SlideShare a Scribd company logo
1 of 11
Download to read offline
Progress Update (Nr. 5)
Week ending 20th November
Programme Update - ITS
For Period : Mon 9th November – Friday 20th November
- Completed reduced level dig to to new ground floor slab and pad foundations
- Completed concrete pours to perimeter retaining walls and stripped formwork
- Commenced ‘making good’ to walls within rooms of existing building
- Completed self level screeding and preparatory overboarding to existing sub-floors
- Continued internal builders work; including installing required lintels and steelwork
- Continued first fix mechanical and electrical works within existing building to all
floors
Progress Photos – External
Basement retaining walls
poured and formwork
stripped
Progress Photos – External
Bolt boxes made and cast in
preparation for steelwork
installation
Progress Photos – External
Pad foundations excavated
and DPM/reinforcement
installed prior to concrete
pour
Progress Photos – Internal
First fix mechanical and
electrical works continued
within the existing building
through all floors
Progress Photos – Internal
Temporary propping system
installed to facilitate
installation of internal load
bearing steelwork
Progress Photos – Internal
Continued infill of new
plasterboard ceilings to
rooms throughout floors
within existing building
Progress Photos – Internal
Completed overboarding
of existing sub floors to
rooms throughout
Progress Photos – Internal
Commenced ‘making good’
to rooms within existing
building including wallpaper
strip and localised filling of
holes etc.
Next Few Weeks………..
A look ahead to works commencing within the next 2 weeks :
- Complete concrete pour to pad foundations
- Complete external drainage works including new manhole and channel drainage
- Backfill and compact surrounding areas with Type 1 stone
- Commence external steelwork installation
- Continue overboarding existing ceilings to all floors within existing building
- Complete internal builders work; including installing required lintels and steelwork
- Continue first fix mechanical and electrical works within existing building to all floors

More Related Content

What's hot

Plots for sale in electronic city
Plots for sale in electronic cityPlots for sale in electronic city
Plots for sale in electronic cityprovidenthousing4
 
Flats for Sale in whitefield, Bangalore
Flats for Sale in whitefield, BangaloreFlats for Sale in whitefield, Bangalore
Flats for Sale in whitefield, Bangaloreprovidenthousing4
 
Fontainebleau Article
Fontainebleau ArticleFontainebleau Article
Fontainebleau ArticleRobert Meller
 
Big Water Visitor Center
Big Water Visitor CenterBig Water Visitor Center
Big Water Visitor CenterRay Rankin
 
Marie Reed School Construction Project Update (April 21, 2017)
Marie Reed School Construction Project Update (April 21, 2017)Marie Reed School Construction Project Update (April 21, 2017)
Marie Reed School Construction Project Update (April 21, 2017)DC Department of General Services
 
Acme Carpentry 09 V2
Acme Carpentry 09 V2Acme Carpentry 09 V2
Acme Carpentry 09 V2spfaust
 
Michael H. Casey Designs
Michael H. Casey DesignsMichael H. Casey Designs
Michael H. Casey DesignsMichaelHCasey
 
Eastern Virtual Open House Deck
Eastern Virtual Open House DeckEastern Virtual Open House Deck
Eastern Virtual Open House DeckCrosstown TO
 
Spring Virtual Open House: West - Mount Dennis to Cedarvale
Spring Virtual Open House: West - Mount Dennis to CedarvaleSpring Virtual Open House: West - Mount Dennis to Cedarvale
Spring Virtual Open House: West - Mount Dennis to CedarvaleCrosstown TO
 
Earth House Field Building Process
Earth House Field Building ProcessEarth House Field Building Process
Earth House Field Building ProcessTimo Kettunen
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
2016 portfolio after uni
2016 portfolio after uni2016 portfolio after uni
2016 portfolio after uniShuxiao Zheng
 
Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)Crosstown TO
 
Eglinton-Mount Pleasant Construction update - May 2020
Eglinton-Mount Pleasant Construction update - May 2020Eglinton-Mount Pleasant Construction update - May 2020
Eglinton-Mount Pleasant Construction update - May 2020Crosstown TO
 
Ben Williams Resume 2016
Ben Williams Resume 2016Ben Williams Resume 2016
Ben Williams Resume 2016Ben Williams
 
R. A. Edwards and Partners Ltd. Company Profile
R. A. Edwards and Partners Ltd.   Company ProfileR. A. Edwards and Partners Ltd.   Company Profile
R. A. Edwards and Partners Ltd. Company Profiledownsy222
 

