SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
1
Software Project Management
Unit 1
Chapter 3
Step Wise: An
approach to planning
software projects
“What we learn with
pleasure…..
we never forget...”
Alfred Mercier
13-07-20
SPM (5e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2009
2
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
3
‘Step Wise’ - aspirations
• Practicality
• tries to answer the question ‘what do I do
now?’
• Scalability
• useful for small project as well as large
• Range of application
• Accepted techniques
• e.g. borrowed from PRINCE etc
SPM (5e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
4
‘Step Wise’ - an overview
0.Select
project
1. Identify
project
objectives
2. Identify
project
infrastructure
3. Analyse
project
characteristics
4. Identify
products
and activities
5. Estimate effort
for activity
8. Review/
publicize
plan
6. Identify activity
risks
7. Allocate
resources
9. Execute plan
10. Lower level
planning
Review
Lower
level
detail
For each
activity
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
5
A project scenario: Brightmouth
College Payroll
• College currently has payroll processing carried
out by a services company
• This is very expensive and does not allow detailed
analysis of personnel data to be carried out
• Decision made to bring payroll ‘in-house’ by
acquiring an ‘off-the-shelf’ application
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
6
Project scenario - continued
• The use of the off-the-shelf system will require
a new, internal, payroll office to be set up
• There will be a need to develop some software
‘add-ons’: one will take payroll data and
combine it with time-table data to calculate the
staff costs for each course run in the college
• The project manager is Brigette.
SPM (5e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2009
7
14-07-20
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
8
Step 1
establish project scope and objectives
• 1.1 Identify objectives and measures of effectiveness
• ‘how do we know if we have succeeded?’
• 1.2 Establish a project authority
• ‘who is the boss?’
• 1.3 Identify all stakeholders in the project and their
interests
• ‘who will be affected/involved in the project?’
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
9
Step 1
continued
• 1.4 Modify objectives in the light of stakeholder
analysis
• ‘do we need to do things to win over
stakeholders?’
• 1.5 Establish methods of communication with all
parties
• ‘how do we keep in contact?’
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
10
Back to the scenario
• Project authority
- Brigette finds she has two different clients for the
new system:
the finance department &
the personnel office
- A vice principal agrees to be official client, and
monthly meetings are chaired by the VP and
attended by Brigette and the heads of finance and
personnel
- These meetings would also help overcome communication
barriers
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
11
Back to the scenario - continued
• Stakeholders
• For example, personnel office would supply
details of new staff, leavers and changes
(e.g. promotions)
• To motivate co-operation Brigette might
ensure new payroll system produces reports
that are useful to personnel staff
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
12
Step 2
Establish project infrastructure
• 2.1 Establish link between project and any
strategic plan
• ‘why did they want the project?’
• 2.2 Identify installation standards and procedures
• ‘what standards do we have to follow?’
• 2.3. Identify project team organization
• ‘where do I fit in?’
Education is not the learning of
facts….
But the training of the mind to
think….
-- Albert Einstein
17-07-20
SPM (5e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2009
13
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
14
Step 3
Analysis of project characteristics
• 3.1 Distinguish the project as either objective or
product-based.
• Is there more than one way of achieving success?
• 3.2 Analyse other project characteristics (including
quality based ones)
• what is different about this project?
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
15
Step 3 continued
• Identify high level project risks
• ‘what could go wrong?’
• ‘what can we do to stop it?’
• Take into account user requirements concerning
implementation
• Select general life cycle approach
• waterfall? Increments? Prototypes?
• Review overall resource estimates
• ‘does all this increase the cost?’
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
16
Back to the scenario
• Objectives vs. products
• An objective-based approach has been adopted
• Some risks
• There may not be an off-the-shelf package that
caters for the way payroll is processed at
Brightmouth College
• Answer?
• Brigette decides to obtain details of how main
candidate packages work as soon as possible; also
agreement that if necessary processes will be
changed to fit in with new system.
