SlideShare a Scribd company logo
1 of 3
Download to read offline
(CHSO)
Annexure 2
2015
Hitesh Dalpat Rathod
I.D number: G6856997
Construction Health and Safety Project report
Project Report
CHALLENGES
Based on the nine knowledge areas in construction Health and Safety, I will highlight the
challenges which I had faced over the 7 + years of my HSE career. Although for
Communication Management and Procurement Management I was not quite broadly
involved, I will give a brief explanation as to what challenges I could have encountered had I
been involved in those two knowledge areas.
Construction Health and Safety - Procurement Management
My biggest challenge for procurement would be relying on the suppliers to deliver the
equipment on time and when required. Usually there would either be a delay or shortage of
that particular equipment. Also too was the cost for some equipment which management
would feel an alternative would be less costly and thus purchasing equipment which is of a
cheaper quality. This would become a significant problem especially when the workforce
identify that the quality of equipment is poor and would make them feel that they are not
valued.
One other challenge was relying on the store controller to ensure that adequate amount of
stock was readily available especially at a peak in manpower.
Construction Health and Safety - Cost Management
When working for a smaller company in comparison to a larger company can be very
challenging when it comes to managing a budget. The budget is much smaller and it's
always more difficult to convince the management that spending can increase employee
morale. Having worked for a small construction company I learned that money is not easily
available and it made it harder to encourage the workforce to work towards achievement an
HSE milestone. Although when a budget is allocated for incentive schemes the workforce are
much more appreciative. Though sourcing items for workers performance on a very small
budget is really difficult.
Construction Health and Safety - Hazard Identification Management
When field supervision overlook hazards or don't take Note of hazards because of production
pressure became challenging due to the fact that I would have to monitor the activities more
frequently to ensure that the employees are working safely. It was never easy to control
hazards immediately when pressure was on production and this increased risk to the project
and to the workforce. When supplying field supervision with theme audits to conduct would
not always be done honestly and would become a paper exercise which would require me to
do more field verifications and rectify deviations myself. Employees not reporting hazards
would also become a challenge as employees would feel that they would get their
supervisors into trouble.
(CHSO)
Construction Health and Safety - Risk Management
The challenges faced with risk management was training and communicating the risk
assessments to the workforce where there was always a language barrier that made it
difficult for them to understand. Ensuring that a risk assessment is done effectively requires
involvement from certain individuals and at times due to pressure on the project a risk
assessment would end up being conducted by myself or with 2 or 3 involved parties making
the risk assessment not as adequate as it should be. Some field supervision do not like to
read and understand the risk assessments for their tasks and would often deviate from the
risk assessment process.
Construction Health and Safety - Accident / Incident Investigation Management
Interviewing witnesses would be one challenge I had to face as this process would become
lengthy when there was a language barrier. Gathering evidence would at times also be
difficult as some employees would tamper with a scene before I arrive to demarcate it off.
Some challenges I faced involved not being supplied with enough resources to conduct a
thorough investigation or not having important people required for the investigation available.
Having to compile all relevant incident investigation packs and submit to client would also
become difficult as some clients would demand the investigation be closed out soon as
possible where at times certain items which were difficult to obtain would delay the close out.
Putting corrective actions and preventative actions in place and ensuring that they were
effective was challenging because at times the field supervisors do not seem to change bad
habits they pick up and tend to allow same incidents to reoccur.
Construction Health and Safety - Legislations and Regulations
When it came to the legal side on a project the Construction Regulations 6.2 field supervision
tend not to fulfil all their legal requirements which places more pressure on me to
continuously emphasise the consequences if they do not fulfil their obligations. Based on
section 19 of the OHS Act 85 of 1993 One case I remember experiencing a challenge was
with the HSE committee meetings which were not being held monthly and the issue was
raised with the site manager and I was told that there is not enough time to hold these
meetings, or not everybody who needed to attend would be available for the meeting.
Another challenge I experienced was according to the section 8 of the Facilities Regulations
the seating arrangements for employees which were to be made available for the workforce
was not sufficient and the site manager did not want to spend any further to purchase more
table and chairs. On one project based on section 7 of the Facilities Regulation due to water
shortages there were days where drinking water was not available for workforce because the
mine had experienced a shortage supply which caused project delays.
Construction Health and Safety - Health, Hygiene and Environmental Management
There was one case where an employee was working on a project of mine and he had
collapsed while working on site because he suffered from epileptic seizures and did not
make mention of it on his medical history report which was a challenge as it came to my
knowledge that employees feared they wouldn’t be employed if they are honest about their
health conditions. Working in extreme heat conditions was also a challenge where the heat
reached a high of 42 Degrees Celsius, making the heat a huge risk factor and I had to
conduct extreme weather conditions management program that at times became very
challenging especially when the mine did not have sufficient water supply. One challenge I
had experienced was when our employees were suffering from food poisoning after eating
the mines food supplied to the workers. On the mine there was no running portable water
point for the workers to wash their hands after using the toilets and I had to request for the
company to have large water drums allocated on site. Waste removal was a big concern on
(CHSO)
one of my projects as the waste removal company was the only company on the mine which
caused a lot of waste to accumulate and become uncontrollable.
Construction Health and Safety - Communication Management
When the servers were down emailing became a challenge as it was difficult to communicate
certain items to the client and the company head office especially at a time when
documentation was urgently required. Working on a mine where the plant was built in the
middle of an open field there was continuous struggles with cellular phone reception which
made it difficult for my company head office to contact me.
Construction Health and Safety - Emergency Preparedness Management
The challenges faced in this Knowledge area was on one project we did not have enough
radios to communicate with the field supervision for me to coordinate the emergency
scenario effectively. On one project the plant production office struggled to provide all the
contractors with enough space to assemble when there was an emergency, which caused a
lot of problems when trying to account for all the people. At times the employees also don't
seem to actually take an emergency very serious and at times tend to take things very
gradual when evacuating the plant.
To conclude with my report these were the challenges which I had faced within the nine
knowledge areas. My intention here was to compress the main challenges I had experienced
into each knowledge area and not stray from the topic. For some areas where I was not very
involved in for example communication management, procurement management and cost
management I did manage/try and put myself into a scenario and put the challenges I may
have faced had I been involved in those areas.

