SlideShare a Scribd company logo
1 of 31
Presented by: Ghawsudin Mayar
GANTRY GIRDER
 Gantry girders are laterally unsupported beams to carry heavy
loads from place to place at the construction sites, mostly these are
of steel material.
2
INTRODUCTION TO THE GANTRY
GIRDER
 Profiles used for Gantry Girder
3
 Wheel Base
 Wheel base means the distance between the two wheels resting on
one gantry girder.
 This depends upon the span of the crane across the shop. The wheel
base may be taken as follows.
4
 Support
Gantry girders may be supported on brackets attached to columns or
stepped columns or on a separate column set on the inner side of the
main columns.
5
 Allowances for Impact of Wheel Loads
The following allowances are made to cover all forces caused by
vibration, shock from slipping of slings, kinetic action of acceleration
and retardation and impact of wheel loads.
6
 Load on Gantry Girder
 Vertical loads transmitted by the crane.
 Lateral forces transmitted due to sudden stopping or starting of the
crab on the crane.
 Longitudinal forces transmitted due to sudden stopping or starting
of the crane.
7
DESIGN PROCEDURES FOR GANTRY
GIRDER
1. Determination of the Maximum Wheel Load
2. Determine Maximum vertical shear force and maximum vertical
bending moment for the gantry girder
3. Determine Corresponding to the wheel loads the appropriate
lateral forces
4. Analysis of the Selected Girder Section
5. Checking
8
PROBLEM
Design a gantry girder to be used in an industrial building carrying a manual
operated travelling crane for the following data:
• Crane capacity: 200 KN
• Self-weight of the crane girder excluding trolley: 200 KN
• Self-weight of the trolley etc.: 40 KN
• Approximate minimum approach of the crane hook: 1.2m
• Wheel base: 3.5m
• Distance between gantry rails: 36m
• Distance between the columns: 8m
• Self-weight of rail section: 300N/m
• Diameter of crane wheel: 150mm
9
STEP (1): PARTIAL SAFETY FACTORS
10
STEP (2): DESIGN FORCES
 Maximum Wheel Load
Maximum concentrated load on crane:
Maximum factored load on crane:
Factored uniform distributed load:
11
200 40 240KN 
240 1.5 360KN 
200
1.5 8.33
36
KN 
Taking moment about (B)
Load on each wheel:
• Total weight of Sections: I section + Channel section + rail section
• Factored load =
12
8.33 36 36
* 36 360 (36 1.2) 498
2
* 161.88
RA RA KN
RB KN
 
      

498
249
2
KN
1432.4 351.2 300 2.3KN
m
  ;
1.5 2.3 3.45KN
m
 
13
* 8 249 (8 1.375) 249 (3.125) 303.46
* 8 249 (1.375) 249 (4.875) 194.5
3.125
* 194 3.125 3.45 3.125 591
2
RC Rc KN
RD Rc KN
Moment KN m
       
      
       
 Maximum Shear
Taking moment about (D)
14
8 249 8 249 4.5 389.06RC Rc KN      
 Impact load
Vertical force to rails
• Machine operated 25% of wheel load
• Hand operated 10% of wheel load
• Total Moment =
15
10
249 24.9
100
KN 
* ' 8 24.9 6.25 24.9 3.125 ' 30.34
* ' 8 2 24.9 30.34 ' 19.46
* 19.46 3.125 60.81
RC RC KN
RD RD KN
Moment KN m
      
     
   
591 60.81 651.81KN m  
Horizontal Force to rail
Factored lateral force:
Lateral force on each wheel:
Maximum B.M due to lateral force by proportion:
16
5
240 12
100
KN 
5
240 1.5 12
100
KN  
18
9
2
KN
9 60.81
2.2
249
KNm


3 3
1.2
1 824.76 10 250 1.2 800.4 10 250
1.1 1.1
187.44 218.29
y y
z
o o
z
Zp f Ze f
Md
m m
Md
KNm KNm

 
   
 
     
 

STEP (3): PRELIMINARY TRIAL
SECTION
According IS 800:2007 (Table 46), I select ISWB 600 with
17
6
31.4 651.81 10
1.4 (3650.136 )
250
Mz
Zp cm
fy
 
  
3
3986.66Zp cm
ISWB 600@133.7 Kg/m ISMC 300@351N/m
bf 250mm 90mm
tf 21.3mm 13.6mm
tw 11.2mm 7.6mm
R1 17 13
Ixx 106198.5cm^4 6362.6cm^4
Iyy 4702.5cm^4 310.8cm^4
Area 17038mm^2 4564mm^2
18
 Moment Inertia of Gantry Girder
 Izz gross = I beam + I channel
19
17038 (300 7.6) 4564 23.6
247.59
4564 17038
AY
y mm
A
   