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
17
Step 4
Identify project products and activities
• 4.1 Identify and describe project products
‘what do we have to produce?’
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
18
Products
• The result of an activity
• Could be (among other things)
• physical thing (‘installed pc’),
• a document (‘logical data structure’)
• a person (‘trained user’)
• a new version of an old product (‘updated
software’)
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
19
Products
• The following are NOT normally products:
• activities (e.g. ‘training’)
• events (e.g. ‘interviews completed’)
• resources and actors (e.g. ‘software
developer’) - may be exceptions to this
• Products CAN BE deliverable or intermediate
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
20
Product description (PD)
• Product identity
• Description - what is it?
• Derivation - what is it
based on?
• Composition - what
does it contain?
• Format
• Relevant standards
• Quality criteria
Create a PD for ‘test data’
Step 4 continued
• 4.2 document generic- product flows
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
21
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
22
Step 4 continued
• 4.3 Recognize product instances
• The PBS (Product breakdown Structure) and PFD
(Product flow diagram) will probably have
identified generic products e.g. ‘software modules’
• It might be possible to identify specific instances
e.g. ‘module A’, ‘module B’ …
• But in many cases this will have to be left to later,
more detailed, planning
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
23
Step 4 continued
• 4.4. Produce ideal activity network
• Identify the activities needed to create each
product in the PFD
• More than one activity might be needed to create
a single product
• Hint: Identify activities by verb + noun but avoid
‘produce…’ (too vague)
• Draw up activity network
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
24
An ‘ideal’ activity
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
25
Step 4.5 Add check-points if needed
Design
module A
Design
module B
Design
system
Design
module C
Code
module A
Code
module B
Code
module C
Test
system
Design
module A
Design
module B
Design
system
Design
module C
Code
module A
Code
module B
Code
module C
Test
system
Check-point
put in a
check point
Successful and unsuccessful
people do not vary greatly in
their abilities....
They vary in their desires to
reach their potential…
20-07-20
JYOTSNA ANTHAL
CHAUHAN
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
27
Step 5:
Estimate effort for each activity
• 5.1 Carry out bottom-up estimates
• distinguish carefully between effort and elapsed
time
• 5.2. Revise plan to create controllable activities
• break up very long activities into a series of
smaller ones
• bundle up very short activities (create check
lists?)
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
28
Step 6
Identify activity risks
• 6.1.Identify and quantify risks for activities
• damage if risk occurs (measure in time lost or
money)
• likelihood if risk occurring
• 6.2. Plan risk reduction and contingency
measures
• risk reduction: activity to stop risk occurring
• contingency: action if risk does occur
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
29
• 6.3 Adjust overall plans and estimates to take
account of risks
• e.g. add new activities which reduce risks
associated with other activities e.g. training,
pilot trials, information gathering
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
30
Step 7
Allocate resources
• 7.1 Identify and allocate resources to activities
• 7.2 Revise plans and estimates to take into
account resource constraints
• e.g. staff not being available until a later date
• non-project activities
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
31
Gantt charts
Obtain user
requirements
Plan office layouts
Week
commencing
5 12 19 26
JUNE
JULY
9 16
Analyse existing
system
2
Draft and issue ITT
Business analyst
Systems assistant
Business
analyst
Premises office
LT = lead tester
TA = testing assistant
Survey potential
suppliers
Generate test cases
Calculate volumes
Business analyst
Finance assistant
Systems assistant
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
32
Step 8
Review/publicise plan
• 8.1 Review quality aspects of project plan
• 8.2 Document plan and obtain agreement
Step 9 & 10
Execute plan and create lower
level plans
SPM (6e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2017
33
Key points
• Establish your objectives
• Think about the characteristics of the project
• Discover/set up the infrastructure to support the
project (including standards)
• Identify products to be created and the
activities that will create them
• Allocate resources
• Set up quality processes
End of Unit 1
The end of one chapter is just
the beginning of another….
Read on….
The BEST part is always yet
to come…..
SPM (5e) Step Wise: an introduction to project
planning© The McGraw-Hill Companies, 2009
34

