SlideShare a Scribd company logo
1 of 35
Download to read offline
1
Design of Forebay
PRESENTED BY HADIQA QADIR
2K22-MS-HIE-02
CIVIL ENGINEERING DEPARTMENT (CED), UCE&T, BZU, MULTAN
2
OUTLINE Of The Topic
 Components Of Hydropower
 Introduction Of Forebay
 Function Of Forebay
 Components Of Forebay
 Hydraulic and Hydrological design aspects
 Design Flowchart
 Design Guidelines
 Design Steps
 Design Parameters
 Design Case I
 Design Case II
3
Components of Hydro Power System
The scheme in which water is supplied to hydro power system has the following components.
Main parts:
1. Head work
2. Intake structure
3. Head race (canal)
4. Forebay
5. Head pond
6. Penstock
7. Power house
8. Tail race
4
Introduction of Forebay
Forebay is a structure like a small reservoir located at the end
of the water passage from the reservoir and before the water is
fed to penstock.
We can define it as,
An impoundment immediately upstream of a diversion dam
or hydroelectric plant intake, where water is temporarily
stored before going into penstock.
5
Introduction of Forebay
 A forebay is required in the case of run-of river plants at the upstream of
diversion work.
 When canal leads water to the turbines the section of the canal in front of
turbines is enlarged to create forebay.
 The reservoir acts as forebay when penstock takes water directly from it.
 Some projects, such as those associated with a large dam having a deep
power intake, may have no specifically designed forebay. Again, other
projects may need more than one forebay; for example, a forebay at the
entrance to the headrace canal and a second forebay at the power intake at
the downstream end of the headrace canal
6
Introduction of Forebay
7
Introduction of Forebay
 The forebay temporarily stores water for supplying the same to the
turbines.
 The storage of water in forebay is decided based on required water
demand in that area. This is also used when the load requirement
in intake is less.
 It forms the transition between the reservoir or conveyance canal
and the power intake and as such is designed to facilitate the
necessary entry flow conditions at the power intake.
8
Components of Forebay
 Entrance Bay or Basin/Tank Body
 Escape weir/spillway
 Fine Trash rack
 Flushing gate
 Water level control system
 Penstock Inlet
9
spillway
Flushing Gate
10
Components of Forebay
Escape weir/spillway
 Spillway is constructed to act as a safety valve. It discharge the
overflow water to the d/s side when forebay is full. The preferred
location for the escape weir is in the rim of the forebay tank. Where this
is not practical for topographic reasons the escape weir should be
located at the nearest suitable site upstream of the forebay tank.
 A simple overflow weir is recommended with a design head that can be
contained within the normal canal freeboard. Weir discharge should be
routed towards a natural water course of adequate capacity or a ditch
provided that is suitably protected against erosion.
11
Components of Forebay
Fine Trash rack
The fine trash racks are used to protect the turbine from small debris. They
can also, in some cases, prevent fish or eel to pass through it.
Flushing Gate
The accumulated debris has to be flushed out from time to time. It is used
to facilitate flush out of any sediment or debris that might settle in the
bottom of the forebay tank and can be drawn in to the penstock. This can
be done by opening the flushing gate or valve. In this manner the material
is allowed to return to the river bed.
12
Components of Forebay
Water level control system:
A water level control system requires that real time water level
measurements in the forebay tank and tailrace canal be transmitted
to the turbine governor. In the water level control mode the governor
will estimate the inflow to the forebay tank and adjust the wicket
gates to correct for difference between turbine and canal flows so as
to maintain forebay tank levels within a prescribed range. A float
type water level gauge with electronic data transmitter is used for
this purpose.
13
Wicket gate is are the series of adjustable
vanes used to guide water in turbines.
Functions of Forebay
 Provide a volume of stored water to permit water level control of turbine operation.
 Reduces the entry of air into penstock pipe, which in turn could cause cavitation (explosion of the trapped
air bubbles under high pressure)
 Flow adjustment: the forebay tank and escape weir facilitate the adjustment of turbine discharge due to