More Related Content

What's hot

Safi-Ullah HSE Resume
Safi-Ullah HSE ResumeSafi-Ullah HSE Resume
Safi-Ullah HSE Resumesaif jutt
 
21 confined space working risk assessment templates
21 confined space working risk assessment templates21 confined space working risk assessment templates
21 confined space working risk assessment templatesDwarika Bhushan Sharma
 
CV HSE SUPERVISOR IN ENGLISH
CV HSE SUPERVISOR IN ENGLISHCV HSE SUPERVISOR IN ENGLISH
CV HSE SUPERVISOR IN ENGLISHwalid akermi
 
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdfRA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdfMohPhoolay
 
WORK AT HEIGHT PERMIT Form # HSEQ - WHP Rev.docx
WORK AT HEIGHT PERMIT Form # HSEQ - WHP Rev.docxWORK AT HEIGHT PERMIT Form # HSEQ - WHP Rev.docx
WORK AT HEIGHT PERMIT Form # HSEQ - WHP Rev.docxDwarika Bhushan Sharma
 
HSE Manager CV
HSE Manager CVHSE Manager CV
HSE Manager CVSony Mani
 
M. Ajmal CV (Field Safety Engineer - 11 Years)
M. Ajmal CV (Field Safety Engineer - 11 Years)M. Ajmal CV (Field Safety Engineer - 11 Years)
M. Ajmal CV (Field Safety Engineer - 11 Years)Muhammad Ajmal
 
Resume offshore field engineer
Resume offshore field engineerResume offshore field engineer
Resume offshore field engineerandi dipayadnya
 
Resume HSE Officer (Jitendra dubey)
Resume HSE Officer (Jitendra dubey)Resume HSE Officer (Jitendra dubey)
Resume HSE Officer (Jitendra dubey)Jitendra Dubey
 
Abdulla Safety Officer CV
Abdulla Safety Officer CVAbdulla Safety Officer CV
Abdulla Safety Officer CVAbdullah Hashmi
 
construction site safety and management
construction site safety and managementconstruction site safety and management
construction site safety and managementAnchal Gupta
 