What's hot (20)

Plots for sale in electronic city
Plots for sale in electronic cityPlots for sale in electronic city
Plots for sale in electronic city
 
Flats for Sale in whitefield, Bangalore
Flats for Sale in whitefield, BangaloreFlats for Sale in whitefield, Bangalore
Flats for Sale in whitefield, Bangalore
 
Fontainebleau Article
Fontainebleau ArticleFontainebleau Article
Fontainebleau Article
 
Big Water Visitor Center
Big Water Visitor CenterBig Water Visitor Center
Big Water Visitor Center
 
Wellesley High School Project
Wellesley High School ProjectWellesley High School Project
Wellesley High School Project
 
Marie Reed School Construction Project Update (April 21, 2017)
Marie Reed School Construction Project Update (April 21, 2017)Marie Reed School Construction Project Update (April 21, 2017)
Marie Reed School Construction Project Update (April 21, 2017)
 
Acme Carpentry 09 V2
Acme Carpentry 09 V2Acme Carpentry 09 V2
Acme Carpentry 09 V2
 
Michael H. Casey Designs
Michael H. Casey DesignsMichael H. Casey Designs
Michael H. Casey Designs
 
Eastern Virtual Open House Deck
Eastern Virtual Open House DeckEastern Virtual Open House Deck
Eastern Virtual Open House Deck
 
Spring Virtual Open House: West - Mount Dennis to Cedarvale
Spring Virtual Open House: West - Mount Dennis to CedarvaleSpring Virtual Open House: West - Mount Dennis to Cedarvale
Spring Virtual Open House: West - Mount Dennis to Cedarvale
 
Earth House Field Building Process
Earth House Field Building ProcessEarth House Field Building Process
Earth House Field Building Process
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
2016 portfolio after uni
2016 portfolio after uni2016 portfolio after uni
2016 portfolio after uni
 
Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)
 
Eglinton-Mount Pleasant Construction update - May 2020
Eglinton-Mount Pleasant Construction update - May 2020Eglinton-Mount Pleasant Construction update - May 2020
Eglinton-Mount Pleasant Construction update - May 2020
 
mathys eugene cv
mathys eugene cvmathys eugene cv
mathys eugene cv
 
Ben Williams Resume 2016
Ben Williams Resume 2016Ben Williams Resume 2016
Ben Williams Resume 2016
 
R. A. Edwards and Partners Ltd. Company Profile
R. A. Edwards and Partners Ltd.   Company ProfileR. A. Edwards and Partners Ltd.   Company Profile
R. A. Edwards and Partners Ltd. Company Profile
 

Viewers also liked

Teamswear be voetbal-voetballen-derbystar
Teamswear be voetbal-voetballen-derbystarTeamswear be voetbal-voetballen-derbystar
Teamswear be voetbal-voetballen-derbystarTeam Swear
 
Trainingspakken ADIDAS Trainingspakken - Teamswear
Trainingspakken  ADIDAS Trainingspakken - TeamswearTrainingspakken  ADIDAS Trainingspakken - Teamswear
Trainingspakken ADIDAS Trainingspakken - TeamswearTeam Swear
 
I breathing
I breathingI breathing
I breathinggranbata
 
Catàleg de nadal
Catàleg de nadalCatàleg de nadal
Catàleg de nadalecojust
 
Den faglige udviklingsproces
Den faglige udviklingsprocesDen faglige udviklingsproces
Den faglige udviklingsprocesTobias Stampesøe
 
How the Internet of Things will change our lives?
How the Internet of Things will change our lives?How the Internet of Things will change our lives?
How the Internet of Things will change our lives?Patryk Omiotek
 
ADIDAS Trainingspakken - Teamswear
ADIDAS Trainingspakken - TeamswearADIDAS Trainingspakken - Teamswear
ADIDAS Trainingspakken - TeamswearTeam Swear
 
Overview of European Activities on Human Factors on Vehicle Automation 2015
Overview of European Activities on Human Factors on Vehicle Automation 2015Overview of European Activities on Human Factors on Vehicle Automation 2015
Overview of European Activities on Human Factors on Vehicle Automation 2015Institute for Transport Studies (ITS)
 
Inclusive urban mobility - social equity and mass transport systems in Quito,...
Inclusive urban mobility - social equity and mass transport systems in Quito,...Inclusive urban mobility - social equity and mass transport systems in Quito,...
Inclusive urban mobility - social equity and mass transport systems in Quito,...Institute for Transport Studies (ITS)
 
