SlideShare a Scribd company logo
1 of 62
Download to read offline
“CONSTRUCTION WORKS AT HWPK”
A
INDUSTRIAL TRAINING REPORT
Submitted in partial fulfillment of the requirements for the degree of
Bachelor of Technology
In
Civil Engineering
By
LOKESH CHOUDHARY
UID: K10673
Submitted to the
Ms. Arpita Sharma
Department of Civil Engineering
Career Point University, Kota-325003
Rajasthan (India) 2013-17
CERTIFICATE
This is to certify that the industrial training project report entitled
“CONSTRUCTION WORKS AT HWPK”, in partial fuilfillment of the
requirements for the degree of Bachelor Of Technology submitted to the
Department of Civil Engineering at Career Ponit University, Kota (Raj.) the
record of work carried out by them under my supervision and guidance.
In my opintion the submitted work has reached a level requred for being accepted
for industrioal trarning examination.
Date: 19 September, 2016 Lokesh Choudhary
UID- K10673
This is to certify that above statement made by the candidates are correct to the
best of my knowledge.
Evaluator
Mr. Sitesh Singh
Civil Engineering Department
Career Point University , Kota,(RAJ)
i
ABSTRACT
During 60 days training session, I have completed many task and learn following skills related
to construction world-
1. Surveying on pond construction.
2. Tendering process
3. Increase the thickness of foundation
4. Water Treatment Plant process
5. Road resurfacing
6. Different construction equipment (machines) and their use in construction site.
7. Concrete is a vital material in any construction of reinforced concrete and is the main constituent
or ingredient of any reinforced concrete structure.
8. To organize our tasks and assignment, we need to analyze our problems and assignment, and to
formulate a good solution to the problem.
9. In working environment, teamwork is vital in contributing to a strong organization. Teamwork
is also essential in reaching the goals of the organization as an entity.
ii
ACKNOWLEDGEMENT
First of all I feel great pleasure in acknowledging my deepest gratitude to Hon’ble Vice
Chancellor providing me opportunity of practical training. I am also thankful to Mr. TS Reddy,
Head of Civil Department at HWPK for arranging such helpful training for me. I also thankful
to Mr. Sitesh Singh for delight guidance.
I find it hard to express my grateful to the Almighty in words for bestowing upon me his deepest
blessings and providing me with the most wonderful opportunity in the form of life of a human
being and for the warmth and kindness he has showered upon me by giving me life’s best.
Last but not least I am thankful to all who helped me direct or indirect for my endeavor.
Date: 19 September 2016 Lokesh Choudhary
(UID: K10673)
iii
CANDIDATES’S DECLARATION
I here declare that work which is being in presented in the Training Report entitled
“Construction Works at HWPK” in partial fulfillment for the award of Degree of ‘Bachelor
Technology in Dept. of Civil Engineering and submitted to the department of Civil
Engineering Career Point University is a record of my own investigation carried of Ms. Arpita
Sharma Head, Civil Engineering department.
I have not submitted the matter presented in this report anywhere for the award of any other
Degree
Lokesh Choudhary
UID-K10673
Career Point University
iv
TABLE OF CONTENTS
CERTIFICATE
ABSTRACT
ACKNOWLEDGEMENT
DECLARATION
TABLE OF CONTENTS
LIST OF FIGURES
LIST OF TABLE
LIST OF ABBREVIATIONS
Page No.
i
ii
iii
iv
v-vii
viii
ix
x
Chapter 1
Introduction 1-7
1.1 Heavy Water Board…………………………………………………………….
1.1.1 The project need………………………………………………………..
1.1.2 About HWB……………………………………………………………
1
1
1
1.2
1.3
Heavy Water Plant, Kota……………………..………….…………………….
1.2.1 Introduction………………………………………………………………
1.2.2 HWPK- Technology Breakthrough in India……………………………..
What is heavy water? ………………………………………………………….
1.3.1 Uses of heavy water……………………………………………………...
1.3.2 Process Description………………………………………………………
3
3
3
3
4
5
Chapter 2
Literature Review
8-41
2.1 Construction of pond…………………………...…………………………….... 8
2.1.1 Pond……………………………..………………………………………. 8
2.1.2 Steps used for build a pond…………………………..………………….. 9
2.2 Water Treatment Plant & Process……………………………………………... 21
2.2.1 Water & its standards……………………………………………………. 22
2.2.2 Quality of water………………………...………………………………..
2.2.3 Water Treatment…………………………………………………………
24
26
2.3 Strengthening of foundation…………………………………………………... 31
2.3.1 Introduction ……………………………………………………………... 31
2.3.2 Strengthening of existing building……………………………………….
2.3.3 Improving the foundation………………………………………………..
31
31
2.4 Tendering……………………………………………………………………… 33
2.4.1 From where it comes……………………………………………………. 33
2.4.2 What is tender? ………………………………………………………….
2.4.3 Contract Strategy………………………………………………………...
2.4.4 Invitation to Tender………………………………………………………
2.4.5 Decision of the review panel……………………………………………..
33
33
35
36
2.5 Road resurfacing……………………………………………………………..... 37
2.5.1 Introduction……………………………………………………………… 37
2.5.2 Points need to be considered……………………………………………..
2.5.3 Detailed Considerations………………………………………………….
2.5.4 Mechanical Adhesion………………………….…………………………
2.5.5 Special Considerations…………………………………………………...
2.5.6 Laying
38
39
40
41
41
Chapter 3 Scope Of Training 42
Chapter 4 Objective Of Training 43
Chapter 5
Chapter 6
Chapter 7
Complete Work plan With Timelines
Result & Outcome
Experimental
44-45
46
47
Chapter 8 Conclusion
Appendix
References
48
49
51
vii
LIST OF FIGURES
Figure No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
Name of Figure
Heavy water plants in India
Cooling & Hot tower at RR site
Girdler Sulphide Process
Survey
Tripod
Digital Theodolite
Rough levelling with the circular level
Levelling with the plate level
Digital theodolite keys
Digital LCD monitor
Tree Slump
Preparing for a pond
Remove the surface soil
Random rubble masonry
Random Rubble Masonry Wall Design
Coping
Turbidity
Colour
Screening
Flocculation
Sedimentation
Rapid sand filter
Slow sand filter
Improving a foundation
Road Resurfacing
Page No.
2
5
6
10
11
11
12
12
13
13
14
15
16
19
19
20
25
25
27
28
28
29
29
32
37
viii
LIST OF TABLE
Table No.
1
2
Name of Table
General Data about HWPK
Indian standard Specification for drinking water (Part 1)
Indian standard Specification for drinking water (Part 2)
Page No.
7
23
24
ix
LIST OF ABBREVIATIONS
1. HWB Heavy Water Board
2. DAE Department of Atomic Energy
3. ISO Indian Organization for Standardization
4. USA United States of America
5. RR site Rawatbhata Rajasthan site
6. Km Kilometer
7. Ev Electronvolt
8. atm Atmosphere
9. MmHg Millimeter of mercury
10. MT/year Metric ton per year
11. Cm Centimeter
12. PCC Plain Cement Concrete
13. NIT Notice Inviting Tender
14. Ca Calcium
15. Mg Magnesium
16. Na Sodium
17. K Potassium
18. MWe
19. HWPK
Megawatt of electricity
Heavy Water Plant Kota
x
1 | P a g e
Chapter 1
Introduction
1.1 Heavy Water Board
1.1.1 The Project Need:
Department of Atomic Energy embarked on an ambitious programme of producing nuclear
power of 10,000 MWe which required setting up a number of heavy water plants. This was
also the time when the need for a separate organisation to oversee the planning and setting up
of Heavy Water Plants was strongly felt. Accordingly an organisation known as the Heavy
Water Projects was set up on May 1, 1969.
1.1.2 About HWB:
Heavy Water Board (HWB), a constituent unit of Industries and Minerals Sector under
Department of Atomic Energy, is primarily responsible for production of Heavy Water
(Deuterium Oxide-D2O). Heavy Water Board and its Plants are ISO Certified for Quality
Management System, Environment Management System and Occupational Health & Safety
Management System.
Heavy Water Board has successfully exported Heavy Water to countries viz. South Korea,
China and USA. This included development of the processes from laboratory synthesis through
scale up to commercially viable plants. The solvents produced by HWB have found
acceptability not only in DAE but outside as well.
HWB also has been successful in engineering / setting up and operating the boron isotope
enrichment units based on different technologies to meet the requirements of fast breeder
reactor programme. The other activities also include development of cryogenic process system
and recovery of rare material from secondary sources.
Apart from the above, HWB has opened avenues for development and promotion of non-
nuclear applications of Heavy Water and Deuterium. HWB has been successful in
2 | P a g e
demonstrating the improved thermal stability of deuterated oral polio vaccine. HWB also has
been working with various institutions in further development in these applications.
1.1.2.1 HWB in India:
1. Heavy Water Plant, Baroda (Gujarat)
2. Heavy Water Plant, Hazira (Gujarat)
3. Heavy Water Plant, Kota (Rajasthan)
4. Heavy Water Plant, Manuguru (Andhra Pradesh)
5. Heavy Water Plant, Talcher (Orissa)
6. Heavy Water Plant, Thal (Maharashtra)
7. Heavy Water Plant, Tuticorin (Tamilnadu)
Fig 1: Heavy water plants in India
3 | P a g e
1.2 Heavy Water Plant, Kota
1.2.1 Introduction:
Heavy Water Plant, Kota is India’s first plant based on Hydrogen sulphide- Water Dual
Temperature Exchange Process, set up indigenously. Plant is sited in close proximity to
Rajasthan Atomic Power Station (RR site), Anushakti with it is integrated for supply of process
steam and electrical power. Anushakti is nearly 65 km from Kota Railway Station in Kherli
block under Tehsil of Rawatbhata in Chittorgarh Distict, Rajasthan. HWP, Kota is located in
the picturesque landscape of lush green hills on the bank of Rana Pratap Sagar reservoir of
Chambal River.
Project activities for this plant began in early 70’s with “Ground Breaking” on July 7, 1972.
Commissioning activities started in early 80’s. Nuclear grade heavy water was first produced
from Distillation Unit in 1981 using off grade heavy water. Trial production run of Exchange
Unit was accomplished in 1983 and full commercial operation of the plant started in April,
1985.
1.2.2 HWPK- Technology Breakthrough in India:
Heavy Water Plant, Kota was conceptualized, designed & engineered based on pilot plant study
at BARC. Development work led to a number of innovative concepts in design, engineering,
construction and operation, many of which were being tried out for first time in India.
Heavy water technology development in India, from grass root level to robust one, is a true
example pf self- reliance. The experience and expertise gained at Kota plant was utilized for
setting up double capacity plant at Manuguru. This technology proved to be a game changer in
Indian Heavy Water Programme making our country self- reliant and the largest global
producer.
1.3 What is Heavy Water?
Heavy water (D2O) is oxide of Deuterium (heavier isotope of hydrogen). Its nuclear properties
display a significant variation which makes it an extremely efficient material for use as
moderator in a nuclear reactor. Deuterium and its compounds have many promising application
4 | P a g e
in advanced technology and life science. Heavy water resembles normal water in appearance
and chemical properties. Heavy Water has great similarity in its physical and chemical
properties to ordinary water. It is noon-radioactive and apparently harmless to human being.
1.3.1 Uses of Heavy water:
Heavy water is largely used in the production of nuclear energy and a number of modern
research experiments as given below:
a.) As a Neutron moderator:
Moderator is required in a thermal reactor to slow down the neutrons produced in the fission
reaction to .025 ev (thermal reaction) so that the chain reaction can be sustained. Different
moderators normally in use are Heavy Water, Graphite, Beryllium and Light water. Heavy
Water is an excellent moderator. A good moderator should have excellent slowing down
power and low absorption cross section for neutrons.
b.) For production of Deuterium:
Heavy water is used for the production of deuterium and its compounds.
c.) As a Tracer Compound:
It is used as a tracer compound for the study of the study of the mechanism of chemical
reactions and in biochemical reactions.
d.) Coolant:
Heat energy produced in the fission reactor will be removed by coolant. Water is an excellent
coolant that can remove the heat from the feed. Heavy Water is used as a primary coolant to
transport heat generated by the fission reaction to secondary coolant, light water. In Gas cooled
reactors carbon di-oxide gas is used as coolant. Coolant transports heat to secondary coolant,
i.e. water for generation of steam at an appropriate pressure for running steam turbines. Steam
turbines drive generators to generate Electricity.
5 | P a g e
1.3.2 Process Description:
Water from the nearby Rana Pratap Sagar lake, purified of suspended and dissolved impurities
forms the process feed with the D20 enriched from 150 ppm (0.015%) in the feed to 15% D20
by chemical exchange with H2S and later by vacuum distillation to produce 99.8% D20. The
exchange unit is arranged in a 3 stage cascade. The first stage handling large quantities of
process water and H2S gas, consists of three pairs of cold and hot towers operating at 30 deg.
C. and 130 deg. C. respectively. The second and third stage each consist of one pair of cold
and hot towers. The purified water enters the top of first stage cold tower and travels down
while hydrogen sulphide gas entering the bottom of the tower meets the water in counter current
way on tower internals and the exchange of deuterium takes place. In cold tower the water gets
enriched with respect to deuterium while gas gets depleted in deuterium concentration. In hot
tower the reverse reaction takes place i.e. the gas gets enriched instead of liquid. By proper
liquid and gas flow rates with gas in closed circuit in a pair of towers, a small quantity of
enriched liquid can be withdrawn from the bottom of the cold tower as a net product. This is
further enriched in a similar way in 2nd and 3rd stages. The hot tower bottoms liquid coming
from the first stage is divided into two parts. One part is recycled to the top of humidification
section located at the bottom of hot tower for heat recovery while the other part constitutes the
waste. Before discarding the waste to the environment it is necessary to recover the H2S
dissolved in the waste. For this purpose a waste stripper is provided to strip H2S by direct steam
stripping and the evolved gas and steam are put back to first stage hot towers. The enriched
water from the 3rd stage is stripped off its H2S in a product stripper and fed to the distillation
unit for further enrichment upto nuclear grade.
Fig 2: Cooling and Hot tower at RR site
6 | P a g e
This process is known as the Girdler sulfide (GS) process.
Fig 3: Girdler sulfide process
As H2S gas is very toxic, corrosive and hazardous in nature and the plant has a dynamic hold
up of 200 Te H2S, extreme care has been taken in the design of the plant, selection of equipment
and materials, adhering to stringent fabrication procedures and codes. The exchange process
operates at about 20 atm. pressure and at a temperature of 30 to 1200
C. while the vacuum
distillation plant works at a pressure of 100 mm Hg absolute. The isotopic exchange reaction
which is the heart of the technology is carried out with the aid of specially designed efficient
trays. The H2S gas required for the process is manufactured in a separate unit at the plant
premises by the chemical reaction between sodium sulphide and sulphuric acid. Very elaborate
and sensitive H2S detection instrumentation is provided not only in the plant but also in the
surrounding areas to monitor the environment.
7 | P a g e
Table 1: General Data about HWPK
Process Used H2S - H2O Exchange
Process Know How Departmental
Capacity of the Plant 80 MT / Year
Date of Commissioning 1-4-1985
Capital cost of the Plant Rs. 7730 Lakhs
Plant Area 20 Hectares
Number of Employees (Man Power) 599 (as on 30.06.2012)
Operating Pressure 20 Kg/Cm 2
Total Weight of Structure 2683 MTe
Total Weight of Equipment 4414 MTe
Weight of Heaviest Equipment 286 MTe
Maximum Diameter of Equipment 4.5 M approx.
Maximum Height of Towers 52 M approx.
Total Length of Piping 64 Km
Total length of Electrical Cables 350 Km
Substation Capacity 40 MVA
Connected Load 35.5 MW
Power Consumption 360 MWH/Day
Water Consumption 32400 M 3 /Day
Steam Consumption 2640 MT/Day
8 | P a g e
Chapter 2
Literature Review
2.1 Construction of Pond
2.1.1 Pond:
A pond is a body of standing water, either natural or artificial, that is usually smaller than a
lake. They may arise naturally in floodplains as part of a river system, or they may be somewhat
isolated depressions (examples include vernal pools and prairie potholes). Usually they contain
shallow water with marsh and aquatic plants and animals.
2.1.1.1 Objective for making Pond:
As the plant comes under central government department, it fulfils all the ecological and
environment friendly structures. So here is a large no. of trees and greenery.
 As where is a large amount of such a greenery there is always standing a chance of fire.
While the plant has a separate system of water pipelines in case of fire but the main
objective of this pond was to prepare such a dangerous accident.
 As the plant is eco-friendly, there are some animals also so the second objective of the
pond is to slake their thirst.
 In agriculture, treatment ponds may reduce nutrients released downstream from the
pond. They may also provide irrigation reservoirs at times of drought.
 Waste stabilization ponds are used as a low-cost method for wastewater treatment.
 In the Indian subcontinent, Hindu temples usually have a pond nearby so that pilgrims
can take baths. These ponds are considered sacred.
9 | P a g e
2.1.2 Steps used for build a pond:
Survey
Site clearance
PCC
Masonry
Coping
Plaster
2.1.2.1 Survey:
Construction surveying or building surveying (otherwise known as "staking", "stake-out", "lay-
out" or "setting-out") is to stake out reference points and markers that will guide the
construction of new structures such as roads or buildings. These markers are usually staked out
according to a suitable coordinate system selected for the project.
Elements of the construction survey:
 Survey existing conditions of the future work site, including topography, existing
buildings and infrastructure, and underground infrastructure whenever possible (for
example, measuring invert elevations and diameters of sewers at manholes);
 Stake out lot corners, stake limit of work and stake location of construction trailer (clear
of all excavation and construction)
 Stake out reference points and markers that will guide the construction of new structures
 Verify the location of structures during construction;
 Provide horizontal control on multiple floors.
 Conduct an As-Built survey: a survey conducted at the end of the construction project
to verify that the work authorized was completed to the specifications set on plans.
10 | P a g e
Fig 4: Survey
Coordinate systems used in construction:
Land surveys and surveys of existing conditions are generally performed according to geodesic
coordinates. However for the purposes of construction a more suitable coordinate system will
often be used. During construction surveying, the surveyor will often have to convert from
geodesic coordinates to the coordinate system used for that project.
Chainage or station:
In the case of roads or other linear infrastructure, a chainage (derived from Gunter's Chain - 1
chain is equal to 66 feet or 100 links) will be established, often to correspond with the center
line of the road or pipeline. During construction, structures would then be located in terms of
chainage, offset and elevation. Offset is said to be "left" or "right" relative to someone standing
on the chainage line who is looking in the direction of increasing chainage.
Other coordinate systems:
In other types of construction projects, arbitrary "north-south" and "east-west" reference lines
may be established, that do not necessarily correspond to true coordinates.
Equipment and techniques used in construction surveying:
Mainly there are three techniques:
1.) By theodolite
2.) Electronic distance measurement (EDM)
11 | P a g e
3.) Total stations
Surveying equipment, such as levels and theodolites, are used for accurate measurement of
angular deviation, horizontal, vertical and slope distances.
The builder's level measures neither horizontal nor vertical angles. It simply combines a spirit
level and telescope to allow the user to visually establish a line of sight along a level plane.
 At the site Theodolite is used.
Brief of Theodolite:
A theodolite is a precision instrument for measuring angles in the horizontal and vertical planes.
Theodolites are used mainly for surveying applications, and have been adapted for specialized
purposes in fields like meteorology and rocket launch technology.
Fig. 5: Tripod Fig 6: Digital Theodolite
Levelling the theodolite:
A. Referring to Fig. 7, roughly level the instrument using the circular level:
1. Turn the levelling screws A and B in opposite directions to centre the bubble along the AB
axis.
2. Turn levelling screw C to bring the bubble to the centre of the circular level.
12 | P a g e
B. Referring to Fig. 8, precisely level the instrument using the plate level.
1. Free the horizontal motion clamp and rotate the instrument horizontally until the plate level
is parallel with line AB.
2. Bring the bubble to the centre of the plate level by turning screws A and B in opposite
directions.
3. Rotate the instrument by 90◦ around its vertical axis and turn screw C to centre the bubble
once more.
4. Repeat procedures 1. and 2. for each 90◦ rotation of the instrument and check that the bubble
is correctly centered for all four points. If after 180◦ of rotation, the bubble is of center, remove
half the error in the bubble centering. Check that when you have swung another 180◦ back to
the initial point, the bubble offset is the same as the offset you allowed to remain in the 180◦
rotated position.
Fig 7: rough levelling with the circular level Fig 8: levelling with the plate level
Glossary of terms:
- An alternative to measuring vertical angles in degrees, the gradient is defending
as the tangent of the vertical angle with respect to the horizontal times 100%. For example, a
gradient of -50% means a slope of 22:5◦ below the horizontal.
- The theodolite position in which the vertical circle is on the viewer's left while he
looks into the telescope.
- The theodolite position in which the vertical circle is on the viewer's right while
he looks into the telescope.
13 | P a g e
- The graduated circle in the horizontal plane that the theodolite reads out
to measure horizontal angles.
- Thumbscrew that can be used to _x the angle of the theodolite with
respect to the
horizontally with the slow-motion screw.
- The line of sight through the centre of the telescope crosshairs.
- Small telescope whose eyepiece is near the bottom of the theodolite that
looks at the directly beneath the theodolite and is used for centring.
- A complete set of angle measurements performed in the face-left, then in
the face-right position.
w-motion screw - The adjustment screw used to translate the theodolite in the horizontal
or vertical plane when the horizontal or vertical clamp is tightened.
- See slow-motion screw.
- The axis about which the telescope pivots.
- The axis about which the horizontal circle pivots.
- The graduated circle in the vertical plane that the theodolite reads out to
measure vertical angles.
Fig 9: Digital theodolite keys Fig 10: Digital LCD monitor
14 | P a g e
2.1.2.2 Site Clearance:
The site should be cleared of all obstructions such as:
 Woody vegetation, where the roots can cause severe cracking in pond structures such
as concrete water inlets and outlets.
 Tree stumps which, when decaying, can also weaken concrete pond structures by
leaving voids in the soil.
Fig 11: Tree Slump
 Large stones, which may need to be dug out.
 Hills and animal burrows, which should be dug completely; clayey soil should be
tramped into the hole created.
Where to clear:
Define carefully the exact area to be cleared before you begin. Determine the outer corners of