  



106198.5 × 104
+ 17038 × 307.6 − 247.59 2
+ 310.8 × 104
+ 4564 × 274.59 − 23.6 2
= 135543 × 104
𝑚𝑚4
• A1+A2+A3+A4=A5+A6
• Equal Area Axis
20
(250 21.3) (300 7.6) (90 7.6 13.6) 2 (557.4 ) 11.2 ( 11.2) (250 21.3)
( 480.83 )
t t
t mm
             
 
600 2 21.3 480.83 76.57mm   
 Plastic Modulus of Section
21
3
7.6
* 300 7.6 (76.57 21.3 )
2
90 7.6
2 13.6 (90 7.6) (76.57 21.3 7.6 ( 7.6)
2
21.3
250 21.3 (76.57 )
2
76.57
76.57 11.2
2
480.83
480.83 11.2
2
21.3
250 21.3 (480.83 )
2
4767935.97
z
z
Zp
Zp mm
    

        
   
  
  
   
 
3 31356033064
* 3766.98 10
600 7.6 247.59
Iz
Ze mm
y
   
 
CLASSIFICATION OF SECTION
 Outstanding of flange of I-Section, b=bf/2<8.4ꜫ
 Outstanding flange of channel section, b=bf – tw/tf <8.4 ꜫ
 Web of I section d/tw
22
125
5.86 8.4
2
 
90 7.6
6.05 8.4
13.6


 
2( 1) 600 2(21.3 17)
46.73 84
11.2
f
w
D t R
t

   
  
Hence, the entire section is plastic.
 Check for moment capacity
Hence, moment capacity of the section
 Combined check for local Moment
23
3 3
1.2
1 824.76 10 250 1.2 800.4 10 250
1.1 1.1
1083.63 1026.81
y y
z
o o
z
Zp f Ze f
Md
m m
Md
KNm KNm

 
   
 
     
 

1026.81 651.81zMd KNm KNm 
1
651.81 2.2
0.64 1.......
1026.81 187.44
My Mz
Mdy Mdz
ok
 
  
 Buckling Resistance Check
24
0.5
2
2
2
4 4 5 4
2
5
1
1 ( )
2 20
8000
607.6
21.3 7.6 28.9
4702.5 10 6362.6 10 1106.51 10
17038 4564 21602
1106.5 10
71.56
21602
LT
y
f
f
L
y f
cr h
tLT
LT
f
f
y
y
EI h
M
L
L mm
h
t mm
I mm
A mm
Iy
A


  
  
  


  
     
  

  
0.5
2 5 4
2 6
2
8000
2 10 11065.1 10 607.6 1 71.561 ( ) 1610.78 10
607.62 8000 20
28.9
crM Nmm

 
     
     
  
 
 Non Dimensional Slender ratio
 Design Bending Compressive Stress
25
3
6
2
2
2 2 0.5
2 2 0.5
1 4767.977 10 250
0.86
1610 10
0.5 1 ( 0.2)
0.5 1 0.21 (0.86 0.2) 0.86 0.93
1
( )
1
0.77
0.93 (0.93 0.86 )
b pz y
LT
cr
LT LT LT LT
LT
LT LT LT
Z f
M


  


    
  

      
       

   
 
 
2
0.77 250
175
1.1
LT y
bd
o
f N
f
m mm


 
  
 Design Bending Strength
26
3
1 4767.977 10 175 834.39
dz b pz bd
dz
M Z f
M KNm
  
    
So 834.39 > 651.81 ………………………………………ok
STEP (4): CHECKING
 Shear Capacity Check
Maximum shear force due to wheel load= 389.06 KN
Impact Load=
Design Shear force= 389.06+38.90 = 427.96KN
So 881.77 > 427.96 ……………………….............ok
27
0.1 389.06 38.90KN 
600 11.2 250
881.77
3 3 1.1
w y
d
mo
h t f
V KNm

   
  
 
 Web Bearing Check
So 626.18 > 427.96 ………………………………ok
28
2
2 1
( 1 )
* 1 (100 150)
* 2.5( ) 2.5(21.3 17) 96
(150 96) 11.2 250
626.18
1.1
w y
w
o
f
w
b n t f
F
m
b
n t R
F KN

  

 
    
  
 
ANALYZE AND DESIGN BY STAAD
PRO
29
30
31

More Related Content

What's hot

What's hot (20)