system load changes by diverting surplus flow over the escape weir back into the river.
 Water level control: For small hydro plants connected to the grid it is convenient to match turbine output to
available flow, thereby maximizing use of available water.
14
Hydraulic and Hydrological design
aspects
 Fish exclusion
 Flow characteristics including flow patterns and velocity distribution in the forebay, and particularly at the
approach to the power plant intake.
 The submergence required at the intake and any depth requirements at sluiceways
 Minimization of hydraulic losses
15
Flow Chart to design forebay
16
 Submergence head is the minimum level of
water required above the penstock pipe to
prevent the entry of air into penstock pipes
 Retention time is the time during which
turbine will be shutdown and water will be
stored in forebay. It is taken as 3-4 minutes.
PLAN & SECTION OF FOREBAY
17
Design Guide Lines of Forebay
 The design discharge for power generation is linked to the turbine and the diameter of the pipe and the
velocity of the flow in the penstock linked to the penstock design.
 Set the width of the forebay. As a thumb rule, to start the design, it can be assumed that the length of the
forebay will be 2 to 2.5 times this size. However according to the required volume of water above the
penstock and to meet the site conditions the designer may have to change this ratio.
 Set the clearance of the penstock from the bottom of the forebay. This is to avoid that particles and
sediments settled in the forebay get in the penstock. The minimum clearance is 0.30 m. While, 0.50 to 1 m
is a common and reasonable value to use.
18
Design Guide Lines of Forebay
 For the design of the forebay it is considered that it should be available (to cope with the flow variations in
the turbine during normal operation conditions) a buffer volume equivalent to 15 seconds of supply at the
design flow. This is also automatically calculated as well as its corresponding depth of water.
 Set the discharger coefficient of the spillway. This depends on the shape of the crest and spillway.
 Set the depth of water over the crest of the spillway. Have in mind that the higher the water depth the
smaller will be the crest length of the spillway. The spillway is designed to spill all the design flow in
case the powerhouse is shut down and no flow is going through the penstock.
 Set the freeboard for the spillway. This is a safety margin in case higher flows than the design flow arrive
to the forebay. Consider a value that is half the water depth over the weir crest. This will increase, if
necessary, in 50% of the discharge capacity of the spillway
19
Design Guide Lines of Forebay
 The length of the spillway is automatically calculated using the previous input data and the weir equation.
It has to be noted that this value must be smaller than the length of the forebay.
 Note that the crest of the spillway will be placed 0.05 m above the Normal Water Level(NWL) so that
small changes in the flow or fluctuations or turbulence in the water surface (like wind) do not cause an
immediate spilling.
 The spillway should be sized such that it can release the entire design flow when required. This is because
if the turbine valve is closed during emergencies, the entire design flow will have to be spilled from the
forebay until the operator reaches the intake or other control structures upstream of the forebay.
20
Design Guide Lines of Forebay
 The trash rack at the forebay should be placed at 1:3 slope for both efficient hydraulic
performance and ease of cleaning.
 To minimize headless and blockage, the recommended velocity through the trash rack is 0.6 m/s.
but a maximum of 1 m/s could be used.
 Set the angle of the transition walls at the entrance of the penstock. This transition must be
smooth so mild angles are recommended (around 20%). However to fit site conditions the values
can be adjusted.
21
Design Steps of Forebay
Calculate
discharge
through
forebay
Assume
detention
time if not
given
Calculate
volume of
forebay
Assume
free
board
and
settling
Height
Calculate
submerge
nce head
above
penstock
Calculate
total
depth of
forebay
Calculate
width of
forebay
for normal
and worst
case
Calculate
length of
forebay
for total
head
22
FOREBAY DESIGN PARAMETERS
23
 Design Discharge = Qd
 Forebay Discharge= Qf = 2(Qd)
 Volume Of Forebay = V = Qf x t x 60