the pond area, which should include the entire area to be covered by the dikes. You could mark
the area using wooden stakes and cord or poles. When this is done, mark out an additional area
beyond the dikes to serve as a work space and a walkway around the site. Then you are ready
to proceed.
(a) Clear the area within the limit of the pond dikes of all vegetation, shrubs, trees (including
woody roots and tree stumps) and all large stones.
(b) Clear the work space and walkway around the dikes.
15 | P a g e
(c) Clear all trees and shrubs within 10 m of dikes and pond structures and any access, water
supply or drainage area.
Fig 12: Preparing for a pond
Proceeding with the clearing:
 The clearing method to be used largely depends on the type of vegetation on the site. In
open savannah country, it is a relatively easy task that can be done manually with limited
special equipment
 There are two basic ways to clear the woody vegetation from a site:
1.) We can cut the trees and then remove the stumps;
2.) We can fell whole trees with their roots attached.
 The clearing of the site should be completed by gathering all cut vegetation, stumps, roots
and large stones. All these should be removed from the work area. When conditions are dry
enough, the clearing can be completed by starting a fire, which should be carefully kept
under control.
We can often sell the wood cleared from the site or make charcoal and sell it at a good price.
16 | P a g e
Surface soil removal:
1. Surface soil has the highest concentration of roots and decaying organic materials. This soil
is unstable as a construction material and cannot be used for the foundations of any dike or
structure. Therefore the surface soil should be removed from the areas where:
 Dikes and structures will be built;
 Soil will be taken as a dike construction material.
2. Soil may also be required outside the site to supply topsoil for newly constructed areas such
as dikes.
3. The depth of the surface soil varies from region to region. It may be totally absent or more
than 1m thick. Usually the surface soil is from 5 to 30 cm deep. Once your site has been cleared,
find out how thick the surface soil is. On this basis plan the construction method for your dikes
and the removal and storage of the surface soil.
Fig 13: Remove the surface soil
4. Stake out clearly the areas of the site from where the surface soil should be removed, as was
done earlier before the clearing started.
5. Excavate to the desired depth and transport the surface soil away from the construction site.
6. To be able to dig out this surface soil without too much effort, it might be necessary to loosen
it by ploughing. In exceptional cases, you may have to rip the soil with a tractor first, before
starting excavation. Use as many shanks as possible, at low speed and maximum soil
penetration, to reach best efficiency. For small areas, the soil may be loosened using a pick.
17 | P a g e
2.1.2.3 PCC
Plain Cement Concrete (PCC) is also called as Cement Concrete (CC) or Blinding
Concrete.
It is used for levelling, bedding for footings, grade slabs, concrete roads etc.
PCC is used to provide non-porous, rigid, impervious, firm and levelled bed for laying
RCC, where earth is soft and yielding.
PCC can be use over brick flat soling or without brick flat soling.
PCC also used as filler like lump concrete; this is a mix of PCC and boulder.
It consists of cement, sand and coarse aggregates mixed with water in the specified
proportions, the following proportions are mostly using:-
For foundation – Concrete Mix M10 (1:3:6) i.e.; 1 part of cement, 3 parts of sand and 6 parts
of coarse aggregates).
For Car park – Concrete Mix M15 (1:2:4) i.e.; 1 part of cement, 2 parts of sand and 4 parts of
coarse aggregates).
 The ratio of PCC at site was 1:4:8.
Specifications for Plain Cement Concrete (PCC)
Materials Specifications:
Aggregate shall be of invert materials and should be clean, dense, hard, sound, durable, non-
absorbent and capable of developing good bond with mortar.
Coarse aggregate shall be of hard broken stone of granite or similar stone, free from dust, dirt
and other foreign matters. The stone ballast shall be of 20mm size and smaller. Fine aggregate
shall be of coarse sand consisting of hard, sharp and angular grains and shall pass through a
screen of 5mm square mesh. Sand shall be of standard specifications, clean and free from dust,
dirt and organic matter. Sea sand shall not be used.
Cement shall be fresh Portland cement of standard ISI specifications and shall have the required
tensile and compressive stresses and fineness.Water shall be clean and free from alkaline and
acid matters and suitable for drinking purposes.
18 | P a g e
Proportion Specifications:
1:2:4 (Cement: sand: stone ballast) by volume when specified. Minimum compressive strength
of concrete of 1:2:4 proportion shall be 140 kg/cm2 in 7 days.
2.1.2.4 Masonry:
Masonry is the building of structures from individual units laid in and bound together by
mortar; the term masonry can also refer to the units themselves. The common materials of
masonry construction are brick, building stone such as marble, granite, travertine, and
limestone, cast stone, concrete block, glass block, and cob. Masonry is generally a highly
durable form of construction. However, the materials used, the quality of the mortar and
workmanship, and the pattern in which the units are assembled can significantly affect the
durability of the overall masonry construction. A person who constructs masonry is called a
mason or bricklayer.
Structural limitations:
Masonry has high compressive strength under vertical loads but has low tensile strength
(against twisting or stretching) unless reinforced. The tensile strength of masonry walls can be
increased by thickening the wall, or by building masonry piers (vertical columns or ribs) at
intervals. Where practical, steel reinforcements such as wind posts can be added.
Random Rubble Masonry:
Random Rubble Masonry is slightly superior to unsourced rubble masonry. In this form the
stones used in the work are hammer or chisel-dressed. The stones are not suitably shaped or
finished and as such the elevation of this type of stone masonry shows irregular shaped stones
with non-uniform joints. In a good work the face stones are of uniform colour and
approximately equal in size. The height of stones should be greater than their breadth or length
of tail into the work.
19 | P a g e
Fig 14: Random Rubble Masonry
At least one fourth of the face stone should tail back into the heading for ensuring proper
strength to the work. The quoins and the through stones are provided in a similar manner as
described earlier. The thickness of joints should not exceed 13 mm.
Fig 15: Random Rubble Masonry Wall Design
20 | P a g e
2.1.2.5 Coping:
The protective top member of any vertical construction such as a wall or chimney. A coping
may be masonry, metal, or wood, and is usually sloped or bevelled to shed water in such a
way that it does not run down the vertical face of the wall. Copings often project out from a
wall with a drip groove on the underside.
Fig 16: Coping
2.1.2.6 Plaster:
Plaster is a building material used for the protective and/or decorative coating of walls and
ceilings and for moulding and casting decorative elements. In English "plaster" usually means
a material used for the interiors of buildings, while "render" commonly refers to external
applications. Another imprecise term used for the material is stucco, which is also often used
for plasterwork that is worked in some way to produce relief decoration, rather than flat
surfaces.The most common types of plaster mainly contain either gypsum, lime, or cement, but
all work in a similar way.
Types:
1. Gypsum plaster
2. Lime plaster
3. Cement plaster
21 | P a g e
4. Heat resistant plaster
Cement Plaster:
Cement plaster is a mixture of suitable plaster, sand, Portland cement and water which is
normally applied to masonry interiors and exteriors to achieve a smooth surface. Interior
surfaces sometimes receive a final layer of gypsum plaster. Walls constructed with stock bricks
are normally plastered while face brick walls are not plastered.
Cement plaster is usually applied in a single coat or double coat. Double coat plaster is applied
where thickness of plaster is required to be more than 15 mm or when it is required to get a
very fine finish.
 At the site we applied 20 mm thick plaster on masonry. The process of applying a
double coat cement plaster on wall surface consists of the following 4 steps.
1-Preparation of surface for plastering
2-Ground work for plaster
3-Applying first coat (or under coat or rendering coat)
4-Applying second coat (or finishing coat or fine coat)
2.2 Water Treatment Plant & Process
2.2.1 Water & its Standards:
Water is a precious commodity. Most of the earth water is sea water. About 2.5% of the water
is fresh water that does not contain significant levels of dissolved minerals or salt and two third
of that is frozen in ice caps and glaciers. In total only 0.01% of the total water of the planet is
accessible for consumption. Clean drinking water is a basic human need. Unfortunately, more
than one in six people still lack reliable access to this precious resource in developing world.
Water purification is the process of removing undesirable chemicals, biological contaminants,
suspended solids and gases from contaminated water. The goal is to produce water fit for a
specific purpose. Most water is disinfected for human consumption (drinking water), but water
purification may also be designed for a variety of other purposes, including fulfilling the
22 | P a g e
requirements of medical, pharmacological, chemical and industrial applications. The methods
used include physical processes such as filtration, sedimentation, and distillation; biological
processes such as slow sand filters or biologically active carbon; chemical processes such as
flocculation and chlorination and the use of electromagnetic radiation such as ultraviolet light.
Purifying water may reduce the concentration of particulate matter including suspended
particles, parasites, bacteria, algae, viruses, fungi, as well as reducing the amount of a range of
dissolved and particulate material derived from the surfaces that come from runoff due to rain.
The standards for drinking water quality are typically set by governments or by international
standards. These standards usually include minimum and maximum concentrations of
contaminants, depending on the intended purpose of water use.
2.2.1.1. Water Quality Standards:
 The definition of water quality depends on the intended use of the water which may be
either human consumption or it may be for industries, irrigation, recreation etc.
 Depending upon the proposed use of water, certain water quality criteria are established
and based on these criteria quality standards are specified by health and other regulation
agencies.
 Different types of water require different level of water purity.
 Drinking water requires highest standard of purity whereas water of lower quality.
23 | P a g e
Table 2 (Part 1): INDIAN STANDARD SPECIFICATIONS FOR DRINKING WATER
24 | P a g e
Table 2 (Part 2): INDIAN STANDARD SPECIFICATIONS FOR DRINKING WATER
2.2.2 Quality of Water:
Parameters of water which are required to be tested for determining the quality of water can be
divided into:
Physical
Chemical
Microbiological
2.2.2.1 Physical Parameters:
It includes -Turbidity
Colour
Odour
Taste
Temperature
25 | P a g e
Turbidity: It is the large amount of suspended matter such as clay, silt, some other finely
divided organic matter present in the water, and it will appear to be muddy or cloudy or turbid
in appearance. Turbidity is measured by turbid meter and is expressed in mg/l.
Fig 17: Turbidity Fig 18: Colour
Colour:
Dissolved organic matter from decaying vegetation or some inorganic materials such as
coloured soils, may impart colour to water. The excessive growth of algae also may impart
colour to the water. The presence of colour in water is not objectionable from health point of
view, but may spoil the colour of clothes being washed in it.
Colour of water is measured by platinum cobalt scale. It should not exceed 20 and should be
less than 10.
Taste and Odour:
 The dissolved organic matter, inorganic salts, or dissolved gases may impart tastes and
odours to the water, which generally occurs together.
 Taste and odour may be due to presence of dissolved gases such as H2S, CH4, CO2,
O2, etc. Some mineral substances like Iron, sulphates, may impart taste to water.
 For drinking purpose water should not contain any undesirable taste and odour.
 Taste of water should be agreeable to the consumers.
 And odour of water is measured in terms of threshold odour number.
 For public supplies threshold odour no should be 1 and should not exceed 3.
26 | P a g e
Temperature:
Temperature of water has no practical significance however temperature of water should be
above 10°C while temperature above 25°C are considered as objectionable.
2.2.2.2 Chemical Parameters:
a) Solids ( Suspended, Dissolved, Volatile)
b) Hardness
c) Chlorides
d) pH
e) Dissolved gases like Oxygen, Carbon dioxide, Hydrogen supplied
f) Nitrogen compound like Nitrates, Nitrites.
g) Metals and other in organic substance like fluoride, iron, and manganese, lead, Arsenic,
Iodide, and Cadmium.
2.2.2.3 Microbiological Parameters:
It Includes various microorganisms i.e. bacteria, virus, protozoa, worms, present in water it
may be pathogenic or non-pathogenic.
2.2.3 Water Treatment:
2.2.3.1 Aims:
The aims of the treatment are to remove unwanted constituents in the water and to make it safe
to drink or fit for a specific purpose in industry or medical applications. Widely varied
techniques are available to remove contaminants like fine solids, micro-organisms and some
dissolved inorganic and organic materials, or environmental persistent pharmaceutical
pollutants. The choice of method will depend on the quality of the water being treated, the cost
of the treatment process and the quality standards expected of the processed water.
The processes below are the ones commonly used in water purification plants. Some or most
may not be used depending on the scale of the plant and quality of the raw (source) water.
2.2.3.2 Pre-treatment:
Pumping and containment – The majority of water must be pumped from its source or directed
into pipes or holding tanks. To avoid adding contaminants to the water, this physical
27 | P a g e
infrastructure must be made from appropriate materials and constructed so that accidental
contamination does not occur.
Screening (see also screen filter) – The first step in purifying surface water is to remove large
Debris such as sticks, leaves, rubbish and other large particles which may interfere with
subsequent purification steps. Most deep groundwater does not need screening before other
purification steps.
Fig 19: Screening
Storage – Water from rivers may also be stored in bankside reservoirs for periods between a
few days and many months to allow natural biological purification to take place. This is
especially important if treatment is by slow sand filters. Storage reservoirs also provide a buffer
against short periods of drought or to allow water supply to be maintained during transitory
pollution incidents in the source river.
Pre-chlorination – In many plants the incoming water was chlorinated to minimize the growth
of fouling organisms on the pipe-work and tanks. Because of the potential adverse quality
effects, this has largely been discontinued.
2.2.3.3 Coagulation and flocculation:
In coagulation we add a chemical such as alum which produces positive charges to neutralize
the negative charges on the particles, particles can stick together, forming larger particles more
easily removed, process involves addition of chemical (e.g. alum) rapid mixing to dissolve the
chemical, distribute it evenly throughout water. Small particles are not removed efficiently by
sedimentation because they settle too slowly & they may also pass through filters easier to
remove if they are clumped together. Coagulated to form larger particles, but they don't because
they have a negative charge repel each other (like two north poles of a magnet).
28 | P a g e
In flocculation now the particles have a neutral charge can stick together. The water flows into
a tank with paddles that provide slow mixing, it bring the small particles together to form larger
particles called flocks. Mixing is done quite slowly and gently in the flocculation step.
Fig 20: Flocculation
If the mixing is too fast, the flocks will break apart into small particles that are difficult to
remove by sedimentation or filtration.
2.2.3.4 Sedimentation:
Water flows to a tank called a sedimentation basin. Gravity causes the flocks to settle to the
bottom. Large particles settle more rapidly than small particles. It would take a very long time
for all particles to settle out and that would mean we would need a very large sedimentation
basin. So the clarified water, with most of the particles removed, moves on to the filtration step
where the finer particles are removed.
Fig 21: Sedimentation
29 | P a g e
2.2.3.5 Filtration:
After separating most flock, the water is filtered as the final step to remove remaining
suspended particles and unsettled flock.
Rapid sand filters:
The most common type of filter is a rapid sand filter. The top layer removes organic
compounds, which contribute to taste and odour. The space between sand particles is larger
than the smallest suspended particles, so simple filtration is not enough. Most particles pass
through surface layers but are trapped in pore spaces or adhere to sand particles. Effective
filtration extends into the depth of the filter. This property of the filter is key to its operation:
if the top layer of sand were to block all the particles, the filter would quickly clog.
Slow sand filters:
Slow sand filters may be used where there is sufficient land and space, as the water must be
passed very slowly through the filters. These filters rely on biological treatment processes for
their action rather than physical filtration. The filters are carefully constructed using graded
layers of sand, with the coarsest sand, along with some gravel, at the bottom and finest sand at
the top. Drains at the base convey treated water away for disinfection. Filtration depends on
the development of a thin biological layer, called the zoogleal layer, on the surface of the filter.
An effective slow sand filter may remain in service for many weeks or even months if the pre-
treatment is well designed and produces water with a very low available nutrient level which
physical methods of treatment rarely achieve. Very low nutrient levels allow water to be safely
sent through distribution systems with very low disinfectant levels, thereby reducing consumer
irritation over offensive levels of chlorine and chlorine by-products.
Fig 22: Rapid Sand Filter Fig 23: Slow Sand Filter
30 | P a g e
2.2.3.6 Removal of ions and other dissolved substances:
Ultrafiltration membranes use polymer membranes with chemically formed microscopic pores
that can be used to filter out dissolved substances avoiding the use of coagulants. The type of
membrane media determines how much pressure is needed to drive the water through and what
sizes of micro-organisms can be filtered out.
Ion exchange: Ion exchange systems use ion exchange resin- or zeolite-packed columns to
replace unwanted ions. The most common case is water softening consisting of removal of
Ca2+ and Mg2+ ions replacing them with benign (soap friendly) Na+ or K+ ions. Ion exchange
resins are also used to remove toxic ions such as nitrite, lead, mercury, arsenic and many others.
2.2.3.7 Disinfection:
With particles removed, it only remains to provide disinfection, so that no pathogens remain in
the water. Protozoan pathogens are large in size and have been removed with other particles.
Bacteria and viruses are now destroyed by addition of a disinfectant.
Chlorination:
Enough chlorine is added so that some remains to go out in the water distribution system,
protecting the public once the water leaves the plant.
31 | P a g e
2.3 Strengthening of Foundation
2.3.1 Introduction:
The need to improve the ability of an existing building to withstand seismic forces arises
usually from the evidence of damage and poor behaviour during a recent earthquake. It can
arise also from calculations or by comparisons with similar buildings that have been damaged
in other places. While in the first case the owner can be rather easily convinced to take measures
to improve the strength of his building, in the second case dwellers that have much more
stringent day-to-day needs are usually reluctant to invest money in the improvement of seismic
safety.
2.3.2 Strengthening of existing buildings:
The seismic behaviour of old existing buildings is affected by their original structural
inadequacies, material degradation due to time, and alterations carried out during use over the
years such as making new openings, addition of new parts inducing dissymmetry in plan and
elevation, etc. The possibility of substituting them with new earthquake resistant buildings is
generally neglected due to historical, artistic, social and economical reasons. The complete
replacement of the buildings in a given area will also lead to destroying a number of social and
human links. Therefore seismic strengthening of existing damaged or undamaged buildings
can be a definite requirement in same areas.
2.3.3 Improving the Foundation:
Seismic strengthening of foundations before or after the earthquake is the most involved task
since it may require careful underpinning operations. Some alternatives are given below for
preliminary consideration of the strengthening scheme.
(i) Introducing new load bearing members including foundations to relieve the already loaded
members. Jacking operations may be needed in this process.
(ii) Improving the drainage of the area to prevent saturation of foundation soil to obviate any
problems of liquefaction which may occur because of poor drainage.
(iii) Providing apron around the building to prevent soaking of foundation directly and draining
off the water.
32 | P a g e
(iv) Adding strong elements in the form of reinforced concrete strips attached to the existing
foundation part of the building. These will also bind the various wall footings and may be
provided on both sides of the wall, to avoid digging the floor inside the building, the extra
width could be provided only on the outside of external walls. The extra width may be provided
above the existing footing or at the level of the existing footing. In any case the reinforced
concrete strips and the walls have to be linked by a number of keys, inserted into the existing
footing.
Fig 24: Improving a foundation by inserting lateral concrete beams
33 | P a g e
2.4 Tendering
2.4.1 From where it comes:
There is an always need of some construction work, repair work, replacement and this need
will continue till so far the world alive. The work is decided by people, committee, and higher
authorities. Every human being or an organisation are not capable to draw self-requirements
i.e. they need professional and experienced worker or company. Around 15 -20 years back the
public decide to hire which company because there are negligible competition but now the
market developed well itself that the public cannot decide to hire which one. So there need
comes to find the experience, budget etc. of the builders. Now the term “Tender” starts and
rules & regulations were made.
2.4.2 What is Tender?
A tender is a submission made by a prospective supplier in response to an invitation to tender.
It makes an offer for the supply of goods or services. In construction, the main tender process
is generally for the selection of the contractor that will construct the works.
2.4.3 Contract Strategy:
 The buyer, in consultation with all interested parties, legal, engineering, finance,