Mr. fateh Sarhan corporate HSE Manager -update cv
Mr. fateh  Sarhan  corporate HSE Manager -update cvMr. fateh  Sarhan  corporate HSE Manager -update cv
Mr. fateh Sarhan corporate HSE Manager -update cvFateh Sarhan
 
Senior HSE Engineer with 17 years experiences
Senior HSE Engineer with 17 years experiencesSenior HSE Engineer with 17 years experiences
Senior HSE Engineer with 17 years experiencesMohammad Ansari
 

What's hot (20)

HSE Engineer Resume
HSE Engineer ResumeHSE Engineer Resume
HSE Engineer Resume
 
shamim ahmad HSE manager CV
shamim ahmad HSE manager CVshamim ahmad HSE manager CV
shamim ahmad HSE manager CV
 
Cv for safety officer
Cv for safety officerCv for safety officer
Cv for safety officer
 
Safi-Ullah HSE Resume
Safi-Ullah HSE ResumeSafi-Ullah HSE Resume
Safi-Ullah HSE Resume
 
21 confined space working risk assessment templates
21 confined space working risk assessment templates21 confined space working risk assessment templates
21 confined space working risk assessment templates
 
CV HSE SUPERVISOR IN ENGLISH
CV HSE SUPERVISOR IN ENGLISHCV HSE SUPERVISOR IN ENGLISH
CV HSE SUPERVISOR IN ENGLISH
 
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdfRA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
 
kabeer's CV
kabeer's CVkabeer's CV
kabeer's CV
 
JUSTICE HSE CV
JUSTICE HSE CVJUSTICE HSE CV
JUSTICE HSE CV
 
WORK AT HEIGHT PERMIT Form # HSEQ - WHP Rev.docx
WORK AT HEIGHT PERMIT Form # HSEQ - WHP Rev.docxWORK AT HEIGHT PERMIT Form # HSEQ - WHP Rev.docx
WORK AT HEIGHT PERMIT Form # HSEQ - WHP Rev.docx
 
HSE Manager CV
HSE Manager CVHSE Manager CV
HSE Manager CV
 
cv piping(1)
cv piping(1)cv piping(1)
cv piping(1)
 
M. Ajmal CV (Field Safety Engineer - 11 Years)
M. Ajmal CV (Field Safety Engineer - 11 Years)M. Ajmal CV (Field Safety Engineer - 11 Years)
M. Ajmal CV (Field Safety Engineer - 11 Years)
 
Resume offshore field engineer
Resume offshore field engineerResume offshore field engineer
Resume offshore field engineer
 
Resume HSE Officer (Jitendra dubey)
Resume HSE Officer (Jitendra dubey)Resume HSE Officer (Jitendra dubey)
Resume HSE Officer (Jitendra dubey)
 
safety officer cv 2
safety officer cv 2safety officer cv 2
safety officer cv 2
 
Abdulla Safety Officer CV
Abdulla Safety Officer CVAbdulla Safety Officer CV
Abdulla Safety Officer CV
 
construction site safety and management
construction site safety and managementconstruction site safety and management
construction site safety and management
 
Mr. fateh Sarhan corporate HSE Manager -update cv
Mr. fateh  Sarhan  corporate HSE Manager -update cvMr. fateh  Sarhan  corporate HSE Manager -update cv
Mr. fateh Sarhan corporate HSE Manager -update cv
 
Senior HSE Engineer with 17 years experiences
Senior HSE Engineer with 17 years experiencesSenior HSE Engineer with 17 years experiences
Senior HSE Engineer with 17 years experiences
 

Viewers also liked

Confirmation letter from SACPCMP
Confirmation letter from SACPCMPConfirmation letter from SACPCMP
Confirmation letter from SACPCMPDeon Strydom
 
Parte 7 métodos de tiragem 1 e 3 cartas
Parte 7   métodos de tiragem 1 e 3 cartasParte 7   métodos de tiragem 1 e 3 cartas
Parte 7 métodos de tiragem 1 e 3 cartasparoca6
 
