SlideShare a Scribd company logo
1 of 91
MIQA, An Ultimate Element of PSM
Implementation
AIM of process Safety Management
PSM Objectives
What’s MIQA , An Ultimate Element of PSM
Why Reliability of Static Equipment Important ?
Real Root Causes of Poor Reliability of Static Equipment
Global Scenario of Static Equipment
:”Wake up Call” to Operators of Ageing Petroleum Industries
MIQA in Ageing Assets : A Global Challenging Problem
Way forward to MIQA in Ageing Plants
Why MIQA (AIM/RBI) fail and how to get success
AIM of Process Safety Management
Develop plant’s systems & procedures to
prevent unwanted releases of spills &
emissions, which may ignite and cause
disaster of toxic impacts, local fires, or
explosions in plants - affecting people,
nearby Communities , Environment &
Image of Company
Flixoborogh, 1 June 1974
Additional facility built in 1972 for the
production of Cyclohexanone
•Used to produce Caprolactum intermediate
for the manufacture of nylon
• Section 25A involved oxidation of
cyclohexane at 8.8 Barg / 155°C
• The reaction was carried out in six liquid
phase reactors
•Each reactor was set 14” lower than the
previous to allow the liquid to flow under
gravity through the reaction train.
• March 27th 1974, a crack developed in
reactor number 5. The maintenance engineer
recommended shutdown for 3 weeks for
repair
Flixoborogh, 1 June 1974
 Proactive identification, evaluation and
mitigation of chemical releases that could
occur as a result of failures of processes,
procedures or equipment.
 Proactive control of the consequences of
catastrophic releases of highly hazardous
chemicals from a process.
PSM Objectives :
Out of 14 PSM Elements, MIQA is Ultimate for Process Safety
MIQA shall ensures 360⁰ Integrity
of equipment starts from inception of
its Design , Construction, Startups,
Commissioning , Operation, Turnaround
till Decommissioning, to prevent out of
containment of hazardous liquid & gases
from its pressure boundary
 Pressure Vessels and Storage tanks
 Piping systems including all components
 Relief & Vent systems and associated devices
 Safety Instrumented Systems (SISs) and Emergency
Shutdown (ESD) systems - Process control systems -
Controls system including monitoring devices and
sensors, critical alarms and interlocks.
 Rotary equipment
 Electrical equipment
Equipment Under MIQA
Identification and documentation of PSM critical equipment
MIQA Implementer Team
PSM critical equipment review
Quality Assurance of New Equipment
Maintenance, Inspection And Testing of Equipment
Repairs and Changes
Maintenance Procedures /schedule
Maintenance training
Quality Control of Maintenance, Repair and Operation (MRO) Materials and Spares
Reliability Engineering
Predictive Maintenance Program
Documentation
MIQA PROCEDURE
Ageing is the main cause of poor reliability of Static Assets
MIQA
VISUALIZING
RISKS & OPPORTUNITIES
IN AGEING ASSETS
Why Do
Equipment Age & Fail
in Petroleum
Industries
What’s Ageing & What are Aged Equipment ?
 Ageing is not by no. of years equipment passed
but by its present condition
 Aged Asset that outlived its useful life and may
include the equipment still functional but
expensive to operate/maintain, still works but
breakdown frequently disrupting operation or
equipment that broken and it is too expensive to
repair
Ageing Assets, a serious concern in petroleum industries for its sustenance
Broadly due to
poor design/construction and
In-service corrosion/ metallurgical
degradation due to poor
maintenance / mal-operation
Leading to Over ageing & premature
failure in catastrophic manner
Causes of Design Deficiencies
 No consideration of Geographical features & types
of crude processing while setting up refinery
 Poor knowledge & experience of designer for
selecting material, its degradation & protection
 Poor knowledge of NDT technologies, its selection
and practicality
 Economical Metallurgy due to limited budget
Off Spec. Materials
Noncompliance in
 METALLURGY
 Heat Treatment Condition
 Forming Method
 Dimensions & geometry
 Poor packing & dispatch
Metallurgy Mismatch
 P9 material in place of P91 resulted catastrophe just
after commissioning
 Carbon steel in place of Alloy steels
 SS 304H in Place of SS 304L & vice versa
 SA 516 Gr70 in place of SA 516 Gr60 in NACE & Caustic
Service
 Ordinary Brass in place of Ar stabilized Admiralty Brass
 SS 304 piping in place of SS 321
Heat Treatment Condition
 No Stabilization Treatment of Stabilized Grade SS 347 &
321 after welding leading to Chloride & Polythionic SCC.
 No PWHT of CS equipment after welding in caustic,
Amine, LPG, sodium carbonate & hydrogen Service causing
catastrophe due to SCC
 Failure of Admiralty brass U tube bundle in lube oil cooler
due to no solution annealing of tubes after bending
Use of SA191 Grade B7 studs in place of Grade B7M in
NACE H2S service
Dimension & Geometry/ Slope
Thinning of Elbow at Crown portion
 Undersize fillet welding in place of
Full Penetration welds
Out of roundness & Verticality in
Storage tanks
Poor Workmanship During Construction
 Welding by helpers / unqualified personnel
 Short Bolting
 Reverse Slope of pipelines causing inefficient
drainage
 Gas Cutting in place of Drilling for holes
 Box up Equipment with foreign materials
 Gas / Grinding Cutting of SS in place of Plasma
Construction Lapses
Poor workmanship & Nonstandard procedures
 Mismatch in Filler Wire.
 Improper baking of electrode / no or improper purging
 Metallurgy mix up.
 Non compliance of welding Procedure & repetitive repairs
 Manipulation in NDT & PWHT.
 Box up of Equipment With Foreign Materials
 No Dewatering & Dry up after Hydro Testing
 Poor Insulation: Aluminium clad on high temperature ASS lines.
 Poor Refractory Application & Dry out
Construction Lapses
Poor workmanship & Nonstandard procedures
 Poor application of coating & lining
 No Passivation & long idling without Preservation
 Use of Poor Quality water in hydro testing
 No PWHT ( Stabilization) in SS 321/347
 No SR of CS equipment in Amine, Caustic, LPG, H₂ service
 No RT after PWHT
 RT interpretation noncompliance with design need
 PWHT cycle problem in P91 & P92 dissimilar material.
 Poor control of welding parameters in Duplex & P91/P92.
 Lack of experience /poor qualification of QA/QC inspectors
Poor Start-Up & Commissioning Damages
Maximum damage in the life of a plant occurs
at start up Due to over run of operating
parameter and the remnant effect of this
damage may affect the design life significantly.
A step by step procedure if followed strictly
can give a safe and risk free plant start up & in-
turn smooth operation , longer run-length &
expected safer design life in future.
Post Commissioning Mal-Operation- No IOW
 Poor Control of Operating Parameters
 Long idling without proper preservation
 Inefficacy of dosing system for corrosion control.
 Running equipment beyond design parameters: No IOW
 Processing High TAN crude with low metallurgy
 Processing High NAN Crude with inadequate Metallurgy
 Running the equipment in leaky condition
Frequent Steam & Power Failures
 Thermal fatigue, Thermal Shocks Causing metallurgical
degradation due to thermo-mechanical Stress in High
Temperature Equipment.
 Accelerate corrosion due to stoppage of pumps causing
condensation of acidic gases in overhead circuit leading
to dew point corrosion at each event.
 Starvation of water in PG boilers leading to creep
failure .
Capacity Utilization Beyond Design
 Refiners running the plant as high as 120% to 140%
of its design just for greed of getting production or
breaking the previous bench mark records of
production causing high velocities of streams & high
temperature leading to erosion corrosion, fatigue &
