SlideShare a Scribd company logo
1 of 13
C.K. PITHAWALA COLLAGE OF
ENGINEERING AND TECHNOLOGY
DEPARTMENT
OF
MECHANICAL ENGINEERING
A Presentation of Winter Internship
At
J.P.C ENTERPRISES Under SIEMENS
Submitted by
ASHWIN ANIL
Enrolment No. 190093119001
in partial fulfilment for the award of the degree of
BACHELOR OF ENGINEERING
L.P
I.P
H.P
K.O.D
K.O.D
GAS
WELL
BLOCK
DIAGRAM
OF PGC
PGC (Process Gas Compressor)
OVERHAULING OF PT (POWER TURBINE)
What is the purpose of overhauling?
Overhauling of a machine is defined as a process of general maintenance performed on a machine or other industrial equipment.
The goal of overhauling is to keep the system in serviceable condition. Regular checks can prevent all kinds of critical damage.
PROCEDURE OF RT56 PT OVERHAULING
• The overhauling of PT starts with pre-shutdown activities.
• Pre- shutdown parameters like vibration and temperature valves are noted down before
shutting down the system.
• Shutdown by isolation of electrical and instrument systems and also positive isolation of
fuel gas system.
• Draining of fuel gas to the pipelines and positive isolation of fuel gas system.
• Isolation of all the compressor inlet and outlet pipelines.
• Removal of starter shaft along with inlet bullet.
• Removal of all bleed pipelines lube oil supply and drain lines
• Removal of guide vane control system of Gas Generator
• Removal of rim cooling piping’s connected between g,g and p,t
• Removal of g,g inlet bell mouth
• Removal of transiton duct between diffuser and g,g exhaust
• Positioning of g.g lifting tool on g.g
• Removal of g.g and placing it on g.g engine cradle.
• Removal p.t inlet diffuser assembly along with 1st satge stator vanes
• Removal of rim cooling manifold from 1st stage nozzle casing along with honeycomb
retaining ring
• Removal of 1st stage honeycomb seal.
• Removal of 2nd stage stator vanes from 2nd stage nozzle casing.
• Removal of 2nd stage nozzle casing along with2nd stage honeycomb seal.
• Removal of top and bottom coupling guard between gearbox and P.T
• Removal of coupling guard adaptor rings.
• Removal of coupling spacer or torque meter.
• Removal of conduits of vibration probes and speed pickup probes from middle and inner
bearing cover.
• Removal of middle and inner bearing covers.
• Installation of dummy shipping bracket for safety before removing the thrust and
journal bearing.
• Removing all the RTD cables from the bearings.
• Removal of top and bottom thrust bearing housing.
• Removal of thrust bearing which is pad type.
• Removal of coupling end and disc end journal bearing caps.
• Removal of pt hub by hydraulic pump method.
• Removal helical gear and spacer ring from pt shaft.
• Pre dismantling alignment check between pt and gear box.
• Unlocking of lock nut of thrust collar and loosing the
thrust collar
• Installation of pt lifter tool.
• Removal of dummy shipping bracket from bearing casing
from pt tunnel.
• Removal of pt from pt tunnel and placing it on the rotor
stand.
• Cleaning of pt tunnel and all bearing covers.
• Removal of diffuser support from pt tunnel.
• Dimensional inspection of bearing caps and visual
inspection of new pt and inlet diffuser by Third party
inspector.
• Dimensional inspection of diffuser support.
• Assembly of pt rotor tool to new pt rotor and installation
of pt rotor.
• Installation of dummy shipping bearing to pt shaft to hold
the pt shaft.
• Pt seal air is done upto a pressure of 50 psi.
• Installation of new disc end coupling bearing and
coupling cap and also routing the RTD cables of the
bearing to junction box.
• Removal of dummy shipping bracket.
• Installation of 2nd stage nozzle casing,
honeycomb seal and reataining ring.
