More Related Content Similar to 2005 CVX Hot Bolting Procedures.ppt (20) 2005 CVX Hot Bolting Procedures.ppt1. DOC ID
© Chevron 2005
CABGOC HOT BOLTING PROCEDURE
By FE Construction Group
November 2005
2. © Chevron 2005 2
CONTENTS
SUMMARY
INTRODUCTION
DEFINITION AND SCOPE
CRITERIA
PRE-JOB REQUIREMENTS
SAFETY GUIDELINES
PROCEDURE
3. © Chevron 2005 3
SUMMARY
Sequential removal and replacement of flange bolts
and nuts.
Only one bolt at a time.
On piping or process systems containing
pressurized materials.
4. © Chevron 2005 4
INTRODUCTION
Each activity should be considered on its individual
merits.
Each activity should follow the guidelines identified.
Guidelines are subject to limitations applied to
standard flanges.
For any doubt consult competent person.
5. © Chevron 2005 5
DEFINITION AND SCOPE
When preparing for equipment maintenance and
repair.
Only when all others methods are fully considered
and reasonably dismissed.
Not advisable when bolts have suffered significant
metal loss.
Safe approach: depressurize equipment and
change bolts off-line.
6. © Chevron 2005 6
CRITERIA
No hot bolting during simultaneous hot work.
Bolt cutting by any hot method is not allowed.
Consideration must be given for certain cold cutting
equipment.
If these options are not feasible then a low impact
flogging method is acceptable.
Operating pressure must be less than 75 % of the
MAWP at the operating temperature.
Flange must have a minimum of 8 bolts.
7. © Chevron 2005 7
CRITERIA (Continued)
Temperature must be between 40°F and 160°F.
No excessive vibration are allowed in the system.
Gasket must not show signs of leakage.
Piping, flanges and bolts must not be severely
corroded.
Existing flange bolts must be tight and of the
correct size and grade.
8. © Chevron 2005 8
PRE-JOB REQUIREMENTS
PSR & RMP and GWP approvals are required.
General Work Permit
Pre-job safety meeting and JSA checklist.
Piping or process system inspection.
Proper materials and tools.
MAWP and temperature.
Emergency plan of action / Spill containment
Location of upstream and downstream isolation
sources.
Control of potential ignition source.
9. © Chevron 2005 9
SAFETY GUIDELINES
Barrier off the hot bolting area.
Wear appropriate PPE, including safety eyewear.
Monitor gas presence before and during hot bolting
operations.
Maintain radio communications with Operations.
For any significant change, cease all hot bolting and
re-evaluate before continuing.
Never leave flanges with bolts missing during
breaks or at shift end.
11. © Chevron 2005 11
PROCEDURE (Continued)
For any doubt contact CABGOC FE-Construction
group for further information.
Exceptions to the above guidelines must be
reviewed / approved by CABGOC FE Construction
management.