Non Destructive Investigation of ESR for Structural
Health Assessment
Mahipal Burdak, A K Gupta, S S Sankhla
Department of Structural Engineering, MBM Engineering College, JNV University, Jodhpur, Rajasthan, India
Abstract- Basic concept of structural health assessment of the
structure or structural evaluation is mainly based on visual
examination and NDT. The purpose of visual examination is to
know the status of structures under applied load and other
environmental. Structural health assessments can be made with
NDT methods to provide important information for the
structural performance of the concrete, rebar location etc. There
are different NDT Techniques for assessment of concrete quality
e.g. Rebound Hammer, Ultra Sonic Pulse Velocity, Impact-echo
etc. Sonic- Integrity Test (SIT) & Pile Integrity Tester is based
on principle of Impact-Echo. Rebound hammer can be used to
find hardness of the concrete structure surface, and its strength
is related using inbuilt calibration curve in the instrument. Ultra-
sonic Pulse Velocity Equipment can be used to observe wave
transmission through Concrete structure.
The Present paper includes the study of correlation of
experimental studies with laboratory results. The objective of
overall investigation is to assess the existing quality, integrity and
compressive strength of concrete in the raft, beam, column and
superstructure element. This can be utilized for overall
structural safety appraisal of the structure. Besides, in case of
any inadequacy in the concrete quality being revealed, suitable
remedial measures can also be suggested.
Keywords- Structural Health Assessment, Rebound Hammer,
Ultra Sonic Pulse Velocity, ESR/Elevated Service Reservoir
I. INTRODUCTION
DT of concrete is a relatively immature discipline.
Because of the two main reasons, the first is the
heterogeneous nature of concrete, which makes detection of
defects difficult to separate from naturally occurring
inclusions and the second reason is immature nature of
concrete.
Non-destructive test methods are used to determine
hardened concrete properties and to evaluate the condition of
concrete in deep foundations, super structure element, bridges,
buildings, pavements, dams and other concrete constructions.
Non-destructive testing is defined as testing that causes no
structurally significant damage to concrete. It does not
damage the intended performance of the element or member
under investigation. NDT has the ability to determine the
strength and durability of critical construction without
damaging them and test can be carried out on site.
NDT of concrete becomes necessary under many
circumstances, such as a natural calamity, fire or an
aggregative environment may damage the structure and
residual strength may need to be ascertained. NDT methods
can be used to estimate the in place strength, quality of
concrete and degree of deterioration due to overloading,
failure, chemical etc. or environmental attack etc. NDT
methods are applied to concrete construction for four primary
reasons i.e. Condition evaluation of older concrete for
rehabilitation purpose, Quality control of new construction,
troubleshooting of problems with new construction and
Quality assurance of concrete repairs.
II. PROBLEM STATEMENT
The ESR1
at Jimme Ki Dhani, Ramsar, Barmer India
started in about July 2016. The ESR designed, vetted and
approved at competent level for staging of 20 m and capacity
of 250 KL. It was planned as an Intze type tank. Bottom ring
beam reinforcement cage prepared by the firm and still
awaited for checking from the competent level and further
construction is stopped. According to Tender stipulation stair
case from first bracing and first braced with roof slab is
constructed at site. It was reported that the construction of
ESR up to fourth bracing was taken up in August 2016. The
height of bracing (c/c) from bottom level is 4.42, 4.12, 4.12,
and 4.12 & 3.57 m. Every bracing height was completed in
three lifts. Reinforcement Detail and Quality of Concrete
Pertaining to ESR is suspected, Copy of SBC, mix design and
record of site testing were made available.
During site testing some of data which could be gathered
are: 6 columns in plan, Size of brace beam 450 mm x 300
mm, Height of first brace (from its bottom) 4.42 m, Dia of
Column 450 mm. In the SBC test report value of SBC in t/m2
by shear failure criteria at 1.5m is given as 8.43 t/m2
, by
settlement criteria 9.74 t/m2
(Peck et al) & 8.93 t/m2
(IS
:8009). Recommendation of foundation depth is not available
and SBC at 02 Boreholes conduced. Strata of subsoil is
defined as dune sand up to 8.00m. Seismic Zone III
considered for design purpose. .
In the mix design report value of parameter K is taken as
1.65, stating that not more than 5 % of results are expected to
fall below fck. The proportion recommended is
N
International Journal of Latest Technology in Engineering, Management & Applied Science (IJLTEMAS)
2nd
Special Issue on Engineering and Technology | Volume VI, Issue VIS, June 2017 | ISSN 2278-2540
www.ijltemas.in Page 20
0.44:1.00:1.62:2.90. The report clearly mentions that no
admixture has to be used.
ESR at Jeeme Ki Dhani is constructed at sloped ground.
No plinth protection is proposed in drawing.
III. OBJECTIVE OF NONDESTRUCTIVE
INVESTIGATION
To assess the existing quality, integrity and allowable
compressive strength of concrete in the raft, beam, column
and foundation and super structure element which can be
utilized for overall structural safety. Besides, in case of any
inadequacy in the concrete quality being revealed, suitable
remedial measures can also be suggested.
IV. NDT RESULTS
Non Destructive Test results are given below on the
randomly selected elements accessed easily on the structure.
Table-I Results of Bar Locater Test at Jimme Ki Dhani ESR
Member
Details of Reinforcement as
Per Drawing
Details of
Reinforcement as Per
Investigation
TB 3/1 C2-C3
25 mm#03, Nos at Top &
Bottom Near to Support
with 2 legged strips of 8mm
@150mm C/C
02 Rebars at Side face
(1-Top +1-Bottom) at
support with 2 legged
strips
@148,155,160,135 mm
C/C
TB 3/1 C2-C3
25 mm#03, 20 mm#02 Nos
at Top & Bottom Near to
Mid Span with 2 legged
strips of 8mm @100mm
C/C
04 Rebars at Side face
(2-Top +2-Bottom) at
Mid Span with 2
legged strips of
@100,90,110,110 mm
C/C
TB 3/2 C3-C4
25 mm#03, Nos at Top &
Bottom Near to Support
with 2 legged strips of 8mm
@150mm C/C
03 Rebars at Top face
at support with 2
legged strips
@160,140,146 mm C/C
TB 3/2 C3-C4
25 mm#03, 20 mm#02 Nos
at Top & Bottom Near to
Mid Span with 2 legged
strips of 8mm @100mm
C/C
04 Rebars at Side face
(2-Top +2-Bottom) at
Mid Span with 2
legged strips of 3 bars
in 320mm
TB 3/2 C3-C4
25 mm#03, 20 mm#02 Nos
at Top & Bottom Near to
Mid Span with 2 legged
strips of 8mm @100mm
C/C
03 Rebars at Top face
at Mid Span with 2
legged strips of 3 bars
in 300mm
TB 3/2 C6-C1
25 mm#03, 20 mm#02 Nos
at Top & Bottom Near to
Mid Span with 2 legged
strips of 8mm @100mm
C/C
03 Rebars at Top face
at Mid Span with 2
legged strips of 3 bars
in 310mm
Column-1/5th 20mm# 12 Nos with strips
of 8mm@190mm c/c at Mid
12 Nos with strips of
8mm@185mm, 188mm
Span & 8mm@100mm c/c
at Corner
c/c at Mid Span
Column-1/2nd
20mm# 12 Nos with strips
of 8mm@190mm c/c at Mid
Span & 8mm@100mm c/c
at Corner
12 Nos with strips of
8mm@153mm, 137mm
c/c at Mid Span
Column-2/2nd
20mm# 12 Nos with strips
of 8mm@190mm c/c at Mid
Span & 8mm@100mm c/c
at Corner
12 Nos with strips of
8mm@189mm, 186mm
c/c at Mid Span
Column-2/3rd
20mm# 12 Nos with strips
of 8mm@190mm c/c at Mid
Span & 8mm@100mm c/c
at Corner
12 Nos with strips of
8mm@184mm, 191mm
c/c at Mid Span
Column-2/5th
20mm# 12 Nos with strips
of 8mm@190mm c/c at Mid
Span & 8mm@100mm c/c
at Corner
12 Nos
Column-3/2nd
20mm# 12 Nos with strips
of 8mm@190mm c/c at Mid
Span & 8mm@100mm c/c
at Corner
12 Nos with strips of
8mm@190mm, 185mm
c/c at Mid Span
Column-3/3rd
20mm# 12 Nos with strips
of 8mm@190mm c/c at Mid
Span & 8mm@100mm c/c
at Corner
12 Nos with strips of
8mm@190mm,
200mm, 205mm,
186mm c/c at Mid
Span
Column-3/5th
20mm# 12 Nos with strips
of 8mm@190mm c/c at Mid
Span & 8mm@100mm c/c
at Corner
12 Nos
Column-4/2nd
20mm# 12 Nos with strips
of 8mm@190mm c/c at Mid
Span & 8mm@100mm c/c
at Corner
12 Nos with strips of
8mm@170mm, 195mm
c/c at Mid Span &
8mm@95mm,105 mm
c/c at Corner
Column-4/3rd
20mm# 12 Nos with strips
of 8mm@190mm c/c at Mid
Span & 8mm@100mm c/c
at Corner
12 Nos
Column-5/2nd
20mm# 12 Nos with strips
of 8mm@190mm c/c at Mid
Span & 8mm@100mm c/c
at Corner
12 Nos with strips of
8mm@178mm, 195mm
c/c at Mid Span
Column-6/2nd
20mm# 12 Nos with strips
of 8mm@190mm c/c at Mid
Span & 8mm@100mm c/c
at Corner
12 Nos
Column-6/4th
20mm# 12 Nos with strips
of 8mm@190mm c/c at Mid
Span & 8mm@100mm c/c
at Corner
12 Nos with strips of
8mm@160mm, 170mm
c/c at Mid Span
Table-II Results of Rebound Hammer Test at Jimme Ki Dhani ESR
Member
Minim
um
Reboun
d No.
Maximu
m
Rebound
No.
Standar
d
Deviati
on
Averag
e
Reboun
d No.
Related
fck
International Journal of Latest Technology in Engineering, Management & Applied Science (IJLTEMAS)
2nd
Special Issue on Engineering and Technology | Volume VI, Issue VIS, June 2017 | ISSN 2278-2540
www.ijltemas.in Page 21
P-1 Vertical 23 27 1.8 25.4 17.8
P-1 Horizontal 32 41 3.6 37.2 37.4
P-2 Vertical 23 26 1.4 24 15.7
P-2 Horizontal 17 22 2.1 20.4 10.5
P-2 Horizontal 19 22 1.2 20 9.9
P-2 Vertical 24 29 1.8 26.4 19.4
Table-III Results of Ultrasound Pulse Velocity Test at Jimme Ki
Dhani ESR
Member
ESR Raft
Length mm
Time µ
sec
Velocity
m/sec
Value of R
considered
from RH
Position 1 (ID) 300 107.2 2800 24
Position 2 (ID) 300 106.9 2810 24
Table-IV Results of Rebound Hammer Test at Jimme Ki Dhani ESR
Member ESR
Super Structure
Minim
um
Reboun
d No.
Maxim
um
Reboun
d No.
Standar
d
Deviati
on
Averag
e
Reboun
d No.
Related
fck
TB-3/1 (C1-C2) 34 40 2.4 37.2 37.4
TB-3/1 (C2-C3) 36 40 1.5 38.4 39.5
C-2/3 36 43 2.6 39.2 41
C-3/3 35 41 2.3 37.2 37.4
C-4/3 32 48 5.9 38.2 39.2
C-4/3 40 47 3.9 42.6 47.4
TB-3/2 (C3-C4) 44 51 2.9 48.2 58.4
TB-3/2 (C3-C4) 43 52 4.0 47.4 56.8
TB-3/2 (C3-C4) 40 46 2.8 43.4 48.9
TB-3/2 (C4-C5) 35 41 2.7 38.4 39.5
C-5/2 35 43 3.2 39.6 41.7
TB-3/2 (C5-C6) 25 38 5.1 33.6 31.1
TB-3/2 (C5-C6) 29 37 3.0 32.8 29.7
C-6/2/2nd
Lift 37 48 4.7 39.8 42.1
C-6/2/2nd
Lift 33 37 1.7 34.4 32.5
C-5/2/2nd
Lift 31 39 3.5 35.4 34.2
C-4/2/2nd
Lift 35 38 1.3 36.6 36.3
C-4/2/2nd
Lift 26 42 6.3 36 35.2
C-4/2/2nd
Lift 37 40 1.5 38.4 39.5
TB-3/1 (C6-C1) 27 44 6.5 38.2 39.2
TB-3/1 (C6-C1) 34 40 2.4 37.2 37.4
C-1/1/1st
Lift 33 39 2.3 35.0 37.5
TB-3/1 (C1-C2) 35 43 3.1 37.6 38.1
C-3/1/2nd
Lift 35 45 3.9 41.8 45.8
C-3/1/2nd
Lift 40 43 1.3 41.2 44.7
C-4/1/3rd
Lift 29 37 3.6 32.8 29.7
C-4/1/3rd
Lift 36 48 4.8 40.8 44.0
C-4/1/3rd
Lift 35 46 4.0 40.8 44.0
C-4/1/3rd
Lift 39 45 2.3 41.2 44.7
Table-V Results of Ultrasound Pulse Velocity Test at Jimme Ki
Dhani ESR
Member
Len
gth
mm
Time µ
sec
Veloc
ity
m/sec
Value of
R
consider
ed from
RH
Combined
Compress
ive
Strength σ
N/mm 2
C-4/2/2nd
Lift (D) 450 105.7 4260 35 28.1
C-4/2/2nd
Lift (ID) 300 104.7 2870 35 -
TB-3/1 (C1-C2) (D) 300 73.4 4090 37
TB-3/1 (C1-C2)
(ID)
300 87.6 3430 37
V. RESULTS BY PHOTOMETER