production and, most importantly, the end user, should agree as early as possible the
overall strategy for the project or purchase. Plans should be agreed concerning the
operation of the tendering exercise, writing the detailed specification, the scope and
appearance of draft tender documents, the timescales of the process and the team which
will have responsibility for the evaluation of bids.
 A timetable of anticipated events is essential and should be completed, at least in draft
form, as early as possible to ensure target dates are achieved. Named persons with
responsibility for each activity should be included to allow them time to allocate the
necessary dates and times.
 The buyer should ensure all likely requirements for the goods, or services, are identified
and included in the bid process. There is nothing worse than nearing completion of one
bid
34 | P a g e
 Process only to find someone else in the enterprise has a need for the same or very
similar product. A whole company business plan, if properly prepared, should remove
the risk of ignoring total requirements.
 The duration of any contract, particularly service contracts should be agreed at the
outset. In Central Government, for instance, this is normally between three and five
years, in order to ensure that the procurement organisation continues to buy in the best
market, and that access to public sector contracts is open. It is a commercial decision
taking into account all costs involved in the tendering process, the balance between the
value of long-term contract against short-term ones and any known likely changes in
the requirement for the service.
 Further areas for the team to consider are improvements in technology, the likelihood
of new contractors or suppliers entering a competitive market, price adjustments that
could be foreseen, and the dangers that may arise from long-term contact with one
supplier. Potential conflict of interests should be considered both within the company
and bid evaluation group and, in the service area, the possibility of contractors being
invited to tender for conflicting or concurrent activities.
How to Prepare and Evaluate Tenders - Knowledge How To
Quality standards must be clearly defined to ensure there is no ambiguity, particularly between
the requirements set out in the specification and information provided through any discussions
or other documents. All critical aspects of the contract should be identified and it might be
necessary to determine and show how they will be identified and measured. It could be that
approval of a quality plan is a condition of contract and a requirement for assessment of the
bids.
The sort of information which might be included on a quality plan is:
• The named people involved in implementing the quality plan
• How the contract will be monitored, measured and reported upon
• The procedures and controls in place
• The quality of materials and how these are to be defined
• How the service or materials will be provided
35 | P a g e
• The method for resolution of difficulties or disputes
• Details of any improvements incorporated or proposed.
All documentation must clearly detail the responsibilities of the customer and supplier with
respect to testing and/or acceptance of the goods or service on completion of supply.
In the event of a failure, by a supplier or contractor, details should be included to the effect that
the customer reserves the right to employ another supplier or contractor to complete the
contract, with all resulting costs becoming the responsibility of the failed contractor or supplier.
Use of any existing services must be detailed. Care must be taken, however, to ensure such
requirements will not limit the scope or range of possible cost savings. As an example, would
any training provide better value if carried out off-site rather than utilizing in-company training
resources?
When drawing up a specification and/or contract details the need for competition must be
maintained. As an example, gains anticipated during the life of the project or process, or from
more efficient equipment, must be considered when preparing any specification or tender
where the exercise is a retendering one.
2.4.4 Invitations to tender:
Invitations to tender should normally consist of the following sections; it will however depend
upon the complexity of the requirement.
Part 1 - Defines the contract, giving details of timescales for commencement and completion
Part 2 - Contains the “Conditions of Contract” wherein the commercial details are explained in
simple language; where appropriate the draft contract can be included.
Part 3 - Should be a pricing schedule
Part 4 - Will give details of the scope of the work or services or the quantity and frequency of
requirements of goods or services to be supplied.
Part 5 - Depending on the size of the contract, should highlight all procedural requirements,
such as third party inspection, variations if any, the communication route and names of people
involved in discharging contractual requirements and so on.
36 | P a g e
Part 6 - The specification; if a “Technical” specification this should give full details of the
work, supply or service to be undertaken; current preference is for this to be a “performance”
or “functional” specification, which allows freedom of choice to the bidder as to how best to
meet the requirement.
Part 7 - Any drawings and/or plans required to allow bidders to ensure their offered goods or
service comply, not only to the specification, but also with those drawings originally issued as
part of the Technical Specification.
Part 8 - Should contain details of free issue goods, if any, and the arrangement for such free
issue.
Part 9 - Gives details of submission of bids, such as time and precise location, that late bids
will not be accepted, the date of bid opening and whether it will be open or closed. Open
bidding is where all bidders have the option of being present to view and note total prices
submitted by all bidders. Often used overseas as a means of avoiding accusations of corrupt
practices as only those bids opened, registered, and with their total cost announced, will be
considered in the evaluation process. Where appropriate, information should be included on
the tender evaluation methods that should be adopted.
Part 10 - Will detail the terms and conditions anticipated in any resultant contract, so that
bidders may take any “special” conditions into consideration when compiling their tender. All
invitations to tender for a specific product or service must be identical on issue.
2.4.5 Decision of the review panel:
Having agreed which tender provides best overall value for money, taking into account price,
quality, timing, and costs in use where appropriate, a decision can be taken about the award of
the contract
Most organizations will have established procedures, including levels of delegated authority,
usually on a defined financial limit basis, under which managers at different levels may take
decisions on award of contracts.
Where decisions have to be referred upwards, recommendations should be put forward,
detailing the factors, including price and performance, which have defined the best offer. These
should be shown in comparison with the details of the nearest competing bids, where
37 | P a g e
appropriate, with reasons for their rejection. A spread-sheet presentation of the competing bids
is often helpful in recording the factors leading to the final recommendation or decision.
Following acceptance of the recommendation for contract award, the formal contract should
be prepared. In some circumstances, post-tender negotiations can be initiated with the
successful tenderer to improve details of the successful offer, such as delivery programs,
packaging and transport details.
2.5 Road Resurfacing
2.5.1 Introduction:
Resurfacing of a road pavement or other paved area is undertaken for one or more of the
following reasons:
• To add strength to the construction to prolong its life;
• To correct the surface profile and thus improve riding quality and surface water drainage;
• To restore skid-resistance to an old surfacing polished by traffic;
• To restore the aesthetic appearance of a worn, aged surface.
Figure 25: Road Resurfacing
As long as an existing pavement is of adequate strength and correct profile, the last two
objectives can be achieved by the application of a surface treatment such as surface dressing
(the technique described in which a bitumen spray is applied to the road surface followed by
an overall application of Chippings. However, in many situations there is a need to correct
38 | P a g e
defective longitudinal/transverse profiles, and frequently the pavement needs to be
strengthened so that it can continue to carry traffic satisfactorily. In such circumstances a new
asphalt surfacing will be required. With judicious choice of a suitable surfacing,
Strength and riding quality can be restored, an adequate skid resistance provided and a
surfacing of pleasing appearance obtained which will give many years of trouble-free service
There is a large and sometimes bewildering choice of asphalt surfacing materials, each with its
own properties and uses. To ensure maximum benefit and durability from them when used in
resurfacing, it is essential that the work is given detailed consideration both before and during
its execution. Resurfacing is not simply a matter of “we’ll put another couple of inches on”.
This information sheet is intended to provide a brief aide-memoire of the main considerations
to be made at the design stage and in carrying out the work.
2.5.2 Points need to be considered:
When preparing for resurfacing work the following main points need to be considered:
• The strength of the existing construction - is it adequate to carry future anticipated loadings
and if not, what degree of strengthening is required?
• The shape (regularity) of the existing surface - is it adequate to ensure satisfactory riding
quality, surface water drainage and uniform compaction of any overlay material or does it need
regulating?
• Thickness - will existing fixed levels, such as kerbs, accesses and bridge headrooms, permit
an overlay to be used or will a particular thickness of the existing construction need to be
removed before a new surfacing is laid?
• Mechanical key/adhesion - will the existing surface with the application of a bond coat
provide adequate key/adhesion to any overlay that is applied?
• The new material - what type of material should be laid?
39 | P a g e
2.5.3 Detailed Considerations
2.5.3.1 Strength:
The strength of the existing construction is all-important when considering resurfacing. Laying
of new material on an unsound substrate is simply wasting time and money. Cracks and crazing
on an existing surfacing are an indication of inadequate strength in the road structure below
and such areas should be taken out and reconstructed. Potholes may simply be localized failures
of a surface course or they may be an indication of more deep-seated weakness. A very poor
shape in a road, even without cracks, is often also an indication of insufficient strength and
sooner or later more definite signs of weakness in the form of cracks are likely to appear. Such
areas, therefore, may also need reconstruction.
In the case of major highways, it is possible from knowledge of the construction, traffic
loadings and transient deflection measurements to assess the strength and probable life of a
road and to estimate the amount of overlay strengthening required. Highway authorities use
detailed procedures for this purpose, but in situations other than major highways, in-depth
examination or knowledge of the existing construction, particularly in obviously weak areas,
may be sufficient to give some indication of the future load-carrying ability and what upgrading
or remedial action is required. Alternatively, mechanical testing to assess the existing strength
of the construction may be desirable.
2.5.3.2 Shape
Frequently, particularly in urban areas, resurfacing is required to restore the surface profile of
a pavement which is reasonably structurally sound. This happens for instance on roads which
have been excavated during the repair or installation of services beneath. Weak places, potholes
for instance, may well require reinstatement of the pavement to some depth. Thereafter
decisions are needed on the types and thicknesses of surfacing to be used, and whether it is
necessary or advantageous to plane off the old surface before laying the new.
Excessive variations in the thickness of asphalt surfacing layers due to the materials being laid
on a poorly shaped substrate are to be avoided as they can cause variations in initial compaction
with subsequent variations in durability of the surfacing and reduction in the riding quality.
British Standard recommends the minimum surface regularity tolerances, in terms of maximum
depression under a 3-metre straight edge, that are required under both single-layer and two-
layer surfacings to ensure a satisfactory uniformity of thickness of these layers.
40 | P a g e
Cases will arise where the thickness of a regulating course will vary from a maximum at the
sides of the road reducing towards the crown. In such circumstances the nominal size or stone
content of the material used will depend on the minimum thickness. As the material will be
covered by a surface course and also in order to make the work more practical, the range of
thicknesses for which a size of material may be used in regulating work is greater than in
normal straightforward surfacing. Unless hot rolled asphalt or dense asphalt concretes are used,
it is advisable to let traffic run on the regulated surface for some time so that any minor
differential compaction arising from thickness variations can occur and be accommodated
when laying the surface course.
When an existing road is structurally sound but limited improvement in its shape is required
(e.g. where only the surface course is deformed or showing signs of wear) or where existing
levels/headroom do not permit any appreciable thickness of overlay, an appropriate thickness
of existing surfacing can be removed by cold planing prior to application of a new surface
course. If the original layer thickness is known, the thickness that will be planed out must be
such that there is either at least 15mm of the original surfacing remaining after planing, or the
whole thickness is removed to prevent the risk of mechanically generating a plane of weakness
at the interface of the two old asphalt layers. This weakness may be evidenced by small thin
slabs of the old surfacing, commonly called “biscuits”, being broken out by the planer.
Accumulations of surface treatments which might have given rise to an excessively soft or
‘fatty’ surfacing may similarly need to be removed. However, these materials will have
provided an impervious seal to the road and care should be taken to ensure that this seal is not
completely removed or is replaced by the new surfacing without delay.
After cold planning all that is normally required before application of a new surfacing is for
the planed area to be thoroughly cleaned and bond-coated.
2.5.4 Mechanical/Key Adhesion:
A smooth or highly polished surface will not give any significant mechanical key to an overlay
and roughening of the surface, e.g. by planning or scrabbling, should be considered,
particularly if on a gradient. Areas of major oil or other contamination should also be removed.
Special grades of bitumen emulsion are available for this purpose and in applying them the
following points should be borne in mind:
41 | P a g e
a. Appropriate guidance on the rates of spread of tack and bond coat are found in British
Standard.
b. The application should be by the use of a pressure sprayer and the rate of spread should be
uniform, with no puddles allowed to form.
c. The emulsion must be allowed to break (that is, to change from brown to black) before the
new material is laid, otherwise it will form a slip coat.
d. The emulsion should not be spread so far in advance of the surfacing work that it is removed
by traffic or otherwise rendered ineffective.
2.5.5 Special Considerations:
When overlaying an existing concrete road or paved area with an asphalt surfacing, there is a
specific problem which arises from the joints or cracks in the concrete. Concrete slabs expand
and contract with changes in temperature creating movement in the joints. This movement will
propagate cracks in the asphalt overlay. Experience has shown that even with relatively thick
overlays this ‘reflective cracking’ will appear in time, although the thicker the surfacing the
slower will be the rate of appearance. Pavement design research has indicated that an asphalt
surfacing thickness of 180mm or more will be needed to significantly delay the onset of
reflective cracking. In view of this, it is recommended that a two-layer surfacing (binder course
plus surface course) is adopted when surfacing over concrete, wherever existing levels permit.
2.5.6 Laying:
It is strongly advised that all surfacing work is entrusted to well-established specialist surfacing
contractors and not to itinerant or casual callers. A list of specialist surfacing contractors in any
area, who are members of the Mineral Products Association, is available from the address given
on this information sheet.
For very lightly trafficked or pedestrian areas, Asphalt Concrete surface course (open, medium
or fine graded) would normally be adequate. The binder course is a very important layer in the
road structure as it experiences high stress and is at risk of exposure to water.
42 | P a g e
Chapter 3
Scope of training
3.1 Scope:
I have done my training at Heavy Water Plant. So I am well aware & have more knowledge
about the plant, its working procedure, their rules & regulations etc. These thing will take me
ahead as compare to other candidates because generally each industry have similar work plan.
By doing the training we will get chances in vast field as I have learnt five different topics of
civil engineering so in future I can engage in any of the following field:
a) Environmental Engineering
b) Contractor
c) Transportation Engineering
d) Structure Engineering
e) Site Engineering
43 | P a g e
Chapter 4
Objective of training
Each work has its own objective. We did our vocational training for:
1. Familiar with basic facts related to that field to overcome difficulties and to become a
successful person.
2. After the completions of study most of engineering students are expected do serve an
industrial institution, may be under Govt. or a private sector so there it will help.
3. To aware of industrial Environment and be familiar with the equipment, their
performance, faults, protection system and maintenance.
4. To co-relate the theory and the practical field.
5. To learn about the general working of the plant and their specific field.
44 | P a g e
Chapter 5
Complete work plan with Time
Week 1
Day Name of activity
Day 1 Issued the Training Pass
Day 2 Safety Class
Day 3 Contd.
Day 4 Contd.
Day 5 Visit the Control Room
Day 6 Learnt about Job Hazard Analysis
WEEK 2
Day Name of activity
Day 1 Visited Water Treatment Plant
Day 2 Get the Data of WTP
Day 3 Understanding the process of filtration
Day 4 Read the water permissible limits
Day 5 Visited the cation & anion bed
Day 6 Find the objective of pond
WEEK 3
Day Name of activity
Day 1 Inspection the area of the pond
Day 2 Survey
Day 3 Survey
Day 4 Site clearance
Day 5 Site clearance
Day 6 PCC work
45 | P a g e
WEEK 4
Day Name of activity
Day 1 Masonry & coping
Day 2 Plaster
Day 3 Welding work at the entrance
Day 4 Tendering Class
Day 5 Tendering Class
Day 6 Tendering Class
WEEK 5
Day Name of activity
Day 1 Fill the pond with water
Day 2 Saw how they made bill
Day 3 Inspection the dumping tank
Day 4 Excavation for foundation
Day 5 Started work to increase the thickness of
foundation
Day 6 Finished the work of foundation
WEEK 6
Day Name of activity
Day 1 Preparation of the existing base course layer
Day 2 Application of tuck coat
Day 3 Preparation and placing of remix
Day 4 Rolling
Day 5 Quality control of bituminous concrete
Day 6 Finished surface
46 | P a g e
Chapter 6
Result & Outcome
The aim of the internship is to address more practical knowledge for student. So, I found a
practical knowledge at the site as much possible within the four month. The knowledge we
have learn in the class is helpful to get those practical or real work in the site and totally
different from the actual knowledge gained from the class. Thus I found some knowledge in
the site which helps me to work with the site environment or site peoples.
At the site, I have learnt the following seven different fields of civil engineering:
1. Water Treatment Plant
2. Tendering
3. Construction of pond
4. Strengthening of foundation
5. Road Resurfacing
6. Safety Measurements
7. Job Hazard Analysis
47 | P a g e
Chapter 7
Experiment
The following practical has been done there:
1. Turbidity Test
2. pH Test
3. Sieve Analysis of fine and coarse aggregate
4. Aggregate Impact Value
5. Cube Test
48 | P a g e
Chapter 8
Conclusion
This report is prepared on the basis of study in Heavy Water Plant and a knowledge gain by
me. The most important aspect during my training was to study of WTP, Tendering and Road
Resurfacing. During this training I got a lot of knowledge from experts who taught me in about
the different Civil engineering fields. I got a real knowledge of practical environment.
Civil is a branch in which practical knowledge is main consideration. Just by reading books we
cannot get the main aspect. To be aware of practical world training is very much necessary.
During this time I was able to relate the theoretical part to the practical one, which relieved
many doubts. According to theory of electrical there has been a great demand of practical
knowledge everywhere so what we got here. To be a good engineer it is very much necessary
to undergo a practical training that's what our Career Point University recommends.
So I am very much thankful to all the group of Heavy Water plant who provided such a good
help and their time to acknowledge us.
49 | P a g e
Appendix
9.1 Specification of water standards taken for water treatment at
HWPK
Table 3: Quality of Raw Water
S. No. Parameter Design (ppm) Actual
1. T.H. as CaCo3 88 90-102
2. Ca Hardness - 68-70
3. Mg Hardness - 30
4. TDS 150 160-170
5. pH 8.7 8.1-8.4
6. Cl 7.0 18-21
7. Turbidity (SiO2) 15 NTU 1-3 NTU
8. Dissolve O2 6 5-8
Table 4: Quality of filter Water
S. No. Parameter Design (ppm) Actual
1. HCL Hardness 88 118-146
2. Chloride Cl-
7 24-34
3 Turbidity (SiO2) 2 3-5.3
4. Sulphate 27 8.3- 15.6
5. Dissolve O2 6 -
50 | P a g e
An Example of NIT:-
Job Hazard Analysis:
A job hazard analysis is a technique that focuses on job tasks as a way to identify hazards
before they occur. It focuses on the relationship between the worker, the task, the tools, and the
work environment. Ideally, after you identify uncontrolled hazards, you will take steps to
eliminate or reduce them to an acceptable risk level.
Why is job hazard analysis important?
Many workers are injured and killed at the workplace every day in the United States. Safety
and health can add value to your business, your job, and your life. You can help prevent
workplace injuries and illnesses by looking at your workplace operations, establishing proper
job procedures, and ensuring that all employees are trained properly. One of the best ways to
determine and establish proper work procedures is to conduct a job hazard analysis. A job
hazard analysis is one component of the larger commitment of a safety and health management
system.
51 | P a g e
References
1. Water Supply Engineering by S. K. Garg
2. http://www.hwb.gov.in/
3. http://www.ustudy.in/node/2757
4. http://www.practicaldiy.com/general-building/plaster-repairs/plaster-repair-large.php
5. http://www.gharexpert.com/tips/articles/Construction/1038/Cement-Plastering-1038-
Ratio-Cement-Sand-%E2%80%98Plastering%E2%80%99_0
6. http://www.dolandemolition.com/site-clearance/