creep damages.
 Change of crude (Opportunity crude) without
metallurgy up-gradation due to international market
drive & availability leading to faster rate of corrosion.
Frequent change of Inspectors
 Poor inspection recommendation
 Poor documentation.
 Lack of proactive skill & confidence In
Decision Making
 All above lead to confusion & chaos in
turn poor reliability.
No Company Owned Standards & Practices
Nonstandard norms & practices of Inspection &
Maintenance result
Repetitive failure
More Maintenance & Inspection cost
Poor Reliability of Equipment
No in-house talent & expertise development
More dependency & panic at time of resigning
Confusion, chaos & delay in jobs
Impact of Ageing on MIQA
 Increased Unpredictable Failures & catastrophes
 More Unsafe situation & fatal
 Pressure from Regulators
 More repair & more maintenance cost
 Poor run length & On-stream Service factor
 Need more Inspection with Advance NDT & Heavy
Replacement for Life Extension.
As per the current industry climate, pipelines
may cost up to $ 3 million per km to replace
for prolonging the lifetime of infrastructure and
avoiding preventable damage is extremely
valuable to operators.
Ageing Pipelines & Replacement Cost
4 million KM Ageing Pipelines replacement in USA
shall cost $12000 billion which can break the
backbone of most developed economy of world
With the safety of personnel being a top
priority across the entire global industry,
operators must ensure they have robust
monitoring and inspection regimes, corrosion
monitoring techniques, risk assessments and
active maintenance programs in place to
safeguard against risk.
Life Extension of Ageing Assets
Continued operation of ageing assets,
through RLA & Life Extension Plans
Creating opportunities to lower costs and
increased profits for sustenance, but
need wisdom & expertize.
As the industry seeks to increase the economic life
of assets, many will remain in operation longer
than anticipated. Some oil and gas assets have
 Current condition assessment
 Life extension evaluation and GAP analysis
 Technical qualification for life extension
 Obsolescence preparedness
 Life extension costs and plans
Five-step approach for Life Extension
 Assess history & present status
 Detect symptoms of ageing
 Examine options: e.g. continued service, re-rating, repair, scrapping
 Use risk-based approach to identify critical systems and equipment
 Life extension evaluation and GAP analysis
 Determine modifications required
 Perform technical qualification to operate structures & equipment
beyond original design life
 Obsolescence preparedness
 Elongated term cost prediction
What we do in Life Extension?
AIMS outline the ability of an asset to perform its
required function effectively and efficiently
whilst protecting health, safety & environment
and the means of ensuring that the people,
systems, processes, and resources that deliver
integrity are in place, in use and will perform
when required over the whole lifecycle of the
asset
What’s AIM
An Integrity Management System should address the
quality at every stage of the asset life cycle, from the
design of new facilities to maintenance management to
decommissioning. Inspections, auditing/assurance and
overall quality processes are just some of the tools
designed to make an AIMS effective
The AIMS should also endeavor to maintain the asset in a
fit-for-service condition while extending its remaining life
in the most reliable, safe, and cost-effective manner. The
AIM programs (in the US) attempt to meet API-580, API-
581, and PAS 55 requirements, as applicable.
MIQA in Ageing Assets : A global Challenge
Ageing Assets : Predict, control , Monitor & Mitigate Complex Corrosion & Metallurgical Degradation
MIQA in Ageing Assets : A Global Challenge for PSM
Management of Ageing Assets: Need Top driven Reliability
Culture & In-house Team Expertise
Proactive Detection, Dynamic Risk Analysis and Timely Action for avoiding Catastrophes
Management of Ageing Assets: A Complex Problem
Corrosion is Cancerous disease to Industries
Specially Oil & Gas which can kill the total
economy of a company or country.
Are you aware of this fact ?
Replacement of Ageing Assets can break the
backbone of even most developed World
economy and life enhancement is the only
option to sustain.
MIQA in Ageing Assets & Cost Reduction
Arbitrary Cost Reduction : Increasing Risk of Replacing the Facility for sustenance
MIQA in Ageing Asset & Cost Reduction
Arbitrarily cutting skilled head counts
Increasing Risk to sustenance due to Poor Monitoring & Maintenance
MIQA in Ageing Assets :A Global Challenge for PSM
Way forward to Reliability of Ageing Assets
MIQA in Ageing Assets & Cost Reduction
Reducing Inspection Budget Arbitrarily : Increasing Risk to Sustenance
Risk Assessment Through RBI & FFS Technologies for
achieving Reliability of static assets, is the key to
survival for Ageing Petroleum Industries
Both Technologies are Complementary, Stands alone
separately but meet together in Crisis
MIQA & Management of Ageing Assets
World over, No break through yet for both RBI/FFS due to
lack of expertise , high complexity and poor culture
A New Way to Use RBI - The Long Play
While RBI will continue to be used in the short term to defer
inspections, its real power lies in its ability to create a long
term plan. Have you thought about using it for the long term?
the term "RBI it away" as in completing an RBI assessment to
make an overdue inspection disappear. These people are very
short sighted in their views of RBI's capabilities. RBI is a
powerful equipment life-cycle tool that can predict damage out
into the future, and the API codes allow you to take full
advantage of this technology.
Ageing Assets : A threat to sustenance , Environment & Human Life
MIQA in Ageing Assets : A Global Challenge for PSM
MIQA in Ageing Assets : A Global Challenge for PSM
Way Forward to Reliability: Life Time Integrated Integrity of Entire Plant
High Temperature Sulfidation
Ф8” 52” length piece u/s bend
Low Silicon CS
Tesoro Refinery, 2 Apr
2010, six fatalities
Thinning & Over pressurization
Importance of Reliability Culture
Importance of Reliability Culture
For long term survival, take significant management energy as well as strong commitment from all levels
Proactive Culture through MIQA, MOC & IOW Implementation
MIQA in Ageing Assets : A Global Challenge for
PSMGood Asset Integrity Management balances Design Integrity , Operating Integrity and Technical
Integrity in the most cost effective and productive way starting from plant design to end of life
 MIQA , most important Element of Process Safety Management and is ultimate to
prevent Out of containment of hydrocarbon or toxic liquid and gases avoiding fire ,
explosion and catastrophes by ensuring the mechanical integrity of assets at every
stage starting from inception of design to start up during construction and then
commissioning to and then during operation , break downs , turn around till
decommissioning.
 Global statistic of petroleum industries estimated 80 % static assets consisting mainly
pipelines, plant piping, pressure vessels and safety valves in refineries and
petrochemicals are aged either due to expiry or due to poor condition. These assets
are still productive but having lot of uncertainty for reliability and frequently failing
resulting catastrophes and explosion. Replacement of these assets is not feasible due
to high cost & time constraint. Life enhancement is the only option . MIQA needs top
driven proactive reliability culture , In-house technical expertize and operational
discipline along with time and funding.
Conclusion
MIQA, An Ultimate Element of PSM Implementation