HARASSMENT IN THE WORKPLACE_THE EFFECTS OF PYSCHOLOGICAL HARASSMENT AND BULLY...
HARASSMENT IN THE WORKPLACE_THE EFFECTS OF PYSCHOLOGICAL HARASSMENT AND BULLY...HARASSMENT IN THE WORKPLACE_THE EFFECTS OF PYSCHOLOGICAL HARASSMENT AND BULLY...
HARASSMENT IN THE WORKPLACE_THE EFFECTS OF PYSCHOLOGICAL HARASSMENT AND BULLY...Ian Manners
 
CDP Interview Guide
CDP Interview GuideCDP Interview Guide
CDP Interview GuideIan Manners
 
Trade Flow Analysis -Uzbekistan_final
Trade Flow Analysis -Uzbekistan_finalTrade Flow Analysis -Uzbekistan_final
Trade Flow Analysis -Uzbekistan_finalAriuntuya Tsend-Ayush
 
Fotorelacja z poznańskiej edycji Kobiecej Liderki (2015)
Fotorelacja z poznańskiej edycji Kobiecej Liderki (2015)Fotorelacja z poznańskiej edycji Kobiecej Liderki (2015)
Fotorelacja z poznańskiej edycji Kobiecej Liderki (2015)Sylwia Bogucka
 
Santa Maria Eufrasia
Santa Maria EufrasiaSanta Maria Eufrasia
Santa Maria Eufrasiaflor garcia
 
Trade Flow Analysis_Tajikistan_final
Trade Flow Analysis_Tajikistan_finalTrade Flow Analysis_Tajikistan_final
Trade Flow Analysis_Tajikistan_finalAriuntuya Tsend-Ayush
 
Trade Flow Analysis- Kyrgyzstan_final
Trade Flow Analysis- Kyrgyzstan_finalTrade Flow Analysis- Kyrgyzstan_final
Trade Flow Analysis- Kyrgyzstan_finalAriuntuya Tsend-Ayush
 
CEPH Consulting Presentation
CEPH Consulting PresentationCEPH Consulting Presentation
CEPH Consulting PresentationBill Papapetrou
 
M2 t1 planificador_aamticdoristeresalopez.docx (1)
M2 t1 planificador_aamticdoristeresalopez.docx (1)M2 t1 planificador_aamticdoristeresalopez.docx (1)
M2 t1 planificador_aamticdoristeresalopez.docx (1)DORIS TERESA LOPEZ LOTERO
 
Finalproject comm 303 zach
Finalproject  comm 303 zachFinalproject  comm 303 zach
Finalproject comm 303 zachztcann01
 
Kobieca Liderka w Krakowie
Kobieca Liderka w KrakowieKobieca Liderka w Krakowie
Kobieca Liderka w KrakowieSylwia Bogucka
 
Resume Shakil Ahmed Jul-2016
Resume Shakil Ahmed Jul-2016Resume Shakil Ahmed Jul-2016
Resume Shakil Ahmed Jul-2016Shakil Ahmed
 

Viewers also liked (18)

Confirmation letter from SACPCMP
Confirmation letter from SACPCMPConfirmation letter from SACPCMP
Confirmation letter from SACPCMP
 
Parte 7 métodos de tiragem 1 e 3 cartas
Parte 7   métodos de tiragem 1 e 3 cartasParte 7   métodos de tiragem 1 e 3 cartas
Parte 7 métodos de tiragem 1 e 3 cartas
 
HARASSMENT IN THE WORKPLACE_THE EFFECTS OF PYSCHOLOGICAL HARASSMENT AND BULLY...
HARASSMENT IN THE WORKPLACE_THE EFFECTS OF PYSCHOLOGICAL HARASSMENT AND BULLY...HARASSMENT IN THE WORKPLACE_THE EFFECTS OF PYSCHOLOGICAL HARASSMENT AND BULLY...
HARASSMENT IN THE WORKPLACE_THE EFFECTS OF PYSCHOLOGICAL HARASSMENT AND BULLY...
 
