SlideShare a Scribd company logo
1 of 105
Download to read offline
CCOSTOST
Hisham Haridy, PMP, PMI-RMP, PMI-SPCCP_SEC 1
1. Cost Elements
2. Pricing and Costing
3. Materials
CContentontent
C O S T
4. Labor
5. Engineering Role and Project Success
6. Machinery, Equipment, and Tools
7. Economic Cost
8. Activity-Based Cost Management
COST ELEMENTSCOST ELEMENTS
1. Cost
The value of an activity or asset.
2. Cost Elements
The value of the resources that are expended to complete the activity or produce
the asset.
Resources used are categorized as equipment, labor, material, and “other.”
C O S T
Material
Labor
Equipment
Variable Fixed
Must be provided and are dependent on the
volume of work activity or asset production
Must be provided independent of the
volume of work, either direct or indirect.
COST ELEMENTSCOST ELEMENTS
3. Cost Structuring
Further structure the cost elements to:
Understand how they influence activity cost .
Get a better understanding of how they can be controlled.
CostStructuring
volume of work activity or asset production
that they support.
Examples the cost of Material, Labors , etc.
volume of work, either direct or indirect.
Examples set-up, Permit fees and Head
office costs, etc.
Direct Indirect
The resources that are expended solely to
complete the activity or asset.
Examples concrete, labors, non reusable
forms, and permit fees.
The resources that need to be expended
to support the activity or asset.
Examples expenses for utilities, taxes,
legal services, etc.
CostStructuring
C O S T
COST ELEMENTSCOST ELEMENTS
4. Cost Center
Groups of activities within a project that provide a convenient point for collecting
and measuring costs.
Profit Centers
Investment
C O S T
Responsibility
Centers
Cost Centers
Investment
Centers
5. Cost Accounting
The historical reporting of disbursements and costs and expenditures on a
project.
Steps:
Classification can be done using the code of accounts or WBS or Activity-
COST ELEMENTSCOST ELEMENTS
Recording Classifying Summarizing
Classification can be done using the code of accounts or WBS or Activity-
Based Costing (ABC)
6. Code of Accounts
All recorded cost elements are classified.
Sometimes referred to as a chart of accounts or as cost code of accounts.
A company’s code of accounts is configured to support the recording of cost data in
the general ledger.
C O S T
COST ELEMENTSCOST ELEMENTS
C O S T
Typical Code of Accounts
Financial Statements according to
GAAP
Income Statement
(Statement of Operations)
The Balance Sheet
(Financial Position) Statement of Cash Flows
COST ELEMENTSCOST ELEMENTS
7. Financial Reporting
(Statement of Operations) (Financial Position)
Revenue
Expenses
Profits
Operation
Investment
Financing
Assets
Liabilities
Equity
Current
Non-Current
Current
Non-Current
Paid in Capital
Retained Earnings
C O S T
8. Assets
Asset is an economic resource.
Anything tangible or intangible that can be owned
or controlled to produce value and that is held to
have positive economic value is considered an
asset.
Simply stated, assets represent value
COST ELEMENTSCOST ELEMENTS
Simply stated, assets represent value
of ownership that can be converted into cash
(although cash itself is also considered an asset).
C O S T
Tangible Assets Intangible Assets
Value is based on physical properties
Examples; buildings, land, machinery
Claim to future income
Examples; various types of financial
assets.
9. Cost Management
A. Estimating
Predicts the quantity and cost of resources needed to accomplish an activity
or create an asset.
A well-defined scope.
A cost element structure.
Historical cost data.
COST ELEMENTSCOST ELEMENTS
Historical cost data.
B. Cost Trending
Established from historical cost accounting information.
How expenditures are trending relative to physical accomplishments.
C. Cost Forecasting
Much like estimates.
An estimate is always for future activities and assets, and establishes the
Budget at Completion (BAC) for performance baselines.
C O S T
COST ELEMENTSCOST ELEMENTS
D. Life-Cycle Costing (LCC)
The total cost to the organization for the ownership and acquisition of the product
over its full life cycle.
This is the concept of life cycle costing-looking at the cost of the whole life of
the product, NOT just the cost of the project.
Life-cycle cost include construction costs, operational and maintenance costs,
taxes, financing, replacement and renovation.taxes, financing, replacement and renovation.
C O S T
Life-Cycle Cost
Elements
Costing Pricing
Cost Estimating is the determination of
approximately how much will it cost the
performing organization to provide the
product or service involved
The determination of the amount to be
charged to the client for the product
or service.
PRICING AND COSTINGPRICING AND COSTING
1. Costing Vs. Pricing
Price = Cost + Profit
Direct cost + Indirect cost + Overhead
C O S T
Inputs
Transforming
Mechanism
Tools and Techniques
Outputs
1. WBS/Scope
2. Historical Records
(Historical data base
management – Continuous
1. Costing and Pricing
Strategies
i. Cost estimating
1. Project Estimate
2. Project Acquisition
3. Business Decision
PRICING AND COSTINGPRICING AND COSTING
2. The costing-Pricing Process
management – Continuous
improvement and Risk
Mitigation)
3. Vendor Quotations
i. Cost estimating
ii. Budgeting
iii. Cost forecasting
2. Financial Management
i. Return on Investment
ii. Return on Assets
iii. Net Profit Margin
3. Business Decision
C O S T
PRICING AND COSTINGPRICING AND COSTING
3. Financial Management
a. Return on investment (ROI) =
[(Profit =(Project Outputs)- Project Costs (Inputs)]
Project Costs (Inputs)
Measures the profitability in dollars invested
b. Net Profit Margin (NPM) =
Net Income
Total Revenue
Measure of the effectiveness of a company at cost control
c. Return on Assets (ROA) =
Net Income
Total Assets
Depicts the efficiency with which management has used resources to
generate income
c. Assets Turnover =
Total Revenue
Total Assets
Return on Assets (ROA) =
Net Profit Margin X Assets Turnover
C O S T
PRICING AND COSTINGPRICING AND COSTING
Return on investment (ROI)???
C O S T
PRICING AND COSTINGPRICING AND COSTING
Net Profit Margin (NPM)????
Return on Assets (ROA) ?????
C O S T
1. Material Procurement
Materials are one of the bulk sums in any project .
If materials are not procured accurately ,it may have a significant bad effect to the
project cost and performance.
The five rights for material procurement
MATERIALSMATERIALS
C O S T
Time
Cost
Quality
Quantity
Vendor
2. Materials Competition
Competition factors including cost, availability, durability, weight, wear
resistance, and ease-of-fabrication are among relevant considerations
regarding choice of materials.
Other items for consideration include: quality assurance/quality control,
materials handling, and materials hazards.
MATERIALSMATERIALS
materials handling, and materials hazards.
3. Materials Handling
A requirement of the production process.
An inefficient materials handling system
can slow production operations, creating other
excessive costs as a result of production delays.
C O S T
These basic principles for material handling:
MATERIALSMATERIALS
1. Material movement should be over the shortest distance
possible.
2. Terminal time should be in the shortest time possible,
since the objective is to move materials.
3. Eliminate manual material handling when mechanized
methods are feasible.
C O S T
methods are feasible.
4. Avoid partial transport loads, since full loads are more
economical.
5. Materials should be identifiable
MATERIALSMATERIALS
4. Materials Handling Decisions
There are four basic decision factors that affect materials handling.
i. Type of material to be handled: Clay in loaders, structural steel by crane,
liquids in pipelines.
ii. Production system type: Job shop or batch process and continuous
process.
iii. Facility type: Low ceiling height, rectangular area, open area.iii. Facility type: Low ceiling height, rectangular area, open area.
iv. Materials handling system costs: Initial Cost, lifecycle costs, disposal
costs.
C O S T
MATERIALSMATERIALS
Raw Materials Bulk Materials Fabricated Materials
Engineered/
Designed
Materials
Materials utilized in
a production or
fabrication process
Materials readily
available with minimal
lead times for order
Bulk materials transformed
into custom-fit items for a
particular product or project.
Materials require
substantial work in
order to attain their
5. Types of Materials and Related Information
The most basic.
Ex: Raw materials
such as coal,
limestone, etc.
and delivery.
EX: Steel Sheet, steel
bars, steel pips..etc
Ex: Steel pipe transformed by
fabrication into custom
dimensions for particular use.
final form.
EX: Pumps, motors,
boilers, chillers, fans,
compressors, etc.
C O S T
MATERIALSMATERIALS
5. Production Materials Purchase and Management
i. Materials Quality
Poor quality materials can result in product defects leading to increased costs.
Higher-quality materials in excess of requirements will lead to excessive costs.
ii. Materials Traceability & Vendor Surveillance
Vendor surveillance may require periodic inspection at the vendors’ location.Vendor surveillance may require periodic inspection at the vendors’ location.
Materials traceability is accomplished by means of Mill Certifications.
iii. Materials Quantity
Materials storage is a further burden that can exceed the value of the
materials.
Insufficient inventories may create dangers of “stock-outs” interrupting process.
To balance these demands, determine Economic Order Quantity (EOQ) number.
C O S T
MATERIALSMATERIALS
iv. Economic Order Quantity (EOQ)
EOQ = (2 x D x P) / S
Where:
EOQ: The optimal order quantity (not function of item cost)
D: Annual demandD: Annual demand
S : Storage costs
P : Purchase order costs which is setup cost (ordering, shipping,
handling) not the cost of goods
A garden tractor manufacturer has a requirement for 15,000 engines per year.
The engines each cost $75. The order cost for a purchase order is $250. The
storage costs for the engine are $12 per year, which includes space costs and
financing costs.
Economic Order Quantity (EOQ)???
C O S T
MATERIALSMATERIALS
v. Reorder Point
Where:
PR: Reorder point
O: Order time
R : Production rate
I : Minimum inventory level or safety stock
(RP) = (O x R) + I
Assume that the production process uses 60 engines per day for the 60 garden
tractors produced per day. If the lead time for an order is 5 days, and the safety
stock level is 180 engines (minimum level), then the reorder formula in this
example yields:
Reorder Point (RP)???
C O S T
MATERIALSMATERIALS
vi. Just-In-Time Inventory Techniques
The just-in-time concept implies that the exact material quantities needed
are delivered at the exact time needed.
The goal is to reduce inventories and the related costs, such as storage
space.
Traditional practices that focus on safety stocks can mask unprofitable
variations in the production process.variations in the production process.
By removing these safety stocks, the goal of just-in-time systems is a lean
production process and an enhanced competitive position.
The production facility therefore receives more frequent deliveries of smaller
shipments on a periodic basis.
C O S T
MATERIALSMATERIALS
C O S T
Just-In-Time Inventory Techniques
MATERIALSMATERIALS
C O S T
Lean Production Process
MATERIALSMATERIALS
viii. Expediting
Non-standard and costly items A continual basis items
A system of plans/specifications
requirements and competitive
bidding.
A systems contract may be the best
solution.
vii. Individual Purchasing Orders and Systems Contracts
Expediting involves the monitoring of
all steps in the procurement cycle to
ensure on-time delivery of the
necessary materials.
This monitoring includes checking
design status, material status,
production status, and shipping
status.
C O S T
MATERIALSMATERIALS
ix. Materials Inspection
Inspections can range from simple visual
methods to machine-assisted inspections
incorporating techniques such as X-ray and
ultrasonic technology to detect flaws.
The goal is to ensure that the correct grade
and quality of materials are being receivedand quality of materials are being received
from suppliers.
x. Global Materials Decisions
Materials fabrication decisions, as to locations
and methods, are being made on a global basis.
Ex, Nike and Dell.
C O S T
MATERIALSMATERIALS
6. Plant Material Management
Materials that are not incorporated into product or project.
Instead assist in production operations.
i. Specialized Plant Materials
Such as replacement parts may be available only from the Original
Equipment Manufacturer (OEM) and require significant lead time.
ii. Plant Materials Benchmarkingii. Plant Materials Benchmarking
Plant materials usage and longevity should be tracked through such measures
as benchmarking.
Benchmarking involves the examination of other organizations as to their
practices
7. Safety Data Sheet and Hazard Communication
Must be readily available and accessible to those dealing with hazardous
materials as required by (OSHA).
C O S T
MATERIALSMATERIALS
8. Material Life Cycle
All materials have a life cycle from initial development through to manufacture,
incorporation in the product, and eventual disposal.
i. Waste Materials
Original materials cost.
Handling costs.
Disposal costs.
ii. Surplus materials
Excessive order.
Change in material requirements.
Incorrect quantity information.
C O S T
I. Labor Classification
Labors are human resources and personnel performing in the activity or the
project.
LABORSLABORS
Direct Labor Indirect Labor Overhead Labor
Directly produce the
product
Not part of product but
that are required to
Allocated as a business expense
independent of the volume ofproduct that are required to
complete the project.
independent of the volume of
production.
C O S T
LABORSLABORS
Base Wages
Fringe Benefits
Paid Time-Off (PTO)
Medical and Life
Insurance Benefits
Government Mandated
Benefits
The amount that
goes directly to the
Labors are paid for
local and national
Some firms and labor
contracts include
Government retirement
funds, unemployment
II. Developing Labor Rates
1. Employees
goes directly to the
employee
local and national
holidays ,vacations
and sick time
contracts include
contributions to a
medical and life
insurance program
funds, unemployment
insurance, retirement
healthcare insurance
C O S T
LABORSLABORS
Workshop
An engineer gets 5 days of sick time, 10 days of vacation, and 10 holidays /year.
1. Calculate the adders cost
If the nominal working time is 52 w/y , 40 h/w , 8 h/d
2. What is the real productive time?
3. What is the actual hour cost?
If the firm contributes $500 per month for medical insuranceIf the firm contributes $500 per month for medical insurance
4. What is the added cost /h?
If the firm contributes Retirement(6.2%), Retirement Medical (1.45%), State
Unemployment (1.0%).
5. What is the added cost /h?
6. What is the total hourly cost?
7. What is the percentage of adders?
C O S T
LABORSLABORS
C O S T
LABORSLABORS
2. Engineering/Contractors Overhead and Profit
When hiring contract employees, labor rates are usually broken down differently.
i. Base wages, including fringes
ii. Worker’s compensation (if applicable)
iii. Overhead
iv. Profit, (if applicable for time and material situations).
3. Fully Loaded or Billing Rate
C O S T
The base wage, plus adders.
An owner pays for the worker’s time when he
or she is on the job.
4. Overtime
(PTO, insurance, and some governmental programs) are
not added to overtime.
Some other governmental retirements are usually added
to overtime.
LABORSLABORS
5. Weighted Average Rates/Crew Composite Rates
The labor composite unit rate is used with unit rate cost estimating.
We use composite labor rate and material, equipment and temporary
construction materials to calculate an activity composite unit rate
C O S T
LABORSLABORS
Workshop
A contractor needs to make up time in the schedule. If the contractor works the
concrete crew, 10 hours per day, Monday through Saturday for two weeks, how
much extra will it cost the contractor?
Overtime is paid for all hours over eight Monday through Friday, and the first
eight hours on Saturday.
Double-time is paid for hours greater than eight on Saturday and all Sunday
work.
Based on the following data, What is the average hourly cost of the crew?
C O S T
LABORSLABORS
C O S T
LABORSLABORS
6. Indirect and Overhead Labor
There are two methods of determining Indirect and Overhead Labor costs
i. To do a direct estimate of the indirect staff required and cost them out the
same way as the direct work crews.
ii. To use historical job percentages to determine an appropriate allowance
for indirect labor.
C O S T
LABORSLABORS
III. Productivity
1. Factors Affecting Productivity
i. Union or non-union craft labor
ii. Local Labors