Building an evidence base (almost) from scratch: what to do when you don't ha...
Building an evidence base (almost) from scratch: what to do when you don't ha...Building an evidence base (almost) from scratch: what to do when you don't ha...
Building an evidence base (almost) from scratch: what to do when you don't ha...Institute for Transport Studies (ITS)
 
Understanding the GDP impact of infrastructure investment - learning from tra...
Understanding the GDP impact of infrastructure investment - learning from tra...Understanding the GDP impact of infrastructure investment - learning from tra...
Understanding the GDP impact of infrastructure investment - learning from tra...Institute for Transport Studies (ITS)
 
Dé'télé - semaine du 24 au 30 janvier
Dé'télé  - semaine du 24 au 30 janvierDé'télé  - semaine du 24 au 30 janvier
Dé'télé - semaine du 24 au 30 janvierJoris Laquittant
 

Viewers also liked (20)

ITS Building Project - progress update 6
ITS Building Project - progress update 6ITS Building Project - progress update 6
ITS Building Project - progress update 6
 
Teamswear be voetbal-voetballen-derbystar
Teamswear be voetbal-voetballen-derbystarTeamswear be voetbal-voetballen-derbystar
Teamswear be voetbal-voetballen-derbystar
 
Trainingspakken ADIDAS Trainingspakken - Teamswear
Trainingspakken  ADIDAS Trainingspakken - TeamswearTrainingspakken  ADIDAS Trainingspakken - Teamswear
Trainingspakken ADIDAS Trainingspakken - Teamswear
 
WordpUp Lublin #1
WordpUp Lublin #1WordpUp Lublin #1
WordpUp Lublin #1
 
I breathing
I breathingI breathing
I breathing
 
Catàleg de nadal
Catàleg de nadalCatàleg de nadal
Catàleg de nadal
 
Den faglige udviklingsproces
Den faglige udviklingsprocesDen faglige udviklingsproces
Den faglige udviklingsproces
 
How the Internet of Things will change our lives?
How the Internet of Things will change our lives?How the Internet of Things will change our lives?
How the Internet of Things will change our lives?
 
ADIDAS Trainingspakken - Teamswear
ADIDAS Trainingspakken - TeamswearADIDAS Trainingspakken - Teamswear
ADIDAS Trainingspakken - Teamswear
 
Overview of European Activities on Human Factors on Vehicle Automation 2015
Overview of European Activities on Human Factors on Vehicle Automation 2015Overview of European Activities on Human Factors on Vehicle Automation 2015
Overview of European Activities on Human Factors on Vehicle Automation 2015
 
Women of Achievement - University of Leeds
Women of Achievement - University of LeedsWomen of Achievement - University of Leeds
Women of Achievement - University of Leeds
 
Visualisations of the ITS building project
Visualisations of the ITS building projectVisualisations of the ITS building project
Visualisations of the ITS building project
 
Making cycling equal - a new approach to planning
Making cycling equal - a new approach to planningMaking cycling equal - a new approach to planning
Making cycling equal - a new approach to planning
 
Inclusive urban mobility - social equity and mass transport systems in Quito,...
Inclusive urban mobility - social equity and mass transport systems in Quito,...Inclusive urban mobility - social equity and mass transport systems in Quito,...
Inclusive urban mobility - social equity and mass transport systems in Quito,...
 
The number 36 bus route - innovation in public transport
The number 36 bus route - innovation in public transportThe number 36 bus route - innovation in public transport
The number 36 bus route - innovation in public transport
 
Building an evidence base (almost) from scratch: what to do when you don't ha...
Building an evidence base (almost) from scratch: what to do when you don't ha...Building an evidence base (almost) from scratch: what to do when you don't ha...
Building an evidence base (almost) from scratch: what to do when you don't ha...
 
Understanding the GDP impact of infrastructure investment - learning from tra...
Understanding the GDP impact of infrastructure investment - learning from tra...Understanding the GDP impact of infrastructure investment - learning from tra...
Understanding the GDP impact of infrastructure investment - learning from tra...
 