More Related Content

What's hot

Process Safety
Process SafetyProcess Safety
Process SafetyConsultivo
 
SPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT SlidesSPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT Slidesidell bryan
 
Hazop Fundamentals Online Training iFluids
Hazop Fundamentals Online Training iFluidsHazop Fundamentals Online Training iFluids
Hazop Fundamentals Online Training iFluidsJohn Kingsley
 
Asset Integrity Management
Asset Integrity Management Asset Integrity Management
Asset Integrity Management Advisian
 
Safety in the oil and gas industry
Safety in the oil and gas industrySafety in the oil and gas industry
Safety in the oil and gas industryMegCario
 
Risk Assessment At Tank- Truck Unloading Section Of LPG Bottling Plant I Gaur...
Risk Assessment At Tank- Truck Unloading Section Of LPG Bottling Plant I Gaur...Risk Assessment At Tank- Truck Unloading Section Of LPG Bottling Plant I Gaur...
Risk Assessment At Tank- Truck Unloading Section Of LPG Bottling Plant I Gaur...Gaurav Singh Rajput
 
Work Permit System
Work Permit SystemWork Permit System
Work Permit SystemGagan Tanwar
 
Shutdown Turnaround and Outage Competency Improvement Program
Shutdown Turnaround and Outage Competency Improvement ProgramShutdown Turnaround and Outage Competency Improvement Program
Shutdown Turnaround and Outage Competency Improvement ProgramLife Cycle Engineering
 
PSM Process Safety Management.pdf
PSM Process Safety Management.pdfPSM Process Safety Management.pdf
PSM Process Safety Management.pdfssuser2fc67e
 
Bow Tie Risk Analysis
Bow Tie Risk AnalysisBow Tie Risk Analysis
Bow Tie Risk AnalysisJohn Kingsley
 
Hazard and Operability Study (HAZOP) | Gaurav Singh Rajput
Hazard and Operability Study (HAZOP) | Gaurav Singh RajputHazard and Operability Study (HAZOP) | Gaurav Singh Rajput
Hazard and Operability Study (HAZOP) | Gaurav Singh RajputGaurav Singh Rajput
 
Process Plant Start Up and Commissioning
Process Plant Start Up and CommissioningProcess Plant Start Up and Commissioning
Process Plant Start Up and CommissioningpetroEDGE
 
Process Safety Management Fundamentals.pptx
Process Safety Management Fundamentals.pptxProcess Safety Management Fundamentals.pptx
Process Safety Management Fundamentals.pptxImtiazHussain312057
 
SAFE HANDING OVER OF EQUIPMENTS.pptx
SAFE HANDING OVER OF EQUIPMENTS.pptxSAFE HANDING OVER OF EQUIPMENTS.pptx
SAFE HANDING OVER OF EQUIPMENTS.pptxJOMON M.C
 

What's hot (20)

Pickling & Passivation
Pickling & PassivationPickling & Passivation
Pickling & Passivation
 
Process Safety
Process SafetyProcess Safety
Process Safety
 
SPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT SlidesSPE Process Safety Workshop PPT Slides
SPE Process Safety Workshop PPT Slides
 
Hazop Fundamentals Online Training iFluids
Hazop Fundamentals Online Training iFluidsHazop Fundamentals Online Training iFluids
Hazop Fundamentals Online Training iFluids
 
Asset Integrity Management
Asset Integrity Management Asset Integrity Management
Asset Integrity Management
 
Safety in the oil and gas industry
Safety in the oil and gas industrySafety in the oil and gas industry
Safety in the oil and gas industry
 
Risk Assessment At Tank- Truck Unloading Section Of LPG Bottling Plant I Gaur...
Risk Assessment At Tank- Truck Unloading Section Of LPG Bottling Plant I Gaur...Risk Assessment At Tank- Truck Unloading Section Of LPG Bottling Plant I Gaur...
Risk Assessment At Tank- Truck Unloading Section Of LPG Bottling Plant I Gaur...
 
Work Permit System
Work Permit SystemWork Permit System
Work Permit System
 
Shutdown Turnaround and Outage Competency Improvement Program
Shutdown Turnaround and Outage Competency Improvement ProgramShutdown Turnaround and Outage Competency Improvement Program
Shutdown Turnaround and Outage Competency Improvement Program
 
management of change
management of changemanagement of change
management of change
 
PSM Process Safety Management.pdf
PSM Process Safety Management.pdfPSM Process Safety Management.pdf
PSM Process Safety Management.pdf
 
Bow Tie Risk Analysis
Bow Tie Risk AnalysisBow Tie Risk Analysis
Bow Tie Risk Analysis
 
14 Tips for Process Safety Management
14 Tips for Process Safety Management14 Tips for Process Safety Management
14 Tips for Process Safety Management
 
Hazard and Operability Study (HAZOP) | Gaurav Singh Rajput
Hazard and Operability Study (HAZOP) | Gaurav Singh RajputHazard and Operability Study (HAZOP) | Gaurav Singh Rajput
Hazard and Operability Study (HAZOP) | Gaurav Singh Rajput
 
Safety in chlorine ppt
Safety in chlorine pptSafety in chlorine ppt
Safety in chlorine ppt
 
Process Plant Start Up and Commissioning
Process Plant Start Up and CommissioningProcess Plant Start Up and Commissioning
Process Plant Start Up and Commissioning
 
Process Safety Management Fundamentals.pptx
Process Safety Management Fundamentals.pptxProcess Safety Management Fundamentals.pptx
Process Safety Management Fundamentals.pptx
 
SAFE HANDING OVER OF EQUIPMENTS.pptx
SAFE HANDING OVER OF EQUIPMENTS.pptxSAFE HANDING OVER OF EQUIPMENTS.pptx
SAFE HANDING OVER OF EQUIPMENTS.pptx
 
Permit to Work Training
Permit to Work TrainingPermit to Work Training
Permit to Work Training
 
Storage Tank Safety
Storage Tank SafetyStorage Tank Safety
Storage Tank Safety
 

Similar to MIQA, An Ultimate Element of PSM Implementation

OH&S Audit Report- JSW Nandyal.doc
OH&S Audit Report- JSW Nandyal.docOH&S Audit Report- JSW Nandyal.doc
OH&S Audit Report- JSW Nandyal.docMirza Saifullah Baig
 
QA-QC ENGINEER
QA-QC ENGINEERQA-QC ENGINEER
QA-QC ENGINEERnader rizq
 
OCS Training - API 570 piping inspection course
OCS Training - API 570 piping inspection courseOCS Training - API 570 piping inspection course
OCS Training - API 570 piping inspection courseMuanisa Waras
 
Casting manufacturing process improvement
Casting manufacturing process improvementCasting manufacturing process improvement
Casting manufacturing process improvementAbdullah Ansari
 
Avoiding Stress Corrosion Cracking of Carbon Low Alloy and Austenitic Stainl...
Avoiding Stress Corrosion Cracking of  Carbon Low Alloy and Austenitic Stainl...Avoiding Stress Corrosion Cracking of  Carbon Low Alloy and Austenitic Stainl...
Avoiding Stress Corrosion Cracking of Carbon Low Alloy and Austenitic Stainl...Gerard B. Hawkins
 