iii. Remote area and transportation
iv. Weather conditions
C O S T
iv. Weather conditions
v. Local holidays
vi. Temporary living quarters
vii. Overtime
viii. Standard work hours and work days?
2. Learning Curve
The concept of learning curve theory is ; If people do a job repeatedly, each
time they double the number of times they repeat the job, the time to do the
work is reduced by a constant percentage.
LABORSLABORS
C O S T
LABORSLABORS
3. Productivity Improvement
The opportunity to put in place procedures or make changes to improve
productivity and minimize the cost of some of these factors.
Shorten waiting time for a crew, material may be pre-staged at the work
location.
A manufacturing plant has the added benefit of more permanent personnel
C O S T
and the same physical location.
Minimize the impact of adverse weather.
Lean Management
Training and team building.
4. Performance Monitoring
i. Work Package/ WBS
The required work hours for each work package or work breakdown structure.
ii. Graphical Presentation of EV Data
Graphical presentation of Earned Value analysis such as CPI, SPI, CV and SV.
LABORSLABORS
iii. Work Sampling
C O S T
iii. Work Sampling
A method that can be used to determine
production or unit rates for specific work
activities.
ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS
Engineering is a key element toward the success of products and projects.
Computerized techniques, such as CAD, BIM, simulation, and others, require
significant upfront investments in software/training, but correctly applied
have proven their worth in reducing overall costs toward the delivery of
products and processes.
Techniques including constructability, manufacturability, and value analysis
have found use in this area.
Process development:
C O S T
Research
Design
Construction
ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS
I. Product, Project, and Process Development
1. Pure and Applied Research
In the development of products, organizations conduct research.
The research can be divided into two types
Pure or Basic Research Applied Research
Involves work without a specific end The attempt to develop usable products or
2. Product, Project, and Process Life Cycles
The life cycle of a particular product/project will have a significant influence on
all design decisions, including producing plant and equipment.
Civil infrastructure projects often have lives of many decades and should be
designed for low-cost maintenance and upgrades.
C O S T
Involves work without a specific end
product or use in mind.
The attempt to develop usable products or
add new feature-sets to existing products
ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS
3. Computer-Aided Design (CAD)/Engineering
(CAE)
Utilization of computerized work stations and
software to develop and analyze a product,
project, or process design.
C O S T
4. Computer-Aided Manufacturing (CAM)
CAD/CAE ported directly into CAM software.
Design is directly sent to machines like CNC
Computer-numerically controlled
ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS
5. Prototypes
Developed prior to large-scale production
i. Test designs
ii. Test customer reaction.
Prototype development is expensive, but is less expensive than discovered afterPrototype development is expensive, but is less expensive than discovered after
numerous units are in customer hands.
C O S T
ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS
6. Patents and Trade Secrets
Investments in new products and research are typically both expensive and
time-consuming endeavors.
This investment must receive protection. (20 years, 8 June 1995, WTO).
Organizations can protect this investment through either patents or trade
secrets.
Organizations wishing to emulate patent’s provisions will develop different
approach different or pay to the patent holder.
Trade secrets can be somewhat broader than patent protection in that they
protect both commercial and technical information from disclosure
7. Product Liability
Those injured by a product can seek compensation for their damage.
The tort law in this area has evolved over decades from a concept of “buyer
beware” to a concept of “seller beware”.
C O S T
ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS
II. Product, Project, and Process Design
1. Standardization
The attempt to base product designs. The advantages are lower costs, shorter
time, and maintenance personnel are more familiar.
The disadvantage that If there is a flaw, it will be spread over a wide variety of
products.
2. Process Selection
Relates to production methods, continuous and discrete
i. Continuous production methods such as petrochemical plants, power
plants and manufacturers with assembly-line methods. It’s less expensive
in the long run.
ii. Discrete production such as pre-cast concrete plant, or structural steel
fabrication shop. It has a higher labor factor. Favored where labor costs are
less expensive.
C O S T
ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS
3. Manufacturability
Slight modifications in a design that promote ease
of product assembly without affecting the product
that designs should be:
i. Forgiving of minor inaccuracies
ii. Easy to fabricate
iii. Based on efficient utilization of labor, materials,
and equipment
4. Constructability (BIM)
The Counterpart of manufacturability applied to
constructed projects to pinpoint problems before
designs are developed to the point where changes
create significant delays and associated costs.
C O S T
ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS
5. Make-or-Buy Decision
Which items should be subcontracted out and which should be made in-house.
Do organization’s quality and cost on an item can compete with outside
suppliers.
If trade secrets are involved, the decision will typically be to make the item,
the goal is to enhance overall quality at a lower cost.
It is better to "make" if:
i. You have an idle plant or workforce.
ii. You want to retain control.
iii. The work involves proprietary information or procedures.
C O S T
(Operation)
Total Cost “of
equipment”
$
Cost of rent
equipment
1.5 M
Example of resource equipment
ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS
(Asset)
1.5 M
Quantity100,000
C O S T
ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS
III.Engineering Production/Construction
1. Production Health and Safety
An accident results in the loss of a trained worker
and an interruption in the process.
Systems must be selected that reduce/eliminate the
potential of accidents
2. Facility Layout
Decisions as to arrangement, including equipment
location, labor location, and services location.
Layout decisions should always consider the potential
impact of additional demand therefore considering
future expansion.
C O S T
ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS
3. Assembly And Flow Process Charts
Assist in planning the facility layout.
They help to analyze production operations in
terms of operations sequences performed,
distances between operations, and operation
time requirements.
4. Quantitative Analysis In Facility Layout.
i. Linear programming is a mathematical
technique that is widely used in finding
optimal solutions to problems.
ii. Monte Carlo techniques can be used to
simulate wait time for a crane in a plant and
its cost impact while data can be generated
via computer programs with random number
generators. C O S T
ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS
5. Reengineering
Redesign of process to achieve improvements such as cost, quality, service,
and speed.
Reengineering focuses on the optimization of the total organization, rather than
sub-optimization of individual departments.
Reengineering focuses on the “whys” of an action or process as opposed to the
“hows”.
C O S T
MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS
Equipment Value
Categories
Replacement cost (the cost
new of an item having the same or
similar utility)
Reproduction Cost
Market value (used equipment,
secondary market value)
Fair Market Value-in-
Place
C O S T
Fair Value
Fair Market Value-in-
Exchange
Orderly Liquidation
Value
Forced Liquidation
Value
Salvage Value/Part-Out
Value
Scrap Value
MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS
I. Equipment Value Categories
Equipment values can be divided into two major categories:
1. Replacement cost (the cost new of an item having the same or similar utility)
2. Market value (used equipment, secondary market value)
1. Replacement cost (the cost new of an item having the same or similar
C O S T
1. Replacement cost (the cost new of an item having the same or similar
utility)
i. Reproduction Cost
The cost new of an identical item.
ii. Fair Value
Cost new of an item considering similar items cost, and taking into account
utility and all standard adjustments and discounts to list price. $350,000
MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS
2. Market value (used equipment, secondary market value)
i. Fair market value in place
The amount expressed in terms of money that may reasonably be expected to
exchange between a willing buyer and a willing seller $250,000, 125%
ii. Fair market value in exchange
The amount expressed in terms of money that may reasonably be expected to
C O S T
The amount expressed in terms of money that may reasonably be expected to
be exchanged in a third party transaction between a willing buyer and a
willing seller (retail value) $200,000, 100%
iii. Orderly Liquidated Value
The estimated gross monetary amount that could typically be realized from a
liquidation sale, given a reasonable period of time to find a purchaser.
(wholesale value) $160,000 , 80%
MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS
iv. Forced Liquidated Value
The amount expressed in terms of money that may reasonably be expected
from a properly advertised and conducted auction where time is of the
essence (blow-out value). $120,000, 60%
v. Salvage value / part out value
The amount expressed in terms of money that the buyer will pay to a seller,
C O S T
recognizing the component value of parts of the equipment that can be used or
resold to end-users, usually for repair or replacement purpose $8,000, 4%
vi. Scrap Value
the estimated monetary amount that could be realized for the property if it
were sold for its material content, not for productive use, as of a specific date
value ie. $/ton of steel $2,000, 1%
MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS
Very Good (VG) Good (G) Fair (F) Poor (P) Scrap (X)
Used with
equipments with
excellent
appearance and
Used with
equipments
that were
modified or
Used with
equipments used at
some point below
its fully specified
Used with
equipments used at
some point below
its fully specified
The
equipment is
no longer
serviceable
3. Equipment Condition Terms and Definition Example
C O S T
appearance and
being used to its
full design
specification
without being
modified or
requiring any
repairs
modified or
repaired
and is being
used at or
near it fully
specified
utilization
its fully specified
utilization due to
the effect of age or
application.
It may require some
general repairs and
replacement of
some minor parts.
its fully specified
utilization that
will require
extensive repairs
and/or
replacement of
major elements
in the near future.
serviceable
and cannot
be utilized to
any
practical
degree.
MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS
I. Equipment Valuation
1. Residual Value
Residual value is the salvage value of an asset.
It represents the amount of value that the owner of an asset can expect to
eventually obtain when the asset is disposition
2. Residual Value Determination Methods
C O S T
i. Income approach (present value of future cash flows)
ii. Market approach (Trade data)
MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS
Normal Curve Disrupted-Market Regulatory Change Curve
long-lived equipment,
usually L-Shape.
Usually U-Shape, results from
equipment shortage or regulatory
pressures causing suddenly
deviation.
Illustrates sudden impact on
market value that regulation can
cause.
C O S T
High Obsolescence Curve New Tax Law / High Inflation Curve
Illustrates impact of technological obsolescence
such as computers and high-tech equipment.
Tax laws and inflation can cause a normal
residual curve to rise in a short time.
MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS
3. Variables That Affect Residual Value
i. Initial Cost
For residual purposes, the estimator should consider hard costs only.
Hard cost includes
a. The cost new equipment
b. Items necessary to make it operate such as motors, electrical, and
controls.
C O S T
controls.
Soft costs should not be included such as foundations, freight, debugging,
taxes, and installation.
ii. Maintenance
It can affect the useful life of equipment. In calculating a residual value,
estimators must consider how the equipment will be maintained and/or the
maintenance provisions in the lease
MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS
iii. Use, Wear, and Tear:
Equipment in harsh service versus mild service can be substantial. Ex: hopper
used in grain service lives 40 to 50 years. However, if used in salt service,
their useful lives can be as short as 15 years.
iv. Population
This gives statistical significance to the residual value, because the value will
be based on a large sample.
C O S T
be based on a large sample.
v. Age
Equipment presented as new in January 2012, could have a 2011 or 2010
build date.
Both are new with the same condition but the price is different.
MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS
vi. Economy
A used truck in a robust economy may be sold for lower price and longer time
in a recession.
Cost of money should also be calculated in the overall cost.
vii. Changes in Technology
An analysis of technological changes occurring over the past 20 years shows
that future advances in technology were generally known at the time of lease
C O S T
that future advances in technology were generally known at the time of lease
origination.
Time necessary to “fix” an image from minutes to seconds.
viii. Foreign Exchange
Changes in foreign exchange value could affect selling / residual value,
causing them to suddenly drop or increase.
Strong foreign currency may rise the price of foreign equipment, which in
turn, may pull residuals up, and vice versa
MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS
ix. Tax Law
Sometimes tax laws can affect new equipments price, hence affecting used
equipment price.
x. Legislation/Regulation
Regulations may impact values in positive ways, however, the impact is often
negative.
xi. Equipment Location
C O S T
xi. Equipment Location
Does the equipment required to be delivered to a prime market location or will
it have to be sold in a remote area?
xii. Method of Sale
Price of cash sales will not be like installment sales.
ECONOMIC COSTSECONOMIC COSTS
Opportunity Costs Sunk Costs Book Costs Incremental Costs
The foregone
benefit by choosing
one alternative
over another.
Funds already spent in by
virtue of past decisions. Since
these expenditures are in the
past, by definition, they should
The value of an
item as reflected
in the firm’s books.
Book costs do not
When comparing
between many
alternatives, cost
differences
I. Types of Costs
C O S T
over another.
You have two
projects to choose
from: Project A
with an NPV of
$45,000 or Project
B with an NPV of
$85,000. What is
the opportunity
cost of selecting
project B?
past, by definition, they should
not influence current
decisions.
Project A had initial budget of
$ 1,000 out of which $ 800
has already been spent. To
complete project A, we will
need additional $ 500. Another
Project B will require $ 1200
for completion. Which project
do you want to select?
Book costs do not
represent cash
flows and thus are
not taken into
account for
economic analysis
decisions.
differences
between them are
called incremental
costs.
If two units have
annual costs of
$1,500, $1,800,
then incremental
cost difference is
….?.
ECONOMIC COSTSECONOMIC COSTS
Inflation Deflation Escalation Currency Variation
A rise in the price level of
a good or service, or
market basket of goods
and/or services
A fall in the general
price level for goods
and services or a
representative market
A technique to
accommodate price
increases or
decreases during
A significant cost
impact both on those
inside the country as
well as those outside
II. Changes in Costs
C O S T
and/or services
i. Money supply
ii. Exchange rates
iii. Demand-pull
inflation
iv. Cost-push inflation
representative market
basket of goods and
services
decreases during
the life of the
contract
well as those outside
the country.
ECONOMIC COSTSECONOMIC COSTS
Regulations Taxes
Depreciation
and Depletion
Mandating
certain actions
by
organizations