More Related Content

Similar to Chapter 03 overview-of project planning Step Wise

Chapter 01 - Introduction to Software Project Management
Chapter 01 - Introduction to Software Project ManagementChapter 01 - Introduction to Software Project Management
Chapter 01 - Introduction to Software Project ManagementRohanMistry15
 
Chapter 2 -project evaluation
Chapter 2 -project evaluationChapter 2 -project evaluation
Chapter 2 -project evaluationRohanMistry15
 
An introduction
An introductionAn introduction
An introductiontumetr
 
What is the business value of my project?
What is the business value of my project?What is the business value of my project?
What is the business value of my project?Joe Raynus
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management FrameworkRahul Sudame
 
Basics in Project Management
Basics in Project ManagementBasics in Project Management
Basics in Project Managementchaitanyakrsk
 
Agile Methods to Develop Tangible Products Quickly
Agile Methods to Develop Tangible Products QuicklyAgile Methods to Develop Tangible Products Quickly
Agile Methods to Develop Tangible Products QuicklyJohn Carter
 
Business Benefits of GIS - ROI
Business Benefits of GIS - ROI Business Benefits of GIS - ROI
Business Benefits of GIS - ROI Sougata Mitra
 
Software Project Management chapter-1
Software Project Management chapter-1Software Project Management chapter-1
Software Project Management chapter-1Computing Cage
 
Lecture 3
Lecture 3Lecture 3
Lecture 39anm12
 
Process Mapping for Credit Suisse AVP Goal & Rising Star Program
Process Mapping for Credit Suisse AVP Goal & Rising Star ProgramProcess Mapping for Credit Suisse AVP Goal & Rising Star Program
Process Mapping for Credit Suisse AVP Goal & Rising Star ProgramKelly Fairbairn
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 

Similar to Chapter 03 overview-of project planning Step Wise (20)

Chapter 01 - Introduction to Software Project Management
Chapter 01 - Introduction to Software Project ManagementChapter 01 - Introduction to Software Project Management
Chapter 01 - Introduction to Software Project Management
 
Chapter 2 -project evaluation
Chapter 2 -project evaluationChapter 2 -project evaluation
Chapter 2 -project evaluation
 
Software project management
Software project managementSoftware project management
Software project management
 
Software project management 3
Software project management 3Software project management 3
Software project management 3
 
Spm chapter 1
Spm chapter 1Spm chapter 1
Spm chapter 1
 
SPM PPT
SPM PPTSPM PPT
SPM PPT
 
Managing Project Success
Managing Project SuccessManaging Project Success
Managing Project Success
 
An introduction
An introductionAn introduction
An introduction
 
What is the business value of my project?
What is the business value of my project?What is the business value of my project?
What is the business value of my project?
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Basics in Project Management
Basics in Project ManagementBasics in Project Management
Basics in Project Management
 
Agile Methods to Develop Tangible Products Quickly
Agile Methods to Develop Tangible Products QuicklyAgile Methods to Develop Tangible Products Quickly
Agile Methods to Develop Tangible Products Quickly
 
Business Benefits of GIS - ROI
Business Benefits of GIS - ROI Business Benefits of GIS - ROI
Business Benefits of GIS - ROI
 
Software Project Management chapter-1
Software Project Management chapter-1Software Project Management chapter-1
Software Project Management chapter-1
 
Lecture1
Lecture1Lecture1
Lecture1
 
Lecture 3
Lecture 3Lecture 3
Lecture 3
 
Process Mapping for Credit Suisse AVP Goal & Rising Star Program
Process Mapping for Credit Suisse AVP Goal & Rising Star ProgramProcess Mapping for Credit Suisse AVP Goal & Rising Star Program
Process Mapping for Credit Suisse AVP Goal & Rising Star Program
 
PW Final Jun7 2012
PW Final Jun7 2012PW Final Jun7 2012
PW Final Jun7 2012
 
03_AgilePM.pptx
03_AgilePM.pptx03_AgilePM.pptx
03_AgilePM.pptx
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 

More from RohanMistry15

software-quality-assurance question paper 2023
software-quality-assurance question paper 2023software-quality-assurance question paper 2023
software-quality-assurance question paper 2023RohanMistry15
 
security-in-computing question paper 2023
security-in-computing question paper 2023security-in-computing question paper 2023
security-in-computing question paper 2023RohanMistry15
 
IT-service-management question paper 2023
IT-service-management question paper 2023IT-service-management question paper 2023
IT-service-management question paper 2023RohanMistry15
 
geographical-information-system question paper
geographical-information-system question papergeographical-information-system question paper
geographical-information-system question paperRohanMistry15
 
Business-Intelligence question paper 2023
Business-Intelligence question paper 2023Business-Intelligence question paper 2023
Business-Intelligence question paper 2023RohanMistry15
 
Aeronautical Engineering Career Information
Aeronautical Engineering Career InformationAeronautical Engineering Career Information
Aeronautical Engineering Career InformationRohanMistry15
 
Chinese Cyber attack on mumbai power plant
Chinese Cyber attack on mumbai power plantChinese Cyber attack on mumbai power plant
Chinese Cyber attack on mumbai power plantRohanMistry15
 
Artificial Intelligence - A modern approach 3ed
Artificial Intelligence - A modern approach 3edArtificial Intelligence - A modern approach 3ed
Artificial Intelligence - A modern approach 3edRohanMistry15
 
Advanced Web Programming Chapter 8
Advanced Web Programming Chapter 8Advanced Web Programming Chapter 8
Advanced Web Programming Chapter 8RohanMistry15
 
Advanced Web Programming Chapter 5
Advanced Web Programming Chapter 5Advanced Web Programming Chapter 5
Advanced Web Programming Chapter 5RohanMistry15
 