How to make drones at home
How to make drones at homeHow to make drones at home
How to make drones at home
 
CDP Interview Guide
CDP Interview GuideCDP Interview Guide
CDP Interview Guide
 
Trade Flow Analysis -Uzbekistan_final
Trade Flow Analysis -Uzbekistan_finalTrade Flow Analysis -Uzbekistan_final
Trade Flow Analysis -Uzbekistan_final
 
Fotorelacja z poznańskiej edycji Kobiecej Liderki (2015)
Fotorelacja z poznańskiej edycji Kobiecej Liderki (2015)Fotorelacja z poznańskiej edycji Kobiecej Liderki (2015)
Fotorelacja z poznańskiej edycji Kobiecej Liderki (2015)
 
Edgar allam
Edgar allamEdgar allam
Edgar allam
 
Santa Maria Eufrasia
Santa Maria EufrasiaSanta Maria Eufrasia
Santa Maria Eufrasia
 
Trade Flow Analysis_Tajikistan_final
Trade Flow Analysis_Tajikistan_finalTrade Flow Analysis_Tajikistan_final
Trade Flow Analysis_Tajikistan_final
 
ARTS: A Child & Youth Community Resource
ARTS: A Child & Youth Community ResourceARTS: A Child & Youth Community Resource
ARTS: A Child & Youth Community Resource
 
Blogger
Blogger Blogger
Blogger
 
Trade Flow Analysis- Kyrgyzstan_final
Trade Flow Analysis- Kyrgyzstan_finalTrade Flow Analysis- Kyrgyzstan_final
Trade Flow Analysis- Kyrgyzstan_final
 
CEPH Consulting Presentation
CEPH Consulting PresentationCEPH Consulting Presentation
CEPH Consulting Presentation
 
M2 t1 planificador_aamticdoristeresalopez.docx (1)
M2 t1 planificador_aamticdoristeresalopez.docx (1)M2 t1 planificador_aamticdoristeresalopez.docx (1)
M2 t1 planificador_aamticdoristeresalopez.docx (1)
 
Finalproject comm 303 zach
Finalproject  comm 303 zachFinalproject  comm 303 zach
Finalproject comm 303 zach
 
Kobieca Liderka w Krakowie
Kobieca Liderka w KrakowieKobieca Liderka w Krakowie
Kobieca Liderka w Krakowie
 
Resume Shakil Ahmed Jul-2016
Resume Shakil Ahmed Jul-2016Resume Shakil Ahmed Jul-2016
Resume Shakil Ahmed Jul-2016
 

Similar to PROJECT REPORT CHALLENGES Hitesh

Health and Safety - Responsibilities of employers’ and workers’ r for a safe ...
Health and Safety - Responsibilities of employers’ and workers’ r for a safe ...Health and Safety - Responsibilities of employers’ and workers’ r for a safe ...
Health and Safety - Responsibilities of employers’ and workers’ r for a safe ...anojan kanagarathnam
 
Fatality prevention and workforce safety- CHESM lessons learned and best prac...
Fatality prevention and workforce safety- CHESM lessons learned and best prac...Fatality prevention and workforce safety- CHESM lessons learned and best prac...
Fatality prevention and workforce safety- CHESM lessons learned and best prac...Kayode Aremu
 
Taking safety measures forward: Zero Incidents
Taking safety measures forward: Zero IncidentsTaking safety measures forward: Zero Incidents
Taking safety measures forward: Zero IncidentsGareth Ashworth
 
Pipeline Construction In Pursuit Of The Zero Accident Project
Pipeline Construction   In Pursuit Of The Zero Accident ProjectPipeline Construction   In Pursuit Of The Zero Accident Project
Pipeline Construction In Pursuit Of The Zero Accident ProjectPeter Kinsey
 
New Age HSE Services - Pics Auditing whitepaper
New Age HSE Services - Pics Auditing whitepaperNew Age HSE Services - Pics Auditing whitepaper
New Age HSE Services - Pics Auditing whitepapercraigwillis_newagehse
 
The factory case study
The factory case studyThe factory case study
The factory case studyVele Galovski
 
An assignment in risk management
An assignment in risk managementAn assignment in risk management
An assignment in risk managementWritingHubUK
 
CL-12 plus Safety 8-11-15
CL-12 plus Safety 8-11-15CL-12 plus Safety 8-11-15
CL-12 plus Safety 8-11-15Joseph Doherty
 
Pgpm12 human resource managment
Pgpm12 human resource managmentPgpm12 human resource managment
Pgpm12 human resource managmentsakariya88
 