More Related Content

What's hot

Problems and prospects of setting up a thermal power plant (1)
Problems and prospects of setting up a thermal power plant (1)Problems and prospects of setting up a thermal power plant (1)
Problems and prospects of setting up a thermal power plant (1)subhadip manna
 
Photovoltaic solar farm: earthing system design for cost reduction and syste...
Photovoltaic solar farm: earthing system design for  cost reduction and syste...Photovoltaic solar farm: earthing system design for  cost reduction and syste...
Photovoltaic solar farm: earthing system design for cost reduction and syste...IJECEIAES
 
Project report on THDC Hydrop Power Plant Summer Training
Project report on THDC Hydrop Power Plant Summer TrainingProject report on THDC Hydrop Power Plant Summer Training
Project report on THDC Hydrop Power Plant Summer TrainingCharu Kandpal
 
Internship front pages (3 files merged)
Internship front pages (3 files merged)Internship front pages (3 files merged)
Internship front pages (3 files merged)tp jayamohan
 
Hydro Electric Power plant
Hydro Electric Power plantHydro Electric Power plant
Hydro Electric Power plantRatan Debnath
 
Solar plant ppt by ritesh kumawat
Solar plant ppt by ritesh kumawatSolar plant ppt by ritesh kumawat
Solar plant ppt by ritesh kumawatRitesh Kumawat
 
200085263 project-report
200085263 project-report200085263 project-report
200085263 project-reporthomeworkping4
 
Bhilai steel plant training report /
Bhilai steel plant  training report /Bhilai steel plant  training report /
Bhilai steel plant training report /Deepash Rajak
 
Hydro electricity and hydro power plant
Hydro electricity and hydro power plantHydro electricity and hydro power plant
Hydro electricity and hydro power plantRaj Kumar Parihar
 
Bhilai Steel Plant presentation
Bhilai Steel Plant presentationBhilai Steel Plant presentation
Bhilai Steel Plant presentationPratyush Raj
 
Hydro power plant presentation project by pratik diyora 100420106008
Hydro power plant presentation project by pratik diyora 100420106008Hydro power plant presentation project by pratik diyora 100420106008
Hydro power plant presentation project by pratik diyora 100420106008Pratik Diyora
 
Pumped storage hydro power plant
Pumped storage hydro power plantPumped storage hydro power plant
Pumped storage hydro power plantCraZzy Shubh
 
Solar energy proposal by MGE
Solar energy proposal by MGESolar energy proposal by MGE
Solar energy proposal by MGEViet Ngo Thanh
 
LAKHRA power generation company limited(LPGCL)
LAKHRA power generation company limited(LPGCL)LAKHRA power generation company limited(LPGCL)
LAKHRA power generation company limited(LPGCL)MUHAMMAD AZMAT ULLAH BAIG
 

What's hot (20)

Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Problems and prospects of setting up a thermal power plant (1)
Problems and prospects of setting up a thermal power plant (1)Problems and prospects of setting up a thermal power plant (1)
Problems and prospects of setting up a thermal power plant (1)
 
solar cooler
solar coolersolar cooler
solar cooler
 
hari_new resume
hari_new resumehari_new resume
hari_new resume
 
Photovoltaic solar farm: earthing system design for cost reduction and syste...
Photovoltaic solar farm: earthing system design for  cost reduction and syste...Photovoltaic solar farm: earthing system design for  cost reduction and syste...
Photovoltaic solar farm: earthing system design for cost reduction and syste...
 
Project report on THDC Hydrop Power Plant Summer Training
Project report on THDC Hydrop Power Plant Summer TrainingProject report on THDC Hydrop Power Plant Summer Training
Project report on THDC Hydrop Power Plant Summer Training
 
Internship front pages (3 files merged)
Internship front pages (3 files merged)Internship front pages (3 files merged)
Internship front pages (3 files merged)
 
Energy storage
Energy storageEnergy storage
Energy storage
 
traning report of bhilai steel plant...
traning report of  bhilai steel plant...traning report of  bhilai steel plant...
traning report of bhilai steel plant...
 