Advanced Web Programming Chapter 4
Advanced Web Programming Chapter 4Advanced Web Programming Chapter 4
Advanced Web Programming Chapter 4RohanMistry15
 
Advanced Web Programming Chapter 13 & 14
Advanced Web Programming Chapter 13 & 14Advanced Web Programming Chapter 13 & 14
Advanced Web Programming Chapter 13 & 14RohanMistry15
 
Advanced Web Programming Chapter 12
Advanced Web Programming Chapter 12Advanced Web Programming Chapter 12
Advanced Web Programming Chapter 12RohanMistry15
 
Advanced Web Programming Chapter 2
Advanced Web Programming Chapter 2Advanced Web Programming Chapter 2
Advanced Web Programming Chapter 2RohanMistry15
 
Advanced Web Programming Chapter 3
Advanced Web Programming Chapter 3Advanced Web Programming Chapter 3
Advanced Web Programming Chapter 3RohanMistry15
 
Advanced Web Programming Chapter 10
Advanced Web Programming  Chapter 10Advanced Web Programming  Chapter 10
Advanced Web Programming Chapter 10RohanMistry15
 
Advanced Web Programming Chapter 11
Advanced Web Programming Chapter 11Advanced Web Programming Chapter 11
Advanced Web Programming Chapter 11RohanMistry15
 
Advanced Web Programming Chapter 9
Advanced Web Programming Chapter 9Advanced Web Programming Chapter 9
Advanced Web Programming Chapter 9RohanMistry15
 
Advanced Web Programming Chapter 6
Advanced Web Programming Chapter 6Advanced Web Programming Chapter 6
Advanced Web Programming Chapter 6RohanMistry15
 

More from RohanMistry15 (20)

software-quality-assurance question paper 2023
software-quality-assurance question paper 2023software-quality-assurance question paper 2023
software-quality-assurance question paper 2023
 
security-in-computing question paper 2023
security-in-computing question paper 2023security-in-computing question paper 2023
security-in-computing question paper 2023
 
IT-service-management question paper 2023
IT-service-management question paper 2023IT-service-management question paper 2023
IT-service-management question paper 2023
 
geographical-information-system question paper
geographical-information-system question papergeographical-information-system question paper
geographical-information-system question paper
 
Business-Intelligence question paper 2023
Business-Intelligence question paper 2023Business-Intelligence question paper 2023
Business-Intelligence question paper 2023
 
Aeronautical Engineering Career Information
Aeronautical Engineering Career InformationAeronautical Engineering Career Information
Aeronautical Engineering Career Information
 
Chinese Cyber attack on mumbai power plant
Chinese Cyber attack on mumbai power plantChinese Cyber attack on mumbai power plant
Chinese Cyber attack on mumbai power plant
 
Zeus learning
Zeus learningZeus learning
Zeus learning
 
Artificial Intelligence - A modern approach 3ed
Artificial Intelligence - A modern approach 3edArtificial Intelligence - A modern approach 3ed
Artificial Intelligence - A modern approach 3ed
 
Advanced Web Programming Chapter 8
Advanced Web Programming Chapter 8Advanced Web Programming Chapter 8
Advanced Web Programming Chapter 8
 
Advanced Web Programming Chapter 5
Advanced Web Programming Chapter 5Advanced Web Programming Chapter 5
Advanced Web Programming Chapter 5
 
Advanced Web Programming Chapter 4
Advanced Web Programming Chapter 4Advanced Web Programming Chapter 4
Advanced Web Programming Chapter 4
 
Advanced Web Programming Chapter 13 & 14
Advanced Web Programming Chapter 13 & 14Advanced Web Programming Chapter 13 & 14
Advanced Web Programming Chapter 13 & 14
 
Advanced Web Programming Chapter 12
Advanced Web Programming Chapter 12Advanced Web Programming Chapter 12
Advanced Web Programming Chapter 12
 
Advanced Web Programming Chapter 2
Advanced Web Programming Chapter 2Advanced Web Programming Chapter 2
Advanced Web Programming Chapter 2
 
Advanced Web Programming Chapter 3
Advanced Web Programming Chapter 3Advanced Web Programming Chapter 3
Advanced Web Programming Chapter 3
 
Advanced Web Programming Chapter 10
Advanced Web Programming  Chapter 10Advanced Web Programming  Chapter 10
Advanced Web Programming Chapter 10
 
Advanced Web Programming Chapter 11
Advanced Web Programming Chapter 11Advanced Web Programming Chapter 11
Advanced Web Programming Chapter 11
 
Advanced Web Programming Chapter 9
Advanced Web Programming Chapter 9Advanced Web Programming Chapter 9
Advanced Web Programming Chapter 9
 