• Installation of 2ndstage stator vanes.
• Installation of 2nd stage nozzle casing ,
honeycomb seal and retaining ring.
• Assembly of inner outer diffuser and 1st
stage stator vanes.
• TPI of the 1st stage stator vanes to determine
the gap between the vanes is within the limit
or not.
• Installation of new coupling end bearing and
coupling cap and also routing the RTD cables
of the bearing to junction box.
• Installation of diffuser to the 1st stage nozzle
casing.
• Installation of lower thrust bearing housing.
• Installation of thrust bearing pads to the pt
shaft.
• Installation of upper thrust bearing housing.
• Flat check of thrust bearing.
• Installation of all RDT cables and all
vibration probes which is connected to the
junction box.
• Installation of coupling hub to the shaft by
hydraulic pump method.
• Installation of inner and middle bearing
cover.
• Alignment check between gear box hub and
pt hub with alignment tool which may be
fabricated one or a special tool.
• Installation of coupling spacer to torque
meter.
• Installation of outer bearing covers and
coupling guard adaptors to lock coupling
guard.
• Installation of coupling guard.
• Installation of G.G to the enclosure and
starter shaft to the motor which can run at
2500 to 3000 RPM.
• Commissioning is done.
• Which include 72hrs running of pt and
monitoring vibration and temperature
parameters.
INSTRUMENTS USED
 Vibration probes
 Speed pickup probes
 RTD
 Pressure sensors
 Thermocouples
MEASURING INSTRUMENTS
 Vernier caliper
 Depth gauge
 Outside micrometer
 Inside micrometer
 Feller gauge
 Spirit level
PROBLEM FACED
COUPLING HUB REMOVAL
• Couplings are mechanical components used
to connect two in-line shafts to enable one
shaft to drive another at the same speed.
• Hubs that are not provided with a keyway
receive (or transmit) the torque from the
shaft through friction. Hence, the hubs must
grip the shaft tightly. This gripping is
accomplished by advancing the hub on the
tapered shaft a specified amount. To
facilitate this advance one must expand the
hub bore. Two methods are used most often:
heating or hydraulic pressure.
• When hydraulic pressure is used, a few
specialized tools are needed. Basically, they
are installation tools, a high-pressure oil
pump with a pressure gauge, and a low-
pressure pump with a pressure gauge.
• Here we used both hydraulic and heating
methods.
• The problem faced was that the hub was not
removed from the shaft because the oil ring
was damaged it can’t sustain the 28000psi.
The oil is leaking when it reaches the
20000psi. All we had found out was that if
we increase the viscosity of oil we are used
to removing the hub. To increase the
viscosity of oil we mix the oil with grease.
By Increasing the viscosity of oil it blocks
the leakage of oil from the oil ring and by
applying the 28000psi the hub is removed.
CONCLUSION
The internship of duration 12 weeks at NQO ONGC Offshore Mumbai high (India) has helped
me to develop a better understanding about the process gas compressor Machine (PGC) and P.T
overhauling. I have gained technical knowledge regarding PGC machine how it transfer the oil
to MUT line and the Overhauling of P.T. This internship connects the knowledge I learned in the
classroom with real life applications which gives me ultimate experience. My concept regarding
Gas turbine, PGC and PT was not that clear but when I joined the internship then I got to know
what actual scenario is going on in this field with detailed description. This internship has taught
me the importance of managerial and supervisors’ skill and team work in the offshore plant
impossible. This internship has truly been outstanding and benefitted me for the future.