Ahmed Ismail (Sr. Welding & Piping) LAST
Ahmed Ismail (Sr. Welding & Piping) LASTAhmed Ismail (Sr. Welding & Piping) LAST
Ahmed Ismail (Sr. Welding & Piping) LASTAhmed Esmail
 
Isa-sachin-upstream-onshore.ppt
Isa-sachin-upstream-onshore.pptIsa-sachin-upstream-onshore.ppt
Isa-sachin-upstream-onshore.pptSachin Rasane
 
Update Profile Siraj......
Update Profile Siraj......Update Profile Siraj......
Update Profile Siraj......Siraj Ahmed
 
VULCAN Series A2ST Advanced Alumina Support Technology
VULCAN Series A2ST Advanced Alumina Support TechnologyVULCAN Series A2ST Advanced Alumina Support Technology
VULCAN Series A2ST Advanced Alumina Support TechnologyGerard B. Hawkins
 
SUOKAS Kuwait s-2015 slides_FINAL
SUOKAS Kuwait s-2015 slides_FINALSUOKAS Kuwait s-2015 slides_FINAL
SUOKAS Kuwait s-2015 slides_FINALJouko Suokas
 
DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS
DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS
DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS Gerard B. Hawkins
 
A life cycle approach to corrosion management and asset integrity
A life cycle approach to corrosion management and asset integrityA life cycle approach to corrosion management and asset integrity
A life cycle approach to corrosion management and asset integrityOkeme Esegine PMP
 
Mechanical Constraints on Thermal Design of Shell and Tube Exchangers
Mechanical Constraints on Thermal Design of Shell and Tube ExchangersMechanical Constraints on Thermal Design of Shell and Tube Exchangers
Mechanical Constraints on Thermal Design of Shell and Tube ExchangersGerard B. Hawkins
 
Allwin21 and main products
Allwin21 and main productsAllwin21 and main products
Allwin21 and main productsPeter Chen
 
rosemount_level_user_guide_refining_ind.pdf
rosemount_level_user_guide_refining_ind.pdfrosemount_level_user_guide_refining_ind.pdf
rosemount_level_user_guide_refining_ind.pdfssuser3eddcd
 
Project Proposal for Predictive Maintenance Power Plant
Project Proposal for Predictive Maintenance Power PlantProject Proposal for Predictive Maintenance Power Plant
Project Proposal for Predictive Maintenance Power PlantFerdous Kabir
 

Similar to MIQA, An Ultimate Element of PSM Implementation (20)

OH&S Audit Report- JSW Nandyal.doc
OH&S Audit Report- JSW Nandyal.docOH&S Audit Report- JSW Nandyal.doc
OH&S Audit Report- JSW Nandyal.doc
 
QA-QC ENGINEER
QA-QC ENGINEERQA-QC ENGINEER
QA-QC ENGINEER
 
OCS Training - API 570 piping inspection course
OCS Training - API 570 piping inspection courseOCS Training - API 570 piping inspection course
OCS Training - API 570 piping inspection course
 
Casting manufacturing process improvement
Casting manufacturing process improvementCasting manufacturing process improvement
Casting manufacturing process improvement
 
Mithun Banjan CV
Mithun Banjan CVMithun Banjan CV
Mithun Banjan CV
 
Avoiding Stress Corrosion Cracking of Carbon Low Alloy and Austenitic Stainl...
Avoiding Stress Corrosion Cracking of  Carbon Low Alloy and Austenitic Stainl...Avoiding Stress Corrosion Cracking of  Carbon Low Alloy and Austenitic Stainl...
Avoiding Stress Corrosion Cracking of Carbon Low Alloy and Austenitic Stainl...
 
Ahmed Ismail (Sr. Welding & Piping) LAST
Ahmed Ismail (Sr. Welding & Piping) LASTAhmed Ismail (Sr. Welding & Piping) LAST
Ahmed Ismail (Sr. Welding & Piping) LAST
 
Isa-sachin-upstream-onshore.ppt
Isa-sachin-upstream-onshore.pptIsa-sachin-upstream-onshore.ppt
Isa-sachin-upstream-onshore.ppt
 
Update Profile Siraj......
Update Profile Siraj......Update Profile Siraj......
Update Profile Siraj......
 
VULCAN Series A2ST Advanced Alumina Support Technology
VULCAN Series A2ST Advanced Alumina Support TechnologyVULCAN Series A2ST Advanced Alumina Support Technology
VULCAN Series A2ST Advanced Alumina Support Technology
 
SUOKAS Kuwait s-2015 slides_FINAL
SUOKAS Kuwait s-2015 slides_FINALSUOKAS Kuwait s-2015 slides_FINAL
SUOKAS Kuwait s-2015 slides_FINAL
 
Kamal resume
Kamal resumeKamal resume
Kamal resume
 
DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS
DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS
DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS
 
Amar Resume
Amar ResumeAmar Resume
Amar Resume
 
A life cycle approach to corrosion management and asset integrity
A life cycle approach to corrosion management and asset integrityA life cycle approach to corrosion management and asset integrity
A life cycle approach to corrosion management and asset integrity
 
Mechanical Constraints on Thermal Design of Shell and Tube Exchangers
Mechanical Constraints on Thermal Design of Shell and Tube ExchangersMechanical Constraints on Thermal Design of Shell and Tube Exchangers
Mechanical Constraints on Thermal Design of Shell and Tube Exchangers
 
Allwin21 and main products
Allwin21 and main productsAllwin21 and main products
Allwin21 and main products
 
rosemount_level_user_guide_refining_ind.pdf
rosemount_level_user_guide_refining_ind.pdfrosemount_level_user_guide_refining_ind.pdf
rosemount_level_user_guide_refining_ind.pdf
 
Project Proposal for Predictive Maintenance Power Plant
Project Proposal for Predictive Maintenance Power PlantProject Proposal for Predictive Maintenance Power Plant
Project Proposal for Predictive Maintenance Power Plant
 
KUMARESH.CV
KUMARESH.CVKUMARESH.CV
KUMARESH.CV
 

More from MAHENDRA KUMAR RASTOGI

Global Energy shift : Oil to Solar - The greatest energy revolution of 21st c...
Global Energy shift : Oil to Solar - The greatest energy revolution of 21st c...Global Energy shift : Oil to Solar - The greatest energy revolution of 21st c...
Global Energy shift : Oil to Solar - The greatest energy revolution of 21st c...MAHENDRA KUMAR RASTOGI
 
"Wake up call " to all operators & Regulators of Ageing petroleum industries.
"Wake up call " to all operators & Regulators of Ageing petroleum industries. "Wake up call " to all operators & Regulators of Ageing petroleum industries.
"Wake up call " to all operators & Regulators of Ageing petroleum industries. MAHENDRA KUMAR RASTOGI
 
How Ageing Assets are Threat to sustenance for petroleum industries in low cr...
How Ageing Assets are Threat to sustenance for petroleum industries in low cr...How Ageing Assets are Threat to sustenance for petroleum industries in low cr...
How Ageing Assets are Threat to sustenance for petroleum industries in low cr...MAHENDRA KUMAR RASTOGI
 