Advanced Web Programming Chapter 6
Advanced Web Programming Chapter 6Advanced Web Programming Chapter 6
Advanced Web Programming Chapter 6
 

Recently uploaded

Artyushina_Guest lecture_YorkU CS May 2024.pptx
Artyushina_Guest lecture_YorkU CS May 2024.pptxArtyushina_Guest lecture_YorkU CS May 2024.pptx
Artyushina_Guest lecture_YorkU CS May 2024.pptxAnnaArtyushina1
 
WSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open Source
WSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open SourceWSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open Source
WSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open SourceWSO2
 
Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024
Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024
Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024VictoriaMetrics
 
AI & Machine Learning Presentation Template
AI & Machine Learning Presentation TemplateAI & Machine Learning Presentation Template
AI & Machine Learning Presentation TemplatePresentation.STUDIO
 
WSO2Con2024 - From Blueprint to Brilliance: WSO2's Guide to API-First Enginee...
WSO2Con2024 - From Blueprint to Brilliance: WSO2's Guide to API-First Enginee...WSO2Con2024 - From Blueprint to Brilliance: WSO2's Guide to API-First Enginee...
WSO2Con2024 - From Blueprint to Brilliance: WSO2's Guide to API-First Enginee...WSO2
 
WSO2Con2024 - Enabling Transactional System's Exponential Growth With Simplicity
WSO2Con2024 - Enabling Transactional System's Exponential Growth With SimplicityWSO2Con2024 - Enabling Transactional System's Exponential Growth With Simplicity
WSO2Con2024 - Enabling Transactional System's Exponential Growth With SimplicityWSO2
 
WSO2CON 2024 - IoT Needs CIAM: The Importance of Centralized IAM in a Growing...
WSO2CON 2024 - IoT Needs CIAM: The Importance of Centralized IAM in a Growing...WSO2CON 2024 - IoT Needs CIAM: The Importance of Centralized IAM in a Growing...
WSO2CON 2024 - IoT Needs CIAM: The Importance of Centralized IAM in a Growing...WSO2
 
WSO2Con2024 - Simplified Integration: Unveiling the Latest Features in WSO2 L...
WSO2Con2024 - Simplified Integration: Unveiling the Latest Features in WSO2 L...WSO2Con2024 - Simplified Integration: Unveiling the Latest Features in WSO2 L...
WSO2Con2024 - Simplified Integration: Unveiling the Latest Features in WSO2 L...WSO2
 
WSO2Con2024 - GitOps in Action: Navigating Application Deployment in the Plat...
WSO2Con2024 - GitOps in Action: Navigating Application Deployment in the Plat...WSO2Con2024 - GitOps in Action: Navigating Application Deployment in the Plat...
WSO2Con2024 - GitOps in Action: Navigating Application Deployment in the Plat...WSO2
 
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...masabamasaba
 
Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...
Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...
Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...Bert Jan Schrijver
 
WSO2Con2024 - Facilitating Broadband Switching Services for UK Telecoms Provi...
WSO2Con2024 - Facilitating Broadband Switching Services for UK Telecoms Provi...WSO2Con2024 - Facilitating Broadband Switching Services for UK Telecoms Provi...
WSO2Con2024 - Facilitating Broadband Switching Services for UK Telecoms Provi...WSO2
 
WSO2CON 2024 Slides - Open Source to SaaS
WSO2CON 2024 Slides - Open Source to SaaSWSO2CON 2024 Slides - Open Source to SaaS
WSO2CON 2024 Slides - Open Source to SaaSWSO2
 
WSO2Con2024 - Hello Choreo Presentation - Kanchana
WSO2Con2024 - Hello Choreo Presentation - KanchanaWSO2Con2024 - Hello Choreo Presentation - Kanchana
WSO2Con2024 - Hello Choreo Presentation - KanchanaWSO2
 
WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...
WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...
WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...WSO2
 
WSO2CON 2024 - Building the API First Enterprise – Running an API Program, fr...
WSO2CON 2024 - Building the API First Enterprise – Running an API Program, fr...WSO2CON 2024 - Building the API First Enterprise – Running an API Program, fr...
WSO2CON 2024 - Building the API First Enterprise – Running an API Program, fr...WSO2
 
WSO2CON2024 - Why Should You Consider Ballerina for Your Next Integration
WSO2CON2024 - Why Should You Consider Ballerina for Your Next IntegrationWSO2CON2024 - Why Should You Consider Ballerina for Your Next Integration
WSO2CON2024 - Why Should You Consider Ballerina for Your Next IntegrationWSO2
 
