RATE ANALYSIS
Introduction
What is Rate Analysis?
ā˜… Rate Analysis is the determination of rate per unit of a particular item of work from
the cost of materials, cost of labour and other miscellenious expenses requires its
completion is known as Analysis of Rate / Rate Analysis.
ā˜… Reasonable proļ¬t usually 10 % to 15 % for the contractor is also included to Rate
Analysis.
ā˜… Rate of materials are usually taken as the rates delivered at the site of work and
include the initial cost ( cost at origin) and also add transportation, freight charges if
any and any other taxes etc.,
ā˜… If the materials are to be carried from a distance place more than 8 km, then the
transportation cost is also included.
ā˜… The rates of materials and labour vary from place to place and therefore, the
rates of different items of works also vary from place to place.
Purpose of Rate Analysis:
- Main purpose of rate analysis are the following:
a) To determine the current rate per unit of an item at the locality.
b) To examine the viability of rates offered by contractors.
c) To calculate the quantity of materials and labour strength required for project
planning.
d) To ļ¬x up labour contract rates.
The rates of particular items of work depends on the following :-
1) Speciļ¬cations of works and materials, quality of material proportion of mortar,
methods of constructional operations etc.,
2) Quantity of materials and their rates, number of different types of labours and
their rates.
3) Location of the site of work and its distances from the sources of water
(construction of roads and irrigation)
4) Trafļ¬cs and miscellenious and overhead expenses of contractor.
Overhead Cost:
Overhead cost includes general ofļ¬ce expenses, rents, taxes, supervision costs and
other costs. Which are indirect expenses and not productive expenses on the job.
The miscellenious expenses are overheads may be under the following heads:
1) General Overheads -
a) Ofļ¬ce Staff
b) Stationary, Printing etc.,
c) Travelling expenses
d) Telephone costs
e) Rents and taxes
2) Job Overheads -
a) Salary of engineers, supervisors etc.,
b) Handling of materials
c) Repairs, carriage and appreciation of tools and plants
d) Amenities of labour
e) Workman insurance, compensation
f) Interest on instruments
ā˜… The contractor may be allowed a net proļ¬t of 6 - 8 % and miscellenious overhead
expenses may come to about 5 - 10 %.
ā˜… For overall expenses and contractor proļ¬t 15% of the actual cost may be
reasonable amount but it is usually practiced to add 10% for all these under the
head proļ¬t.
ā˜… The analysis of rate is usually worked out for the unit of payment of the
particular item of work under two heads.
(i) Material (ii) Labour
ā˜… The cost of materials are taken as delivery at site inclusive of the transportation,
local charges and other taxes.
ā˜… For tool and plants and miscellenious pity expenses which cannot be accounted
in details. Lump Sum provision is made.
Sl.
No
Particular of Item Quantity Per Day
1 Brickwork in lime or cement mortar in foundation and
plinth
1.25 MĀ³ Per Mason
2 Brickwork in lime or cement mortar in super structure 1 MĀ³ Per Mason
3 Brickwork in cement or lime mortar in arches 0.55 MĀ³ Per Mason
4 Brickwork in cement or lime mortar in jack arches 0.55 MĀ³ Per Mason
5 Half brick wall in partition 5 MĀ² Per Mason
6 Course rubble stone in lime or cement mortar including
dressing
0.80 MĀ³ Per Mason
7 Random Rubble stone in lime or cement mortar 1 MĀ³ Per Mason
8 Stone arch work 0.4 MĀ³ Per Mason
Sl.
No
Particular of Item Quantity Per Day
9 Lime concrete in foundation or floor 8.50 MĀ³ Per Mason
10 Lime concrete in roof terracing 6.0 MĀ³ Per Mason
11 Cement concrete M15 (1:2:4) 5.0 MĀ³ Per Mason
12 Reinforced Brickwork 1.0 MĀ³ Per Mason
13 R.C.C. Work 3.0 MĀ³ Per Mason
14 12 mm thick plastering with cement or lime mortar 8.0 MĀ² Per Mason
15 Pointing with cement or lime mortar 10.0 MĀ² Per Mason
16 White washing or colour washing - 3 coats 70.0 MĀ² Per white washer
17 White washing or colour washing - 1 coat 200.0MĀ² Per white washer
Sl.
No
Particular of Item Quantity Per Day
18 Painting of doors or windows - 1 coat 25.0 MĀ² Per Painter
19 Painting large surface - 1 coat 35.0 MĀ² Per Painter
20 Distempering - 1 coat 35.0 MĀ² Per Painter
21 2.5 cm C.C. Floor 7.50 MĀ² Per Painter
22 Brick ballast 40 mm gauge 0.75 MĀ³ Per Labourer
23 Breaking of brick ballast 25 mm gauge 0.55 MĀ³ Per Labourer
24 Breaking of stone ballast 40 mm (1 Ā½ ) gauge 0.40 MĀ³ Per Labourer
25 Breaking of stone ballast 25 mm (1ā€³) gauge 0.25 MĀ³ Per Labourer
26 Flagstone dressing 1.50 MĀ² Per Stone Cutter
Sl.
No
Particular of Item Quantity Per Day
27 Earthwork excavation in ordinary soils 3.00 MĀ³ Per Beldar/Mazdoor
28 Earthwork excavation in hard soils 2.00 MĀ³ Per Beldar/Mazdoor
29 Excavation in rock 1.00 MĀ³ Per Beldar/Mazdoor
30 Sand filling in plinth 4.00 MĀ³ Per Beldar/Mazdoor
31 No. of Bricks laid by a mason in brickwork upto a
height of 3 M
600 Bricks Per Mason
32
Amount of work done by a Mazdoor per day.
(i) Mix
(ii) Deliver Brick
(iii) Deliver Mortar
3 MĀ³
4000 Noā€™s
5.50 MĀ³
Mortar per Mazdoor
Per Mazdoor
Per Mazdoor
Labour Required for Different Works:
I. Earthwork per 28.30 Cu.m : -
1) Excavation in foundation, trenches etc., in ordinary soil including disposal upto 30 m
and lift of 1.5 m - 5 beldar, 4 mazdoor can do 28.30 cu .m of work per day.
2) Reļ¬lling excavated earth in foundation, plinth etc., including consolidation in 15 cm
layer - 3 beldars, 2 mazdoor and 1/2 Bisti can do 28.30 cu .m per day.
3) Disposal of surplus earth within a lead of 30 m that requires - 1 Mazdoor can do 2.83
cu . m per day.
II. Cement Concrete Work per 2.83 Cu . m : -
1) Laying of cement concrete requires - 2 beldars, 3 Mazdoors, 3/4 Bisti and 1/4 Mason
can do a 2.83 cu . m of work per day.
III. R. C. C. Work : -
1) Laying of Reinforced concrete requires - 3 Beldars, 3 Mazdoors, 4/3 Bisti and 1/2
Mason can do a 2.83 cu . m per day.
2) Centering and shuttering for ļ¬‚at surface requires - 4 Beldars and 4 Carpenters can do
9.60 Sq .m per day.
3) Reinforcement work for R.C.C requires - 1 Black smith , 1 Beldar can bend and place in
position one Quintal of steel.
IV. Stone Work for 2.83 cu . m : -
1) Random Rubble Masonry for foundation requires - 3 Masons, 3 Beldars, 2 Mazdoors and
1/4 Bisti can do 2.83 cu . m of work per day.
V. Brick Work for 2.83 cu . m : -
1) First Class Brickwork in 1:4 cement mortar in super structure, partition works, junctions
of roof, parapet wall etc., requires - 2 Ā¼ Masons, 4 Ā½ Mazdoors, and 1/2 Bisti can do
2.83 cu .m of work per day.
VI. Wood Work : -
1) For the frames of doors and windows - 2 Carpenters and 1 Beldar can work 0.18 cu . m
of wood equivalent to 4 door frames 7.50 X 10.00 cm of 1.20 m X 2.10 m per day.
2) For panel, glazed, shutters requires - 15 Carpenters and 4 Beldars can make and ļ¬x 4
shutters 40 mm thick of size 2 M X 1.15 M per day. Quantity of wood for shutter is
0.075 mĀ³.
VII. Iron Work : -
1) Fixing 40 mm X 3 mm X 38 cm ļ¬‚at iron fasteners requires - 1 Blacksmith, 1 Mason, 1
Beldar can ļ¬x 36 fasteners per day.
2) Fixing 16 mm dia mild steel rod requires - 1 Blacksmith, 2 Carpenters and 3 Beldars
can ļ¬x 16.50 m per day.
VIII. Flooring : -
1) 4 cm thick cement concrete ļ¬‚ooring of 40 Sq . m requires - 5 Masons, 4 Beldars, 3
Mazdoors and 1 Bisti per day. For mixing, laying and ļ¬nishing.
IX. Finishing : -
1) plastering with any mortar 12 mm thick requires - 3 Masons, 3 Mazdoors and 1
Bhisti can plaster 40 sq. m per day.
2) White Washing / Colour Washing ( 3 coats) requires - 1 White washer and 1
Mazdoor can do 60 sq. m per day.
3) Painting 2 coats on wood (or) steel requires - 3 Painters and 2 Mazdoors can paint
10 sq. m per day.
Rate of Material: ( Consider as per the local market)
Cement - ā‚¹. 350 / bag
Steel - ā‚¹. 45,000 / tonne
20 mm Coarse Aggregate - ā‚¹. 5,200 / unit
40 mm Coarse Aggregate - ā‚¹. 4,500 / unit
Bricks - ā‚¹ 4,500 / 1000 Noā€™s
Sand - ā‚¹. 3,500 / unit
Labour - 1st Class Mason - ā‚¹ 700 / day
Labour - 2nd Class Mason - ā‚¹. 500 / day
Man Mazdoor - ā‚¹. 350 / day
Women Mazdoor - ā‚¹. 250 / day
Lead Statement:
- The distance between the source of availability of material and construction site is
known as ā€œLeadā€ and is expected in Km. the cost of conveyance of material depends on
lead.
- This statement will give the total cost of materials per unit item. It includes initial cost,
conveyance loading, unloading, stacking charges etc.,
- The rate shown in the lead statement are for metalled road and include loading and
stacking charges.
- The environmental lead on the metalled roads are arrived by multiplying by a factor
a) For metal tracks - Lead X 1.0
b) For cartz tracks - Lead X 1.1
c) For sandy tracks - Lead X 1.4
1 Unit = 100 Cu feet = 2.83 Cu m
Unit weight of Steel = 7850 Kg / mĀ³
Unit weight of Cement = 1440 Kg / mĀ³
Unit weight of Fine Aggregate = 1450 to 1600 Kg/mĀ³
Unit weight of Coarse Aggregate = 1450 to 1500 Kg/mĀ³
1 Cu m of cement is how many bags?
1 Bag of Cement = 50 Kg
Density of Cement = 1440 Kg/mĀ³
1 Bag of cement Volume is---
1 mĀ³ bag has 1440 kg of cement
For 50 kg cement bag volume is 0.034 m
1/0.034 = 28.8 bags - Say 30 Bags.
Note: For 1 mĀ³ wet concrete = 1.52 mĀ³ dry volume of concrete approximately
Ex : M15 Grade 10 Cu m wet concrete material (1:2:4) but entire 52% to 54 %
of dry material will be added to it.
= 10.00 + 10.00 X (52 / 100)
= 10.00 + 5.20
= 15.20
1 Cu m of wet concrete in dry material is = 15.2/10 = 1.52
1 Cu m of wet concrete = 1.52 unit dry material.
M5 = 1:5:10 ( Cement : Sand : Aggregate)
M7.5 = 1:4:8 ( Cement : Sand : Aggregate)
M10 = 1:3:6 ( Cement : Sand : Aggregate)
M15 = 1:2:4 ( Cement : Sand : Aggregate)
M20 = 1:1.5:3 ( Cement : Sand : Aggregate)
M25 = 1:1:2 ( Cement : Sand : Aggregate)
Consider for 10 mĀ³ M5 (1:5:10)
15.20/16 = 0.95 cu m
Cement = 0.95x1 = 0.95 = 0.95 X 1440 = 1368 kg = 1368/50 = 27.36 bags
Sand = 0.95 X 5 = 4.75 Cu m
Coarse Aggregate = 0.95 x 10 =9.50 Cu m
Cost of Cement = 27.36 X 350/bag = ā‚¹. 9576.00
Cost of F.A / Sand = 4.75 X 1236.75/Cu m = ā‚¹. 5874.56
Cost of C . A = 9.50 X 1590.11/ cu m = ā‚¹. 15106.04
M7.5 ( 1:4:8) Calculate for the 10 cu m
15.20/(1+4+8) = 15.20/13 = 1.17 Cu m
Cement = 1.17x1 = 1.17 cu m = 1.17x 1440 = 1684.8 /50 = 33.70 Bags
Sand = 1.17 x 4 = 4.68 Cu m
C.A = 1.17 x 8 = 9.36 cu m
Cost of the Materials:
Cement = 33.70 x 350 = ā‚¹. 11795.00
Sand/ F.A = 4.68 x 1236.75 = ā‚¹. 5787.99
C.A = 9.36 x 1590.11 = ā‚¹. 14883.43
M10 (1:3:6) Consider 10 cu m
15.20 / 10 = 1.52 cu m
Quantity of the Materials:
Cement = 1.52 Cu m = 1.52 x 1440 = 2188.80 Kgā€™s = 2188.8/50 = 43.78 Baga
Sand = 1.52 x 3 = 4.56 cu m
C.A = 1.52 x 6 = 9.12 cu m
Cost of Material:
Cement = 43.78 x 350 = ā‚¹. 15323.00
Sand = 4.56 x 1236.75 = ā‚¹. 5639.58
C.A = 9.12 x 1590.11 = ā‚¹. 14501.80
M15 ( 1:2:4) Consider for 10 Cu m.
15.20/7 = 2.17 cu m
Quantity of Material:
Cement = 2.17 cu m = 2.17 x 1440 =3124.80 kg = 3124.8/50 = 62.50 Bags
Sand= 2.17 x 2 = 4.34 cu m
C.A = 2.17 x 4 = 8.68 cum
Cost of Materials:
Cement = 62.50 x 350 = ā‚¹. 21875.00
Sand = 4.34 x 1236.75 = ā‚¹. 5367.49
C.A = 8.68 x 1590.11 = ā‚¹. 13802.15