 At TB3/2 C4-C5 (Near to Junction Upper Face) bar
diameter is traced as 24.9.
 At TB3/2 C4-C5 (Near to Mid Span Bottom Side
Face) bar diameter is traced as 28.5 which indicates
overlap of 20mm & 8mm bars.
 At TB3/2 C4-C5 (Near to Mid Span Bottom Side
Face) bar diameter is traced as 41.5 which indicates
overlap of 20mm & its development bars.
 At C5/3-4 (Near to Mid Hieght) bar diameter is
traced as 18.2.
 At C5/3-4 (Near to Mid Hieght) bar diameter is
traced as 9.1mm.
VI. TESTS AT LABORATORY
Few sample casted at actual time of construction provided
by your team tested at laboratory to establish the correlation
between NDT results and actual destructive test. Rebound
Hammer, UPV and Compressive strength test carried out at
our laboratory and test results are as follows.
Table-VI Results of Rebound Hammer Test at Laboratory
Laboratory
Specimen
Minimu
m
Reboun
d No.
Maxim
um
Reboun
d No.
Standar
d
Deviati
on
Averag
e
Reboun
d No.
Related
fck
Cube 1/ Raft /
14.07.16
28 37 4.1 31.8 28.0
Cube 2/ Raft /
14.07.16
25 36 4.0 31.2 27.0
International Journal of Latest Technology in Engineering, Management & Applied Science (IJLTEMAS)
2nd
Special Issue on Engineering and Technology | Volume VI, Issue VIS, June 2017 | ISSN 2278-2540
www.ijltemas.in Page 22
Cube 3/ Raft /
14.07.16
25 31 2.4 28.0 21.9
Cube 3/ Raft /
14.07.16
25 35 4.6 28.6 22.8
Cube1/Column/1
3.08.16
27 34 2.5 30.6 26.1
Cube2/Column/1
3.08.16
29 34 2.0 31.0 26.7
Cube3/Column/1
3.08.16
25 37 5.2 30.8 26.4
Cube3/Column/1
3.08.16
24 32 3.4 30.0 25.1
Cube1/Beam/
08.08.16
30 36 2.6 32.6 29.4
Cube2/Beam/
08.08.16
27 32 2.3 30.0 25.1
Cube3/Beam/
08.08.16
28 37 3.4 32.4 29.0
Table-VII Results of Ultrasound Pulse Velocity Test at Laboratory
Laboratory
Specimen
Length
mm
Time µ
sec
Velocit
y m/sec
Value of
R
consider
ed from
RH
Combined
Compress
ive
Strength σ
N/mm 2
Cube 1 / Raft /
14.07.16 (D)
150 35.6 4210 30 25.1
Cube 2 / Raft /
14.07.16 (D)
150 35.3 4250 30 26.2
Cube 3 / Raft /
14.07.16 (D)
150 37.2 4030 30 19.8
Cube
1/Column /
13.08.16 (D)
150 38.4 3910 30 17.3
Cube
2/Column /
13.08.16 (D)
150 35.6 4210 30 25.1
Cube
3/Column /
13.08.16 (D)
150 35.4 4240 30 25.9
Cube 1 / Beam
/ 08.08.16
150 34.1 4400 31 30.8
Cube 2 / Beam
/ 08.08.16 (D)
150 35.7 4200 31 25.1
Cube 3 / Beam
/ 08.08.16 (D)
150 34.9 4300 31 27.9
Table-VIII Results of Rebound Hammer Test at Laboratory
Laboratory Specimen Cube Compressive
Test Result
Cube 1/ Raft / 14.07.16 30.22
Cube 2/ Raft / 14.07.16 33.55
Cube 3/ Raft / 14.07.16 27.55
Cube1/Column/13.08.16 30.86
Cube2/Column/13.08.16 29.55
Cube3/Column/13.08.16 32.02
Cube1/Beam/ 08.08.16 31.42
Cube2/Beam/ 08.08.16 28.68
Cube3/Beam/ 08.08.16 31.18
Some Citations:-
With reference to IS 456-2000, Clause 16
Acceptance Criteria and Clause 16.1 for Compressive
Strength, The Concrete shall be deemed to comply with the
strength requirements when both the following conditions are
met:-
(a) The mean strength determined from any group of four
consecutive test results complies with the appropriate limits in
column 2 of table 11
(b) Any individual test results complies with the appropriate
limits in column 3 of table 11
Clause 16.3 Quantity of Concrete Represented by
Strength Test Results
Clause 16.3 states ie the quantity represented by a
group of four consecutive test results shall include the batches
from which the first and last were taken together with all
intervening results.
Clause 16.6 Concrete is liable to be rejected if it
porous or honey combed, its placing has been interrupted
without providing a proper construction joint, the
reinforcement has been displaced beyond the tolerances
specified, or construction tolerances have been met, However,
the hardened concrete may be accepted after carrying out
suitable remedial measures to the satisfaction of the Engineers
In charge.
Clause 17.3 Testing Clause 17.4.3, Concrete in the
member represented by a core test shall be considered
acceptable if the average equivalent cube strength of cores is
equal to at least 85 percent of the cube strength of the grade of
concrete specified for the corresponding age and no individual
core has a strength less than 75 percent.
VII. THE PURPOSE OF THE INSPECTION
The purpose of the inspection is to provide advice to a
prospective or other interested party regarding the condition
of the structure at the time of the inspection. The advice is
limited to the reporting of the condition of the structure in
accord with IS 456. This report is limited to (unless otherwise
noted) the main structure on the site. This report is not
intended as a certificate of compliance of the structure within
the requirements of any act, regulation, and ordinance or by
law, or, as a warranty or an insurance policy against problems
developing with the building in the future.
Assumptions & Limitations-
International Journal of Latest Technology in Engineering, Management & Applied Science (IJLTEMAS)
2nd
Special Issue on Engineering and Technology | Volume VI, Issue VIS, June 2017 | ISSN 2278-2540
www.ijltemas.in Page 23
 Any person who relies upon the contents of this
report does so acknowledging that the following
clauses, which define the Scope and Limitations of
the inspection, form an integral part of the report.
 This NDT inspection is limited to those areas and
sections of the structure fully accessible and visible
to the Inspector at the time and on the date of
Inspection.
 The inspection didn’t include breaking apart,
dismantling, removing or moving objects including,
but not limited to, foliage, moldings, sparking
membrane, appliances or personal possessions.
 Provisions of IS 13311 part I and part II 1992 applies
in addition to provisions of IS 516 latest version
applies. So far as mix design is concerns provisions
of IS 10262 and SP 23 latest versions shall comply.
Needless to say that Provisions of IS 456-2000 also
applies.
 The visiting team DID NOT dig, gouge, force or
perform any invasive procedures.
 Nothing contained in the Report implies that any
inaccessible or partly inaccessible area(s) or
section(s) of the structure being inspected by the
Inspector on the date of the inspection were free
from defects latent or otherwise.
 No responsibility can be accepted for defects which
are latent or otherwise not reasonably detected on
limited requirement.
 Durability of exposed finishes.
 Photographic evidence taken on the day of inspection
is given as an example of the NDTs found to the
structure for reporting purposes only. These photos
within the report are to assist, and May not show all
the tests and/or the areas noted on the day of
inspection.
 Any person who relies upon the contents of this
Report does so acknowledging that the above
clauses, definitions and disclaimers that follow
define the Scope and Limitations of the inspection
and form an integral part of the report.
 Disclaimer of Liability: No liability shall be accepted
on account of failure of the Report to notify any
problems in any area(s) or section(s) of the subject
structure physically inaccessible for testing purpose,
or to which access for testing is denied by or to the
visiting team (including but not limited to any area(s)
or section(s) so specified by the Report.
 Disclaimer of Liability To Third Parties: This report
is made solely for the use and benefit of the Client
named on the front of this report. No liability or
responsibility whatsoever, in contract or tort, is
accepted to any third party who may rely on the
Report wholly or in part. Any third party acting or
relying on this Report, in whole or in part does so at
their own risk.
 As requested in letter referred above of the party,
care has been taken not dig out a core however
combined method of Rebound hammer and Ultra
Sonic Pulse Velocity meter were applied.
VIII. SUGGESTIONS
It is suggested that the construction should not be
discontinued for so long time as it can hamper quality of
construction. Other agencies can further deteriorate quality of
materials used and part of the construction which has made
the progress.
IX. RECOMMENDATIONS
All process should be including testing, witnessed by either
the contractor or the agency owning the construction. The
matter may be referred to a competent authority as per norms
of NDMA considering Qualification and experience of the
expert concerned. Ultimately onus lies on the agency owning
the construction later on.
X. CONCLUSION
Unnecessary obstacles should be avoided. Looking to
provisions of table 11 of IS 456-200 the case reported falls
under individual category i.e. fck - 4 N/sq mm should be
criteria for acceptance. So far as the citation quoted and visit
at the site including other parameters, reported and generated,
it is felt that there should not be an issue so far quality of
Concrete is concerned.
REFERENCES
[1]. ACI 228.1R-95, In-Place Test Methods for Determination of
Strength of Concrete.
[2]. ACI 364.1R-94, Guide for the Evaluation of Concrete Structures
Prior to Rehabilitation.
[3]. ACI Manual, December 2007, Inspection Instruments Inc.
[4]. Gupta A.K. and Sharma Ravi Kumar, “Short term course on
Non-destructive Assessment of Structure (NONDAS)”.
Department of Structural Engineering, M.B.M. Engineering
College, Jodhpur
[5]. Gambhir, M.L. (2000), “Concrete Technology”, Tata McGraw
Hill, N. Delhi.
[6]. IS: 10262:2000, Recommended guide line for concrete mix
design", Bureau of Indian Standards, New Delhi.
[7]. IS: 13311 – (Part 1) 1992, "Non Destructive Testing of Concrete –
Methods of Test – Ultrasonic Pulse Velocity", Bureau of Indian
Standards, New Delhi.
[8]. IS: 13311-(Part 2) 1992, "Non Destructive Testing of Concrete –
Methods of Test – Rebound Hammer", Bureau of Indian
Standards, New Delhi.
[9]. IS: 456-2000, "Code of Practice for Plain and Reinforced
Concrete", Bureau of Indian Standards, New Delhi.
[10]. IS: 516-1959, "Method of Test for Strength of Concrete", Bureau
of Indian Standards, New Delhi.
International Journal of Latest Technology in Engineering, Management & Applied Science (IJLTEMAS)
2nd
Special Issue on Engineering and Technology | Volume VI, Issue VIS, June 2017 | ISSN 2278-2540
www.ijltemas.in Page 24
[11]. Kaushik, S.K. (1996), “Non-destructive testing in Civil
Engineering”, Dec., Indo-US workshop on N.D.T., I.C.I., U.P.,
Roorkee.
[12]. Malhotra V.M. and NaikTarun, "The Ultrasonic Pulse Velocity
Method". CRC Handbook on NDT of concrete, CRC Press
[13]. Malhotra, V., "Testing Hardened Concrete: Nondestructive
Methods," ACI Monograph No. 9, 1976, 188 pages.
[14]. Neville A.M. and Brooks J.J., "Concrete Technology", Third
edition reprint, Pearson Education P. Ltd., Indian branch, New
Delhi.
[15]. Neville A.M., "Properties of Concrete", Fourth Edition, Pearson
Education, 2008.
[16]. Smart NDT System, Investigation of a Fire Damaged Structure: A
Report (1999), 203, Signature- 1, Productivity Road, Vadodara.
[17]. Smart NDT System, NDT of Earth quake Affected Structure,@
Cement Plant , Kutch. : A Report, June 2001, 203, Signature- 1,
Productivity Road, Vadodara.
[18]. V.M. Malhotra, Testing Hardened Concrete: Nondestructive
Methods, Published jointly by The Lowa State University Press,
Lowa and ACI, Michigan, 1976.

