This document discusses the critical chain project management concept introduced by Dr. Eliyahu Goldratt to help projects finish on time and budget. It outlines the five steps: 1) identify constraints, 2) exploit constraints, 3) subordinate everything else to the constraints, 4) elevate constraints, and 5) don't let inertia become new constraints. Buffers are added to the critical chain to account for risks. Tracking focuses on the remaining work in the critical chain and buffers rather than completed work. When properly implemented, critical chain management can improve project team effectiveness, tracking, and decision making to help ensure on-time completion.
2. Background
Why to complete project on time?
Basics of Project
Step1: Identify system’s constraints
Step2: Exploit system’s constraints
Step3: Subordinate everything
Step4: Elevate system’s constraints
Step5: Don’t allow inertia to become constraints
Challenges to implement CCPM
Summary
Views about author
Crtical Chain Concept by Kaushik Shah 2
3. Huge cost and time overruns while executing
most of the projects in year 1950s.
Critical Path based Project management
introduced during 1960s
Overall project management improved but
still the project could not deliver on time and
in the given cost
In year 1997, Dr. Goldratt introduced ‘Critical
chain’ based project management concept to
deliver project on time & budget.
Crtical Chain Concept by Kaushik Shah 3
4. ROI = Net profit/Investment
◦ Assumption:
Project will be completed in stipulated time
Time to market
Increase Revenue & profit margin
◦ Launch of product ahead of competitor
◦ Investment: Money * Time
Crtical Chain Concept by Kaushik Shah 4
Loss of
Revenue
5. Crtical Chain Concept by Kaushik Shah 5
Process
Input Output
Few Examples:
Automotive Industry:
◦ Raw Material -> Assembly Line -> Vehicle
IT Industry
◦ Requirement -> Software Program -> Application
Textile Industry
◦ Yarn -> Weaving -> Cloth
Step1 Step2 Step4 Step5
Step3
Chain
6. Constraint: Anything that limits / hinder to
meet the goal of the project.
Crtical Chain Concept by Kaushik Shah
6
Critical Path
* Critical path is a longest path of the project in terms of
time and dependent steps.
7. Crtical Chain Concept by Kaushik Shah
7
Critical Chain
Critical Chain: Longest chain, in terms of time &
dependent steps considering common resources
8. Why do we still fail on commitment?
◦ Reason1: Incorporate ‘Safety’ ( Typically due to Lower safety)
Crtical Chain Concept by Kaushik Shah
8
50% 30%
Safety
Time
Probability
9. Crtical Chain Concept by Kaushik Shah 9
Start of the
task
Unexpected
problem
Delayed
Completion
Why do we still fail on commitment?
◦ Reason2: Students syndrome
10. Crtical Chain Concept by Kaushik Shah 10
Why do we still fail on commitment?
◦ Reason3: Parkinson’s Law: Work expands to fit
allocated time.
No reward for completing the tasks before time
Typically cut in the estimation based on past history
11. Crtical Chain Concept by Kaushik Shah
11
Why do we still fail on commitment?
◦ Reason4: Multitasking
12. Crtical Chain Concept by Kaushik Shah
12
Estimation with
50% probability
Introduce
buffer with
Safety margin
Project Buffer
Feeding Buffer
7d
7d
7d
3d
6d
13. Crtical Chain Concept by Kaushik Shah 13
This is a process to subordinate all other
activities to maintain / improve the critical
chain schedule.
14. Crtical Chain Concept by Kaushik Shah 14
Reduce number of Dependent task
◦ Any opportunity for improvement should be
checked against ROI calculation
ROI = Incremental Net profit / Incremental
investments
Reduce time to perform task
Reduce number of Dependency due to
common resources
15. Crtical Chain Concept by Kaushik Shah
15
Carefully consider the following:
◦ Any opportunity for moving the critical chain
should be testing using ROI calculation (NP/I)
◦ Ability of non-critical tasks & resources to
subordinate the new critical chain tasks
◦ Risk associated with disrupting the project
Restart the process in case critical chain
moves
16. Crtical Chain Concept by Kaushik Shah
16
Use the following method to track the
project:
◦ Track the project completion using remaining
work and not the completed work
◦ Divide the buffer in 3 equal zone
Green Zone: No action required
Yellow Zone: Assess the problem and prepare action
plan
Red Zone: Implement action plan
17. Crtical Chain Concept by Kaushik Shah 17
Cultural change in the organization
Estimation technique – Buffer calculation
Multitasking of critical resource
Make or Buy Decision (Skip/Implement task)
18. Crtical Chain Concept by Kaushik Shah 18
Critical Chain project management provides
following major benefits
◦ Project will be completed faster
◦ The project team moral and effectiveness will
improve
◦ Tracking will become easy be looking at critical
chain task and status on Buffer
◦ Effective tool for decision making for choosing or
skipping the task
19. Crtical Chain Concept by Kaushik Shah 19
Positive comments
◦ A small idea can change the world – Jargon of
Critical Chain
◦ The book is like a novel which made the subject
interesting
◦ Presented practical examples supported
graphically
Improvement areas
◦ Lots of background story and main topic was
discussed later part of the book
◦ Difficult to understand the implementation part of
critical chain