Governments are most often maintained by the taxes that
they impose. These taxes take many forms, such as
income taxes, property taxes, inventory taxes,
employment taxes, gross receipts taxes, and sales taxes
Depreciation
is a non-cash
expense that
reduces taxable
III. Governmental Cost Impact
C O S T
organizations
may or may
not have an
impact on
costs.
employment taxes, gross receipts taxes, and sales taxes
Effective tax rates termed average tax rates are
calculated for income taxation purposes by the percentage
of total taxable income paid in taxes.
The marginal tax rate is the tax rate on the next
dollar of taxable income.
Investment Tax Credits that governments may give
firms tax credits to encourage economic activity.
reduces taxable
income.
Depletion
analogous to
depreciation but
for natural
resources.
IV. Depreciation
Large assets (e.g., equipment) purchased by a company lose value over time.
There are two forms of depreciation:
1. Straight Line Depreciation
2. Accelerated Depreciation
Accelerated depreciation depreciates faster than straight line.
Straight Line Depreciation Accelerated Depreciation
ECONOMIC COSTSECONOMIC COSTS
Straight Line Depreciation Accelerated Depreciation
The same amount of depreciation is taken
each year.
D = (C - S) / N
There are two forms:
1. Double Declining Balance D = ( 2 / N ) (BVt-1)
2. Sum of the Years Digits
Dr = (C - S) x [ (N-r+1) / ((N(N + 1) /2 )]
Example: A $1,000 item with a 10-year
useful life and no salvage value (how much
the item is worth at the end of its life)
Would be depreciated at $100 per year.
Example: A $1,000 item with a 10-year useful life
and no salvage value (how much the item is worth at
the end of its life)
Would be depreciated at $180 the first year, $150 the
second, $130 the next, etc.
C O S T
ECONOMIC COSTSECONOMIC COSTS
Year
Depreciation
Formula
Depreciation
Amount
Book Value
0 0 0 5000
Your company bought a new equipment with Life time =5years ,Initial cost =5,000,
Salvage value =1,000.
Find the equipment value throughout the life period.
C O S T
1 (5000-1000)/5 800 4200
2 (5000-1000)/5 800 3400
3 (5000-1000)/5 800 2600
4 (5000-1000)/5 800 1800
5 (5000-1000)/5 800 1000
4000
Straight Line Depreciation
ECONOMIC COSTSECONOMIC COSTS
3000
3500
4000
4500
5000
Depreciation Curve
C O S T
0
500
1000
1500
2000
2500
0 1 2 3 4 5
Depreciation Curve
Straight Line Depreciation
Double Declining Balance Sum of the Years Digits
A uniform rate of depreciation is applied
annually to the undepreciated value as
of the end of the previous year.
The rate used is double the
depreciation rate used in the
The depreciation charge is calculated as follows:
1. Calculate the sum of years' digits as SYD=
n(n+1/2).
2. For each year, calculate the sum of years' digits
fraction as the ratio of the number of remaining
ECONOMIC COSTSECONOMIC COSTS
straight line method.
In the first year, this depreciation rate is
applied to the initial cost of the asset
without subtracting the salvage value.
5 years, 100,000 (40%), 100,000
*40%, 60*40%, ..etc
fraction as the ratio of the number of remaining
years over the sum of years' digits.
3. Multiply the sum of years' digits fraction by
depreciable cost.
4. 5years, (5+4+3+2+1), 5/15, 4/15, 3/15, 2/15,
1/15
C O S T
ECONOMIC COSTSECONOMIC COSTS
Your company bought a new equipment with Life time =5years ,Initial cost
=5,000, Salvage value =1,000.
Find the equipment value throughout the life period.
Year
Depreciation
Formula
Depreciation
Amount
Equipment
Value
Book Value
C O S T
0 0 0 5000 5000
1 (2/5) (5,000-0) 2000 3000 3000
2 (2/5) (5,000-2,000) 1200 1800 1800
3 (2/5) (5,000-3,200) 720 1080 1080
4 (2/5) (5,000-3,920) 432 648 1000
5 (2/5) (5,000-4,352) 259.2 388.8 1000
Double Declining Balance
ECONOMIC COSTSECONOMIC COSTS
3000
3500
4000
4500
5000
Depreciation Curve
C O S T
0
500
1000
1500
2000
2500
0 1 2 3 4 5
Depreciation Curve
Double Declining Balance
ECONOMIC COSTSECONOMIC COSTS
Your company bought a new equipment with Life time =5years ,Initial cost
=5,000, Salvage value =1,000.
Find the equipment value throughout the life period.
Year
Depreciation
Formula
Depreciation
Amount
Book Value
0 0 0 5000
C O S T
0 0 0 5000
1 (5/15) (5,000-1,000) 1333 3667
2 (4/15) (5,000-1,000) 1067 2600
3 (3/15) (5,000-1,000) 800 1800
4 (2/15) (5,000-1,000) 533 1267
5 (1/15) (5,000-1,000) 267 1000
Sum of the Years Digits
ECONOMIC COSTSECONOMIC COSTS
2500
3000
3500
4000
4500
5000
Depreciation Curve
Depreciation Curve
C O S T
Sum of the Years Digits
0
500
1000
1500
2000
2500
0 1 2 3 4 5
Depreciation Curve
Another form of depreciation is called Units of Activity (or Production)
In this method, the depreciation charge is calculated as follows:
a. Divide the depreciable cost over the expected useful life of the asset (in hours, miles, or
similar units) to obtain the depreciation rate per unit.
b. At the end of each year, multiply the depreciation rate per unit by the actual usage during
that year.
In the units of activity (or production) method, the depreciation charge is not
ECONOMIC COSTSECONOMIC COSTS
In the units of activity (or production) method, the depreciation charge is not
known in advance for each year. It is calculated after the conclusion of each
year's activities.
An organization, or an individual, may choose the depreciation method that best
fits their business needs.
In depreciating real estate, only the straight line method is allowed.
An organization, or an individual, may switch the depreciation method, during the
life of the asset, only once and only to the straight line method.
C O S T
V. Economic Analysis Techniques
1. Time Value of Money
In order to compare different alternatives on the same basis, these cash amounts of
income and expenditures must be set to equivalent terms.
There will be an interest rate set which provides the common basis for calculations.
When evaluating expected income/cost flows in the future, this interest rate can also be
referred to as a “discount rate,” since money in the future is “worth” less than money in
ECONOMIC COSTSECONOMIC COSTS
the present.
Common Language terms are;
C O S T
Economic Analysis Techniques
Standard Formulas for Economic Analysis
ECONOMIC COSTSECONOMIC COSTS
C O S T
i. Present Value (PV):
The value today of future cash flows.
This is the method of determining today’s value of future money.
PV =
FV
(1+i)n
Where:
PV: Present Value
FV: Future Value
ECONOMIC COSTSECONOMIC COSTS
Example
What is the present value of $300,000 received three years from now if we
expect the interest rate to be 10 percent?
FV: Future Value
i : Interest rate
n : number of time periods
PV =
300000
= $225,394
(1+0.1)3
C O S T
ii. Net Present Value (NPV)
The sum of the present value of all income and expenditures of a project. (> 0
is ok).
It is the present value of the total benefits (income or revenue) minus the costs
over many time periods.
NPV= PV (all cash inflows) – PV (all cash outflows)
FV
ECONOMIC COSTSECONOMIC COSTS
Example
You have two projects to choose from. Project A will take three years to
complete and has an NPV of $45,000. Project B will take six years to complete
and has an NPV of $85,000. Which one would you prefer?
Decision: Maximum NPV Project “B”
NPV = ∑
FV
- Initial Investment
(1+i)n
NPV = ∑ PVCF - II
C O S T
Time Income / Present Value of Income Present Value of Cost
Example
Cash flow as follow with interest 10%.
NPV?
200
50 100 300
100
I or WACC= 10%
0
1 2 3
ECONOMIC COSTSECONOMIC COSTS
NPV= 353 - 291 = $ 62
Time
Period
Income /
Revenue
Present Value of Income
at 10% Interest Rate
Costs
Present Value of Cost
at 10% Interest Rate
0 0 0 200 200
1 50 45 100 91
2 100 83 0 0
3 300 225 0 0
Total 353 291
Decision: Accepted
C O S T
iii. Capitalized Cost (CC)
Capitalized cost (CC) represents the present sum of money that needs to be set
aside now, at some interest rate, to yield the funds required to provide the
service.
A= P X I
Where:
P: Present Value
i : Interest rate
ECONOMIC COSTSECONOMIC COSTS
Example
A bridge is built for $5,000,000 and will have maintenance costs of $100,000
per year at 6%, what is the capitalized cost of service?
i : Interest rate
A : End of year payment of uniform amount series
CC = 5,000,000 +
100,000
= $6,666,667
0.06
C O S T
iv. Equivalent Uniform Annual Cost (EUAC) or Benefit
It may be preferable to resolve the comparison to annual cash flow analysis.
The comparison may be made on the basis of Equivalent Uniform Annual Cost
(EUAC), Equivalent Uniform Annual Benefit (EUAB) or on the EUAB-EUAC
difference.
ECONOMIC COSTSECONOMIC COSTS
EUAC = (P – S) (A/P, i, n) +SI
Where:
P: Present Value
S: Salvage value
Example
A bridge Assume that the two units, Unit A and Unit B are compared on the
basis of EUAC. Unit A has an initial cost of $20,000 and $3,000 salvage value,
while Unit B has an initial cost of $15,000 and $2,000 salvage value. Unit A has
a life of ten-years, whereas Unit B has a five-year life. Cost of capital is ten
percent.
C O S T
S: Salvage value
i : Interest rate
A: Annuity
n : number of time periods
v. Rate of Return (ROR)
Many organizations often set hurdle rates (benchmark rate of return) that a
capital investment decision must achieve to be acceptable.
In the case where investment funds are limited, projects with the highest
ROR values can be selected.
0 = ∑
FV
- Initial investment
(1+i)n
Where:
ECONOMIC COSTSECONOMIC COSTS
Project “Proceed”
The NPV of the cost is set equal to the NPV of the benefit. The NPV Cost of
Unit A versus Unit B is $10,000 ($20,000 - $10,000). The NPV of the Unit A
– Unit B Benefit is $15,000.
Example
Unit A cost of $20,000 and Unit B of $10,000 and each 1-year life. Incremental
benefit of $15,000 for A compared to B. Organization hurdle rate is 20%.
Decision: ROR= 50% > 20%, investment
Where:
i : Rate of return
C O S T
vi. Payback Period
The payback period is the length of time required to recover an initial
investment through cash flows generated from the investment.
The shorter the time period, the better the investment opportunity.
Common use because it used be small and medium enterprises (represent 80%
of the market).
Payback period is THE LEAST precise of all capital budgeting methods because:
1. There is NO discounting involved, so the time value of money is completely
ECONOMIC COSTSECONOMIC COSTS
1. There is NO discounting involved, so the time value of money is completely
ignored.
2. The payback rule also fails to consider any risk differences (Calculated the
same way for both very risky and very safe projects).
Payback Period=
Initial Investment
(Annual cash inflows)
C O S T
Example
A project costs $100,000 to implement and has annual net cash inflows of
$25,000.
Example
Project A has an investment of $ 500,000 and payback period of 3 years.
Payback Period=
100,000
= 4 years
25,000
ECONOMIC COSTSECONOMIC COSTS
Project A has an investment of $ 500,000 and payback period of 3 years.
Project B has an investment of $ 300,000 and payback period of 5 years. Using
the payback period criteria, which project will you select?
Project “A”
Key selection: Lowest Payback period
C O S T
Example
Example
Years 0 1 2 3 4
Cash flow -1000 500 400 300 100
Net Cash
flow
-1000 -500 -100 200 300
Payback period = 2.33 years
ECONOMIC COSTSECONOMIC COSTS
Example
Years 0 1 2 3 4
Cash flow -1000 100 300 400 600
Net Cash
flow
-1000 -900 -600 -200 400
Payback period = 3.33 years
C O S T
vii.Benefit Cost Ratio (BCR)
A comparison of revenue to costs. Greater than 1 is good.
BCR of > 1 means that benefits (i.e. expected revenue) is greater than the
cost. Hence it is beneficial to do the project.
BCR=
Benefits (or Payback or Revenue)
Costs
ECONOMIC COSTSECONOMIC COSTS
C O S T
ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT
Case
Jon, Ian, Michel and Nancy order separate items for lunch.
Jon’s order amounts to $14
Ian consumed $30
Michel’s order is $16
Nancy’s order is $24
C O S T
Nancy’s order is $24
Total $84
What is the average cost per lunch?
$84 ÷ 4 =
$21
Jon and Michel
are overcosted
Jan and Nancy
are
undercosted
ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT
I. Overhead Expenses and Direct Expenses
Overhead expenses have been displacing the recurring costs.
Organizations have visibility of direct costs, but not have any insights into overhead
or its reasons.
Activity Based Cost Management can help provide for insights.
C O S T
Indirect Expenses are
Displacing Direct Expenses
ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT
Activity-Based Management Activity-Based Costing
Focuses on activities during
production and performance process
Improves the value received by
customers
Recognizes several levels of costs
Accumulates costs into related cost
pools
Uses multiple cost drivers to assign
C O S T
Enhances profitability costs to products and services
Cost Driver
A factor that can causes a change in the cost of an activity.
An activity can have more than one cost driver attached to it.
For example, a production activity may have the following associated cost-
drivers: a machine, machine operator(s), floor space occupied, power consumed,
and the quantity of waste and/or rejected output.
ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT
C O S T
Each Activity Has its Own Driver
ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT
II. Activities are Expressed with Action Verbs and Trace Expenses to Output
General Ledger ABC/M
Transaction - centric Work - centric
Uses chart of accounts Uses chart of activities
What was spent What it was spent for
C O S T
Records the expenses
Calculates the costs of activities
and unit cost
Organized around cost centres to
accumulate transactions into their
accounts.
But this format is deficient for
decision support
Describes activities using an
“action verb- adjective-noun”
format, such as inspect defective
products, open new customer
accounts
ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT
Cost Elements Activities Cost Object
III. ABC/M is a Cost Re-assignment Network
ABC re-assigns all of the costs into the final products, service lines, and
customers.
ABC cost re-assignment network consists of the three modules connected by
cost assignment paths.
C O S T
Cost of a
resource or
input consumed
by an activity.
Aggregations of
actions performed
in an organization
which are useful
for ABC
computations
A product or
department for
which costs are
accumulated or
measured
ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT
C O S T
ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT
IV. Using The Attributes of Activity –Based Costing
One role for calculating costs is to identify which activities are:
1. Not required and can be eliminated (Ex: Duplication of effort)
2. Ineffectively accomplished and can be reduced
3. Required to sustain the organization (not be possible to reduce or eliminate).
4. Discretionary and can potentially be eliminated (Ex: Annual employees’ picnic).
Traditional methods do not provide any way to tag/highlight individual costs.
C O S T
Traditional methods do not provide any way to tag/highlight individual costs.
ABC/M allow managers to differentiate activities from one another.
ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT
C O S T
ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT
V. Local vs. Enterprise-Wide ABC/M
A common misconception is that ABC/M system must be enterprise-wide. However
In practice, the majority of ABC/M is applied to subsets of the organization for
process improvement rather than revenue enhancement.
The local model is used for tactical purposes, often to improve productivity. In
contrast, the enterprise-wide model is often used for strategic purposes because
C O S T
contrast, the enterprise-wide model is often used for strategic purposes because
it helps focus on where to look for problems and opportunities.
Also, enterprise-wide models are popular for calculating profit margin at all
levels.
Commercial ABC/M software now enables consolidating some, and usually all, of
the local, children ABC/M models into the enterprise-wide, parent ABC/M model.
ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT
VI. An Example of Unitized Costs
C O S T
ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT
VII.Applications Of Local ABC/M
The objective of local ABC/M models is not to calculate the profit margins; it is to
compute the diverse costs of outputs to better understand how they create the
organization’s cost structure.
An interesting application is when marketing department is trying multiple tools,
such as newspapers, radio, television, tradeshows, Websites, ...etc.
C O S T
ABC/M calculation determine the costs versus benefits of all the channel
combinations to rank in order which are the least to best return on spending.
1. Cost Estimating
2. Process Product Manufacturing
3. Discrete Part Manufacturing
COST ESTIMATINGCOST ESTIMATING
C O S T
THANK YOU
C O S T

