IMPORTANT CODE REQUIREMENT AND
PRACTICES RELATED TO WELDING
2. Checkthe seamnumberon the job.
( A ) BEFORE STARTING WELDING
1. Forspecific seam:
Refershop weld plan, WPS and test plan.
2
( A ) BEFORE STARTING WELDING
6. Checkcable connections and earthing.
IMPORTANT CODE REQUIREMENT AND
PRACTICES RELATED TO WELDING
8. Provide run - in, run - out plates forL - seams.
25 mm 25 mm
25 mm25 mm
7. Clean WEP+25 mmon eitherside. Remove rust , paint, oil etc.
3
11. Use SS wire brush /wire wheel forSS, Inconels , Monels and
Cupro-nickels. Do not use grinding wheels used on CS.
9. Get temperature sticks for preheat & interpass.
Temperature > Preheat
< Interpass
25 mm 25 mm
BURNER
10. Checkpreheat at least 25 mm
away fromWEPon both sides.
IMPORTANT CODE REQUIREMENT AND
PRACTICES RELATED TO WELDING
4
IMPORTANT CODE REQUIREMENT AND
PRACTICES RELATED TO WELDING
2. Weaving < 3 x Electrode diameter.
( B) WHILE WELDING
1. Tacks and temporary cleats
- Use specified electrodes and preheats
- Qualified Welder
- No hammering
4. SMAWElectrode left overafter4 hrs - return to stores.
3. No stray arcing on job.
7
• WELD JOINT NOT CLEAN
• LOWER PREHEAT TEMPERATURE
WELDING DEFECTS
POROSITIES:
• STRONG WIND FLOW ON ARC
8
- GTAW / GMAW / FCAW :
• RUSTED FILLER WIRE
• DAMAGED TORCH- CLOGGED TUBE, GAS PASSAGE
• TURBULENT GAS FLOW - USE GAS LENS
• INADEQUATE GAS FLOW - FAULTY FLOW METER
• FCAW GAS PREHEATER NOT WORKING
• GAS PURITY CHECK
WELDING DEFECTS
POROSITIES:
9
• IMPROPER INTERPASS CLEANING
• POOR BEAD FINISH- ROUGH, LUMPY BEADS NOT
DRESSED BEFORE WELDING
• FAULTY RESTART - LUMP AT STARING POINT - TO BE
GROUND
• WELDING PARAMETERS (I,V, T.S) NOT AS PER WPS
• WRONG BEAD PLACEMENT
SLAG INCLUSIONS:
WELDING DEFECTS
10
• LOWER CURRENT
WELDING DEFECTS
LACK OF FUSION / PENETRATION
LF
LP
• POOR WEP / SET-UP - LOW ROOT GAP,
HIGH ROOT FACE, LOWER INCLUDED ANGLE
• RUST / PAINT ON WEP
11
• UNBAKED ELECTRODES / FLUXES
• LOW PREHEAT
• INSUFFICIENT POST HEATING
• UNCLEAN WELD JOINTS
WELDING DEFECTS
CRACKS
12
• HEAVY RESTRAINT- WELD TACKS WITH HIGHER
CROSS SECTION
• EXCESSIVE LOCAL HEATING - USE OF RING BURNERS
( NOZZLE# SHELL/ D.END JOINTS )
• USE OF WRONG ELECTRODE / FLUX
• FAULTY CONS. QUALITY / SELECTION
WELDING DEFECTS
CRACKS

More Related Content

Similar to Weld defects

01) workshop design consideration for bolted and welded connections -apr '20
01) workshop   design consideration for bolted and welded connections -apr '2001) workshop   design consideration for bolted and welded connections -apr '20
01) workshop design consideration for bolted and welded connections -apr '20sameer sawant
 
Handboek Aristorod Lasdraden
Handboek Aristorod LasdradenHandboek Aristorod Lasdraden
Handboek Aristorod LasdradenJorg Eichhorn
 
10 Ways to murder your pump.pdf
10 Ways to murder your pump.pdf10 Ways to murder your pump.pdf
10 Ways to murder your pump.pdfKetanBhore
 
Completion equipment part 1
Completion equipment part 1Completion equipment part 1
Completion equipment part 1Elsayed Amer
 
Managing Downhole Failures in a Rod Pumped Well
Managing Downhole Failures in a Rod Pumped Well Managing Downhole Failures in a Rod Pumped Well
Managing Downhole Failures in a Rod Pumped Well Ramez Abdalla, M.Sc
 
2005 CVX Hot Bolting Procedures.ppt
2005 CVX Hot Bolting Procedures.ppt2005 CVX Hot Bolting Procedures.ppt
2005 CVX Hot Bolting Procedures.pptDebbie Collett
 
The Impact of Temperature-on-Common Sealer Defects
The Impact of Temperature-on-Common Sealer DefectsThe Impact of Temperature-on-Common Sealer Defects
The Impact of Temperature-on-Common Sealer DefectsRob Gladstone
 
