Status of Geothermal
Development in Tanzania
Eng. Kato Kabaka
Tanzania Geothermal Company Limited (TGDC)
April, 2018
Iceland Geothermal Conference
Reykjavik, Iceland
Outline
1. Country in Brief
2. Significance of geothermal in energy mix
3. Policy and Legal framework
4. Establishment of State Owned Company (TGDC)
5. Geothermal Resources in Tanzania
6. Flagship projects update
7. Direct use opportunities
8. Capacity Development
9. Way forward
1. Tanzania In Brief Background information
• Country area: 945,087 km2
• Population: 55 million (2017 projections )
• Access to electricity: 67%
• Connection to electricity : 30%
• Grid installed capacity: 1431.42 MW;
-Gas: 782.82MW, Hydropower :567.7 MW,
Diesel/HFO: 70.4 MW, Biomass: 10.5MW
• Off grid & cross border imports: 94.3MW
• Target installed capacity by 2020: 5000 MW
 Increasing base load energy source
 Increasing system reliability
 Cushion against climate variability
 Increasingly cost-effectiveness
 Environmentally clean renewable energy
4
2. Significance of geothermal in the energy mix
• Regulatory Authority: EWURA Act, 2001
• Environmental Management Act, 2004;
• Public-Private Partnership Act, 2010 and its Regulations (2011);
• National Energy Policy, 2015 ( Energy policy document)
• Power System Master Plan 2016
• The Mining Act with its Regulations, 2010 and its updates 2017;
• Geothermal law ( legislation process has started)
3. Policies and Legal and regulatory framework
4. Establishment of TGDC
TGDC was established in December 2013; operational since July 2014
TGDC’S MANDATES
• Geothermal resource assessment
• Domestic capacity for geothermal development and Consultancy services
• Promoting direct uses of geothermal energy
• Assist the GOT to mobilize finance for geothermal resource development
• Geothermal power generation and supply steam for power generation
and direct use to public and private companies
TARGET: 200MW FROM GEOTHERMAL BY 2025
TGDC has developed a roadmap and project pipeline for 2025 target and
beyond up to 2042.
TGDC STRATEGIC FOCUS AREAS
1. Mobilize funds for project implementation
2. Capacity building (human skills and equipment)
3. Research and development (with higher learning institution)
4. Enabling environment- appropriate legal and regulatory framework
... TGDC in Brief
5. Geothermal Energy potential Areas in Tanzania
NGOZI
SONGWE
MBAKA- KIEJO
LUHOI
NATRON
Flagship Projects
1. Ngozi
2. Songwe
3. Kiejo- Mbaka
4. Luhoi
5. Natron
PROJEC
T SITE
STATUS
Ngozi
• Volcano- based geothermal system (T>223+130C)
• Preparations for Test Drilling ongoing
• Environmental certificate obtained
• GRMF support for 40% grant finance
• The GoT has allocated funds test drilling
• Test drilling planned in 2018/19
• Next steps: Infrastructure upgrading and
drilling of three slim test wells
• Funds: GOT/SREP/GRMF ( 17.5MUSD)
6. Status of Major Projects
PROJECT
SITE
STATUS
Songwe
• Fault- based geothermal system, T=112+ 160C
• Detailed surface study was completed in 2016
• Direct use study in progress (DFID/EAGER support)
• Gap filling study for shallow wells locations ongoing
• The GoT has allocated funds for test drilling
• Next steps: Infrastructure improvement and
drilling of three shallow wells
• Funds: GOT/SREP ( 650,000 USD)
5. Status of Major Projects
PROJECT • STATUS
MBAKA-
KIEJO
• Project located in SW Tanzania
• Medium temperature T=1400C
• Detail surface study completed in 2017;
• The test drilling locations identified.
• Mobilizing fund from GoT and GRMF 5th
AR (prequalified)
• Direct use study ongoing
• Environmental studies ongoing for permits
• Support: MFA-Iceland
PROJECT STATUS
Luhoi
• Project is located in coastal area
• Fault- based geothermal system
• Low temperature system
• Detailed surface study completed
• Working on Final report
• Support: MFA-Iceland/ ICEIDA
PROJECT STATUS
NATRON
• Natron is located at the southern
border with Kenya
• Preliminary surface study completed
• EoI submitted to GRMF 5th AR for co-
financing of detailed surface study
• Packaging of full application to GRMF
in preparation
• Next step is mobilization of funds for
test drilling
Site Status Next steps
Ngozi
Detailed surface study
completed
Mobilization of funds for test drilling (slim wells)
Estimated cost of test drilling =17.5MUSD
Songwe
Detailed surface study
completed
Mobilization of funds for test drilling (TGH),
Estimated cost of test drilling = 650,000 USD
Kiejo-Mbaka
Technical surface study
completed
Mobilization of funds for test drilling (GOT/GRMF)
Environmental studies ongoing
Luhoi Technical surface study
completed
Mobilization of funds for test drilling (GOT/GRMF)
Environmental studies ongoing
Natron Reconnaissance
Mobilization of funds for detailed surface study
(GOT/GRMF)
Summary of project implementation
7. Direct use opportunities
Firewood piles at Wakulima Tea Factory for drying tea
leavesRiverside fish farming
Green house farming near Ngozi project
No commercial application
✓ Swimming/refreshment
✓ Sinters for feeding animals
Potential uses
✓Drying of Agricultural produce
✓Greenhouse Farming
✓Aquaculture
✓Industrial uses
✓Direct space heating/cooling
✓Geo-tourism
✓Swimming pools/refreshment
8. Local Capacity building for geothermal development
a) Human skill development
• Good cooperation with local and international academic institutions
(UNU-GTP, AGCE/UNEP, Japan, local institutions, etc.,)
• Developing organizational & institutional capacity (geosciences,
engineering, compliance, project management, drilling, direct uses,
etc.)
b) Essential equipment and tools
• Acquisition of basic exploration equipment e.g.., MT, TEM, etc.
• Processes for procurement of small drilling rig is on going
1. Target is develop 200 MW from geothermal by 2025.
2. Projects consider both power generation and direct uses
3. Formulation of geothermal law on going
4. Development of local capacity for geothermal projects
5. Ngozi and Songwe projects are ready for test drilling
6. Mobilization of funds (GoT, GRMF, SREP, and other partners) to
support geothermal development ongoing
9.Way forward
Field team at work

