SlideShare a Scribd company logo
1 of 3
Download to read offline
SB Rail and Rail Infrastructure have each
developed significantly over the last 99
issues of this magazine, which perhaps
explains the relationship between the editorial
team and one of the most innovative on-track
plant suppliers in the UK today.
One has found its way on to the desks (and
into the hearts) of railway engineering
professionals up and down the country, and the
other has been at the forefront of introducing
the very latest on-track technologies to the UK
railway. This magazine has expertly chronicled
SB Rail’s new introductions and innovations
over the years and we would like to take the
opportunity of summarising these
achievements in this special 100th issue.
Pioneering new machines
SB Rail traces its lineage back through the
First Swietelsky Joint Venture partnership
formed in 2004. First Engineering introduced
the first new generation of on-track machines
built to the GM/RT 2400 requirements
ordering three Unimat designs from Plasser &
Theurer, beginning with the Unimat 08-
4x4/4S-RT in August 1997. Not only was this
the first Unimat in the UK, it was also the first
post-privatisation purchase of an on-track
machine demonstrating early leadership in the
market. This machine design rendered all
other S&C tampers in the UK and a large
portion of the plain line fleet obsolete.
The new machine was capable of tamping
both S&C and plain line track, equipped with
four tamping units each carrying four
individually tilting tines. The tamping units could
each be lifted and lowered independently and
traverse 930mm laterally allowing the straight
and turnout sections to be tamped in a single
pass with a synchronous three-rail lifting unit
providing additional lift.
The 08 tampers were soon followed by
the introduction of the first purpose-built for
the UK mobile flash-butt welder in August
1998. The APT 500L, otherwise known as
‘Sparky’, incorporated a number of design
features unique in the UK at the time,
including the transfer gearbox allowing the
welding head’s generator to be driven from the
truck engine and improved track access and
operational capabilities without the need for
overhead line isolation. Previously, the
process of flash-butt welding had been
confined to factory conditions and the use of
an aging fleet of long-welded rail trains. During
the rolling contact fatigue elimination
programme in the late 1990s, Sparky provided
a remote CWR production depot in the centre
of Glasgow to provide almost all of the CWR
required by the Scottish rail network.
Companies join forces
Now working in co-operation, First Engineering
and Swietelsky carried out the first tandem
tamping of S&C in the UK on ‘through
alignment’ works to a ladder of eight
crossovers at Bourne End on the West Coast
Main Line during Christmas working in
2004. Two 08-4x4/4S machines were linked
in a master/slave arrangement and controlled
by a single geometry design source using
Leica on-track telematics.
Following the formation of the First
Swietelsky Joint Venture, a further wave of
innovative new equipment was soon on its way.
The first Plasser & Theurer AFM 2000 RT was
delivered in March 2006 and offered a complete
track-finishing system combining ballast
regulation and stabilising work processes in a
single system. At that time, Rail Infrastructure
described the AFM as a ‘stretched limo’
version of the USP 5000 RT with the
A centenary of firsts
RAIL INFRASTRUCTURE 43
First Engineering’s Plasser & Theurer 08-4x4/4S-RT Unimat tamper is
pictured during acceptance testing at Derby. This was the first
post-privatisation on-track machine to be delivered.
First Engineering was an early purchaser
of the Plasser & Theurer Compact
type of tampers.
The First Engineering mobile flash-butt welder
‘Sparky’ is pictured in production mode.
On-Track Plant
SB Rail’s Gordon Suthorn discusses a reputation that has been built on innovation and ‘firsts’.
addition of a Dynamic Track Stabiliser
(DTS). The enhanced regulation capability
was enabled by a larger 18 tonne hopper
capacity coupled with an advanced ballast
profile measurement system used to precisely
determine locations of heavy or deficient
ballast. The AFMs support the UK tamping fleet
comprising mainly of tampers without DTS units,
however when an AFM is combined with an 09-
3X or 09-4S it creates a world class track
maintenance system. AFM remains the highest
performance track-finishing system available
anywhere in the world.
The award of a five-year track renewals
contract prompted the development of and
investment in more reliable plant to modernise
the operation of removing and relaying track.
First Swietelsky’s purchase of three Kirow KRC
250UK rail cranes, the first arriving in the
summer of 2006, represented a step-change in
capability. Improvements to the KRC 250
design for introduction in the UK included
60mph running in train formation, 15 tonnes
lifting capacity at 16 metres radius and
outriggers for heavier loads. SB Rail has since
developed a series of unique attachments and
enhancements making its fleet of KRC 250UKs
the most capable in the market and first choice
for S&C relaying and, in particular, modular
S&C. SB Rail’s KRC 500S and SG system
comprises two KRC 250UK cranes deployed in
a single formation with an integrated wagon
and tandem tensioning system. This negates
the need for down-rating and is capable of
installing all modular track designs and panels
up to and including ‘SG’ switches. Further
enhancements enabled by a unique robotic arm
include a 28 sleeper fully automatic relaying
beam and high output piling system.
High output
The First Swietelsky Joint Venture (JV)
partnership (now SB Rail) won the highly
coveted inaugural contract to commission,
operate and maintain Network Rail’s high output
track renewals fleet beginning in 2004. The JV
began the introduction of the first RM 900 RT
ballast cleaner and support MFS wagons in
August 2004, followed by the first P 95 UK track
renewal train in April 2005 and a second RM
900 RT and support MFS wagons in June of the
same year, bringing all these systems up to full