Hydro Electric Power plant
Hydro Electric Power plantHydro Electric Power plant
Hydro Electric Power plant
 
Solar plant ppt by ritesh kumawat
Solar plant ppt by ritesh kumawatSolar plant ppt by ritesh kumawat
Solar plant ppt by ritesh kumawat
 
Energy project report on hydropower
Energy project report on hydropowerEnergy project report on hydropower
Energy project report on hydropower
 
200085263 project-report
200085263 project-report200085263 project-report
200085263 project-report
 
Bhilai steel plant training report /
Bhilai steel plant  training report /Bhilai steel plant  training report /
Bhilai steel plant training report /
 
Hydro electricity and hydro power plant
Hydro electricity and hydro power plantHydro electricity and hydro power plant
Hydro electricity and hydro power plant
 
Bhilai Steel Plant presentation
Bhilai Steel Plant presentationBhilai Steel Plant presentation
Bhilai Steel Plant presentation
 
Hydro power plant presentation project by pratik diyora 100420106008
Hydro power plant presentation project by pratik diyora 100420106008Hydro power plant presentation project by pratik diyora 100420106008
Hydro power plant presentation project by pratik diyora 100420106008
 
Pumped storage hydro power plant
Pumped storage hydro power plantPumped storage hydro power plant
Pumped storage hydro power plant
 
Solar energy proposal by MGE
Solar energy proposal by MGESolar energy proposal by MGE
Solar energy proposal by MGE
 
LAKHRA power generation company limited(LPGCL)
LAKHRA power generation company limited(LPGCL)LAKHRA power generation company limited(LPGCL)
LAKHRA power generation company limited(LPGCL)
 

Viewers also liked

Industrial Training Report(HLL) Darshana 2016
Industrial Training Report(HLL) Darshana 2016Industrial Training Report(HLL) Darshana 2016
Industrial Training Report(HLL) Darshana 2016Darshana Sankalpa
 
Industrial report for civil engg. training
Industrial report for civil engg. trainingIndustrial report for civil engg. training
Industrial report for civil engg. trainingRam1239
 
Summer training report in civil engineering
Summer training report in civil engineeringSummer training report in civil engineering
Summer training report in civil engineeringalok0025
 
Internship Final Report
Internship Final Report Internship Final Report
Internship Final Report Nadia Nahar
 
Slideshare Project
Slideshare ProjectSlideshare Project
Slideshare Projectsuzrocky
 

Viewers also liked (10)

Industrial Training Report(HLL) Darshana 2016
Industrial Training Report(HLL) Darshana 2016Industrial Training Report(HLL) Darshana 2016
Industrial Training Report(HLL) Darshana 2016
 
John salmon
John salmonJohn salmon
John salmon
 
Project data
Project dataProject data
Project data
 
Industrial report for civil engg. training
Industrial report for civil engg. trainingIndustrial report for civil engg. training
Industrial report for civil engg. training
 
Summer training report in civil engineering
Summer training report in civil engineeringSummer training report in civil engineering
Summer training report in civil engineering
 
Internship Report
Internship ReportInternship Report
Internship Report
 
Internship Final Report
Internship Final Report Internship Final Report
Internship Final Report
 
Industrial Training Report-1
Industrial Training Report-1Industrial Training Report-1
Industrial Training Report-1
 
Slideshare Project
Slideshare ProjectSlideshare Project
Slideshare Project
 
internship report
internship reportinternship report
internship report
 

Similar to Heavy Water Plant Kota training report (CIVIL)

construction of barrage cum bridge and canal works
construction of barrage cum bridge and canal worksconstruction of barrage cum bridge and canal works
construction of barrage cum bridge and canal worksPANEM SRINIVASULU
 
SUMMER RESEARCH REPORT
SUMMER RESEARCH REPORTSUMMER RESEARCH REPORT
SUMMER RESEARCH REPORTAditya Bajaj
 
nucliar power plant
nucliar power plantnucliar power plant
nucliar power plant94600banti
 
Rohit pandey bhel training report
Rohit pandey bhel training reportRohit pandey bhel training report
Rohit pandey bhel training reportROHIT PANDEY
 
Ghazi Barotha Hydropower project Internship Report
Ghazi Barotha Hydropower project Internship ReportGhazi Barotha Hydropower project Internship Report
Ghazi Barotha Hydropower project Internship ReportIhtisham Saeed
 
Maducon projects Ltd, Internship project
Maducon projects Ltd, Internship projectMaducon projects Ltd, Internship project
Maducon projects Ltd, Internship projectRenu Gopal
 
A report on combine system of air cooler and water chiller by Sanjay Neolia.
A report on combine system of air cooler and water chiller by Sanjay Neolia.A report on combine system of air cooler and water chiller by Sanjay Neolia.
A report on combine system of air cooler and water chiller by Sanjay Neolia.SANJAY NEOLIA
 
Industrial training report of thermal power plant
Industrial training report of thermal power plantIndustrial training report of thermal power plant
Industrial training report of thermal power plantRavinder Jangid
 
PROJECT 7TH SEM REPORT
PROJECT 7TH SEM REPORTPROJECT 7TH SEM REPORT
PROJECT 7TH SEM REPORTPradip Vasoya
 
BHEL summer internship report
BHEL summer internship reportBHEL summer internship report
BHEL summer internship reportShivam Teotia
 
Report on "IFFCO-KANDLA UNIT by Darshan-JEC KUKAS,JAIPUR
Report on "IFFCO-KANDLA UNIT by Darshan-JEC KUKAS,JAIPURReport on "IFFCO-KANDLA UNIT by Darshan-JEC KUKAS,JAIPUR
Report on "IFFCO-KANDLA UNIT by Darshan-JEC KUKAS,JAIPURDarshan Singh
 
Electricity Generation Using Staircase
Electricity Generation Using StaircaseElectricity Generation Using Staircase
Electricity Generation Using StaircaseShubham Patel
 
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...Probir Bidhan
 
Performance Evaluation of Small Hydro Power Plant
Performance Evaluation of Small Hydro Power PlantPerformance Evaluation of Small Hydro Power Plant
Performance Evaluation of Small Hydro Power PlantGirish Gupta
 
Turbine manufacturing at BHEL Haridwar
Turbine manufacturing at BHEL HaridwarTurbine manufacturing at BHEL Haridwar
Turbine manufacturing at BHEL HaridwarABHISHEK CHAURASIYA
 

Similar to Heavy Water Plant Kota training report (CIVIL) (20)

Report on practical training NTPC BARH
Report on practical training NTPC BARHReport on practical training NTPC BARH
Report on practical training NTPC BARH
 
NHPC Training Report
NHPC Training ReportNHPC Training Report
NHPC Training Report
 
construction of barrage cum bridge and canal works
construction of barrage cum bridge and canal worksconstruction of barrage cum bridge and canal works
construction of barrage cum bridge and canal works
 
SUMMER RESEARCH REPORT
SUMMER RESEARCH REPORTSUMMER RESEARCH REPORT
SUMMER RESEARCH REPORT
 
nucliar power plant
nucliar power plantnucliar power plant
nucliar power plant
 
Final Project
Final ProjectFinal Project
Final Project
 
madhu
madhumadhu
madhu
 
Rohit pandey bhel training report
Rohit pandey bhel training reportRohit pandey bhel training report
Rohit pandey bhel training report
 
Ghazi Barotha Hydropower project Internship Report
Ghazi Barotha Hydropower project Internship ReportGhazi Barotha Hydropower project Internship Report
Ghazi Barotha Hydropower project Internship Report
 
Maducon projects Ltd, Internship project
Maducon projects Ltd, Internship projectMaducon projects Ltd, Internship project
Maducon projects Ltd, Internship project
 
A report on combine system of air cooler and water chiller by Sanjay Neolia.
A report on combine system of air cooler and water chiller by Sanjay Neolia.A report on combine system of air cooler and water chiller by Sanjay Neolia.
A report on combine system of air cooler and water chiller by Sanjay Neolia.
 
Industrial training report of thermal power plant
Industrial training report of thermal power plantIndustrial training report of thermal power plant
Industrial training report of thermal power plant
 
PROJECT 7TH SEM REPORT
PROJECT 7TH SEM REPORTPROJECT 7TH SEM REPORT
PROJECT 7TH SEM REPORT
 
BHEL summer internship report
BHEL summer internship reportBHEL summer internship report
BHEL summer internship report
 
Report on "IFFCO-KANDLA UNIT by Darshan-JEC KUKAS,JAIPUR
Report on "IFFCO-KANDLA UNIT by Darshan-JEC KUKAS,JAIPURReport on "IFFCO-KANDLA UNIT by Darshan-JEC KUKAS,JAIPUR
Report on "IFFCO-KANDLA UNIT by Darshan-JEC KUKAS,JAIPUR
 
Electricity Generation Using Staircase
Electricity Generation Using StaircaseElectricity Generation Using Staircase
Electricity Generation Using Staircase
 
Arun Kumar
Arun KumarArun Kumar
Arun Kumar
 
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...
 
Performance Evaluation of Small Hydro Power Plant
Performance Evaluation of Small Hydro Power PlantPerformance Evaluation of Small Hydro Power Plant
Performance Evaluation of Small Hydro Power Plant
 
Turbine manufacturing at BHEL Haridwar
Turbine manufacturing at BHEL HaridwarTurbine manufacturing at BHEL Haridwar
Turbine manufacturing at BHEL Haridwar
 

Recently uploaded

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 

Heavy Water Plant Kota training report (CIVIL)

