2. CSTD CONSISTS OF
Technical head
Specification Manager – HO (Supporting All India Basis)
Training Manager- HO (Supporting All India Basis)
Technical Executives Supporting In Respective Regions
2
Wednesday, December 14, 2011
3. CTSD RESPONISBILITIES
1. New Product Development
2. Deriving advanced application methods
3. Designing CAD and 3 D drawings
4. Designing technical bulletin, manual and write ups
5. Competitor comparisons during tenders
6. Evaluating building standards for our products
7. Designing training presentations
8. Supporting technical executives
9. Value engineered speciation development
10. Case studies
11. Complaint handling
4. SPECIFICATION MANAGER
1. After taking all the details of the identified project which may be
conceptual design stage or ongoing:
a. Understanding the requirements of the project
b. Providing a proper recommendation to the sales team after
discussions with architects/consultants etc
2. Initiation of project ground work
a. Studying the site drawings
b. Designing specification on the project specifically for various
areas depending on the client’s requirements
3. Presenting Technical document
a. Proposal of ARDEX Endura technical services including features
and benefits, system specification, treatment methodology and
Auto CAD drawings, 3D illustration if required.
b. Preparing detailed estimate of the proposed areas
c. Preparing Bill of Quantities
5. TRAINING MANAGER
1. Designing training calendar.
2. Providing training to all in house team including
technical executives, Applicator’s, client’s including
hands on
3. Training on basics of building technologies (civil
engineering)
4. Creating modules to make site mock ups, site trials,
on site training to workmen.
5. Responsible for centralized training centre/academy
6. Designing samples of system recommendations
6. TECHNICAL EXECUTIVES
1. Product presentation/Comparison/Mock up
a. Highlighting the product features and characteristics in
comparison with the other proposed competitor products and
systems
b. Executing live mock up on site to show product
performance
c. Mock up management.
2. Quality assurance and Quality check
a. Regular site visits to ensure the applicator ‘s adherence to
the specifications
b. Imparting site training and instructions to the applicators
3. Certification of executions
a. Making the final site visit after completion of job and
certifying the job (Based on the requirements in consultation
with sales team)
7. WATERPROOFING
Waterproofing portfolio
Surface preparations
Critical areas of waterproofing
System recommendations
8. Waterproofing portfolio
We have various waterproofing systems to suite different
areas of building
Wet areas
Under tile – Liquid applied membranes
Under tile – Sheet applied waterproofing membranes
Roof areas
Roof protected
Roof exposed
Roof landscaped
Basement
Liquid applied membranes
Positive side
Sheet applied membranes
Positive side
9. Waterproofing portfolio
We have various waterproofing systems to suite different
areas of building
Swimming pool areas
Critical pools
Sheet applied membranes
Liquid applied membranes
Water containment structures
Under tile liquid applied membranes
Epoxy potable systems
Expansion joint areas
10. Surface Preparation
Surface Preparation for Waterproofing
Surface must be structurally sound
Cracking or movement of the substrate after a membrane has been installed is
likely to cause the membrane to fracture.
Treat cracks and movement joints
Cracks, construction joints, expansion joints and other mobile joints should be
treated in accordance with the membrane manufacturers recommendations.
Clean and free from any contaminant materials
A membranes bond will fail at its weakest point so if applied over dust, loose
materials or poorly bonded contaminants it will fail prematurely.
Repair any holes/voids in the substrate
A uniform thickness membrane is very difficult to achieve over holes/voids.
Remove any protrusions and sharp edges
A uniform thickness membrane is very difficult to achieve over protrusions or
sharp edges.
11. Surface Preparation
Surface Preparation for Waterproofing
Concrete should be aged for 28 days and screeds should be aged
for 7 days
Cementitious surfaces can develop plastic shrinkage cracks during initial
curing which must be totally formed before the membrane is applied.
Time must also be allowed for the development of efflorescence which
must be removed before the membrane application.
Ensure substrate is dry (5% moisture or less)
High substrate moisture content will form blisters in the membrane during
curing.
Seal wet or freshly laid concrete with ARDEX WPM 300
Allow to cure overnight. Provides a concrete curing membrane and barrier
coat.
