ABC_1st Progress Mtg Briefing_291014_final.ppt1. ABC WATERS PROJECT AT
PANG SUA POND AND
TOA PAYOH LORONG 8
5th Progress Meeting
DATE : 29 October 2014
2. Agenda of Meeting
Organization Chart (updated)
Site Progress Update
(Master Programme and Photos)
PQP Checklist
Status of clearances from Agencies/Authorities
11. Agencies / Authorities Clearance Update
S/No. Agencies Submission/ Resubmission Date Reply/ Approval Date Remarks
1 URA
1st Subm – 04 Feb 2014
2nd Subm – 19 May 2014
3rd Subm – 09 Jul 2014
1st Reply – 11 Feb 2014
2nd Reply – 16 Jun 2014
3rd Reply – 21 Jul 2014
PP and WP approved
2 BCA
ST01 (RC Seating Works)
1st Subm – 20 Aug 2014
2nd Subm – 19 May 2014
ST02 (Piling and Pilecap Works)
ST03 (Steel Structures Works)
ST01 (RC Seating Works)
1st Reply – 01 Sep 2014
1st Reply – 01 Sep 2014
ST02 (Piling and Pilecap Works)
ST03 (Steel Structures Works)
ST01 Approved
ST02 (Pending AC Comments to submit)
ST03 (In Progress)
Pending Approval (permit to start works)
3 NParks 1st Subm – 24 Oct 2014 1st Reply -
Pending Approval
(To fell trees at site storage and barge
berthing area)
(Pang Sua Pond)
(Lorong 8 Toa Payoh)
S/No. Agencies Submission/ Resubmission Date Reply/ Approval Date Remarks
1 URA 1st Subm – 05 Feb 2014 1st Reply – 26 Feb 2014 PP approved
2 BCA
In Progress