M 20 (1:1.5:3) - Consider 10 Cu m
15.2/1+1.5+3) = 15./ 5.5 = 2.76 cu m
Quantity of the materials:
Cement = 2.76x1 = 2.76 cu m = 2.76 x 1440 = 3974.40kg = 79.50 bags
Sand = 2.76 x 1.5 = 4.14 cu m
C.A = 2.76 x 3 = 8.28 cu m
Cost of the Materials:
Cement = 79.50 bags x 350/bag = 27825.00/ 10 cu m = 2782.50/ cu m
Sand = 4.14 x 1236.75 = 5120.14 / 10 cu m = 512.00 / cu m
C.A = 8.28 x 1590.11 = 13166.00/ 10 cu m = 1316.60/ cu m
M25 ( 1:1:2) Consider 10 Cu m
15.20/4 = 3.80 cu m
Quantity of the Materials:
Cement = 3.80 cu m = 3.80 x 1440 = 5472 kgs = 109.44 Bags
Sand/ F.A = 3.80 x 1 = 3.80 cu m
C.A = 3.80 x 2 = 7.60 cu m
Cost of the Materials:
Cement = 109.44 x 350/bag = 38304.00/10 cu m = 3830.40/ 1 cu m
Sand/ F.A = 3.80 x 1236.75 = 4699.65/10 cu m = 470.00/ 1 cu m
C.A = 7.60 x 1590.11 = 12084.83/ 10 cu m = 1208.48 / 1 cu m
Example - 1.
Calculate the cost of the concrete of M5 grade, take 10 cu m and ļ¬nd the 1 cu m cost?
1st class mason - 0.5 Noā€™s
2nd Class Mason - 1.5 Noā€™s
Man Mazdoor - 12 Noā€™s
Women Mazdoor - 18 Noā€™s and
Curing purpose - 4 Noā€™s
Assume water charges 1 Ā½ % of total cost and Contractor proļ¬t is 15% of the total cost.
Solution:
For M5 Grade of Concrete mix proportion is 1:5:10
15.2/(1+5+10) = 15.2/16 = 0.95 mĀ³
Sl.
No
Particulars Quantity Rate in ā‚¹. Per
unit
Amount in ā‚¹.
1 Materials
Cement
Fine Aggregate/Sand
Coarse Aggregate
0.95 x 1 = 0.95 mĀ³
0.95 x 1440 = 1368 kgā€™s
1368/50 = 27.36 bags
0.95 x 5 = 4.75 mĀ³
0.95 x 10 = 9.50 mĀ³
350/-
1236.75
1590.11
Bag
MĀ³
mĀ³
9576.00
5874.56
15106.04
2 Labour
1st Class Mason
2nd Class Mason
Man Mazdoor
Women Mazdoor
Curing purpose
0.5
1.5
12
18
4
700
500
350
250
250
Day
Day
Day
Day
Day
350.00
750.00
4200.00
4500.00
1000.00
TOTAL COST ā‚¹. 41356.60
Add water charges (1 Ā½ %) of total cost.
= ā‚¹. 41,356.60 X (1.5/100) = 620.35 Say ā‚¹, 620/-
= ā‚¹. 620.00
Add Contractor Proļ¬t (15%) of total cost.
= ā‚¹. 41,356.60 X (15/100) = 6203.49 Say ā‚¹. 6203.00
= ā‚¹. 6203.00
Total Cost = ā‚¹. 41,356.60 + 620.00 + 6203.00 = ā‚¹. 48,179.60
Sundries = ā‚¹. 820.40
Total Cost for 10 mĀ³ = ā‚¹. 49,000=00
Cost of 1 mĀ³ = ā‚¹. 49,000/10 = ā‚¹. 4,900.00
Example - 2:
Calculate the cost of the concrete of M15 Grade, take 10 mĀ³ and ļ¬nd the 1 mĀ³cost?. 1st Class
mason - 0.5 Noā€™s, 2nd class mason - 1 No, Man mazdoor - 12 Noā€™s, women mazdoor - 18 Noā€™s
and curing purpose - 4 noā€™s.
Solution:
M15 - 1:2:4
15.2 / 7 = 2.17 mĀ³
Sl.
No
Particulars Quantity Rate in ā‚¹. Per unit Amount in .Rs
1 Materials
Cement
Sand
Coarse Aggregate
2.17*1440=
3124.80kgs=62.50 bags
2.17*2 = 4.34mĀ³
2.17*4 = 8.68mĀ³
350
1236.75
1590.11
Bag
MĀ³
mĀ³
21875.00
5367.50
13802.15
Sl.
No
Particulars Quantity Rate in ā‚¹. Per unit Amount in .Rs
2 Labour
1st class Mason
2nd class mason
Man mazdoor
Women mazdoor
0.5
1.0
12.0
18+4=22.0
700
500
350
250
Day
Day
Day
day
350.00
500.00
4200.00
5500.00
Total Cost ā‚¹. 51,594.65
Water Charges - (1 Ā½ %) of total cost: = 51594.65 x (1.5/100) = 773.91 say Rs.774.00
Add contractor proļ¬t (15%) of total cost = 51594.65 x (15/100) = Rs.7739.00
Total Cost = 51,594.65 + 774.00 + 7739.00 = Rs. 60,107.65
Sundries = Rs.892.35 = Rs. 892.35
Cost of 10 mĀ³ cement concrete of M15 grade = Rs. 61,000.00
Cost of 1 mĀ³ cement concrete of M15 Grade = 61,000/10 = Rs. 6,100.00 / mĀ³
Example - 3:
Calculate the cost of the concrete of M25 grade and ļ¬nd the one cu m cost?. 1st class
mason - 1.5 Noā€™s, 2nd class mason - 2 Noā€™s, Man mazdoor - 12 Noā€™s, Women mazdoor
- 18+4, water charges 1 Ā½ % of total cost and consider the contractor proļ¬t is 12 %
of total cost.
Solution:
Grade of Concrete = M25. Mix Proportion: 1:1:2
1.52 / 4 = 0.38 mĀ³
Sl.
No
Particulars Quantity Rate in ā‚¹. Per unit Amount in Rs.
1 Materials
Cement
Sand
Coarse Aggregate
0.38*1440 =547.20
kgā€™s = 10.90 bags
0.38*1 = 0.38 mĀ³
0.38*2 = 0.76 mĀ³
350
1236.75
1590.11
Bag
MĀ³
mĀ³
3815.00
470.00
1208.48
Sl.
No
Particulars Quantity Rate Per unit Amount in Rs.
2 Labour
1st Class mason
2nd Class Mason
Man mazdoor
Women mazdoor
1.5
2.0
12
22
700/-
500/-
350/-
250/-
Day
Day
Day
Day
1050.00
1000.00
4200.00
5500.00
Total Cost ā‚¹. 17259.00
Add Water Charges 1 Ā½ % of Total cost = 17259 x (1.5/100) = 258.88 Say ā‚¹. 259.00
Add Contractor Proļ¬t 12% of total cost = 17259 x (12/100) = ā‚¹. 2071.00
Cost of 1 mĀ³ cement concrete of M25 Grade = 17259 + 259 + 2071= ā‚¹. 19589.00
Sundries = ā‚¹. 411.00 = ā‚¹. 20,000.00
BRICKWORK
Brickwork with Standard Bricks ( Calculation of material required for brickwork)
1. Take a wall of 1 Ā½ brick thickness i.e. 30 cm, nominal thickness of 20 m length and 5 m
height.
2. Nominal volume = Length X width X Height
= 20.00 X 0.30 X 5.00
= 30.00 Cu .m
3. Normal mortar joint will be less than 1 cm, taking 1 cm mortar joint, the actual
thickness of the wall be 29 cm.
Actual Volume = Length X Width X Height
= 20.00 X 0.29 X 5.00
= 29.00 Cu . m
4. Number of Standard bricks ( 20 X 10 X 10 Cm) = 29.00 / (0.2x0.1x0.1)
= 14500 Noā€™s
5. This 14500 no. of bricks is for 29 MĀ³
Therefore Number of bricks per MĀ³ ( Nominal Volume)
= 14500 / 30
= 483.30 - Say 484 Noā€™s
6. Consider 5% of breakage, wastage etc.,. This may be taken as 500 no.of bricks.
Therefore 1 MĀ³ requires 500 no. of bricks.
Mortar Calculations:
Mortar requirement = Actual Volume of brickwork - Net volume of bricks.
= 29.00 - (0.19 x 0.09 x 0.09) x 14500
= 6.68 MĀ³
For frog ļ¬lling, for use of cut bricks, for bonding, for uniform joints, wastages etc., 15% extra
mortar may be required.
Therefore the Volume of Mortar = 6.68 + (6.685 X 15/100)
= 7.688 MĀ³ ( Wet Volume)
For dry volume increase the wet volume by 25%
= 1.25 X 7.68 MĀ³
= 9.61 MĀ³
For 30 Cu .m of brick work, dry volume of mortar = 9.61 MĀ³
For 1 Cu .m of brick work = 0.32 MĀ³
For 10 Cu .m of brick work, dry volume of mortar = 0.32 / 10
= 3.20 MĀ³
For 10 Cu .m of brick work, No.of bricks = 5000 Noā€™s
Dry volume of mortar = 3.20 MĀ³
Brick Masonry :
Brick size with mortar = (20 x 10 x10) CmĀ³
Brick size without mortar = (19 x 9 x 9) CmĀ³
Length = 20 m, Thickness = 1 Ā½ brick wall Height = 3 m.
Nominal volume of Brick wall = 20 x 0.3 x 3 = 18 MĀ³
Actual volume of 1 brick = 0.19 x 0.09 x 0.09 = 1.539 x 10ā» Ā³
Example : - 1 Brick volume = 20 x 10 x 10 cmĀ³
= 2000 cmĀ³ 0.002 MĀ³
For a volume of 18 mĀ³, No.of bricks = 18 / 0.002 = 9000 bricks
1 MĀ³ = 9000 / 18 = 500 Bricks.
Example : -
Total volume of 500 bricks = 500 x 0.20 x 0.10 x 0.10 = 1 MĀ³
Modular brick volume for 500 bricks = 500 x 0.19 x 0.09 x 0.09 = 0.769 MĀ³
Volume of mortar = 1 - 0.769 = 0.231 MĀ³
Cement = (0.231 x 1)/7 = 0.033 MĀ³
Mortar = (0.231 /7) x 6 = 0.198 MĀ³
Density of Cement = Weight / Volume = 1440 Kg / mĀ³
1 MĀ³ = 1440 kg
1 Bag = 50 kg
1 Bag = 50 / 1440 = 0.034 MĀ³
Cement Mortar :- 1:6
Wall = 10.00 X 0.23 X 3.00 m = 6.90 mĀ³
For 1 mĀ³ = 1/Brick volume= 1/ (0.1 x 0.1 x 0.2) = 1/0.002 = 500 Noā€™s
Bricks for 1 cu m = 500 Noā€™s
For 6.90 Cu m = 6.90 X 500 = 3450 Noā€™s (or) 6.9/0.002 = 3450 Noā€™s
For 10 Cu m = 10/0.002 = 5000 Noā€™s
For 10 cu m of Brick work with CM (1:6)
70% of Brick volume = 7 cu m
30% of Cement Mortar = 3 cu m
The quantity of material for cement mortar - (1:6)
Cement = 3 / (1+6) = 3/7 = 0.42 mĀ³
Sand/F.A= 0.42 X 6 = 2.52 mĀ³
Cement Mortar for 10 Cu m of Brick Work
Mortar No of Bricks Cement Fine Aggregate/Sand
1:2 5000 1.0 mĀ³ 2.0 mĀ³
1:3 5000 0.75 mĀ³ 2.25 mĀ³
1:4 5000 0.60 mĀ³ 2.40 mĀ³
1:5 5000 0.50 mĀ³ 2.50 mĀ³
1:6 5000 0.43 mĀ³ 2.58 mĀ³
Labour Required for 10 Cu m Brick Work:
1st Class Mason - 0.50 Noā€™s
2nd Class Mason - 1 No.
Man Mazdoor - 12 Noā€™s
Women Mazdoor - 12 Noā€™s
Watering / Curing - 2 Noā€™s
Example - 4:
Calculate the quantity of cement, number of bricks, quantity of sand for C.M
(1:6) for 1 Ā½ brick thick, take the length of wall is 20 m and height of wall is 5 m.
Solution:
Volume of wall = Length X Breadth X Height
20.00 X 0.30 X 5.00 = 30 Cu m
Number of bricks = 30 /0.002 or 30 X 500 = 15,000 Noā€™s
Cement Mortar = 1:6
Quantity of cement mortar ( 30%) - 9 mĀ³
Quantity of Cement = 9 / (1+6) = 9/7 = 1.29 mĀ³= 1.29 x 1440
= 1857.6 kg = 37.15 bags X 350/- = Rs.13003.00
Quantity of F.A. = 1.29 X 6 = 7.74 cu m = 1236.75 = Rs. 9572.00
Bricks = 15000 = 4500/1000 = Rs. 67500.00
For 10 Cu m For 30 Cu m
1st ClassMason - 0.50 Noā€™s 1 st Class Mason - 1.50 Noā€™s
2nd Class mason - 1 No 2nd Class Mason - 3.00 Noā€™s
Man Mazdoor - 12 Noā€™s Man Mazdoor - 36 Noā€™s
Women Mazdoor - 12 Noā€™s Women Mazdoor - 36 Noā€™s
Curing - 2 Noā€™s Curing - 6 Noā€™s
1St Class Mason - 1.50 X 700 = Rs.1050.00
2nd Class Mason - 3.00 X 500 = Rs.1500.00
Man Mazdoor - 36 X 350 = Rs. 12600.00
Women Mazdoor - 36 X 250 = Rs. 9000.00
Curing - 6 X 250 = Rs. 1500.00
Total Cost = Cost of the Material + Cost of the Labour = Rs. 1,15,725.00
Add water charges @ 1 Ā½ % = 115725x1.5/100 = Rs.1736.00
Add Contractor Proļ¬t @ 15% = 115725 X 15/100 = Rs.17359.00
TOTAL COST IN Rs. 1,15,725 + 1,736 + 17,359 = Rs. 1,34,820.00
Sundries = Rs. 180.00
Scaffolding = Rs. 5,000.00
Total Cost in Rs. 1,40,000.00
Example - 5:
Calculate the quantity of cement, number of bricks, quantity of sand for C.M (1:5)
for 1 Ā½ brick thick, take the length of wall is 15 m and height of wall is 3.5 m.
Solution:
Given data - Length of Wall = 15.00 m
Height of Wall = 3.50 m
Thickness of Wall = 1 Ā½ brick wall = 0.30 m
Cement Mortar = 1:5
Volume of Wall= 15.0 X 0.30 X 3.50 = 15.75 MĀ³
Quantity of cement Mortar (30%) = 4.73 MĀ³
Quantity of Cement = 4.73 /(1+5) = 4.73 / 6 = 0.79 mĀ³
= 0.79 / 0.034 = 23 Bags.
Quantity of Sand / F.A = 0.79 X 5 = 3.95 mĀ³
Number of bricks = 15.75 / 0.002 = 7875 Noā€™s
Cost of Cement = 23 bags X 350/- = ā‚¹. 8050.00
Cost of Sand/F.A = 3.95 X 1236.75 = ā‚¹. 4885.00
Cost of Brick = 7875 X 4.50 = ā‚¹. 35438.00
Total Cost of the Material - Rs. 48373.00
Labour for 15.75 Cu . m
1st Class Mason - 0.788 Noā€™s X Rs. 700 = Rs. 551.60
2nd Class Mason - 1.575 Noā€™s X Rs. 500 = Rs. 787.50
Man Mazdoor - 18.90 Noā€™s X Rs. 350 = Rs. 6615.00
Women Mazdoor - 18.90 Noā€™s X Rs. 250 = Rs. 4725.00
Curing purpose - 3.15 Noā€™s X Rs. 250 = Rs. 787.50
Total Labour Cost = Rs. 13466.60
TOTAL COST = Total cost of the Material + Total cost of the Labour
= Rs. 48,373.00 + 13,466.60
= Rs. 61,839.60
Add Water charges (1 Ā½ %) = Rs. 61,839.60 X 1.5/100= Rs. 928.00
Add Contractor Proļ¬t (10%) = Rs. 61,839.60 X 10/100 = Rs. 6184.00
Total Cost = Rs. 61,839.6 + 928.0 + 6184.0 = Rs. 68,951.60
Sundries = Rs. 48.40
Scaffolding = Rs. 1,000.00
TOTAL COST = Rs. 70,000.00
Example - 6:
Estimate the 1st class brick work of a room size 3.50 m X 4.0 m and height is
3 m thickness of wall is 1 Ā½ brick wall. Mortar proportion is 1:4.
Solution:
Given data - Room dimensions - 3.5 X 4 m
Thickness of wall - 0.30 m
Height of wall - 3 m
Total Volume of brick work = 2(0.15 + 4.00 + 0.15) + 2(0.15 + 3.5 + 0.15)
= 8.60 + 7.60 = 16.20 m
Volume = 16.20 X 0.30 X 3.00 = 14.58 Cu .m
Volume of 1 mĀ³ of bricks = 500 Noā€™s
Volume of 14.58 mĀ³ bricks 500 X 14.58 = 7290 Noā€™s
Mortar proportion is 1:4
Dry Volume of mortar - 1 mĀ³ = 0.3 mĀ³
For 14.58 mĀ³ = 0.3 X 14.58 = 4.374 mĀ³
Volume of cement= 4.374 / (1+4) = 4.374 / 5 = 0.875 mĀ³
No of bags = 0.875/0.034 = 25 Bags
Volume of F.A / Sand = 0.875 x 4 = 3.5 mĀ³