The Impact of Temperature On Common Sealer Defects
The Impact of Temperature On Common Sealer DefectsThe Impact of Temperature On Common Sealer Defects
The Impact of Temperature On Common Sealer DefectsAllison Spooner
 
Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trialNagesh H
 
140416_14_54_NAMAT_UPVC_DRAINAGE (4).pdf
140416_14_54_NAMAT_UPVC_DRAINAGE (4).pdf140416_14_54_NAMAT_UPVC_DRAINAGE (4).pdf
140416_14_54_NAMAT_UPVC_DRAINAGE (4).pdfGirgis A. Rezqallah
 
PRODUCT CATALOG RAPPID VALVES
PRODUCT CATALOG RAPPID VALVESPRODUCT CATALOG RAPPID VALVES
PRODUCT CATALOG RAPPID VALVESGaurav Dalal
 
LOST CIRCULATION - THE BASICS
LOST CIRCULATION - THE BASICSLOST CIRCULATION - THE BASICS
LOST CIRCULATION - THE BASICSMohan Doshi
 
Sn100c Bar Solder
Sn100c Bar SolderSn100c Bar Solder
Sn100c Bar SolderFCT Solder
 
PPE Demo Report by Tuan Afaham Burah
PPE Demo Report by Tuan Afaham BurahPPE Demo Report by Tuan Afaham Burah
PPE Demo Report by Tuan Afaham BurahTuan Afaham Burah
 

Similar to Weld defects (20)

Improving PCBA wave soldering Quality
Improving PCBA wave soldering QualityImproving PCBA wave soldering Quality
Improving PCBA wave soldering Quality
 
PROJECT PPT. (1)
PROJECT PPT. (1)PROJECT PPT. (1)
PROJECT PPT. (1)
 
Spot weldings
Spot weldingsSpot weldings
Spot weldings
 
01) workshop design consideration for bolted and welded connections -apr '20
01) workshop   design consideration for bolted and welded connections -apr '2001) workshop   design consideration for bolted and welded connections -apr '20
01) workshop design consideration for bolted and welded connections -apr '20
 
Handboek Aristorod Lasdraden
Handboek Aristorod LasdradenHandboek Aristorod Lasdraden
Handboek Aristorod Lasdraden
 
10 Ways to murder your pump.pdf
10 Ways to murder your pump.pdf10 Ways to murder your pump.pdf
10 Ways to murder your pump.pdf
 
Completion equipment part 1
Completion equipment part 1Completion equipment part 1
Completion equipment part 1
 
Managing Downhole Failures in a Rod Pumped Well
Managing Downhole Failures in a Rod Pumped Well Managing Downhole Failures in a Rod Pumped Well
Managing Downhole Failures in a Rod Pumped Well
 
2005 CVX Hot Bolting Procedures.ppt
2005 CVX Hot Bolting Procedures.ppt2005 CVX Hot Bolting Procedures.ppt
2005 CVX Hot Bolting Procedures.ppt
 
The Impact of Temperature-on-Common Sealer Defects
The Impact of Temperature-on-Common Sealer DefectsThe Impact of Temperature-on-Common Sealer Defects
The Impact of Temperature-on-Common Sealer Defects
 
The Impact of Temperature On Common Sealer Defects
The Impact of Temperature On Common Sealer DefectsThe Impact of Temperature On Common Sealer Defects
The Impact of Temperature On Common Sealer Defects
 
Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trial
 
140416_14_54_NAMAT_UPVC_DRAINAGE (4).pdf
140416_14_54_NAMAT_UPVC_DRAINAGE (4).pdf140416_14_54_NAMAT_UPVC_DRAINAGE (4).pdf
140416_14_54_NAMAT_UPVC_DRAINAGE (4).pdf
 
Steam blowing procedure
Steam blowing procedure Steam blowing procedure
Steam blowing procedure
 
PRODUCT CATALOG RAPPID VALVES
PRODUCT CATALOG RAPPID VALVESPRODUCT CATALOG RAPPID VALVES
PRODUCT CATALOG RAPPID VALVES
 
LOST CIRCULATION - THE BASICS
LOST CIRCULATION - THE BASICSLOST CIRCULATION - THE BASICS
LOST CIRCULATION - THE BASICS
 
Sn100c Bar Solder
Sn100c Bar SolderSn100c Bar Solder
Sn100c Bar Solder
 
PRESNTAION
PRESNTAIONPRESNTAION
PRESNTAION
 
Gas disaster in steel industries
Gas disaster in steel industriesGas disaster in steel industries
Gas disaster in steel industries
 
PPE Demo Report by Tuan Afaham Burah
PPE Demo Report by Tuan Afaham BurahPPE Demo Report by Tuan Afaham Burah
PPE Demo Report by Tuan Afaham Burah
 