Reinforced slab
Reinforced slabReinforced slab
Reinforced slab
 
Bolted connections
Bolted connectionsBolted connections
Bolted connections
 
Eccentric connections 1
Eccentric connections 1Eccentric connections 1
Eccentric connections 1
 
Design of column base plates anchor bolt
Design of column base plates anchor boltDesign of column base plates anchor bolt
Design of column base plates anchor bolt
 
Design of compression members
Design of compression membersDesign of compression members
Design of compression members
 
Steel warehouse design report
Steel warehouse design reportSteel warehouse design report
Steel warehouse design report
 
Design of tension members
Design of tension membersDesign of tension members
Design of tension members
 
report
reportreport
report
 
T beam TYPES
T beam TYPEST beam TYPES
T beam TYPES
 
Design of columns as per IS 456-2000
Design of columns as per IS 456-2000Design of columns as per IS 456-2000
Design of columns as per IS 456-2000
 
Prestress loss
Prestress lossPrestress loss
Prestress loss
 
Beam design
Beam designBeam design
Beam design
 
Singly reinforced beam design
Singly reinforced beam   designSingly reinforced beam   design
Singly reinforced beam design
 
Onewayslab
OnewayslabOnewayslab
Onewayslab
 
Design of steel beams
Design of steel beamsDesign of steel beams
Design of steel beams
 
Column Interaction Diagram construction
Column Interaction Diagram constructionColumn Interaction Diagram construction
Column Interaction Diagram construction
 
Design of beam
Design of beamDesign of beam
Design of beam
 
Cable Layout, Continuous Beam & Load Balancing Method
 Cable Layout, Continuous Beam & Load Balancing Method Cable Layout, Continuous Beam & Load Balancing Method
Cable Layout, Continuous Beam & Load Balancing Method
 
composite beam problems.pdf
composite beam problems.pdfcomposite beam problems.pdf
composite beam problems.pdf
 
Shear centre
Shear centreShear centre
Shear centre
 

Similar to Gantry girder Analyse & design

MAIN CANOPY BAJAJ HR(22.09.2016)
MAIN CANOPY BAJAJ HR(22.09.2016)MAIN CANOPY BAJAJ HR(22.09.2016)
MAIN CANOPY BAJAJ HR(22.09.2016)sufiyan shaikh
 
Vertical Screw Conveyor - Design Project
Vertical Screw Conveyor - Design ProjectVertical Screw Conveyor - Design Project
Vertical Screw Conveyor - Design ProjectPoorna Hewapathirana
 
Ref F2F Week 4 - Solution_unlocked.pdf
Ref F2F Week 4 - Solution_unlocked.pdfRef F2F Week 4 - Solution_unlocked.pdf
Ref F2F Week 4 - Solution_unlocked.pdfRobin Arthur Flores
 
Ship design project &amp; presentation 3
Ship design project &amp;  presentation 3Ship design project &amp;  presentation 3
Ship design project &amp; presentation 3Kifayath Chowdhury
 
08.2010 fsae hybrid 3rd presentation gen-3 geared bldc motors, planetary tr...
08.2010 fsae hybrid 3rd presentation   gen-3 geared bldc motors, planetary tr...08.2010 fsae hybrid 3rd presentation   gen-3 geared bldc motors, planetary tr...
08.2010 fsae hybrid 3rd presentation gen-3 geared bldc motors, planetary tr...Tobias Overdiek
 
AS4100 Steel Design Webinar Worked Examples
AS4100 Steel Design Webinar Worked ExamplesAS4100 Steel Design Webinar Worked Examples
AS4100 Steel Design Webinar Worked ExamplesClearCalcs
 
Ship design project Final presentation
Ship design project Final presentationShip design project Final presentation
Ship design project Final presentationKifayath Chowdhury
 
DESIGN OF DECK SLAB AND GIRDERS- BRIDGE ENGINEERING
DESIGN OF DECK SLAB AND GIRDERS- BRIDGE ENGINEERINGDESIGN OF DECK SLAB AND GIRDERS- BRIDGE ENGINEERING
DESIGN OF DECK SLAB AND GIRDERS- BRIDGE ENGINEERINGLiyaWilson4
 
Iai isdbcr ispdbcr_esd_specsheet
Iai isdbcr ispdbcr_esd_specsheetIai isdbcr ispdbcr_esd_specsheet
Iai isdbcr ispdbcr_esd_specsheetElectromate
 