More Related Content

What's hot

Comparative Study on Flexural Strength of M-40 Grade with Lapping of Bars
Comparative Study on Flexural Strength of M-40 Grade with Lapping of BarsComparative Study on Flexural Strength of M-40 Grade with Lapping of Bars
Comparative Study on Flexural Strength of M-40 Grade with Lapping of BarsIRJET Journal
 
Experimental study on Torsion behavior of Flange beam with GFRP
Experimental study on Torsion behavior of Flange beam with GFRPExperimental study on Torsion behavior of Flange beam with GFRP
Experimental study on Torsion behavior of Flange beam with GFRPIJSRD
 
Comparative Study of Concrete Prisms Confined with G-FRP Wrapping Under Compr...
Comparative Study of Concrete Prisms Confined with G-FRP Wrapping Under Compr...Comparative Study of Concrete Prisms Confined with G-FRP Wrapping Under Compr...
Comparative Study of Concrete Prisms Confined with G-FRP Wrapping Under Compr...IRJET Journal
 
Research on the influence of sagging and continuous undercut on the capacity
Research on the influence of sagging and continuous undercut on the capacityResearch on the influence of sagging and continuous undercut on the capacity
Research on the influence of sagging and continuous undercut on the capacityIAEME Publication
 
IRJET- Experimental Investigation on Partial Replacement of M-Sand by Steel Slag
IRJET- Experimental Investigation on Partial Replacement of M-Sand by Steel SlagIRJET- Experimental Investigation on Partial Replacement of M-Sand by Steel Slag
IRJET- Experimental Investigation on Partial Replacement of M-Sand by Steel SlagIRJET Journal
 
IRJET- Comparative Study on the Characteristic Behaviour of CFDSST, CFDSSAT &...
IRJET- Comparative Study on the Characteristic Behaviour of CFDSST, CFDSSAT &...IRJET- Comparative Study on the Characteristic Behaviour of CFDSST, CFDSSAT &...
IRJET- Comparative Study on the Characteristic Behaviour of CFDSST, CFDSSAT &...IRJET Journal
 
Finite Element Analysis of the Composite Patch Repairs of the Plates
Finite Element Analysis of the Composite Patch Repairs of the PlatesFinite Element Analysis of the Composite Patch Repairs of the Plates
Finite Element Analysis of the Composite Patch Repairs of the PlatesIJERA Editor
 
Soundness & feasibility of additional floor on existing rc building with ...
Soundness & feasibility of additional floor on existing rc building with ...Soundness & feasibility of additional floor on existing rc building with ...
Soundness & feasibility of additional floor on existing rc building with ...eSAT Journals
 
Behavior of r.c.c. beam with rectangular opening
Behavior of r.c.c. beam with rectangular openingBehavior of r.c.c. beam with rectangular opening
Behavior of r.c.c. beam with rectangular openingeSAT Publishing House
 
Toolwear surface-qual
Toolwear surface-qualToolwear surface-qual
Toolwear surface-qualDave Davidson
 
Structural steel division, Jindal Steel
Structural steel division, Jindal SteelStructural steel division, Jindal Steel
Structural steel division, Jindal Steelsamidhathakur
 
An investigation of adhering layer formation during tool wear progression in ...
An investigation of adhering layer formation during tool wear progression in ...An investigation of adhering layer formation during tool wear progression in ...
An investigation of adhering layer formation during tool wear progression in ...Lepuufu
 
Dr.R.Narayanasamy - Formability of Automobile grade steels
Dr.R.Narayanasamy - Formability of Automobile grade steelsDr.R.Narayanasamy - Formability of Automobile grade steels
Dr.R.Narayanasamy - Formability of Automobile grade steelsDr.Ramaswamy Narayanasamy
 
SLIDING WEAR BEHAVIOUR OF ALUMINUM ALLOY (LM-13) REINFORCED WITH NANO-ZrO2 MA...
SLIDING WEAR BEHAVIOUR OF ALUMINUM ALLOY (LM-13) REINFORCED WITH NANO-ZrO2 MA...SLIDING WEAR BEHAVIOUR OF ALUMINUM ALLOY (LM-13) REINFORCED WITH NANO-ZrO2 MA...
SLIDING WEAR BEHAVIOUR OF ALUMINUM ALLOY (LM-13) REINFORCED WITH NANO-ZrO2 MA...ijiert bestjournal
 
SHEAR PERFORMANCE OF FIBER REINFORCED SELF COMPACTING CONCRETE DEEP BEAMS
SHEAR PERFORMANCE OF FIBER REINFORCED SELF COMPACTING CONCRETE DEEP BEAMSSHEAR PERFORMANCE OF FIBER REINFORCED SELF COMPACTING CONCRETE DEEP BEAMS
SHEAR PERFORMANCE OF FIBER REINFORCED SELF COMPACTING CONCRETE DEEP BEAMSIAEME Publication
 
Canister testing chamber design & analysis using fem
Canister testing chamber design & analysis using femCanister testing chamber design & analysis using fem
Canister testing chamber design & analysis using femIAEME Publication
 

What's hot (19)

Comparative Study on Flexural Strength of M-40 Grade with Lapping of Bars
Comparative Study on Flexural Strength of M-40 Grade with Lapping of BarsComparative Study on Flexural Strength of M-40 Grade with Lapping of Bars
Comparative Study on Flexural Strength of M-40 Grade with Lapping of Bars
 
Experimental study on Torsion behavior of Flange beam with GFRP
Experimental study on Torsion behavior of Flange beam with GFRPExperimental study on Torsion behavior of Flange beam with GFRP
Experimental study on Torsion behavior of Flange beam with GFRP
 
Comparative Study of Concrete Prisms Confined with G-FRP Wrapping Under Compr...
Comparative Study of Concrete Prisms Confined with G-FRP Wrapping Under Compr...Comparative Study of Concrete Prisms Confined with G-FRP Wrapping Under Compr...
Comparative Study of Concrete Prisms Confined with G-FRP Wrapping Under Compr...
 