Reduction of Un-safe Work Practices by Enhancing Shop floor Safety– A case study
Reduction of Un-safe Work Practices by Enhancing Shop floor Safety– A case studyReduction of Un-safe Work Practices by Enhancing Shop floor Safety– A case study
Reduction of Un-safe Work Practices by Enhancing Shop floor Safety– A case studyIJERA Editor
 
Building Operational Excellence in Petroleum Refining Training Course
Building Operational Excellence  in Petroleum Refining  Training CourseBuilding Operational Excellence  in Petroleum Refining  Training Course
Building Operational Excellence in Petroleum Refining Training CourseKarl Kolmetz
 
US5620 A3 2012002052 FS
US5620 A3 2012002052 FSUS5620 A3 2012002052 FS
US5620 A3 2012002052 FSPhillip Jonker
 
Procedure Based Maintenance White Paper
Procedure Based Maintenance White PaperProcedure Based Maintenance White Paper
Procedure Based Maintenance White PaperRicky Smith CMRP, CMRT
 
Running head DEEPWATER HORIZON INCIDENT CASE ANALYSIS .docx
Running head DEEPWATER HORIZON INCIDENT CASE ANALYSIS            .docxRunning head DEEPWATER HORIZON INCIDENT CASE ANALYSIS            .docx
Running head DEEPWATER HORIZON INCIDENT CASE ANALYSIS .docxtodd271
 
Occupational diseases caused by physical agents, chemical
Occupational diseases caused by physical agents, chemicalOccupational diseases caused by physical agents, chemical
Occupational diseases caused by physical agents, chemicalUniversidade Federal Fluminense
 
Honeywell forge-inspection-rounds-whitepaper
Honeywell forge-inspection-rounds-whitepaperHoneywell forge-inspection-rounds-whitepaper
Honeywell forge-inspection-rounds-whitepaperSoubhagya Panda
 
Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...
Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...
Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...Nippin Anand
 

Similar to PROJECT REPORT CHALLENGES Hitesh (20)

Health and Safety - Responsibilities of employers’ and workers’ r for a safe ...
Health and Safety - Responsibilities of employers’ and workers’ r for a safe ...Health and Safety - Responsibilities of employers’ and workers’ r for a safe ...
Health and Safety - Responsibilities of employers’ and workers’ r for a safe ...
 
Practical reliability
Practical reliabilityPractical reliability
Practical reliability
 
Fatality prevention and workforce safety- CHESM lessons learned and best prac...
Fatality prevention and workforce safety- CHESM lessons learned and best prac...Fatality prevention and workforce safety- CHESM lessons learned and best prac...
Fatality prevention and workforce safety- CHESM lessons learned and best prac...
 
Taking safety measures forward: Zero Incidents
Taking safety measures forward: Zero IncidentsTaking safety measures forward: Zero Incidents
Taking safety measures forward: Zero Incidents
 
Pipeline Construction In Pursuit Of The Zero Accident Project
Pipeline Construction   In Pursuit Of The Zero Accident ProjectPipeline Construction   In Pursuit Of The Zero Accident Project
Pipeline Construction In Pursuit Of The Zero Accident Project
 
New Age HSE Services - Pics Auditing whitepaper
New Age HSE Services - Pics Auditing whitepaperNew Age HSE Services - Pics Auditing whitepaper
New Age HSE Services - Pics Auditing whitepaper
 
Fenwick SHP0412
Fenwick SHP0412Fenwick SHP0412
Fenwick SHP0412
 
The factory case study
The factory case studyThe factory case study
The factory case study
 
An assignment in risk management
An assignment in risk managementAn assignment in risk management
An assignment in risk management
 
CL-12 plus Safety 8-11-15
CL-12 plus Safety 8-11-15CL-12 plus Safety 8-11-15
CL-12 plus Safety 8-11-15
 
Pgpm12 human resource managment
Pgpm12 human resource managmentPgpm12 human resource managment
Pgpm12 human resource managment
 
Reduction of Un-safe Work Practices by Enhancing Shop floor Safety– A case study
Reduction of Un-safe Work Practices by Enhancing Shop floor Safety– A case studyReduction of Un-safe Work Practices by Enhancing Shop floor Safety– A case study
Reduction of Un-safe Work Practices by Enhancing Shop floor Safety– A case study
 