Why Globally Future of Future of petroleum industries is in doldrum ?
Why Globally Future of Future of petroleum industries is in doldrum ?Why Globally Future of Future of petroleum industries is in doldrum ?
Why Globally Future of Future of petroleum industries is in doldrum ?MAHENDRA KUMAR RASTOGI
 
Why Globally Future of petroleum industries is in doldrum ?
Why Globally Future of petroleum industries is in doldrum ?Why Globally Future of petroleum industries is in doldrum ?
Why Globally Future of petroleum industries is in doldrum ?MAHENDRA KUMAR RASTOGI
 
Key Point Message to Attendees on " Global Turbulence in Oil & Gas Sector and...
Key Point Message to Attendees on " Global Turbulence in Oil & Gas Sector and...Key Point Message to Attendees on " Global Turbulence in Oil & Gas Sector and...
Key Point Message to Attendees on " Global Turbulence in Oil & Gas Sector and...MAHENDRA KUMAR RASTOGI
 
Radison Refining & Petrochemicals New Delhi
Radison Refining & Petrochemicals New DelhiRadison Refining & Petrochemicals New Delhi
Radison Refining & Petrochemicals New DelhiMAHENDRA KUMAR RASTOGI
 
3rd Asian Refinery & Petrochemical Forum 26-27 April'2017
3rd Asian Refinery & Petrochemical Forum 26-27 April'20173rd Asian Refinery & Petrochemical Forum 26-27 April'2017
3rd Asian Refinery & Petrochemical Forum 26-27 April'2017MAHENDRA KUMAR RASTOGI
 
Operational Excellence at Ibis Hotel London IQPC MAHENDRA
Operational Excellence at Ibis Hotel London IQPC MAHENDRAOperational Excellence at Ibis Hotel London IQPC MAHENDRA
Operational Excellence at Ibis Hotel London IQPC MAHENDRAMAHENDRA KUMAR RASTOGI
 

More from MAHENDRA KUMAR RASTOGI (20)

Third eye inspection no. 2
Third eye inspection no. 2Third eye inspection no. 2
Third eye inspection no. 2
 
Third eye inspection no. 1
Third eye inspection no. 1Third eye inspection no. 1
Third eye inspection no. 1
 
Third eye inspection no. 1
Third eye inspection no. 1Third eye inspection no. 1
Third eye inspection no. 1
 
Global Energy shift : Oil to Solar - The greatest energy revolution of 21st c...
Global Energy shift : Oil to Solar - The greatest energy revolution of 21st c...Global Energy shift : Oil to Solar - The greatest energy revolution of 21st c...
Global Energy shift : Oil to Solar - The greatest energy revolution of 21st c...
 
"Wake up call " to all operators & Regulators of Ageing petroleum industries.
"Wake up call " to all operators & Regulators of Ageing petroleum industries. "Wake up call " to all operators & Regulators of Ageing petroleum industries.
"Wake up call " to all operators & Regulators of Ageing petroleum industries.
 
How Ageing Assets are Threat to sustenance for petroleum industries in low cr...
How Ageing Assets are Threat to sustenance for petroleum industries in low cr...How Ageing Assets are Threat to sustenance for petroleum industries in low cr...
How Ageing Assets are Threat to sustenance for petroleum industries in low cr...
 
Why Globally Future of Future of petroleum industries is in doldrum ?
Why Globally Future of Future of petroleum industries is in doldrum ?Why Globally Future of Future of petroleum industries is in doldrum ?
Why Globally Future of Future of petroleum industries is in doldrum ?
 
Why Globally Future of petroleum industries is in doldrum ?
Why Globally Future of petroleum industries is in doldrum ?Why Globally Future of petroleum industries is in doldrum ?
Why Globally Future of petroleum industries is in doldrum ?
 
Key Point Message to Attendees on " Global Turbulence in Oil & Gas Sector and...
Key Point Message to Attendees on " Global Turbulence in Oil & Gas Sector and...Key Point Message to Attendees on " Global Turbulence in Oil & Gas Sector and...
Key Point Message to Attendees on " Global Turbulence in Oil & Gas Sector and...
 
Radison Refining & Petrochemicals New Delhi
Radison Refining & Petrochemicals New DelhiRadison Refining & Petrochemicals New Delhi
Radison Refining & Petrochemicals New Delhi
 
Reliability & Maintenance Dubai
Reliability & Maintenance DubaiReliability & Maintenance Dubai
Reliability & Maintenance Dubai
 
Refining & Prtochemical Conference
Refining & Prtochemical  ConferenceRefining & Prtochemical  Conference
Refining & Prtochemical Conference
 
Refining & Prtochemical Conference
Refining & Prtochemical  ConferenceRefining & Prtochemical  Conference
Refining & Prtochemical Conference
 
Saudi Arabia turn around conference
Saudi Arabia turn around conferenceSaudi Arabia turn around conference
Saudi Arabia turn around conference
 
Saudi Arabia turn around conference
Saudi Arabia turn around conferenceSaudi Arabia turn around conference
Saudi Arabia turn around conference
 
3rd Asian Refinery & Petrochemical Forum 26-27 April'2017
3rd Asian Refinery & Petrochemical Forum 26-27 April'20173rd Asian Refinery & Petrochemical Forum 26-27 April'2017
3rd Asian Refinery & Petrochemical Forum 26-27 April'2017
 
Operational Excellence at Ibis Hotel London IQPC MAHENDRA
Operational Excellence at Ibis Hotel London IQPC MAHENDRAOperational Excellence at Ibis Hotel London IQPC MAHENDRA
Operational Excellence at Ibis Hotel London IQPC MAHENDRA
 
Abberdeen UK Presentation
Abberdeen  UK PresentationAbberdeen  UK Presentation
Abberdeen UK Presentation
 
AIM Scotland
AIM ScotlandAIM Scotland
AIM Scotland
 
Mahendra on Asset Integrity
Mahendra on Asset IntegrityMahendra on Asset Integrity
Mahendra on Asset Integrity
 

Recently uploaded

chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 

Recently uploaded (20)

chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 

MIQA, An Ultimate Element of PSM Implementation

  • 1.
  • 2. MIQA, An Ultimate Element of PSM Implementation AIM of process Safety Management PSM Objectives What’s MIQA , An Ultimate Element of PSM Why Reliability of Static Equipment Important ? Real Root Causes of Poor Reliability of Static Equipment Global Scenario of Static Equipment :”Wake up Call” to Operators of Ageing Petroleum Industries MIQA in Ageing Assets : A Global Challenging Problem Way forward to MIQA in Ageing Plants Why MIQA (AIM/RBI) fail and how to get success
  • 3. AIM of Process Safety Management Develop plant’s systems & procedures to prevent unwanted releases of spills & emissions, which may ignite and cause disaster of toxic impacts, local fires, or explosions in plants - affecting people, nearby Communities , Environment & Image of Company
  • 4. Flixoborogh, 1 June 1974 Additional facility built in 1972 for the production of Cyclohexanone •Used to produce Caprolactum intermediate for the manufacture of nylon • Section 25A involved oxidation of cyclohexane at 8.8 Barg / 155°C • The reaction was carried out in six liquid phase reactors •Each reactor was set 14” lower than the previous to allow the liquid to flow under gravity through the reaction train. • March 27th 1974, a crack developed in reactor number 5. The maintenance engineer recommended shutdown for 3 weeks for repair Flixoborogh, 1 June 1974
  • 5.
  • 6.
  • 7.  Proactive identification, evaluation and mitigation of chemical releases that could occur as a result of failures of processes, procedures or equipment.  Proactive control of the consequences of catastrophic releases of highly hazardous chemicals from a process. PSM Objectives :
  • 8. Out of 14 PSM Elements, MIQA is Ultimate for Process Safety
  • 9.
  • 10. MIQA shall ensures 360⁰ Integrity of equipment starts from inception of its Design , Construction, Startups, Commissioning , Operation, Turnaround till Decommissioning, to prevent out of containment of hazardous liquid & gases from its pressure boundary
  • 11.  Pressure Vessels and Storage tanks  Piping systems including all components  Relief & Vent systems and associated devices  Safety Instrumented Systems (SISs) and Emergency Shutdown (ESD) systems - Process control systems - Controls system including monitoring devices and sensors, critical alarms and interlocks.  Rotary equipment  Electrical equipment Equipment Under MIQA
  • 12. Identification and documentation of PSM critical equipment MIQA Implementer Team PSM critical equipment review Quality Assurance of New Equipment Maintenance, Inspection And Testing of Equipment Repairs and Changes Maintenance Procedures /schedule Maintenance training Quality Control of Maintenance, Repair and Operation (MRO) Materials and Spares Reliability Engineering Predictive Maintenance Program Documentation MIQA PROCEDURE
  • 13.
  • 14. Ageing is the main cause of poor reliability of Static Assets
  • 15.
  • 17. Why Do Equipment Age & Fail in Petroleum Industries
  • 18. What’s Ageing & What are Aged Equipment ?  Ageing is not by no. of years equipment passed but by its present condition  Aged Asset that outlived its useful life and may include the equipment still functional but expensive to operate/maintain, still works but breakdown frequently disrupting operation or equipment that broken and it is too expensive to repair Ageing Assets, a serious concern in petroleum industries for its sustenance
  • 19. Broadly due to poor design/construction and In-service corrosion/ metallurgical degradation due to poor maintenance / mal-operation Leading to Over ageing & premature failure in catastrophic manner
  • 20. Causes of Design Deficiencies  No consideration of Geographical features & types of crude processing while setting up refinery  Poor knowledge & experience of designer for selecting material, its degradation & protection  Poor knowledge of NDT technologies, its selection and practicality  Economical Metallurgy due to limited budget
  • 21. Off Spec. Materials Noncompliance in  METALLURGY  Heat Treatment Condition  Forming Method  Dimensions & geometry  Poor packing & dispatch
  • 22. Metallurgy Mismatch  P9 material in place of P91 resulted catastrophe just after commissioning  Carbon steel in place of Alloy steels  SS 304H in Place of SS 304L & vice versa  SA 516 Gr70 in place of SA 516 Gr60 in NACE & Caustic Service  Ordinary Brass in place of Ar stabilized Admiralty Brass  SS 304 piping in place of SS 321
  • 23. Heat Treatment Condition  No Stabilization Treatment of Stabilized Grade SS 347 & 321 after welding leading to Chloride & Polythionic SCC.  No PWHT of CS equipment after welding in caustic, Amine, LPG, sodium carbonate & hydrogen Service causing catastrophe due to SCC  Failure of Admiralty brass U tube bundle in lube oil cooler due to no solution annealing of tubes after bending Use of SA191 Grade B7 studs in place of Grade B7M in NACE H2S service
  • 24. Dimension & Geometry/ Slope Thinning of Elbow at Crown portion  Undersize fillet welding in place of Full Penetration welds Out of roundness & Verticality in Storage tanks
  • 25. Poor Workmanship During Construction  Welding by helpers / unqualified personnel  Short Bolting  Reverse Slope of pipelines causing inefficient drainage  Gas Cutting in place of Drilling for holes  Box up Equipment with foreign materials  Gas / Grinding Cutting of SS in place of Plasma
  • 26. Construction Lapses Poor workmanship & Nonstandard procedures  Mismatch in Filler Wire.  Improper baking of electrode / no or improper purging  Metallurgy mix up.  Non compliance of welding Procedure & repetitive repairs  Manipulation in NDT & PWHT.  Box up of Equipment With Foreign Materials  No Dewatering & Dry up after Hydro Testing  Poor Insulation: Aluminium clad on high temperature ASS lines.  Poor Refractory Application & Dry out
  • 27. Construction Lapses Poor workmanship & Nonstandard procedures  Poor application of coating & lining  No Passivation & long idling without Preservation  Use of Poor Quality water in hydro testing  No PWHT ( Stabilization) in SS 321/347  No SR of CS equipment in Amine, Caustic, LPG, H₂ service  No RT after PWHT  RT interpretation noncompliance with design need  PWHT cycle problem in P91 & P92 dissimilar material.  Poor control of welding parameters in Duplex & P91/P92.  Lack of experience /poor qualification of QA/QC inspectors
  • 28. Poor Start-Up & Commissioning Damages Maximum damage in the life of a plant occurs at start up Due to over run of operating parameter and the remnant effect of this damage may affect the design life significantly. A step by step procedure if followed strictly can give a safe and risk free plant start up & in- turn smooth operation , longer run-length & expected safer design life in future.
  • 29. Post Commissioning Mal-Operation- No IOW  Poor Control of Operating Parameters  Long idling without proper preservation  Inefficacy of dosing system for corrosion control.  Running equipment beyond design parameters: No IOW  Processing High TAN crude with low metallurgy  Processing High NAN Crude with inadequate Metallurgy  Running the equipment in leaky condition
  • 30. Frequent Steam & Power Failures  Thermal fatigue, Thermal Shocks Causing metallurgical degradation due to thermo-mechanical Stress in High Temperature Equipment.  Accelerate corrosion due to stoppage of pumps causing condensation of acidic gases in overhead circuit leading to dew point corrosion at each event.  Starvation of water in PG boilers leading to creep failure .
  • 31. Capacity Utilization Beyond Design  Refiners running the plant as high as 120% to 140% of its design just for greed of getting production or breaking the previous bench mark records of production causing high velocities of streams & high temperature leading to erosion corrosion, fatigue & creep damages.  Change of crude (Opportunity crude) without metallurgy up-gradation due to international market drive & availability leading to faster rate of corrosion.