 Detention time = t (3-4 minutes)
 Limiting Velocity In Forebay = Vf (0.2-0.6 m/s)
 Submergence Head = Hs, Hs >1.5
𝑉𝑝2
2𝑔
Or 0.5 Vp 𝐷𝑝0.5
 Diameter of Penstock = Dp or 𝜑
 Total Head/ Depth Of Forebay = H = H-drawdown + Hs + dia of penstock
+ Freeboard + minimum bottom height H
 Total Head in worst condition = Hw = Hs + dia of penstock
 H-drawdown/H-downsurge = Vp
𝐿 𝐴𝑝
𝑔 𝐴𝑓
, but we will take it 0 in our design examples
Design Case-1
Design a forebay with Design discharge of 2mᶟ/s, flow is carried into a penstock of diameter 1.5m. Limiting velocity is
0.3m/s.
Solution
 Step1: Discharge through the forebay = Qf =2(Qd) = 2x2=4 mᶟ /s
Assume detention time, t = 3 min
 Step 2: Volume of forebay = V = Qf * t*60 = 4*3*60 =720 mᶟ
 Step 3: Determination of Total Head/depth of forebay = H-downsurge + Hs + Diameter of Penstock + Freeboard +
minimum bottom height
take Free board = 1m Settling height/Bottom height = 1m,
Diameter of Penstock = 1.5m (given)
24
Solution
 For Submergence Head, Hs
Hs >1.5
𝑽𝒑𝟐
𝟐𝒈
Or 0.5 Vp 𝑫𝒑𝟎.𝟓
(Select Greater Value)
Vp = Velocity In Penstock,
We Know that Q=A*V ; Area Of Penstock = (𝜋𝐷2
)/4 = 𝜋*1.52
/4 = 1.766m²
Vp = Qd/Ap = 2/1.766 =1.1325 m/s
Then, Hs is
=(1.5 *1.13^2)/(2*9.81)=0.0977m
Or
= 0.5*(1.13)*(1.5)^0.5=0.69m
25
Solution
Taking Greater Value,
Hs = 0.69m ≈ 0.7m
Also, assume H-downsurge = 0
 Total Head/depth of forebay = H-downsurge + Hs + Diameter of Penstock + Freeboard + minimum bottom
H = 0+0.7+1.5+1+1 = 4.2m
 Step 4: Determination of Forebay Width
For normal case B= Qf/(H*Vf) = 4/(4.2*0.3) =3.175m
Also assumed Vf = 0.3 m/s
For worst case
Total Head against worst cond = Hw = Hs + diameter of Penstoke = 0.7+1.5 = 2.2m
B՛ = Qf/(Hw*Vf) = 4/(2.2*0.3) = 6.06 m (Select greater value of B)
26
Solution
 Step 5 Determination of Length of forebay against worst case
L= volume/(Bw*H) = 720/(6.06*2.2) = 55m
Dimensions of forebay = (55m*6.06m*4.2m)
 Step 6 Determination of Spillway Length (Ls)
As we know that discharge eq for spillway is
Qf = Cd*L* (𝑯𝒄)𝟏.𝟓
Take head over crest of spillway, H-spillway = 0.5m, Cd = 1.7
So, Ls = Qf/(Cd*(𝑯𝒄)𝟏.𝟓
) = 4/(1.7*0.5^1.5) = 6.65m ≈ 7m
L-spillway < L-forebay
27
Solution
 Step 7: Design Check
Check 1 Since, L-spillway < L-forebay (OK)
Check 2: Let’s check for limiting velocity, for which forebay and
settling depth are not considered,
Vf = Qf/(Bw*Hw) = 4/(6.06*2.2) = 0.3 m/s (OK)
Note: Here “V” which we calculated is the average horizontal flow
velocity of the water inside the forebay after the water enters in the
forebay. It is the velocity of water along the length of forebay.
28
Design Case-2
Design a forebay with turbine discharge 12 m3/s. Water conveyed from forebay to powerhouse by 2
penstock of 2m diameter each. The retention time is 3 minutes and limiting velocity is 0.2m/s.
Solution
 Qd = 12 mᶟ/s
Diameter of penstock = 2m
Discharge in each penstock = qd = 12/2= 6mᶟ/s
Discharge for forebay = 2* Qd = 2*12 = 24mᶟ/s
Given retention time, t = 3 min
Area of penstock = Ap = (pi*2^2)/4 = 3.1415 m²
Velocity in penstock, Vp = qd/ap = 6/3.1415= 1.91m/s
Given Limiting velocity (Vf) = 0.2m/s
29
Solution
 Volume of forebay (V) = Qf *t*60
= 24*3*60 = 4320 mᶟ
 For height (H)
take Free board = 1m Settling height = 1m,
And submergence head, Hs
Hs >1.5
𝑉𝑝2
2𝑔
Or 0.5 Vp 𝐷𝑝0.5 (Select Greater Value)
Then, Hs is =(1.5 *1.91^2)/(2*9.81)=0.278m Or = 0.5*(1.91)*(2)^0.5=1.47m
Take greater value, Hs = 1.47m
30
Solution
 Total head/depth of forebay = H- downsurge + Hs + diameter of penstock + freeboard +minimum bottom
height
H = 0+1.47+2+1+1 = 5.47m
 For Width,
For normal case, B = Qf/(H*V) = 24/(5.47*0.2) = 21.937m
For worst case,
Total head against worst case= Hw = Hs + diameter of penstoke = 1.47+2 = 3.47m
B՛= Qf/(H*V) =24/(3.47*0.2) = 34.5 m
 For length
L= volume/(Bw*H) = 4320/(34.5*3.47) = 36m
Dimensions of forebay = (36m*34.5m*5.47m)
31
Solution
 For Length of spillway (Ls),
Qf = Cd*L* 𝑯𝒔𝟏.𝟓
Take head over crest for spillway= Hc = 0.5m
Coefficient of discharge = Cd = 1.7
Then, Ls = Qf/(Cd*𝑯𝒄𝟏.𝟓) = 24/(1.7*0.5^1.5) = 9.98m ≈ 10m
 Since, L-spillway < L-forebay (OK)
 Let’s check for limiting velocity, for which forebay and settling depth are not considered,
V = Qf/(Bw*Hw) = 24/(34.5*3.47) = 0.21 m/s > 0.2m/s (OK)
Note: Here “V” which we calculated is the average horizontal flow velocity of the water inside the forebay after the
water enters in the forebay. It is the velocity of water along the length of forebay.
32
Air Vent Pipe at inlet of penstock