  • 1. “CONSTRUCTION WORKS AT HWPK” A INDUSTRIAL TRAINING REPORT Submitted in partial fulfillment of the requirements for the degree of Bachelor of Technology In Civil Engineering By LOKESH CHOUDHARY UID: K10673 Submitted to the Ms. Arpita Sharma Department of Civil Engineering Career Point University, Kota-325003 Rajasthan (India) 2013-17
  • 2. CERTIFICATE This is to certify that the industrial training project report entitled “CONSTRUCTION WORKS AT HWPK”, in partial fuilfillment of the requirements for the degree of Bachelor Of Technology submitted to the Department of Civil Engineering at Career Ponit University, Kota (Raj.) the record of work carried out by them under my supervision and guidance. In my opintion the submitted work has reached a level requred for being accepted for industrioal trarning examination. Date: 19 September, 2016 Lokesh Choudhary UID- K10673 This is to certify that above statement made by the candidates are correct to the best of my knowledge. Evaluator Mr. Sitesh Singh Civil Engineering Department Career Point University , Kota,(RAJ) i
  • 3. ABSTRACT During 60 days training session, I have completed many task and learn following skills related to construction world- 1. Surveying on pond construction. 2. Tendering process 3. Increase the thickness of foundation 4. Water Treatment Plant process 5. Road resurfacing 6. Different construction equipment (machines) and their use in construction site. 7. Concrete is a vital material in any construction of reinforced concrete and is the main constituent or ingredient of any reinforced concrete structure. 8. To organize our tasks and assignment, we need to analyze our problems and assignment, and to formulate a good solution to the problem. 9. In working environment, teamwork is vital in contributing to a strong organization. Teamwork is also essential in reaching the goals of the organization as an entity. ii
  • 4. ACKNOWLEDGEMENT First of all I feel great pleasure in acknowledging my deepest gratitude to Hon’ble Vice Chancellor providing me opportunity of practical training. I am also thankful to Mr. TS Reddy, Head of Civil Department at HWPK for arranging such helpful training for me. I also thankful to Mr. Sitesh Singh for delight guidance. I find it hard to express my grateful to the Almighty in words for bestowing upon me his deepest blessings and providing me with the most wonderful opportunity in the form of life of a human being and for the warmth and kindness he has showered upon me by giving me life’s best. Last but not least I am thankful to all who helped me direct or indirect for my endeavor. Date: 19 September 2016 Lokesh Choudhary (UID: K10673) iii
  • 5. CANDIDATES’S DECLARATION I here declare that work which is being in presented in the Training Report entitled “Construction Works at HWPK” in partial fulfillment for the award of Degree of ‘Bachelor Technology in Dept. of Civil Engineering and submitted to the department of Civil Engineering Career Point University is a record of my own investigation carried of Ms. Arpita Sharma Head, Civil Engineering department. I have not submitted the matter presented in this report anywhere for the award of any other Degree Lokesh Choudhary UID-K10673 Career Point University iv
  • 6. TABLE OF CONTENTS CERTIFICATE ABSTRACT ACKNOWLEDGEMENT DECLARATION TABLE OF CONTENTS LIST OF FIGURES LIST OF TABLE LIST OF ABBREVIATIONS Page No. i ii iii iv v-vii viii ix x Chapter 1 Introduction 1-7 1.1 Heavy Water Board……………………………………………………………. 1.1.1 The project need……………………………………………………….. 1.1.2 About HWB…………………………………………………………… 1 1 1 1.2 1.3 Heavy Water Plant, Kota……………………..………….……………………. 1.2.1 Introduction……………………………………………………………… 1.2.2 HWPK- Technology Breakthrough in India…………………………….. What is heavy water? …………………………………………………………. 1.3.1 Uses of heavy water……………………………………………………... 1.3.2 Process Description……………………………………………………… 3 3 3 3 4 5 Chapter 2 Literature Review 8-41 2.1 Construction of pond…………………………...…………………………….... 8 2.1.1 Pond……………………………..………………………………………. 8 2.1.2 Steps used for build a pond…………………………..………………….. 9 2.2 Water Treatment Plant & Process……………………………………………... 21 2.2.1 Water & its standards……………………………………………………. 22
  • 7. 2.2.2 Quality of water………………………...……………………………….. 2.2.3 Water Treatment………………………………………………………… 24 26 2.3 Strengthening of foundation…………………………………………………... 31 2.3.1 Introduction ……………………………………………………………... 31 2.3.2 Strengthening of existing building………………………………………. 2.3.3 Improving the foundation……………………………………………….. 31 31 2.4 Tendering……………………………………………………………………… 33 2.4.1 From where it comes……………………………………………………. 33 2.4.2 What is tender? …………………………………………………………. 2.4.3 Contract Strategy………………………………………………………... 2.4.4 Invitation to Tender……………………………………………………… 2.4.5 Decision of the review panel…………………………………………….. 33 33 35 36 2.5 Road resurfacing……………………………………………………………..... 37 2.5.1 Introduction……………………………………………………………… 37 2.5.2 Points need to be considered…………………………………………….. 2.5.3 Detailed Considerations…………………………………………………. 2.5.4 Mechanical Adhesion………………………….………………………… 2.5.5 Special Considerations…………………………………………………... 2.5.6 Laying 38 39 40 41 41 Chapter 3 Scope Of Training 42 Chapter 4 Objective Of Training 43 Chapter 5 Chapter 6 Chapter 7 Complete Work plan With Timelines Result & Outcome Experimental 44-45 46 47
  • 9. LIST OF FIGURES Figure No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Name of Figure Heavy water plants in India Cooling & Hot tower at RR site Girdler Sulphide Process Survey Tripod Digital Theodolite Rough levelling with the circular level Levelling with the plate level Digital theodolite keys Digital LCD monitor Tree Slump Preparing for a pond Remove the surface soil Random rubble masonry Random Rubble Masonry Wall Design Coping Turbidity Colour Screening Flocculation Sedimentation Rapid sand filter Slow sand filter Improving a foundation Road Resurfacing Page No. 2 5 6 10 11 11 12 12 13 13 14 15 16 19 19 20 25 25 27 28 28 29 29 32 37 viii
  • 10. LIST OF TABLE Table No. 1 2 Name of Table General Data about HWPK Indian standard Specification for drinking water (Part 1) Indian standard Specification for drinking water (Part 2) Page No. 7 23 24 ix
  • 11. LIST OF ABBREVIATIONS 1. HWB Heavy Water Board 2. DAE Department of Atomic Energy 3. ISO Indian Organization for Standardization 4. USA United States of America 5. RR site Rawatbhata Rajasthan site 6. Km Kilometer 7. Ev Electronvolt 8. atm Atmosphere 9. MmHg Millimeter of mercury 10. MT/year Metric ton per year 11. Cm Centimeter 12. PCC Plain Cement Concrete 13. NIT Notice Inviting Tender 14. Ca Calcium 15. Mg Magnesium 16. Na Sodium 17. K Potassium 18. MWe 19. HWPK Megawatt of electricity Heavy Water Plant Kota x
  • 12. 1 | P a g e Chapter 1 Introduction 1.1 Heavy Water Board 1.1.1 The Project Need: Department of Atomic Energy embarked on an ambitious programme of producing nuclear power of 10,000 MWe which required setting up a number of heavy water plants. This was also the time when the need for a separate organisation to oversee the planning and setting up of Heavy Water Plants was strongly felt. Accordingly an organisation known as the Heavy Water Projects was set up on May 1, 1969. 1.1.2 About HWB: Heavy Water Board (HWB), a constituent unit of Industries and Minerals Sector under Department of Atomic Energy, is primarily responsible for production of Heavy Water (Deuterium Oxide-D2O). Heavy Water Board and its Plants are ISO Certified for Quality Management System, Environment Management System and Occupational Health & Safety Management System. Heavy Water Board has successfully exported Heavy Water to countries viz. South Korea, China and USA. This included development of the processes from laboratory synthesis through scale up to commercially viable plants. The solvents produced by HWB have found acceptability not only in DAE but outside as well. HWB also has been successful in engineering / setting up and operating the boron isotope enrichment units based on different technologies to meet the requirements of fast breeder reactor programme. The other activities also include development of cryogenic process system and recovery of rare material from secondary sources. Apart from the above, HWB has opened avenues for development and promotion of non- nuclear applications of Heavy Water and Deuterium. HWB has been successful in
  • 13. 2 | P a g e demonstrating the improved thermal stability of deuterated oral polio vaccine. HWB also has been working with various institutions in further development in these applications. 1.1.2.1 HWB in India: 1. Heavy Water Plant, Baroda (Gujarat) 2. Heavy Water Plant, Hazira (Gujarat) 3. Heavy Water Plant, Kota (Rajasthan) 4. Heavy Water Plant, Manuguru (Andhra Pradesh) 5. Heavy Water Plant, Talcher (Orissa) 6. Heavy Water Plant, Thal (Maharashtra) 7. Heavy Water Plant, Tuticorin (Tamilnadu) Fig 1: Heavy water plants in India
  • 14. 3 | P a g e 1.2 Heavy Water Plant, Kota 1.2.1 Introduction: Heavy Water Plant, Kota is India’s first plant based on Hydrogen sulphide- Water Dual Temperature Exchange Process, set up indigenously. Plant is sited in close proximity to Rajasthan Atomic Power Station (RR site), Anushakti with it is integrated for supply of process steam and electrical power. Anushakti is nearly 65 km from Kota Railway Station in Kherli block under Tehsil of Rawatbhata in Chittorgarh Distict, Rajasthan. HWP, Kota is located in the picturesque landscape of lush green hills on the bank of Rana Pratap Sagar reservoir of Chambal River. Project activities for this plant began in early 70’s with “Ground Breaking” on July 7, 1972. Commissioning activities started in early 80’s. Nuclear grade heavy water was first produced from Distillation Unit in 1981 using off grade heavy water. Trial production run of Exchange Unit was accomplished in 1983 and full commercial operation of the plant started in April, 1985. 1.2.2 HWPK- Technology Breakthrough in India: Heavy Water Plant, Kota was conceptualized, designed & engineered based on pilot plant study at BARC. Development work led to a number of innovative concepts in design, engineering, construction and operation, many of which were being tried out for first time in India. Heavy water technology development in India, from grass root level to robust one, is a true example pf self- reliance. The experience and expertise gained at Kota plant was utilized for setting up double capacity plant at Manuguru. This technology proved to be a game changer in Indian Heavy Water Programme making our country self- reliant and the largest global producer. 1.3 What is Heavy Water? Heavy water (D2O) is oxide of Deuterium (heavier isotope of hydrogen). Its nuclear properties display a significant variation which makes it an extremely efficient material for use as moderator in a nuclear reactor. Deuterium and its compounds have many promising application
  • 15. 4 | P a g e in advanced technology and life science. Heavy water resembles normal water in appearance and chemical properties. Heavy Water has great similarity in its physical and chemical properties to ordinary water. It is noon-radioactive and apparently harmless to human being. 1.3.1 Uses of Heavy water: Heavy water is largely used in the production of nuclear energy and a number of modern research experiments as given below: a.) As a Neutron moderator: Moderator is required in a thermal reactor to slow down the neutrons produced in the fission reaction to .025 ev (thermal reaction) so that the chain reaction can be sustained. Different moderators normally in use are Heavy Water, Graphite, Beryllium and Light water. Heavy Water is an excellent moderator. A good moderator should have excellent slowing down power and low absorption cross section for neutrons. b.) For production of Deuterium: Heavy water is used for the production of deuterium and its compounds. c.) As a Tracer Compound: It is used as a tracer compound for the study of the study of the mechanism of chemical reactions and in biochemical reactions. d.) Coolant: Heat energy produced in the fission reactor will be removed by coolant. Water is an excellent coolant that can remove the heat from the feed. Heavy Water is used as a primary coolant to transport heat generated by the fission reaction to secondary coolant, light water. In Gas cooled reactors carbon di-oxide gas is used as coolant. Coolant transports heat to secondary coolant, i.e. water for generation of steam at an appropriate pressure for running steam turbines. Steam turbines drive generators to generate Electricity.
  • 16. 5 | P a g e 1.3.2 Process Description: Water from the nearby Rana Pratap Sagar lake, purified of suspended and dissolved impurities forms the process feed with the D20 enriched from 150 ppm (0.015%) in the feed to 15% D20 by chemical exchange with H2S and later by vacuum distillation to produce 99.8% D20. The exchange unit is arranged in a 3 stage cascade. The first stage handling large quantities of process water and H2S gas, consists of three pairs of cold and hot towers operating at 30 deg. C. and 130 deg. C. respectively. The second and third stage each consist of one pair of cold and hot towers. The purified water enters the top of first stage cold tower and travels down while hydrogen sulphide gas entering the bottom of the tower meets the water in counter current way on tower internals and the exchange of deuterium takes place. In cold tower the water gets enriched with respect to deuterium while gas gets depleted in deuterium concentration. In hot tower the reverse reaction takes place i.e. the gas gets enriched instead of liquid. By proper liquid and gas flow rates with gas in closed circuit in a pair of towers, a small quantity of enriched liquid can be withdrawn from the bottom of the cold tower as a net product. This is further enriched in a similar way in 2nd and 3rd stages. The hot tower bottoms liquid coming from the first stage is divided into two parts. One part is recycled to the top of humidification section located at the bottom of hot tower for heat recovery while the other part constitutes the waste. Before discarding the waste to the environment it is necessary to recover the H2S dissolved in the waste. For this purpose a waste stripper is provided to strip H2S by direct steam stripping and the evolved gas and steam are put back to first stage hot towers. The enriched water from the 3rd stage is stripped off its H2S in a product stripper and fed to the distillation unit for further enrichment upto nuclear grade. Fig 2: Cooling and Hot tower at RR site
  • 17. 6 | P a g e This process is known as the Girdler sulfide (GS) process. Fig 3: Girdler sulfide process As H2S gas is very toxic, corrosive and hazardous in nature and the plant has a dynamic hold up of 200 Te H2S, extreme care has been taken in the design of the plant, selection of equipment and materials, adhering to stringent fabrication procedures and codes. The exchange process operates at about 20 atm. pressure and at a temperature of 30 to 1200 C. while the vacuum distillation plant works at a pressure of 100 mm Hg absolute. The isotopic exchange reaction which is the heart of the technology is carried out with the aid of specially designed efficient trays. The H2S gas required for the process is manufactured in a separate unit at the plant premises by the chemical reaction between sodium sulphide and sulphuric acid. Very elaborate and sensitive H2S detection instrumentation is provided not only in the plant but also in the surrounding areas to monitor the environment.
  • 18. 7 | P a g e Table 1: General Data about HWPK Process Used H2S - H2O Exchange Process Know How Departmental Capacity of the Plant 80 MT / Year Date of Commissioning 1-4-1985 Capital cost of the Plant Rs. 7730 Lakhs Plant Area 20 Hectares Number of Employees (Man Power) 599 (as on 30.06.2012) Operating Pressure 20 Kg/Cm 2 Total Weight of Structure 2683 MTe Total Weight of Equipment 4414 MTe Weight of Heaviest Equipment 286 MTe Maximum Diameter of Equipment 4.5 M approx. Maximum Height of Towers 52 M approx. Total Length of Piping 64 Km Total length of Electrical Cables 350 Km Substation Capacity 40 MVA Connected Load 35.5 MW Power Consumption 360 MWH/Day Water Consumption 32400 M 3 /Day Steam Consumption 2640 MT/Day
  • 19. 8 | P a g e Chapter 2 Literature Review 2.1 Construction of Pond 2.1.1 Pond: A pond is a body of standing water, either natural or artificial, that is usually smaller than a lake. They may arise naturally in floodplains as part of a river system, or they may be somewhat isolated depressions (examples include vernal pools and prairie potholes). Usually they contain shallow water with marsh and aquatic plants and animals. 2.1.1.1 Objective for making Pond: As the plant comes under central government department, it fulfils all the ecological and environment friendly structures. So here is a large no. of trees and greenery.  As where is a large amount of such a greenery there is always standing a chance of fire. While the plant has a separate system of water pipelines in case of fire but the main objective of this pond was to prepare such a dangerous accident.  As the plant is eco-friendly, there are some animals also so the second objective of the pond is to slake their thirst.  In agriculture, treatment ponds may reduce nutrients released downstream from the pond. They may also provide irrigation reservoirs at times of drought.  Waste stabilization ponds are used as a low-cost method for wastewater treatment.  In the Indian subcontinent, Hindu temples usually have a pond nearby so that pilgrims can take baths. These ponds are considered sacred.
  • 20. 9 | P a g e 2.1.2 Steps used for build a pond: Survey Site clearance PCC Masonry Coping Plaster 2.1.2.1 Survey: Construction surveying or building surveying (otherwise known as "staking", "stake-out", "lay- out" or "setting-out") is to stake out reference points and markers that will guide the construction of new structures such as roads or buildings. These markers are usually staked out according to a suitable coordinate system selected for the project. Elements of the construction survey:  Survey existing conditions of the future work site, including topography, existing buildings and infrastructure, and underground infrastructure whenever possible (for example, measuring invert elevations and diameters of sewers at manholes);  Stake out lot corners, stake limit of work and stake location of construction trailer (clear of all excavation and construction)  Stake out reference points and markers that will guide the construction of new structures  Verify the location of structures during construction;  Provide horizontal control on multiple floors.  Conduct an As-Built survey: a survey conducted at the end of the construction project to verify that the work authorized was completed to the specifications set on plans.
  • 21. 10 | P a g e Fig 4: Survey Coordinate systems used in construction: Land surveys and surveys of existing conditions are generally performed according to geodesic coordinates. However for the purposes of construction a more suitable coordinate system will often be used. During construction surveying, the surveyor will often have to convert from geodesic coordinates to the coordinate system used for that project. Chainage or station: In the case of roads or other linear infrastructure, a chainage (derived from Gunter's Chain - 1 chain is equal to 66 feet or 100 links) will be established, often to correspond with the center line of the road or pipeline. During construction, structures would then be located in terms of chainage, offset and elevation. Offset is said to be "left" or "right" relative to someone standing on the chainage line who is looking in the direction of increasing chainage. Other coordinate systems: In other types of construction projects, arbitrary "north-south" and "east-west" reference lines may be established, that do not necessarily correspond to true coordinates. Equipment and techniques used in construction surveying: Mainly there are three techniques: 1.) By theodolite 2.) Electronic distance measurement (EDM)
  • 22. 11 | P a g e 3.) Total stations Surveying equipment, such as levels and theodolites, are used for accurate measurement of angular deviation, horizontal, vertical and slope distances. The builder's level measures neither horizontal nor vertical angles. It simply combines a spirit level and telescope to allow the user to visually establish a line of sight along a level plane.  At the site Theodolite is used. Brief of Theodolite: A theodolite is a precision instrument for measuring angles in the horizontal and vertical planes. Theodolites are used mainly for surveying applications, and have been adapted for specialized purposes in fields like meteorology and rocket launch technology. Fig. 5: Tripod Fig 6: Digital Theodolite Levelling the theodolite: A. Referring to Fig. 7, roughly level the instrument using the circular level: 1. Turn the levelling screws A and B in opposite directions to centre the bubble along the AB axis. 2. Turn levelling screw C to bring the bubble to the centre of the circular level.
  • 23. 12 | P a g e B. Referring to Fig. 8, precisely level the instrument using the plate level. 1. Free the horizontal motion clamp and rotate the instrument horizontally until the plate level is parallel with line AB. 2. Bring the bubble to the centre of the plate level by turning screws A and B in opposite directions. 3. Rotate the instrument by 90◦ around its vertical axis and turn screw C to centre the bubble once more. 4. Repeat procedures 1. and 2. for each 90◦ rotation of the instrument and check that the bubble is correctly centered for all four points. If after 180◦ of rotation, the bubble is of center, remove half the error in the bubble centering. Check that when you have swung another 180◦ back to the initial point, the bubble offset is the same as the offset you allowed to remain in the 180◦ rotated position. Fig 7: rough levelling with the circular level Fig 8: levelling with the plate level Glossary of terms: - An alternative to measuring vertical angles in degrees, the gradient is defending as the tangent of the vertical angle with respect to the horizontal times 100%. For example, a gradient of -50% means a slope of 22:5◦ below the horizontal. - The theodolite position in which the vertical circle is on the viewer's left while he looks into the telescope. - The theodolite position in which the vertical circle is on the viewer's right while he looks into the telescope.
  • 24. 13 | P a g e - The graduated circle in the horizontal plane that the theodolite reads out to measure horizontal angles. - Thumbscrew that can be used to _x the angle of the theodolite with respect to the horizontally with the slow-motion screw. - The line of sight through the centre of the telescope crosshairs. - Small telescope whose eyepiece is near the bottom of the theodolite that looks at the directly beneath the theodolite and is used for centring. - A complete set of angle measurements performed in the face-left, then in the face-right position. w-motion screw - The adjustment screw used to translate the theodolite in the horizontal or vertical plane when the horizontal or vertical clamp is tightened. - See slow-motion screw. - The axis about which the telescope pivots. - The axis about which the horizontal circle pivots. - The graduated circle in the vertical plane that the theodolite reads out to measure vertical angles. Fig 9: Digital theodolite keys Fig 10: Digital LCD monitor
  • 25. 14 | P a g e 2.1.2.2 Site Clearance: The site should be cleared of all obstructions such as:  Woody vegetation, where the roots can cause severe cracking in pond structures such as concrete water inlets and outlets.  Tree stumps which, when decaying, can also weaken concrete pond structures by leaving voids in the soil. Fig 11: Tree Slump  Large stones, which may need to be dug out.  Hills and animal burrows, which should be dug completely; clayey soil should be tramped into the hole created. Where to clear: Define carefully the exact area to be cleared before you begin. Determine the outer corners of the pond area, which should include the entire area to be covered by the dikes. You could mark the area using wooden stakes and cord or poles. When this is done, mark out an additional area beyond the dikes to serve as a work space and a walkway around the site. Then you are ready to proceed. (a) Clear the area within the limit of the pond dikes of all vegetation, shrubs, trees (including woody roots and tree stumps) and all large stones. (b) Clear the work space and walkway around the dikes.