Types of gauges
Types of gaugesTypes of gauges
Types of gauges
 
Research on the influence of sagging and continuous undercut on the capacity
Research on the influence of sagging and continuous undercut on the capacityResearch on the influence of sagging and continuous undercut on the capacity
Research on the influence of sagging and continuous undercut on the capacity
 
IRJET- Experimental Investigation on Partial Replacement of M-Sand by Steel Slag
IRJET- Experimental Investigation on Partial Replacement of M-Sand by Steel SlagIRJET- Experimental Investigation on Partial Replacement of M-Sand by Steel Slag
IRJET- Experimental Investigation on Partial Replacement of M-Sand by Steel Slag
 
IRJET- Comparative Study on the Characteristic Behaviour of CFDSST, CFDSSAT &...
IRJET- Comparative Study on the Characteristic Behaviour of CFDSST, CFDSSAT &...IRJET- Comparative Study on the Characteristic Behaviour of CFDSST, CFDSSAT &...
IRJET- Comparative Study on the Characteristic Behaviour of CFDSST, CFDSSAT &...
 
Finite Element Analysis of the Composite Patch Repairs of the Plates
Finite Element Analysis of the Composite Patch Repairs of the PlatesFinite Element Analysis of the Composite Patch Repairs of the Plates
Finite Element Analysis of the Composite Patch Repairs of the Plates
 
Soundness & feasibility of additional floor on existing rc building with ...
Soundness & feasibility of additional floor on existing rc building with ...Soundness & feasibility of additional floor on existing rc building with ...
Soundness & feasibility of additional floor on existing rc building with ...
 
Behavior of r.c.c. beam with rectangular opening
Behavior of r.c.c. beam with rectangular openingBehavior of r.c.c. beam with rectangular opening
Behavior of r.c.c. beam with rectangular opening
 
Toolwear surface-qual
Toolwear surface-qualToolwear surface-qual
Toolwear surface-qual
 
Structural steel division, Jindal Steel
Structural steel division, Jindal SteelStructural steel division, Jindal Steel
Structural steel division, Jindal Steel
 
An investigation of adhering layer formation during tool wear progression in ...
An investigation of adhering layer formation during tool wear progression in ...An investigation of adhering layer formation during tool wear progression in ...
An investigation of adhering layer formation during tool wear progression in ...
 
Surface topography assessment techniques based on an in-process monitoring ap...
Surface topography assessment techniques based on an in-process monitoring ap...Surface topography assessment techniques based on an in-process monitoring ap...
Surface topography assessment techniques based on an in-process monitoring ap...
 
Dr.R.Narayanasamy - Formability of Automobile grade steels
Dr.R.Narayanasamy - Formability of Automobile grade steelsDr.R.Narayanasamy - Formability of Automobile grade steels
Dr.R.Narayanasamy - Formability of Automobile grade steels
 
J43025258
J43025258J43025258
J43025258
 
SLIDING WEAR BEHAVIOUR OF ALUMINUM ALLOY (LM-13) REINFORCED WITH NANO-ZrO2 MA...
SLIDING WEAR BEHAVIOUR OF ALUMINUM ALLOY (LM-13) REINFORCED WITH NANO-ZrO2 MA...SLIDING WEAR BEHAVIOUR OF ALUMINUM ALLOY (LM-13) REINFORCED WITH NANO-ZrO2 MA...
SLIDING WEAR BEHAVIOUR OF ALUMINUM ALLOY (LM-13) REINFORCED WITH NANO-ZrO2 MA...
 
SHEAR PERFORMANCE OF FIBER REINFORCED SELF COMPACTING CONCRETE DEEP BEAMS
SHEAR PERFORMANCE OF FIBER REINFORCED SELF COMPACTING CONCRETE DEEP BEAMSSHEAR PERFORMANCE OF FIBER REINFORCED SELF COMPACTING CONCRETE DEEP BEAMS
SHEAR PERFORMANCE OF FIBER REINFORCED SELF COMPACTING CONCRETE DEEP BEAMS
 
Canister testing chamber design & analysis using fem
Canister testing chamber design & analysis using femCanister testing chamber design & analysis using fem
Canister testing chamber design & analysis using fem
 

Similar to Non Destructive Investigation of ESR for Structural Health Assessment

Experimental Study of Improvement in Confinement of Reinforced Concrete Column
Experimental Study of Improvement in Confinement of Reinforced Concrete ColumnExperimental Study of Improvement in Confinement of Reinforced Concrete Column
Experimental Study of Improvement in Confinement of Reinforced Concrete ColumnIRJET Journal
 
Shear Strengthening of RC Beams using Embedded Through Section (ETS) Technique
Shear Strengthening of RC Beams using Embedded Through Section (ETS) TechniqueShear Strengthening of RC Beams using Embedded Through Section (ETS) Technique
Shear Strengthening of RC Beams using Embedded Through Section (ETS) TechniqueIRJET Journal
 
IRJET- Experimental Evaluation of Strength of Damaged RCC Beam Repaired us...
IRJET- 	  Experimental Evaluation of Strength of Damaged RCC Beam Repaired us...IRJET- 	  Experimental Evaluation of Strength of Damaged RCC Beam Repaired us...
IRJET- Experimental Evaluation of Strength of Damaged RCC Beam Repaired us...IRJET Journal
 
IRJET- Construction of Hollow Reinforced Concrete Block
IRJET- Construction of Hollow Reinforced Concrete BlockIRJET- Construction of Hollow Reinforced Concrete Block
IRJET- Construction of Hollow Reinforced Concrete BlockIRJET Journal
 
IRJET-Experimental Study on the Effect of Basalt Fiber Reinforced Concrete in...
IRJET-Experimental Study on the Effect of Basalt Fiber Reinforced Concrete in...IRJET-Experimental Study on the Effect of Basalt Fiber Reinforced Concrete in...
IRJET-Experimental Study on the Effect of Basalt Fiber Reinforced Concrete in...IRJET Journal
 
Structural Health Monitoring of Aluminium Stiffened Sandwich Plate using Ultr...
Structural Health Monitoring of Aluminium Stiffened Sandwich Plate using Ultr...Structural Health Monitoring of Aluminium Stiffened Sandwich Plate using Ultr...
Structural Health Monitoring of Aluminium Stiffened Sandwich Plate using Ultr...IRJET Journal
 
IRJET- Experimental Study of Structural Behaviour of Double Skin Hollow –...
IRJET-  	  Experimental Study of Structural Behaviour of Double Skin Hollow –...IRJET-  	  Experimental Study of Structural Behaviour of Double Skin Hollow –...
IRJET- Experimental Study of Structural Behaviour of Double Skin Hollow –...IRJET Journal
 
Experimental Performance, Mathematical Modelling and Development of Stress Bl...
Experimental Performance, Mathematical Modelling and Development of Stress Bl...Experimental Performance, Mathematical Modelling and Development of Stress Bl...
Experimental Performance, Mathematical Modelling and Development of Stress Bl...IRJET Journal
 
IRJET- Experimental Study on Partial Replacement of Coarse Aggregate by C...
IRJET-  	  Experimental Study on Partial Replacement of Coarse Aggregate by C...IRJET-  	  Experimental Study on Partial Replacement of Coarse Aggregate by C...
IRJET- Experimental Study on Partial Replacement of Coarse Aggregate by C...IRJET Journal
 
INVESTIGATION REPORT ON PRELIMINARY TESTS ON FAILURE OF STRUCTURE AND MONITORING
INVESTIGATION REPORT ON PRELIMINARY TESTS ON FAILURE OF STRUCTURE AND MONITORINGINVESTIGATION REPORT ON PRELIMINARY TESTS ON FAILURE OF STRUCTURE AND MONITORING
INVESTIGATION REPORT ON PRELIMINARY TESTS ON FAILURE OF STRUCTURE AND MONITORINGIRJET Journal
 
Behaviour of reinforced concrete beams with 50 percentage fly ash
Behaviour of reinforced concrete beams with 50 percentage fly ashBehaviour of reinforced concrete beams with 50 percentage fly ash
Behaviour of reinforced concrete beams with 50 percentage fly ashIAEME Publication
 
Experimental Investigation on Effect of Curtailed reinforcement in R.C beams
Experimental Investigation on Effect of Curtailed reinforcement in R.C beamsExperimental Investigation on Effect of Curtailed reinforcement in R.C beams
Experimental Investigation on Effect of Curtailed reinforcement in R.C beamsIRJET Journal
 
IRJET- Enhancing the Performance of Concrete by using Nano Silica
IRJET-  	  Enhancing the Performance of Concrete by using Nano SilicaIRJET-  	  Enhancing the Performance of Concrete by using Nano Silica
IRJET- Enhancing the Performance of Concrete by using Nano SilicaIRJET Journal
 
The Study of Flexural and Ultimate Behavior of Ferrocement Lightweight Beam b...
The Study of Flexural and Ultimate Behavior of Ferrocement Lightweight Beam b...The Study of Flexural and Ultimate Behavior of Ferrocement Lightweight Beam b...
The Study of Flexural and Ultimate Behavior of Ferrocement Lightweight Beam b...IRJET Journal
 