  • 32. Frequent change of Inspectors  Poor inspection recommendation  Poor documentation.  Lack of proactive skill & confidence In Decision Making  All above lead to confusion & chaos in turn poor reliability.
  • 33. No Company Owned Standards & Practices Nonstandard norms & practices of Inspection & Maintenance result Repetitive failure More Maintenance & Inspection cost Poor Reliability of Equipment No in-house talent & expertise development More dependency & panic at time of resigning Confusion, chaos & delay in jobs
  • 34.
  • 35. Impact of Ageing on MIQA  Increased Unpredictable Failures & catastrophes  More Unsafe situation & fatal  Pressure from Regulators  More repair & more maintenance cost  Poor run length & On-stream Service factor  Need more Inspection with Advance NDT & Heavy Replacement for Life Extension.
  • 36. As per the current industry climate, pipelines may cost up to $ 3 million per km to replace for prolonging the lifetime of infrastructure and avoiding preventable damage is extremely valuable to operators. Ageing Pipelines & Replacement Cost 4 million KM Ageing Pipelines replacement in USA shall cost $12000 billion which can break the backbone of most developed economy of world
  • 37. With the safety of personnel being a top priority across the entire global industry, operators must ensure they have robust monitoring and inspection regimes, corrosion monitoring techniques, risk assessments and active maintenance programs in place to safeguard against risk. Life Extension of Ageing Assets
  • 38. Continued operation of ageing assets, through RLA & Life Extension Plans Creating opportunities to lower costs and increased profits for sustenance, but need wisdom & expertize. As the industry seeks to increase the economic life of assets, many will remain in operation longer than anticipated. Some oil and gas assets have
  • 39.  Current condition assessment  Life extension evaluation and GAP analysis  Technical qualification for life extension  Obsolescence preparedness  Life extension costs and plans Five-step approach for Life Extension
  • 40.  Assess history & present status  Detect symptoms of ageing  Examine options: e.g. continued service, re-rating, repair, scrapping  Use risk-based approach to identify critical systems and equipment  Life extension evaluation and GAP analysis  Determine modifications required  Perform technical qualification to operate structures & equipment beyond original design life  Obsolescence preparedness  Elongated term cost prediction What we do in Life Extension?
  • 41. AIMS outline the ability of an asset to perform its required function effectively and efficiently whilst protecting health, safety & environment and the means of ensuring that the people, systems, processes, and resources that deliver integrity are in place, in use and will perform when required over the whole lifecycle of the asset What’s AIM
  • 42. An Integrity Management System should address the quality at every stage of the asset life cycle, from the design of new facilities to maintenance management to decommissioning. Inspections, auditing/assurance and overall quality processes are just some of the tools designed to make an AIMS effective The AIMS should also endeavor to maintain the asset in a fit-for-service condition while extending its remaining life in the most reliable, safe, and cost-effective manner. The AIM programs (in the US) attempt to meet API-580, API- 581, and PAS 55 requirements, as applicable.
  • 43.
  • 44.
  • 45.
  • 46. MIQA in Ageing Assets : A global Challenge Ageing Assets : Predict, control , Monitor & Mitigate Complex Corrosion & Metallurgical Degradation
  • 47. MIQA in Ageing Assets : A Global Challenge for PSM Management of Ageing Assets: Need Top driven Reliability Culture & In-house Team Expertise Proactive Detection, Dynamic Risk Analysis and Timely Action for avoiding Catastrophes
  • 48. Management of Ageing Assets: A Complex Problem
  • 49.
  • 50. Corrosion is Cancerous disease to Industries Specially Oil & Gas which can kill the total economy of a company or country. Are you aware of this fact ? Replacement of Ageing Assets can break the backbone of even most developed World economy and life enhancement is the only option to sustain.
  • 51.
  • 52. MIQA in Ageing Assets & Cost Reduction Arbitrary Cost Reduction : Increasing Risk of Replacing the Facility for sustenance
  • 53. MIQA in Ageing Asset & Cost Reduction Arbitrarily cutting skilled head counts Increasing Risk to sustenance due to Poor Monitoring & Maintenance
  • 54. MIQA in Ageing Assets :A Global Challenge for PSM Way forward to Reliability of Ageing Assets
  • 55. MIQA in Ageing Assets & Cost Reduction Reducing Inspection Budget Arbitrarily : Increasing Risk to Sustenance
  • 56. Risk Assessment Through RBI & FFS Technologies for achieving Reliability of static assets, is the key to survival for Ageing Petroleum Industries Both Technologies are Complementary, Stands alone separately but meet together in Crisis MIQA & Management of Ageing Assets World over, No break through yet for both RBI/FFS due to lack of expertise , high complexity and poor culture
  • 57.
  • 58. A New Way to Use RBI - The Long Play While RBI will continue to be used in the short term to defer inspections, its real power lies in its ability to create a long term plan. Have you thought about using it for the long term? the term "RBI it away" as in completing an RBI assessment to make an overdue inspection disappear. These people are very short sighted in their views of RBI's capabilities. RBI is a powerful equipment life-cycle tool that can predict damage out into the future, and the API codes allow you to take full advantage of this technology.
  • 59.
  • 60.
  • 61. Ageing Assets : A threat to sustenance , Environment & Human Life MIQA in Ageing Assets : A Global Challenge for PSM
  • 62. MIQA in Ageing Assets : A Global Challenge for PSM Way Forward to Reliability: Life Time Integrated Integrity of Entire Plant
  • 63.
  • 64. High Temperature Sulfidation Ф8” 52” length piece u/s bend Low Silicon CS
  • 65. Tesoro Refinery, 2 Apr 2010, six fatalities
  • 66.
  • 67.
  • 68.
  • 69.
  • 70. Thinning & Over pressurization
  • 71.
  • 73. Importance of Reliability Culture For long term survival, take significant management energy as well as strong commitment from all levels
  • 74. Proactive Culture through MIQA, MOC & IOW Implementation
  • 75.
  • 76.
  • 77.
  • 78.
  • 79. MIQA in Ageing Assets : A Global Challenge for PSMGood Asset Integrity Management balances Design Integrity , Operating Integrity and Technical Integrity in the most cost effective and productive way starting from plant design to end of life
  • 80.
  • 81.
  • 82.
  • 83.
  • 84.
  • 85.
  • 86.
  • 87.
  • 88.
  • 89.
  • 90.  MIQA , most important Element of Process Safety Management and is ultimate to prevent Out of containment of hydrocarbon or toxic liquid and gases avoiding fire , explosion and catastrophes by ensuring the mechanical integrity of assets at every stage starting from inception of design to start up during construction and then commissioning to and then during operation , break downs , turn around till decommissioning.  Global statistic of petroleum industries estimated 80 % static assets consisting mainly pipelines, plant piping, pressure vessels and safety valves in refineries and petrochemicals are aged either due to expiry or due to poor condition. These assets are still productive but having lot of uncertainty for reliability and frequently failing resulting catastrophes and explosion. Replacement of these assets is not feasible due to high cost & time constraint. Life enhancement is the only option . MIQA needs top driven proactive reliability culture , In-house technical expertize and operational discipline along with time and funding. Conclusion