More Related Content

What's hot

[Climate Change Program]City Paper Presentation : Beijing(China)
[Climate Change Program]City Paper Presentation : Beijing(China)[Climate Change Program]City Paper Presentation : Beijing(China)
[Climate Change Program]City Paper Presentation : Beijing(China)
shrdcinfo
 
Clinton climate initiative cci
Clinton climate initiative   cciClinton climate initiative   cci
Clinton climate initiative cci
cenafrica
 
[Climate Change Program]City Paper Presentation : Quito(Ecuador)
[Climate Change Program]City Paper Presentation : Quito(Ecuador)[Climate Change Program]City Paper Presentation : Quito(Ecuador)
[Climate Change Program]City Paper Presentation : Quito(Ecuador)
shrdcinfo
 
Rural Economic Development Organization Green Business Fund Presentation
Rural Economic Development Organization Green Business Fund PresentationRural Economic Development Organization Green Business Fund Presentation
Rural Economic Development Organization Green Business Fund Presentation
RV Rikard
 

What's hot (20)

[Climate Change Program]City Paper Presentation : Beijing(China)
[Climate Change Program]City Paper Presentation : Beijing(China)[Climate Change Program]City Paper Presentation : Beijing(China)
[Climate Change Program]City Paper Presentation : Beijing(China)
 
Clinton climate initiative cci
Clinton climate initiative   cciClinton climate initiative   cci
Clinton climate initiative cci
 
News Release: Commerce Resources Corp. Receives Grant for Environmental Studi...
News Release: Commerce Resources Corp. Receives Grant for Environmental Studi...News Release: Commerce Resources Corp. Receives Grant for Environmental Studi...
News Release: Commerce Resources Corp. Receives Grant for Environmental Studi...
 
Sectoral and-regional-mobilisation-to-support-the-achievement-of-indonesia’s-...
Sectoral and-regional-mobilisation-to-support-the-achievement-of-indonesia’s-...Sectoral and-regional-mobilisation-to-support-the-achievement-of-indonesia’s-...
Sectoral and-regional-mobilisation-to-support-the-achievement-of-indonesia’s-...
 