IRJET- Effect of Steel Ratio and Mineral Admixtures on Short Columns
IRJET- Effect of Steel Ratio and Mineral Admixtures on Short ColumnsIRJET- Effect of Steel Ratio and Mineral Admixtures on Short Columns
IRJET- Effect of Steel Ratio and Mineral Admixtures on Short ColumnsIRJET Journal
 
Analysis of Concrete Filled Double Skin Steel Tube (CFDST) column with FRP wr...
Analysis of Concrete Filled Double Skin Steel Tube (CFDST) column with FRP wr...Analysis of Concrete Filled Double Skin Steel Tube (CFDST) column with FRP wr...
Analysis of Concrete Filled Double Skin Steel Tube (CFDST) column with FRP wr...IRJET Journal
 
IRJET- Experimental Investigation on Mechanical Splices in Fiber Reinforc...
IRJET-  	  Experimental Investigation on Mechanical Splices in Fiber Reinforc...IRJET-  	  Experimental Investigation on Mechanical Splices in Fiber Reinforc...
IRJET- Experimental Investigation on Mechanical Splices in Fiber Reinforc...IRJET Journal
 
IRJET- Strengthening of New Building
IRJET- Strengthening of New BuildingIRJET- Strengthening of New Building
IRJET- Strengthening of New BuildingIRJET Journal
 

Similar to Non Destructive Investigation of ESR for Structural Health Assessment (20)

Experimental Study of Improvement in Confinement of Reinforced Concrete Column
Experimental Study of Improvement in Confinement of Reinforced Concrete ColumnExperimental Study of Improvement in Confinement of Reinforced Concrete Column
Experimental Study of Improvement in Confinement of Reinforced Concrete Column
 
Shear Strengthening of RC Beams using Embedded Through Section (ETS) Technique
Shear Strengthening of RC Beams using Embedded Through Section (ETS) TechniqueShear Strengthening of RC Beams using Embedded Through Section (ETS) Technique
Shear Strengthening of RC Beams using Embedded Through Section (ETS) Technique
 
20320140502006 2
20320140502006 220320140502006 2
20320140502006 2
 
20320140502006 2
20320140502006 220320140502006 2
20320140502006 2
 
IRJET- Experimental Evaluation of Strength of Damaged RCC Beam Repaired us...
IRJET- 	  Experimental Evaluation of Strength of Damaged RCC Beam Repaired us...IRJET- 	  Experimental Evaluation of Strength of Damaged RCC Beam Repaired us...
IRJET- Experimental Evaluation of Strength of Damaged RCC Beam Repaired us...
 
IRJET- Construction of Hollow Reinforced Concrete Block
IRJET- Construction of Hollow Reinforced Concrete BlockIRJET- Construction of Hollow Reinforced Concrete Block
IRJET- Construction of Hollow Reinforced Concrete Block
 
IRJET-Experimental Study on the Effect of Basalt Fiber Reinforced Concrete in...
IRJET-Experimental Study on the Effect of Basalt Fiber Reinforced Concrete in...IRJET-Experimental Study on the Effect of Basalt Fiber Reinforced Concrete in...
IRJET-Experimental Study on the Effect of Basalt Fiber Reinforced Concrete in...
 
Structural Health Monitoring of Aluminium Stiffened Sandwich Plate using Ultr...
Structural Health Monitoring of Aluminium Stiffened Sandwich Plate using Ultr...Structural Health Monitoring of Aluminium Stiffened Sandwich Plate using Ultr...
Structural Health Monitoring of Aluminium Stiffened Sandwich Plate using Ultr...
 
IRJET- Experimental Study of Structural Behaviour of Double Skin Hollow –...
IRJET-  	  Experimental Study of Structural Behaviour of Double Skin Hollow –...IRJET-  	  Experimental Study of Structural Behaviour of Double Skin Hollow –...
IRJET- Experimental Study of Structural Behaviour of Double Skin Hollow –...
 
Experimental Performance, Mathematical Modelling and Development of Stress Bl...
Experimental Performance, Mathematical Modelling and Development of Stress Bl...Experimental Performance, Mathematical Modelling and Development of Stress Bl...
Experimental Performance, Mathematical Modelling and Development of Stress Bl...
 
IRJET- Experimental Study on Partial Replacement of Coarse Aggregate by C...
IRJET-  	  Experimental Study on Partial Replacement of Coarse Aggregate by C...IRJET-  	  Experimental Study on Partial Replacement of Coarse Aggregate by C...
IRJET- Experimental Study on Partial Replacement of Coarse Aggregate by C...
 
INVESTIGATION REPORT ON PRELIMINARY TESTS ON FAILURE OF STRUCTURE AND MONITORING
INVESTIGATION REPORT ON PRELIMINARY TESTS ON FAILURE OF STRUCTURE AND MONITORINGINVESTIGATION REPORT ON PRELIMINARY TESTS ON FAILURE OF STRUCTURE AND MONITORING
INVESTIGATION REPORT ON PRELIMINARY TESTS ON FAILURE OF STRUCTURE AND MONITORING
 
Behaviour of reinforced concrete beams with 50 percentage fly ash
Behaviour of reinforced concrete beams with 50 percentage fly ashBehaviour of reinforced concrete beams with 50 percentage fly ash
Behaviour of reinforced concrete beams with 50 percentage fly ash
 
Experimental Investigation on Effect of Curtailed reinforcement in R.C beams
Experimental Investigation on Effect of Curtailed reinforcement in R.C beamsExperimental Investigation on Effect of Curtailed reinforcement in R.C beams
Experimental Investigation on Effect of Curtailed reinforcement in R.C beams
 
IRJET- Enhancing the Performance of Concrete by using Nano Silica
IRJET-  	  Enhancing the Performance of Concrete by using Nano SilicaIRJET-  	  Enhancing the Performance of Concrete by using Nano Silica
IRJET- Enhancing the Performance of Concrete by using Nano Silica
 
The Study of Flexural and Ultimate Behavior of Ferrocement Lightweight Beam b...
The Study of Flexural and Ultimate Behavior of Ferrocement Lightweight Beam b...The Study of Flexural and Ultimate Behavior of Ferrocement Lightweight Beam b...
The Study of Flexural and Ultimate Behavior of Ferrocement Lightweight Beam b...
 
IRJET- Effect of Steel Ratio and Mineral Admixtures on Short Columns
IRJET- Effect of Steel Ratio and Mineral Admixtures on Short ColumnsIRJET- Effect of Steel Ratio and Mineral Admixtures on Short Columns
IRJET- Effect of Steel Ratio and Mineral Admixtures on Short Columns
 
Analysis of Concrete Filled Double Skin Steel Tube (CFDST) column with FRP wr...
Analysis of Concrete Filled Double Skin Steel Tube (CFDST) column with FRP wr...Analysis of Concrete Filled Double Skin Steel Tube (CFDST) column with FRP wr...
Analysis of Concrete Filled Double Skin Steel Tube (CFDST) column with FRP wr...
 
IRJET- Experimental Investigation on Mechanical Splices in Fiber Reinforc...
IRJET-  	  Experimental Investigation on Mechanical Splices in Fiber Reinforc...IRJET-  	  Experimental Investigation on Mechanical Splices in Fiber Reinforc...
IRJET- Experimental Investigation on Mechanical Splices in Fiber Reinforc...
 
IRJET- Strengthening of New Building
IRJET- Strengthening of New BuildingIRJET- Strengthening of New Building
IRJET- Strengthening of New Building
 

More from IJLT EMAS

Lithological Investigation at Tombia and Opolo Using Vertical Electrical Soun...
Lithological Investigation at Tombia and Opolo Using Vertical Electrical Soun...Lithological Investigation at Tombia and Opolo Using Vertical Electrical Soun...
Lithological Investigation at Tombia and Opolo Using Vertical Electrical Soun...IJLT EMAS
 
Public Health Implications of Locally Femented Milk (Nono) and Antibiotic Sus...
Public Health Implications of Locally Femented Milk (Nono) and Antibiotic Sus...Public Health Implications of Locally Femented Milk (Nono) and Antibiotic Sus...
Public Health Implications of Locally Femented Milk (Nono) and Antibiotic Sus...IJLT EMAS
 
Bioremediation Potentials of Hydrocarbonoclastic Bacteria Indigenous in the O...
Bioremediation Potentials of Hydrocarbonoclastic Bacteria Indigenous in the O...Bioremediation Potentials of Hydrocarbonoclastic Bacteria Indigenous in the O...
Bioremediation Potentials of Hydrocarbonoclastic Bacteria Indigenous in the O...IJLT EMAS
 
Comparison of Concurrent Mobile OS Characteristics
Comparison of Concurrent Mobile OS CharacteristicsComparison of Concurrent Mobile OS Characteristics
Comparison of Concurrent Mobile OS CharacteristicsIJLT EMAS
 
Design of Complex Adders and Parity Generators Using Reversible Gates
Design of Complex Adders and Parity Generators Using Reversible GatesDesign of Complex Adders and Parity Generators Using Reversible Gates
Design of Complex Adders and Parity Generators Using Reversible GatesIJLT EMAS
 
Design of Multiplexers, Decoder and a Full Subtractor using Reversible Gates
Design of Multiplexers, Decoder and a Full Subtractor using Reversible GatesDesign of Multiplexers, Decoder and a Full Subtractor using Reversible Gates
Design of Multiplexers, Decoder and a Full Subtractor using Reversible GatesIJLT EMAS
 
Multistage Classification of Alzheimer’s Disease
Multistage Classification of Alzheimer’s DiseaseMultistage Classification of Alzheimer’s Disease
Multistage Classification of Alzheimer’s DiseaseIJLT EMAS
 
Design and Analysis of Disc Brake for Low Brake Squeal
Design and Analysis of Disc Brake for Low Brake SquealDesign and Analysis of Disc Brake for Low Brake Squeal
Design and Analysis of Disc Brake for Low Brake SquealIJLT EMAS
 
Tomato Processing Industry Management
Tomato Processing Industry ManagementTomato Processing Industry Management
Tomato Processing Industry ManagementIJLT EMAS
 
Management of Propylene Recovery Unit
Management of Propylene Recovery UnitManagement of Propylene Recovery Unit
Management of Propylene Recovery UnitIJLT EMAS
 
Online Grocery Market
Online Grocery MarketOnline Grocery Market
Online Grocery MarketIJLT EMAS
 
