume Extraction Systems & Components
A Guide To Fume Extraction Systems & Components
 
Control valves for thermal power plants
Control valves for thermal power plantsControl valves for thermal power plants
Control valves for thermal power plants
 
QX1403 VDL(H) spec.
QX1403 VDL(H) spec.QX1403 VDL(H) spec.
QX1403 VDL(H) spec.
 
QX1901 VDL(H) spec.
QX1901 VDL(H) spec.QX1901 VDL(H) spec.
QX1901 VDL(H) spec.
 
QX1903 VDL(H) spec.
QX1903 VDL(H) spec.QX1903 VDL(H) spec.
QX1903 VDL(H) spec.
 
Adm apn051-en
Adm apn051-enAdm apn051-en
Adm apn051-en
 
Dental_Chair_2.doc
Dental_Chair_2.docDental_Chair_2.doc
Dental_Chair_2.doc
 
AIR CONDITIONING SYSTEM DESINGING
AIR CONDITIONING SYSTEM DESINGINGAIR CONDITIONING SYSTEM DESINGING
AIR CONDITIONING SYSTEM DESINGING
 
Refrigeration and Air Conditioning
Refrigeration and Air ConditioningRefrigeration and Air Conditioning
Refrigeration and Air Conditioning
 
heat exchangers | column components | couplings
heat exchangers | column components | couplingsheat exchangers | column components | couplings
heat exchangers | column components | couplings
 
FIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPT
FIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPTFIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPT
FIRE FIGHTING NOTES PART 02 BY ER. EZAZUL HAQUE SIDDIQUE .PPT
 
Barometric condensor
Barometric condensorBarometric condensor
Barometric condensor
 
Catálogo Williams _ X series
Catálogo Williams _ X series Catálogo Williams _ X series
Catálogo Williams _ X series
 
QX1902 VDL(H) spec.
QX1902 VDL(H) spec.QX1902 VDL(H) spec.
QX1902 VDL(H) spec.
 
Compressed Coalescing Filters for Industrial Use
Compressed Coalescing Filters for Industrial UseCompressed Coalescing Filters for Industrial Use
Compressed Coalescing Filters for Industrial Use
 

More from MUSTAFA AHMED ABDULJABBAR

Slide rule part2 carrier part load calculator supplement
Slide rule part2 carrier part load calculator supplementSlide rule part2 carrier part load calculator supplement
Slide rule part2 carrier part load calculator supplementMUSTAFA AHMED ABDULJABBAR
 
Slide rule part1 carrier part load calculator user manual and instructions
Slide rule part1 carrier part load calculator user manual and instructionsSlide rule part1 carrier part load calculator user manual and instructions
Slide rule part1 carrier part load calculator user manual and instructionsMUSTAFA AHMED ABDULJABBAR
 
Module 9 GENERAL TRAINING ELECTRICITY ELECTRICAL TROUBLESHOOTING GTAC GTE GTH
Module 9 GENERAL TRAINING ELECTRICITY ELECTRICAL TROUBLESHOOTING GTAC GTE GTHModule 9 GENERAL TRAINING ELECTRICITY ELECTRICAL TROUBLESHOOTING GTAC GTE GTH
Module 9 GENERAL TRAINING ELECTRICITY ELECTRICAL TROUBLESHOOTING GTAC GTE GTHMUSTAFA AHMED ABDULJABBAR
 
Module 8 ELECTRONIC DEVICES AND CIRUITS GTAC GTE GTH
Module 8 ELECTRONIC DEVICES AND CIRUITS GTAC GTE GTH Module 8 ELECTRONIC DEVICES AND CIRUITS GTAC GTE GTH
Module 8 ELECTRONIC DEVICES AND CIRUITS GTAC GTE GTH MUSTAFA AHMED ABDULJABBAR
 
Wiring.module.3 GENERAL TRAINING ELECTRICITY
Wiring.module.3 GENERAL TRAINING ELECTRICITYWiring.module.3 GENERAL TRAINING ELECTRICITY
Wiring.module.3 GENERAL TRAINING ELECTRICITYMUSTAFA AHMED ABDULJABBAR
 

More from MUSTAFA AHMED ABDULJABBAR (20)

Hvac formulas
Hvac formulasHvac formulas
Hvac formulas
 
Slide rule part2 carrier part load calculator supplement
Slide rule part2 carrier part load calculator supplementSlide rule part2 carrier part load calculator supplement
Slide rule part2 carrier part load calculator supplement
 
Slide rule part1 carrier part load calculator user manual and instructions
Slide rule part1 carrier part load calculator user manual and instructionsSlide rule part1 carrier part load calculator user manual and instructions
Slide rule part1 carrier part load calculator user manual and instructions
 