News Release: Commerce Resources Corp. Completes Preliminary Evaluation for ...
News Release:  Commerce Resources Corp. Completes Preliminary Evaluation for ...News Release:  Commerce Resources Corp. Completes Preliminary Evaluation for ...
News Release: Commerce Resources Corp. Completes Preliminary Evaluation for ...
 
[Climate Change Program]City Paper Presentation : Quito(Ecuador)
[Climate Change Program]City Paper Presentation : Quito(Ecuador)[Climate Change Program]City Paper Presentation : Quito(Ecuador)
[Climate Change Program]City Paper Presentation : Quito(Ecuador)
 
Energy Security and Resilience in the ASEAN Region - Prof Jun Arima | ERIA
Energy Security and Resilience in the ASEAN Region - Prof Jun Arima | ERIAEnergy Security and Resilience in the ASEAN Region - Prof Jun Arima | ERIA
Energy Security and Resilience in the ASEAN Region - Prof Jun Arima | ERIA
 
MNRE - Bio Energy Division
MNRE - Bio Energy DivisionMNRE - Bio Energy Division
MNRE - Bio Energy Division
 
Green Development of Small Hydropower: China’s Practice and Outlook
Green Development of Small Hydropower: China’s Practice and OutlookGreen Development of Small Hydropower: China’s Practice and Outlook
Green Development of Small Hydropower: China’s Practice and Outlook
 
B4 - Status of Geothermal Exploration and Development in Ethiopia
B4 - Status of  Geothermal Exploration and Development in EthiopiaB4 - Status of  Geothermal Exploration and Development in Ethiopia
B4 - Status of Geothermal Exploration and Development in Ethiopia
 
Presentation final2
Presentation final2Presentation final2
Presentation final2
 
Capacity Building on the IPCC 2013 Wetlands Supplement, FREL Diagnostic and U...
Capacity Building on the IPCC 2013 Wetlands Supplement, FREL Diagnostic and U...Capacity Building on the IPCC 2013 Wetlands Supplement, FREL Diagnostic and U...
Capacity Building on the IPCC 2013 Wetlands Supplement, FREL Diagnostic and U...
 
Powering sri lanka towards sustainability (Cabraal 03 Apr17)
Powering sri lanka towards sustainability (Cabraal 03 Apr17)Powering sri lanka towards sustainability (Cabraal 03 Apr17)
Powering sri lanka towards sustainability (Cabraal 03 Apr17)
 
NDC of sri lanka
NDC of sri lankaNDC of sri lanka
NDC of sri lanka
 
The wealth of scientific data to support FOLU Net Sinks 2030
The wealth of scientific data to support FOLU Net Sinks 2030The wealth of scientific data to support FOLU Net Sinks 2030
The wealth of scientific data to support FOLU Net Sinks 2030
 
Deep decarbonisation scenarios for New Zealand: perspectives of geothermal en...
Deep decarbonisation scenarios for New Zealand: perspectives of geothermal en...Deep decarbonisation scenarios for New Zealand: perspectives of geothermal en...
Deep decarbonisation scenarios for New Zealand: perspectives of geothermal en...
 
Rural Economic Development Organization Green Business Fund Presentation
Rural Economic Development Organization Green Business Fund PresentationRural Economic Development Organization Green Business Fund Presentation
Rural Economic Development Organization Green Business Fund Presentation
 
Geothermal Resources at the Azores
Geothermal Resources at the AzoresGeothermal Resources at the Azores
Geothermal Resources at the Azores
 
Biomethane in the Netherlands - current state and future outlook - Michael Sa...
Biomethane in the Netherlands - current state and future outlook - Michael Sa...Biomethane in the Netherlands - current state and future outlook - Michael Sa...
Biomethane in the Netherlands - current state and future outlook - Michael Sa...
 