12. Surface Preparation
Priming for Waterproofing
Porous surfaces are primed to consolidate residual dust and reduce the
porosity of the substrate to avoid excessively fast interface drying
and blistering of the membrane
Wet or fresh concrete, PVC and metal are primed to provide a barrier
between the substrate and the membrane
All cementitious substrates should be primed with ARDEX WPM 265
Water Based Primer at a rate of 6m2/L
Highly porous substrates may require 2 coats
PVC should be primed with pink plumbers primer
Metal surfaces should be primed with a two pack epoxy zinc phosphate
primer
If moisture content is too high or concrete is freshly laid, use ARDEX
WPM 300 water based epoxy as a barrier coating
Allow primer to dry prior to waterproofing
13. CRITICAL AREAS OF WATERPROOFING
Other than the main treatments of waterproofing the following are the most critical
areas which needs to be addressed before the main waterproofing treatment
• Cracks & Construction Joints
• Rain Outlets / Bore Packing
• Dissimilar Construction Joints / Corner treatment
• Surface Moisture
• Corners
• Protection of Waterproofing Treatment
Wednesday, December 14, 2011 13
14. CRITICAL AREAS OF WATERPROOFING
Cracks & Construction Joints
Surface cracks
•Surface Crack
Wednesday, December 14, 2011 14
15. CRITICAL AREAS OF WATERPROOFING
Cracks & Construction Joints
Crack Chasing
• Surface crack
• Crack Chasing
Wednesday, December 14, 2011 15
16. CRITICAL AREAS OF WATERPROOFING
Cracks & Construction Joints
Crack filling with sealant
• Surface crack
• Crack chasing
• Crack filling with sealant
Wednesday, December 14, 2011 16
17. CRITICAL AREAS OF WATERPROOFING
Cracks & Construction Joints
Priming with WPM 300
• Surface crack
• Crack chasing
• Crack filling with sealant
• Priming with WPM 300
Wednesday, December 14, 2011 17
18. CRITICAL AREAS OF WATERPROOFING
Cracks & Construction Joints
1st Coat of WPM 002
• Surface cracks
• Crack chasing
• Crack filling with sealant
• Priming with WPM 300
• 1st Coat of WPM 002
Wednesday, December 14, 2011 18
19. CRITICAL AREAS OF WATERPROOFING
Cracks & Construction Joints
Reinforcement cloth
• Surface cracks
• Crack chasing
• Crack filling with sealant
• Priming with WPM 300
• 1st Coat of WPM 002
• Reinforcement cloth
Wednesday, December 14, 2011 19
20. CRITICAL AREAS OF WATERPROOFING
Cracks & Construction Joints
2nd coat of WPM 002
• Surface crack
• Crack chasing
• Crack filling with sealant
• Priming with WPM 300
• 1st Coat of WPM 002
• Reinforcement cloth
• 2nd coat of WPM 002
Wednesday, December 14, 2011 20
21. CRITICAL AREAS OF WATERPROOFING
Rain Outlets/ Bore Packing
Core cutting
• Core cutting
Wednesday, December 14, 2011 21
22. CRITICAL AREAS OF WATERPROOFING
Rain Outlets/ Bore Packing
Cleaning
• Core Cutting
• Cleaning
Wednesday, December 14, 2011 22
23. CRITICAL AREAS OF WATERPROOFING
Rain Outlets/ Bore Packing
Pipe Fixing
• Core cutting
• Cleaning
• Pipe fixing
Wednesday, December 14, 2011 23
24. CRITICAL AREAS OF WATERPROOFING
Rain Outlets/ Bore Packing
Pipe fixing
• Core cutting
• Cleaning
• Pipe fixing
• Pipe fixing
Wednesday, December 14, 2011 24
25. CRITICAL AREAS OF WATERPROOFING
Rain Outlets/ Bore Packing
Filling with WPM SG
• Core cutting
• Cleaning
• Pipe fixing
• Pipe fixing
• Filling with WPM SG
Wednesday, December 14, 2011 25
26. CRITICAL AREAS OF WATERPROOFING
Rain Outlets/ Bore Packing
Priming with WPM 300
• Core cutting
• Cleaning
• Pipe fixing
• Pipe fixing
• Filling with WPM SG
• Priming with WPM 300
Wednesday, December 14, 2011 26
27. CRITICAL AREAS OF WATERPROOFING
Rain Outlets/ Bore Packing