33
References
 BPC Hydroconsult. (2012). Civil Works Guidelines for Micro-Hydropower in Nepal.
 Chow, V. T. (1959). Open-Channel Hydraulics. McGraw-Hill.
 Micro/Mini Hydropower Design Aspects, Micro/Mini Hydropower Design Aspects - Pakistan
Poverty ...www.ppaf.org.pk › hre › publications › vol 11 mhp design-final-05-12-13, Carlos Martins,
Ajoy Karki, Ulrich Frings, 2013.
34
35

More Related Content

What's hot (20)

Gravity dam
Gravity damGravity dam
Gravity dam
 
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
 
Design of gravity dams
Design of gravity damsDesign of gravity dams
Design of gravity dams
 
Stilling basin
Stilling basinStilling basin
Stilling basin
 
Canal regulation works. m4pptx
Canal regulation works. m4pptxCanal regulation works. m4pptx
Canal regulation works. m4pptx
 
5 Reservoir Planning
5 Reservoir Planning5 Reservoir Planning
5 Reservoir Planning
 
Classification of dams
Classification of damsClassification of dams
Classification of dams
 
Gravity Dam
Gravity DamGravity Dam
Gravity Dam
 
Reservoir capacity
Reservoir capacityReservoir capacity
Reservoir capacity
 
Reservoir Planning
Reservoir PlanningReservoir Planning
Reservoir Planning
 
Cross section of the canal, balancing depth and canal fsl
Cross section of the canal, balancing depth  and canal fslCross section of the canal, balancing depth  and canal fsl
Cross section of the canal, balancing depth and canal fsl
 
Canal irrigation
Canal irrigationCanal irrigation
Canal irrigation
 
river training work
river training workriver training work
river training work
 
Spillways
SpillwaysSpillways
Spillways
 
Spillways components and types
Spillways components and typesSpillways components and types
Spillways components and types
 
Hydraulics structures
Hydraulics  structuresHydraulics  structures
Hydraulics structures
 
Dam and types of dam with site selection
Dam and types of dam with site selectionDam and types of dam with site selection
Dam and types of dam with site selection
 
Design of barrages
Design of barragesDesign of barrages
Design of barrages
 
LIFT IRRIGATION SYSTEM
LIFT IRRIGATION SYSTEMLIFT IRRIGATION SYSTEM
LIFT IRRIGATION SYSTEM
 
Gravity dam stability analysis
Gravity dam stability analysisGravity dam stability analysis
Gravity dam stability analysis
 

Similar to Lec7. Design Of Forebay-1.pdf

hydro-electricpowerplant_NPS.pdf
hydro-electricpowerplant_NPS.pdfhydro-electricpowerplant_NPS.pdf
hydro-electricpowerplant_NPS.pdfNAVEENM849290
 
Hydro electric power plant lecture
Hydro electric power plant lectureHydro electric power plant lecture
Hydro electric power plant lecturec3b2a1
 
Basics of Hydro power plant
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant Prasad Vejendla
 
Malay nces ppt
Malay nces pptMalay nces ppt
Malay nces ppt9888437802
 
Canal regulation work 1
Canal regulation work 1Canal regulation work 1
Canal regulation work 1manjeet singh
 
2 c 9detentionstoragedesign
2 c 9detentionstoragedesign2 c 9detentionstoragedesign
2 c 9detentionstoragedesignSiam Kak
 
IES Academy Fluid Machine by S K Mondal.ppt
IES Academy Fluid Machine by S K Mondal.pptIES Academy Fluid Machine by S K Mondal.ppt
IES Academy Fluid Machine by S K Mondal.pptSubbuSuni
 
Hydraulic Ram Pumps - Technical Brief - Natural Resources Conservation Service
Hydraulic Ram Pumps - Technical Brief -  Natural Resources Conservation ServiceHydraulic Ram Pumps - Technical Brief -  Natural Resources Conservation Service
Hydraulic Ram Pumps - Technical Brief - Natural Resources Conservation ServiceFatin62c
 
Design Principles that are involved in the Design of Flow over an Ogee Crest ...
Design Principles that are involved in the Design of Flow over an Ogee Crest ...Design Principles that are involved in the Design of Flow over an Ogee Crest ...
Design Principles that are involved in the Design of Flow over an Ogee Crest ...Venkataraju Badanapuri
 
Canal outlets
Canal outletsCanal outlets
Canal outletssaibabu48
 
5. Conduits, Intake, Power house and Accessories.ppt
5. Conduits, Intake, Power house and Accessories.ppt5. Conduits, Intake, Power house and Accessories.ppt
5. Conduits, Intake, Power house and Accessories.ppthussenbelew
 