Building Operational Excellence in Petroleum Refining Training Course
Building Operational Excellence  in Petroleum Refining  Training CourseBuilding Operational Excellence  in Petroleum Refining  Training Course
Building Operational Excellence in Petroleum Refining Training Course
 
US5620 A3 2012002052 FS
US5620 A3 2012002052 FSUS5620 A3 2012002052 FS
US5620 A3 2012002052 FS
 
Procedure Based Maintenance
Procedure Based MaintenanceProcedure Based Maintenance
Procedure Based Maintenance
 
Procedure Based Maintenance White Paper
Procedure Based Maintenance White PaperProcedure Based Maintenance White Paper
Procedure Based Maintenance White Paper
 
Running head DEEPWATER HORIZON INCIDENT CASE ANALYSIS .docx
Running head DEEPWATER HORIZON INCIDENT CASE ANALYSIS            .docxRunning head DEEPWATER HORIZON INCIDENT CASE ANALYSIS            .docx
Running head DEEPWATER HORIZON INCIDENT CASE ANALYSIS .docx
 
Occupational diseases caused by physical agents, chemical
Occupational diseases caused by physical agents, chemicalOccupational diseases caused by physical agents, chemical
Occupational diseases caused by physical agents, chemical
 
Honeywell forge-inspection-rounds-whitepaper
Honeywell forge-inspection-rounds-whitepaperHoneywell forge-inspection-rounds-whitepaper
Honeywell forge-inspection-rounds-whitepaper
 
Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...
Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...
Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...
 

More from HITESH RATHOD

More from HITESH RATHOD (8)

img587
img587img587
img587
 
PROJECT PROFILE ANNEXURE A2 KAMOTO Hitesh
PROJECT PROFILE ANNEXURE A2 KAMOTO HiteshPROJECT PROFILE ANNEXURE A2 KAMOTO Hitesh
PROJECT PROFILE ANNEXURE A2 KAMOTO Hitesh
 
img589
img589img589
img589
 
SHE ORGANOGRAM QATAR Construction
SHE ORGANOGRAM QATAR ConstructionSHE ORGANOGRAM QATAR Construction
SHE ORGANOGRAM QATAR Construction
 