WSO2Con2024 - Low-Code Integration Tooling
WSO2Con2024 - Low-Code Integration ToolingWSO2Con2024 - Low-Code Integration Tooling
WSO2Con2024 - Low-Code Integration ToolingWSO2
 
WSO2CON 2024 - Navigating API Complexity: REST, GraphQL, gRPC, Websocket, Web...
WSO2CON 2024 - Navigating API Complexity: REST, GraphQL, gRPC, Websocket, Web...WSO2CON 2024 - Navigating API Complexity: REST, GraphQL, gRPC, Websocket, Web...
WSO2CON 2024 - Navigating API Complexity: REST, GraphQL, gRPC, Websocket, Web...WSO2
 

Recently uploaded (20)

Artyushina_Guest lecture_YorkU CS May 2024.pptx
Artyushina_Guest lecture_YorkU CS May 2024.pptxArtyushina_Guest lecture_YorkU CS May 2024.pptx
Artyushina_Guest lecture_YorkU CS May 2024.pptx
 
WSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open Source
WSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open SourceWSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open Source
WSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open Source
 
Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024
Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024
Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024
 
AI & Machine Learning Presentation Template
AI & Machine Learning Presentation TemplateAI & Machine Learning Presentation Template
AI & Machine Learning Presentation Template
 
WSO2Con2024 - From Blueprint to Brilliance: WSO2's Guide to API-First Enginee...
WSO2Con2024 - From Blueprint to Brilliance: WSO2's Guide to API-First Enginee...WSO2Con2024 - From Blueprint to Brilliance: WSO2's Guide to API-First Enginee...
WSO2Con2024 - From Blueprint to Brilliance: WSO2's Guide to API-First Enginee...
 
WSO2Con2024 - Enabling Transactional System's Exponential Growth With Simplicity
WSO2Con2024 - Enabling Transactional System's Exponential Growth With SimplicityWSO2Con2024 - Enabling Transactional System's Exponential Growth With Simplicity
WSO2Con2024 - Enabling Transactional System's Exponential Growth With Simplicity
 
WSO2CON 2024 - IoT Needs CIAM: The Importance of Centralized IAM in a Growing...
WSO2CON 2024 - IoT Needs CIAM: The Importance of Centralized IAM in a Growing...WSO2CON 2024 - IoT Needs CIAM: The Importance of Centralized IAM in a Growing...
WSO2CON 2024 - IoT Needs CIAM: The Importance of Centralized IAM in a Growing...
 
WSO2Con2024 - Simplified Integration: Unveiling the Latest Features in WSO2 L...
WSO2Con2024 - Simplified Integration: Unveiling the Latest Features in WSO2 L...WSO2Con2024 - Simplified Integration: Unveiling the Latest Features in WSO2 L...
WSO2Con2024 - Simplified Integration: Unveiling the Latest Features in WSO2 L...
 
WSO2Con2024 - GitOps in Action: Navigating Application Deployment in the Plat...
WSO2Con2024 - GitOps in Action: Navigating Application Deployment in the Plat...WSO2Con2024 - GitOps in Action: Navigating Application Deployment in the Plat...
WSO2Con2024 - GitOps in Action: Navigating Application Deployment in the Plat...
 
Abortion Pill Prices Tembisa [(+27832195400*)] 🏥 Women's Abortion Clinic in T...
Abortion Pill Prices Tembisa [(+27832195400*)] 🏥 Women's Abortion Clinic in T...Abortion Pill Prices Tembisa [(+27832195400*)] 🏥 Women's Abortion Clinic in T...
Abortion Pill Prices Tembisa [(+27832195400*)] 🏥 Women's Abortion Clinic in T...
 
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
 
Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...
Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...
Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...
 
WSO2Con2024 - Facilitating Broadband Switching Services for UK Telecoms Provi...
WSO2Con2024 - Facilitating Broadband Switching Services for UK Telecoms Provi...WSO2Con2024 - Facilitating Broadband Switching Services for UK Telecoms Provi...
WSO2Con2024 - Facilitating Broadband Switching Services for UK Telecoms Provi...
 
WSO2CON 2024 Slides - Open Source to SaaS
WSO2CON 2024 Slides - Open Source to SaaSWSO2CON 2024 Slides - Open Source to SaaS
WSO2CON 2024 Slides - Open Source to SaaS
 
WSO2Con2024 - Hello Choreo Presentation - Kanchana
WSO2Con2024 - Hello Choreo Presentation - KanchanaWSO2Con2024 - Hello Choreo Presentation - Kanchana
WSO2Con2024 - Hello Choreo Presentation - Kanchana
 
WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...
WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...
WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...
 