  • 26. 15 | P a g e (c) Clear all trees and shrubs within 10 m of dikes and pond structures and any access, water supply or drainage area. Fig 12: Preparing for a pond Proceeding with the clearing:  The clearing method to be used largely depends on the type of vegetation on the site. In open savannah country, it is a relatively easy task that can be done manually with limited special equipment  There are two basic ways to clear the woody vegetation from a site: 1.) We can cut the trees and then remove the stumps; 2.) We can fell whole trees with their roots attached.  The clearing of the site should be completed by gathering all cut vegetation, stumps, roots and large stones. All these should be removed from the work area. When conditions are dry enough, the clearing can be completed by starting a fire, which should be carefully kept under control. We can often sell the wood cleared from the site or make charcoal and sell it at a good price.
  • 27. 16 | P a g e Surface soil removal: 1. Surface soil has the highest concentration of roots and decaying organic materials. This soil is unstable as a construction material and cannot be used for the foundations of any dike or structure. Therefore the surface soil should be removed from the areas where:  Dikes and structures will be built;  Soil will be taken as a dike construction material. 2. Soil may also be required outside the site to supply topsoil for newly constructed areas such as dikes. 3. The depth of the surface soil varies from region to region. It may be totally absent or more than 1m thick. Usually the surface soil is from 5 to 30 cm deep. Once your site has been cleared, find out how thick the surface soil is. On this basis plan the construction method for your dikes and the removal and storage of the surface soil. Fig 13: Remove the surface soil 4. Stake out clearly the areas of the site from where the surface soil should be removed, as was done earlier before the clearing started. 5. Excavate to the desired depth and transport the surface soil away from the construction site. 6. To be able to dig out this surface soil without too much effort, it might be necessary to loosen it by ploughing. In exceptional cases, you may have to rip the soil with a tractor first, before starting excavation. Use as many shanks as possible, at low speed and maximum soil penetration, to reach best efficiency. For small areas, the soil may be loosened using a pick.
  • 28. 17 | P a g e 2.1.2.3 PCC Plain Cement Concrete (PCC) is also called as Cement Concrete (CC) or Blinding Concrete. It is used for levelling, bedding for footings, grade slabs, concrete roads etc. PCC is used to provide non-porous, rigid, impervious, firm and levelled bed for laying RCC, where earth is soft and yielding. PCC can be use over brick flat soling or without brick flat soling. PCC also used as filler like lump concrete; this is a mix of PCC and boulder. It consists of cement, sand and coarse aggregates mixed with water in the specified proportions, the following proportions are mostly using:- For foundation – Concrete Mix M10 (1:3:6) i.e.; 1 part of cement, 3 parts of sand and 6 parts of coarse aggregates). For Car park – Concrete Mix M15 (1:2:4) i.e.; 1 part of cement, 2 parts of sand and 4 parts of coarse aggregates).  The ratio of PCC at site was 1:4:8. Specifications for Plain Cement Concrete (PCC) Materials Specifications: Aggregate shall be of invert materials and should be clean, dense, hard, sound, durable, non- absorbent and capable of developing good bond with mortar. Coarse aggregate shall be of hard broken stone of granite or similar stone, free from dust, dirt and other foreign matters. The stone ballast shall be of 20mm size and smaller. Fine aggregate shall be of coarse sand consisting of hard, sharp and angular grains and shall pass through a screen of 5mm square mesh. Sand shall be of standard specifications, clean and free from dust, dirt and organic matter. Sea sand shall not be used. Cement shall be fresh Portland cement of standard ISI specifications and shall have the required tensile and compressive stresses and fineness.Water shall be clean and free from alkaline and acid matters and suitable for drinking purposes.
  • 29. 18 | P a g e Proportion Specifications: 1:2:4 (Cement: sand: stone ballast) by volume when specified. Minimum compressive strength of concrete of 1:2:4 proportion shall be 140 kg/cm2 in 7 days. 2.1.2.4 Masonry: Masonry is the building of structures from individual units laid in and bound together by mortar; the term masonry can also refer to the units themselves. The common materials of masonry construction are brick, building stone such as marble, granite, travertine, and limestone, cast stone, concrete block, glass block, and cob. Masonry is generally a highly durable form of construction. However, the materials used, the quality of the mortar and workmanship, and the pattern in which the units are assembled can significantly affect the durability of the overall masonry construction. A person who constructs masonry is called a mason or bricklayer. Structural limitations: Masonry has high compressive strength under vertical loads but has low tensile strength (against twisting or stretching) unless reinforced. The tensile strength of masonry walls can be increased by thickening the wall, or by building masonry piers (vertical columns or ribs) at intervals. Where practical, steel reinforcements such as wind posts can be added. Random Rubble Masonry: Random Rubble Masonry is slightly superior to unsourced rubble masonry. In this form the stones used in the work are hammer or chisel-dressed. The stones are not suitably shaped or finished and as such the elevation of this type of stone masonry shows irregular shaped stones with non-uniform joints. In a good work the face stones are of uniform colour and approximately equal in size. The height of stones should be greater than their breadth or length of tail into the work.
  • 30. 19 | P a g e Fig 14: Random Rubble Masonry At least one fourth of the face stone should tail back into the heading for ensuring proper strength to the work. The quoins and the through stones are provided in a similar manner as described earlier. The thickness of joints should not exceed 13 mm. Fig 15: Random Rubble Masonry Wall Design
  • 31. 20 | P a g e 2.1.2.5 Coping: The protective top member of any vertical construction such as a wall or chimney. A coping may be masonry, metal, or wood, and is usually sloped or bevelled to shed water in such a way that it does not run down the vertical face of the wall. Copings often project out from a wall with a drip groove on the underside. Fig 16: Coping 2.1.2.6 Plaster: Plaster is a building material used for the protective and/or decorative coating of walls and ceilings and for moulding and casting decorative elements. In English "plaster" usually means a material used for the interiors of buildings, while "render" commonly refers to external applications. Another imprecise term used for the material is stucco, which is also often used for plasterwork that is worked in some way to produce relief decoration, rather than flat surfaces.The most common types of plaster mainly contain either gypsum, lime, or cement, but all work in a similar way. Types: 1. Gypsum plaster 2. Lime plaster 3. Cement plaster
  • 32. 21 | P a g e 4. Heat resistant plaster Cement Plaster: Cement plaster is a mixture of suitable plaster, sand, Portland cement and water which is normally applied to masonry interiors and exteriors to achieve a smooth surface. Interior surfaces sometimes receive a final layer of gypsum plaster. Walls constructed with stock bricks are normally plastered while face brick walls are not plastered. Cement plaster is usually applied in a single coat or double coat. Double coat plaster is applied where thickness of plaster is required to be more than 15 mm or when it is required to get a very fine finish.  At the site we applied 20 mm thick plaster on masonry. The process of applying a double coat cement plaster on wall surface consists of the following 4 steps. 1-Preparation of surface for plastering 2-Ground work for plaster 3-Applying first coat (or under coat or rendering coat) 4-Applying second coat (or finishing coat or fine coat) 2.2 Water Treatment Plant & Process 2.2.1 Water & its Standards: Water is a precious commodity. Most of the earth water is sea water. About 2.5% of the water is fresh water that does not contain significant levels of dissolved minerals or salt and two third of that is frozen in ice caps and glaciers. In total only 0.01% of the total water of the planet is accessible for consumption. Clean drinking water is a basic human need. Unfortunately, more than one in six people still lack reliable access to this precious resource in developing world. Water purification is the process of removing undesirable chemicals, biological contaminants, suspended solids and gases from contaminated water. The goal is to produce water fit for a specific purpose. Most water is disinfected for human consumption (drinking water), but water purification may also be designed for a variety of other purposes, including fulfilling the
  • 33. 22 | P a g e requirements of medical, pharmacological, chemical and industrial applications. The methods used include physical processes such as filtration, sedimentation, and distillation; biological processes such as slow sand filters or biologically active carbon; chemical processes such as flocculation and chlorination and the use of electromagnetic radiation such as ultraviolet light. Purifying water may reduce the concentration of particulate matter including suspended particles, parasites, bacteria, algae, viruses, fungi, as well as reducing the amount of a range of dissolved and particulate material derived from the surfaces that come from runoff due to rain. The standards for drinking water quality are typically set by governments or by international standards. These standards usually include minimum and maximum concentrations of contaminants, depending on the intended purpose of water use. 2.2.1.1. Water Quality Standards:  The definition of water quality depends on the intended use of the water which may be either human consumption or it may be for industries, irrigation, recreation etc.  Depending upon the proposed use of water, certain water quality criteria are established and based on these criteria quality standards are specified by health and other regulation agencies.  Different types of water require different level of water purity.  Drinking water requires highest standard of purity whereas water of lower quality.
  • 34. 23 | P a g e Table 2 (Part 1): INDIAN STANDARD SPECIFICATIONS FOR DRINKING WATER
  • 35. 24 | P a g e Table 2 (Part 2): INDIAN STANDARD SPECIFICATIONS FOR DRINKING WATER 2.2.2 Quality of Water: Parameters of water which are required to be tested for determining the quality of water can be divided into: Physical Chemical Microbiological 2.2.2.1 Physical Parameters: It includes -Turbidity Colour Odour Taste Temperature
  • 36. 25 | P a g e Turbidity: It is the large amount of suspended matter such as clay, silt, some other finely divided organic matter present in the water, and it will appear to be muddy or cloudy or turbid in appearance. Turbidity is measured by turbid meter and is expressed in mg/l. Fig 17: Turbidity Fig 18: Colour Colour: Dissolved organic matter from decaying vegetation or some inorganic materials such as coloured soils, may impart colour to water. The excessive growth of algae also may impart colour to the water. The presence of colour in water is not objectionable from health point of view, but may spoil the colour of clothes being washed in it. Colour of water is measured by platinum cobalt scale. It should not exceed 20 and should be less than 10. Taste and Odour:  The dissolved organic matter, inorganic salts, or dissolved gases may impart tastes and odours to the water, which generally occurs together.  Taste and odour may be due to presence of dissolved gases such as H2S, CH4, CO2, O2, etc. Some mineral substances like Iron, sulphates, may impart taste to water.  For drinking purpose water should not contain any undesirable taste and odour.  Taste of water should be agreeable to the consumers.  And odour of water is measured in terms of threshold odour number.  For public supplies threshold odour no should be 1 and should not exceed 3.
  • 37. 26 | P a g e Temperature: Temperature of water has no practical significance however temperature of water should be above 10°C while temperature above 25°C are considered as objectionable. 2.2.2.2 Chemical Parameters: a) Solids ( Suspended, Dissolved, Volatile) b) Hardness c) Chlorides d) pH e) Dissolved gases like Oxygen, Carbon dioxide, Hydrogen supplied f) Nitrogen compound like Nitrates, Nitrites. g) Metals and other in organic substance like fluoride, iron, and manganese, lead, Arsenic, Iodide, and Cadmium. 2.2.2.3 Microbiological Parameters: It Includes various microorganisms i.e. bacteria, virus, protozoa, worms, present in water it may be pathogenic or non-pathogenic. 2.2.3 Water Treatment: 2.2.3.1 Aims: The aims of the treatment are to remove unwanted constituents in the water and to make it safe to drink or fit for a specific purpose in industry or medical applications. Widely varied techniques are available to remove contaminants like fine solids, micro-organisms and some dissolved inorganic and organic materials, or environmental persistent pharmaceutical pollutants. The choice of method will depend on the quality of the water being treated, the cost of the treatment process and the quality standards expected of the processed water. The processes below are the ones commonly used in water purification plants. Some or most may not be used depending on the scale of the plant and quality of the raw (source) water. 2.2.3.2 Pre-treatment: Pumping and containment – The majority of water must be pumped from its source or directed into pipes or holding tanks. To avoid adding contaminants to the water, this physical
  • 38. 27 | P a g e infrastructure must be made from appropriate materials and constructed so that accidental contamination does not occur. Screening (see also screen filter) – The first step in purifying surface water is to remove large Debris such as sticks, leaves, rubbish and other large particles which may interfere with subsequent purification steps. Most deep groundwater does not need screening before other purification steps. Fig 19: Screening Storage – Water from rivers may also be stored in bankside reservoirs for periods between a few days and many months to allow natural biological purification to take place. This is especially important if treatment is by slow sand filters. Storage reservoirs also provide a buffer against short periods of drought or to allow water supply to be maintained during transitory pollution incidents in the source river. Pre-chlorination – In many plants the incoming water was chlorinated to minimize the growth of fouling organisms on the pipe-work and tanks. Because of the potential adverse quality effects, this has largely been discontinued. 2.2.3.3 Coagulation and flocculation: In coagulation we add a chemical such as alum which produces positive charges to neutralize the negative charges on the particles, particles can stick together, forming larger particles more easily removed, process involves addition of chemical (e.g. alum) rapid mixing to dissolve the chemical, distribute it evenly throughout water. Small particles are not removed efficiently by sedimentation because they settle too slowly & they may also pass through filters easier to remove if they are clumped together. Coagulated to form larger particles, but they don't because they have a negative charge repel each other (like two north poles of a magnet).
  • 39. 28 | P a g e In flocculation now the particles have a neutral charge can stick together. The water flows into a tank with paddles that provide slow mixing, it bring the small particles together to form larger particles called flocks. Mixing is done quite slowly and gently in the flocculation step. Fig 20: Flocculation If the mixing is too fast, the flocks will break apart into small particles that are difficult to remove by sedimentation or filtration. 2.2.3.4 Sedimentation: Water flows to a tank called a sedimentation basin. Gravity causes the flocks to settle to the bottom. Large particles settle more rapidly than small particles. It would take a very long time for all particles to settle out and that would mean we would need a very large sedimentation basin. So the clarified water, with most of the particles removed, moves on to the filtration step where the finer particles are removed. Fig 21: Sedimentation
  • 40. 29 | P a g e 2.2.3.5 Filtration: After separating most flock, the water is filtered as the final step to remove remaining suspended particles and unsettled flock. Rapid sand filters: The most common type of filter is a rapid sand filter. The top layer removes organic compounds, which contribute to taste and odour. The space between sand particles is larger than the smallest suspended particles, so simple filtration is not enough. Most particles pass through surface layers but are trapped in pore spaces or adhere to sand particles. Effective filtration extends into the depth of the filter. This property of the filter is key to its operation: if the top layer of sand were to block all the particles, the filter would quickly clog. Slow sand filters: Slow sand filters may be used where there is sufficient land and space, as the water must be passed very slowly through the filters. These filters rely on biological treatment processes for their action rather than physical filtration. The filters are carefully constructed using graded layers of sand, with the coarsest sand, along with some gravel, at the bottom and finest sand at the top. Drains at the base convey treated water away for disinfection. Filtration depends on the development of a thin biological layer, called the zoogleal layer, on the surface of the filter. An effective slow sand filter may remain in service for many weeks or even months if the pre- treatment is well designed and produces water with a very low available nutrient level which physical methods of treatment rarely achieve. Very low nutrient levels allow water to be safely sent through distribution systems with very low disinfectant levels, thereby reducing consumer irritation over offensive levels of chlorine and chlorine by-products. Fig 22: Rapid Sand Filter Fig 23: Slow Sand Filter
  • 41. 30 | P a g e 2.2.3.6 Removal of ions and other dissolved substances: Ultrafiltration membranes use polymer membranes with chemically formed microscopic pores that can be used to filter out dissolved substances avoiding the use of coagulants. The type of membrane media determines how much pressure is needed to drive the water through and what sizes of micro-organisms can be filtered out. Ion exchange: Ion exchange systems use ion exchange resin- or zeolite-packed columns to replace unwanted ions. The most common case is water softening consisting of removal of Ca2+ and Mg2+ ions replacing them with benign (soap friendly) Na+ or K+ ions. Ion exchange resins are also used to remove toxic ions such as nitrite, lead, mercury, arsenic and many others. 2.2.3.7 Disinfection: With particles removed, it only remains to provide disinfection, so that no pathogens remain in the water. Protozoan pathogens are large in size and have been removed with other particles. Bacteria and viruses are now destroyed by addition of a disinfectant. Chlorination: Enough chlorine is added so that some remains to go out in the water distribution system, protecting the public once the water leaves the plant.
  • 42. 31 | P a g e 2.3 Strengthening of Foundation 2.3.1 Introduction: The need to improve the ability of an existing building to withstand seismic forces arises usually from the evidence of damage and poor behaviour during a recent earthquake. It can arise also from calculations or by comparisons with similar buildings that have been damaged in other places. While in the first case the owner can be rather easily convinced to take measures to improve the strength of his building, in the second case dwellers that have much more stringent day-to-day needs are usually reluctant to invest money in the improvement of seismic safety. 2.3.2 Strengthening of existing buildings: The seismic behaviour of old existing buildings is affected by their original structural inadequacies, material degradation due to time, and alterations carried out during use over the years such as making new openings, addition of new parts inducing dissymmetry in plan and elevation, etc. The possibility of substituting them with new earthquake resistant buildings is generally neglected due to historical, artistic, social and economical reasons. The complete replacement of the buildings in a given area will also lead to destroying a number of social and human links. Therefore seismic strengthening of existing damaged or undamaged buildings can be a definite requirement in same areas. 2.3.3 Improving the Foundation: Seismic strengthening of foundations before or after the earthquake is the most involved task since it may require careful underpinning operations. Some alternatives are given below for preliminary consideration of the strengthening scheme. (i) Introducing new load bearing members including foundations to relieve the already loaded members. Jacking operations may be needed in this process. (ii) Improving the drainage of the area to prevent saturation of foundation soil to obviate any problems of liquefaction which may occur because of poor drainage. (iii) Providing apron around the building to prevent soaking of foundation directly and draining off the water.
  • 43. 32 | P a g e (iv) Adding strong elements in the form of reinforced concrete strips attached to the existing foundation part of the building. These will also bind the various wall footings and may be provided on both sides of the wall, to avoid digging the floor inside the building, the extra width could be provided only on the outside of external walls. The extra width may be provided above the existing footing or at the level of the existing footing. In any case the reinforced concrete strips and the walls have to be linked by a number of keys, inserted into the existing footing. Fig 24: Improving a foundation by inserting lateral concrete beams
  • 44. 33 | P a g e 2.4 Tendering 2.4.1 From where it comes: There is an always need of some construction work, repair work, replacement and this need will continue till so far the world alive. The work is decided by people, committee, and higher authorities. Every human being or an organisation are not capable to draw self-requirements i.e. they need professional and experienced worker or company. Around 15 -20 years back the public decide to hire which company because there are negligible competition but now the market developed well itself that the public cannot decide to hire which one. So there need comes to find the experience, budget etc. of the builders. Now the term “Tender” starts and rules & regulations were made. 2.4.2 What is Tender? A tender is a submission made by a prospective supplier in response to an invitation to tender. It makes an offer for the supply of goods or services. In construction, the main tender process is generally for the selection of the contractor that will construct the works. 2.4.3 Contract Strategy:  The buyer, in consultation with all interested parties, legal, engineering, finance, production and, most importantly, the end user, should agree as early as possible the overall strategy for the project or purchase. Plans should be agreed concerning the operation of the tendering exercise, writing the detailed specification, the scope and appearance of draft tender documents, the timescales of the process and the team which will have responsibility for the evaluation of bids.  A timetable of anticipated events is essential and should be completed, at least in draft form, as early as possible to ensure target dates are achieved. Named persons with responsibility for each activity should be included to allow them time to allocate the necessary dates and times.  The buyer should ensure all likely requirements for the goods, or services, are identified and included in the bid process. There is nothing worse than nearing completion of one bid