More Related Content

What's hot

Chap 5 Estimating Project Times
Chap 5 Estimating Project TimesChap 5 Estimating Project Times
Chap 5 Estimating Project Timesproject management
 
project cost management
project cost managementproject cost management
project cost managementjay mitkari
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgetingIzah Asmadi
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsEssam Lotffy, PMP®, CCP®
 
cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriaNewman Jonathan
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementHayat Denzi
 
Project Monitoring and Controlling Processes
Project Monitoring and Controlling ProcessesProject Monitoring and Controlling Processes
Project Monitoring and Controlling ProcessesNishant Munjal
 

What's hot (20)

Cost Control Process for Construction
Cost Control Process for ConstructionCost Control Process for Construction
Cost Control Process for Construction
 
Chap 5 Estimating Project Times
Chap 5 Estimating Project TimesChap 5 Estimating Project Times
Chap 5 Estimating Project Times
 
PMP_Economic Selection Criteria
PMP_Economic Selection CriteriaPMP_Economic Selection Criteria
PMP_Economic Selection Criteria
 
Project cost management
Project cost management Project cost management
Project cost management
 
Cost management
Cost managementCost management
Cost management
 
project cost management
project cost managementproject cost management
project cost management
 
CCP_SEC3_Planning and Scheduling
CCP_SEC3_Planning and SchedulingCCP_SEC3_Planning and Scheduling
CCP_SEC3_Planning and Scheduling
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slides
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
 
Cost management
Cost managementCost management
Cost management
 
cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeria
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project Monitoring and Controlling Processes
Project Monitoring and Controlling ProcessesProject Monitoring and Controlling Processes
Project Monitoring and Controlling Processes
 
CCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost ControlCCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost Control
 
Construction KPIs & Dashboards
Construction KPIs & DashboardsConstruction KPIs & Dashboards
Construction KPIs & Dashboards
 

Similar to CCP_SEC1_Cost

Preparation and approaches of cost estimates
Preparation and approaches of cost estimatesPreparation and approaches of cost estimates
Preparation and approaches of cost estimatesnagashree123
 
Strategic Cost Management – A Profitability Tool, Bp, Fla, November 20, 2010
Strategic Cost Management – A Profitability Tool, Bp, Fla, November 20, 2010Strategic Cost Management – A Profitability Tool, Bp, Fla, November 20, 2010
Strategic Cost Management – A Profitability Tool, Bp, Fla, November 20, 2010Barrett Peterson
 
Cost accounting intro
Cost accounting introCost accounting intro
Cost accounting intropooja yadav
 
Variance Analysis in Standard Costing
Variance Analysis in Standard CostingVariance Analysis in Standard Costing
Variance Analysis in Standard CostingVivek Mahajan
 
Engineering Design: Prototype to Product-Planning, Scheduling, Inventory Cost...
Engineering Design: Prototype to Product-Planning, Scheduling, Inventory Cost...Engineering Design: Prototype to Product-Planning, Scheduling, Inventory Cost...
Engineering Design: Prototype to Product-Planning, Scheduling, Inventory Cost...Naseel Ibnu Azeez
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation StepsSHAZEBALIKHAN1
 
IRJET- Cost Control Methods used in Construction Projects
IRJET- Cost Control Methods used in Construction ProjectsIRJET- Cost Control Methods used in Construction Projects
IRJET- Cost Control Methods used in Construction ProjectsIRJET Journal
 
Investigation on Cycle Time Reduction in Production and Implementation of an ...
Investigation on Cycle Time Reduction in Production and Implementation of an ...Investigation on Cycle Time Reduction in Production and Implementation of an ...
Investigation on Cycle Time Reduction in Production and Implementation of an ...IRJET Journal
 
ACTIVITY BASED COSTING
ACTIVITY BASED COSTINGACTIVITY BASED COSTING
ACTIVITY BASED COSTINGAKSHIT JAIN
 

Similar to CCP_SEC1_Cost (20)

Cost accounting 1
Cost accounting 1Cost accounting 1
Cost accounting 1
 
Pom1
Pom1Pom1
Pom1
 
Pom1
Pom1Pom1
Pom1
 
Preparation and approaches of cost estimates
Preparation and approaches of cost estimatesPreparation and approaches of cost estimates
Preparation and approaches of cost estimates
 
Strategic Cost Management – A Profitability Tool, Bp, Fla, November 20, 2010
Strategic Cost Management – A Profitability Tool, Bp, Fla, November 20, 2010Strategic Cost Management – A Profitability Tool, Bp, Fla, November 20, 2010
Strategic Cost Management – A Profitability Tool, Bp, Fla, November 20, 2010
 