operational service on behalf of Network Rail.
The main systems were supported by a fleet of
09-3X-D-RT Dynamic tampers and USP 5000 RT
regulators. The introduction of the RM 900 RT
and P 95 UK heralded a step-change in plain
line track renewals capability in the UK, allowing
the team involved to deliver up to 300%
output improvements over conventional
systems and methodologies.
Whilst SB Rail was not the first to
introduce the 09-3X, it was the first to bring in
the Dynamic version. Swietelsky did later
acquire the only other 09-3X-RT machines in
the UK and brought these up to their intended
level of performance in Network Rail’s
National Plant Contract. The three-sleeper
tamping banks and continuous action of the
09-3X enables performance increases of up
to 40% over conventional machines and
increases tamping quality. Further features
include split design banks to allow single
sleeper tamping in the case of irregular
spacing, something the company certainly
made use of during the first high output
ballast cleaning campaign on the Midland
main line! The introduction of the Dynamic
version efficiently incorporated the tamping
and stabilisation work processes in a single
piece of equipment for the first time and has
been put to extensive use ever since.
Establishing the project infrastructure and
safe working methodologies for the deployment
of this fleet of new equipment was a
considerable challenge. It included creating
several high output operations bases,
establishing and continually improving the
logistics and maintenance regimes,
implementing Adjacent Line Open (ALO) working,
introducing Curve Alignment Laser (CAL) and
‘Tandem Drive’, raising hand-back speeds from
50mph to 80mph and driving the improvement
of track quality to the first ever 100% score
consistently achieved in the UK.
RAIL INFRASTRUCTURE 43
One of SB Rail’s two Plasser & Theurer AFM
2000 RT track-finishing machines.
Two Plasser & Theurer 09-3X-RT machines are
within SB Rail’s resources.
The SB Rail fleet includes three Kirow KRC250UK
cranes, one of which is pictured here
undertaking piling operations.
On-Track Plant
Over the course of the first high
output contract, the team created and
refined best practices and a blueprint enabling
the future expansion of the project whilst
delivering circa 300 miles of track renewals
activity with associated tamping, stabilising and
ballast finishing works on the Great Western,
East Coast and Midland main lines.
High Speed 1
Now to the Plasser & Theurer 09-32/4S
Dynamic, the most advanced high
performance tamping system available. This
Swietelsky machine is based in mainland
Europe, but since 2010 has been used by SB
Rail and Network Rail (HS1) working in
partnership to plan and deliver the tamping
and regulation campaigns on High Speed 1
infrastructure. The advantages of using the
09-32/4S Dynamic over conventional UK
machines include:
n Continuous action tamping for both plain
line and turnouts.
n Integrated track stabilising unit.
n Three rail lifting and four rail tamping.
n High output capacity - plain line rating
1,400m/h.
n Reduced track occupation of high speed
turnouts (1/46 turnouts on HS1).
n Sleeper end consolidator (increases
resistance to lateral displacement circa 4%).
In another first, this system has been
used on HS1 to maintenance tamp and DTS
S&C in one continuous cycle with significant
sustainability benefits.
It is not all about bigger and faster in
tamping though. In conjunction with HS1, SB
Rail introduced new technology for shortwave
tamping to complement its high output
campaign work and the concept of ‘Sprinter’
tamping was born in the UK. For anyone who
has not heard of Sprinter tamping yet, it is a
mechanised means of repairing shortwave
defects including faults within horizontal
transitions. The software targets only small
areas in need of geometrical repair, but since
this will be the subject of a detailed article in a
future issue of Rail Infrastructure we will leave
‘whistles wetted’ for now! Currently, SB Rail
has two UNIMAT 08-4x4 machines fitted to
work either in conventional or ‘Sprinter’ modes.
Recent developments
So here we are in 2014, 17 years after the first
08 UNIMAT and history is repeating itself with
SB Rail’s most recent fleet addition, the 09-
4x4/4S Dynamic. This is the ‘brother’ of the 09-
32/4S and another first in the UK. The 09-4x4
is equipped with the latest Plasser & Theurer
Intelligent Control System (P-IC 2.0), ‘intelligent’
DTS, DRP, CAL and RLD (Resistance to Lateral
Displacement) technologies. The tamping banks
are operated in manual, semi-automatic or fully-
automatic modes, depending on-site conditions
and the synchronous three-rail lifting unit
provides additional lift to S&C. The WIN ALC
computer provides complete guidance to the
machine’s levelling and lining systems whilst
the multi-channel DRP captures a series of track
quality measurements.
Designed and built for working in the field
for extended periods, the 09-4x4/4S tamps
S&C up to 40% faster and plain line up to 30%
faster in comparison with older machines. The
integrated intelligent DTS unit achieves rapid
and measured consolidation of the track,
restoring resistance to lateral displacement
and making higher speed hand-backs over
S&C a reality.
Conclusion
The last 99 issues of Rail Infrastructure have
intelligently informed the industry on a great
many new or improved items of plant and
equipment being put to use on Britain’s
railways. SB Rail is proud to have taken a
leading role developing and introducing the
very latest on-track technologies in the UK.
We look forward to pushing back
boundaries further and bringing in many more
‘firsts’ in the pursuit of ever more efficient
railway engineering methodologies in the
future. Our heartfelt thanks to Roger and Alex
and here’s to the next 100 issues!
Additional contributors: Craig Goldie
and Matt Whiting, Swietelsky.
44 RAIL INFRASTRUCTURE
On-Track Plant
SB Rail’s state-of-the-art Plasser & Theurer
09-4x4/4S Dynamic tamper.
Above: Plasser & Theurer 09-32/4S Dynamic tamper as first used on High Speed 1.
Below: Also first introduced on High Speed 1 by SB Rail has been Sprinter tamping.