1st Coat of WPM 002
• Core cutting
• Cleaning
• Pipe fixing
• Pipe fixing
• Filling with WPM SG
• Priming with WPM 300
• 1st Coat of WPM 002
Wednesday, December 14, 2011 27
28. CRITICAL AREAS OF WATERPROOFING
Rain Outlets/ Bore Packing
Reinforcement cloth
• Core cutting
• Cleaning
• Pipe fixing
• Pipe fixing
• Filling with WPM SG
• Priming with WPM 300
• 1st Coat of WPM 002
• Reinforcement
Wednesday, December 14, 2011 28
29. CRITICAL AREAS OF WATERPROOFING
Rain Outlets/ Bore Packing
2nd Coat of WPM 002
• Core cutting
• Cleaning
• Pipe fixing
• Pipe fixing
• Filling with WPM SG
• Priming with WPM 300
• 1st Coat of WPM 002
• Reinforcement
• 2nd Coat of WPM 002
Wednesday, December 14, 2011 29
30. CRITICAL AREAS OF WATERPROOFING
Dissimilar Construction Joints / Corner treatment
Dissimilar joints
• Dissimilar joints
Wednesday, December 14, 2011 30
31. CRITICAL AREAS OF WATERPROOFING
Dissimilar Construction Joints / Corner treatment
Surface consolidation
• Dissimilar joints
• Surface consolidation
Wednesday, December 14, 2011 31
32. CRITICAL AREAS OF WATERPROOFING
Dissimilar Construction Joints / Corner treatment
Moisture barrier coating
• Dissimilar joints
• Surface consolidation
• Moisture barrier coating
Wednesday, December 14, 2011 32
33. CRITICAL AREAS OF WATERPROOFING
Dissimilar Construction Joints / Corner treatment
1st Coat of WPM 002
• Dissimilar joints
• Surface consolidation
• Moisture barrier coating
• 1st Coat of WPM 002
Wednesday, December 14, 2011 33
34. CRITICAL AREAS OF WATERPROOFING
Dissimilar Construction Joints / Corner treatment
Reinforcement cloth
• Dissimilar joints
• Surface consolidation
• Moisture barrier coating
• 1st Coat of WPM 002
• Reinforcement cloth
Wednesday, December 14, 2011 34
35. CRITICAL AREAS OF WATERPROOFING
Dissimilar Construction Joints / Corner treatment
2nd Coat of WPM 002
• Dissimilar joints
• Surface consolidation
• Moisture barrier coating
• 1st Coat of WPM 002
• Reinforcement cloth
• 2nd Coat of WPM 002
Wednesday, December 14, 2011 35
36. CRITICAL AREAS OF WATERPROOFING
Surface Moisture
Moisture raising in the
surface
• Moisture raising in the surface
Wednesday, December 14, 2011 36
37. CRITICAL AREAS OF WATERPROOFING
Surface Moisture
Moisture barrier coat
• Moisture raising in the surface
• Moisture barrier coat
Wednesday, December 14, 2011 37
38. CRITICAL AREAS OF WATERPROOFING
Protection of Waterproofing Treatment
Waterproofing Treated
surface
• Waterproofing treated surface
Wednesday, December 14, 2011 38
39. CRITICAL AREAS OF WATERPROOFING
Protection of Waterproofing Treatment
Damages to membrane
• Waterproofing treated surface
• Damages to treated surface
Wednesday, December 14, 2011 39
40. CRITICAL AREAS OF WATERPROOFING
Protection of Waterproofing Treatment
Protection plastering
• Waterproofing treated surface
• Damages to treated surface
• Protection plastering
Wednesday, December 14, 2011 40
41. WATERPROOFING
SYSTEM
RECOMMENDATIONS
Wednesday, December 14, 2011 41
42. WET AREA (BATHROOM, TOILET, BALCONY) WATERPROOFING
WT1 - WPM 002 – Two component Acrylic Co polymer modified waterproofing System
ADHESIVE WPM 002 WPM 002 WPM 300 Concrete, Timber or
AND TILING F/C Substrate
43. WET AREA (BATHROOM, TOILET, BALCONY) WATERPROOFING
WT1 - WPM 002 – Two component Acrylic Co polymer modified waterproofing System
• Surface preparation
• Crack treatment
• Wall consolidation
• Bond breakers/cove installation
• Priming with WPM 300
• 1st coat of WPM 002
• Reinforcement installation in the
corners using WPM deck web over wet
coat of WPM 002
• 2nd coat of WPM 002
• Protection plaster
44.