Cost of Bricks = 7290 x 4.5/- = Rs. 32,805.00
Cost of Cement = 25 X 350/- = Rs. 8750.00
Cost of F.A/Sand = 3.5 X 1236.75= Rs. 4328.60
Total cost of the Material = Rs. 45,883.60
Labour for 14.58 cu .m
1st class Mason - 0.73 Noā€™s Man Mazdoor - 17.50 Noā€™s
2nd Class Mason - 1.46 Noā€™s Women Mazdoor - 17.50 Noā€™s
Curing - 3 Noā€™s
1st Class Mason - 0.73 X 700 = Rs. 511.00
2nd Class Mason - 1.46 X 500 = Rs. 730.00
Man Mazdoor - 17.5 X 350 = Rs. 6,125.00
Women Mazdoor - 17.50 X 250 = Rs. 4,375.00
Curing - 3 X 250 = Rs. 750.00
Total Labour Cost = Rs. 12,491.00
TOTAL COST = Cost of the Material + Cost of the Labour
= Rs. 45,883.60 + 12,491.00 = Rs.58374.60
Add water charges (1 Ā½ %) = 58,374.60 X 1.5/100 = Rs.875.60
Add contractor charges (10%) = 58,374.60 X 10/100 = Rs. 5837.46
TOTAL COST = 58374.60+875.60+5837.46 = Rs. 65,087.66
Sundries = Rs. 412.34
Scaffolding = Rs. 4500.00
TOTAL COST OF THE 1ST CLASS BRICKWORK = Rs. 70,000.00
Random Rubble Masonry
For 10 Cu . m of Random Rubble Stone masonry. Add 25% of dry volume of material
10.00 + [10.00 X (25/100)] = 12.50 Cu . m
Take 42% of Cement Mortar = 4.20 Cu m
Cement , sand mix Proportion is - 1 : 6
Volume of Cement = 4.20 /(1+6) = 4.20/7 = 0.60 Cu . m
Volume of Sand/F.A = 0.60 X 6 = 3.60 Cu . m
Example : 7
Calculate the cost of the R.R.S masonry for 1 Cu . m. The ratio of mortar is 1:6. The
cost of boulders for 1 Cu . m is ā‚¹.800/-, Labour 1st class mason - 0.5, 2nd class mason - 12 Noā€™s,
man mazdoor - 10 Noā€™s, women mazdoor - 10 Noā€™s. For R.R.S masonry volume 10 Cu .m is taken
as 12.5 cu . m. For 1 Cu . m = 1.25 Cu . m.
MORTAR CEMENT SAND
1: 3 ( Cement : Sand) 1.0 cu . m 3.0 Cu . m
1: 4 ( Cement : Sand) 0.85 Cu . m 3.40 Cu . m
1: 5 ( Cement : Sand) 0.70 Cu . m 3.5 Cu . m
1 : 6 ( Cement : Sand) 0.60 Cu . m 3.60 Cu . m
1 : 2 ( Lime : Sand) 1.60 Cu . m of Lime 3.20 Cu . m
1 : 3 ( Lime : Sand) 1.20 Cu . m of Lime 3.60 Cu . m
Solution:
Given data:- CM (1:6),
Volume of cement mortar for 10 MĀ³ - 42% = 4.20 MĀ³
Volume of Cement = 4.20 / (1+6) = 4.20/7 = 0.60 mĀ³
0.60 / 0.034 = 17.64 bags Say 18 Bags
Volume of Sand = 0.60 X 6 = 3.60 mĀ³
Volume of Boulders = 12.50 mĀ³
Sl.No Particulars Quantity Rate Per Amount in
ā‚¹.
1 Materials
a. Cement
b. Sand
c. Boulders
18 bags
3.60 cu .m
12.50 cu .m
350.00
1236.75
800.00
Bag
Cu m
Cu m
6300.00
4452.30
10,000.00
Sl.
No
Particulars Quantit
y
Rate Per Amount in
ā‚¹.
2 Labour
a. 1st class mason
b. 2nd class mason
c. Man mazdoor
d. Women mazdoor
0.50 Noā€™s
12 Noā€™s
10 Noā€™s
10 Noā€™s
700.00
500.00
350.00
250.00
Day
Day
Day
Day
350.00
6000.00
3500.00
2500.00
33,102.30
3 Add water charges - (1 Ā½ %) 496.50
4 Add contractor charges 10% 3310.23
Sundries 90.97
TOTAL COST FOR 10 MĀ³ 37,000.00
For 1 MĀ³ Cost of R.R.S Masonry 37000/10 ā‚¹. 3,700.00
U. C. R. S. MASONRY
U. C. R. S. MASONRY FOR 10 Cu. M
Take Cement Mortar - 1:6
U.C.R.Stone for 10 Cu m - Add 25% dry volume of material
= [10.00 + (10.00+25/100)]
= 12.50 Cu m
Volume of Stone can take = 12.50 Cu.m for 10 Cu . m
Volume of cement mortar take - 40 % = 4.00 Cu . m for 10 Cu .m
4.00 Cu. m Cement Mortar
Volume of cement = 4.00 / (1+6) = 4/7 = 0.57 Cu . m
Volume of sand = 0.57 X 6 = 3.42 Cu . m
MORTAR CEMENT SAND
1: 3 ( Cement : Sand) 1.00 Cu . m 3.00 Cu . m
1: 4 ( Cement : Sand) 0.80 Cu . m 3.20 Cu . m
1: 5 ( Cement : Sand) 0.67 Cu . m 3.35 Cu . m
1 : 6 ( Cement : Sand) 0.60 Cu . m 3.60 Cu . m
Example : 8
Calculate the cost of the U.C.R.S masonry for 1 Cu . m. The ratio of mortar is 1:4. The
cost of boulders for 1 Cu . m is ā‚¹.1200/-, Labour 1st class mason - 0.5, 2nd class mason - 12 Noā€™s,
man mazdoor - 10 Noā€™s, women mazdoor - 10 Noā€™s. For U.C.R.S masonry volume 10 Cu .m is
taken as 12.5 cu . m.
Solution:
Given data:- CM (1:4),
Volume of cement mortar for 10 MĀ³ - 40% = 4.00 MĀ³
Volume of Cement = 4.00 / (1+4) = 4.00/5 = 0.80 mĀ³
0.80 / 0.034 = 23.53 bags Say 24 Bags
Volume of Sand = 0.80 X 4 = 3.20 mĀ³
Volume of Stone = 12.50 mĀ³
Sl.No Particulars Quantity Rate Per Amount in
ā‚¹.
1 Materials
a. Cement
b. Sand
c. Boulders
24 bags
3.2 cu .m
12.50 cu .m
350.00
1236.75
1200.00
Bag
Cu m
Cu m
8400.00
3957.60
15,000.00
Sl.
No
Particulars Quantity Rate Per Amount in
ā‚¹.
2 Labour
a. 1st class mason
b. 2nd class mason
c. Man mazdoor
d. Women mazdoor
0.50 Noā€™s
12 Noā€™s
10 Noā€™s
10 Noā€™s
700.00
500.00
350.00
250.00
Day
Day
Day
Day
350.00
6000.00
3500.00
2500.00
39,707.60
3 Add water charges - (1 Ā½ %) 595.60
4 Add contractor charges 10% 3970.76
Sundries & L.S 726.04
TOTAL COST FOR 10 MĀ³ 45,000.00
For 1 MĀ³ Cost of R.R.S Masonry ā‚¹. 45,000/10 ā‚¹. 4,500.00
PLASTERING
Calculation of quantity mortar and materials Area X thickness gives the quantity of
mortar for uniform thickness, for ļ¬lling of the joints and to make up non uniform
surface of wall. This may be increased by 30% which will give wet mixed mortar to
get the total dry volume of materials it may be further increased by 25%.
Material for 12 mm thick plastering in wall for 100 sq . m
Wet mixed mortar for uniform layer = 12 mm
= 0.012 x 100
= 1.20 Cu . m
Adding 30% to ļ¬ll up the joints, uneven surface etc.,
Now the wet volume of mortar = {1.20 + [1.20 x (30/100)]}
= 1.56 Cu . m
1.56 Cu . m of wet volume is converted into dry volume by increasing 25%
Now dry volume of mortar = 1.56 + [1.56 x (25/100)]
= 1.95 Cu . m Say 2.00 Cu . m
Therefore Dry volume of mortar is 2 Cu . m ( For 100 Sq . m at 12 mm thickness)
Material for 20 mm thick plastering
As the thickness of the plaster is more, 20% of mortar is taken to ļ¬ll up the joints,
unevenness etc.,
The quantity of wet mortar = 0.02 X 100 = 2.00 Cu . m
Now the wet volume of mortar = 2.00 + [2.00 x (20/100)] = 2.40 Cu . m
Volume of dry mortar = 2.40 + [ 2.40 x (25/100)] = 3.00 Cu . m
Plastering 12mm thickness; Cement Mortar for 100 Sq.m
Mortar Cement Sand / F.A
1:2 0.60 Cu.m [ 18 Bags] 1.20 Cu.m
1:3 0.5 Cu.m [ 15 Bags] 1.50 Cu.m
1:4 0.4 Cu.m [ 12 Bags] 1.60 Cu.m
1:5 0.35 Cu.m [ 10 Bags] 1.75 Cu.m
1:6 0.30 Cu.m [ 9 Bags] 1.80 Cu.m
Plastering 20 mm thickness; Cement Mortar for 100 Sq.m
Mortar Cement Sand / F.A
1:2 1.00 Cu.m [ 29 Bags] 2.00 Cu.m
1:3 0.75 Cu.m [ 22 Bags] 2.25 Cu.m
1:4 0.60 Cu.m [ 18 Bags] 2.40 Cu.m
1:5 0.50 Cu.m [ 15 Bags] 2.50 Cu.m
1:6 0.43 Cu.m [ 13 Bags] 2.60 Cu.m
Requirement of Workmanship for Plastering for 100 Sq.m :
Labour Quantity
1st Class Mason 0.35 Noā€™s
2nd Class Mason 10 Noā€™s
Man Mazdoor 15 Noā€™s
Women Mazdoor / Curing 0.75 Noā€™s
Example - 9 :
Estimate the plastering work thickness of 12 mm, area 100 sq.m for 1:6
Solution :
volume = Wet mixed mortar for uniform layer = 12 mm
= 0.012 x 100
= 1.20 Cu . m
Thickness = 12 mm; Area= 100 sq.m
1.20 + 1.20 (30/100)= 1.56 Cu.m ( Wet Volume)
1.56 + 1.56 (25/100)= 1.95 Cu.m ( Dry Volume)
Dry Volume = 1.95 Cu.m ā‰ƒ 2 Cu.m
Cement = 2.00/(1+6) = 0.285 Cu.m X 1 = 0.285 Cu.m
= 0.285 / 0.034 = 8.38 ā‰ƒ 8 Bags
Sand = 0.285 X 6 = 1.71 Cu.m
Sl.No Particulars Quantity Rate Per Amount in ā‚¹.
1
Materials
a. Cement
b. Sand
8 bags
1.71 cu .m
350.00
1236.75
Bag
Cu m
8400.00
3957.60
2
Labour
a. 1st Class Mason
b. 2nd Class Mason
c. Man Mazdoor
d. Curing
0.35 No
10 Noā€™s
15 Noā€™s
0.75 No
700.00
500.00
350.00
250.00
Day
Day
Day
Day
245.00
5000.00
5250.00
187.50
ā‚¹. 23,040.10
3 Add Water Charges (1 Ā½ %) ā‚¹. 345.60
4 Add Contractor Profit (10%) ā‚¹. 2304.01
Sundries & L.S Charges ā‚¹. 310.29
TOTAL COST FOR 100 Sq. M ā‚¹. 26,000.00
For Pointing in Brick work for total dry volume of material is taken
as 0.60 Cu.m for 100 Sq.m
Example - 10 :
Estimate the pointing work quantity 1:2 for 1200 Sq.m ?
Solution :
0.60 Cu.m - 100 Sq.m
? - 1200 Sq.m
1200 Sq.m = (0.60 X 1200) / 100 = 7.20 Cu.m
Cement = 7.20 / (1+2) = 2.40 Cu.m X 1 = 2.40 Cu.m
= 2.40 / 0.034 = 70.58 ā‰ƒ 71 Bags
Sand = 2.40 X 2 = 4.80 Cu.m
Sl.No Particulars Quantity Rate Per Amount in ā‚¹.
1
Materials
a. Cement
b. Sand
71 Bags
4.80 Cu.m
350.00
1,236.75
Bag
Cu.m
24,850.00
5,936.40
2
Labour
a. 1st Class Mason
b. 2nd Class Mason
c. Man Mazdoor
d. Curing
0.35 No
10 Noā€™s
10Noā€™s
0.50 No
700.00
500.00
350.00
250.00
Day
Day
Day
Day
245.00
5,000.00
3,500.00
125.00
ā‚¹.39,656.40
3 Add Water Charges (1 Ā½ %) ā‚¹. 594.85
4 Add Contractor Profit (10%) ā‚¹. 3.965.64
Sundries & L.S Charges ā‚¹. 283.11
TOTAL COST FOR 100 Sq. M ā‚¹.44,500.00
Cement Concrete Floor
- The quantity of cement concrete may be calculated by multiplying area of ļ¬‚oor
by the thickness.
- The quantity of each material may be found same as the plain concrete of
cement (PCC) .
1. For 2.5 cm cement concrete ļ¬‚oor for 100 MĀ² of area the quantity of cement
concrete is 2.5 MĀ³. Now add 10% extra for unevenness of base concrete.
2.5 + 2.5 X (10/100) = 2.75 MĀ³
For neat cement surface ļ¬nishing additionally 0.20 MĀ³ (6 Bags) are required
2. For 100 MĀ³ cement concrete, the total dry volume of material is approximately
increased by 50%.
2.75 + 2.75 X (50/100) = 4.125 MĀ³
3. For 2 cm thick cement concrete ļ¬‚oor for 100 MĀ² area, the dry volume is 4.125 MĀ³.
4. For 4 cm thick cement concrete ļ¬‚oor for 100 MĀ² area, the dry volume is 4 MĀ³
Add 10%= 4 + 4 x (10/100) = 4.40 MĀ³ ( Wet Volume)
Add 50% Dry volume
= 4.40 + 4.40 X (50/100) = 6.60 MĀ³
Example - 11 :
Estimate the 2.5 cm cement concrete ļ¬‚oor of 1:2:4 for 1 Sq.m ?
Solution :
100 Sq . m = 2.50 MĀ³ of quantity of dry volume is = 4.125 MĀ³
Cement = 4.125 /(1+2+4) = 0.59 MĀ³ X 1 = 0.59 MĀ³
1 Bag = 0.034 MĀ³
0.59 MĀ³ = ?
No.of bags = 0.59 / 0.034 = 17.35 ā‰ƒ 17 Bags
Sand = 0.59 X 2 = 1.18 MĀ³
Coarse Aggregates = 0.59 X 4 = 2.36 MĀ³
Note : [ For neat ļ¬nishing of ļ¬‚oor, the thickness of neat cement layer is 1.50mm.
āˆ“ The cement paste requirement for 100 MĀ²
= 0.0015 X 100 = 0.15 MĀ³ .
Dry volume of cement is increased by 25% (For 100MĀ² only)
= 0.15 + 0.15 X (25/100)
= 0.187 MĀ³ ā‰ƒ 0.20 MĀ³ ]
Surface ļ¬nishing for 100 Sq . m = 0.20 Cu . m
Sl.No Particulars Quantity Rate Per Amount in ā‚¹.
1
Materials
a. Cement
b. Sand
c. Coarse Aggregate
17 Bags
1.18 Cu .m
2.36 Cu.m
350.00
1,236.75
1590.11
Bag
Cu.m
Cu.m
5950.00
1459.36
3752.65
2
Labour
a. 1st Class Mason
b. 2nd Class Mason
c. Man Mazdoor
d. Curing
0.75 No
10 Noā€™s
10 Noā€™s
2 Noā€™s
700.00
500.00
350.00
250.00
Day
Day
Day
Day
525.00
5,000.00
3,500.00
500.00
ā‚¹. 20,687.01
3 Add Water Charges (1 Ā½ %) ā‚¹. 310.30
4 Add Contractor Profit (10%) ā‚¹. 2068.70
Sundries & L.S Charges ā‚¹. 933.99
TOTAL COST FOR 100 Sq. M ā‚¹. 24,000.00
Cost for 1 Sq.M = ā‚¹. 24000 / 100 = ā‚¹. 240.00 ā‚¹. 240.00
Example - 12 :
Estimate the White Washing of 1 coat for 1 Sq.m area, Taking 100 Sq.m as the area
10 kg of white lime unslaked ?
Solution :
Sl.No Particulars Quantity Rate Per Amount in ā‚¹.
1
Materials
White Lime unslaked
10 Kgā€™s 950.00
9.50
Quintal
Kg
95.00
2 Glue Powder Lumpsum 30.00 L.S 30.00
3
Labour
a. White Washer
b. Men Mazdoor
0.70 (or) 2/3 Noā€™s
0.70 (or) 2/3 Noā€™s
500.00
350.00
Day
Day
350.00
245.00
4 Sundries & Lump Sum 80.00
Total Cost in Rs. 800.00
Add Water charges (1 Ā½ %) = Rs. 800 X )1.5/100) = Rs. 12.00
Add Contractor Charges (10%) = Rs. 800 X (10/100) = Rs. 80.00
Total Cost for 100 Sq.m = Rs. 800.00 + 12.00 + 80.00 = Rs. 892.00
Cost for 1 Sq.m of White Washing of 1 coat = Rs. 892.00 / 100 = Rs. 8.92
EQS -  RATE ANALYSIS.pdf