More Related Content

What's hot

HI RAIL BROCHURE 3PNL LoRes
HI RAIL BROCHURE 3PNL LoResHI RAIL BROCHURE 3PNL LoRes
HI RAIL BROCHURE 3PNL LoResHank Holterman
 
Part 1 T-Track - Introduction
Part 1 T-Track - IntroductionPart 1 T-Track - Introduction
Part 1 T-Track - IntroductionSean Wilson
 
Brochure_-_Bulk_Material_Handling_and_Mining
Brochure_-_Bulk_Material_Handling_and_MiningBrochure_-_Bulk_Material_Handling_and_Mining
Brochure_-_Bulk_Material_Handling_and_MiningMarvin Smith
 
project report about brun standard company ltd
project report  about brun standard company ltdproject report  about brun standard company ltd
project report about brun standard company ltdsubhajit dutta
 
Gurit UK - Projects and Case Studies
Gurit UK - Projects and Case StudiesGurit UK - Projects and Case Studies
Gurit UK - Projects and Case StudiesAdam Davison
 
Yale Big Truck Flyer
Yale Big Truck Flyer Yale Big Truck Flyer
Yale Big Truck Flyer mattguye
 
Other capabilities by STF
Other capabilities by STFOther capabilities by STF
Other capabilities by STFMark Hirzel
 
Diesel locomotive works, varanasi presentation
Diesel locomotive works, varanasi presentationDiesel locomotive works, varanasi presentation
Diesel locomotive works, varanasi presentationShubham​ Yadav
 
Him cableways - An Introduction
Him cableways - An IntroductionHim cableways - An Introduction
Him cableways - An IntroductionTuneer Garga
 
Strategic analysis of communications based train control systems in the weste...
Strategic analysis of communications based train control systems in the weste...Strategic analysis of communications based train control systems in the weste...
Strategic analysis of communications based train control systems in the weste...Shyam Raman
 
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, Patiala
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, PatialaPresentation on Remanufacturing of Engine Block of a locomotive at DMW, Patiala
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, PatialaArjun Gaur
 
Diesel locomotive works, varanasi
Diesel locomotive works, varanasiDiesel locomotive works, varanasi
Diesel locomotive works, varanasiShubham​ Yadav
 
Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)
Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)
Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)Vivek Yadav
 
Brijeh yadav ppt
Brijeh yadav pptBrijeh yadav ppt
Brijeh yadav pptbky2756
 
Dlw summer trainning project electrical branch by shubhang pandey
Dlw summer trainning project electrical branch by shubhang pandeyDlw summer trainning project electrical branch by shubhang pandey
Dlw summer trainning project electrical branch by shubhang pandeyshubhangpandey5
 

What's hot (20)

HI RAIL BROCHURE 3PNL LoRes
HI RAIL BROCHURE 3PNL LoResHI RAIL BROCHURE 3PNL LoRes
HI RAIL BROCHURE 3PNL LoRes
 
Part 1 T-Track - Introduction
Part 1 T-Track - IntroductionPart 1 T-Track - Introduction
Part 1 T-Track - Introduction
 
Brochure_-_Bulk_Material_Handling_and_Mining
Brochure_-_Bulk_Material_Handling_and_MiningBrochure_-_Bulk_Material_Handling_and_Mining
Brochure_-_Bulk_Material_Handling_and_Mining
 
project report about brun standard company ltd
project report  about brun standard company ltdproject report  about brun standard company ltd
project report about brun standard company ltd
 