Congestion pricing in Gothenburg
Congestion pricing in GothenburgCongestion pricing in Gothenburg
Congestion pricing in Gothenburg
 
The Near Miss Project - some findings and implications
The Near Miss Project - some findings and implicationsThe Near Miss Project - some findings and implications
The Near Miss Project - some findings and implications
 
Dé'télé - semaine du 24 au 30 janvier
Dé'télé  - semaine du 24 au 30 janvierDé'télé  - semaine du 24 au 30 janvier
Dé'télé - semaine du 24 au 30 janvier
 

Similar to ITS Building Project - progress update 5

Office Building Constructed in Nine Weeks !
Office Building Constructed in Nine Weeks !Office Building Constructed in Nine Weeks !
Office Building Constructed in Nine Weeks !wesleyvillhard
 
Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021 Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021 Crosstown TO
 
R&M Developments & Property Group Ltd
R&M Developments & Property Group LtdR&M Developments & Property Group Ltd
R&M Developments & Property Group LtdThomas McKenna
 
Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021Crosstown TO
 
Please click here to view the Cranmer Court Presentation
Please click here to view the Cranmer Court Presentation Please click here to view the Cranmer Court Presentation
Please click here to view the Cranmer Court Presentation vsproul
 

Similar to ITS Building Project - progress update 5 (9)

ITS Building Project - progress update 4
ITS Building Project - progress update 4ITS Building Project - progress update 4
ITS Building Project - progress update 4
 
ITS Bulding Project - progress update April 2016
ITS Bulding Project  - progress update April 2016 ITS Bulding Project  - progress update April 2016
ITS Bulding Project - progress update April 2016
 
ITS building project progress update 3
ITS building project progress update 3ITS building project progress update 3
ITS building project progress update 3
 
Office Building Constructed in Nine Weeks !
Office Building Constructed in Nine Weeks !Office Building Constructed in Nine Weeks !
Office Building Constructed in Nine Weeks !
 
Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021 Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021
 
R&M Developments & Property Group Ltd
R&M Developments & Property Group LtdR&M Developments & Property Group Ltd
R&M Developments & Property Group Ltd
 
Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021
 
progress of work till date
progress of work till dateprogress of work till date
progress of work till date
 
Please click here to view the Cranmer Court Presentation
Please click here to view the Cranmer Court Presentation Please click here to view the Cranmer Court Presentation
Please click here to view the Cranmer Court Presentation
 

More from Institute for Transport Studies (ITS)

Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...
Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...
Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...Institute for Transport Studies (ITS)
 
London's Crossrail Scheme - its evolution, governance, financing and challenges
London's Crossrail Scheme  - its evolution, governance, financing and challengesLondon's Crossrail Scheme  - its evolution, governance, financing and challenges
London's Crossrail Scheme - its evolution, governance, financing and challengesInstitute for Transport Studies (ITS)
 
A clustering method based on repeated trip behaviour to identify road user cl...
A clustering method based on repeated trip behaviour to identify road user cl...A clustering method based on repeated trip behaviour to identify road user cl...
A clustering method based on repeated trip behaviour to identify road user cl...Institute for Transport Studies (ITS)
 
Social networks, activities, and travel - building links to understand behaviour
Social networks, activities, and travel - building links to understand behaviourSocial networks, activities, and travel - building links to understand behaviour
Social networks, activities, and travel - building links to understand behaviourInstitute for Transport Studies (ITS)
 
Agent based car following model for heterogeneities of platoon driving with v...
Agent based car following model for heterogeneities of platoon driving with v...Agent based car following model for heterogeneities of platoon driving with v...
Agent based car following model for heterogeneities of platoon driving with v...Institute for Transport Studies (ITS)
 

More from Institute for Transport Studies (ITS) (20)

Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...
Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...
Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...
 
BA Geography with Transport Studies at the University of Leeds
BA Geography with Transport Studies at the University of LeedsBA Geography with Transport Studies at the University of Leeds
BA Geography with Transport Studies at the University of Leeds
 
Highways Benchmarking - Accelerating Impact
Highways Benchmarking - Accelerating ImpactHighways Benchmarking - Accelerating Impact
Highways Benchmarking - Accelerating Impact
 
Using telematics data to research traffic related air pollution
Using telematics data to research traffic related air pollutionUsing telematics data to research traffic related air pollution
Using telematics data to research traffic related air pollution
 
Masters Dissertation Posters 2017
Masters Dissertation Posters 2017Masters Dissertation Posters 2017
Masters Dissertation Posters 2017
 
Institute for Transport Studies - Masters Open Day 2017
Institute for Transport Studies - Masters Open Day 2017Institute for Transport Studies - Masters Open Day 2017
Institute for Transport Studies - Masters Open Day 2017
 