Management of Home Textiles Export
Management of Home Textiles ExportManagement of Home Textiles Export
Management of Home Textiles ExportIJLT EMAS
 
Coffee Shop Management
Coffee Shop ManagementCoffee Shop Management
Coffee Shop ManagementIJLT EMAS
 
Management of a Paper Manufacturing Industry
Management of a Paper Manufacturing IndustryManagement of a Paper Manufacturing Industry
Management of a Paper Manufacturing IndustryIJLT EMAS
 
Application of Big Data Systems to Airline Management
Application of Big Data Systems to Airline ManagementApplication of Big Data Systems to Airline Management
Application of Big Data Systems to Airline ManagementIJLT EMAS
 
Impact of Organisational behaviour and HR Practices on Employee Retention in ...
Impact of Organisational behaviour and HR Practices on Employee Retention in ...Impact of Organisational behaviour and HR Practices on Employee Retention in ...
Impact of Organisational behaviour and HR Practices on Employee Retention in ...IJLT EMAS
 
Sustainable Methods used to reduce the Energy Consumption by Various Faciliti...
Sustainable Methods used to reduce the Energy Consumption by Various Faciliti...Sustainable Methods used to reduce the Energy Consumption by Various Faciliti...
Sustainable Methods used to reduce the Energy Consumption by Various Faciliti...IJLT EMAS
 
Sweet-shop Management
Sweet-shop ManagementSweet-shop Management
Sweet-shop ManagementIJLT EMAS
 
Hassle Free Travel
Hassle Free TravelHassle Free Travel
Hassle Free TravelIJLT EMAS
 
Aviation Meteorology
Aviation MeteorologyAviation Meteorology
Aviation MeteorologyIJLT EMAS
 

More from IJLT EMAS (20)

Lithological Investigation at Tombia and Opolo Using Vertical Electrical Soun...
Lithological Investigation at Tombia and Opolo Using Vertical Electrical Soun...Lithological Investigation at Tombia and Opolo Using Vertical Electrical Soun...
Lithological Investigation at Tombia and Opolo Using Vertical Electrical Soun...
 
Public Health Implications of Locally Femented Milk (Nono) and Antibiotic Sus...
Public Health Implications of Locally Femented Milk (Nono) and Antibiotic Sus...Public Health Implications of Locally Femented Milk (Nono) and Antibiotic Sus...
Public Health Implications of Locally Femented Milk (Nono) and Antibiotic Sus...
 
Bioremediation Potentials of Hydrocarbonoclastic Bacteria Indigenous in the O...
Bioremediation Potentials of Hydrocarbonoclastic Bacteria Indigenous in the O...Bioremediation Potentials of Hydrocarbonoclastic Bacteria Indigenous in the O...
Bioremediation Potentials of Hydrocarbonoclastic Bacteria Indigenous in the O...
 
Comparison of Concurrent Mobile OS Characteristics
Comparison of Concurrent Mobile OS CharacteristicsComparison of Concurrent Mobile OS Characteristics
Comparison of Concurrent Mobile OS Characteristics
 
Design of Complex Adders and Parity Generators Using Reversible Gates
Design of Complex Adders and Parity Generators Using Reversible GatesDesign of Complex Adders and Parity Generators Using Reversible Gates
Design of Complex Adders and Parity Generators Using Reversible Gates
 
Design of Multiplexers, Decoder and a Full Subtractor using Reversible Gates
Design of Multiplexers, Decoder and a Full Subtractor using Reversible GatesDesign of Multiplexers, Decoder and a Full Subtractor using Reversible Gates
Design of Multiplexers, Decoder and a Full Subtractor using Reversible Gates
 
Multistage Classification of Alzheimer’s Disease
Multistage Classification of Alzheimer’s DiseaseMultistage Classification of Alzheimer’s Disease
Multistage Classification of Alzheimer’s Disease
 
Design and Analysis of Disc Brake for Low Brake Squeal
Design and Analysis of Disc Brake for Low Brake SquealDesign and Analysis of Disc Brake for Low Brake Squeal
Design and Analysis of Disc Brake for Low Brake Squeal
 
Tomato Processing Industry Management
Tomato Processing Industry ManagementTomato Processing Industry Management
Tomato Processing Industry Management
 
Management of Propylene Recovery Unit
Management of Propylene Recovery UnitManagement of Propylene Recovery Unit
Management of Propylene Recovery Unit
 
Online Grocery Market
Online Grocery MarketOnline Grocery Market
Online Grocery Market
 
Management of Home Textiles Export
Management of Home Textiles ExportManagement of Home Textiles Export
Management of Home Textiles Export
 
Coffee Shop Management
Coffee Shop ManagementCoffee Shop Management
Coffee Shop Management
 
Management of a Paper Manufacturing Industry
Management of a Paper Manufacturing IndustryManagement of a Paper Manufacturing Industry
Management of a Paper Manufacturing Industry
 
Application of Big Data Systems to Airline Management
Application of Big Data Systems to Airline ManagementApplication of Big Data Systems to Airline Management
Application of Big Data Systems to Airline Management
 
Impact of Organisational behaviour and HR Practices on Employee Retention in ...
Impact of Organisational behaviour and HR Practices on Employee Retention in ...Impact of Organisational behaviour and HR Practices on Employee Retention in ...
Impact of Organisational behaviour and HR Practices on Employee Retention in ...
 
Sustainable Methods used to reduce the Energy Consumption by Various Faciliti...
Sustainable Methods used to reduce the Energy Consumption by Various Faciliti...Sustainable Methods used to reduce the Energy Consumption by Various Faciliti...
Sustainable Methods used to reduce the Energy Consumption by Various Faciliti...
 
Sweet-shop Management
Sweet-shop ManagementSweet-shop Management
Sweet-shop Management
 
Hassle Free Travel
Hassle Free TravelHassle Free Travel
Hassle Free Travel
 
Aviation Meteorology
Aviation MeteorologyAviation Meteorology
Aviation Meteorology
 

Recently uploaded

ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 

Recently uploaded (20)