Btpl ver4
Btpl ver4Btpl ver4
Btpl ver4
 
Gurit UK - Projects and Case Studies
Gurit UK - Projects and Case StudiesGurit UK - Projects and Case Studies
Gurit UK - Projects and Case Studies
 
Yale Big Truck Flyer
Yale Big Truck Flyer Yale Big Truck Flyer
Yale Big Truck Flyer
 
Rail in the Philippines 2012
Rail in the Philippines 2012 Rail in the Philippines 2012
Rail in the Philippines 2012
 
Other capabilities by STF
Other capabilities by STFOther capabilities by STF
Other capabilities by STF
 
Diesel locomotive works, varanasi presentation
Diesel locomotive works, varanasi presentationDiesel locomotive works, varanasi presentation
Diesel locomotive works, varanasi presentation
 
Him cableways - An Introduction
Him cableways - An IntroductionHim cableways - An Introduction
Him cableways - An Introduction
 
Strategic analysis of communications based train control systems in the weste...
Strategic analysis of communications based train control systems in the weste...Strategic analysis of communications based train control systems in the weste...
Strategic analysis of communications based train control systems in the weste...
 
Maglev train
Maglev trainMaglev train
Maglev train
 
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, Patiala
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, PatialaPresentation on Remanufacturing of Engine Block of a locomotive at DMW, Patiala
Presentation on Remanufacturing of Engine Block of a locomotive at DMW, Patiala
 
Diesel locomotive works, varanasi
Diesel locomotive works, varanasiDiesel locomotive works, varanasi
Diesel locomotive works, varanasi
 
Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)
Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)
Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)
 
Brijeh yadav ppt
Brijeh yadav pptBrijeh yadav ppt
Brijeh yadav ppt
 
deep_orient
deep_orientdeep_orient
deep_orient
 
introuduction DLW varanaesi
introuduction DLW varanaesiintrouduction DLW varanaesi
introuduction DLW varanaesi
 
Dlw summer trainning project electrical branch by shubhang pandey
Dlw summer trainning project electrical branch by shubhang pandeyDlw summer trainning project electrical branch by shubhang pandey
Dlw summer trainning project electrical branch by shubhang pandey
 

Viewers also liked

Conclusiones gastritis
Conclusiones gastritisConclusiones gastritis
Conclusiones gastritisaletixilima
 
Presentation_ENG_full_07_06_16
Presentation_ENG_full_07_06_16Presentation_ENG_full_07_06_16
Presentation_ENG_full_07_06_16Andy Kozlov
 
Riski uzņēmumu IT nodrošināšanā. Situācijas anatomija.
Riski uzņēmumu IT nodrošināšanā. Situācijas anatomija.Riski uzņēmumu IT nodrošināšanā. Situācijas anatomija.
Riski uzņēmumu IT nodrošināšanā. Situācijas anatomija.HORTUS Digital
 
Resume upto august 2016
Resume upto august 2016Resume upto august 2016
Resume upto august 2016Chandan Raj
 
C OPERATOR
C OPERATORC OPERATOR
C OPERATORrricky98
 
Commission13 workshop 2015 01 commission 13 report
Commission13 workshop 2015 01 commission 13 reportCommission13 workshop 2015 01 commission 13 report
Commission13 workshop 2015 01 commission 13 reportilpscommission13
 
Distribucion binomial
Distribucion binomialDistribucion binomial
Distribucion binomialdaenma23
 
What have you learnt about technologies from the
What have you learnt about technologies from theWhat have you learnt about technologies from the
What have you learnt about technologies from thechristycy
 
Bruce Balfour Resume June 2016
Bruce Balfour Resume June 2016Bruce Balfour Resume June 2016
Bruce Balfour Resume June 2016Bruce Balfour
 
Shared Care Meeting 1 1.13.09hm
Shared Care Meeting 1  1.13.09hmShared Care Meeting 1  1.13.09hm
Shared Care Meeting 1 1.13.09hmCarol Gray, MHA
 
Sticky Note Audience Feedback
Sticky Note Audience FeedbackSticky Note Audience Feedback
Sticky Note Audience Feedbackmaryashtona2
 

Viewers also liked (16)

MARATUM - 2º Congreso Asociación AISLA
MARATUM - 2º Congreso Asociación AISLAMARATUM - 2º Congreso Asociación AISLA
MARATUM - 2º Congreso Asociación AISLA
 
Conclusiones gastritis
Conclusiones gastritisConclusiones gastritis
Conclusiones gastritis
 
Analysis Report
 Analysis Report  Analysis Report
Analysis Report
 
Presentation_ENG_full_07_06_16
Presentation_ENG_full_07_06_16Presentation_ENG_full_07_06_16
Presentation_ENG_full_07_06_16
 
Riski uzņēmumu IT nodrošināšanā. Situācijas anatomija.
Riski uzņēmumu IT nodrošināšanā. Situācijas anatomija.Riski uzņēmumu IT nodrošināšanā. Situācijas anatomija.
Riski uzņēmumu IT nodrošināšanā. Situācijas anatomija.
 