Basics
BasicsBasics
Basics
 
CCP Material.pdf
CCP Material.pdfCCP Material.pdf
CCP Material.pdf
 
Basic cost concepts
Basic cost conceptsBasic cost concepts
Basic cost concepts
 
Cost accounting intro
Cost accounting introCost accounting intro
Cost accounting intro
 
CCP Material
CCP MaterialCCP Material
CCP Material
 
Preparing Cost Estimate for Manufactured Products.ppt-Aragaw-edited.pdf
Preparing Cost Estimate for Manufactured Products.ppt-Aragaw-edited.pdfPreparing Cost Estimate for Manufactured Products.ppt-Aragaw-edited.pdf
Preparing Cost Estimate for Manufactured Products.ppt-Aragaw-edited.pdf
 
UNIT-3.pptx
UNIT-3.pptxUNIT-3.pptx
UNIT-3.pptx
 
Variance Analysis in Standard Costing
Variance Analysis in Standard CostingVariance Analysis in Standard Costing
Variance Analysis in Standard Costing
 
Cost Accounting
 Cost Accounting  Cost Accounting
Cost Accounting
 
Engineering Design: Prototype to Product-Planning, Scheduling, Inventory Cost...
Engineering Design: Prototype to Product-Planning, Scheduling, Inventory Cost...Engineering Design: Prototype to Product-Planning, Scheduling, Inventory Cost...
Engineering Design: Prototype to Product-Planning, Scheduling, Inventory Cost...
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
 
IRJET- Cost Control Methods used in Construction Projects
IRJET- Cost Control Methods used in Construction ProjectsIRJET- Cost Control Methods used in Construction Projects
IRJET- Cost Control Methods used in Construction Projects
 
Investigation on Cycle Time Reduction in Production and Implementation of an ...
Investigation on Cycle Time Reduction in Production and Implementation of an ...Investigation on Cycle Time Reduction in Production and Implementation of an ...
Investigation on Cycle Time Reduction in Production and Implementation of an ...
 
ACTIVITY BASED COSTING
ACTIVITY BASED COSTINGACTIVITY BASED COSTING
ACTIVITY BASED COSTING
 
Material Management
Material ManagementMaterial Management
Material Management
 

More from Hisham Haridy MBA, PMP®, RMP®, SP®

Implication of economic conditions in changing project objectives (how to ada...
Implication of economic conditions in changing project objectives (how to ada...Implication of economic conditions in changing project objectives (how to ada...
Implication of economic conditions in changing project objectives (how to ada...Hisham Haridy MBA, PMP®, RMP®, SP®
 
Practical project risk management implementation challenges in saudi arabia
Practical project risk management implementation challenges in saudi arabiaPractical project risk management implementation challenges in saudi arabia
Practical project risk management implementation challenges in saudi arabiaHisham Haridy MBA, PMP®, RMP®, SP®
 

More from Hisham Haridy MBA, PMP®, RMP®, SP® (20)

Implication of economic conditions in changing project objectives (how to ada...
Implication of economic conditions in changing project objectives (how to ada...Implication of economic conditions in changing project objectives (how to ada...
Implication of economic conditions in changing project objectives (how to ada...
 
Implication of economic conditions in changing project objectives
Implication of economic conditions in changing project objectivesImplication of economic conditions in changing project objectives
Implication of economic conditions in changing project objectives
 
Practical project risk management implementation challenges in saudi arabia
Practical project risk management implementation challenges in saudi arabiaPractical project risk management implementation challenges in saudi arabia
Practical project risk management implementation challenges in saudi arabia
 
2_Project Scope Management
2_Project Scope Management2_Project Scope Management
2_Project Scope Management
 
1_Project Management Foundation
1_Project Management Foundation1_Project Management Foundation
1_Project Management Foundation
 
ERM overview
ERM overviewERM overview
ERM overview
 
CCP_SEC6_Economic Analysis Statistics and Probability and Risk
CCP_SEC6_Economic Analysis Statistics and Probability and RiskCCP_SEC6_Economic Analysis Statistics and Probability and Risk
CCP_SEC6_Economic Analysis Statistics and Probability and Risk
 
PMP_Project Integration Management
PMP_Project Integration ManagementPMP_Project Integration Management
PMP_Project Integration Management
 
1_PMI-RMP_Project Risk Management Plan
1_PMI-RMP_Project Risk Management Plan1_PMI-RMP_Project Risk Management Plan
1_PMI-RMP_Project Risk Management Plan
 
CCP_SEC5_ Project Management
CCP_SEC5_ Project ManagementCCP_SEC5_ Project Management
CCP_SEC5_ Project Management
 
CCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost EstimatingCCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost Estimating
 
CCP_introduction
CCP_introductionCCP_introduction
CCP_introduction
 
PMP_Professional and Social Responsibility
PMP_Professional and Social ResponsibilityPMP_Professional and Social Responsibility
PMP_Professional and Social Responsibility
 
PMP_Project Stakeholder Management
PMP_Project Stakeholder ManagementPMP_Project Stakeholder Management
PMP_Project Stakeholder Management
 
PMP_Project Procurement Management
PMP_Project Procurement ManagementPMP_Project Procurement Management
PMP_Project Procurement Management
 
PMP_Project Risk Management
PMP_Project Risk ManagementPMP_Project Risk Management
PMP_Project Risk Management
 
PMP_Project Communication Management
PMP_Project Communication ManagementPMP_Project Communication Management
PMP_Project Communication Management
 
PMP_Project Human Resources Management
PMP_Project Human Resources ManagementPMP_Project Human Resources Management
PMP_Project Human Resources Management
 
PMP_Project Quality Management
PMP_Project Quality ManagementPMP_Project Quality Management
PMP_Project Quality Management
 
PMP_Project Time Management
PMP_Project Time ManagementPMP_Project Time Management
PMP_Project Time Management
 

Recently uploaded

ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...AgileNetwork
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramCIToolkit
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证jdkhjh
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)jennyeacort
 

Recently uploaded (17)

ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
 

CCP_SEC1_Cost

  • 1. CCOSTOST Hisham Haridy, PMP, PMI-RMP, PMI-SPCCP_SEC 1
  • 2. 1. Cost Elements 2. Pricing and Costing 3. Materials CContentontent C O S T 4. Labor 5. Engineering Role and Project Success 6. Machinery, Equipment, and Tools 7. Economic Cost 8. Activity-Based Cost Management
  • 3. COST ELEMENTSCOST ELEMENTS 1. Cost The value of an activity or asset. 2. Cost Elements The value of the resources that are expended to complete the activity or produce the asset. Resources used are categorized as equipment, labor, material, and “other.” C O S T Material Labor Equipment
  • 4. Variable Fixed Must be provided and are dependent on the volume of work activity or asset production Must be provided independent of the volume of work, either direct or indirect. COST ELEMENTSCOST ELEMENTS 3. Cost Structuring Further structure the cost elements to: Understand how they influence activity cost . Get a better understanding of how they can be controlled. CostStructuring volume of work activity or asset production that they support. Examples the cost of Material, Labors , etc. volume of work, either direct or indirect. Examples set-up, Permit fees and Head office costs, etc. Direct Indirect The resources that are expended solely to complete the activity or asset. Examples concrete, labors, non reusable forms, and permit fees. The resources that need to be expended to support the activity or asset. Examples expenses for utilities, taxes, legal services, etc. CostStructuring C O S T
  • 5. COST ELEMENTSCOST ELEMENTS 4. Cost Center Groups of activities within a project that provide a convenient point for collecting and measuring costs. Profit Centers Investment C O S T Responsibility Centers Cost Centers Investment Centers
  • 6. 5. Cost Accounting The historical reporting of disbursements and costs and expenditures on a project. Steps: Classification can be done using the code of accounts or WBS or Activity- COST ELEMENTSCOST ELEMENTS Recording Classifying Summarizing Classification can be done using the code of accounts or WBS or Activity- Based Costing (ABC) 6. Code of Accounts All recorded cost elements are classified. Sometimes referred to as a chart of accounts or as cost code of accounts. A company’s code of accounts is configured to support the recording of cost data in the general ledger. C O S T
  • 7. COST ELEMENTSCOST ELEMENTS C O S T Typical Code of Accounts
  • 8. Financial Statements according to GAAP Income Statement (Statement of Operations) The Balance Sheet (Financial Position) Statement of Cash Flows COST ELEMENTSCOST ELEMENTS 7. Financial Reporting (Statement of Operations) (Financial Position) Revenue Expenses Profits Operation Investment Financing Assets Liabilities Equity Current Non-Current Current Non-Current Paid in Capital Retained Earnings C O S T
  • 9. 8. Assets Asset is an economic resource. Anything tangible or intangible that can be owned or controlled to produce value and that is held to have positive economic value is considered an asset. Simply stated, assets represent value COST ELEMENTSCOST ELEMENTS Simply stated, assets represent value of ownership that can be converted into cash (although cash itself is also considered an asset). C O S T Tangible Assets Intangible Assets Value is based on physical properties Examples; buildings, land, machinery Claim to future income Examples; various types of financial assets.
  • 10. 9. Cost Management A. Estimating Predicts the quantity and cost of resources needed to accomplish an activity or create an asset. A well-defined scope. A cost element structure. Historical cost data. COST ELEMENTSCOST ELEMENTS Historical cost data. B. Cost Trending Established from historical cost accounting information. How expenditures are trending relative to physical accomplishments. C. Cost Forecasting Much like estimates. An estimate is always for future activities and assets, and establishes the Budget at Completion (BAC) for performance baselines. C O S T
  • 11. COST ELEMENTSCOST ELEMENTS D. Life-Cycle Costing (LCC) The total cost to the organization for the ownership and acquisition of the product over its full life cycle. This is the concept of life cycle costing-looking at the cost of the whole life of the product, NOT just the cost of the project. Life-cycle cost include construction costs, operational and maintenance costs, taxes, financing, replacement and renovation.taxes, financing, replacement and renovation. C O S T Life-Cycle Cost Elements
  • 12. Costing Pricing Cost Estimating is the determination of approximately how much will it cost the performing organization to provide the product or service involved The determination of the amount to be charged to the client for the product or service. PRICING AND COSTINGPRICING AND COSTING 1. Costing Vs. Pricing Price = Cost + Profit Direct cost + Indirect cost + Overhead C O S T
  • 13. Inputs Transforming Mechanism Tools and Techniques Outputs 1. WBS/Scope 2. Historical Records (Historical data base management – Continuous 1. Costing and Pricing Strategies i. Cost estimating 1. Project Estimate 2. Project Acquisition 3. Business Decision PRICING AND COSTINGPRICING AND COSTING 2. The costing-Pricing Process management – Continuous improvement and Risk Mitigation) 3. Vendor Quotations i. Cost estimating ii. Budgeting iii. Cost forecasting 2. Financial Management i. Return on Investment ii. Return on Assets iii. Net Profit Margin 3. Business Decision C O S T
  • 14. PRICING AND COSTINGPRICING AND COSTING 3. Financial Management a. Return on investment (ROI) = [(Profit =(Project Outputs)- Project Costs (Inputs)] Project Costs (Inputs) Measures the profitability in dollars invested b. Net Profit Margin (NPM) = Net Income Total Revenue Measure of the effectiveness of a company at cost control c. Return on Assets (ROA) = Net Income Total Assets Depicts the efficiency with which management has used resources to generate income c. Assets Turnover = Total Revenue Total Assets Return on Assets (ROA) = Net Profit Margin X Assets Turnover C O S T
  • 15. PRICING AND COSTINGPRICING AND COSTING Return on investment (ROI)??? C O S T
  • 16. PRICING AND COSTINGPRICING AND COSTING Net Profit Margin (NPM)???? Return on Assets (ROA) ????? C O S T
  • 17. 1. Material Procurement Materials are one of the bulk sums in any project . If materials are not procured accurately ,it may have a significant bad effect to the project cost and performance. The five rights for material procurement MATERIALSMATERIALS C O S T Time Cost Quality Quantity Vendor
  • 18. 2. Materials Competition Competition factors including cost, availability, durability, weight, wear resistance, and ease-of-fabrication are among relevant considerations regarding choice of materials. Other items for consideration include: quality assurance/quality control, materials handling, and materials hazards. MATERIALSMATERIALS materials handling, and materials hazards. 3. Materials Handling A requirement of the production process. An inefficient materials handling system can slow production operations, creating other excessive costs as a result of production delays. C O S T
  • 19. These basic principles for material handling: MATERIALSMATERIALS 1. Material movement should be over the shortest distance possible. 2. Terminal time should be in the shortest time possible, since the objective is to move materials. 3. Eliminate manual material handling when mechanized methods are feasible. C O S T methods are feasible. 4. Avoid partial transport loads, since full loads are more economical. 5. Materials should be identifiable
  • 20. MATERIALSMATERIALS 4. Materials Handling Decisions There are four basic decision factors that affect materials handling. i. Type of material to be handled: Clay in loaders, structural steel by crane, liquids in pipelines. ii. Production system type: Job shop or batch process and continuous process. iii. Facility type: Low ceiling height, rectangular area, open area.iii. Facility type: Low ceiling height, rectangular area, open area. iv. Materials handling system costs: Initial Cost, lifecycle costs, disposal costs. C O S T
  • 21. MATERIALSMATERIALS Raw Materials Bulk Materials Fabricated Materials Engineered/ Designed Materials Materials utilized in a production or fabrication process Materials readily available with minimal lead times for order Bulk materials transformed into custom-fit items for a particular product or project. Materials require substantial work in order to attain their 5. Types of Materials and Related Information The most basic. Ex: Raw materials such as coal, limestone, etc. and delivery. EX: Steel Sheet, steel bars, steel pips..etc Ex: Steel pipe transformed by fabrication into custom dimensions for particular use. final form. EX: Pumps, motors, boilers, chillers, fans, compressors, etc. C O S T
  • 22. MATERIALSMATERIALS 5. Production Materials Purchase and Management i. Materials Quality Poor quality materials can result in product defects leading to increased costs. Higher-quality materials in excess of requirements will lead to excessive costs. ii. Materials Traceability & Vendor Surveillance Vendor surveillance may require periodic inspection at the vendors’ location.Vendor surveillance may require periodic inspection at the vendors’ location. Materials traceability is accomplished by means of Mill Certifications. iii. Materials Quantity Materials storage is a further burden that can exceed the value of the materials. Insufficient inventories may create dangers of “stock-outs” interrupting process. To balance these demands, determine Economic Order Quantity (EOQ) number. C O S T
  • 23. MATERIALSMATERIALS iv. Economic Order Quantity (EOQ) EOQ = (2 x D x P) / S Where: EOQ: The optimal order quantity (not function of item cost) D: Annual demandD: Annual demand S : Storage costs P : Purchase order costs which is setup cost (ordering, shipping, handling) not the cost of goods A garden tractor manufacturer has a requirement for 15,000 engines per year. The engines each cost $75. The order cost for a purchase order is $250. The storage costs for the engine are $12 per year, which includes space costs and financing costs. Economic Order Quantity (EOQ)??? C O S T
  • 24. MATERIALSMATERIALS v. Reorder Point Where: PR: Reorder point O: Order time R : Production rate I : Minimum inventory level or safety stock (RP) = (O x R) + I Assume that the production process uses 60 engines per day for the 60 garden tractors produced per day. If the lead time for an order is 5 days, and the safety stock level is 180 engines (minimum level), then the reorder formula in this example yields: Reorder Point (RP)??? C O S T
  • 25. MATERIALSMATERIALS vi. Just-In-Time Inventory Techniques The just-in-time concept implies that the exact material quantities needed are delivered at the exact time needed. The goal is to reduce inventories and the related costs, such as storage space. Traditional practices that focus on safety stocks can mask unprofitable variations in the production process.variations in the production process. By removing these safety stocks, the goal of just-in-time systems is a lean production process and an enhanced competitive position. The production facility therefore receives more frequent deliveries of smaller shipments on a periodic basis. C O S T
  • 26. MATERIALSMATERIALS C O S T Just-In-Time Inventory Techniques
  • 27. MATERIALSMATERIALS C O S T Lean Production Process
  • 28. MATERIALSMATERIALS viii. Expediting Non-standard and costly items A continual basis items A system of plans/specifications requirements and competitive bidding. A systems contract may be the best solution. vii. Individual Purchasing Orders and Systems Contracts Expediting involves the monitoring of all steps in the procurement cycle to ensure on-time delivery of the necessary materials. This monitoring includes checking design status, material status, production status, and shipping status. C O S T
  • 29. MATERIALSMATERIALS ix. Materials Inspection Inspections can range from simple visual methods to machine-assisted inspections incorporating techniques such as X-ray and ultrasonic technology to detect flaws. The goal is to ensure that the correct grade and quality of materials are being receivedand quality of materials are being received from suppliers. x. Global Materials Decisions Materials fabrication decisions, as to locations and methods, are being made on a global basis. Ex, Nike and Dell. C O S T
  • 30. MATERIALSMATERIALS 6. Plant Material Management Materials that are not incorporated into product or project. Instead assist in production operations. i. Specialized Plant Materials Such as replacement parts may be available only from the Original Equipment Manufacturer (OEM) and require significant lead time. ii. Plant Materials Benchmarkingii. Plant Materials Benchmarking Plant materials usage and longevity should be tracked through such measures as benchmarking. Benchmarking involves the examination of other organizations as to their practices 7. Safety Data Sheet and Hazard Communication Must be readily available and accessible to those dealing with hazardous materials as required by (OSHA). C O S T
  • 31. MATERIALSMATERIALS 8. Material Life Cycle All materials have a life cycle from initial development through to manufacture, incorporation in the product, and eventual disposal. i. Waste Materials Original materials cost. Handling costs. Disposal costs. ii. Surplus materials Excessive order. Change in material requirements. Incorrect quantity information. C O S T
  • 32. I. Labor Classification Labors are human resources and personnel performing in the activity or the project. LABORSLABORS Direct Labor Indirect Labor Overhead Labor Directly produce the product Not part of product but that are required to Allocated as a business expense independent of the volume ofproduct that are required to complete the project. independent of the volume of production. C O S T
  • 33. LABORSLABORS Base Wages Fringe Benefits Paid Time-Off (PTO) Medical and Life Insurance Benefits Government Mandated Benefits The amount that goes directly to the Labors are paid for local and national Some firms and labor contracts include Government retirement funds, unemployment II. Developing Labor Rates 1. Employees goes directly to the employee local and national holidays ,vacations and sick time contracts include contributions to a medical and life insurance program funds, unemployment insurance, retirement healthcare insurance C O S T
  • 34. LABORSLABORS Workshop An engineer gets 5 days of sick time, 10 days of vacation, and 10 holidays /year. 1. Calculate the adders cost If the nominal working time is 52 w/y , 40 h/w , 8 h/d 2. What is the real productive time? 3. What is the actual hour cost? If the firm contributes $500 per month for medical insuranceIf the firm contributes $500 per month for medical insurance 4. What is the added cost /h? If the firm contributes Retirement(6.2%), Retirement Medical (1.45%), State Unemployment (1.0%). 5. What is the added cost /h? 6. What is the total hourly cost? 7. What is the percentage of adders? C O S T
  • 36. LABORSLABORS 2. Engineering/Contractors Overhead and Profit When hiring contract employees, labor rates are usually broken down differently. i. Base wages, including fringes ii. Worker’s compensation (if applicable) iii. Overhead iv. Profit, (if applicable for time and material situations). 3. Fully Loaded or Billing Rate C O S T The base wage, plus adders. An owner pays for the worker’s time when he or she is on the job. 4. Overtime (PTO, insurance, and some governmental programs) are not added to overtime. Some other governmental retirements are usually added to overtime.
  • 37. LABORSLABORS 5. Weighted Average Rates/Crew Composite Rates The labor composite unit rate is used with unit rate cost estimating. We use composite labor rate and material, equipment and temporary construction materials to calculate an activity composite unit rate C O S T
  • 38. LABORSLABORS Workshop A contractor needs to make up time in the schedule. If the contractor works the concrete crew, 10 hours per day, Monday through Saturday for two weeks, how much extra will it cost the contractor? Overtime is paid for all hours over eight Monday through Friday, and the first eight hours on Saturday. Double-time is paid for hours greater than eight on Saturday and all Sunday work. Based on the following data, What is the average hourly cost of the crew? C O S T
  • 40. LABORSLABORS 6. Indirect and Overhead Labor There are two methods of determining Indirect and Overhead Labor costs i. To do a direct estimate of the indirect staff required and cost them out the same way as the direct work crews. ii. To use historical job percentages to determine an appropriate allowance for indirect labor. C O S T