young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 

Non Destructive Investigation of ESR for Structural Health Assessment

  • 1. International Journal of Latest Technology in Engineering, Management & Applied Science (IJLTEMAS) 2nd Special Issue on Engineering and Technology | Volume VI, Issue VIS, June 2017 | ISSN 2278-2540 www.ijltemas.in Page 19 Non Destructive Investigation of ESR for Structural Health Assessment Mahipal Burdak, A K Gupta, S S Sankhla Department of Structural Engineering, MBM Engineering College, JNV University, Jodhpur, Rajasthan, India Abstract- Basic concept of structural health assessment of the structure or structural evaluation is mainly based on visual examination and NDT. The purpose of visual examination is to know the status of structures under applied load and other environmental. Structural health assessments can be made with NDT methods to provide important information for the structural performance of the concrete, rebar location etc. There are different NDT Techniques for assessment of concrete quality e.g. Rebound Hammer, Ultra Sonic Pulse Velocity, Impact-echo etc. Sonic- Integrity Test (SIT) & Pile Integrity Tester is based on principle of Impact-Echo. Rebound hammer can be used to find hardness of the concrete structure surface, and its strength is related using inbuilt calibration curve in the instrument. Ultra- sonic Pulse Velocity Equipment can be used to observe wave transmission through Concrete structure. The Present paper includes the study of correlation of experimental studies with laboratory results. The objective of overall investigation is to assess the existing quality, integrity and compressive strength of concrete in the raft, beam, column and superstructure element. This can be utilized for overall structural safety appraisal of the structure. Besides, in case of any inadequacy in the concrete quality being revealed, suitable remedial measures can also be suggested. Keywords- Structural Health Assessment, Rebound Hammer, Ultra Sonic Pulse Velocity, ESR/Elevated Service Reservoir I. INTRODUCTION DT of concrete is a relatively immature discipline. Because of the two main reasons, the first is the heterogeneous nature of concrete, which makes detection of defects difficult to separate from naturally occurring inclusions and the second reason is immature nature of concrete. Non-destructive test methods are used to determine hardened concrete properties and to evaluate the condition of concrete in deep foundations, super structure element, bridges, buildings, pavements, dams and other concrete constructions. Non-destructive testing is defined as testing that causes no structurally significant damage to concrete. It does not damage the intended performance of the element or member under investigation. NDT has the ability to determine the strength and durability of critical construction without damaging them and test can be carried out on site. NDT of concrete becomes necessary under many circumstances, such as a natural calamity, fire or an aggregative environment may damage the structure and residual strength may need to be ascertained. NDT methods can be used to estimate the in place strength, quality of concrete and degree of deterioration due to overloading, failure, chemical etc. or environmental attack etc. NDT methods are applied to concrete construction for four primary reasons i.e. Condition evaluation of older concrete for rehabilitation purpose, Quality control of new construction, troubleshooting of problems with new construction and Quality assurance of concrete repairs. II. PROBLEM STATEMENT The ESR1 at Jimme Ki Dhani, Ramsar, Barmer India started in about July 2016. The ESR designed, vetted and approved at competent level for staging of 20 m and capacity of 250 KL. It was planned as an Intze type tank. Bottom ring beam reinforcement cage prepared by the firm and still awaited for checking from the competent level and further construction is stopped. According to Tender stipulation stair case from first bracing and first braced with roof slab is constructed at site. It was reported that the construction of ESR up to fourth bracing was taken up in August 2016. The height of bracing (c/c) from bottom level is 4.42, 4.12, 4.12, and 4.12 & 3.57 m. Every bracing height was completed in three lifts. Reinforcement Detail and Quality of Concrete Pertaining to ESR is suspected, Copy of SBC, mix design and record of site testing were made available. During site testing some of data which could be gathered are: 6 columns in plan, Size of brace beam 450 mm x 300 mm, Height of first brace (from its bottom) 4.42 m, Dia of Column 450 mm. In the SBC test report value of SBC in t/m2 by shear failure criteria at 1.5m is given as 8.43 t/m2 , by settlement criteria 9.74 t/m2 (Peck et al) & 8.93 t/m2 (IS :8009). Recommendation of foundation depth is not available and SBC at 02 Boreholes conduced. Strata of subsoil is defined as dune sand up to 8.00m. Seismic Zone III considered for design purpose. . In the mix design report value of parameter K is taken as 1.65, stating that not more than 5 % of results are expected to fall below fck. The proportion recommended is N
  • 2. International Journal of Latest Technology in Engineering, Management & Applied Science (IJLTEMAS) 2nd Special Issue on Engineering and Technology | Volume VI, Issue VIS, June 2017 | ISSN 2278-2540 www.ijltemas.in Page 20 0.44:1.00:1.62:2.90. The report clearly mentions that no admixture has to be used. ESR at Jeeme Ki Dhani is constructed at sloped ground. No plinth protection is proposed in drawing. III. OBJECTIVE OF NONDESTRUCTIVE INVESTIGATION To assess the existing quality, integrity and allowable compressive strength of concrete in the raft, beam, column and foundation and super structure element which can be utilized for overall structural safety. Besides, in case of any inadequacy in the concrete quality being revealed, suitable remedial measures can also be suggested. IV. NDT RESULTS Non Destructive Test results are given below on the randomly selected elements accessed easily on the structure. Table-I Results of Bar Locater Test at Jimme Ki Dhani ESR Member Details of Reinforcement as Per Drawing Details of Reinforcement as Per Investigation TB 3/1 C2-C3 25 mm#03, Nos at Top & Bottom Near to Support with 2 legged strips of 8mm @150mm C/C 02 Rebars at Side face (1-Top +1-Bottom) at support with 2 legged strips @148,155,160,135 mm C/C TB 3/1 C2-C3 25 mm#03, 20 mm#02 Nos at Top & Bottom Near to Mid Span with 2 legged strips of 8mm @100mm C/C 04 Rebars at Side face (2-Top +2-Bottom) at Mid Span with 2 legged strips of @100,90,110,110 mm C/C TB 3/2 C3-C4 25 mm#03, Nos at Top & Bottom Near to Support with 2 legged strips of 8mm @150mm C/C 03 Rebars at Top face at support with 2 legged strips @160,140,146 mm C/C TB 3/2 C3-C4 25 mm#03, 20 mm#02 Nos at Top & Bottom Near to Mid Span with 2 legged strips of 8mm @100mm C/C 04 Rebars at Side face (2-Top +2-Bottom) at Mid Span with 2 legged strips of 3 bars in 320mm TB 3/2 C3-C4 25 mm#03, 20 mm#02 Nos at Top & Bottom Near to Mid Span with 2 legged strips of 8mm @100mm C/C 03 Rebars at Top face at Mid Span with 2 legged strips of 3 bars in 300mm TB 3/2 C6-C1 25 mm#03, 20 mm#02 Nos at Top & Bottom Near to Mid Span with 2 legged strips of 8mm @100mm C/C 03 Rebars at Top face at Mid Span with 2 legged strips of 3 bars in 310mm Column-1/5th 20mm# 12 Nos with strips of 8mm@190mm c/c at Mid 12 Nos with strips of 8mm@185mm, 188mm Span & 8mm@100mm c/c at Corner c/c at Mid Span Column-1/2nd 20mm# 12 Nos with strips of 8mm@190mm c/c at Mid Span & 8mm@100mm c/c at Corner 12 Nos with strips of 8mm@153mm, 137mm c/c at Mid Span Column-2/2nd 20mm# 12 Nos with strips of 8mm@190mm c/c at Mid Span & 8mm@100mm c/c at Corner 12 Nos with strips of 8mm@189mm, 186mm c/c at Mid Span Column-2/3rd 20mm# 12 Nos with strips of 8mm@190mm c/c at Mid Span & 8mm@100mm c/c at Corner 12 Nos with strips of 8mm@184mm, 191mm c/c at Mid Span Column-2/5th 20mm# 12 Nos with strips of 8mm@190mm c/c at Mid Span & 8mm@100mm c/c at Corner 12 Nos Column-3/2nd 20mm# 12 Nos with strips of 8mm@190mm c/c at Mid Span & 8mm@100mm c/c at Corner 12 Nos with strips of 8mm@190mm, 185mm c/c at Mid Span Column-3/3rd 20mm# 12 Nos with strips of 8mm@190mm c/c at Mid Span & 8mm@100mm c/c at Corner 12 Nos with strips of 8mm@190mm, 200mm, 205mm, 186mm c/c at Mid Span Column-3/5th 20mm# 12 Nos with strips of 8mm@190mm c/c at Mid Span & 8mm@100mm c/c at Corner 12 Nos Column-4/2nd 20mm# 12 Nos with strips of 8mm@190mm c/c at Mid Span & 8mm@100mm c/c at Corner 12 Nos with strips of 8mm@170mm, 195mm c/c at Mid Span & 8mm@95mm,105 mm c/c at Corner Column-4/3rd 20mm# 12 Nos with strips of 8mm@190mm c/c at Mid Span & 8mm@100mm c/c at Corner 12 Nos Column-5/2nd 20mm# 12 Nos with strips of 8mm@190mm c/c at Mid Span & 8mm@100mm c/c at Corner 12 Nos with strips of 8mm@178mm, 195mm c/c at Mid Span Column-6/2nd 20mm# 12 Nos with strips of 8mm@190mm c/c at Mid Span & 8mm@100mm c/c at Corner 12 Nos Column-6/4th 20mm# 12 Nos with strips of 8mm@190mm c/c at Mid Span & 8mm@100mm c/c at Corner 12 Nos with strips of 8mm@160mm, 170mm c/c at Mid Span Table-II Results of Rebound Hammer Test at Jimme Ki Dhani ESR Member Minim um Reboun d No. Maximu m Rebound No. Standar d Deviati on Averag e Reboun d No. Related fck
  • 3. International Journal of Latest Technology in Engineering, Management & Applied Science (IJLTEMAS) 2nd Special Issue on Engineering and Technology | Volume VI, Issue VIS, June 2017 | ISSN 2278-2540 www.ijltemas.in Page 21 P-1 Vertical 23 27 1.8 25.4 17.8 P-1 Horizontal 32 41 3.6 37.2 37.4 P-2 Vertical 23 26 1.4 24 15.7 P-2 Horizontal 17 22 2.1 20.4 10.5 P-2 Horizontal 19 22 1.2 20 9.9 P-2 Vertical 24 29 1.8 26.4 19.4 Table-III Results of Ultrasound Pulse Velocity Test at Jimme Ki Dhani ESR Member ESR Raft Length mm Time µ sec Velocity m/sec Value of R considered from RH Position 1 (ID) 300 107.2 2800 24 Position 2 (ID) 300 106.9 2810 24 Table-IV Results of Rebound Hammer Test at Jimme Ki Dhani ESR Member ESR Super Structure Minim um Reboun d No. Maxim um Reboun d No. Standar d Deviati on Averag e Reboun d No. Related fck TB-3/1 (C1-C2) 34 40 2.4 37.2 37.4 TB-3/1 (C2-C3) 36 40 1.5 38.4 39.5 C-2/3 36 43 2.6 39.2 41 C-3/3 35 41 2.3 37.2 37.4 C-4/3 32 48 5.9 38.2 39.2 C-4/3 40 47 3.9 42.6 47.4 TB-3/2 (C3-C4) 44 51 2.9 48.2 58.4 TB-3/2 (C3-C4) 43 52 4.0 47.4 56.8 TB-3/2 (C3-C4) 40 46 2.8 43.4 48.9 TB-3/2 (C4-C5) 35 41 2.7 38.4 39.5 C-5/2 35 43 3.2 39.6 41.7 TB-3/2 (C5-C6) 25 38 5.1 33.6 31.1 TB-3/2 (C5-C6) 29 37 3.0 32.8 29.7 C-6/2/2nd Lift 37 48 4.7 39.8 42.1 C-6/2/2nd Lift 33 37 1.7 34.4 32.5 C-5/2/2nd Lift 31 39 3.5 35.4 34.2 C-4/2/2nd Lift 35 38 1.3 36.6 36.3 C-4/2/2nd Lift 26 42 6.3 36 35.2 C-4/2/2nd Lift 37 40 1.5 38.4 39.5 TB-3/1 (C6-C1) 27 44 6.5 38.2 39.2 TB-3/1 (C6-C1) 34 40 2.4 37.2 37.4 C-1/1/1st Lift 33 39 2.3 35.0 37.5 TB-3/1 (C1-C2) 35 43 3.1 37.6 38.1 C-3/1/2nd Lift 35 45 3.9 41.8 45.8 C-3/1/2nd Lift 40 43 1.3 41.2 44.7 C-4/1/3rd Lift 29 37 3.6 32.8 29.7 C-4/1/3rd Lift 36 48 4.8 40.8 44.0 C-4/1/3rd Lift 35 46 4.0 40.8 44.0 C-4/1/3rd Lift 39 45 2.3 41.2 44.7 Table-V Results of Ultrasound Pulse Velocity Test at Jimme Ki Dhani ESR Member Len gth mm Time µ sec Veloc ity m/sec Value of R consider ed from RH Combined Compress ive Strength σ N/mm 2 C-4/2/2nd Lift (D) 450 105.7 4260 35 28.1 C-4/2/2nd Lift (ID) 300 104.7 2870 35 - TB-3/1 (C1-C2) (D) 300 73.4 4090 37 TB-3/1 (C1-C2) (ID) 300 87.6 3430 37 V. RESULTS BY PHOTOMETER  At TB3/2 C4-C5 (Near to Junction Upper Face) bar diameter is traced as 24.9.  At TB3/2 C4-C5 (Near to Mid Span Bottom Side Face) bar diameter is traced as 28.5 which indicates overlap of 20mm & 8mm bars.  At TB3/2 C4-C5 (Near to Mid Span Bottom Side Face) bar diameter is traced as 41.5 which indicates overlap of 20mm & its development bars.  At C5/3-4 (Near to Mid Hieght) bar diameter is traced as 18.2.  At C5/3-4 (Near to Mid Hieght) bar diameter is traced as 9.1mm. VI. TESTS AT LABORATORY Few sample casted at actual time of construction provided by your team tested at laboratory to establish the correlation between NDT results and actual destructive test. Rebound Hammer, UPV and Compressive strength test carried out at our laboratory and test results are as follows. Table-VI Results of Rebound Hammer Test at Laboratory Laboratory Specimen Minimu m Reboun d No. Maxim um Reboun d No. Standar d Deviati on Averag e Reboun d No. Related fck Cube 1/ Raft / 14.07.16 28 37 4.1 31.8 28.0 Cube 2/ Raft / 14.07.16 25 36 4.0 31.2 27.0