Transition from coal fire power generation to renewable energy for public.pptx
Transition from coal fire power generation to renewable energy   for public.pptxTransition from coal fire power generation to renewable energy   for public.pptx
Transition from coal fire power generation to renewable energy for public.pptx
 

Similar to B2 - Status of Geothermal Development in Tanzania

Similar to B2 - Status of Geothermal Development in Tanzania (20)

C1 - STATUS OF GEOTHERMAL DEVELOPMENT IN MENENGAI AND BARINGO- SILALI PROJECTS
C1 - STATUS OF GEOTHERMAL DEVELOPMENT IN MENENGAI AND BARINGO- SILALI PROJECTSC1 - STATUS OF GEOTHERMAL DEVELOPMENT IN MENENGAI AND BARINGO- SILALI PROJECTS
C1 - STATUS OF GEOTHERMAL DEVELOPMENT IN MENENGAI AND BARINGO- SILALI PROJECTS
 
Climate finance sato (jica)coop geothermal energy dvpt indonesia-ccxg gf marc...
Climate finance sato (jica)coop geothermal energy dvpt indonesia-ccxg gf marc...Climate finance sato (jica)coop geothermal energy dvpt indonesia-ccxg gf marc...
Climate finance sato (jica)coop geothermal energy dvpt indonesia-ccxg gf marc...
 
Philippine Geothermal Industry: Current Status and Perspectives
Philippine Geothermal Industry: Current Status and Perspectives�Philippine Geothermal Industry: Current Status and Perspectives�
Philippine Geothermal Industry: Current Status and Perspectives
 
DGH Report
DGH ReportDGH Report
DGH Report
 
Strategies and Scenario for Geothermal Resource Development and Utilization i...
Strategies and Scenario for Geothermal Resource Development and Utilization i...Strategies and Scenario for Geothermal Resource Development and Utilization i...
Strategies and Scenario for Geothermal Resource Development and Utilization i...
 
4-RE Status.Phils (1).pdf
4-RE Status.Phils (1).pdf4-RE Status.Phils (1).pdf
4-RE Status.Phils (1).pdf
 
Prospect of Developments of the Clean Energy in Indonesia
Prospect of Developments of the Clean Energy in IndonesiaProspect of Developments of the Clean Energy in Indonesia
Prospect of Developments of the Clean Energy in Indonesia
 
Sustainable development model of geothermal energy
Sustainable development model of geothermal energySustainable development model of geothermal energy
Sustainable development model of geothermal energy
 
Bhutan Country Presentation at ACEF 2014
Bhutan Country Presentation at ACEF 2014Bhutan Country Presentation at ACEF 2014
Bhutan Country Presentation at ACEF 2014
 
Green hydrogen production potential and opportunities for Vietnam, Dr Pham Du...
Green hydrogen production potential and opportunities for Vietnam, Dr Pham Du...Green hydrogen production potential and opportunities for Vietnam, Dr Pham Du...
Green hydrogen production potential and opportunities for Vietnam, Dr Pham Du...
 
The Global Geothermal Development Plan
The Global Geothermal Development PlanThe Global Geothermal Development Plan
The Global Geothermal Development Plan
 
offshore.pptx
offshore.pptxoffshore.pptx
offshore.pptx
 
Geothermal Incentive Schemes in Germany, Kenya, New Zealand, Philippines and ...
Geothermal Incentive Schemes in Germany, Kenya, New Zealand, Philippines and ...Geothermal Incentive Schemes in Germany, Kenya, New Zealand, Philippines and ...
Geothermal Incentive Schemes in Germany, Kenya, New Zealand, Philippines and ...
 
New and renewable energy policy and investment in thailand 05-jun-13
New and renewable energy policy and investment in thailand 05-jun-13New and renewable energy policy and investment in thailand 05-jun-13
New and renewable energy policy and investment in thailand 05-jun-13
 
230729 Investment Forum Tokyo_Draft.pdf
230729 Investment Forum Tokyo_Draft.pdf230729 Investment Forum Tokyo_Draft.pdf
230729 Investment Forum Tokyo_Draft.pdf
 
A2 - SENER: Setting the Frame for Success
A2 - SENER: Setting the Frame for SuccessA2 - SENER: Setting the Frame for Success
A2 - SENER: Setting the Frame for Success
 
EIA Report Analysis of Rampal Power Plant
EIA Report Analysis of Rampal Power PlantEIA Report Analysis of Rampal Power Plant
EIA Report Analysis of Rampal Power Plant
 