More from Jithu John

More from Jithu John (17)

Hydrotest
HydrotestHydrotest
Hydrotest
 
Pwht1
Pwht1Pwht1
Pwht1
 
Rolling
RollingRolling
Rolling
 
Saw defects
Saw defectsSaw defects
Saw defects
 
Saw
SawSaw
Saw
 
Ut c
Ut cUt c
Ut c
 
Weld discountinuitie
Weld discountinuitieWeld discountinuitie
Weld discountinuitie
 
Weld ability of the new generation stainless steels
Weld ability of the new generation stainless steelsWeld ability of the new generation stainless steels
Weld ability of the new generation stainless steels
 
Weldability pc
Weldability pcWeldability pc
Weldability pc
 
Welding 1
Welding   1Welding   1
Welding 1
 
Welding 2
Welding  2Welding  2
Welding 2
 
Welding 3
Welding  3Welding  3
Welding 3
 
Welding 4
Welding  4Welding  4
Welding 4
 
Welding iv
Welding   ivWelding   iv
Welding iv
 
Welding flaws
Welding flawsWelding flaws
Welding flaws
 
Welding qualification a
Welding qualification aWelding qualification a
Welding qualification a
 
Radiography
RadiographyRadiography
Radiography
 

Recently uploaded

SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 

Recently uploaded (20)

SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 

Weld defects

  • 1. 1 IMPORTANT CODE REQUIREMENT AND PRACTICES RELATED TO WELDING 2. Checkthe seamnumberon the job. ( A ) BEFORE STARTING WELDING 1. Forspecific seam: Refershop weld plan, WPS and test plan.
  • 2. 2 ( A ) BEFORE STARTING WELDING 6. Checkcable connections and earthing. IMPORTANT CODE REQUIREMENT AND PRACTICES RELATED TO WELDING 8. Provide run - in, run - out plates forL - seams. 25 mm 25 mm 25 mm25 mm 7. Clean WEP+25 mmon eitherside. Remove rust , paint, oil etc.
  • 3. 3 11. Use SS wire brush /wire wheel forSS, Inconels , Monels and Cupro-nickels. Do not use grinding wheels used on CS. 9. Get temperature sticks for preheat & interpass. Temperature > Preheat < Interpass 25 mm 25 mm BURNER 10. Checkpreheat at least 25 mm away fromWEPon both sides. IMPORTANT CODE REQUIREMENT AND PRACTICES RELATED TO WELDING
  • 4. 4 IMPORTANT CODE REQUIREMENT AND PRACTICES RELATED TO WELDING 2. Weaving < 3 x Electrode diameter. ( B) WHILE WELDING 1. Tacks and temporary cleats - Use specified electrodes and preheats - Qualified Welder - No hammering 4. SMAWElectrode left overafter4 hrs - return to stores. 3. No stray arcing on job.
  • 5. 7 • WELD JOINT NOT CLEAN • LOWER PREHEAT TEMPERATURE WELDING DEFECTS POROSITIES: • STRONG WIND FLOW ON ARC
  • 6. 8 - GTAW / GMAW / FCAW : • RUSTED FILLER WIRE • DAMAGED TORCH- CLOGGED TUBE, GAS PASSAGE • TURBULENT GAS FLOW - USE GAS LENS • INADEQUATE GAS FLOW - FAULTY FLOW METER • FCAW GAS PREHEATER NOT WORKING • GAS PURITY CHECK WELDING DEFECTS POROSITIES:
  • 7. 9 • IMPROPER INTERPASS CLEANING • POOR BEAD FINISH- ROUGH, LUMPY BEADS NOT DRESSED BEFORE WELDING • FAULTY RESTART - LUMP AT STARING POINT - TO BE GROUND • WELDING PARAMETERS (I,V, T.S) NOT AS PER WPS • WRONG BEAD PLACEMENT SLAG INCLUSIONS: WELDING DEFECTS
  • 8. 10 • LOWER CURRENT WELDING DEFECTS LACK OF FUSION / PENETRATION LF LP • POOR WEP / SET-UP - LOW ROOT GAP, HIGH ROOT FACE, LOWER INCLUDED ANGLE • RUST / PAINT ON WEP
  • 9. 11 • UNBAKED ELECTRODES / FLUXES • LOW PREHEAT • INSUFFICIENT POST HEATING • UNCLEAN WELD JOINTS WELDING DEFECTS CRACKS
  • 10. 12 • HEAVY RESTRAINT- WELD TACKS WITH HIGHER CROSS SECTION • EXCESSIVE LOCAL HEATING - USE OF RING BURNERS ( NOZZLE# SHELL/ D.END JOINTS ) • USE OF WRONG ELECTRODE / FLUX • FAULTY CONS. QUALITY / SELECTION WELDING DEFECTS CRACKS