2. Programme Update - ITS
For Period : Mon 9th November – Friday 20th November
- Completed reduced level dig to to new ground floor slab and pad foundations
- Completed concrete pours to perimeter retaining walls and stripped formwork
- Commenced ‘making good’ to walls within rooms of existing building
- Completed self level screeding and preparatory overboarding to existing sub-floors
- Continued internal builders work; including installing required lintels and steelwork
- Continued first fix mechanical and electrical works within existing building to all
floors
4. Progress Photos – External
Bolt boxes made and cast in
preparation for steelwork
installation
5. Progress Photos – External
Pad foundations excavated
and DPM/reinforcement
installed prior to concrete
pour
6. Progress Photos – Internal
First fix mechanical and
electrical works continued
within the existing building
through all floors
7. Progress Photos – Internal
Temporary propping system
installed to facilitate
installation of internal load
bearing steelwork
8. Progress Photos – Internal
Continued infill of new
plasterboard ceilings to
rooms throughout floors
within existing building
9. Progress Photos – Internal
Completed overboarding
of existing sub floors to
rooms throughout
10. Progress Photos – Internal
Commenced ‘making good’
to rooms within existing
building including wallpaper
strip and localised filling of
holes etc.
11. Next Few Weeks………..
A look ahead to works commencing within the next 2 weeks :
- Complete concrete pour to pad foundations
- Complete external drainage works including new manhole and channel drainage
- Backfill and compact surrounding areas with Type 1 stone
- Commence external steelwork installation
- Continue overboarding existing ceilings to all floors within existing building
- Complete internal builders work; including installing required lintels and steelwork
- Continue first fix mechanical and electrical works within existing building to all floors