WorldHepatitisDay
WorldHepatitisDayWorldHepatitisDay
WorldHepatitisDay
 
Stephen Sandeman cv7
Stephen Sandeman cv7Stephen Sandeman cv7
Stephen Sandeman cv7
 
Resume upto august 2016
Resume upto august 2016Resume upto august 2016
Resume upto august 2016
 
C OPERATOR
C OPERATORC OPERATOR
C OPERATOR
 
Hb20S turbo Sedã
Hb20S turbo SedãHb20S turbo Sedã
Hb20S turbo Sedã
 
Commission13 workshop 2015 01 commission 13 report
Commission13 workshop 2015 01 commission 13 reportCommission13 workshop 2015 01 commission 13 report
Commission13 workshop 2015 01 commission 13 report
 
Distribucion binomial
Distribucion binomialDistribucion binomial
Distribucion binomial
 
What have you learnt about technologies from the
What have you learnt about technologies from theWhat have you learnt about technologies from the
What have you learnt about technologies from the
 
Bruce Balfour Resume June 2016
Bruce Balfour Resume June 2016Bruce Balfour Resume June 2016
Bruce Balfour Resume June 2016
 
Shared Care Meeting 1 1.13.09hm
Shared Care Meeting 1  1.13.09hmShared Care Meeting 1  1.13.09hm
Shared Care Meeting 1 1.13.09hm
 
Sticky Note Audience Feedback
Sticky Note Audience FeedbackSticky Note Audience Feedback
Sticky Note Audience Feedback
 

Similar to SB Rail Pioneers Railway Infrastructure Advancements

Uromac Catalogue 2014 (2)
Uromac Catalogue 2014 (2)Uromac Catalogue 2014 (2)
Uromac Catalogue 2014 (2)Peter de Ryk
 
CSRE UK Approach Linkedin Feb11
CSRE UK Approach Linkedin Feb11CSRE UK Approach Linkedin Feb11
CSRE UK Approach Linkedin Feb11David Shipley
 
IRJET-Implementation of TOPSIS Technique for Supplier Selection
IRJET-Implementation of TOPSIS Technique for Supplier SelectionIRJET-Implementation of TOPSIS Technique for Supplier Selection
IRJET-Implementation of TOPSIS Technique for Supplier SelectionIRJET Journal
 
dlw taining file
dlw taining filedlw taining file
dlw taining fileRam Bahadur
 
B&B Attachments Presents New Material Handling Innovations at IMHX
B&B Attachments Presents New Material Handling Innovations at IMHXB&B Attachments Presents New Material Handling Innovations at IMHX
B&B Attachments Presents New Material Handling Innovations at IMHXMJDelaMasa
 
Electrification Clearance Solutions
Electrification Clearance SolutionsElectrification Clearance Solutions
Electrification Clearance SolutionsBalfour Beatty Rail
 
Prysmian Cable Support & Fixing System Catalogue - Prysmian Group (Bicon) Cab...
Prysmian Cable Support & Fixing System Catalogue - Prysmian Group (Bicon) Cab...Prysmian Cable Support & Fixing System Catalogue - Prysmian Group (Bicon) Cab...
Prysmian Cable Support & Fixing System Catalogue - Prysmian Group (Bicon) Cab...Thorne & Derrick International
 
Intelligent infrastructure and maintenance on the railway network - Andy Doherty
Intelligent infrastructure and maintenance on the railway network - Andy DohertyIntelligent infrastructure and maintenance on the railway network - Andy Doherty
Intelligent infrastructure and maintenance on the railway network - Andy DohertyKTN
 
The_Practical_Application_of_Technology_in_the_Roy_Hill_Railway_Ver 3
The_Practical_Application_of_Technology_in_the_Roy_Hill_Railway_Ver 3The_Practical_Application_of_Technology_in_the_Roy_Hill_Railway_Ver 3
The_Practical_Application_of_Technology_in_the_Roy_Hill_Railway_Ver 3Bruce Brymer
 
Km08 pneumatic automatic bumper (wecompress)
Km08 pneumatic automatic bumper (wecompress)Km08 pneumatic automatic bumper (wecompress)
Km08 pneumatic automatic bumper (wecompress)1000kv technologies
 
ERTMS Fact Sheet 14 - ERTMS deployment in the UK
ERTMS Fact Sheet 14 - ERTMS deployment in the UKERTMS Fact Sheet 14 - ERTMS deployment in the UK
ERTMS Fact Sheet 14 - ERTMS deployment in the UKUNIFE2012
 
Kanchrapara Railway workshop Project(Short)
Kanchrapara Railway workshop Project(Short)Kanchrapara Railway workshop Project(Short)
Kanchrapara Railway workshop Project(Short)babai das
 