CHECK LIST FOR ( HVAC ) WORK & SHOP DRAWING
CHECK LIST FOR ( HVAC ) WORK & SHOP DRAWINGCHECK LIST FOR ( HVAC ) WORK & SHOP DRAWING
CHECK LIST FOR ( HVAC ) WORK & SHOP DRAWING
 
Preventing compressor failure
Preventing compressor failurePreventing compressor failure
Preventing compressor failure
 
smacna cad standard
smacna cad standardsmacna cad standard
smacna cad standard
 
HVAC QUICK COMPRESSOR WINDING CHECK
HVAC QUICK COMPRESSOR WINDING CHECK  HVAC QUICK COMPRESSOR WINDING CHECK
HVAC QUICK COMPRESSOR WINDING CHECK
 
Equations
EquationsEquations
Equations
 
Stair case fan sizing
Stair case fan sizingStair case fan sizing
Stair case fan sizing
 
Smoke fan sizing
Smoke fan sizingSmoke fan sizing
Smoke fan sizing
 
Auto cad shortcuts
Auto cad shortcutsAuto cad shortcuts
Auto cad shortcuts
 
Micro soft word arabic lang shortcut
Micro soft word arabic lang shortcutMicro soft word arabic lang shortcut
Micro soft word arabic lang shortcut
 
REFRIGERANT pipING module 3 GTAC
REFRIGERANT pipING module 3 GTACREFRIGERANT pipING module 3 GTAC
REFRIGERANT pipING module 3 GTAC
 
Module 9 GENERAL TRAINING ELECTRICITY ELECTRICAL TROUBLESHOOTING GTAC GTE GTH
Module 9 GENERAL TRAINING ELECTRICITY ELECTRICAL TROUBLESHOOTING GTAC GTE GTHModule 9 GENERAL TRAINING ELECTRICITY ELECTRICAL TROUBLESHOOTING GTAC GTE GTH
Module 9 GENERAL TRAINING ELECTRICITY ELECTRICAL TROUBLESHOOTING GTAC GTE GTH
 
Module 8 ELECTRONIC DEVICES AND CIRUITS GTAC GTE GTH
Module 8 ELECTRONIC DEVICES AND CIRUITS GTAC GTE GTH Module 8 ELECTRONIC DEVICES AND CIRUITS GTAC GTE GTH
Module 8 ELECTRONIC DEVICES AND CIRUITS GTAC GTE GTH
 
MODULE 4 Wiring diagram exercises
MODULE 4 Wiring diagram exercises MODULE 4 Wiring diagram exercises
MODULE 4 Wiring diagram exercises
 
30GT15-35 TON RECIPROCATING LIQUID CHILLERS
30GT15-35 TON  RECIPROCATING LIQUID CHILLERS30GT15-35 TON  RECIPROCATING LIQUID CHILLERS
30GT15-35 TON RECIPROCATING LIQUID CHILLERS
 
Wiring.module.3 GENERAL TRAINING ELECTRICITY
Wiring.module.3 GENERAL TRAINING ELECTRICITYWiring.module.3 GENERAL TRAINING ELECTRICITY
Wiring.module.3 GENERAL TRAINING ELECTRICITY
 
Understanding electronic.contrOL
Understanding electronic.contrOLUnderstanding electronic.contrOL
Understanding electronic.contrOL
 
Scroll compressors
Scroll compressorsScroll compressors
Scroll compressors
 

Recently uploaded

Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 

Recently uploaded (20)

Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 

hvac refragration Pipes size and table

  • 1. Max measured length is 200', max equivalent length is 250' Liquid Lines Velocity This should be between 100 fpm and 400 fpm for either R- 410A or R-22.Exceeding 400 fpm is acceptable, but may lead to refrigerant noise issues. 5 ton units using 3/8" lines will be 405 fpm for R-22 or 483 fpm for R-410A. While acceptable, the possibility of noise must be understood and explained to the owner Avoid placing lines inside walls or directly above sleeping areas whenever possible Pressure Drop This can be no more than 35 psi for R-22 or 60 psi for R- 410A. Exceeding those parameters is NOT ALLOWED as it would cause a loss of subcooling which leads to capacity loss and/or failed components. If a HP system has both vertical rise and vertical drop in the liquid line, enter the NET value as a rise. In an A/C system enter the net rise OR net drop as appropriate. Suction Lines Velocity This should be between 1000 fpm and 3000 fpm for either R- 410A or R-22. Less than 1000 fpm on vertical risers may not allow oil to be returned to the compressor and exceeding 3000 fpm will cause noise and vibration problems. Velocity on horizontal runs is allowed to be as low as 800 fpm. Pressure Drop This should be no more than 3 psi for R-22 or 5 psi for R- 410A Exceeding these values is not recommended but is allowed. However it results in capacity loss at a rate of 1% for every psi on R-22 and .7% for every psi on R-410A Long Line Sets A long line set is defined as exceeding 75 Feet in length and MUST include a: 1. crankcase heater if one is not factory installed. 2. normally closed solenoid valve installed in the liquid line near the condensing unit. 3. Non Bleed TXV (standard requirement on most units at 13 SEER and higher). 4. hard start kit (single phase units only). 5. Install Schrader access valves at the indoor unit for both the suction and liquid lines. These are optional, but recommended to aid in troubleshooting pressure drops, subcooling and TXV operation Using Receivers to overcome loss of subcooling When using a receiver it must be understood that subcooling measurements cannot be attempted in the field as the receiver contents are in a saturated state. No hydrolic or hydorstatic seal exists so subcooling cannot be measured. A sight glass between the receiver and TXV must be used to charge the system by adding refrigerant until bubbles are gone, then adding 1/2 the pump down capacity of the receiver. Use of receivers is not supported by the factory because the application typically does not fall within their published guidelines. NOTES: 1. If on a long line set the liquid line will be exposed to direct sunlight, or very high ambient conditions, it should be insulated 2. If the unit contains a rotary compressor the MAXIMUM line length is 100' 3. If more than 5 feet of underground piping is installed on a cooling only system, install an accumulator with volume equal to 1/2 the system's refrigerant volume. 4. If a long line set application uses a two stage system, meaning a single refrigerant circuit with either two compressors or a single compressor that reduces capacity, consider decreasing the vertical suction riser (if one exists) by one line size. 5. Noise from lines running through basements and/or attics can often be avoided by adhearing to the velocity guidelines and taking care use non metalic hangers such as mesh strap which insulates the refrigerant lines from the joists. Overcharging will also contribute to noise. Discharge or vapor line mufflers can eliminate harmonic noises sometimes encountered in otherwise properly sized and charged systems. 6. For addtional information consult the most recent Application Guidlines for Refrigeration Piping as published by UPG. If your application exceeds theseparameters, you must contact Jack Bartell or the factory for assistance REMEMBER: With 2 stage units you must look at the suction line velocity at reduced capacity to insure velocity remains above 1000fpm on suction risers. If it does not, reducing the riser size by one size will correct the problem 1. Slope horizontal suction lines on cooling only systems approximately 1 inch every 20 feet toward the outdoor unit to facilitate proper oil return. Since the flow of refrigerant is bidirectional on heat pumps, all horizontal vapor lines should be level. Pre-charged lines with excess tubing should be coiled horizontally in an inconspicuous location to avoid oil trapping. Never coil excess tubing vertically. 2. Use long radius elbows wherever possible 3. Use PVC piping as a conduit for all underground installations.See Figure 2. Buried lines must be kept as short as possible to minimize the build up of liquid refrigerant in the vapor line during long periods of shutdown. TRAPS Traps are not required if the piping is properly sized. Traps will only add pressure drop to the system, further reducing capacity INDOOR UNIT ABOVE OUTDOOR UNIT a common problem with the cooling cycle (air conditioning or heat pump) is that the amount of liquid sub-cooling varies as operating conditions change (such as outdoor ambient). Under some conditions, it is possible that flashing will actually occur in the liquid riser. As long as only liquid is present in the liquid riser, the liquid static pressure loss can be calculated at 1/2 psi per foot of rise. However, as soon as flashing starts, the rate of pressure loss increases and continues to increase as the amount of gas increases. For this reason, the restrictions on elevation differences for this configuration must be based on the entire range of operating conditions. When the indoor unit is above the outdoor unit, the pressure loss in the liquid line during the cooling cycle will limit the amount of elevation difference allowed. Since both friction and static head contribute to pressure loss, it can be stated that the elevation difference allowed decreases as the total equivalent line length (horizontal plus vertical) increases. OUTDOOR UNIT ABOVE INDOOR UNIT When the outdoor unit is above the indoor unit, the static pressure gain in the liquid line vertical drop (1/2 psi per foot) may overcome the frictional pressure loss resulting in a total pressure gain. A pressure gain in the liquid line is not detrimental to the performance of the system. On cooling only systems where the outdoor unit is located high above the indoor coil, it may even be possible to reduce the size of the liquid line. The static gain in the vertical drop will offset the increased friction loss caused by smaller tubing. In addition, the reduction in the total system charge due to the smaller liquid line will enhance the reliability of the system. With this configuration, gas velocity in the vapor riser must be kept above 1000 feet per minute for proper oil return and below 3000 feet per minute to avoid noise and vibration problems.