img581
img581img581
img581
 
img578
img578img578
img578
 
img577
img577img577
img577
 
img576
img576img576
img576
 

PROJECT REPORT CHALLENGES Hitesh

  • 1. (CHSO) Annexure 2 2015 Hitesh Dalpat Rathod I.D number: G6856997 Construction Health and Safety Project report Project Report CHALLENGES Based on the nine knowledge areas in construction Health and Safety, I will highlight the challenges which I had faced over the 7 + years of my HSE career. Although for Communication Management and Procurement Management I was not quite broadly involved, I will give a brief explanation as to what challenges I could have encountered had I been involved in those two knowledge areas. Construction Health and Safety - Procurement Management My biggest challenge for procurement would be relying on the suppliers to deliver the equipment on time and when required. Usually there would either be a delay or shortage of that particular equipment. Also too was the cost for some equipment which management would feel an alternative would be less costly and thus purchasing equipment which is of a cheaper quality. This would become a significant problem especially when the workforce identify that the quality of equipment is poor and would make them feel that they are not valued. One other challenge was relying on the store controller to ensure that adequate amount of stock was readily available especially at a peak in manpower. Construction Health and Safety - Cost Management When working for a smaller company in comparison to a larger company can be very challenging when it comes to managing a budget. The budget is much smaller and it's always more difficult to convince the management that spending can increase employee morale. Having worked for a small construction company I learned that money is not easily available and it made it harder to encourage the workforce to work towards achievement an HSE milestone. Although when a budget is allocated for incentive schemes the workforce are much more appreciative. Though sourcing items for workers performance on a very small budget is really difficult. Construction Health and Safety - Hazard Identification Management When field supervision overlook hazards or don't take Note of hazards because of production pressure became challenging due to the fact that I would have to monitor the activities more frequently to ensure that the employees are working safely. It was never easy to control hazards immediately when pressure was on production and this increased risk to the project and to the workforce. When supplying field supervision with theme audits to conduct would not always be done honestly and would become a paper exercise which would require me to do more field verifications and rectify deviations myself. Employees not reporting hazards would also become a challenge as employees would feel that they would get their supervisors into trouble.
  • 2. (CHSO) Construction Health and Safety - Risk Management The challenges faced with risk management was training and communicating the risk assessments to the workforce where there was always a language barrier that made it difficult for them to understand. Ensuring that a risk assessment is done effectively requires involvement from certain individuals and at times due to pressure on the project a risk assessment would end up being conducted by myself or with 2 or 3 involved parties making the risk assessment not as adequate as it should be. Some field supervision do not like to read and understand the risk assessments for their tasks and would often deviate from the risk assessment process. Construction Health and Safety - Accident / Incident Investigation Management Interviewing witnesses would be one challenge I had to face as this process would become lengthy when there was a language barrier. Gathering evidence would at times also be difficult as some employees would tamper with a scene before I arrive to demarcate it off. Some challenges I faced involved not being supplied with enough resources to conduct a thorough investigation or not having important people required for the investigation available. Having to compile all relevant incident investigation packs and submit to client would also become difficult as some clients would demand the investigation be closed out soon as possible where at times certain items which were difficult to obtain would delay the close out. Putting corrective actions and preventative actions in place and ensuring that they were effective was challenging because at times the field supervisors do not seem to change bad habits they pick up and tend to allow same incidents to reoccur. Construction Health and Safety - Legislations and Regulations When it came to the legal side on a project the Construction Regulations 6.2 field supervision tend not to fulfil all their legal requirements which places more pressure on me to continuously emphasise the consequences if they do not fulfil their obligations. Based on section 19 of the OHS Act 85 of 1993 One case I remember experiencing a challenge was with the HSE committee meetings which were not being held monthly and the issue was raised with the site manager and I was told that there is not enough time to hold these meetings, or not everybody who needed to attend would be available for the meeting. Another challenge I experienced was according to the section 8 of the Facilities Regulations the seating arrangements for employees which were to be made available for the workforce was not sufficient and the site manager did not want to spend any further to purchase more table and chairs. On one project based on section 7 of the Facilities Regulation due to water shortages there were days where drinking water was not available for workforce because the mine had experienced a shortage supply which caused project delays. Construction Health and Safety - Health, Hygiene and Environmental Management There was one case where an employee was working on a project of mine and he had collapsed while working on site because he suffered from epileptic seizures and did not make mention of it on his medical history report which was a challenge as it came to my knowledge that employees feared they wouldn’t be employed if they are honest about their health conditions. Working in extreme heat conditions was also a challenge where the heat reached a high of 42 Degrees Celsius, making the heat a huge risk factor and I had to conduct extreme weather conditions management program that at times became very challenging especially when the mine did not have sufficient water supply. One challenge I had experienced was when our employees were suffering from food poisoning after eating the mines food supplied to the workers. On the mine there was no running portable water point for the workers to wash their hands after using the toilets and I had to request for the company to have large water drums allocated on site. Waste removal was a big concern on
  • 3. (CHSO) one of my projects as the waste removal company was the only company on the mine which caused a lot of waste to accumulate and become uncontrollable. Construction Health and Safety - Communication Management When the servers were down emailing became a challenge as it was difficult to communicate certain items to the client and the company head office especially at a time when documentation was urgently required. Working on a mine where the plant was built in the middle of an open field there was continuous struggles with cellular phone reception which made it difficult for my company head office to contact me. Construction Health and Safety - Emergency Preparedness Management The challenges faced in this Knowledge area was on one project we did not have enough radios to communicate with the field supervision for me to coordinate the emergency scenario effectively. On one project the plant production office struggled to provide all the contractors with enough space to assemble when there was an emergency, which caused a lot of problems when trying to account for all the people. At times the employees also don't seem to actually take an emergency very serious and at times tend to take things very gradual when evacuating the plant. To conclude with my report these were the challenges which I had faced within the nine knowledge areas. My intention here was to compress the main challenges I had experienced into each knowledge area and not stray from the topic. For some areas where I was not very involved in for example communication management, procurement management and cost management I did manage/try and put myself into a scenario and put the challenges I may have faced had I been involved in those areas.