More Related Content

What's hot

Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing bookThomas Britto
Ā 
minor project report on design of residential building
minor project report on design of residential buildingminor project report on design of residential building
minor project report on design of residential buildingtushar garg
Ā 
SMM7 Cost Summary Report
SMM7 Cost Summary ReportSMM7 Cost Summary Report
SMM7 Cost Summary ReportNatalie Reid
Ā 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveyingAwanish Shukla
Ā 
Mode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickworkMode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickworkAshwiniChaudhari13
Ā 
Valuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation EngineeringValuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation EngineeringShanmugasundaram N
Ā 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and materialALI HYDER GADHI
Ā 
Civil Quantity Survey and Estimation
Civil Quantity Survey and EstimationCivil Quantity Survey and Estimation
Civil Quantity Survey and EstimationGide India
Ā 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In ConstructionAB MAKASANA
Ā 
Tender notice Drafting Procedure
Tender notice Drafting ProcedureTender notice Drafting Procedure
Tender notice Drafting ProcedureSachin1385
Ā 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveyingsooricivil
Ā 
Rate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisRate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisJaptyesh Singh
Ā 
Prefabricationā€‹ structure ppt
Prefabricationā€‹ structure pptPrefabricationā€‹ structure ppt
Prefabricationā€‹ structure pptAbhishekM45
Ā 
Item rate contract
Item rate contractItem rate contract
Item rate contractsauravkapadia
Ā 
Cost estimation of a Building
Cost  estimation of a BuildingCost  estimation of a Building
Cost estimation of a BuildingARAVINDBORRA1
Ā 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimateGanesh Tatikonda
Ā 
Report of an estimation
Report of an estimationReport of an estimation
Report of an estimationSuhaa Chine
Ā 

What's hot (20)

Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
Ā 
minor project report on design of residential building
minor project report on design of residential buildingminor project report on design of residential building
minor project report on design of residential building
Ā 
Rate analysis
Rate analysisRate analysis
Rate analysis
Ā 
SMM7 Cost Summary Report
SMM7 Cost Summary ReportSMM7 Cost Summary Report
SMM7 Cost Summary Report
Ā 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveying
Ā 
Mode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickworkMode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickwork
Ā 
Valuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation EngineeringValuation - Estimation, Costing and Valuation Engineering
Valuation - Estimation, Costing and Valuation Engineering
Ā 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
Ā 
Civil Quantity Survey and Estimation
Civil Quantity Survey and EstimationCivil Quantity Survey and Estimation
Civil Quantity Survey and Estimation
Ā 
Revit Architecture notes
Revit Architecture notesRevit Architecture notes
Revit Architecture notes
Ā 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
Ā 
Tender notice Drafting Procedure
Tender notice Drafting ProcedureTender notice Drafting Procedure
Tender notice Drafting Procedure
Ā 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
Ā 
Rate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisRate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate Analyisis
Ā 
Prefabricationā€‹ structure ppt
Prefabricationā€‹ structure pptPrefabricationā€‹ structure ppt
Prefabricationā€‹ structure ppt
Ā 
Item rate contract
Item rate contractItem rate contract
Item rate contract
Ā 
Cost estimation of a Building
Cost  estimation of a BuildingCost  estimation of a Building
Cost estimation of a Building
Ā 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
Ā 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
Ā 
Report of an estimation
Report of an estimationReport of an estimation
Report of an estimation
Ā 

Similar to EQS - RATE ANALYSIS.pdf

rate analysis for structural buildingsppt 1.pptx
rate analysis for structural buildingsppt 1.pptxrate analysis for structural buildingsppt 1.pptx
rate analysis for structural buildingsppt 1.pptxAyan Sengupta
Ā 
estimating and costing (1).pdf
estimating and costing (1).pdfestimating and costing (1).pdf
estimating and costing (1).pdfRoshani Shahi
Ā 
Ratesanalysis for Material and Labor
Ratesanalysis for Material and LaborRatesanalysis for Material and Labor
Ratesanalysis for Material and LaborNagoorkani Majeed
Ā 
Notes on Estimation.ppt
Notes on Estimation.pptNotes on Estimation.ppt
Notes on Estimation.pptashoklalwani6
Ā 
ANALYSIS_OF_RATES.ppt
ANALYSIS_OF_RATES.pptANALYSIS_OF_RATES.ppt
ANALYSIS_OF_RATES.pptRijuDasgupta
Ā 
Eqs unit 3 final
Eqs unit 3 finalEqs unit 3 final
Eqs unit 3 finaldhanapal143
Ā 
chapter1-210122051628.pdf
chapter1-210122051628.pdfchapter1-210122051628.pdf
chapter1-210122051628.pdfDeepak37004
Ā 
80623277 cost-estimator
80623277 cost-estimator80623277 cost-estimator
80623277 cost-estimatorimaduddin91
Ā 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculationZIyeeTan
Ā 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculationZIyeeTan
Ā 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculationZIyeeTan
Ā 
Building materials, Basic civil engineering ,unit-1
Building materials, Basic civil engineering ,unit-1Building materials, Basic civil engineering ,unit-1
Building materials, Basic civil engineering ,unit-1Parimal Jha
Ā 
Brick Industry project report
Brick Industry project reportBrick Industry project report
Brick Industry project reportRajuPodagatlaPjr
Ā 
New Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxNew Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxQAQCGCC
Ā 
2 review
2 review2 review
2 reviewEr Kumaran
Ā 
Amit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAmit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAman Jain
Ā 
Environment friendly indian_building_material_technologies_for_cost_effective...
Environment friendly indian_building_material_technologies_for_cost_effective...Environment friendly indian_building_material_technologies_for_cost_effective...
Environment friendly indian_building_material_technologies_for_cost_effective...Akshaya Selvam
Ā 
Environment friendly building_material_technologies_for_low_cost_housing (1)
Environment friendly building_material_technologies_for_low_cost_housing (1)Environment friendly building_material_technologies_for_low_cost_housing (1)
Environment friendly building_material_technologies_for_low_cost_housing (1)Hammam El Meseiry
Ā 