PLANNING & DESIGN OF LIFT IRRIGATION.pptx
PLANNING & DESIGN OF LIFT IRRIGATION.pptxPLANNING & DESIGN OF LIFT IRRIGATION.pptx
PLANNING & DESIGN OF LIFT IRRIGATION.pptxExeEnggManchannalaDi
 
Variable Headmeter
Variable HeadmeterVariable Headmeter
Variable HeadmeterShivang258
 
Presentation(Hydro Power Plant) (1).pptx
Presentation(Hydro Power Plant) (1).pptxPresentation(Hydro Power Plant) (1).pptx
Presentation(Hydro Power Plant) (1).pptxRajeshKumar590762
 
Elements of Water Conductor System
Elements of Water Conductor SystemElements of Water Conductor System
Elements of Water Conductor SystemSatish Taji
 
Official Final Report Volterix COMPLETE
Official Final Report Volterix COMPLETEOfficial Final Report Volterix COMPLETE
Official Final Report Volterix COMPLETEKyler Lucas
 

Similar to Lec7. Design Of Forebay-1.pdf (20)

hydro-electricpowerplant_NPS.pdf
hydro-electricpowerplant_NPS.pdfhydro-electricpowerplant_NPS.pdf
hydro-electricpowerplant_NPS.pdf
 
Hydro electric power plant lecture
Hydro electric power plant lectureHydro electric power plant lecture
Hydro electric power plant lecture
 
4 spillways
4 spillways4 spillways
4 spillways
 
Basics of Hydro power plant
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant
 
Malay nces ppt
Malay nces pptMalay nces ppt
Malay nces ppt
 
Canal regulation work 1
Canal regulation work 1Canal regulation work 1
Canal regulation work 1
 
2 c 9detentionstoragedesign
2 c 9detentionstoragedesign2 c 9detentionstoragedesign
2 c 9detentionstoragedesign
 
IES Academy Fluid Machine by S K Mondal.ppt
IES Academy Fluid Machine by S K Mondal.pptIES Academy Fluid Machine by S K Mondal.ppt
IES Academy Fluid Machine by S K Mondal.ppt
 
Hydraulic ram pumps
Hydraulic ram pumpsHydraulic ram pumps
Hydraulic ram pumps
 
Hydraulic Ram Pumps - Technical Brief - Natural Resources Conservation Service
Hydraulic Ram Pumps - Technical Brief -  Natural Resources Conservation ServiceHydraulic Ram Pumps - Technical Brief -  Natural Resources Conservation Service
Hydraulic Ram Pumps - Technical Brief - Natural Resources Conservation Service
 
Design Principles that are involved in the Design of Flow over an Ogee Crest ...
Design Principles that are involved in the Design of Flow over an Ogee Crest ...Design Principles that are involved in the Design of Flow over an Ogee Crest ...
Design Principles that are involved in the Design of Flow over an Ogee Crest ...
 
Canal outlets
Canal outletsCanal outlets
Canal outlets
 
5. Conduits, Intake, Power house and Accessories.ppt
5. Conduits, Intake, Power house and Accessories.ppt5. Conduits, Intake, Power house and Accessories.ppt
5. Conduits, Intake, Power house and Accessories.ppt
 
PLANNING & DESIGN OF LIFT IRRIGATION.pptx
PLANNING & DESIGN OF LIFT IRRIGATION.pptxPLANNING & DESIGN OF LIFT IRRIGATION.pptx
PLANNING & DESIGN OF LIFT IRRIGATION.pptx
 
Variable Headmeter
Variable HeadmeterVariable Headmeter
Variable Headmeter
 
Presentation(Hydro Power Plant) (1).pptx
Presentation(Hydro Power Plant) (1).pptxPresentation(Hydro Power Plant) (1).pptx
Presentation(Hydro Power Plant) (1).pptx
 
Elements of Water Conductor System
Elements of Water Conductor SystemElements of Water Conductor System
Elements of Water Conductor System
 
Hydrolic Power Plant
Hydrolic Power PlantHydrolic Power Plant
Hydrolic Power Plant
 
Pumping Stations
Pumping StationsPumping Stations
Pumping Stations
 
Official Final Report Volterix COMPLETE
Official Final Report Volterix COMPLETEOfficial Final Report Volterix COMPLETE
Official Final Report Volterix COMPLETE
 

Recently uploaded

Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 

Recently uploaded (20)

Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 

Lec7. Design Of Forebay-1.pdf

  • 1. 1
  • 2. Design of Forebay PRESENTED BY HADIQA QADIR 2K22-MS-HIE-02 CIVIL ENGINEERING DEPARTMENT (CED), UCE&T, BZU, MULTAN 2
  • 3. OUTLINE Of The Topic  Components Of Hydropower  Introduction Of Forebay  Function Of Forebay  Components Of Forebay  Hydraulic and Hydrological design aspects  Design Flowchart  Design Guidelines  Design Steps  Design Parameters  Design Case I  Design Case II 3
  • 4. Components of Hydro Power System The scheme in which water is supplied to hydro power system has the following components. Main parts: 1. Head work 2. Intake structure 3. Head race (canal) 4. Forebay 5. Head pond 6. Penstock 7. Power house 8. Tail race 4
  • 5. Introduction of Forebay Forebay is a structure like a small reservoir located at the end of the water passage from the reservoir and before the water is fed to penstock. We can define it as, An impoundment immediately upstream of a diversion dam or hydroelectric plant intake, where water is temporarily stored before going into penstock. 5
  • 6. Introduction of Forebay  A forebay is required in the case of run-of river plants at the upstream of diversion work.  When canal leads water to the turbines the section of the canal in front of turbines is enlarged to create forebay.  The reservoir acts as forebay when penstock takes water directly from it.  Some projects, such as those associated with a large dam having a deep power intake, may have no specifically designed forebay. Again, other projects may need more than one forebay; for example, a forebay at the entrance to the headrace canal and a second forebay at the power intake at the downstream end of the headrace canal 6
  • 8. Introduction of Forebay  The forebay temporarily stores water for supplying the same to the turbines.  The storage of water in forebay is decided based on required water demand in that area. This is also used when the load requirement in intake is less.  It forms the transition between the reservoir or conveyance canal and the power intake and as such is designed to facilitate the necessary entry flow conditions at the power intake. 8
  • 9. Components of Forebay  Entrance Bay or Basin/Tank Body  Escape weir/spillway  Fine Trash rack  Flushing gate  Water level control system  Penstock Inlet 9 spillway
  • 11. Components of Forebay Escape weir/spillway  Spillway is constructed to act as a safety valve. It discharge the overflow water to the d/s side when forebay is full. The preferred location for the escape weir is in the rim of the forebay tank. Where this is not practical for topographic reasons the escape weir should be located at the nearest suitable site upstream of the forebay tank.  A simple overflow weir is recommended with a design head that can be contained within the normal canal freeboard. Weir discharge should be routed towards a natural water course of adequate capacity or a ditch provided that is suitably protected against erosion. 11
  • 12. Components of Forebay Fine Trash rack The fine trash racks are used to protect the turbine from small debris. They can also, in some cases, prevent fish or eel to pass through it. Flushing Gate The accumulated debris has to be flushed out from time to time. It is used to facilitate flush out of any sediment or debris that might settle in the bottom of the forebay tank and can be drawn in to the penstock. This can be done by opening the flushing gate or valve. In this manner the material is allowed to return to the river bed. 12
  • 13. Components of Forebay Water level control system: A water level control system requires that real time water level measurements in the forebay tank and tailrace canal be transmitted to the turbine governor. In the water level control mode the governor will estimate the inflow to the forebay tank and adjust the wicket gates to correct for difference between turbine and canal flows so as to maintain forebay tank levels within a prescribed range. A float type water level gauge with electronic data transmitter is used for this purpose. 13 Wicket gate is are the series of adjustable vanes used to guide water in turbines.
  • 14. Functions of Forebay  Provide a volume of stored water to permit water level control of turbine operation.  Reduces the entry of air into penstock pipe, which in turn could cause cavitation (explosion of the trapped air bubbles under high pressure)  Flow adjustment: the forebay tank and escape weir facilitate the adjustment of turbine discharge due to system load changes by diverting surplus flow over the escape weir back into the river.  Water level control: For small hydro plants connected to the grid it is convenient to match turbine output to available flow, thereby maximizing use of available water. 14