45. WET AREA (BATHROOM, TOILET, BALCONY) WATERPROOFING
WT2 – WPM 750 Butynol – Synthetic Rubber Sheet 0.50mm – 1mm thick Waterproofing System
BUTYNOL #2 BUTYNOL #1
ADHESIVE ARDEX WA 98 Concrete, Timber or
AND TILING ARDEX ADHESIVE F/C Substrate
SEAM TAPE
48. WET AREA (BATHROOM, TOILET, BALCONY) WATERPROOFING
WT3 – Waterproofing and decoupling - Seal Sheet under tile waterproofing system
Butt joint
Seal Sheet
Treatment with
Waterproofing
WPM Deck web sandwiched b/n
Membrane
Necessary 2coats of WPM 002 BAL Gold star Concrete Substrate
Tiling Adhesive
Necessary
BAL adhesive `
49. WET AREA (BATHROOM, TOILET, BALCONY) WATERPROOFING
002 - Butynol – Synthetic Rubber Sheet 0.50mm – 1mm thick Waterproofing System
• Surface preparation
• Bond breakers
• Adhesive installation
• Seal sheet installation
• Butt joint treatment
• Tile installation with
necessary adhesives
63. ROOFS & DECKS – LANDSCAPE WATERPROOFING
RL1 - WPM 320 – Liquid Applied Root Inhibiting Latex Emulsion Waterproofing System
• Surface preparation
• Crack treatment
• Wall consolidation
• Bond breakers/cove installation
• Priming with WPM 300
• 1st coat of WPM 320
• Reinforcement installation in the
corners using WPM deck web over
wet coat of WPM 320
• 2nd coat of WPM 320
• Protection plaster
• Necessary screeding/tilingdrainage
cells
64. Typical Planter Box — Detail
Finished height of
Membrane min. 50mm
Capping or
Above soil
Applied finish
Coating over Apply two
Membrane Coats of
WPM 320
Podium/deck Retaining
Waterproofed with Wall to
WPM 350 Wall and
Roof & Deck Base of
Membrane Planter box
(Min. DFT
WPM 265 1.2mm)
Primer
Slab PU Seal 100 Note: Proper drainage should
Be incorporated into planter
Planter Box — Drainage Detail
Optional: Protection lining
Take WPM 320
Pebbles/ (Punch hole
Down into waste
Stones or Over waste if
Ensure 1:80 Drainage cell Using board)
Falls to waste Pipe
Slab
68. ROOFS & DECKS – LANDSCAPE WATERPROOFING
RL3 - WPM 3000 X – 1 Layer Self Adhesive SBS 1.5mm thick Waterproofing System
WPM 3000 X
SELF ADHESIVE ARDEX Concrete Substrate
LANDSCAPE
WPM 3000 X WPM 240
SELF ADHESIVE
69. ROOFS & DECKS – LANDSCAPE WATERPROOFING
RL3 - WPM 3000 X – 1 Layer Self Adhesive SBS 1.5mm thick Waterproofing System
• Surface preparation
• Priming with WPM 240
• Additional 300mm wide WPM
3000X at all internal and external
corners
• WPM 3000X installation
• Necessary drainage cells
70. BASEMENT FLOOR & WALL BELOW GRADE – POSITIVE SIDE
BR1 - WPM 3000 X – 2 Layers of Self Adhesive SBS 3.00mm thick Waterproofing System
PROTECTION WPM 3000 X WPM 3000 X ARDEX
BOARD WPM 249 Concrete Substrate
2nd LAYER 1st LAYER
PRIMER
71. BASEMENT FLOOR & WALL BELOW GRADE – POSITIVE SIDE
BR1 - WPM 3000 X – 2 Layers of Self Adhesive SBS 3.00mm thick Waterproofing System
System Benefits
Prime with ARDEX WPM 249 3mm thick system
Install 2 layers of WPM 3000 X Double seal at laps
(1.5mm each), self adhesive SBS Positive vapour barrier
membrane in lap staggered manner
Uniform film thickness
Install a Protection Board or Drainage Cell
Excellent elongation
Life expectancy 20 yrs plus
Applications
Below Grade basement floor & wall
positive side
72. BASEMENT FLOOR & WALL BELOW GRADE – POSITIVE SIDE
BR2 - WPM 3000 X – 1 Layer Self Adhesive SBS 1.5mm thick Waterproofing System
WPM 3000 X
SELF ADHESIVE ARDEX Concrete Substrate
PROTECTION
BOARD WPM 3000 X WPM 249
SELF ADHESIVE
73. BASEMENT FLOOR & WALL BELOW GRADE – POSITIVE SIDE
BR2 - WPM 3000 X – 1 Layer Self Adhesive SBS 1.5mm thick Waterproofing System
System Benefits
Prime with ARDEX WPM 249 1.5mm thick system
Install a layer of WPM 3000 X 1.5mm Double seal at laps
self adhesive SBS membrane Positive vapour barrier