Similar to EQS - RATE ANALYSIS.pdf (20)

rate analysis for structural buildingsppt 1.pptx
rate analysis for structural buildingsppt 1.pptxrate analysis for structural buildingsppt 1.pptx
rate analysis for structural buildingsppt 1.pptx
Ā 
estimating and costing (1).pdf
estimating and costing (1).pdfestimating and costing (1).pdf
estimating and costing (1).pdf
Ā 
Ratesanalysis for Material and Labor
Ratesanalysis for Material and LaborRatesanalysis for Material and Labor
Ratesanalysis for Material and Labor
Ā 
Notes on Estimation.ppt
Notes on Estimation.pptNotes on Estimation.ppt
Notes on Estimation.ppt
Ā 
ANALYSIS_OF_RATES.ppt
ANALYSIS_OF_RATES.pptANALYSIS_OF_RATES.ppt
ANALYSIS_OF_RATES.ppt
Ā 
Eqs unit 3 final
Eqs unit 3 finalEqs unit 3 final
Eqs unit 3 final
Ā 
chapter1-210122051628.pdf
chapter1-210122051628.pdfchapter1-210122051628.pdf
chapter1-210122051628.pdf
Ā 
80623277 cost-estimator
80623277 cost-estimator80623277 cost-estimator
80623277 cost-estimator
Ā 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
Ā 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
Ā 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
Ā 
Building materials, Basic civil engineering ,unit-1
Building materials, Basic civil engineering ,unit-1Building materials, Basic civil engineering ,unit-1
Building materials, Basic civil engineering ,unit-1
Ā 
Brick Industry project report
Brick Industry project reportBrick Industry project report
Brick Industry project report
Ā 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
Ā 
New Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxNew Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptx
Ā 
2 review
2 review2 review
2 review
Ā 
Amit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAmit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha university
Ā 
Environment friendly indian_building_material_technologies_for_cost_effective...
Environment friendly indian_building_material_technologies_for_cost_effective...Environment friendly indian_building_material_technologies_for_cost_effective...
Environment friendly indian_building_material_technologies_for_cost_effective...
Ā 
Environment friendly building_material_technologies_for_low_cost_housing (1)
Environment friendly building_material_technologies_for_low_cost_housing (1)Environment friendly building_material_technologies_for_low_cost_housing (1)
Environment friendly building_material_technologies_for_low_cost_housing (1)
Ā 
Bricks
BricksBricks
Bricks
Ā 

Recently uploaded

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
Ā 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
Ā 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
Ā 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
Ā 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
Ā 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
Ā 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
Ā 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
Ā 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
Ā 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
Ā 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
Ā 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
Ā 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
Ā 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
Ā 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
Ā 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
Ā 
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...9953056974 Low Rate Call Girls In Saket, Delhi NCR
Ā 

Recently uploaded (20)

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Ā 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
Ā 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
Ā 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
Ā 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
Ā 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
Ā 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
Ā 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
Ā 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
Ā 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
Ā 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
Ā 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
Ā 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
Ā 
young call girls in Rajiv ChowkšŸ” 9953056974 šŸ” Delhi escort Service
young call girls in Rajiv ChowkšŸ” 9953056974 šŸ” Delhi escort Serviceyoung call girls in Rajiv ChowkšŸ” 9953056974 šŸ” Delhi escort Service
young call girls in Rajiv ChowkšŸ” 9953056974 šŸ” Delhi escort Service
Ā 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Ā 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
Ā 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
Ā 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Ā 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
Ā 
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
Ā 