Similar to SB Rail Pioneers Railway Infrastructure Advancements (20)

Uromac Catalogue 2014 (2)
Uromac Catalogue 2014 (2)Uromac Catalogue 2014 (2)
Uromac Catalogue 2014 (2)
 
TRE July 2016 - Stirling
TRE July 2016 - StirlingTRE July 2016 - Stirling
TRE July 2016 - Stirling
 
456.pdf
456.pdf456.pdf
456.pdf
 
CSRE UK Approach Linkedin Feb11
CSRE UK Approach Linkedin Feb11CSRE UK Approach Linkedin Feb11
CSRE UK Approach Linkedin Feb11
 
IRJET-Implementation of TOPSIS Technique for Supplier Selection
IRJET-Implementation of TOPSIS Technique for Supplier SelectionIRJET-Implementation of TOPSIS Technique for Supplier Selection
IRJET-Implementation of TOPSIS Technique for Supplier Selection
 
dlw taining file
dlw taining filedlw taining file
dlw taining file
 
C05 The specification and use of Profibus networks in the UK water industry...
C05   The specification and use of Profibus networks in the UK water industry...C05   The specification and use of Profibus networks in the UK water industry...
C05 The specification and use of Profibus networks in the UK water industry...
 
B&B Attachments Presents New Material Handling Innovations at IMHX
B&B Attachments Presents New Material Handling Innovations at IMHXB&B Attachments Presents New Material Handling Innovations at IMHX
B&B Attachments Presents New Material Handling Innovations at IMHX
 
Electrification Clearance Solutions
Electrification Clearance SolutionsElectrification Clearance Solutions
Electrification Clearance Solutions
 
A seminar on ir coaches2018
A seminar on ir coaches2018A seminar on ir coaches2018
A seminar on ir coaches2018
 
Prysmian Cable Support & Fixing System Catalogue - Prysmian Group (Bicon) Cab...
Prysmian Cable Support & Fixing System Catalogue - Prysmian Group (Bicon) Cab...Prysmian Cable Support & Fixing System Catalogue - Prysmian Group (Bicon) Cab...
Prysmian Cable Support & Fixing System Catalogue - Prysmian Group (Bicon) Cab...
 
Publications
PublicationsPublications
Publications
 
Intelligent infrastructure and maintenance on the railway network - Andy Doherty
Intelligent infrastructure and maintenance on the railway network - Andy DohertyIntelligent infrastructure and maintenance on the railway network - Andy Doherty
Intelligent infrastructure and maintenance on the railway network - Andy Doherty
 
Dlw locomotive workshop
Dlw locomotive workshopDlw locomotive workshop
Dlw locomotive workshop
 
The_Practical_Application_of_Technology_in_the_Roy_Hill_Railway_Ver 3
The_Practical_Application_of_Technology_in_the_Roy_Hill_Railway_Ver 3The_Practical_Application_of_Technology_in_the_Roy_Hill_Railway_Ver 3
The_Practical_Application_of_Technology_in_the_Roy_Hill_Railway_Ver 3
 
Km08 pneumatic automatic bumper (wecompress)
Km08 pneumatic automatic bumper (wecompress)Km08 pneumatic automatic bumper (wecompress)
Km08 pneumatic automatic bumper (wecompress)
 
velaro-Türkiye
velaro-Türkiyevelaro-Türkiye
velaro-Türkiye
 
ERTMS Fact Sheet 14 - ERTMS deployment in the UK
ERTMS Fact Sheet 14 - ERTMS deployment in the UKERTMS Fact Sheet 14 - ERTMS deployment in the UK
ERTMS Fact Sheet 14 - ERTMS deployment in the UK
 
CAF Presentation
CAF PresentationCAF Presentation
CAF Presentation
 
Kanchrapara Railway workshop Project(Short)
Kanchrapara Railway workshop Project(Short)Kanchrapara Railway workshop Project(Short)
Kanchrapara Railway workshop Project(Short)
 