Editor's Notes

  1. Management or stake holders can not wait until an incident occurs to take action We must be PROACTIVE
  2. Data to ensure MIQA : know it & prove it What is the exact corrosion condition of plant Where the plant is in poor condition and mitigation action plans made and implemented Where the plant is in good condition and the action plans made to maintain it as such
  3. On 06Aug2012, explosion & fire took place due to Ф8” just upstream of bend rupture in LGO side stream of crude distillation of Chevron Richmond refinery in USA. Analysis of ruptured component indicated low silicon carbon steel material and failed due to high temperature sulphur corrosion (erosion corrosion phenomenon) which is localised damage mostly prevalent in the location of turbulence and high velocity region causing uniform thinning over a large area. Silicon content is an important parameter to prevent HTSC in carbon steel since silicon content if lower than 0.1% corrosion rate soot up exponentially. HTSC failures tend to involve rupture resulting large leaks rather than pinhole leak. Historical data revealed no thickness data recorded on this component in their RBI plans . This component was never replaced since its commissioning in seventies when there was no control over silicon content in CS. After USTM & silicon many other components were found having the silicon content lesser than 0.1%. This incident due to several fatalities , production loss and damage to plant and image/reputation of company has given big jolt to chevron. After that Chevron has developed new construction guidelines stating piping installed in high temperature and high sulphur service shall be constructed with 9 chrome steel. This incident has brought the revolution in material selection world over to “ use inherently safer material and robust design instead economical” to avoid failures and catastrophes. Hence let’s say “ Reliable is safe ! Safe is profitable”
  4. On 2nd Apr 2010 six fatalities with explosion / fire due to catastrophic rupture of CS heat exchanger shell in NHT . In the fire zone there are six exchanger in two rows of three exchanger each in series. (Naphtha+hydrogen) feed tube side enter into heater at 550 ᴼF & 630 Psig. After heating at 625ᴼF, this feed enter into reactor for removing impurities from naphtha. The O/L feed of reactor passes shell side of exchanger A & D for cooling at 630ᴼF- 710ᴼF at 590 psig. After A & B, the effluent passes into B & E and then A & F for further cooling and finally effluent come out at 270ᴼF from exchanger C & F . Shell longitudinal joint rupture took place in exchanger E and in exchanger B circumferential joint was found cracked. Cause of rupture is due to long term hydrogen exposure of CS shell beyond the HTHA limit of Nelson curve of CS due to chockage of tube preventing heat flow from shell to tube in exchanger E & B. Investigation revealed there was no TI points on these exchangers. This incident brought the revolution in selection of material for resistant to HTHA and modified the Nelson curve & API RP 941 mentioning CS in high temperature can be used if the temperature is lesser than 400ᴼF & hydrogen Pressure is lesser than 50 psig. API 571 damage mechanisms recommend to use inherently safer material as 300 series as well as 5 Cr, 9 Cr & 12 Cr alloys or stabilized grades special Cr-Ni steel as in reformer. This incidents has brought the revolution to use inherently safer material instead using economical carbon steel and given big impact world over to modify the existing plant. Again Let’s say “ Reliable is Safe ! Safe is profitable
  5. On 16 Apr2001, big fire took place subsequent to vapour cloud formation due to rupture of 90 deg elbow over head circuit of saturate gas plant. Cause of leak is the erosion corrosion aggravated after the provision of BFW injection point in the upstream of elbow. After few years of commissioning, refinery was facing the shell side chockage problem in condenser in O/H circuit due to which throughput was affected and frequent plant shutdown for cleaning the exchanger. To mitigate this problem, refinery has planned the modification by providing intermittent BFW water injection point just upstream of the elbow to wash the deposit on stream. After few years of operation , on 16 apr2001 elbow in down stream just after the injection point was suddenly ruptured and hydrocarbon vapours develop the cloud on the top of column and subsequently big fire took place. Many equipment in SGP and adjacent unit were badly damaged. Cause of failure: wrong location of injection point which is causing erosion – corrosion due to water droplets and corrosives in vapour in presence of turbulence and impact force of water droplets favouring ideal condition for erosion corrosion to take place. Poor inspection & RBI monitoring No MOC approval done before going for modification in overhead lines. This incident has created lot of awareness about the susceptibility of injection points, mixing points, dead legs, dead ends and dosing point to corrosion . Lot of case study and mechanisms along with preventive measures articles published in NACE after this incident.
  6. On 16Feb2016, LPG fire at Valero – PDA unit MCKEE REFINERY took place due to sudden leak from ruptured elbow. The control station connected to the PDA extractor column was not in use for last 15 years and was isolated by closing two gate valves and one control valve but it remains connected to propane pump. Water settling out of a propane leaked through 10” gate valve and accumulated in the low point elbow. During cold weather, water in the elbow was frozen and due to increase in volume, it exerted stresses on the elbow wall at subzero temperature making the material brittle. During the summer season the ice got melted and lot of propane released after the rupture of elbow in brittle mode and resulted fire. Later this fire spread in other areas and resulted multiple fire in entire plant. Four people injured and shutdown of the plant extended. This is the burning examples of damages due to cold leg formation.
  7. Crevice Corrosion of piping at support location is the biggest problems of ageing pipelines. Due to lack of access these pipeline could not be protected from corrosion externally by coating in their entire life. These pipelines are badly corroded on the support location . Frequent failure and catastrophes are taking place in these piping . Correction is time taking and difficult and require shutdown of the plant in many cases and expensive. Avoid the stitch weld and crevices in modified support system of piping. Phase wise correction/replacement of these piping segments
  8. CUI is a silent killer & big constraint for reliability of ageing assets more chronic problem in coastal area. API RP 583 describe how to protect and design piping and equipment to prevent and monitor CUI. Ingress of water and its stagnation should be avoided to prevent CUI. Thermo-graphy is used to detect the damaged insulation remotely in insulated piping and equipment and does not require access. Neutron back scatter technique is used to detect usceptible locations where water ingress / stagnation is taking place within insulation. LRUT can detect the CUI damages remotely by removing the insulation locally. Profile radiography & real time tangential RT can detect the CUI but require access to location.CUI can be controlled during the design of equipment itself by avoiding water ingress / water retention on the structural and nozzle attachment locations of equipment and piping and workmanship during the application of insulation and cladding / sealing material .
  9. PG&E pipe explosion in San Bruno took place on 09 Sep 2010 due to rupture of natural gas U/G pipelines. 38 houses burnt and more than eight people killed in this mishap. PG&E fined 1.6 billion dollars which is the highest penalty in the history of USA. Cause of failure: This line was constructed in nineteen fifties and corrosion because of ageing along with over pressurization is the main cause of failure which resulted thinning and ductile mode of failure in 6 o’clock position of pipe. Demand of natural gas increased due to increasing population . To meet this demand pipelines was over pressurized. However as seen in the photograph all girth weld remain intact during the rupture. Further investigation revealed: lapses in hydro-test & history data found missing and some places not matching. This incident had created lot of awareness about the safety of gas pipeline, among operators , regulators and public / politics. However still the trend of pipelines in USA is increasing and it is a big matter of concern how to improve the reliability of these ageing assets causing frequent catastrophes affecting the environment & human safety.
  10. AIM / RBI is the combined responsibility of each and every department including HR, Finance, Commercial & Contractual manpower. Hence everyone shall be aware and trained about reliability and what is their role in that.
  11. Reliability has to start from inception of thought to have facility. Reliability is important start from conceptual design (feed data), detailed engineering, procurement, construction and start up till commissioning at every step but design stage it is easier and without expense. Hence during design stage the reliability shall be given special emphasis. RBI shall not be done during operation & turn around but it must be done during design and construction stage otherwise it becomes unreliable. Material spec. & quality lapses are to be monitored & controlled at every steps in the entire life cycle of assets from its design to final decommissioning . if not done will result into in born sick plant & AIM/ RBI becomes herculean task.
  12. Integrity operating window design to control the operating parameters for maintaining the integrity of equipment and improving the run length and availability of plant.