EQS - RATE ANALYSIS.pdf

  • 1. UNIT - III Prepared by : B. Govinda Rajulu RATE ANALYSIS
  • 2. Introduction What is Rate Analysis? ā˜… Rate Analysis is the determination of rate per unit of a particular item of work from the cost of materials, cost of labour and other miscellenious expenses requires its completion is known as Analysis of Rate / Rate Analysis. ā˜… Reasonable proļ¬t usually 10 % to 15 % for the contractor is also included to Rate Analysis. ā˜… Rate of materials are usually taken as the rates delivered at the site of work and include the initial cost ( cost at origin) and also add transportation, freight charges if any and any other taxes etc.,
  • 3. ā˜… If the materials are to be carried from a distance place more than 8 km, then the transportation cost is also included. ā˜… The rates of materials and labour vary from place to place and therefore, the rates of different items of works also vary from place to place. Purpose of Rate Analysis: - Main purpose of rate analysis are the following: a) To determine the current rate per unit of an item at the locality. b) To examine the viability of rates offered by contractors. c) To calculate the quantity of materials and labour strength required for project planning. d) To ļ¬x up labour contract rates.
  • 4. The rates of particular items of work depends on the following :- 1) Speciļ¬cations of works and materials, quality of material proportion of mortar, methods of constructional operations etc., 2) Quantity of materials and their rates, number of different types of labours and their rates. 3) Location of the site of work and its distances from the sources of water (construction of roads and irrigation) 4) Trafļ¬cs and miscellenious and overhead expenses of contractor. Overhead Cost: Overhead cost includes general ofļ¬ce expenses, rents, taxes, supervision costs and other costs. Which are indirect expenses and not productive expenses on the job.
  • 5. The miscellenious expenses are overheads may be under the following heads: 1) General Overheads - a) Ofļ¬ce Staff b) Stationary, Printing etc., c) Travelling expenses d) Telephone costs e) Rents and taxes 2) Job Overheads - a) Salary of engineers, supervisors etc., b) Handling of materials c) Repairs, carriage and appreciation of tools and plants d) Amenities of labour e) Workman insurance, compensation f) Interest on instruments
  • 6. ā˜… The contractor may be allowed a net proļ¬t of 6 - 8 % and miscellenious overhead expenses may come to about 5 - 10 %. ā˜… For overall expenses and contractor proļ¬t 15% of the actual cost may be reasonable amount but it is usually practiced to add 10% for all these under the head proļ¬t. ā˜… The analysis of rate is usually worked out for the unit of payment of the particular item of work under two heads. (i) Material (ii) Labour ā˜… The cost of materials are taken as delivery at site inclusive of the transportation, local charges and other taxes. ā˜… For tool and plants and miscellenious pity expenses which cannot be accounted in details. Lump Sum provision is made.
  • 7. Sl. No Particular of Item Quantity Per Day 1 Brickwork in lime or cement mortar in foundation and plinth 1.25 MĀ³ Per Mason 2 Brickwork in lime or cement mortar in super structure 1 MĀ³ Per Mason 3 Brickwork in cement or lime mortar in arches 0.55 MĀ³ Per Mason 4 Brickwork in cement or lime mortar in jack arches 0.55 MĀ³ Per Mason 5 Half brick wall in partition 5 MĀ² Per Mason 6 Course rubble stone in lime or cement mortar including dressing 0.80 MĀ³ Per Mason 7 Random Rubble stone in lime or cement mortar 1 MĀ³ Per Mason 8 Stone arch work 0.4 MĀ³ Per Mason
  • 8. Sl. No Particular of Item Quantity Per Day 9 Lime concrete in foundation or floor 8.50 MĀ³ Per Mason 10 Lime concrete in roof terracing 6.0 MĀ³ Per Mason 11 Cement concrete M15 (1:2:4) 5.0 MĀ³ Per Mason 12 Reinforced Brickwork 1.0 MĀ³ Per Mason 13 R.C.C. Work 3.0 MĀ³ Per Mason 14 12 mm thick plastering with cement or lime mortar 8.0 MĀ² Per Mason 15 Pointing with cement or lime mortar 10.0 MĀ² Per Mason 16 White washing or colour washing - 3 coats 70.0 MĀ² Per white washer 17 White washing or colour washing - 1 coat 200.0MĀ² Per white washer
  • 9. Sl. No Particular of Item Quantity Per Day 18 Painting of doors or windows - 1 coat 25.0 MĀ² Per Painter 19 Painting large surface - 1 coat 35.0 MĀ² Per Painter 20 Distempering - 1 coat 35.0 MĀ² Per Painter 21 2.5 cm C.C. Floor 7.50 MĀ² Per Painter 22 Brick ballast 40 mm gauge 0.75 MĀ³ Per Labourer 23 Breaking of brick ballast 25 mm gauge 0.55 MĀ³ Per Labourer 24 Breaking of stone ballast 40 mm (1 Ā½ ) gauge 0.40 MĀ³ Per Labourer 25 Breaking of stone ballast 25 mm (1ā€³) gauge 0.25 MĀ³ Per Labourer 26 Flagstone dressing 1.50 MĀ² Per Stone Cutter
  • 10. Sl. No Particular of Item Quantity Per Day 27 Earthwork excavation in ordinary soils 3.00 MĀ³ Per Beldar/Mazdoor 28 Earthwork excavation in hard soils 2.00 MĀ³ Per Beldar/Mazdoor 29 Excavation in rock 1.00 MĀ³ Per Beldar/Mazdoor 30 Sand filling in plinth 4.00 MĀ³ Per Beldar/Mazdoor 31 No. of Bricks laid by a mason in brickwork upto a height of 3 M 600 Bricks Per Mason 32 Amount of work done by a Mazdoor per day. (i) Mix (ii) Deliver Brick (iii) Deliver Mortar 3 MĀ³ 4000 Noā€™s 5.50 MĀ³ Mortar per Mazdoor Per Mazdoor Per Mazdoor
  • 11. Labour Required for Different Works: I. Earthwork per 28.30 Cu.m : - 1) Excavation in foundation, trenches etc., in ordinary soil including disposal upto 30 m and lift of 1.5 m - 5 beldar, 4 mazdoor can do 28.30 cu .m of work per day. 2) Reļ¬lling excavated earth in foundation, plinth etc., including consolidation in 15 cm layer - 3 beldars, 2 mazdoor and 1/2 Bisti can do 28.30 cu .m per day. 3) Disposal of surplus earth within a lead of 30 m that requires - 1 Mazdoor can do 2.83 cu . m per day. II. Cement Concrete Work per 2.83 Cu . m : - 1) Laying of cement concrete requires - 2 beldars, 3 Mazdoors, 3/4 Bisti and 1/4 Mason can do a 2.83 cu . m of work per day.
  • 12. III. R. C. C. Work : - 1) Laying of Reinforced concrete requires - 3 Beldars, 3 Mazdoors, 4/3 Bisti and 1/2 Mason can do a 2.83 cu . m per day. 2) Centering and shuttering for ļ¬‚at surface requires - 4 Beldars and 4 Carpenters can do 9.60 Sq .m per day. 3) Reinforcement work for R.C.C requires - 1 Black smith , 1 Beldar can bend and place in position one Quintal of steel. IV. Stone Work for 2.83 cu . m : - 1) Random Rubble Masonry for foundation requires - 3 Masons, 3 Beldars, 2 Mazdoors and 1/4 Bisti can do 2.83 cu . m of work per day. V. Brick Work for 2.83 cu . m : - 1) First Class Brickwork in 1:4 cement mortar in super structure, partition works, junctions of roof, parapet wall etc., requires - 2 Ā¼ Masons, 4 Ā½ Mazdoors, and 1/2 Bisti can do 2.83 cu .m of work per day.
  • 13. VI. Wood Work : - 1) For the frames of doors and windows - 2 Carpenters and 1 Beldar can work 0.18 cu . m of wood equivalent to 4 door frames 7.50 X 10.00 cm of 1.20 m X 2.10 m per day. 2) For panel, glazed, shutters requires - 15 Carpenters and 4 Beldars can make and ļ¬x 4 shutters 40 mm thick of size 2 M X 1.15 M per day. Quantity of wood for shutter is 0.075 mĀ³. VII. Iron Work : - 1) Fixing 40 mm X 3 mm X 38 cm ļ¬‚at iron fasteners requires - 1 Blacksmith, 1 Mason, 1 Beldar can ļ¬x 36 fasteners per day. 2) Fixing 16 mm dia mild steel rod requires - 1 Blacksmith, 2 Carpenters and 3 Beldars can ļ¬x 16.50 m per day.
  • 14. VIII. Flooring : - 1) 4 cm thick cement concrete ļ¬‚ooring of 40 Sq . m requires - 5 Masons, 4 Beldars, 3 Mazdoors and 1 Bisti per day. For mixing, laying and ļ¬nishing. IX. Finishing : - 1) plastering with any mortar 12 mm thick requires - 3 Masons, 3 Mazdoors and 1 Bhisti can plaster 40 sq. m per day. 2) White Washing / Colour Washing ( 3 coats) requires - 1 White washer and 1 Mazdoor can do 60 sq. m per day. 3) Painting 2 coats on wood (or) steel requires - 3 Painters and 2 Mazdoors can paint 10 sq. m per day.
  • 15. Rate of Material: ( Consider as per the local market) Cement - ā‚¹. 350 / bag Steel - ā‚¹. 45,000 / tonne 20 mm Coarse Aggregate - ā‚¹. 5,200 / unit 40 mm Coarse Aggregate - ā‚¹. 4,500 / unit Bricks - ā‚¹ 4,500 / 1000 Noā€™s Sand - ā‚¹. 3,500 / unit Labour - 1st Class Mason - ā‚¹ 700 / day Labour - 2nd Class Mason - ā‚¹. 500 / day Man Mazdoor - ā‚¹. 350 / day Women Mazdoor - ā‚¹. 250 / day
  • 16. Lead Statement: - The distance between the source of availability of material and construction site is known as ā€œLeadā€ and is expected in Km. the cost of conveyance of material depends on lead. - This statement will give the total cost of materials per unit item. It includes initial cost, conveyance loading, unloading, stacking charges etc., - The rate shown in the lead statement are for metalled road and include loading and stacking charges. - The environmental lead on the metalled roads are arrived by multiplying by a factor a) For metal tracks - Lead X 1.0 b) For cartz tracks - Lead X 1.1 c) For sandy tracks - Lead X 1.4
  • 17. 1 Unit = 100 Cu feet = 2.83 Cu m Unit weight of Steel = 7850 Kg / mĀ³ Unit weight of Cement = 1440 Kg / mĀ³ Unit weight of Fine Aggregate = 1450 to 1600 Kg/mĀ³ Unit weight of Coarse Aggregate = 1450 to 1500 Kg/mĀ³ 1 Cu m of cement is how many bags? 1 Bag of Cement = 50 Kg Density of Cement = 1440 Kg/mĀ³ 1 Bag of cement Volume is--- 1 mĀ³ bag has 1440 kg of cement For 50 kg cement bag volume is 0.034 m 1/0.034 = 28.8 bags - Say 30 Bags.
  • 18. Note: For 1 mĀ³ wet concrete = 1.52 mĀ³ dry volume of concrete approximately Ex : M15 Grade 10 Cu m wet concrete material (1:2:4) but entire 52% to 54 % of dry material will be added to it. = 10.00 + 10.00 X (52 / 100) = 10.00 + 5.20 = 15.20 1 Cu m of wet concrete in dry material is = 15.2/10 = 1.52 1 Cu m of wet concrete = 1.52 unit dry material. M5 = 1:5:10 ( Cement : Sand : Aggregate) M7.5 = 1:4:8 ( Cement : Sand : Aggregate) M10 = 1:3:6 ( Cement : Sand : Aggregate) M15 = 1:2:4 ( Cement : Sand : Aggregate) M20 = 1:1.5:3 ( Cement : Sand : Aggregate) M25 = 1:1:2 ( Cement : Sand : Aggregate)
  • 19. Consider for 10 mĀ³ M5 (1:5:10) 15.20/16 = 0.95 cu m Cement = 0.95x1 = 0.95 = 0.95 X 1440 = 1368 kg = 1368/50 = 27.36 bags Sand = 0.95 X 5 = 4.75 Cu m Coarse Aggregate = 0.95 x 10 =9.50 Cu m Cost of Cement = 27.36 X 350/bag = ā‚¹. 9576.00 Cost of F.A / Sand = 4.75 X 1236.75/Cu m = ā‚¹. 5874.56 Cost of C . A = 9.50 X 1590.11/ cu m = ā‚¹. 15106.04
  • 20. M7.5 ( 1:4:8) Calculate for the 10 cu m 15.20/(1+4+8) = 15.20/13 = 1.17 Cu m Cement = 1.17x1 = 1.17 cu m = 1.17x 1440 = 1684.8 /50 = 33.70 Bags Sand = 1.17 x 4 = 4.68 Cu m C.A = 1.17 x 8 = 9.36 cu m Cost of the Materials: Cement = 33.70 x 350 = ā‚¹. 11795.00 Sand/ F.A = 4.68 x 1236.75 = ā‚¹. 5787.99 C.A = 9.36 x 1590.11 = ā‚¹. 14883.43
  • 21. M10 (1:3:6) Consider 10 cu m 15.20 / 10 = 1.52 cu m Quantity of the Materials: Cement = 1.52 Cu m = 1.52 x 1440 = 2188.80 Kgā€™s = 2188.8/50 = 43.78 Baga Sand = 1.52 x 3 = 4.56 cu m C.A = 1.52 x 6 = 9.12 cu m Cost of Material: Cement = 43.78 x 350 = ā‚¹. 15323.00 Sand = 4.56 x 1236.75 = ā‚¹. 5639.58 C.A = 9.12 x 1590.11 = ā‚¹. 14501.80
  • 22. M15 ( 1:2:4) Consider for 10 Cu m. 15.20/7 = 2.17 cu m Quantity of Material: Cement = 2.17 cu m = 2.17 x 1440 =3124.80 kg = 3124.8/50 = 62.50 Bags Sand= 2.17 x 2 = 4.34 cu m C.A = 2.17 x 4 = 8.68 cum Cost of Materials: Cement = 62.50 x 350 = ā‚¹. 21875.00 Sand = 4.34 x 1236.75 = ā‚¹. 5367.49 C.A = 8.68 x 1590.11 = ā‚¹. 13802.15