  • 15. Hydraulic and Hydrological design aspects  Fish exclusion  Flow characteristics including flow patterns and velocity distribution in the forebay, and particularly at the approach to the power plant intake.  The submergence required at the intake and any depth requirements at sluiceways  Minimization of hydraulic losses 15
  • 16. Flow Chart to design forebay 16  Submergence head is the minimum level of water required above the penstock pipe to prevent the entry of air into penstock pipes  Retention time is the time during which turbine will be shutdown and water will be stored in forebay. It is taken as 3-4 minutes.
  • 17. PLAN & SECTION OF FOREBAY 17
  • 18. Design Guide Lines of Forebay  The design discharge for power generation is linked to the turbine and the diameter of the pipe and the velocity of the flow in the penstock linked to the penstock design.  Set the width of the forebay. As a thumb rule, to start the design, it can be assumed that the length of the forebay will be 2 to 2.5 times this size. However according to the required volume of water above the penstock and to meet the site conditions the designer may have to change this ratio.  Set the clearance of the penstock from the bottom of the forebay. This is to avoid that particles and sediments settled in the forebay get in the penstock. The minimum clearance is 0.30 m. While, 0.50 to 1 m is a common and reasonable value to use. 18
  • 19. Design Guide Lines of Forebay  For the design of the forebay it is considered that it should be available (to cope with the flow variations in the turbine during normal operation conditions) a buffer volume equivalent to 15 seconds of supply at the design flow. This is also automatically calculated as well as its corresponding depth of water.  Set the discharger coefficient of the spillway. This depends on the shape of the crest and spillway.  Set the depth of water over the crest of the spillway. Have in mind that the higher the water depth the smaller will be the crest length of the spillway. The spillway is designed to spill all the design flow in case the powerhouse is shut down and no flow is going through the penstock.  Set the freeboard for the spillway. This is a safety margin in case higher flows than the design flow arrive to the forebay. Consider a value that is half the water depth over the weir crest. This will increase, if necessary, in 50% of the discharge capacity of the spillway 19
  • 20. Design Guide Lines of Forebay  The length of the spillway is automatically calculated using the previous input data and the weir equation. It has to be noted that this value must be smaller than the length of the forebay.  Note that the crest of the spillway will be placed 0.05 m above the Normal Water Level(NWL) so that small changes in the flow or fluctuations or turbulence in the water surface (like wind) do not cause an immediate spilling.  The spillway should be sized such that it can release the entire design flow when required. This is because if the turbine valve is closed during emergencies, the entire design flow will have to be spilled from the forebay until the operator reaches the intake or other control structures upstream of the forebay. 20
  • 21. Design Guide Lines of Forebay  The trash rack at the forebay should be placed at 1:3 slope for both efficient hydraulic performance and ease of cleaning.  To minimize headless and blockage, the recommended velocity through the trash rack is 0.6 m/s. but a maximum of 1 m/s could be used.  Set the angle of the transition walls at the entrance of the penstock. This transition must be smooth so mild angles are recommended (around 20%). However to fit site conditions the values can be adjusted. 21
  • 22. Design Steps of Forebay Calculate discharge through forebay Assume detention time if not given Calculate volume of forebay Assume free board and settling Height Calculate submerge nce head above penstock Calculate total depth of forebay Calculate width of forebay for normal and worst case Calculate length of forebay for total head 22
  • 23. FOREBAY DESIGN PARAMETERS 23  Design Discharge = Qd  Forebay Discharge= Qf = 2(Qd)  Volume Of Forebay = V = Qf x t x 60  Detention time = t (3-4 minutes)  Limiting Velocity In Forebay = Vf (0.2-0.6 m/s)  Submergence Head = Hs, Hs >1.5 𝑉𝑝2 2𝑔 Or 0.5 Vp 𝐷𝑝0.5  Diameter of Penstock = Dp or 𝜑  Total Head/ Depth Of Forebay = H = H-drawdown + Hs + dia of penstock + Freeboard + minimum bottom height H  Total Head in worst condition = Hw = Hs + dia of penstock  H-drawdown/H-downsurge = Vp 𝐿 𝐴𝑝 𝑔 𝐴𝑓 , but we will take it 0 in our design examples