More Related Content

What's hot

Centrifugal compressor head - Impact of MW and other parameters
Centrifugal compressor head - Impact of MW and other parametersCentrifugal compressor head - Impact of MW and other parameters
Centrifugal compressor head - Impact of MW and other parametersSudhindra Tiwari
 
Inline fuel injuction pump
Inline fuel injuction pumpInline fuel injuction pump
Inline fuel injuction pumpJohns Joseph
 
System Components, Hydraulic Oils, Fluid Properties and Filter
System Components, Hydraulic Oils, Fluid Properties and FilterSystem Components, Hydraulic Oils, Fluid Properties and Filter
System Components, Hydraulic Oils, Fluid Properties and FilterRAHUL THAKER
 
Common rail diesel fuel systems
Common rail diesel fuel systemsCommon rail diesel fuel systems
Common rail diesel fuel systemsamged radhi
 
Presentation(Turbocharger)
Presentation(Turbocharger)Presentation(Turbocharger)
Presentation(Turbocharger)Syihab umam
 
Mechanical Seal presentations .pdf
Mechanical Seal presentations .pdfMechanical Seal presentations .pdf
Mechanical Seal presentations .pdfssuser1dde51
 
Unit shutdown procedure operation
Unit shutdown procedure operationUnit shutdown procedure operation
Unit shutdown procedure operationNitin Patel
 
HYDRAULIC CONTROL COMPONENTS.pptx
HYDRAULIC CONTROL COMPONENTS.pptxHYDRAULIC CONTROL COMPONENTS.pptx
HYDRAULIC CONTROL COMPONENTS.pptxHARIBALAJIMECH
 
Pump Maintenance and Troubleshooting
Pump Maintenance and TroubleshootingPump Maintenance and Troubleshooting
Pump Maintenance and TroubleshootingBrian Gongol
 
Scania industrial and marine engines 12 litre engine service repair manual
Scania industrial and marine engines 12 litre engine service repair manualScania industrial and marine engines 12 litre engine service repair manual
Scania industrial and marine engines 12 litre engine service repair manualufsiekdolskek
 
Carburetor Theory
Carburetor TheoryCarburetor Theory
Carburetor TheoryJ.T.A.JONES
 
CENTRIFUGAL PUMP WITH CASE STUDY
CENTRIFUGAL PUMP WITH CASE STUDYCENTRIFUGAL PUMP WITH CASE STUDY
CENTRIFUGAL PUMP WITH CASE STUDYVaibhav Kumar Arya
 
Steam turbine introduction & maintenance ppt
Steam turbine introduction & maintenance pptSteam turbine introduction & maintenance ppt
Steam turbine introduction & maintenance pptBiswajit Mohanty
 
Dry Gas Seal Presentation
Dry Gas Seal PresentationDry Gas Seal Presentation
Dry Gas Seal PresentationIONEL DUTU
 
Basics of IC Engines
Basics of IC EnginesBasics of IC Engines
Basics of IC EnginesJinshah B.S
 

What's hot (20)

U12. sistema de combustible
U12. sistema de combustibleU12. sistema de combustible
U12. sistema de combustible
 
Centrifugal compressor head - Impact of MW and other parameters
Centrifugal compressor head - Impact of MW and other parametersCentrifugal compressor head - Impact of MW and other parameters
Centrifugal compressor head - Impact of MW and other parameters
 
Inline fuel injuction pump
Inline fuel injuction pumpInline fuel injuction pump
Inline fuel injuction pump
 
System Components, Hydraulic Oils, Fluid Properties and Filter
System Components, Hydraulic Oils, Fluid Properties and FilterSystem Components, Hydraulic Oils, Fluid Properties and Filter
System Components, Hydraulic Oils, Fluid Properties and Filter
 
Common rail diesel fuel systems
Common rail diesel fuel systemsCommon rail diesel fuel systems
Common rail diesel fuel systems
 
Presentation(Turbocharger)
Presentation(Turbocharger)Presentation(Turbocharger)
Presentation(Turbocharger)
 
Mechanical Seal presentations .pdf
Mechanical Seal presentations .pdfMechanical Seal presentations .pdf
Mechanical Seal presentations .pdf
 
Unit shutdown procedure operation
Unit shutdown procedure operationUnit shutdown procedure operation
Unit shutdown procedure operation
 
HYDRAULIC CONTROL COMPONENTS.pptx
HYDRAULIC CONTROL COMPONENTS.pptxHYDRAULIC CONTROL COMPONENTS.pptx
HYDRAULIC CONTROL COMPONENTS.pptx
 
Pump Maintenance and Troubleshooting
Pump Maintenance and TroubleshootingPump Maintenance and Troubleshooting
Pump Maintenance and Troubleshooting
 