SB Rail Pioneers Railway Infrastructure Advancements

  • 1. SB Rail and Rail Infrastructure have each developed significantly over the last 99 issues of this magazine, which perhaps explains the relationship between the editorial team and one of the most innovative on-track plant suppliers in the UK today. One has found its way on to the desks (and into the hearts) of railway engineering professionals up and down the country, and the other has been at the forefront of introducing the very latest on-track technologies to the UK railway. This magazine has expertly chronicled SB Rail’s new introductions and innovations over the years and we would like to take the opportunity of summarising these achievements in this special 100th issue. Pioneering new machines SB Rail traces its lineage back through the First Swietelsky Joint Venture partnership formed in 2004. First Engineering introduced the first new generation of on-track machines built to the GM/RT 2400 requirements ordering three Unimat designs from Plasser & Theurer, beginning with the Unimat 08- 4x4/4S-RT in August 1997. Not only was this the first Unimat in the UK, it was also the first post-privatisation purchase of an on-track machine demonstrating early leadership in the market. This machine design rendered all other S&C tampers in the UK and a large portion of the plain line fleet obsolete. The new machine was capable of tamping both S&C and plain line track, equipped with four tamping units each carrying four individually tilting tines. The tamping units could each be lifted and lowered independently and traverse 930mm laterally allowing the straight and turnout sections to be tamped in a single pass with a synchronous three-rail lifting unit providing additional lift. The 08 tampers were soon followed by the introduction of the first purpose-built for the UK mobile flash-butt welder in August 1998. The APT 500L, otherwise known as ‘Sparky’, incorporated a number of design features unique in the UK at the time, including the transfer gearbox allowing the welding head’s generator to be driven from the truck engine and improved track access and operational capabilities without the need for overhead line isolation. Previously, the process of flash-butt welding had been confined to factory conditions and the use of an aging fleet of long-welded rail trains. During the rolling contact fatigue elimination programme in the late 1990s, Sparky provided a remote CWR production depot in the centre of Glasgow to provide almost all of the CWR required by the Scottish rail network. Companies join forces Now working in co-operation, First Engineering and Swietelsky carried out the first tandem tamping of S&C in the UK on ‘through alignment’ works to a ladder of eight crossovers at Bourne End on the West Coast Main Line during Christmas working in 2004. Two 08-4x4/4S machines were linked in a master/slave arrangement and controlled by a single geometry design source using Leica on-track telematics. Following the formation of the First Swietelsky Joint Venture, a further wave of innovative new equipment was soon on its way. The first Plasser & Theurer AFM 2000 RT was delivered in March 2006 and offered a complete track-finishing system combining ballast regulation and stabilising work processes in a single system. At that time, Rail Infrastructure described the AFM as a ‘stretched limo’ version of the USP 5000 RT with the A centenary of firsts RAIL INFRASTRUCTURE 43 First Engineering’s Plasser & Theurer 08-4x4/4S-RT Unimat tamper is pictured during acceptance testing at Derby. This was the first post-privatisation on-track machine to be delivered. First Engineering was an early purchaser of the Plasser & Theurer Compact type of tampers. The First Engineering mobile flash-butt welder ‘Sparky’ is pictured in production mode. On-Track Plant SB Rail’s Gordon Suthorn discusses a reputation that has been built on innovation and ‘firsts’.
  • 2. addition of a Dynamic Track Stabiliser (DTS). The enhanced regulation capability was enabled by a larger 18 tonne hopper capacity coupled with an advanced ballast profile measurement system used to precisely determine locations of heavy or deficient ballast. The AFMs support the UK tamping fleet comprising mainly of tampers without DTS units, however when an AFM is combined with an 09- 3X or 09-4S it creates a world class track maintenance system. AFM remains the highest performance track-finishing system available anywhere in the world. The award of a five-year track renewals contract prompted the development of and investment in more reliable plant to modernise the operation of removing and relaying track. First Swietelsky’s purchase of three Kirow KRC 250UK rail cranes, the first arriving in the summer of 2006, represented a step-change in capability. Improvements to the KRC 250 design for introduction in the UK included 60mph running in train formation, 15 tonnes lifting capacity at 16 metres radius and outriggers for heavier loads. SB Rail has since developed a series of unique attachments and enhancements making its fleet of KRC 250UKs the most capable in the market and first choice for S&C relaying and, in particular, modular S&C. SB Rail’s KRC 500S and SG system comprises two KRC 250UK cranes deployed in a single formation with an integrated wagon and tandem tensioning system. This negates the need for down-rating and is capable of installing all modular track designs and panels up to and including ‘SG’ switches. Further enhancements enabled by a unique robotic arm include a 28 sleeper fully automatic relaying beam and high output piling system. High output The First Swietelsky Joint Venture (JV) partnership (now SB Rail) won the highly coveted inaugural contract to commission, operate and maintain Network Rail’s high output track renewals fleet beginning in 2004. The JV began the introduction of the first RM 900 RT ballast cleaner and support MFS wagons in August 2004, followed by the first P 95 UK track renewal train in April 2005 and a second RM 900 RT and support MFS wagons in June of the same year, bringing all these systems up to full operational service