  • 24. Design Case-1 Design a forebay with Design discharge of 2mᶟ/s, flow is carried into a penstock of diameter 1.5m. Limiting velocity is 0.3m/s. Solution  Step1: Discharge through the forebay = Qf =2(Qd) = 2x2=4 mᶟ /s Assume detention time, t = 3 min  Step 2: Volume of forebay = V = Qf * t*60 = 4*3*60 =720 mᶟ  Step 3: Determination of Total Head/depth of forebay = H-downsurge + Hs + Diameter of Penstock + Freeboard + minimum bottom height take Free board = 1m Settling height/Bottom height = 1m, Diameter of Penstock = 1.5m (given) 24
  • 25. Solution  For Submergence Head, Hs Hs >1.5 𝑽𝒑𝟐 𝟐𝒈 Or 0.5 Vp 𝑫𝒑𝟎.𝟓 (Select Greater Value) Vp = Velocity In Penstock, We Know that Q=A*V ; Area Of Penstock = (𝜋𝐷2 )/4 = 𝜋*1.52 /4 = 1.766m² Vp = Qd/Ap = 2/1.766 =1.1325 m/s Then, Hs is =(1.5 *1.13^2)/(2*9.81)=0.0977m Or = 0.5*(1.13)*(1.5)^0.5=0.69m 25
  • 26. Solution Taking Greater Value, Hs = 0.69m ≈ 0.7m Also, assume H-downsurge = 0  Total Head/depth of forebay = H-downsurge + Hs + Diameter of Penstock + Freeboard + minimum bottom H = 0+0.7+1.5+1+1 = 4.2m  Step 4: Determination of Forebay Width For normal case B= Qf/(H*Vf) = 4/(4.2*0.3) =3.175m Also assumed Vf = 0.3 m/s For worst case Total Head against worst cond = Hw = Hs + diameter of Penstoke = 0.7+1.5 = 2.2m B՛ = Qf/(Hw*Vf) = 4/(2.2*0.3) = 6.06 m (Select greater value of B) 26
  • 27. Solution  Step 5 Determination of Length of forebay against worst case L= volume/(Bw*H) = 720/(6.06*2.2) = 55m Dimensions of forebay = (55m*6.06m*4.2m)  Step 6 Determination of Spillway Length (Ls) As we know that discharge eq for spillway is Qf = Cd*L* (𝑯𝒄)𝟏.𝟓 Take head over crest of spillway, H-spillway = 0.5m, Cd = 1.7 So, Ls = Qf/(Cd*(𝑯𝒄)𝟏.𝟓 ) = 4/(1.7*0.5^1.5) = 6.65m ≈ 7m L-spillway < L-forebay 27
  • 28. Solution  Step 7: Design Check Check 1 Since, L-spillway < L-forebay (OK) Check 2: Let’s check for limiting velocity, for which forebay and settling depth are not considered, Vf = Qf/(Bw*Hw) = 4/(6.06*2.2) = 0.3 m/s (OK) Note: Here “V” which we calculated is the average horizontal flow velocity of the water inside the forebay after the water enters in the forebay. It is the velocity of water along the length of forebay. 28
  • 29. Design Case-2 Design a forebay with turbine discharge 12 m3/s. Water conveyed from forebay to powerhouse by 2 penstock of 2m diameter each. The retention time is 3 minutes and limiting velocity is 0.2m/s. Solution  Qd = 12 mᶟ/s Diameter of penstock = 2m Discharge in each penstock = qd = 12/2= 6mᶟ/s Discharge for forebay = 2* Qd = 2*12 = 24mᶟ/s Given retention time, t = 3 min Area of penstock = Ap = (pi*2^2)/4 = 3.1415 m² Velocity in penstock, Vp = qd/ap = 6/3.1415= 1.91m/s Given Limiting velocity (Vf) = 0.2m/s 29
  • 30. Solution  Volume of forebay (V) = Qf *t*60 = 24*3*60 = 4320 mᶟ  For height (H) take Free board = 1m Settling height = 1m, And submergence head, Hs Hs >1.5 𝑉𝑝2 2𝑔 Or 0.5 Vp 𝐷𝑝0.5 (Select Greater Value) Then, Hs is =(1.5 *1.91^2)/(2*9.81)=0.278m Or = 0.5*(1.91)*(2)^0.5=1.47m Take greater value, Hs = 1.47m 30
  • 31. Solution  Total head/depth of forebay = H- downsurge + Hs + diameter of penstock + freeboard +minimum bottom height H = 0+1.47+2+1+1 = 5.47m  For Width, For normal case, B = Qf/(H*V) = 24/(5.47*0.2) = 21.937m For worst case, Total head against worst case= Hw = Hs + diameter of penstoke = 1.47+2 = 3.47m B՛= Qf/(H*V) =24/(3.47*0.2) = 34.5 m  For length L= volume/(Bw*H) = 4320/(34.5*3.47) = 36m Dimensions of forebay = (36m*34.5m*5.47m) 31
  • 32. Solution  For Length of spillway (Ls), Qf = Cd*L* 𝑯𝒔𝟏.𝟓 Take head over crest for spillway= Hc = 0.5m Coefficient of discharge = Cd = 1.7 Then, Ls = Qf/(Cd*𝑯𝒄𝟏.𝟓) = 24/(1.7*0.5^1.5) = 9.98m ≈ 10m  Since, L-spillway < L-forebay (OK)  Let’s check for limiting velocity, for which forebay and settling depth are not considered, V = Qf/(Bw*Hw) = 24/(34.5*3.47) = 0.21 m/s > 0.2m/s (OK) Note: Here “V” which we calculated is the average horizontal flow velocity of the water inside the forebay after the water enters in the forebay. It is the velocity of water along the length of forebay. 32
  • 33. Air Vent Pipe at inlet of penstock  33
  • 34. References  BPC Hydroconsult. (2012). Civil Works Guidelines for Micro-Hydropower in Nepal.  Chow, V. T. (1959). Open-Channel Hydraulics. McGraw-Hill.  Micro/Mini Hydropower Design Aspects, Micro/Mini Hydropower Design Aspects - Pakistan Poverty ...www.ppaf.org.pk › hre › publications › vol 11 mhp design-final-05-12-13, Carlos Martins, Ajoy Karki, Ulrich Frings, 2013. 34
  • 35. 35