Scania industrial and marine engines 12 litre engine service repair manual
Scania industrial and marine engines 12 litre engine service repair manualScania industrial and marine engines 12 litre engine service repair manual
Scania industrial and marine engines 12 litre engine service repair manual
 
Ci
CiCi
Ci
 
Carburetor Theory
Carburetor TheoryCarburetor Theory
Carburetor Theory
 
Supercharger vs turbocharger
Supercharger vs turbochargerSupercharger vs turbocharger
Supercharger vs turbocharger
 
Centrifugal compressor
Centrifugal compressor Centrifugal compressor
Centrifugal compressor
 
CENTRIFUGAL PUMP WITH CASE STUDY
CENTRIFUGAL PUMP WITH CASE STUDYCENTRIFUGAL PUMP WITH CASE STUDY
CENTRIFUGAL PUMP WITH CASE STUDY
 
Steam turbine introduction & maintenance ppt
Steam turbine introduction & maintenance pptSteam turbine introduction & maintenance ppt
Steam turbine introduction & maintenance ppt
 
Dry Gas Seal Presentation
Dry Gas Seal PresentationDry Gas Seal Presentation
Dry Gas Seal Presentation
 
Steam turbine basics
Steam turbine basicsSteam turbine basics
Steam turbine basics
 
Basics of IC Engines
Basics of IC EnginesBasics of IC Engines
Basics of IC Engines
 

Similar to PROCESS GAS COMPRESSOR AND PT OVERHAULING

Report steffones
Report steffonesReport steffones
Report steffonesSteffones K
 
Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trialNagesh H
 
compressor Operation pdf.pdf
compressor Operation pdf.pdfcompressor Operation pdf.pdf
compressor Operation pdf.pdfyusuf699644
 
Compressor operation.pdf
Compressor operation.pdfCompressor operation.pdf
Compressor operation.pdfMBouderbala
 
Fuel gas system of gas production
Fuel gas system of gas productionFuel gas system of gas production
Fuel gas system of gas productionPhyoe Maung Maung
 
15 intake and exhaust
15 intake and exhaust15 intake and exhaust
15 intake and exhaustRuan Moura
 
Condensate Return Solutions.ppt
Condensate Return Solutions.pptCondensate Return Solutions.ppt
Condensate Return Solutions.pptssuser8006c7
 
Inplant training report
Inplant training reportInplant training report
Inplant training reportapplesam8
 
1999 TOYOTA COROLLA Service Repair Manual
1999 TOYOTA COROLLA Service Repair Manual1999 TOYOTA COROLLA Service Repair Manual
1999 TOYOTA COROLLA Service Repair Manualjksmemd eudkmmd
 
1998 toyota corolla service repair manual
1998 toyota corolla service repair manual1998 toyota corolla service repair manual
1998 toyota corolla service repair manualfujjsekfkksekm
 
2002 toyota corolla service repair manual
2002 toyota corolla service repair manual2002 toyota corolla service repair manual
2002 toyota corolla service repair manualjknsmmem
 
2000 toyota corolla service repair manual
2000 toyota corolla service repair manual2000 toyota corolla service repair manual
2000 toyota corolla service repair manualjkmsedopl
 
1999 toyota corolla service repair manual
1999 toyota corolla service repair manual1999 toyota corolla service repair manual
1999 toyota corolla service repair manualfujjsefkksemmm
 
2002 TOYOTA COROLLA Service Repair Manual
2002 TOYOTA COROLLA Service Repair Manual2002 TOYOTA COROLLA Service Repair Manual
2002 TOYOTA COROLLA Service Repair Manualjnsekmdmm
 
1999 toyota corolla service repair manual
1999 toyota corolla service repair manual1999 toyota corolla service repair manual
1999 toyota corolla service repair manualfujsejfkskemem
 
2001 toyota corolla service repair manual
2001 toyota corolla service repair manual2001 toyota corolla service repair manual
2001 toyota corolla service repair manualjksnmdms
 