  • 23. M 20 (1:1.5:3) - Consider 10 Cu m 15.2/1+1.5+3) = 15./ 5.5 = 2.76 cu m Quantity of the materials: Cement = 2.76x1 = 2.76 cu m = 2.76 x 1440 = 3974.40kg = 79.50 bags Sand = 2.76 x 1.5 = 4.14 cu m C.A = 2.76 x 3 = 8.28 cu m Cost of the Materials: Cement = 79.50 bags x 350/bag = 27825.00/ 10 cu m = 2782.50/ cu m Sand = 4.14 x 1236.75 = 5120.14 / 10 cu m = 512.00 / cu m C.A = 8.28 x 1590.11 = 13166.00/ 10 cu m = 1316.60/ cu m
  • 24. M25 ( 1:1:2) Consider 10 Cu m 15.20/4 = 3.80 cu m Quantity of the Materials: Cement = 3.80 cu m = 3.80 x 1440 = 5472 kgs = 109.44 Bags Sand/ F.A = 3.80 x 1 = 3.80 cu m C.A = 3.80 x 2 = 7.60 cu m Cost of the Materials: Cement = 109.44 x 350/bag = 38304.00/10 cu m = 3830.40/ 1 cu m Sand/ F.A = 3.80 x 1236.75 = 4699.65/10 cu m = 470.00/ 1 cu m C.A = 7.60 x 1590.11 = 12084.83/ 10 cu m = 1208.48 / 1 cu m
  • 25. Example - 1. Calculate the cost of the concrete of M5 grade, take 10 cu m and ļ¬nd the 1 cu m cost? 1st class mason - 0.5 Noā€™s 2nd Class Mason - 1.5 Noā€™s Man Mazdoor - 12 Noā€™s Women Mazdoor - 18 Noā€™s and Curing purpose - 4 Noā€™s Assume water charges 1 Ā½ % of total cost and Contractor proļ¬t is 15% of the total cost. Solution: For M5 Grade of Concrete mix proportion is 1:5:10 15.2/(1+5+10) = 15.2/16 = 0.95 mĀ³
  • 26. Sl. No Particulars Quantity Rate in ā‚¹. Per unit Amount in ā‚¹. 1 Materials Cement Fine Aggregate/Sand Coarse Aggregate 0.95 x 1 = 0.95 mĀ³ 0.95 x 1440 = 1368 kgā€™s 1368/50 = 27.36 bags 0.95 x 5 = 4.75 mĀ³ 0.95 x 10 = 9.50 mĀ³ 350/- 1236.75 1590.11 Bag MĀ³ mĀ³ 9576.00 5874.56 15106.04 2 Labour 1st Class Mason 2nd Class Mason Man Mazdoor Women Mazdoor Curing purpose 0.5 1.5 12 18 4 700 500 350 250 250 Day Day Day Day Day 350.00 750.00 4200.00 4500.00 1000.00 TOTAL COST ā‚¹. 41356.60
  • 27. Add water charges (1 Ā½ %) of total cost. = ā‚¹. 41,356.60 X (1.5/100) = 620.35 Say ā‚¹, 620/- = ā‚¹. 620.00 Add Contractor Proļ¬t (15%) of total cost. = ā‚¹. 41,356.60 X (15/100) = 6203.49 Say ā‚¹. 6203.00 = ā‚¹. 6203.00 Total Cost = ā‚¹. 41,356.60 + 620.00 + 6203.00 = ā‚¹. 48,179.60 Sundries = ā‚¹. 820.40 Total Cost for 10 mĀ³ = ā‚¹. 49,000=00 Cost of 1 mĀ³ = ā‚¹. 49,000/10 = ā‚¹. 4,900.00
  • 28. Example - 2: Calculate the cost of the concrete of M15 Grade, take 10 mĀ³ and ļ¬nd the 1 mĀ³cost?. 1st Class mason - 0.5 Noā€™s, 2nd class mason - 1 No, Man mazdoor - 12 Noā€™s, women mazdoor - 18 Noā€™s and curing purpose - 4 noā€™s. Solution: M15 - 1:2:4 15.2 / 7 = 2.17 mĀ³ Sl. No Particulars Quantity Rate in ā‚¹. Per unit Amount in .Rs 1 Materials Cement Sand Coarse Aggregate 2.17*1440= 3124.80kgs=62.50 bags 2.17*2 = 4.34mĀ³ 2.17*4 = 8.68mĀ³ 350 1236.75 1590.11 Bag MĀ³ mĀ³ 21875.00 5367.50 13802.15
  • 29. Sl. No Particulars Quantity Rate in ā‚¹. Per unit Amount in .Rs 2 Labour 1st class Mason 2nd class mason Man mazdoor Women mazdoor 0.5 1.0 12.0 18+4=22.0 700 500 350 250 Day Day Day day 350.00 500.00 4200.00 5500.00 Total Cost ā‚¹. 51,594.65 Water Charges - (1 Ā½ %) of total cost: = 51594.65 x (1.5/100) = 773.91 say Rs.774.00 Add contractor proļ¬t (15%) of total cost = 51594.65 x (15/100) = Rs.7739.00 Total Cost = 51,594.65 + 774.00 + 7739.00 = Rs. 60,107.65 Sundries = Rs.892.35 = Rs. 892.35 Cost of 10 mĀ³ cement concrete of M15 grade = Rs. 61,000.00 Cost of 1 mĀ³ cement concrete of M15 Grade = 61,000/10 = Rs. 6,100.00 / mĀ³
  • 30. Example - 3: Calculate the cost of the concrete of M25 grade and ļ¬nd the one cu m cost?. 1st class mason - 1.5 Noā€™s, 2nd class mason - 2 Noā€™s, Man mazdoor - 12 Noā€™s, Women mazdoor - 18+4, water charges 1 Ā½ % of total cost and consider the contractor proļ¬t is 12 % of total cost. Solution: Grade of Concrete = M25. Mix Proportion: 1:1:2 1.52 / 4 = 0.38 mĀ³ Sl. No Particulars Quantity Rate in ā‚¹. Per unit Amount in Rs. 1 Materials Cement Sand Coarse Aggregate 0.38*1440 =547.20 kgā€™s = 10.90 bags 0.38*1 = 0.38 mĀ³ 0.38*2 = 0.76 mĀ³ 350 1236.75 1590.11 Bag MĀ³ mĀ³ 3815.00 470.00 1208.48
  • 31. Sl. No Particulars Quantity Rate Per unit Amount in Rs. 2 Labour 1st Class mason 2nd Class Mason Man mazdoor Women mazdoor 1.5 2.0 12 22 700/- 500/- 350/- 250/- Day Day Day Day 1050.00 1000.00 4200.00 5500.00 Total Cost ā‚¹. 17259.00 Add Water Charges 1 Ā½ % of Total cost = 17259 x (1.5/100) = 258.88 Say ā‚¹. 259.00 Add Contractor Proļ¬t 12% of total cost = 17259 x (12/100) = ā‚¹. 2071.00 Cost of 1 mĀ³ cement concrete of M25 Grade = 17259 + 259 + 2071= ā‚¹. 19589.00 Sundries = ā‚¹. 411.00 = ā‚¹. 20,000.00
  • 32. BRICKWORK Brickwork with Standard Bricks ( Calculation of material required for brickwork) 1. Take a wall of 1 Ā½ brick thickness i.e. 30 cm, nominal thickness of 20 m length and 5 m height. 2. Nominal volume = Length X width X Height = 20.00 X 0.30 X 5.00 = 30.00 Cu .m 3. Normal mortar joint will be less than 1 cm, taking 1 cm mortar joint, the actual thickness of the wall be 29 cm. Actual Volume = Length X Width X Height = 20.00 X 0.29 X 5.00 = 29.00 Cu . m 4. Number of Standard bricks ( 20 X 10 X 10 Cm) = 29.00 / (0.2x0.1x0.1) = 14500 Noā€™s
  • 33. 5. This 14500 no. of bricks is for 29 MĀ³ Therefore Number of bricks per MĀ³ ( Nominal Volume) = 14500 / 30 = 483.30 - Say 484 Noā€™s 6. Consider 5% of breakage, wastage etc.,. This may be taken as 500 no.of bricks. Therefore 1 MĀ³ requires 500 no. of bricks. Mortar Calculations: Mortar requirement = Actual Volume of brickwork - Net volume of bricks. = 29.00 - (0.19 x 0.09 x 0.09) x 14500 = 6.68 MĀ³ For frog ļ¬lling, for use of cut bricks, for bonding, for uniform joints, wastages etc., 15% extra mortar may be required. Therefore the Volume of Mortar = 6.68 + (6.685 X 15/100) = 7.688 MĀ³ ( Wet Volume)
  • 34. For dry volume increase the wet volume by 25% = 1.25 X 7.68 MĀ³ = 9.61 MĀ³ For 30 Cu .m of brick work, dry volume of mortar = 9.61 MĀ³ For 1 Cu .m of brick work = 0.32 MĀ³ For 10 Cu .m of brick work, dry volume of mortar = 0.32 / 10 = 3.20 MĀ³ For 10 Cu .m of brick work, No.of bricks = 5000 Noā€™s Dry volume of mortar = 3.20 MĀ³ Brick Masonry : Brick size with mortar = (20 x 10 x10) CmĀ³ Brick size without mortar = (19 x 9 x 9) CmĀ³
  • 35. Length = 20 m, Thickness = 1 Ā½ brick wall Height = 3 m. Nominal volume of Brick wall = 20 x 0.3 x 3 = 18 MĀ³ Actual volume of 1 brick = 0.19 x 0.09 x 0.09 = 1.539 x 10ā» Ā³ Example : - 1 Brick volume = 20 x 10 x 10 cmĀ³ = 2000 cmĀ³ 0.002 MĀ³ For a volume of 18 mĀ³, No.of bricks = 18 / 0.002 = 9000 bricks 1 MĀ³ = 9000 / 18 = 500 Bricks.
  • 36. Example : - Total volume of 500 bricks = 500 x 0.20 x 0.10 x 0.10 = 1 MĀ³ Modular brick volume for 500 bricks = 500 x 0.19 x 0.09 x 0.09 = 0.769 MĀ³ Volume of mortar = 1 - 0.769 = 0.231 MĀ³ Cement = (0.231 x 1)/7 = 0.033 MĀ³ Mortar = (0.231 /7) x 6 = 0.198 MĀ³ Density of Cement = Weight / Volume = 1440 Kg / mĀ³ 1 MĀ³ = 1440 kg 1 Bag = 50 kg 1 Bag = 50 / 1440 = 0.034 MĀ³
  • 37. Cement Mortar :- 1:6 Wall = 10.00 X 0.23 X 3.00 m = 6.90 mĀ³ For 1 mĀ³ = 1/Brick volume= 1/ (0.1 x 0.1 x 0.2) = 1/0.002 = 500 Noā€™s Bricks for 1 cu m = 500 Noā€™s For 6.90 Cu m = 6.90 X 500 = 3450 Noā€™s (or) 6.9/0.002 = 3450 Noā€™s For 10 Cu m = 10/0.002 = 5000 Noā€™s For 10 cu m of Brick work with CM (1:6) 70% of Brick volume = 7 cu m 30% of Cement Mortar = 3 cu m
  • 38. The quantity of material for cement mortar - (1:6) Cement = 3 / (1+6) = 3/7 = 0.42 mĀ³ Sand/F.A= 0.42 X 6 = 2.52 mĀ³ Cement Mortar for 10 Cu m of Brick Work Mortar No of Bricks Cement Fine Aggregate/Sand 1:2 5000 1.0 mĀ³ 2.0 mĀ³ 1:3 5000 0.75 mĀ³ 2.25 mĀ³ 1:4 5000 0.60 mĀ³ 2.40 mĀ³ 1:5 5000 0.50 mĀ³ 2.50 mĀ³ 1:6 5000 0.43 mĀ³ 2.58 mĀ³
  • 39. Labour Required for 10 Cu m Brick Work: 1st Class Mason - 0.50 Noā€™s 2nd Class Mason - 1 No. Man Mazdoor - 12 Noā€™s Women Mazdoor - 12 Noā€™s Watering / Curing - 2 Noā€™s
  • 40. Example - 4: Calculate the quantity of cement, number of bricks, quantity of sand for C.M (1:6) for 1 Ā½ brick thick, take the length of wall is 20 m and height of wall is 5 m. Solution: Volume of wall = Length X Breadth X Height 20.00 X 0.30 X 5.00 = 30 Cu m Number of bricks = 30 /0.002 or 30 X 500 = 15,000 Noā€™s Cement Mortar = 1:6 Quantity of cement mortar ( 30%) - 9 mĀ³ Quantity of Cement = 9 / (1+6) = 9/7 = 1.29 mĀ³= 1.29 x 1440 = 1857.6 kg = 37.15 bags X 350/- = Rs.13003.00 Quantity of F.A. = 1.29 X 6 = 7.74 cu m = 1236.75 = Rs. 9572.00 Bricks = 15000 = 4500/1000 = Rs. 67500.00
  • 41. For 10 Cu m For 30 Cu m 1st ClassMason - 0.50 Noā€™s 1 st Class Mason - 1.50 Noā€™s 2nd Class mason - 1 No 2nd Class Mason - 3.00 Noā€™s Man Mazdoor - 12 Noā€™s Man Mazdoor - 36 Noā€™s Women Mazdoor - 12 Noā€™s Women Mazdoor - 36 Noā€™s Curing - 2 Noā€™s Curing - 6 Noā€™s 1St Class Mason - 1.50 X 700 = Rs.1050.00 2nd Class Mason - 3.00 X 500 = Rs.1500.00 Man Mazdoor - 36 X 350 = Rs. 12600.00 Women Mazdoor - 36 X 250 = Rs. 9000.00 Curing - 6 X 250 = Rs. 1500.00 Total Cost = Cost of the Material + Cost of the Labour = Rs. 1,15,725.00
  • 42. Add water charges @ 1 Ā½ % = 115725x1.5/100 = Rs.1736.00 Add Contractor Proļ¬t @ 15% = 115725 X 15/100 = Rs.17359.00 TOTAL COST IN Rs. 1,15,725 + 1,736 + 17,359 = Rs. 1,34,820.00 Sundries = Rs. 180.00 Scaffolding = Rs. 5,000.00 Total Cost in Rs. 1,40,000.00 Example - 5: Calculate the quantity of cement, number of bricks, quantity of sand for C.M (1:5) for 1 Ā½ brick thick, take the length of wall is 15 m and height of wall is 3.5 m.
  • 43. Solution: Given data - Length of Wall = 15.00 m Height of Wall = 3.50 m Thickness of Wall = 1 Ā½ brick wall = 0.30 m Cement Mortar = 1:5 Volume of Wall= 15.0 X 0.30 X 3.50 = 15.75 MĀ³ Quantity of cement Mortar (30%) = 4.73 MĀ³ Quantity of Cement = 4.73 /(1+5) = 4.73 / 6 = 0.79 mĀ³ = 0.79 / 0.034 = 23 Bags. Quantity of Sand / F.A = 0.79 X 5 = 3.95 mĀ³ Number of bricks = 15.75 / 0.002 = 7875 Noā€™s Cost of Cement = 23 bags X 350/- = ā‚¹. 8050.00 Cost of Sand/F.A = 3.95 X 1236.75 = ā‚¹. 4885.00 Cost of Brick = 7875 X 4.50 = ā‚¹. 35438.00 Total Cost of the Material - Rs. 48373.00
  • 44. Labour for 15.75 Cu . m 1st Class Mason - 0.788 Noā€™s X Rs. 700 = Rs. 551.60 2nd Class Mason - 1.575 Noā€™s X Rs. 500 = Rs. 787.50 Man Mazdoor - 18.90 Noā€™s X Rs. 350 = Rs. 6615.00 Women Mazdoor - 18.90 Noā€™s X Rs. 250 = Rs. 4725.00 Curing purpose - 3.15 Noā€™s X Rs. 250 = Rs. 787.50 Total Labour Cost = Rs. 13466.60 TOTAL COST = Total cost of the Material + Total cost of the Labour = Rs. 48,373.00 + 13,466.60 = Rs. 61,839.60 Add Water charges (1 Ā½ %) = Rs. 61,839.60 X 1.5/100= Rs. 928.00 Add Contractor Proļ¬t (10%) = Rs. 61,839.60 X 10/100 = Rs. 6184.00 Total Cost = Rs. 61,839.6 + 928.0 + 6184.0 = Rs. 68,951.60 Sundries = Rs. 48.40 Scaffolding = Rs. 1,000.00 TOTAL COST = Rs. 70,000.00
  • 45. Example - 6: Estimate the 1st class brick work of a room size 3.50 m X 4.0 m and height is 3 m thickness of wall is 1 Ā½ brick wall. Mortar proportion is 1:4. Solution: Given data - Room dimensions - 3.5 X 4 m Thickness of wall - 0.30 m Height of wall - 3 m Total Volume of brick work = 2(0.15 + 4.00 + 0.15) + 2(0.15 + 3.5 + 0.15) = 8.60 + 7.60 = 16.20 m Volume = 16.20 X 0.30 X 3.00 = 14.58 Cu .m Volume of 1 mĀ³ of bricks = 500 Noā€™s Volume of 14.58 mĀ³ bricks 500 X 14.58 = 7290 Noā€™s