Install a Protection Board
Uniform film thickness
Excellent elongation
Life expectancy 10 yrs plus
Applications
Below Grade basement floor & wall
positive side
74. BASEMENT FLOOR & WALL BELOW GRADE – POSITIVE SIDE
BR3 - Butynol Synthetic Rubber Sheet 1.2mm – 1.5mm thick Waterproofing System
BUTYNOL #1
BUTYNOL #2
ARDEX WA 98 Concrete, Timber or
PROTECTION
ARDEX ADHESIVE F/C Substrate
BOARD
SEAM TAPE
75. BASEMENT FLOOR & WALL BELOW GRADE – POSITIVE SIDE
BR3 - Butynol Synthetic Rubber Sheet 1.2mm – 1.5mm thick Waterproofing System
System Benefits
ARDEX WA 98 Adhesive Uniform Film Thickness
Install Butynol Sheet #1 1.4 mtr wide sheets
One layer installation
Apply Seam Primer in between sheet laps
High flexibility >300%
Apply ARDEX Seam Tape in between sheet laps
High tensile strength
Install Butynol Sheet #2
Compatible with BAL ENDURA Adhesive
Install a Protection Board Life expectancy 20 yrs plus
Applications
Below Grade basement floor & wall
positive side
77. BASEMENT FLOOR & WALL BELOW GRADE – POSITIVE SIDE
BR4 - WPM 320 – Liquid Applied Below Grade Latex Emulsion Waterproofing System
System Benefits
Prime with WPM 300 1.0mm thick system
Contains root inhibitors to prevent root
Apply 1st coat of WPM 320
growth ingress to the membrane
Deck web reinforcing cloth in corner, cracks & joints
Positive vapour barrier
Apply 2nd coat of WPM 320
Excellent elongation
Protection Board
Heavy duty, chemical resistant
Life expectancy 10 yrs plus
Applications
Only on positive side retaining wall
78. EXTERNAL FAÇADE & ANTICORBONATION SYSTEMS
EF1 - WPM 330 – Anti Carbonation Waterproofing Façade Membrane System
WPM 330 WPM 330 WPM 300 Concrete, Timber or
FACADE F/C Substrate
79. EXTERNAL FAÇADE & ANTICORBONATION SYSTEMS
EF1 - WPM 330 – Anti Carbonation Waterproofing Façade Membrane System
System Benefits
Prime with WPM 300 water based moisture 100% water based acrylic.
barrier coat Anti-carbonation semi permeable
membrane preventing concrete
Apply 1 coat of WPM 330 Facade
corrosion and allowing the substrate to
Apply 2nd coat of WPM 330 Facade breathe.
Excellent dirt retention properties.
Excellent colour retention
Variable texture finish
High flexibility
Applications Life expectancy 10 yrs plus
External facades of buildings
CBD's building
Sea shore buildings
Chemical & Gas plants etc
80. EXTERNAL FAÇADE & ANTICORBONATION SYSTEMS
EF2 - WPM 310 – Waterproofing Facade Membrane System
WPM 310 WPM 310 WPM 300 Concrete, Timber or
FACADE F/C Substrate
81. EXTERNAL FAÇADE & ANTICORBONATION SYSTEMS
EF2 - WPM 310 – Waterproofing Facade Membrane System
System Benefits
Prime with WPM 300 water based primer 100% water based acrylic.
Apply 1st coat of WPM 310 Façade membrane Semi permeable membrane allowing the
substrate to breathe.
Apply 2nd coat of WPM 310 Facade
Excellent dirt retention properties.
Excellent colour retention
Variable texture finish
High flexibility
Life expectancy 10 yrs plus
Applications
External facades of buildings
82. WATER IMMERSION – OHT/UG SUMP TANKING SYSTEMS
OS1 – WPM 200/WPM 300/WPM 300 Potable Grade Waterproofing Systems
WPM 300 WPM 300 WPM 200 Concrete Substrate/
Neatly plastered
substrate
83. WATER IMMERSION – OHT/UG SUMP TANKING SYSTEMS
OS1 – WPM 200/WPM 300/WPM 300 Potable Grade Waterproofing Systems
System Benefits
Apply 1 coat of concrete sealer WPM 200 Two Part Epoxy system
Apply 1st coat of WPM 300 Water Based – compatible with
damp or wet surfaces
Apply 2nd coat of WPM 300
0.3 mm thick
Bond strength to concrete >5Mpa
Life expectancy 10 yrs plus
Applications
Internal of water tanks, reservoirs,
fish ponds and water features
Conforms to AS4020 and BS6920 for use in
contact with potable water
84.