2001 TOYOTA COROLLA Service Repair Manual
2001 TOYOTA COROLLA Service Repair Manual2001 TOYOTA COROLLA Service Repair Manual
2001 TOYOTA COROLLA Service Repair Manualjkndhjsnhd
 
Appraisal ppt ankur
Appraisal ppt ankurAppraisal ppt ankur
Appraisal ppt ankurAnkur Mishra
 
171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.pptssuser9e9be71
 

Similar to PROCESS GAS COMPRESSOR AND PT OVERHAULING (20)

Report steffones
Report steffonesReport steffones
Report steffones
 
Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trial
 
compressor Operation pdf.pdf
compressor Operation pdf.pdfcompressor Operation pdf.pdf
compressor Operation pdf.pdf
 
Compressor operation.pdf
Compressor operation.pdfCompressor operation.pdf
Compressor operation.pdf
 
Fuel gas system of gas production
Fuel gas system of gas productionFuel gas system of gas production
Fuel gas system of gas production
 
15 intake and exhaust
15 intake and exhaust15 intake and exhaust
15 intake and exhaust
 
Condensate Return Solutions.ppt
Condensate Return Solutions.pptCondensate Return Solutions.ppt
Condensate Return Solutions.ppt
 
Inplant training report
Inplant training reportInplant training report
Inplant training report
 
1999 TOYOTA COROLLA Service Repair Manual
1999 TOYOTA COROLLA Service Repair Manual1999 TOYOTA COROLLA Service Repair Manual
1999 TOYOTA COROLLA Service Repair Manual
 
1998 toyota corolla service repair manual
1998 toyota corolla service repair manual1998 toyota corolla service repair manual
1998 toyota corolla service repair manual
 
2002 toyota corolla service repair manual
2002 toyota corolla service repair manual2002 toyota corolla service repair manual
2002 toyota corolla service repair manual
 
2000 toyota corolla service repair manual
2000 toyota corolla service repair manual2000 toyota corolla service repair manual
2000 toyota corolla service repair manual
 
1999 toyota corolla service repair manual
1999 toyota corolla service repair manual1999 toyota corolla service repair manual
1999 toyota corolla service repair manual
 
2002 TOYOTA COROLLA Service Repair Manual
2002 TOYOTA COROLLA Service Repair Manual2002 TOYOTA COROLLA Service Repair Manual
2002 TOYOTA COROLLA Service Repair Manual
 
1999 toyota corolla service repair manual
1999 toyota corolla service repair manual1999 toyota corolla service repair manual
1999 toyota corolla service repair manual
 
2001 toyota corolla service repair manual
2001 toyota corolla service repair manual2001 toyota corolla service repair manual
2001 toyota corolla service repair manual
 
2001 TOYOTA COROLLA Service Repair Manual
2001 TOYOTA COROLLA Service Repair Manual2001 TOYOTA COROLLA Service Repair Manual
2001 TOYOTA COROLLA Service Repair Manual
 
Fmp 8000 manual
Fmp 8000 manualFmp 8000 manual
Fmp 8000 manual
 
Appraisal ppt ankur
Appraisal ppt ankurAppraisal ppt ankur
Appraisal ppt ankur
 
171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt
 

More from ASHWIN A

BAT KNOCKING MACHINE PART 2
BAT KNOCKING MACHINE PART 2BAT KNOCKING MACHINE PART 2
BAT KNOCKING MACHINE PART 2ASHWIN A
 
OB STRUCTURE & GROUP DYNAMICS
OB STRUCTURE & GROUP DYNAMICSOB STRUCTURE & GROUP DYNAMICS
OB STRUCTURE & GROUP DYNAMICSASHWIN A
 
ORGANIZATIONAL BEHAVIOUR
ORGANIZATIONAL BEHAVIOURORGANIZATIONAL BEHAVIOUR
ORGANIZATIONAL BEHAVIOURASHWIN A
 
Automatic bat knocking machine ppt
Automatic bat knocking machine pptAutomatic bat knocking machine ppt
Automatic bat knocking machine pptASHWIN A
 
