INTRODUCTION
HS-08 one component water based acrylic ester waterproofing coating is a kind of acrylate emulsion as
basic material, adding a variety of additives and fillers is processed by meticulously one-component
high quality water based waterproof coating.
MAIN FEATURE
1. Open barrels and use, simple and convenient construction, suitable for home decoration waterproof;
2. Low VOC, with water as dispersion medium, no solvent pollution, non-toxic harmless, environmental
protection products;
3. Can be in damp base construction, has good air permeability; Excellent high and low temperature
resistance;
4. Good flexibility, elongation, with excellent crack resistance.
WHERE TO USE
Roof, hutch defends, basement, of water proof and seepage proof of pool, wall and wood floor
moistureproof.
CONSTRUCTION TECHNOLOGY
1. The base level requirements: base should be solid, smooth, clean, no floating ash and oil, inside and
outside Angle should be circular. Before the construction, such as base bibulous rate is large or relatively
dry, available water along the base level, but you can't have water.
2. The coating: use a brush or through direct coating, should besmear commonly 2-3 times; Besmear
after the first pass dry (about 3 hours) before besmear to brush the second time, the second time to the
first time brushing direction perpendicular. The second time (about four hours) after dry solid can
besmear brushes a third time, and with the second time brushing direction perpendicular; In the corner
and tube root to besmear again.
3. The subsequent working procedure on the waterproof layer, should be carried out after coating is dry
solid.
2. TECHNICAL DATA SHEET
Executive Standard: JC/T864-2000
Item
Index
I II
Solid content ≥ 65%
Tensile strength ,MPa≥ 1.0 1.5
Elongation at break ,%≥ 300 300
Low temperature flexibility,around 10 mm rod bent 180 -10℃ No crack -20℃ No crack
Impermeability(0.3MPa,30min) Impermeable
Drying time
Surface drying time ≤4h
Fully drying time ≤8h
MATTER ATTENTION
1. The temperature is lower than 5 ℃ when crossing construction;
2. The leakage engineering construction, sandstorm days should not be rain and snow days;
3. The grassroots have water, leakage part should be handle in advance before the construction.
DOSAGE OF REFERENCE
Every time is about 0.5 kg per square meter
PACKING SPECIFICATION
25kg/barrel 50kg/barrel
TRANSPORTATION AND STORAGE
1. This product is not flammable and explosive materials, according to general cargo transportation,
transportation should prevent sun, cold;
2. Storage temperature should not be less than 5 ℃;
3. The shelf life of 12 months.
SAFETY GUIDELINES
This product is a water-based non-toxic products, please put on the gloves and other protective measures
when using, accidentally or sticky clothes, please use clear water is rinsed clean.
Foshan Shunde Hesheng Chemical Industry Co., Ltd.
Web: www.he-sheng.com.cn/en/ E-mail:kevin@he-sheng.com.cn
Sales Manager: Kevin Cell/WhatsApp: +86 13794633232 Tel.:+86 757 22904888 Fax.:+86 757 22904999
Headquarter Addr.:No.11-1-2, Fu An Industrial Area, Leliu, Shunde, Foshan City, Guangdong Province, China
Sub-factory Addr.:NO.10 Fuyuan Rd.,Rongbian, Rongui, Shunde, Foshan City, Guangdong Province, China