London's Crossrail Scheme - its evolution, governance, financing and challenges
London's Crossrail Scheme  - its evolution, governance, financing and challengesLondon's Crossrail Scheme  - its evolution, governance, financing and challenges
London's Crossrail Scheme - its evolution, governance, financing and challenges
 
Secretary of State Visit
Secretary of State VisitSecretary of State Visit
Secretary of State Visit
 
Business model innovation for electrical vehicle futures
Business model innovation for electrical vehicle futuresBusiness model innovation for electrical vehicle futures
Business model innovation for electrical vehicle futures
 
A clustering method based on repeated trip behaviour to identify road user cl...
A clustering method based on repeated trip behaviour to identify road user cl...A clustering method based on repeated trip behaviour to identify road user cl...
A clustering method based on repeated trip behaviour to identify road user cl...
 
Cars cars everywhere
Cars cars everywhereCars cars everywhere
Cars cars everywhere
 
Annual Review 2015-16 - University of leeds
Annual Review 2015-16 - University of leedsAnnual Review 2015-16 - University of leeds
Annual Review 2015-16 - University of leeds
 
Social networks, activities, and travel - building links to understand behaviour
Social networks, activities, and travel - building links to understand behaviourSocial networks, activities, and travel - building links to understand behaviour
Social networks, activities, and travel - building links to understand behaviour
 
Rail freight in Japan - track access
Rail freight in Japan - track accessRail freight in Japan - track access
Rail freight in Japan - track access
 
Real time traffic management - challenges and solutions
Real time traffic management - challenges and solutionsReal time traffic management - challenges and solutions
Real time traffic management - challenges and solutions
 
Proportionally fair scheduling for traffic light networks
Proportionally fair scheduling for traffic light networksProportionally fair scheduling for traffic light networks
Proportionally fair scheduling for traffic light networks
 
Capacity maximising traffic signal control policies
Capacity maximising traffic signal control policiesCapacity maximising traffic signal control policies
Capacity maximising traffic signal control policies
 
Bayesian risk assessment of autonomous vehicles
Bayesian risk assessment of autonomous vehiclesBayesian risk assessment of autonomous vehicles
Bayesian risk assessment of autonomous vehicles
 
Agent based car following model for heterogeneities of platoon driving with v...
Agent based car following model for heterogeneities of platoon driving with v...Agent based car following model for heterogeneities of platoon driving with v...
Agent based car following model for heterogeneities of platoon driving with v...
 
A new theory of lane selection on highways
A new theory of lane selection on highwaysA new theory of lane selection on highways
A new theory of lane selection on highways
 

Recently uploaded

Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...jaredbarbolino94
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementmkooblal
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 

Recently uploaded (20)

Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of management
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 

ITS Building Project - progress update 5

  • 1. Progress Update (Nr. 5) Week ending 20th November
  • 2. Programme Update - ITS For Period : Mon 9th November – Friday 20th November - Completed reduced level dig to to new ground floor slab and pad foundations - Completed concrete pours to perimeter retaining walls and stripped formwork - Commenced ‘making good’ to walls within rooms of existing building - Completed self level screeding and preparatory overboarding to existing sub-floors - Continued internal builders work; including installing required lintels and steelwork - Continued first fix mechanical and electrical works within existing building to all floors
  • 3. Progress Photos – External Basement retaining walls poured and formwork stripped
  • 4. Progress Photos – External Bolt boxes made and cast in preparation for steelwork installation
  • 5. Progress Photos – External Pad foundations excavated and DPM/reinforcement installed prior to concrete pour
  • 6. Progress Photos – Internal First fix mechanical and electrical works continued within the existing building through all floors
  • 7. Progress Photos – Internal Temporary propping system installed to facilitate installation of internal load bearing steelwork
  • 8. Progress Photos – Internal Continued infill of new plasterboard ceilings to rooms throughout floors within existing building
  • 9. Progress Photos – Internal Completed overboarding of existing sub floors to rooms throughout
  • 10. Progress Photos – Internal Commenced ‘making good’ to rooms within existing building including wallpaper strip and localised filling of holes etc.
  • 11. Next Few Weeks……….. A look ahead to works commencing within the next 2 weeks : - Complete concrete pour to pad foundations - Complete external drainage works including new manhole and channel drainage - Backfill and compact surrounding areas with Type 1 stone - Commence external steelwork installation - Continue overboarding existing ceilings to all floors within existing building - Complete internal builders work; including installing required lintels and steelwork - Continue first fix mechanical and electrical works within existing building to all floors