Candu reactor ppt
Candu reactor pptCandu reactor ppt
Candu reactor pptASHWIN A
 

More from ASHWIN A (6)

BAT KNOCKING MACHINE PART 2
BAT KNOCKING MACHINE PART 2BAT KNOCKING MACHINE PART 2
BAT KNOCKING MACHINE PART 2
 
Drone ppt
Drone pptDrone ppt
Drone ppt
 
OB STRUCTURE & GROUP DYNAMICS
OB STRUCTURE & GROUP DYNAMICSOB STRUCTURE & GROUP DYNAMICS
OB STRUCTURE & GROUP DYNAMICS
 
ORGANIZATIONAL BEHAVIOUR
ORGANIZATIONAL BEHAVIOURORGANIZATIONAL BEHAVIOUR
ORGANIZATIONAL BEHAVIOUR
 
Automatic bat knocking machine ppt
Automatic bat knocking machine pptAutomatic bat knocking machine ppt
Automatic bat knocking machine ppt
 
Candu reactor ppt
Candu reactor pptCandu reactor ppt
Candu reactor ppt
 

Recently uploaded

UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 

Recently uploaded (20)

UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 

PROCESS GAS COMPRESSOR AND PT OVERHAULING

  • 1. C.K. PITHAWALA COLLAGE OF ENGINEERING AND TECHNOLOGY DEPARTMENT OF MECHANICAL ENGINEERING A Presentation of Winter Internship At J.P.C ENTERPRISES Under SIEMENS Submitted by ASHWIN ANIL Enrolment No. 190093119001 in partial fulfilment for the award of the degree of BACHELOR OF ENGINEERING
  • 3. OVERHAULING OF PT (POWER TURBINE) What is the purpose of overhauling? Overhauling of a machine is defined as a process of general maintenance performed on a machine or other industrial equipment. The goal of overhauling is to keep the system in serviceable condition. Regular checks can prevent all kinds of critical damage. PROCEDURE OF RT56 PT OVERHAULING • The overhauling of PT starts with pre-shutdown activities. • Pre- shutdown parameters like vibration and temperature valves are noted down before shutting down the system. • Shutdown by isolation of electrical and instrument systems and also positive isolation of fuel gas system. • Draining of fuel gas to the pipelines and positive isolation of fuel gas system. • Isolation of all the compressor inlet and outlet pipelines.
  • 4. • Removal of starter shaft along with inlet bullet. • Removal of all bleed pipelines lube oil supply and drain lines • Removal of guide vane control system of Gas Generator • Removal of rim cooling piping’s connected between g,g and p,t • Removal of g,g inlet bell mouth • Removal of transiton duct between diffuser and g,g exhaust • Positioning of g.g lifting tool on g.g • Removal of g.g and placing it on g.g engine cradle. • Removal p.t inlet diffuser assembly along with 1st satge stator vanes • Removal of rim cooling manifold from 1st stage nozzle casing along with honeycomb retaining ring • Removal of 1st stage honeycomb seal. • Removal of 2nd stage stator vanes from 2nd stage nozzle casing. • Removal of 2nd stage nozzle casing along with2nd stage honeycomb seal.
  • 5. • Removal of top and bottom coupling guard between gearbox and P.T • Removal of coupling guard adaptor rings. • Removal of coupling spacer or torque meter. • Removal of conduits of vibration probes and speed pickup probes from middle and inner bearing cover. • Removal of middle and inner bearing covers. • Installation of dummy shipping bracket for safety before removing the thrust and journal bearing. • Removing all the RTD cables from the bearings. • Removal of top and bottom thrust bearing housing. • Removal of thrust bearing which is pad type. • Removal of coupling end and disc end journal bearing caps. • Removal of pt hub by hydraulic pump method.
  • 6. • Removal helical gear and spacer ring from pt shaft. • Pre dismantling alignment check between pt and gear box. • Unlocking of lock nut of thrust collar and loosing the thrust collar • Installation of pt lifter tool. • Removal of dummy shipping bracket from bearing casing from pt tunnel. • Removal of pt from pt tunnel and placing it on the rotor stand. • Cleaning of pt tunnel and all bearing covers. • Removal of diffuser support from pt tunnel. • Dimensional inspection of bearing caps and visual inspection of new pt and inlet diffuser by Third party inspector. • Dimensional inspection of diffuser support. • Assembly of pt rotor tool to new pt rotor and installation of pt rotor. • Installation of dummy shipping bearing to pt shaft to hold the pt shaft. • Pt seal air is done upto a pressure of 50 psi. • Installation of new disc end coupling bearing and coupling cap and also routing the RTD cables of the bearing to junction box.