WSO2CON 2024 - Building the API First Enterprise – Running an API Program, fr...
WSO2CON 2024 - Building the API First Enterprise – Running an API Program, fr...WSO2CON 2024 - Building the API First Enterprise – Running an API Program, fr...
WSO2CON 2024 - Building the API First Enterprise – Running an API Program, fr...
 
WSO2CON2024 - Why Should You Consider Ballerina for Your Next Integration
WSO2CON2024 - Why Should You Consider Ballerina for Your Next IntegrationWSO2CON2024 - Why Should You Consider Ballerina for Your Next Integration
WSO2CON2024 - Why Should You Consider Ballerina for Your Next Integration
 
WSO2Con2024 - Low-Code Integration Tooling
WSO2Con2024 - Low-Code Integration ToolingWSO2Con2024 - Low-Code Integration Tooling
WSO2Con2024 - Low-Code Integration Tooling
 
WSO2CON 2024 - Navigating API Complexity: REST, GraphQL, gRPC, Websocket, Web...
WSO2CON 2024 - Navigating API Complexity: REST, GraphQL, gRPC, Websocket, Web...WSO2CON 2024 - Navigating API Complexity: REST, GraphQL, gRPC, Websocket, Web...
WSO2CON 2024 - Navigating API Complexity: REST, GraphQL, gRPC, Websocket, Web...
 