Day 1_Session3_TRIPS_WASDS_ICRISAT
Day 1_Session3_TRIPS_WASDS_ICRISATDay 1_Session3_TRIPS_WASDS_ICRISAT
Day 1_Session3_TRIPS_WASDS_ICRISAT
 
Enhancing The Regulatory Framework for Non Conventional Geothermal Resources
Enhancing The Regulatory Framework for Non Conventional Geothermal ResourcesEnhancing The Regulatory Framework for Non Conventional Geothermal Resources
Enhancing The Regulatory Framework for Non Conventional Geothermal Resources
 
Renewable energy-masterplan-february-2019
Renewable energy-masterplan-february-2019Renewable energy-masterplan-february-2019
Renewable energy-masterplan-february-2019
 

More from Iceland Geothermal

More from Iceland Geothermal (20)

Geothermal Landscape study final
Geothermal Landscape study finalGeothermal Landscape study final
Geothermal Landscape study final
 
A1 Winning Public Acceptance: Preparation of Geothermal Sustainability Asses...
A1  Winning Public Acceptance: Preparation of Geothermal Sustainability Asses...A1  Winning Public Acceptance: Preparation of Geothermal Sustainability Asses...
A1 Winning Public Acceptance: Preparation of Geothermal Sustainability Asses...
 
C4 - Geothermal Fuels Prosperity: How Geothermal Direct Use Projects Enable ...
C4 - Geothermal Fuels Prosperity:  How Geothermal Direct Use Projects Enable ...C4 - Geothermal Fuels Prosperity:  How Geothermal Direct Use Projects Enable ...
C4 - Geothermal Fuels Prosperity: How Geothermal Direct Use Projects Enable ...
 
C4 - Climeworks: Capturing CO2 from air
C4 - Climeworks: Capturing CO2 from airC4 - Climeworks: Capturing CO2 from air
C4 - Climeworks: Capturing CO2 from air
 
C4 - Opportunities to develop low-enthalpy geothermal project in Mexico
C4 - Opportunities to develop low-enthalpy geothermal project in MexicoC4 - Opportunities to develop low-enthalpy geothermal project in Mexico
C4 - Opportunities to develop low-enthalpy geothermal project in Mexico
 
C4 - Lithium recovery from high temperature geothermal brines.
C4 - Lithium recovery from high temperature geothermal brines.C4 - Lithium recovery from high temperature geothermal brines.
C4 - Lithium recovery from high temperature geothermal brines.
 
C4 - Transforming CO2 into a commercial product
C4 - Transforming CO2 into a commercial productC4 - Transforming CO2 into a commercial product
C4 - Transforming CO2 into a commercial product
 
C3 - Production Modelling for Sustainability
C3 - Production Modelling for SustainabilityC3 - Production Modelling for Sustainability
C3 - Production Modelling for Sustainability
 
C3 - IDDP2 A better tomorrow
C3 - IDDP2 A better tomorrowC3 - IDDP2 A better tomorrow
C3 - IDDP2 A better tomorrow
 
C3 - Production and reinjection at Hellisheiði: Holistic approach
C3 - Production and reinjection at Hellisheiði: Holistic approachC3 - Production and reinjection at Hellisheiði: Holistic approach
C3 - Production and reinjection at Hellisheiði: Holistic approach
 
C3 - Geothermal reservoir management and sustainable use
C3 - Geothermal reservoir management and sustainable useC3 - Geothermal reservoir management and sustainable use
C3 - Geothermal reservoir management and sustainable use
 
C2 - Optimization of existing systems: Improvement of plants in operation and...
C2 - Optimization of existing systems: Improvement of plants in operation and...C2 - Optimization of existing systems: Improvement of plants in operation and...
C2 - Optimization of existing systems: Improvement of plants in operation and...
 
C2 - Managing Silica Deposits in Geothermal: Pros & Cons of pH Mod vs. Silica...
C2 - Managing Silica Deposits in Geothermal: Pros & Cons of pH Mod vs. Silica...C2 - Managing Silica Deposits in Geothermal: Pros & Cons of pH Mod vs. Silica...
C2 - Managing Silica Deposits in Geothermal: Pros & Cons of pH Mod vs. Silica...
 