  • 7. • Removal of dummy shipping bracket. • Installation of 2nd stage nozzle casing, honeycomb seal and reataining ring. • Installation of 2ndstage stator vanes. • Installation of 2nd stage nozzle casing , honeycomb seal and retaining ring. • Assembly of inner outer diffuser and 1st stage stator vanes. • TPI of the 1st stage stator vanes to determine the gap between the vanes is within the limit or not. • Installation of new coupling end bearing and coupling cap and also routing the RTD cables of the bearing to junction box. • Installation of diffuser to the 1st stage nozzle casing.
  • 8. • Installation of lower thrust bearing housing. • Installation of thrust bearing pads to the pt shaft. • Installation of upper thrust bearing housing. • Flat check of thrust bearing. • Installation of all RDT cables and all vibration probes which is connected to the junction box. • Installation of coupling hub to the shaft by hydraulic pump method. • Installation of inner and middle bearing cover.
  • 9. • Alignment check between gear box hub and pt hub with alignment tool which may be fabricated one or a special tool. • Installation of coupling spacer to torque meter. • Installation of outer bearing covers and coupling guard adaptors to lock coupling guard. • Installation of coupling guard. • Installation of G.G to the enclosure and starter shaft to the motor which can run at 2500 to 3000 RPM. • Commissioning is done. • Which include 72hrs running of pt and monitoring vibration and temperature parameters.
  • 10. INSTRUMENTS USED  Vibration probes  Speed pickup probes  RTD  Pressure sensors  Thermocouples MEASURING INSTRUMENTS  Vernier caliper  Depth gauge  Outside micrometer  Inside micrometer  Feller gauge  Spirit level
  • 11. PROBLEM FACED COUPLING HUB REMOVAL • Couplings are mechanical components used to connect two in-line shafts to enable one shaft to drive another at the same speed. • Hubs that are not provided with a keyway receive (or transmit) the torque from the shaft through friction. Hence, the hubs must grip the shaft tightly. This gripping is accomplished by advancing the hub on the tapered shaft a specified amount. To facilitate this advance one must expand the hub bore. Two methods are used most often: heating or hydraulic pressure. • When hydraulic pressure is used, a few specialized tools are needed. Basically, they are installation tools, a high-pressure oil pump with a pressure gauge, and a low- pressure pump with a pressure gauge.
  • 12. • Here we used both hydraulic and heating methods. • The problem faced was that the hub was not removed from the shaft because the oil ring was damaged it can’t sustain the 28000psi. The oil is leaking when it reaches the 20000psi. All we had found out was that if we increase the viscosity of oil we are used to removing the hub. To increase the viscosity of oil we mix the oil with grease. By Increasing the viscosity of oil it blocks the leakage of oil from the oil ring and by applying the 28000psi the hub is removed.
  • 13. CONCLUSION The internship of duration 12 weeks at NQO ONGC Offshore Mumbai high (India) has helped me to develop a better understanding about the process gas compressor Machine (PGC) and P.T overhauling. I have gained technical knowledge regarding PGC machine how it transfer the oil to MUT line and the Overhauling of P.T. This internship connects the knowledge I learned in the classroom with real life applications which gives me ultimate experience. My concept regarding Gas turbine, PGC and PT was not that clear but when I joined the internship then I got to know what actual scenario is going on in this field with detailed description. This internship has taught me the importance of managerial and supervisors’ skill and team work in the offshore plant impossible. This internship has truly been outstanding and benefitted me for the future.