  • 46. Mortar proportion is 1:4 Dry Volume of mortar - 1 mĀ³ = 0.3 mĀ³ For 14.58 mĀ³ = 0.3 X 14.58 = 4.374 mĀ³ Volume of cement= 4.374 / (1+4) = 4.374 / 5 = 0.875 mĀ³ No of bags = 0.875/0.034 = 25 Bags Volume of F.A / Sand = 0.875 x 4 = 3.5 mĀ³ Cost of Bricks = 7290 x 4.5/- = Rs. 32,805.00 Cost of Cement = 25 X 350/- = Rs. 8750.00 Cost of F.A/Sand = 3.5 X 1236.75= Rs. 4328.60 Total cost of the Material = Rs. 45,883.60 Labour for 14.58 cu .m 1st class Mason - 0.73 Noā€™s Man Mazdoor - 17.50 Noā€™s 2nd Class Mason - 1.46 Noā€™s Women Mazdoor - 17.50 Noā€™s Curing - 3 Noā€™s
  • 47. 1st Class Mason - 0.73 X 700 = Rs. 511.00 2nd Class Mason - 1.46 X 500 = Rs. 730.00 Man Mazdoor - 17.5 X 350 = Rs. 6,125.00 Women Mazdoor - 17.50 X 250 = Rs. 4,375.00 Curing - 3 X 250 = Rs. 750.00 Total Labour Cost = Rs. 12,491.00 TOTAL COST = Cost of the Material + Cost of the Labour = Rs. 45,883.60 + 12,491.00 = Rs.58374.60 Add water charges (1 Ā½ %) = 58,374.60 X 1.5/100 = Rs.875.60 Add contractor charges (10%) = 58,374.60 X 10/100 = Rs. 5837.46 TOTAL COST = 58374.60+875.60+5837.46 = Rs. 65,087.66 Sundries = Rs. 412.34 Scaffolding = Rs. 4500.00 TOTAL COST OF THE 1ST CLASS BRICKWORK = Rs. 70,000.00
  • 48. Random Rubble Masonry For 10 Cu . m of Random Rubble Stone masonry. Add 25% of dry volume of material 10.00 + [10.00 X (25/100)] = 12.50 Cu . m Take 42% of Cement Mortar = 4.20 Cu m Cement , sand mix Proportion is - 1 : 6 Volume of Cement = 4.20 /(1+6) = 4.20/7 = 0.60 Cu . m Volume of Sand/F.A = 0.60 X 6 = 3.60 Cu . m
  • 49. Example : 7 Calculate the cost of the R.R.S masonry for 1 Cu . m. The ratio of mortar is 1:6. The cost of boulders for 1 Cu . m is ā‚¹.800/-, Labour 1st class mason - 0.5, 2nd class mason - 12 Noā€™s, man mazdoor - 10 Noā€™s, women mazdoor - 10 Noā€™s. For R.R.S masonry volume 10 Cu .m is taken as 12.5 cu . m. For 1 Cu . m = 1.25 Cu . m. MORTAR CEMENT SAND 1: 3 ( Cement : Sand) 1.0 cu . m 3.0 Cu . m 1: 4 ( Cement : Sand) 0.85 Cu . m 3.40 Cu . m 1: 5 ( Cement : Sand) 0.70 Cu . m 3.5 Cu . m 1 : 6 ( Cement : Sand) 0.60 Cu . m 3.60 Cu . m 1 : 2 ( Lime : Sand) 1.60 Cu . m of Lime 3.20 Cu . m 1 : 3 ( Lime : Sand) 1.20 Cu . m of Lime 3.60 Cu . m
  • 50. Solution: Given data:- CM (1:6), Volume of cement mortar for 10 MĀ³ - 42% = 4.20 MĀ³ Volume of Cement = 4.20 / (1+6) = 4.20/7 = 0.60 mĀ³ 0.60 / 0.034 = 17.64 bags Say 18 Bags Volume of Sand = 0.60 X 6 = 3.60 mĀ³ Volume of Boulders = 12.50 mĀ³ Sl.No Particulars Quantity Rate Per Amount in ā‚¹. 1 Materials a. Cement b. Sand c. Boulders 18 bags 3.60 cu .m 12.50 cu .m 350.00 1236.75 800.00 Bag Cu m Cu m 6300.00 4452.30 10,000.00
  • 51. Sl. No Particulars Quantit y Rate Per Amount in ā‚¹. 2 Labour a. 1st class mason b. 2nd class mason c. Man mazdoor d. Women mazdoor 0.50 Noā€™s 12 Noā€™s 10 Noā€™s 10 Noā€™s 700.00 500.00 350.00 250.00 Day Day Day Day 350.00 6000.00 3500.00 2500.00 33,102.30 3 Add water charges - (1 Ā½ %) 496.50 4 Add contractor charges 10% 3310.23 Sundries 90.97 TOTAL COST FOR 10 MĀ³ 37,000.00 For 1 MĀ³ Cost of R.R.S Masonry 37000/10 ā‚¹. 3,700.00
  • 52. U. C. R. S. MASONRY U. C. R. S. MASONRY FOR 10 Cu. M Take Cement Mortar - 1:6 U.C.R.Stone for 10 Cu m - Add 25% dry volume of material = [10.00 + (10.00+25/100)] = 12.50 Cu m Volume of Stone can take = 12.50 Cu.m for 10 Cu . m Volume of cement mortar take - 40 % = 4.00 Cu . m for 10 Cu .m 4.00 Cu. m Cement Mortar Volume of cement = 4.00 / (1+6) = 4/7 = 0.57 Cu . m Volume of sand = 0.57 X 6 = 3.42 Cu . m
  • 53. MORTAR CEMENT SAND 1: 3 ( Cement : Sand) 1.00 Cu . m 3.00 Cu . m 1: 4 ( Cement : Sand) 0.80 Cu . m 3.20 Cu . m 1: 5 ( Cement : Sand) 0.67 Cu . m 3.35 Cu . m 1 : 6 ( Cement : Sand) 0.60 Cu . m 3.60 Cu . m Example : 8 Calculate the cost of the U.C.R.S masonry for 1 Cu . m. The ratio of mortar is 1:4. The cost of boulders for 1 Cu . m is ā‚¹.1200/-, Labour 1st class mason - 0.5, 2nd class mason - 12 Noā€™s, man mazdoor - 10 Noā€™s, women mazdoor - 10 Noā€™s. For U.C.R.S masonry volume 10 Cu .m is taken as 12.5 cu . m.
  • 54. Solution: Given data:- CM (1:4), Volume of cement mortar for 10 MĀ³ - 40% = 4.00 MĀ³ Volume of Cement = 4.00 / (1+4) = 4.00/5 = 0.80 mĀ³ 0.80 / 0.034 = 23.53 bags Say 24 Bags Volume of Sand = 0.80 X 4 = 3.20 mĀ³ Volume of Stone = 12.50 mĀ³ Sl.No Particulars Quantity Rate Per Amount in ā‚¹. 1 Materials a. Cement b. Sand c. Boulders 24 bags 3.2 cu .m 12.50 cu .m 350.00 1236.75 1200.00 Bag Cu m Cu m 8400.00 3957.60 15,000.00
  • 55. Sl. No Particulars Quantity Rate Per Amount in ā‚¹. 2 Labour a. 1st class mason b. 2nd class mason c. Man mazdoor d. Women mazdoor 0.50 Noā€™s 12 Noā€™s 10 Noā€™s 10 Noā€™s 700.00 500.00 350.00 250.00 Day Day Day Day 350.00 6000.00 3500.00 2500.00 39,707.60 3 Add water charges - (1 Ā½ %) 595.60 4 Add contractor charges 10% 3970.76 Sundries & L.S 726.04 TOTAL COST FOR 10 MĀ³ 45,000.00 For 1 MĀ³ Cost of R.R.S Masonry ā‚¹. 45,000/10 ā‚¹. 4,500.00
  • 56. PLASTERING Calculation of quantity mortar and materials Area X thickness gives the quantity of mortar for uniform thickness, for ļ¬lling of the joints and to make up non uniform surface of wall. This may be increased by 30% which will give wet mixed mortar to get the total dry volume of materials it may be further increased by 25%. Material for 12 mm thick plastering in wall for 100 sq . m Wet mixed mortar for uniform layer = 12 mm = 0.012 x 100 = 1.20 Cu . m Adding 30% to ļ¬ll up the joints, uneven surface etc., Now the wet volume of mortar = {1.20 + [1.20 x (30/100)]} = 1.56 Cu . m
  • 57. 1.56 Cu . m of wet volume is converted into dry volume by increasing 25% Now dry volume of mortar = 1.56 + [1.56 x (25/100)] = 1.95 Cu . m Say 2.00 Cu . m Therefore Dry volume of mortar is 2 Cu . m ( For 100 Sq . m at 12 mm thickness) Material for 20 mm thick plastering As the thickness of the plaster is more, 20% of mortar is taken to ļ¬ll up the joints, unevenness etc., The quantity of wet mortar = 0.02 X 100 = 2.00 Cu . m Now the wet volume of mortar = 2.00 + [2.00 x (20/100)] = 2.40 Cu . m Volume of dry mortar = 2.40 + [ 2.40 x (25/100)] = 3.00 Cu . m
  • 58. Plastering 12mm thickness; Cement Mortar for 100 Sq.m Mortar Cement Sand / F.A 1:2 0.60 Cu.m [ 18 Bags] 1.20 Cu.m 1:3 0.5 Cu.m [ 15 Bags] 1.50 Cu.m 1:4 0.4 Cu.m [ 12 Bags] 1.60 Cu.m 1:5 0.35 Cu.m [ 10 Bags] 1.75 Cu.m 1:6 0.30 Cu.m [ 9 Bags] 1.80 Cu.m
  • 59. Plastering 20 mm thickness; Cement Mortar for 100 Sq.m Mortar Cement Sand / F.A 1:2 1.00 Cu.m [ 29 Bags] 2.00 Cu.m 1:3 0.75 Cu.m [ 22 Bags] 2.25 Cu.m 1:4 0.60 Cu.m [ 18 Bags] 2.40 Cu.m 1:5 0.50 Cu.m [ 15 Bags] 2.50 Cu.m 1:6 0.43 Cu.m [ 13 Bags] 2.60 Cu.m
  • 60. Requirement of Workmanship for Plastering for 100 Sq.m : Labour Quantity 1st Class Mason 0.35 Noā€™s 2nd Class Mason 10 Noā€™s Man Mazdoor 15 Noā€™s Women Mazdoor / Curing 0.75 Noā€™s
  • 61. Example - 9 : Estimate the plastering work thickness of 12 mm, area 100 sq.m for 1:6 Solution : volume = Wet mixed mortar for uniform layer = 12 mm = 0.012 x 100 = 1.20 Cu . m Thickness = 12 mm; Area= 100 sq.m 1.20 + 1.20 (30/100)= 1.56 Cu.m ( Wet Volume) 1.56 + 1.56 (25/100)= 1.95 Cu.m ( Dry Volume) Dry Volume = 1.95 Cu.m ā‰ƒ 2 Cu.m Cement = 2.00/(1+6) = 0.285 Cu.m X 1 = 0.285 Cu.m = 0.285 / 0.034 = 8.38 ā‰ƒ 8 Bags Sand = 0.285 X 6 = 1.71 Cu.m
  • 62. Sl.No Particulars Quantity Rate Per Amount in ā‚¹. 1 Materials a. Cement b. Sand 8 bags 1.71 cu .m 350.00 1236.75 Bag Cu m 8400.00 3957.60 2 Labour a. 1st Class Mason b. 2nd Class Mason c. Man Mazdoor d. Curing 0.35 No 10 Noā€™s 15 Noā€™s 0.75 No 700.00 500.00 350.00 250.00 Day Day Day Day 245.00 5000.00 5250.00 187.50 ā‚¹. 23,040.10 3 Add Water Charges (1 Ā½ %) ā‚¹. 345.60 4 Add Contractor Profit (10%) ā‚¹. 2304.01 Sundries & L.S Charges ā‚¹. 310.29 TOTAL COST FOR 100 Sq. M ā‚¹. 26,000.00
  • 63. For Pointing in Brick work for total dry volume of material is taken as 0.60 Cu.m for 100 Sq.m Example - 10 : Estimate the pointing work quantity 1:2 for 1200 Sq.m ? Solution : 0.60 Cu.m - 100 Sq.m ? - 1200 Sq.m 1200 Sq.m = (0.60 X 1200) / 100 = 7.20 Cu.m Cement = 7.20 / (1+2) = 2.40 Cu.m X 1 = 2.40 Cu.m = 2.40 / 0.034 = 70.58 ā‰ƒ 71 Bags Sand = 2.40 X 2 = 4.80 Cu.m
  • 64. Sl.No Particulars Quantity Rate Per Amount in ā‚¹. 1 Materials a. Cement b. Sand 71 Bags 4.80 Cu.m 350.00 1,236.75 Bag Cu.m 24,850.00 5,936.40 2 Labour a. 1st Class Mason b. 2nd Class Mason c. Man Mazdoor d. Curing 0.35 No 10 Noā€™s 10Noā€™s 0.50 No 700.00 500.00 350.00 250.00 Day Day Day Day 245.00 5,000.00 3,500.00 125.00 ā‚¹.39,656.40 3 Add Water Charges (1 Ā½ %) ā‚¹. 594.85 4 Add Contractor Profit (10%) ā‚¹. 3.965.64 Sundries & L.S Charges ā‚¹. 283.11 TOTAL COST FOR 100 Sq. M ā‚¹.44,500.00
  • 65. Cement Concrete Floor - The quantity of cement concrete may be calculated by multiplying area of ļ¬‚oor by the thickness. - The quantity of each material may be found same as the plain concrete of cement (PCC) . 1. For 2.5 cm cement concrete ļ¬‚oor for 100 MĀ² of area the quantity of cement concrete is 2.5 MĀ³. Now add 10% extra for unevenness of base concrete. 2.5 + 2.5 X (10/100) = 2.75 MĀ³ For neat cement surface ļ¬nishing additionally 0.20 MĀ³ (6 Bags) are required 2. For 100 MĀ³ cement concrete, the total dry volume of material is approximately increased by 50%. 2.75 + 2.75 X (50/100) = 4.125 MĀ³ 3. For 2 cm thick cement concrete ļ¬‚oor for 100 MĀ² area, the dry volume is 4.125 MĀ³.
  • 66. 4. For 4 cm thick cement concrete ļ¬‚oor for 100 MĀ² area, the dry volume is 4 MĀ³ Add 10%= 4 + 4 x (10/100) = 4.40 MĀ³ ( Wet Volume) Add 50% Dry volume = 4.40 + 4.40 X (50/100) = 6.60 MĀ³ Example - 11 : Estimate the 2.5 cm cement concrete ļ¬‚oor of 1:2:4 for 1 Sq.m ? Solution : 100 Sq . m = 2.50 MĀ³ of quantity of dry volume is = 4.125 MĀ³ Cement = 4.125 /(1+2+4) = 0.59 MĀ³ X 1 = 0.59 MĀ³ 1 Bag = 0.034 MĀ³ 0.59 MĀ³ = ? No.of bags = 0.59 / 0.034 = 17.35 ā‰ƒ 17 Bags Sand = 0.59 X 2 = 1.18 MĀ³ Coarse Aggregates = 0.59 X 4 = 2.36 MĀ³
  • 67. Note : [ For neat ļ¬nishing of ļ¬‚oor, the thickness of neat cement layer is 1.50mm. āˆ“ The cement paste requirement for 100 MĀ² = 0.0015 X 100 = 0.15 MĀ³ . Dry volume of cement is increased by 25% (For 100MĀ² only) = 0.15 + 0.15 X (25/100) = 0.187 MĀ³ ā‰ƒ 0.20 MĀ³ ] Surface ļ¬nishing for 100 Sq . m = 0.20 Cu . m
  • 68. Sl.No Particulars Quantity Rate Per Amount in ā‚¹. 1 Materials a. Cement b. Sand c. Coarse Aggregate 17 Bags 1.18 Cu .m 2.36 Cu.m 350.00 1,236.75 1590.11 Bag Cu.m Cu.m 5950.00 1459.36 3752.65 2 Labour a. 1st Class Mason b. 2nd Class Mason c. Man Mazdoor d. Curing 0.75 No 10 Noā€™s 10 Noā€™s 2 Noā€™s 700.00 500.00 350.00 250.00 Day Day Day Day 525.00 5,000.00 3,500.00 500.00 ā‚¹. 20,687.01 3 Add Water Charges (1 Ā½ %) ā‚¹. 310.30 4 Add Contractor Profit (10%) ā‚¹. 2068.70 Sundries & L.S Charges ā‚¹. 933.99 TOTAL COST FOR 100 Sq. M ā‚¹. 24,000.00 Cost for 1 Sq.M = ā‚¹. 24000 / 100 = ā‚¹. 240.00 ā‚¹. 240.00
  • 69. Example - 12 : Estimate the White Washing of 1 coat for 1 Sq.m area, Taking 100 Sq.m as the area 10 kg of white lime unslaked ? Solution : Sl.No Particulars Quantity Rate Per Amount in ā‚¹. 1 Materials White Lime unslaked 10 Kgā€™s 950.00 9.50 Quintal Kg 95.00 2 Glue Powder Lumpsum 30.00 L.S 30.00 3 Labour a. White Washer b. Men Mazdoor 0.70 (or) 2/3 Noā€™s 0.70 (or) 2/3 Noā€™s 500.00 350.00 Day Day 350.00 245.00 4 Sundries & Lump Sum 80.00 Total Cost in Rs. 800.00
  • 70. Add Water charges (1 Ā½ %) = Rs. 800 X )1.5/100) = Rs. 12.00 Add Contractor Charges (10%) = Rs. 800 X (10/100) = Rs. 80.00 Total Cost for 100 Sq.m = Rs. 800.00 + 12.00 + 80.00 = Rs. 892.00 Cost for 1 Sq.m of White Washing of 1 coat = Rs. 892.00 / 100 = Rs. 8.92