C2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATION
C2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATIONC2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATION
C2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATION
 
C2 - ENGINEERING THE ENERGY TRANSITION
C2 - ENGINEERING THE  ENERGY TRANSITIONC2 - ENGINEERING THE  ENERGY TRANSITION
C2 - ENGINEERING THE ENERGY TRANSITION
 
C1 - Impacting Operating Costs and Revenues: If Geothermal is so Clever, wher...
C1 - Impacting Operating Costs and Revenues: If Geothermal is so Clever, wher...C1 - Impacting Operating Costs and Revenues: If Geothermal is so Clever, wher...
C1 - Impacting Operating Costs and Revenues: If Geothermal is so Clever, wher...
 
C1 - Operation: Ownership Structure and its Effects
C1 - Operation: Ownership Structure and its EffectsC1 - Operation: Ownership Structure and its Effects
C1 - Operation: Ownership Structure and its Effects
 
C1 - Financing Geothermal Development: Overview, Challenges and opportunities...
C1 - Financing Geothermal Development: Overview, Challenges and opportunities...C1 - Financing Geothermal Development: Overview, Challenges and opportunities...
C1 - Financing Geothermal Development: Overview, Challenges and opportunities...
 
B4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
B4 - Successful Implementation of a Modular Geothermal Wellhead StrategyB4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
B4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
 
B4 - RG: The Corbetti and Tulu Moye Geothermal Projects
B4 - RG: The Corbetti and Tulu Moye Geothermal ProjectsB4 - RG: The Corbetti and Tulu Moye Geothermal Projects
B4 - RG: The Corbetti and Tulu Moye Geothermal Projects
 

Recently uploaded

Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
Chris Hunter
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
QucHHunhnh
 
An Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdfAn Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdf
SanaAli374401
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
kauryashika82
 
Gardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch LetterGardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch Letter
MateoGardella
 

Recently uploaded (20)

Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
An Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdfAn Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdf
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Gardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch LetterGardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch Letter
 