  • 4. International Journal of Latest Technology in Engineering, Management & Applied Science (IJLTEMAS) 2nd Special Issue on Engineering and Technology | Volume VI, Issue VIS, June 2017 | ISSN 2278-2540 www.ijltemas.in Page 22 Cube 3/ Raft / 14.07.16 25 31 2.4 28.0 21.9 Cube 3/ Raft / 14.07.16 25 35 4.6 28.6 22.8 Cube1/Column/1 3.08.16 27 34 2.5 30.6 26.1 Cube2/Column/1 3.08.16 29 34 2.0 31.0 26.7 Cube3/Column/1 3.08.16 25 37 5.2 30.8 26.4 Cube3/Column/1 3.08.16 24 32 3.4 30.0 25.1 Cube1/Beam/ 08.08.16 30 36 2.6 32.6 29.4 Cube2/Beam/ 08.08.16 27 32 2.3 30.0 25.1 Cube3/Beam/ 08.08.16 28 37 3.4 32.4 29.0 Table-VII Results of Ultrasound Pulse Velocity Test at Laboratory Laboratory Specimen Length mm Time µ sec Velocit y m/sec Value of R consider ed from RH Combined Compress ive Strength σ N/mm 2 Cube 1 / Raft / 14.07.16 (D) 150 35.6 4210 30 25.1 Cube 2 / Raft / 14.07.16 (D) 150 35.3 4250 30 26.2 Cube 3 / Raft / 14.07.16 (D) 150 37.2 4030 30 19.8 Cube 1/Column / 13.08.16 (D) 150 38.4 3910 30 17.3 Cube 2/Column / 13.08.16 (D) 150 35.6 4210 30 25.1 Cube 3/Column / 13.08.16 (D) 150 35.4 4240 30 25.9 Cube 1 / Beam / 08.08.16 150 34.1 4400 31 30.8 Cube 2 / Beam / 08.08.16 (D) 150 35.7 4200 31 25.1 Cube 3 / Beam / 08.08.16 (D) 150 34.9 4300 31 27.9 Table-VIII Results of Rebound Hammer Test at Laboratory Laboratory Specimen Cube Compressive Test Result Cube 1/ Raft / 14.07.16 30.22 Cube 2/ Raft / 14.07.16 33.55 Cube 3/ Raft / 14.07.16 27.55 Cube1/Column/13.08.16 30.86 Cube2/Column/13.08.16 29.55 Cube3/Column/13.08.16 32.02 Cube1/Beam/ 08.08.16 31.42 Cube2/Beam/ 08.08.16 28.68 Cube3/Beam/ 08.08.16 31.18 Some Citations:- With reference to IS 456-2000, Clause 16 Acceptance Criteria and Clause 16.1 for Compressive Strength, The Concrete shall be deemed to comply with the strength requirements when both the following conditions are met:- (a) The mean strength determined from any group of four consecutive test results complies with the appropriate limits in column 2 of table 11 (b) Any individual test results complies with the appropriate limits in column 3 of table 11 Clause 16.3 Quantity of Concrete Represented by Strength Test Results Clause 16.3 states ie the quantity represented by a group of four consecutive test results shall include the batches from which the first and last were taken together with all intervening results. Clause 16.6 Concrete is liable to be rejected if it porous or honey combed, its placing has been interrupted without providing a proper construction joint, the reinforcement has been displaced beyond the tolerances specified, or construction tolerances have been met, However, the hardened concrete may be accepted after carrying out suitable remedial measures to the satisfaction of the Engineers In charge. Clause 17.3 Testing Clause 17.4.3, Concrete in the member represented by a core test shall be considered acceptable if the average equivalent cube strength of cores is equal to at least 85 percent of the cube strength of the grade of concrete specified for the corresponding age and no individual core has a strength less than 75 percent. VII. THE PURPOSE OF THE INSPECTION The purpose of the inspection is to provide advice to a prospective or other interested party regarding the condition of the structure at the time of the inspection. The advice is limited to the reporting of the condition of the structure in accord with IS 456. This report is limited to (unless otherwise noted) the main structure on the site. This report is not intended as a certificate of compliance of the structure within the requirements of any act, regulation, and ordinance or by law, or, as a warranty or an insurance policy against problems developing with the building in the future. Assumptions & Limitations-
  • 5. International Journal of Latest Technology in Engineering, Management & Applied Science (IJLTEMAS) 2nd Special Issue on Engineering and Technology | Volume VI, Issue VIS, June 2017 | ISSN 2278-2540 www.ijltemas.in Page 23  Any person who relies upon the contents of this report does so acknowledging that the following clauses, which define the Scope and Limitations of the inspection, form an integral part of the report.  This NDT inspection is limited to those areas and sections of the structure fully accessible and visible to the Inspector at the time and on the date of Inspection.  The inspection didn’t include breaking apart, dismantling, removing or moving objects including, but not limited to, foliage, moldings, sparking membrane, appliances or personal possessions.  Provisions of IS 13311 part I and part II 1992 applies in addition to provisions of IS 516 latest version applies. So far as mix design is concerns provisions of IS 10262 and SP 23 latest versions shall comply. Needless to say that Provisions of IS 456-2000 also applies.  The visiting team DID NOT dig, gouge, force or perform any invasive procedures.  Nothing contained in the Report implies that any inaccessible or partly inaccessible area(s) or section(s) of the structure being inspected by the Inspector on the date of the inspection were free from defects latent or otherwise.  No responsibility can be accepted for defects which are latent or otherwise not reasonably detected on limited requirement.  Durability of exposed finishes.  Photographic evidence taken on the day of inspection is given as an example of the NDTs found to the structure for reporting purposes only. These photos within the report are to assist, and May not show all the tests and/or the areas noted on the day of inspection.  Any person who relies upon the contents of this Report does so acknowledging that the above clauses, definitions and disclaimers that follow define the Scope and Limitations of the inspection and form an integral part of the report.  Disclaimer of Liability: No liability shall be accepted on account of failure of the Report to notify any problems in any area(s) or section(s) of the subject structure physically inaccessible for testing purpose, or to which access for testing is denied by or to the visiting team (including but not limited to any area(s) or section(s) so specified by the Report.  Disclaimer of Liability To Third Parties: This report is made solely for the use and benefit of the Client named on the front of this report. No liability or responsibility whatsoever, in contract or tort, is accepted to any third party who may rely on the Report wholly or in part. Any third party acting or relying on this Report, in whole or in part does so at their own risk.  As requested in letter referred above of the party, care has been taken not dig out a core however combined method of Rebound hammer and Ultra Sonic Pulse Velocity meter were applied. VIII. SUGGESTIONS It is suggested that the construction should not be discontinued for so long time as it can hamper quality of construction. Other agencies can further deteriorate quality of materials used and part of the construction which has made the progress. IX. RECOMMENDATIONS All process should be including testing, witnessed by either the contractor or the agency owning the construction. The matter may be referred to a competent authority as per norms of NDMA considering Qualification and experience of the expert concerned. Ultimately onus lies on the agency owning the construction later on. X. CONCLUSION Unnecessary obstacles should be avoided. Looking to provisions of table 11 of IS 456-200 the case reported falls under individual category i.e. fck - 4 N/sq mm should be criteria for acceptance. So far as the citation quoted and visit at the site including other parameters, reported and generated, it is felt that there should not be an issue so far quality of Concrete is concerned. REFERENCES [1]. ACI 228.1R-95, In-Place Test Methods for Determination of Strength of Concrete. [2]. ACI 364.1R-94, Guide for the Evaluation of Concrete Structures Prior to Rehabilitation. [3]. ACI Manual, December 2007, Inspection Instruments Inc. [4]. Gupta A.K. and Sharma Ravi Kumar, “Short term course on Non-destructive Assessment of Structure (NONDAS)”. Department of Structural Engineering, M.B.M. Engineering College, Jodhpur [5]. Gambhir, M.L. (2000), “Concrete Technology”, Tata McGraw Hill, N. Delhi. [6]. IS: 10262:2000, Recommended guide line for concrete mix design", Bureau of Indian Standards, New Delhi. [7]. IS: 13311 – (Part 1) 1992, "Non Destructive Testing of Concrete – Methods of Test – Ultrasonic Pulse Velocity", Bureau of Indian Standards, New Delhi. [8]. IS: 13311-(Part 2) 1992, "Non Destructive Testing of Concrete – Methods of Test – Rebound Hammer", Bureau of Indian Standards, New Delhi. [9]. IS: 456-2000, "Code of Practice for Plain and Reinforced Concrete", Bureau of Indian Standards, New Delhi. [10]. IS: 516-1959, "Method of Test for Strength of Concrete", Bureau of Indian Standards, New Delhi.
  • 6. International Journal of Latest Technology in Engineering, Management & Applied Science (IJLTEMAS) 2nd Special Issue on Engineering and Technology | Volume VI, Issue VIS, June 2017 | ISSN 2278-2540 www.ijltemas.in Page 24 [11]. Kaushik, S.K. (1996), “Non-destructive testing in Civil Engineering”, Dec., Indo-US workshop on N.D.T., I.C.I., U.P., Roorkee. [12]. Malhotra V.M. and NaikTarun, "The Ultrasonic Pulse Velocity Method". CRC Handbook on NDT of concrete, CRC Press [13]. Malhotra, V., "Testing Hardened Concrete: Nondestructive Methods," ACI Monograph No. 9, 1976, 188 pages. [14]. Neville A.M. and Brooks J.J., "Concrete Technology", Third edition reprint, Pearson Education P. Ltd., Indian branch, New Delhi. [15]. Neville A.M., "Properties of Concrete", Fourth Edition, Pearson Education, 2008. [16]. Smart NDT System, Investigation of a Fire Damaged Structure: A Report (1999), 203, Signature- 1, Productivity Road, Vadodara. [17]. Smart NDT System, NDT of Earth quake Affected Structure,@ Cement Plant , Kutch. : A Report, June 2001, 203, Signature- 1, Productivity Road, Vadodara. [18]. V.M. Malhotra, Testing Hardened Concrete: Nondestructive Methods, Published jointly by The Lowa State University Press, Lowa and ACI, Michigan, 1976.