on behalf of Network Rail. The main systems were supported by a fleet of 09-3X-D-RT Dynamic tampers and USP 5000 RT regulators. The introduction of the RM 900 RT and P 95 UK heralded a step-change in plain line track renewals capability in the UK, allowing the team involved to deliver up to 300% output improvements over conventional systems and methodologies. Whilst SB Rail was not the first to introduce the 09-3X, it was the first to bring in the Dynamic version. Swietelsky did later acquire the only other 09-3X-RT machines in the UK and brought these up to their intended level of performance in Network Rail’s National Plant Contract. The three-sleeper tamping banks and continuous action of the 09-3X enables performance increases of up to 40% over conventional machines and increases tamping quality. Further features include split design banks to allow single sleeper tamping in the case of irregular spacing, something the company certainly made use of during the first high output ballast cleaning campaign on the Midland main line! The introduction of the Dynamic version efficiently incorporated the tamping and stabilisation work processes in a single piece of equipment for the first time and has been put to extensive use ever since. Establishing the project infrastructure and safe working methodologies for the deployment of this fleet of new equipment was a considerable challenge. It included creating several high output operations bases, establishing and continually improving the logistics and maintenance regimes, implementing Adjacent Line Open (ALO) working, introducing Curve Alignment Laser (CAL) and ‘Tandem Drive’, raising hand-back speeds from 50mph to 80mph and driving the improvement of track quality to the first ever 100% score consistently achieved in the UK. RAIL INFRASTRUCTURE 43 One of SB Rail’s two Plasser & Theurer AFM 2000 RT track-finishing machines. Two Plasser & Theurer 09-3X-RT machines are within SB Rail’s resources. The SB Rail fleet includes three Kirow KRC250UK cranes, one of which is pictured here undertaking piling operations. On-Track Plant
  • 3. Over the course of the first high output contract, the team created and refined best practices and a blueprint enabling the future expansion of the project whilst delivering circa 300 miles of track renewals activity with associated tamping, stabilising and ballast finishing works on the Great Western, East Coast and Midland main lines. High Speed 1 Now to the Plasser & Theurer 09-32/4S Dynamic, the most advanced high performance tamping system available. This Swietelsky machine is based in mainland Europe, but since 2010 has been used by SB Rail and Network Rail (HS1) working in partnership to plan and deliver the tamping and regulation campaigns on High Speed 1 infrastructure. The advantages of using the 09-32/4S Dynamic over conventional UK machines include: n Continuous action tamping for both plain line and turnouts. n Integrated track stabilising unit. n Three rail lifting and four rail tamping. n High output capacity - plain line rating 1,400m/h. n Reduced track occupation of high speed turnouts (1/46 turnouts on HS1). n Sleeper end consolidator (increases resistance to lateral displacement circa 4%). In another first, this system has been used on HS1 to maintenance tamp and DTS S&C in one continuous cycle with significant sustainability benefits. It is not all about bigger and faster in tamping though. In conjunction with HS1, SB Rail introduced new technology for shortwave tamping to complement its high output campaign work and the concept of ‘Sprinter’ tamping was born in the UK. For anyone who has not heard of Sprinter tamping yet, it is a mechanised means of repairing shortwave defects including faults within horizontal transitions. The software targets only small areas in need of geometrical repair, but since this will be the subject of a detailed article in a future issue of Rail Infrastructure we will leave ‘whistles wetted’ for now! Currently, SB Rail has two UNIMAT 08-4x4 machines fitted to work either in conventional or ‘Sprinter’ modes. Recent developments So here we are in 2014, 17 years after the first 08 UNIMAT and history is repeating itself with SB Rail’s most recent fleet addition, the 09- 4x4/4S Dynamic. This is the ‘brother’ of the 09- 32/4S and another first in the UK. The 09-4x4 is equipped with the latest Plasser & Theurer Intelligent Control System (P-IC 2.0), ‘intelligent’ DTS, DRP, CAL and RLD (Resistance to Lateral Displacement) technologies. The tamping banks are operated in manual, semi-automatic or fully- automatic modes, depending on-site conditions and the synchronous three-rail lifting unit provides additional lift to S&C. The WIN ALC computer provides complete guidance to the machine’s levelling and lining systems whilst the multi-channel DRP captures a series of track quality measurements. Designed and built for working in the field for extended periods, the 09-4x4/4S tamps S&C up to 40% faster and plain line up to 30% faster in comparison with older machines. The integrated intelligent DTS unit achieves rapid and measured consolidation of the track, restoring resistance to lateral displacement and making higher speed hand-backs over S&C a reality. Conclusion The last 99 issues of Rail Infrastructure have intelligently informed the industry on a great many new or improved items of plant and equipment being put to use on Britain’s railways. SB Rail is proud to have taken a leading role developing and introducing the very latest on-track technologies in the UK. We look forward to pushing back boundaries further and bringing in many more ‘firsts’ in the pursuit of ever more efficient railway engineering methodologies in the future. Our heartfelt thanks to Roger and Alex and here’s to the next 100 issues! Additional contributors: Craig Goldie and Matt Whiting, Swietelsky. 44 RAIL INFRASTRUCTURE On-Track Plant SB Rail’s state-of-the-art Plasser & Theurer 09-4x4/4S Dynamic tamper. Above: Plasser & Theurer 09-32/4S Dynamic tamper as first used on High Speed 1. Below: Also first introduced on High Speed 1 by SB Rail has been Sprinter tamping.