B2 - Status of Geothermal Development in Tanzania

  • 1. Status of Geothermal Development in Tanzania Eng. Kato Kabaka Tanzania Geothermal Company Limited (TGDC) April, 2018 Iceland Geothermal Conference Reykjavik, Iceland
  • 2. Outline 1. Country in Brief 2. Significance of geothermal in energy mix 3. Policy and Legal framework 4. Establishment of State Owned Company (TGDC) 5. Geothermal Resources in Tanzania 6. Flagship projects update 7. Direct use opportunities 8. Capacity Development 9. Way forward
  • 3. 1. Tanzania In Brief Background information • Country area: 945,087 km2 • Population: 55 million (2017 projections ) • Access to electricity: 67% • Connection to electricity : 30% • Grid installed capacity: 1431.42 MW; -Gas: 782.82MW, Hydropower :567.7 MW, Diesel/HFO: 70.4 MW, Biomass: 10.5MW • Off grid & cross border imports: 94.3MW • Target installed capacity by 2020: 5000 MW
  • 4.  Increasing base load energy source  Increasing system reliability  Cushion against climate variability  Increasingly cost-effectiveness  Environmentally clean renewable energy 4 2. Significance of geothermal in the energy mix
  • 5. • Regulatory Authority: EWURA Act, 2001 • Environmental Management Act, 2004; • Public-Private Partnership Act, 2010 and its Regulations (2011); • National Energy Policy, 2015 ( Energy policy document) • Power System Master Plan 2016 • The Mining Act with its Regulations, 2010 and its updates 2017; • Geothermal law ( legislation process has started) 3. Policies and Legal and regulatory framework
  • 6. 4. Establishment of TGDC TGDC was established in December 2013; operational since July 2014 TGDC’S MANDATES • Geothermal resource assessment • Domestic capacity for geothermal development and Consultancy services • Promoting direct uses of geothermal energy • Assist the GOT to mobilize finance for geothermal resource development • Geothermal power generation and supply steam for power generation and direct use to public and private companies
  • 7. TARGET: 200MW FROM GEOTHERMAL BY 2025 TGDC has developed a roadmap and project pipeline for 2025 target and beyond up to 2042. TGDC STRATEGIC FOCUS AREAS 1. Mobilize funds for project implementation 2. Capacity building (human skills and equipment) 3. Research and development (with higher learning institution) 4. Enabling environment- appropriate legal and regulatory framework ... TGDC in Brief
  • 8. 5. Geothermal Energy potential Areas in Tanzania NGOZI SONGWE MBAKA- KIEJO LUHOI NATRON Flagship Projects 1. Ngozi 2. Songwe 3. Kiejo- Mbaka 4. Luhoi 5. Natron
  • 9. PROJEC T SITE STATUS Ngozi • Volcano- based geothermal system (T>223+130C) • Preparations for Test Drilling ongoing • Environmental certificate obtained • GRMF support for 40% grant finance • The GoT has allocated funds test drilling • Test drilling planned in 2018/19 • Next steps: Infrastructure upgrading and drilling of three slim test wells • Funds: GOT/SREP/GRMF ( 17.5MUSD) 6. Status of Major Projects
  • 10. PROJECT SITE STATUS Songwe • Fault- based geothermal system, T=112+ 160C • Detailed surface study was completed in 2016 • Direct use study in progress (DFID/EAGER support) • Gap filling study for shallow wells locations ongoing • The GoT has allocated funds for test drilling • Next steps: Infrastructure improvement and drilling of three shallow wells • Funds: GOT/SREP ( 650,000 USD) 5. Status of Major Projects
  • 11. PROJECT • STATUS MBAKA- KIEJO • Project located in SW Tanzania • Medium temperature T=1400C • Detail surface study completed in 2017; • The test drilling locations identified. • Mobilizing fund from GoT and GRMF 5th AR (prequalified) • Direct use study ongoing • Environmental studies ongoing for permits • Support: MFA-Iceland
  • 12. PROJECT STATUS Luhoi • Project is located in coastal area • Fault- based geothermal system • Low temperature system • Detailed surface study completed • Working on Final report • Support: MFA-Iceland/ ICEIDA
  • 13. PROJECT STATUS NATRON • Natron is located at the southern border with Kenya • Preliminary surface study completed • EoI submitted to GRMF 5th AR for co- financing of detailed surface study • Packaging of full application to GRMF in preparation • Next step is mobilization of funds for test drilling
  • 14. Site Status Next steps Ngozi Detailed surface study completed Mobilization of funds for test drilling (slim wells) Estimated cost of test drilling =17.5MUSD Songwe Detailed surface study completed Mobilization of funds for test drilling (TGH), Estimated cost of test drilling = 650,000 USD Kiejo-Mbaka Technical surface study completed Mobilization of funds for test drilling (GOT/GRMF) Environmental studies ongoing Luhoi Technical surface study completed Mobilization of funds for test drilling (GOT/GRMF) Environmental studies ongoing Natron Reconnaissance Mobilization of funds for detailed surface study (GOT/GRMF) Summary of project implementation
  • 15. 7. Direct use opportunities Firewood piles at Wakulima Tea Factory for drying tea leavesRiverside fish farming Green house farming near Ngozi project No commercial application ✓ Swimming/refreshment ✓ Sinters for feeding animals Potential uses ✓Drying of Agricultural produce ✓Greenhouse Farming ✓Aquaculture ✓Industrial uses ✓Direct space heating/cooling ✓Geo-tourism ✓Swimming pools/refreshment
  • 16. 8. Local Capacity building for geothermal development a) Human skill development • Good cooperation with local and international academic institutions (UNU-GTP, AGCE/UNEP, Japan, local institutions, etc.,) • Developing organizational & institutional capacity (geosciences, engineering, compliance, project management, drilling, direct uses, etc.) b) Essential equipment and tools • Acquisition of basic exploration equipment e.g.., MT, TEM, etc. • Processes for procurement of small drilling rig is on going
  • 17. 1. Target is develop 200 MW from geothermal by 2025. 2. Projects consider both power generation and direct uses 3. Formulation of geothermal law on going 4. Development of local capacity for geothermal projects 5. Ngozi and Songwe projects are ready for test drilling 6. Mobilization of funds (GoT, GRMF, SREP, and other partners) to support geothermal development ongoing 9.Way forward