  • 45. 34 | P a g e  Process only to find someone else in the enterprise has a need for the same or very similar product. A whole company business plan, if properly prepared, should remove the risk of ignoring total requirements.  The duration of any contract, particularly service contracts should be agreed at the outset. In Central Government, for instance, this is normally between three and five years, in order to ensure that the procurement organisation continues to buy in the best market, and that access to public sector contracts is open. It is a commercial decision taking into account all costs involved in the tendering process, the balance between the value of long-term contract against short-term ones and any known likely changes in the requirement for the service.  Further areas for the team to consider are improvements in technology, the likelihood of new contractors or suppliers entering a competitive market, price adjustments that could be foreseen, and the dangers that may arise from long-term contact with one supplier. Potential conflict of interests should be considered both within the company and bid evaluation group and, in the service area, the possibility of contractors being invited to tender for conflicting or concurrent activities. How to Prepare and Evaluate Tenders - Knowledge How To Quality standards must be clearly defined to ensure there is no ambiguity, particularly between the requirements set out in the specification and information provided through any discussions or other documents. All critical aspects of the contract should be identified and it might be necessary to determine and show how they will be identified and measured. It could be that approval of a quality plan is a condition of contract and a requirement for assessment of the bids. The sort of information which might be included on a quality plan is: • The named people involved in implementing the quality plan • How the contract will be monitored, measured and reported upon • The procedures and controls in place • The quality of materials and how these are to be defined • How the service or materials will be provided
  • 46. 35 | P a g e • The method for resolution of difficulties or disputes • Details of any improvements incorporated or proposed. All documentation must clearly detail the responsibilities of the customer and supplier with respect to testing and/or acceptance of the goods or service on completion of supply. In the event of a failure, by a supplier or contractor, details should be included to the effect that the customer reserves the right to employ another supplier or contractor to complete the contract, with all resulting costs becoming the responsibility of the failed contractor or supplier. Use of any existing services must be detailed. Care must be taken, however, to ensure such requirements will not limit the scope or range of possible cost savings. As an example, would any training provide better value if carried out off-site rather than utilizing in-company training resources? When drawing up a specification and/or contract details the need for competition must be maintained. As an example, gains anticipated during the life of the project or process, or from more efficient equipment, must be considered when preparing any specification or tender where the exercise is a retendering one. 2.4.4 Invitations to tender: Invitations to tender should normally consist of the following sections; it will however depend upon the complexity of the requirement. Part 1 - Defines the contract, giving details of timescales for commencement and completion Part 2 - Contains the “Conditions of Contract” wherein the commercial details are explained in simple language; where appropriate the draft contract can be included. Part 3 - Should be a pricing schedule Part 4 - Will give details of the scope of the work or services or the quantity and frequency of requirements of goods or services to be supplied. Part 5 - Depending on the size of the contract, should highlight all procedural requirements, such as third party inspection, variations if any, the communication route and names of people involved in discharging contractual requirements and so on.
  • 47. 36 | P a g e Part 6 - The specification; if a “Technical” specification this should give full details of the work, supply or service to be undertaken; current preference is for this to be a “performance” or “functional” specification, which allows freedom of choice to the bidder as to how best to meet the requirement. Part 7 - Any drawings and/or plans required to allow bidders to ensure their offered goods or service comply, not only to the specification, but also with those drawings originally issued as part of the Technical Specification. Part 8 - Should contain details of free issue goods, if any, and the arrangement for such free issue. Part 9 - Gives details of submission of bids, such as time and precise location, that late bids will not be accepted, the date of bid opening and whether it will be open or closed. Open bidding is where all bidders have the option of being present to view and note total prices submitted by all bidders. Often used overseas as a means of avoiding accusations of corrupt practices as only those bids opened, registered, and with their total cost announced, will be considered in the evaluation process. Where appropriate, information should be included on the tender evaluation methods that should be adopted. Part 10 - Will detail the terms and conditions anticipated in any resultant contract, so that bidders may take any “special” conditions into consideration when compiling their tender. All invitations to tender for a specific product or service must be identical on issue. 2.4.5 Decision of the review panel: Having agreed which tender provides best overall value for money, taking into account price, quality, timing, and costs in use where appropriate, a decision can be taken about the award of the contract Most organizations will have established procedures, including levels of delegated authority, usually on a defined financial limit basis, under which managers at different levels may take decisions on award of contracts. Where decisions have to be referred upwards, recommendations should be put forward, detailing the factors, including price and performance, which have defined the best offer. These should be shown in comparison with the details of the nearest competing bids, where
  • 48. 37 | P a g e appropriate, with reasons for their rejection. A spread-sheet presentation of the competing bids is often helpful in recording the factors leading to the final recommendation or decision. Following acceptance of the recommendation for contract award, the formal contract should be prepared. In some circumstances, post-tender negotiations can be initiated with the successful tenderer to improve details of the successful offer, such as delivery programs, packaging and transport details. 2.5 Road Resurfacing 2.5.1 Introduction: Resurfacing of a road pavement or other paved area is undertaken for one or more of the following reasons: • To add strength to the construction to prolong its life; • To correct the surface profile and thus improve riding quality and surface water drainage; • To restore skid-resistance to an old surfacing polished by traffic; • To restore the aesthetic appearance of a worn, aged surface. Figure 25: Road Resurfacing As long as an existing pavement is of adequate strength and correct profile, the last two objectives can be achieved by the application of a surface treatment such as surface dressing (the technique described in which a bitumen spray is applied to the road surface followed by an overall application of Chippings. However, in many situations there is a need to correct
  • 49. 38 | P a g e defective longitudinal/transverse profiles, and frequently the pavement needs to be strengthened so that it can continue to carry traffic satisfactorily. In such circumstances a new asphalt surfacing will be required. With judicious choice of a suitable surfacing, Strength and riding quality can be restored, an adequate skid resistance provided and a surfacing of pleasing appearance obtained which will give many years of trouble-free service There is a large and sometimes bewildering choice of asphalt surfacing materials, each with its own properties and uses. To ensure maximum benefit and durability from them when used in resurfacing, it is essential that the work is given detailed consideration both before and during its execution. Resurfacing is not simply a matter of “we’ll put another couple of inches on”. This information sheet is intended to provide a brief aide-memoire of the main considerations to be made at the design stage and in carrying out the work. 2.5.2 Points need to be considered: When preparing for resurfacing work the following main points need to be considered: • The strength of the existing construction - is it adequate to carry future anticipated loadings and if not, what degree of strengthening is required? • The shape (regularity) of the existing surface - is it adequate to ensure satisfactory riding quality, surface water drainage and uniform compaction of any overlay material or does it need regulating? • Thickness - will existing fixed levels, such as kerbs, accesses and bridge headrooms, permit an overlay to be used or will a particular thickness of the existing construction need to be removed before a new surfacing is laid? • Mechanical key/adhesion - will the existing surface with the application of a bond coat provide adequate key/adhesion to any overlay that is applied? • The new material - what type of material should be laid?
  • 50. 39 | P a g e 2.5.3 Detailed Considerations 2.5.3.1 Strength: The strength of the existing construction is all-important when considering resurfacing. Laying of new material on an unsound substrate is simply wasting time and money. Cracks and crazing on an existing surfacing are an indication of inadequate strength in the road structure below and such areas should be taken out and reconstructed. Potholes may simply be localized failures of a surface course or they may be an indication of more deep-seated weakness. A very poor shape in a road, even without cracks, is often also an indication of insufficient strength and sooner or later more definite signs of weakness in the form of cracks are likely to appear. Such areas, therefore, may also need reconstruction. In the case of major highways, it is possible from knowledge of the construction, traffic loadings and transient deflection measurements to assess the strength and probable life of a road and to estimate the amount of overlay strengthening required. Highway authorities use detailed procedures for this purpose, but in situations other than major highways, in-depth examination or knowledge of the existing construction, particularly in obviously weak areas, may be sufficient to give some indication of the future load-carrying ability and what upgrading or remedial action is required. Alternatively, mechanical testing to assess the existing strength of the construction may be desirable. 2.5.3.2 Shape Frequently, particularly in urban areas, resurfacing is required to restore the surface profile of a pavement which is reasonably structurally sound. This happens for instance on roads which have been excavated during the repair or installation of services beneath. Weak places, potholes for instance, may well require reinstatement of the pavement to some depth. Thereafter decisions are needed on the types and thicknesses of surfacing to be used, and whether it is necessary or advantageous to plane off the old surface before laying the new. Excessive variations in the thickness of asphalt surfacing layers due to the materials being laid on a poorly shaped substrate are to be avoided as they can cause variations in initial compaction with subsequent variations in durability of the surfacing and reduction in the riding quality. British Standard recommends the minimum surface regularity tolerances, in terms of maximum depression under a 3-metre straight edge, that are required under both single-layer and two- layer surfacings to ensure a satisfactory uniformity of thickness of these layers.
  • 51. 40 | P a g e Cases will arise where the thickness of a regulating course will vary from a maximum at the sides of the road reducing towards the crown. In such circumstances the nominal size or stone content of the material used will depend on the minimum thickness. As the material will be covered by a surface course and also in order to make the work more practical, the range of thicknesses for which a size of material may be used in regulating work is greater than in normal straightforward surfacing. Unless hot rolled asphalt or dense asphalt concretes are used, it is advisable to let traffic run on the regulated surface for some time so that any minor differential compaction arising from thickness variations can occur and be accommodated when laying the surface course. When an existing road is structurally sound but limited improvement in its shape is required (e.g. where only the surface course is deformed or showing signs of wear) or where existing levels/headroom do not permit any appreciable thickness of overlay, an appropriate thickness of existing surfacing can be removed by cold planing prior to application of a new surface course. If the original layer thickness is known, the thickness that will be planed out must be such that there is either at least 15mm of the original surfacing remaining after planing, or the whole thickness is removed to prevent the risk of mechanically generating a plane of weakness at the interface of the two old asphalt layers. This weakness may be evidenced by small thin slabs of the old surfacing, commonly called “biscuits”, being broken out by the planer. Accumulations of surface treatments which might have given rise to an excessively soft or ‘fatty’ surfacing may similarly need to be removed. However, these materials will have provided an impervious seal to the road and care should be taken to ensure that this seal is not completely removed or is replaced by the new surfacing without delay. After cold planning all that is normally required before application of a new surfacing is for the planed area to be thoroughly cleaned and bond-coated. 2.5.4 Mechanical/Key Adhesion: A smooth or highly polished surface will not give any significant mechanical key to an overlay and roughening of the surface, e.g. by planning or scrabbling, should be considered, particularly if on a gradient. Areas of major oil or other contamination should also be removed. Special grades of bitumen emulsion are available for this purpose and in applying them the following points should be borne in mind:
  • 52. 41 | P a g e a. Appropriate guidance on the rates of spread of tack and bond coat are found in British Standard. b. The application should be by the use of a pressure sprayer and the rate of spread should be uniform, with no puddles allowed to form. c. The emulsion must be allowed to break (that is, to change from brown to black) before the new material is laid, otherwise it will form a slip coat. d. The emulsion should not be spread so far in advance of the surfacing work that it is removed by traffic or otherwise rendered ineffective. 2.5.5 Special Considerations: When overlaying an existing concrete road or paved area with an asphalt surfacing, there is a specific problem which arises from the joints or cracks in the concrete. Concrete slabs expand and contract with changes in temperature creating movement in the joints. This movement will propagate cracks in the asphalt overlay. Experience has shown that even with relatively thick overlays this ‘reflective cracking’ will appear in time, although the thicker the surfacing the slower will be the rate of appearance. Pavement design research has indicated that an asphalt surfacing thickness of 180mm or more will be needed to significantly delay the onset of reflective cracking. In view of this, it is recommended that a two-layer surfacing (binder course plus surface course) is adopted when surfacing over concrete, wherever existing levels permit. 2.5.6 Laying: It is strongly advised that all surfacing work is entrusted to well-established specialist surfacing contractors and not to itinerant or casual callers. A list of specialist surfacing contractors in any area, who are members of the Mineral Products Association, is available from the address given on this information sheet. For very lightly trafficked or pedestrian areas, Asphalt Concrete surface course (open, medium or fine graded) would normally be adequate. The binder course is a very important layer in the road structure as it experiences high stress and is at risk of exposure to water.
  • 53. 42 | P a g e Chapter 3 Scope of training 3.1 Scope: I have done my training at Heavy Water Plant. So I am well aware & have more knowledge about the plant, its working procedure, their rules & regulations etc. These thing will take me ahead as compare to other candidates because generally each industry have similar work plan. By doing the training we will get chances in vast field as I have learnt five different topics of civil engineering so in future I can engage in any of the following field: a) Environmental Engineering b) Contractor c) Transportation Engineering d) Structure Engineering e) Site Engineering
  • 54. 43 | P a g e Chapter 4 Objective of training Each work has its own objective. We did our vocational training for: 1. Familiar with basic facts related to that field to overcome difficulties and to become a successful person. 2. After the completions of study most of engineering students are expected do serve an industrial institution, may be under Govt. or a private sector so there it will help. 3. To aware of industrial Environment and be familiar with the equipment, their performance, faults, protection system and maintenance. 4. To co-relate the theory and the practical field. 5. To learn about the general working of the plant and their specific field.
  • 55. 44 | P a g e Chapter 5 Complete work plan with Time Week 1 Day Name of activity Day 1 Issued the Training Pass Day 2 Safety Class Day 3 Contd. Day 4 Contd. Day 5 Visit the Control Room Day 6 Learnt about Job Hazard Analysis WEEK 2 Day Name of activity Day 1 Visited Water Treatment Plant Day 2 Get the Data of WTP Day 3 Understanding the process of filtration Day 4 Read the water permissible limits Day 5 Visited the cation & anion bed Day 6 Find the objective of pond WEEK 3 Day Name of activity Day 1 Inspection the area of the pond Day 2 Survey Day 3 Survey Day 4 Site clearance Day 5 Site clearance Day 6 PCC work
  • 56. 45 | P a g e WEEK 4 Day Name of activity Day 1 Masonry & coping Day 2 Plaster Day 3 Welding work at the entrance Day 4 Tendering Class Day 5 Tendering Class Day 6 Tendering Class WEEK 5 Day Name of activity Day 1 Fill the pond with water Day 2 Saw how they made bill Day 3 Inspection the dumping tank Day 4 Excavation for foundation Day 5 Started work to increase the thickness of foundation Day 6 Finished the work of foundation WEEK 6 Day Name of activity Day 1 Preparation of the existing base course layer Day 2 Application of tuck coat Day 3 Preparation and placing of remix Day 4 Rolling Day 5 Quality control of bituminous concrete Day 6 Finished surface
  • 57. 46 | P a g e Chapter 6 Result & Outcome The aim of the internship is to address more practical knowledge for student. So, I found a practical knowledge at the site as much possible within the four month. The knowledge we have learn in the class is helpful to get those practical or real work in the site and totally different from the actual knowledge gained from the class. Thus I found some knowledge in the site which helps me to work with the site environment or site peoples. At the site, I have learnt the following seven different fields of civil engineering: 1. Water Treatment Plant 2. Tendering 3. Construction of pond 4. Strengthening of foundation 5. Road Resurfacing 6. Safety Measurements 7. Job Hazard Analysis
  • 58. 47 | P a g e Chapter 7 Experiment The following practical has been done there: 1. Turbidity Test 2. pH Test 3. Sieve Analysis of fine and coarse aggregate 4. Aggregate Impact Value 5. Cube Test
  • 59. 48 | P a g e Chapter 8 Conclusion This report is prepared on the basis of study in Heavy Water Plant and a knowledge gain by me. The most important aspect during my training was to study of WTP, Tendering and Road Resurfacing. During this training I got a lot of knowledge from experts who taught me in about the different Civil engineering fields. I got a real knowledge of practical environment. Civil is a branch in which practical knowledge is main consideration. Just by reading books we cannot get the main aspect. To be aware of practical world training is very much necessary. During this time I was able to relate the theoretical part to the practical one, which relieved many doubts. According to theory of electrical there has been a great demand of practical knowledge everywhere so what we got here. To be a good engineer it is very much necessary to undergo a practical training that's what our Career Point University recommends. So I am very much thankful to all the group of Heavy Water plant who provided such a good help and their time to acknowledge us.
  • 60. 49 | P a g e Appendix 9.1 Specification of water standards taken for water treatment at HWPK Table 3: Quality of Raw Water S. No. Parameter Design (ppm) Actual 1. T.H. as CaCo3 88 90-102 2. Ca Hardness - 68-70 3. Mg Hardness - 30 4. TDS 150 160-170 5. pH 8.7 8.1-8.4 6. Cl 7.0 18-21 7. Turbidity (SiO2) 15 NTU 1-3 NTU 8. Dissolve O2 6 5-8 Table 4: Quality of filter Water S. No. Parameter Design (ppm) Actual 1. HCL Hardness 88 118-146 2. Chloride Cl- 7 24-34 3 Turbidity (SiO2) 2 3-5.3 4. Sulphate 27 8.3- 15.6 5. Dissolve O2 6 -
  • 61. 50 | P a g e An Example of NIT:- Job Hazard Analysis: A job hazard analysis is a technique that focuses on job tasks as a way to identify hazards before they occur. It focuses on the relationship between the worker, the task, the tools, and the work environment. Ideally, after you identify uncontrolled hazards, you will take steps to eliminate or reduce them to an acceptable risk level. Why is job hazard analysis important? Many workers are injured and killed at the workplace every day in the United States. Safety and health can add value to your business, your job, and your life. You can help prevent workplace injuries and illnesses by looking at your workplace operations, establishing proper job procedures, and ensuring that all employees are trained properly. One of the best ways to determine and establish proper work procedures is to conduct a job hazard analysis. A job hazard analysis is one component of the larger commitment of a safety and health management system.
  • 62. 51 | P a g e References 1. Water Supply Engineering by S. K. Garg 2. http://www.hwb.gov.in/ 3. http://www.ustudy.in/node/2757 4. http://www.practicaldiy.com/general-building/plaster-repairs/plaster-repair-large.php 5. http://www.gharexpert.com/tips/articles/Construction/1038/Cement-Plastering-1038- Ratio-Cement-Sand-%E2%80%98Plastering%E2%80%99_0 6. http://www.dolandemolition.com/site-clearance/