85. WATER IMMERSION – OHT/UG SUMP TANKING SYSTEMS
OS2 Butynol Synthetic Rubber Welded Bag of Butynol 1.5mm Potable Grade Waterproofing System
BUTYNOL #2 Concrete Substrate
FACTORY
WELD
BUTYNOL #1
86. WATER IMMERSION – OHT/UG SUMP TANKING SYSTEMS
OS2 Butynol Synthetic Rubber Welded Bag of Butynol 1.5mm Potable Grade Waterproofing System
System Benefits
Where the structural design fits a factory Uniform Film Thickness
welded bag of Butynol is laid into the Loose laid installation
containment structure. High flexibility >300%
Bag must be detailed in accordance with High tensile strength
Ardex recommendations Life expectancy 20 yrs plus
Conforms to AS4020 for use in contact with
potable water
Applications
Potable Water Tanks
87. WATER IMMERSION – OHT/UG SUMP TANKING SYSTEMS
OS3 WPM 300/WPM 002/WPM 002/Tile/Screed Tanking Waterproofing Systems
Tile WPM 002 WPM 002 WPM 300 Concrete Substrate
Protective
plaster
88. WATER IMMERSION – OHT/UG SUMP TANKING SYSTEMS
OS 3 WPM 200/WPM 300/WPM 002/WPM 002/Tile/Screed Tanking Waterproofing Systems
System Benefits
Two Part Epoxy system
Apply 1st coat of WPM 300 Water Based – compatible with
damp or wet surfaces
Apply 2 coats of WPM 002 Acrylic
0.3 mm thick
Co polymer waterproofing membrane.
Bond strength to concrete >5Mpa
Install a protective plaster or tiling Life expectancy 10 yrs plus
Applications
Internal of water tanks, reservoirs,
fish ponds and water features
For use under tile/under screed
89.
90. WATERPROOFING OF SWIMMING POOL & WATER BODY
SP1 WPM 200/WPM 300/WPM 002/WPM 002 Pool Waterproofing System In Hydrostatic Situations
ADHESIVE WPM 002 WPM 200
AND TILING
WPM 002 WPM 300 Concrete Substrate
91. WATERPROOFING OF SWIMMING POOL & WATER BODY
SP1 WPM 200/WPM 300/WPM 002/WPM 002 Pool Waterproofing System In Hydrostatic Situations
System Benefits
Prime with WPM 200 concrete sealer Water based
Apply 1 coat of WPM 300 Internally reinforced
High flexibility >300%
Apply 1st coats WPM 002 2 component
waterproofing membrane Cementitious Acrylic
Compatible with BAL ENDURA Adhesive
Deck web polyester cloth (for corners)
Apply 2nd coat WPM 002 40Kg covers 20 Sqm
Surfaces must be tiled
Protective layer of plaster
Life expectancy 10 yrs plus
Necessary tile installation
Applications
Swimming Pools & Water Features
Must be tiled
92.
93. SP2 Seal Sheet – Waterproofing and decoupling membrane
- Elevated Pool Waterproofing System In Hydrostatic Situations
Seal sheet
TILING Waterproofing membrane
Necessary Gold star Concrete Substrate
Adhesive Adhesive
94. SP2 Seal Sheet – Waterproofing and decoupling membrane
- Elevated Pool Waterproofing System In Hydrostatic Situations
• Surface preparation
• Bond breakers
• Adhesive installation
• Seal sheet installation
• Butt joint treatment
• Tile installation with necessary
adhesives
97. 1001 Expansion Joint Treatment
THERMO PLASTIC COATED 1ST COAT WPM
ELASTOMETER SEALING
2ND COAT WPM
TAPE 29200
WPM PRIMER RCC SLAB
WITH EXPANSION JOINT
PUSEAL 100
SEALANT
BACKER ROD
98. 1001 Expansion Joint Treatment
System Benefits
Prepare the joint with WPM 256 in Total protection of expansion joints
conjunction with cement / sand in all aspects of requirements
Install a PU Seal 100 after installation of including provision for proper
polystyrene backer rod movements and waterproofing
properties
Prime both side of joints with WPM 256
High elongation
Install Coving Bandage sandwiched between
2 coats of liquid applied membranes Durable & heavy duty
Applications
Expansion joints