  • 41. LABORSLABORS III. Productivity 1. Factors Affecting Productivity i. Union or non-union craft labor ii. Local Labors iii. Remote area and transportation iv. Weather conditions C O S T iv. Weather conditions v. Local holidays vi. Temporary living quarters vii. Overtime viii. Standard work hours and work days?
  • 42. 2. Learning Curve The concept of learning curve theory is ; If people do a job repeatedly, each time they double the number of times they repeat the job, the time to do the work is reduced by a constant percentage. LABORSLABORS C O S T
  • 43. LABORSLABORS 3. Productivity Improvement The opportunity to put in place procedures or make changes to improve productivity and minimize the cost of some of these factors. Shorten waiting time for a crew, material may be pre-staged at the work location. A manufacturing plant has the added benefit of more permanent personnel C O S T and the same physical location. Minimize the impact of adverse weather. Lean Management Training and team building.
  • 44. 4. Performance Monitoring i. Work Package/ WBS The required work hours for each work package or work breakdown structure. ii. Graphical Presentation of EV Data Graphical presentation of Earned Value analysis such as CPI, SPI, CV and SV. LABORSLABORS iii. Work Sampling C O S T iii. Work Sampling A method that can be used to determine production or unit rates for specific work activities.
  • 45. ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS Engineering is a key element toward the success of products and projects. Computerized techniques, such as CAD, BIM, simulation, and others, require significant upfront investments in software/training, but correctly applied have proven their worth in reducing overall costs toward the delivery of products and processes. Techniques including constructability, manufacturability, and value analysis have found use in this area. Process development: C O S T Research Design Construction
  • 46. ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS I. Product, Project, and Process Development 1. Pure and Applied Research In the development of products, organizations conduct research. The research can be divided into two types Pure or Basic Research Applied Research Involves work without a specific end The attempt to develop usable products or 2. Product, Project, and Process Life Cycles The life cycle of a particular product/project will have a significant influence on all design decisions, including producing plant and equipment. Civil infrastructure projects often have lives of many decades and should be designed for low-cost maintenance and upgrades. C O S T Involves work without a specific end product or use in mind. The attempt to develop usable products or add new feature-sets to existing products
  • 47. ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS 3. Computer-Aided Design (CAD)/Engineering (CAE) Utilization of computerized work stations and software to develop and analyze a product, project, or process design. C O S T 4. Computer-Aided Manufacturing (CAM) CAD/CAE ported directly into CAM software. Design is directly sent to machines like CNC Computer-numerically controlled
  • 48. ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS 5. Prototypes Developed prior to large-scale production i. Test designs ii. Test customer reaction. Prototype development is expensive, but is less expensive than discovered afterPrototype development is expensive, but is less expensive than discovered after numerous units are in customer hands. C O S T
  • 49. ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS 6. Patents and Trade Secrets Investments in new products and research are typically both expensive and time-consuming endeavors. This investment must receive protection. (20 years, 8 June 1995, WTO). Organizations can protect this investment through either patents or trade secrets. Organizations wishing to emulate patent’s provisions will develop different approach different or pay to the patent holder. Trade secrets can be somewhat broader than patent protection in that they protect both commercial and technical information from disclosure 7. Product Liability Those injured by a product can seek compensation for their damage. The tort law in this area has evolved over decades from a concept of “buyer beware” to a concept of “seller beware”. C O S T
  • 50. ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS II. Product, Project, and Process Design 1. Standardization The attempt to base product designs. The advantages are lower costs, shorter time, and maintenance personnel are more familiar. The disadvantage that If there is a flaw, it will be spread over a wide variety of products. 2. Process Selection Relates to production methods, continuous and discrete i. Continuous production methods such as petrochemical plants, power plants and manufacturers with assembly-line methods. It’s less expensive in the long run. ii. Discrete production such as pre-cast concrete plant, or structural steel fabrication shop. It has a higher labor factor. Favored where labor costs are less expensive. C O S T
  • 51. ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS 3. Manufacturability Slight modifications in a design that promote ease of product assembly without affecting the product that designs should be: i. Forgiving of minor inaccuracies ii. Easy to fabricate iii. Based on efficient utilization of labor, materials, and equipment 4. Constructability (BIM) The Counterpart of manufacturability applied to constructed projects to pinpoint problems before designs are developed to the point where changes create significant delays and associated costs. C O S T
  • 52. ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS 5. Make-or-Buy Decision Which items should be subcontracted out and which should be made in-house. Do organization’s quality and cost on an item can compete with outside suppliers. If trade secrets are involved, the decision will typically be to make the item, the goal is to enhance overall quality at a lower cost. It is better to "make" if: i. You have an idle plant or workforce. ii. You want to retain control. iii. The work involves proprietary information or procedures. C O S T
  • 53. (Operation) Total Cost “of equipment” $ Cost of rent equipment 1.5 M Example of resource equipment ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS (Asset) 1.5 M Quantity100,000 C O S T
  • 54. ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS III.Engineering Production/Construction 1. Production Health and Safety An accident results in the loss of a trained worker and an interruption in the process. Systems must be selected that reduce/eliminate the potential of accidents 2. Facility Layout Decisions as to arrangement, including equipment location, labor location, and services location. Layout decisions should always consider the potential impact of additional demand therefore considering future expansion. C O S T
  • 55. ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS 3. Assembly And Flow Process Charts Assist in planning the facility layout. They help to analyze production operations in terms of operations sequences performed, distances between operations, and operation time requirements. 4. Quantitative Analysis In Facility Layout. i. Linear programming is a mathematical technique that is widely used in finding optimal solutions to problems. ii. Monte Carlo techniques can be used to simulate wait time for a crane in a plant and its cost impact while data can be generated via computer programs with random number generators. C O S T
  • 56. ENGINEERING ROLE AND PROJECT SUCCESSENGINEERING ROLE AND PROJECT SUCCESS 5. Reengineering Redesign of process to achieve improvements such as cost, quality, service, and speed. Reengineering focuses on the optimization of the total organization, rather than sub-optimization of individual departments. Reengineering focuses on the “whys” of an action or process as opposed to the “hows”. C O S T
  • 57. MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS Equipment Value Categories Replacement cost (the cost new of an item having the same or similar utility) Reproduction Cost Market value (used equipment, secondary market value) Fair Market Value-in- Place C O S T Fair Value Fair Market Value-in- Exchange Orderly Liquidation Value Forced Liquidation Value Salvage Value/Part-Out Value Scrap Value
  • 58. MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS I. Equipment Value Categories Equipment values can be divided into two major categories: 1. Replacement cost (the cost new of an item having the same or similar utility) 2. Market value (used equipment, secondary market value) 1. Replacement cost (the cost new of an item having the same or similar C O S T 1. Replacement cost (the cost new of an item having the same or similar utility) i. Reproduction Cost The cost new of an identical item. ii. Fair Value Cost new of an item considering similar items cost, and taking into account utility and all standard adjustments and discounts to list price. $350,000
  • 59. MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS 2. Market value (used equipment, secondary market value) i. Fair market value in place The amount expressed in terms of money that may reasonably be expected to exchange between a willing buyer and a willing seller $250,000, 125% ii. Fair market value in exchange The amount expressed in terms of money that may reasonably be expected to C O S T The amount expressed in terms of money that may reasonably be expected to be exchanged in a third party transaction between a willing buyer and a willing seller (retail value) $200,000, 100% iii. Orderly Liquidated Value The estimated gross monetary amount that could typically be realized from a liquidation sale, given a reasonable period of time to find a purchaser. (wholesale value) $160,000 , 80%
  • 60. MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS iv. Forced Liquidated Value The amount expressed in terms of money that may reasonably be expected from a properly advertised and conducted auction where time is of the essence (blow-out value). $120,000, 60% v. Salvage value / part out value The amount expressed in terms of money that the buyer will pay to a seller, C O S T recognizing the component value of parts of the equipment that can be used or resold to end-users, usually for repair or replacement purpose $8,000, 4% vi. Scrap Value the estimated monetary amount that could be realized for the property if it were sold for its material content, not for productive use, as of a specific date value ie. $/ton of steel $2,000, 1%
  • 61. MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS Very Good (VG) Good (G) Fair (F) Poor (P) Scrap (X) Used with equipments with excellent appearance and Used with equipments that were modified or Used with equipments used at some point below its fully specified Used with equipments used at some point below its fully specified The equipment is no longer serviceable 3. Equipment Condition Terms and Definition Example C O S T appearance and being used to its full design specification without being modified or requiring any repairs modified or repaired and is being used at or near it fully specified utilization its fully specified utilization due to the effect of age or application. It may require some general repairs and replacement of some minor parts. its fully specified utilization that will require extensive repairs and/or replacement of major elements in the near future. serviceable and cannot be utilized to any practical degree.
  • 62. MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS I. Equipment Valuation 1. Residual Value Residual value is the salvage value of an asset. It represents the amount of value that the owner of an asset can expect to eventually obtain when the asset is disposition 2. Residual Value Determination Methods C O S T i. Income approach (present value of future cash flows) ii. Market approach (Trade data)
  • 63. MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS Normal Curve Disrupted-Market Regulatory Change Curve long-lived equipment, usually L-Shape. Usually U-Shape, results from equipment shortage or regulatory pressures causing suddenly deviation. Illustrates sudden impact on market value that regulation can cause. C O S T High Obsolescence Curve New Tax Law / High Inflation Curve Illustrates impact of technological obsolescence such as computers and high-tech equipment. Tax laws and inflation can cause a normal residual curve to rise in a short time.
  • 64. MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS 3. Variables That Affect Residual Value i. Initial Cost For residual purposes, the estimator should consider hard costs only. Hard cost includes a. The cost new equipment b. Items necessary to make it operate such as motors, electrical, and controls. C O S T controls. Soft costs should not be included such as foundations, freight, debugging, taxes, and installation. ii. Maintenance It can affect the useful life of equipment. In calculating a residual value, estimators must consider how the equipment will be maintained and/or the maintenance provisions in the lease
  • 65. MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS iii. Use, Wear, and Tear: Equipment in harsh service versus mild service can be substantial. Ex: hopper used in grain service lives 40 to 50 years. However, if used in salt service, their useful lives can be as short as 15 years. iv. Population This gives statistical significance to the residual value, because the value will be based on a large sample. C O S T be based on a large sample. v. Age Equipment presented as new in January 2012, could have a 2011 or 2010 build date. Both are new with the same condition but the price is different.
  • 66. MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS vi. Economy A used truck in a robust economy may be sold for lower price and longer time in a recession. Cost of money should also be calculated in the overall cost. vii. Changes in Technology An analysis of technological changes occurring over the past 20 years shows that future advances in technology were generally known at the time of lease C O S T that future advances in technology were generally known at the time of lease origination. Time necessary to “fix” an image from minutes to seconds. viii. Foreign Exchange Changes in foreign exchange value could affect selling / residual value, causing them to suddenly drop or increase. Strong foreign currency may rise the price of foreign equipment, which in turn, may pull residuals up, and vice versa
  • 67. MACHINERY, EQUIPMENT, & TOOLSMACHINERY, EQUIPMENT, & TOOLS ix. Tax Law Sometimes tax laws can affect new equipments price, hence affecting used equipment price. x. Legislation/Regulation Regulations may impact values in positive ways, however, the impact is often negative. xi. Equipment Location C O S T xi. Equipment Location Does the equipment required to be delivered to a prime market location or will it have to be sold in a remote area? xii. Method of Sale Price of cash sales will not be like installment sales.
  • 68. ECONOMIC COSTSECONOMIC COSTS Opportunity Costs Sunk Costs Book Costs Incremental Costs The foregone benefit by choosing one alternative over another. Funds already spent in by virtue of past decisions. Since these expenditures are in the past, by definition, they should The value of an item as reflected in the firm’s books. Book costs do not When comparing between many alternatives, cost differences I. Types of Costs C O S T over another. You have two projects to choose from: Project A with an NPV of $45,000 or Project B with an NPV of $85,000. What is the opportunity cost of selecting project B? past, by definition, they should not influence current decisions. Project A had initial budget of $ 1,000 out of which $ 800 has already been spent. To complete project A, we will need additional $ 500. Another Project B will require $ 1200 for completion. Which project do you want to select? Book costs do not represent cash flows and thus are not taken into account for economic analysis decisions. differences between them are called incremental costs. If two units have annual costs of $1,500, $1,800, then incremental cost difference is ….?.
  • 69. ECONOMIC COSTSECONOMIC COSTS Inflation Deflation Escalation Currency Variation A rise in the price level of a good or service, or market basket of goods and/or services A fall in the general price level for goods and services or a representative market A technique to accommodate price increases or decreases during A significant cost impact both on those inside the country as well as those outside II. Changes in Costs C O S T and/or services i. Money supply ii. Exchange rates iii. Demand-pull inflation iv. Cost-push inflation representative market basket of goods and services decreases during the life of the contract well as those outside the country.