Chapter 03 overview-of project planning Step Wise

  • 1. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 1 Software Project Management Unit 1 Chapter 3 Step Wise: An approach to planning software projects
  • 2. “What we learn with pleasure….. we never forget...” Alfred Mercier 13-07-20 SPM (5e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2009 2
  • 3. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 3 ‘Step Wise’ - aspirations • Practicality • tries to answer the question ‘what do I do now?’ • Scalability • useful for small project as well as large • Range of application • Accepted techniques • e.g. borrowed from PRINCE etc
  • 4. SPM (5e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 4 ‘Step Wise’ - an overview 0.Select project 1. Identify project objectives 2. Identify project infrastructure 3. Analyse project characteristics 4. Identify products and activities 5. Estimate effort for activity 8. Review/ publicize plan 6. Identify activity risks 7. Allocate resources 9. Execute plan 10. Lower level planning Review Lower level detail For each activity
  • 5. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 5 A project scenario: Brightmouth College Payroll • College currently has payroll processing carried out by a services company • This is very expensive and does not allow detailed analysis of personnel data to be carried out • Decision made to bring payroll ‘in-house’ by acquiring an ‘off-the-shelf’ application
  • 6. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 6 Project scenario - continued • The use of the off-the-shelf system will require a new, internal, payroll office to be set up • There will be a need to develop some software ‘add-ons’: one will take payroll data and combine it with time-table data to calculate the staff costs for each course run in the college • The project manager is Brigette.
  • 7. SPM (5e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2009 7 14-07-20
  • 8. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 8 Step 1 establish project scope and objectives • 1.1 Identify objectives and measures of effectiveness • ‘how do we know if we have succeeded?’ • 1.2 Establish a project authority • ‘who is the boss?’ • 1.3 Identify all stakeholders in the project and their interests • ‘who will be affected/involved in the project?’
  • 9. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 9 Step 1 continued • 1.4 Modify objectives in the light of stakeholder analysis • ‘do we need to do things to win over stakeholders?’ • 1.5 Establish methods of communication with all parties • ‘how do we keep in contact?’
  • 10. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 10 Back to the scenario • Project authority - Brigette finds she has two different clients for the new system: the finance department & the personnel office - A vice principal agrees to be official client, and monthly meetings are chaired by the VP and attended by Brigette and the heads of finance and personnel - These meetings would also help overcome communication barriers
  • 11. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 11 Back to the scenario - continued • Stakeholders • For example, personnel office would supply details of new staff, leavers and changes (e.g. promotions) • To motivate co-operation Brigette might ensure new payroll system produces reports that are useful to personnel staff
  • 12. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 12 Step 2 Establish project infrastructure • 2.1 Establish link between project and any strategic plan • ‘why did they want the project?’ • 2.2 Identify installation standards and procedures • ‘what standards do we have to follow?’ • 2.3. Identify project team organization • ‘where do I fit in?’
  • 13. Education is not the learning of facts…. But the training of the mind to think…. -- Albert Einstein 17-07-20 SPM (5e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2009 13
  • 14. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 14 Step 3 Analysis of project characteristics • 3.1 Distinguish the project as either objective or product-based. • Is there more than one way of achieving success? • 3.2 Analyse other project characteristics (including quality based ones) • what is different about this project?
  • 15. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 15 Step 3 continued • Identify high level project risks • ‘what could go wrong?’ • ‘what can we do to stop it?’ • Take into account user requirements concerning implementation • Select general life cycle approach • waterfall? Increments? Prototypes? • Review overall resource estimates • ‘does all this increase the cost?’
  • 16. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 16 Back to the scenario • Objectives vs. products • An objective-based approach has been adopted • Some risks • There may not be an off-the-shelf package that caters for the way payroll is processed at Brightmouth College • Answer? • Brigette decides to obtain details of how main candidate packages work as soon as possible; also agreement that if necessary processes will be changed to fit in with new system.
  • 17. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 17 Step 4 Identify project products and activities • 4.1 Identify and describe project products ‘what do we have to produce?’
  • 18. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 18 Products • The result of an activity • Could be (among other things) • physical thing (‘installed pc’), • a document (‘logical data structure’) • a person (‘trained user’) • a new version of an old product (‘updated software’)
  • 19. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 19 Products • The following are NOT normally products: • activities (e.g. ‘training’) • events (e.g. ‘interviews completed’) • resources and actors (e.g. ‘software developer’) - may be exceptions to this • Products CAN BE deliverable or intermediate
  • 20. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 20 Product description (PD) • Product identity • Description - what is it? • Derivation - what is it based on? • Composition - what does it contain? • Format • Relevant standards • Quality criteria Create a PD for ‘test data’
  • 21. Step 4 continued • 4.2 document generic- product flows SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 21
  • 22. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 22 Step 4 continued • 4.3 Recognize product instances • The PBS (Product breakdown Structure) and PFD (Product flow diagram) will probably have identified generic products e.g. ‘software modules’ • It might be possible to identify specific instances e.g. ‘module A’, ‘module B’ … • But in many cases this will have to be left to later, more detailed, planning
  • 23. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 23 Step 4 continued • 4.4. Produce ideal activity network • Identify the activities needed to create each product in the PFD • More than one activity might be needed to create a single product • Hint: Identify activities by verb + noun but avoid ‘produce…’ (too vague) • Draw up activity network
  • 24. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 24 An ‘ideal’ activity
  • 25. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 25 Step 4.5 Add check-points if needed Design module A Design module B Design system Design module C Code module A Code module B Code module C Test system Design module A Design module B Design system Design module C Code module A Code module B Code module C Test system Check-point put in a check point
  • 26. Successful and unsuccessful people do not vary greatly in their abilities.... They vary in their desires to reach their potential… 20-07-20 JYOTSNA ANTHAL CHAUHAN
  • 27. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 27 Step 5: Estimate effort for each activity • 5.1 Carry out bottom-up estimates • distinguish carefully between effort and elapsed time • 5.2. Revise plan to create controllable activities • break up very long activities into a series of smaller ones • bundle up very short activities (create check lists?)
  • 28. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 28 Step 6 Identify activity risks • 6.1.Identify and quantify risks for activities • damage if risk occurs (measure in time lost or money) • likelihood if risk occurring • 6.2. Plan risk reduction and contingency measures • risk reduction: activity to stop risk occurring • contingency: action if risk does occur
  • 29. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 29 • 6.3 Adjust overall plans and estimates to take account of risks • e.g. add new activities which reduce risks associated with other activities e.g. training, pilot trials, information gathering
  • 30. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 30 Step 7 Allocate resources • 7.1 Identify and allocate resources to activities • 7.2 Revise plans and estimates to take into account resource constraints • e.g. staff not being available until a later date • non-project activities
  • 31. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 31 Gantt charts Obtain user requirements Plan office layouts Week commencing 5 12 19 26 JUNE JULY 9 16 Analyse existing system 2 Draft and issue ITT Business analyst Systems assistant Business analyst Premises office LT = lead tester TA = testing assistant Survey potential suppliers Generate test cases Calculate volumes Business analyst Finance assistant Systems assistant
  • 32. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 32 Step 8 Review/publicise plan • 8.1 Review quality aspects of project plan • 8.2 Document plan and obtain agreement Step 9 & 10 Execute plan and create lower level plans
  • 33. SPM (6e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2017 33 Key points • Establish your objectives • Think about the characteristics of the project • Discover/set up the infrastructure to support the project (including standards) • Identify products to be created and the activities that will create them • Allocate resources • Set up quality processes
  • 34. End of Unit 1 The end of one chapter is just the beginning of another…. Read on…. The BEST part is always yet to come….. SPM (5e) Step Wise: an introduction to project planning© The McGraw-Hill Companies, 2009 34