  • 70. ECONOMIC COSTSECONOMIC COSTS Regulations Taxes Depreciation and Depletion Mandating certain actions by organizations Governments are most often maintained by the taxes that they impose. These taxes take many forms, such as income taxes, property taxes, inventory taxes, employment taxes, gross receipts taxes, and sales taxes Depreciation is a non-cash expense that reduces taxable III. Governmental Cost Impact C O S T organizations may or may not have an impact on costs. employment taxes, gross receipts taxes, and sales taxes Effective tax rates termed average tax rates are calculated for income taxation purposes by the percentage of total taxable income paid in taxes. The marginal tax rate is the tax rate on the next dollar of taxable income. Investment Tax Credits that governments may give firms tax credits to encourage economic activity. reduces taxable income. Depletion analogous to depreciation but for natural resources.
  • 71. IV. Depreciation Large assets (e.g., equipment) purchased by a company lose value over time. There are two forms of depreciation: 1. Straight Line Depreciation 2. Accelerated Depreciation Accelerated depreciation depreciates faster than straight line. Straight Line Depreciation Accelerated Depreciation ECONOMIC COSTSECONOMIC COSTS Straight Line Depreciation Accelerated Depreciation The same amount of depreciation is taken each year. D = (C - S) / N There are two forms: 1. Double Declining Balance D = ( 2 / N ) (BVt-1) 2. Sum of the Years Digits Dr = (C - S) x [ (N-r+1) / ((N(N + 1) /2 )] Example: A $1,000 item with a 10-year useful life and no salvage value (how much the item is worth at the end of its life) Would be depreciated at $100 per year. Example: A $1,000 item with a 10-year useful life and no salvage value (how much the item is worth at the end of its life) Would be depreciated at $180 the first year, $150 the second, $130 the next, etc. C O S T
  • 72. ECONOMIC COSTSECONOMIC COSTS Year Depreciation Formula Depreciation Amount Book Value 0 0 0 5000 Your company bought a new equipment with Life time =5years ,Initial cost =5,000, Salvage value =1,000. Find the equipment value throughout the life period. C O S T 1 (5000-1000)/5 800 4200 2 (5000-1000)/5 800 3400 3 (5000-1000)/5 800 2600 4 (5000-1000)/5 800 1800 5 (5000-1000)/5 800 1000 4000 Straight Line Depreciation
  • 73. ECONOMIC COSTSECONOMIC COSTS 3000 3500 4000 4500 5000 Depreciation Curve C O S T 0 500 1000 1500 2000 2500 0 1 2 3 4 5 Depreciation Curve Straight Line Depreciation
  • 74. Double Declining Balance Sum of the Years Digits A uniform rate of depreciation is applied annually to the undepreciated value as of the end of the previous year. The rate used is double the depreciation rate used in the The depreciation charge is calculated as follows: 1. Calculate the sum of years' digits as SYD= n(n+1/2). 2. For each year, calculate the sum of years' digits fraction as the ratio of the number of remaining ECONOMIC COSTSECONOMIC COSTS straight line method. In the first year, this depreciation rate is applied to the initial cost of the asset without subtracting the salvage value. 5 years, 100,000 (40%), 100,000 *40%, 60*40%, ..etc fraction as the ratio of the number of remaining years over the sum of years' digits. 3. Multiply the sum of years' digits fraction by depreciable cost. 4. 5years, (5+4+3+2+1), 5/15, 4/15, 3/15, 2/15, 1/15 C O S T
  • 75. ECONOMIC COSTSECONOMIC COSTS Your company bought a new equipment with Life time =5years ,Initial cost =5,000, Salvage value =1,000. Find the equipment value throughout the life period. Year Depreciation Formula Depreciation Amount Equipment Value Book Value C O S T 0 0 0 5000 5000 1 (2/5) (5,000-0) 2000 3000 3000 2 (2/5) (5,000-2,000) 1200 1800 1800 3 (2/5) (5,000-3,200) 720 1080 1080 4 (2/5) (5,000-3,920) 432 648 1000 5 (2/5) (5,000-4,352) 259.2 388.8 1000 Double Declining Balance
  • 76. ECONOMIC COSTSECONOMIC COSTS 3000 3500 4000 4500 5000 Depreciation Curve C O S T 0 500 1000 1500 2000 2500 0 1 2 3 4 5 Depreciation Curve Double Declining Balance
  • 77. ECONOMIC COSTSECONOMIC COSTS Your company bought a new equipment with Life time =5years ,Initial cost =5,000, Salvage value =1,000. Find the equipment value throughout the life period. Year Depreciation Formula Depreciation Amount Book Value 0 0 0 5000 C O S T 0 0 0 5000 1 (5/15) (5,000-1,000) 1333 3667 2 (4/15) (5,000-1,000) 1067 2600 3 (3/15) (5,000-1,000) 800 1800 4 (2/15) (5,000-1,000) 533 1267 5 (1/15) (5,000-1,000) 267 1000 Sum of the Years Digits
  • 78. ECONOMIC COSTSECONOMIC COSTS 2500 3000 3500 4000 4500 5000 Depreciation Curve Depreciation Curve C O S T Sum of the Years Digits 0 500 1000 1500 2000 2500 0 1 2 3 4 5 Depreciation Curve
  • 79. Another form of depreciation is called Units of Activity (or Production) In this method, the depreciation charge is calculated as follows: a. Divide the depreciable cost over the expected useful life of the asset (in hours, miles, or similar units) to obtain the depreciation rate per unit. b. At the end of each year, multiply the depreciation rate per unit by the actual usage during that year. In the units of activity (or production) method, the depreciation charge is not ECONOMIC COSTSECONOMIC COSTS In the units of activity (or production) method, the depreciation charge is not known in advance for each year. It is calculated after the conclusion of each year's activities. An organization, or an individual, may choose the depreciation method that best fits their business needs. In depreciating real estate, only the straight line method is allowed. An organization, or an individual, may switch the depreciation method, during the life of the asset, only once and only to the straight line method. C O S T
  • 80. V. Economic Analysis Techniques 1. Time Value of Money In order to compare different alternatives on the same basis, these cash amounts of income and expenditures must be set to equivalent terms. There will be an interest rate set which provides the common basis for calculations. When evaluating expected income/cost flows in the future, this interest rate can also be referred to as a “discount rate,” since money in the future is “worth” less than money in ECONOMIC COSTSECONOMIC COSTS the present. Common Language terms are; C O S T
  • 81. Economic Analysis Techniques Standard Formulas for Economic Analysis ECONOMIC COSTSECONOMIC COSTS C O S T
  • 82. i. Present Value (PV): The value today of future cash flows. This is the method of determining today’s value of future money. PV = FV (1+i)n Where: PV: Present Value FV: Future Value ECONOMIC COSTSECONOMIC COSTS Example What is the present value of $300,000 received three years from now if we expect the interest rate to be 10 percent? FV: Future Value i : Interest rate n : number of time periods PV = 300000 = $225,394 (1+0.1)3 C O S T
  • 83. ii. Net Present Value (NPV) The sum of the present value of all income and expenditures of a project. (> 0 is ok). It is the present value of the total benefits (income or revenue) minus the costs over many time periods. NPV= PV (all cash inflows) – PV (all cash outflows) FV ECONOMIC COSTSECONOMIC COSTS Example You have two projects to choose from. Project A will take three years to complete and has an NPV of $45,000. Project B will take six years to complete and has an NPV of $85,000. Which one would you prefer? Decision: Maximum NPV Project “B” NPV = ∑ FV - Initial Investment (1+i)n NPV = ∑ PVCF - II C O S T
  • 84. Time Income / Present Value of Income Present Value of Cost Example Cash flow as follow with interest 10%. NPV? 200 50 100 300 100 I or WACC= 10% 0 1 2 3 ECONOMIC COSTSECONOMIC COSTS NPV= 353 - 291 = $ 62 Time Period Income / Revenue Present Value of Income at 10% Interest Rate Costs Present Value of Cost at 10% Interest Rate 0 0 0 200 200 1 50 45 100 91 2 100 83 0 0 3 300 225 0 0 Total 353 291 Decision: Accepted C O S T
  • 85. iii. Capitalized Cost (CC) Capitalized cost (CC) represents the present sum of money that needs to be set aside now, at some interest rate, to yield the funds required to provide the service. A= P X I Where: P: Present Value i : Interest rate ECONOMIC COSTSECONOMIC COSTS Example A bridge is built for $5,000,000 and will have maintenance costs of $100,000 per year at 6%, what is the capitalized cost of service? i : Interest rate A : End of year payment of uniform amount series CC = 5,000,000 + 100,000 = $6,666,667 0.06 C O S T
  • 86. iv. Equivalent Uniform Annual Cost (EUAC) or Benefit It may be preferable to resolve the comparison to annual cash flow analysis. The comparison may be made on the basis of Equivalent Uniform Annual Cost (EUAC), Equivalent Uniform Annual Benefit (EUAB) or on the EUAB-EUAC difference. ECONOMIC COSTSECONOMIC COSTS EUAC = (P – S) (A/P, i, n) +SI Where: P: Present Value S: Salvage value Example A bridge Assume that the two units, Unit A and Unit B are compared on the basis of EUAC. Unit A has an initial cost of $20,000 and $3,000 salvage value, while Unit B has an initial cost of $15,000 and $2,000 salvage value. Unit A has a life of ten-years, whereas Unit B has a five-year life. Cost of capital is ten percent. C O S T S: Salvage value i : Interest rate A: Annuity n : number of time periods
  • 87. v. Rate of Return (ROR) Many organizations often set hurdle rates (benchmark rate of return) that a capital investment decision must achieve to be acceptable. In the case where investment funds are limited, projects with the highest ROR values can be selected. 0 = ∑ FV - Initial investment (1+i)n Where: ECONOMIC COSTSECONOMIC COSTS Project “Proceed” The NPV of the cost is set equal to the NPV of the benefit. The NPV Cost of Unit A versus Unit B is $10,000 ($20,000 - $10,000). The NPV of the Unit A – Unit B Benefit is $15,000. Example Unit A cost of $20,000 and Unit B of $10,000 and each 1-year life. Incremental benefit of $15,000 for A compared to B. Organization hurdle rate is 20%. Decision: ROR= 50% > 20%, investment Where: i : Rate of return C O S T
  • 88. vi. Payback Period The payback period is the length of time required to recover an initial investment through cash flows generated from the investment. The shorter the time period, the better the investment opportunity. Common use because it used be small and medium enterprises (represent 80% of the market). Payback period is THE LEAST precise of all capital budgeting methods because: 1. There is NO discounting involved, so the time value of money is completely ECONOMIC COSTSECONOMIC COSTS 1. There is NO discounting involved, so the time value of money is completely ignored. 2. The payback rule also fails to consider any risk differences (Calculated the same way for both very risky and very safe projects). Payback Period= Initial Investment (Annual cash inflows) C O S T
  • 89. Example A project costs $100,000 to implement and has annual net cash inflows of $25,000. Example Project A has an investment of $ 500,000 and payback period of 3 years. Payback Period= 100,000 = 4 years 25,000 ECONOMIC COSTSECONOMIC COSTS Project A has an investment of $ 500,000 and payback period of 3 years. Project B has an investment of $ 300,000 and payback period of 5 years. Using the payback period criteria, which project will you select? Project “A” Key selection: Lowest Payback period C O S T
  • 90. Example Example Years 0 1 2 3 4 Cash flow -1000 500 400 300 100 Net Cash flow -1000 -500 -100 200 300 Payback period = 2.33 years ECONOMIC COSTSECONOMIC COSTS Example Years 0 1 2 3 4 Cash flow -1000 100 300 400 600 Net Cash flow -1000 -900 -600 -200 400 Payback period = 3.33 years C O S T
  • 91. vii.Benefit Cost Ratio (BCR) A comparison of revenue to costs. Greater than 1 is good. BCR of > 1 means that benefits (i.e. expected revenue) is greater than the cost. Hence it is beneficial to do the project. BCR= Benefits (or Payback or Revenue) Costs ECONOMIC COSTSECONOMIC COSTS C O S T
  • 92. ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT Case Jon, Ian, Michel and Nancy order separate items for lunch. Jon’s order amounts to $14 Ian consumed $30 Michel’s order is $16 Nancy’s order is $24 C O S T Nancy’s order is $24 Total $84 What is the average cost per lunch? $84 ÷ 4 = $21 Jon and Michel are overcosted Jan and Nancy are undercosted
  • 93. ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT I. Overhead Expenses and Direct Expenses Overhead expenses have been displacing the recurring costs. Organizations have visibility of direct costs, but not have any insights into overhead or its reasons. Activity Based Cost Management can help provide for insights. C O S T Indirect Expenses are Displacing Direct Expenses
  • 94. ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT Activity-Based Management Activity-Based Costing Focuses on activities during production and performance process Improves the value received by customers Recognizes several levels of costs Accumulates costs into related cost pools Uses multiple cost drivers to assign C O S T Enhances profitability costs to products and services Cost Driver A factor that can causes a change in the cost of an activity. An activity can have more than one cost driver attached to it. For example, a production activity may have the following associated cost- drivers: a machine, machine operator(s), floor space occupied, power consumed, and the quantity of waste and/or rejected output.
  • 95. ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT C O S T Each Activity Has its Own Driver
  • 96. ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT II. Activities are Expressed with Action Verbs and Trace Expenses to Output General Ledger ABC/M Transaction - centric Work - centric Uses chart of accounts Uses chart of activities What was spent What it was spent for C O S T Records the expenses Calculates the costs of activities and unit cost Organized around cost centres to accumulate transactions into their accounts. But this format is deficient for decision support Describes activities using an “action verb- adjective-noun” format, such as inspect defective products, open new customer accounts
  • 97. ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT Cost Elements Activities Cost Object III. ABC/M is a Cost Re-assignment Network ABC re-assigns all of the costs into the final products, service lines, and customers. ABC cost re-assignment network consists of the three modules connected by cost assignment paths. C O S T Cost of a resource or input consumed by an activity. Aggregations of actions performed in an organization which are useful for ABC computations A product or department for which costs are accumulated or measured
  • 98. ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT C O S T
  • 99. ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT IV. Using The Attributes of Activity –Based Costing One role for calculating costs is to identify which activities are: 1. Not required and can be eliminated (Ex: Duplication of effort) 2. Ineffectively accomplished and can be reduced 3. Required to sustain the organization (not be possible to reduce or eliminate). 4. Discretionary and can potentially be eliminated (Ex: Annual employees’ picnic). Traditional methods do not provide any way to tag/highlight individual costs. C O S T Traditional methods do not provide any way to tag/highlight individual costs. ABC/M allow managers to differentiate activities from one another.
  • 100. ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT C O S T
  • 101. ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT V. Local vs. Enterprise-Wide ABC/M A common misconception is that ABC/M system must be enterprise-wide. However In practice, the majority of ABC/M is applied to subsets of the organization for process improvement rather than revenue enhancement. The local model is used for tactical purposes, often to improve productivity. In contrast, the enterprise-wide model is often used for strategic purposes because C O S T contrast, the enterprise-wide model is often used for strategic purposes because it helps focus on where to look for problems and opportunities. Also, enterprise-wide models are popular for calculating profit margin at all levels. Commercial ABC/M software now enables consolidating some, and usually all, of the local, children ABC/M models into the enterprise-wide, parent ABC/M model.
  • 102. ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT VI. An Example of Unitized Costs C O S T
  • 103. ACTIVITY BASED COST MANAGEMENTACTIVITY BASED COST MANAGEMENT VII.Applications Of Local ABC/M The objective of local ABC/M models is not to calculate the profit margins; it is to compute the diverse costs of outputs to better understand how they create the organization’s cost structure. An interesting application is when marketing department is trying multiple tools, such as newspapers, radio, television, tradeshows, Websites, ...etc. C O S T ABC/M calculation determine the costs versus benefits of all the channel combinations to rank in order which are the least to best return on spending.
  • 104. 1. Cost Estimating 2. Process Product Manufacturing 3. Discrete Part Manufacturing COST ESTIMATINGCOST ESTIMATING C O S T