98375_DIRT CRUSADERS
98375_DIRT CRUSADERS98375_DIRT CRUSADERS
98375_DIRT CRUSADERSurbanangel08g
 
2014 new catalogue cubicle gearbox screw jacks,screw jacks with cubic housing...
2014 new catalogue cubicle gearbox screw jacks,screw jacks with cubic housing...2014 new catalogue cubicle gearbox screw jacks,screw jacks with cubic housing...
2014 new catalogue cubicle gearbox screw jacks,screw jacks with cubic housing...Jacton Electromechanical Co.,Ltd
 
Hyster a217 (n30 fr) forklift service repair manual
Hyster a217 (n30 fr) forklift service repair manualHyster a217 (n30 fr) forklift service repair manual
Hyster a217 (n30 fr) forklift service repair manualfusjejfskekemm
 

Similar to Gantry girder Analyse & design (20)

MAIN CANOPY BAJAJ HR(22.09.2016)
MAIN CANOPY BAJAJ HR(22.09.2016)MAIN CANOPY BAJAJ HR(22.09.2016)
MAIN CANOPY BAJAJ HR(22.09.2016)
 
Vertical Screw Conveyor - Design Project
Vertical Screw Conveyor - Design ProjectVertical Screw Conveyor - Design Project
Vertical Screw Conveyor - Design Project
 
Ref F2F Week 4 - Solution_unlocked.pdf
Ref F2F Week 4 - Solution_unlocked.pdfRef F2F Week 4 - Solution_unlocked.pdf
Ref F2F Week 4 - Solution_unlocked.pdf
 
Mojtaba Hasanlu's Portfolios in Rotor
Mojtaba Hasanlu's Portfolios in RotorMojtaba Hasanlu's Portfolios in Rotor
Mojtaba Hasanlu's Portfolios in Rotor
 
Strauto 2015
Strauto 2015Strauto 2015
Strauto 2015
 
psad 1.pdf
psad 1.pdfpsad 1.pdf
psad 1.pdf
 
B012460814
B012460814B012460814
B012460814
 
Ship design project &amp; presentation 3
Ship design project &amp;  presentation 3Ship design project &amp;  presentation 3
Ship design project &amp; presentation 3
 
08.2010 fsae hybrid 3rd presentation gen-3 geared bldc motors, planetary tr...
08.2010 fsae hybrid 3rd presentation   gen-3 geared bldc motors, planetary tr...08.2010 fsae hybrid 3rd presentation   gen-3 geared bldc motors, planetary tr...
08.2010 fsae hybrid 3rd presentation gen-3 geared bldc motors, planetary tr...
 
AS4100 Steel Design Webinar Worked Examples
AS4100 Steel Design Webinar Worked ExamplesAS4100 Steel Design Webinar Worked Examples
AS4100 Steel Design Webinar Worked Examples
 
Ship design project Final presentation
Ship design project Final presentationShip design project Final presentation
Ship design project Final presentation
 
DESIGN BUILDING BY STAD PRO
DESIGN BUILDING BY STAD PRODESIGN BUILDING BY STAD PRO
DESIGN BUILDING BY STAD PRO
 
unit-3.ppt
unit-3.pptunit-3.ppt
unit-3.ppt
 
DESIGN OF DECK SLAB AND GIRDERS- BRIDGE ENGINEERING
DESIGN OF DECK SLAB AND GIRDERS- BRIDGE ENGINEERINGDESIGN OF DECK SLAB AND GIRDERS- BRIDGE ENGINEERING
DESIGN OF DECK SLAB AND GIRDERS- BRIDGE ENGINEERING
 
Iai isdbcr ispdbcr_esd_specsheet
Iai isdbcr ispdbcr_esd_specsheetIai isdbcr ispdbcr_esd_specsheet
Iai isdbcr ispdbcr_esd_specsheet
 
98375_DIRT CRUSADERS
98375_DIRT CRUSADERS98375_DIRT CRUSADERS
98375_DIRT CRUSADERS
 
Gearbox design
Gearbox designGearbox design
Gearbox design
 
Project 2b (1) (2)
Project 2b  (1) (2)Project 2b  (1) (2)
Project 2b (1) (2)
 
2014 new catalogue cubicle gearbox screw jacks,screw jacks with cubic housing...
2014 new catalogue cubicle gearbox screw jacks,screw jacks with cubic housing...2014 new catalogue cubicle gearbox screw jacks,screw jacks with cubic housing...
2014 new catalogue cubicle gearbox screw jacks,screw jacks with cubic housing...
 
Hyster a217 (n30 fr) forklift service repair manual
Hyster a217 (n30 fr) forklift service repair manualHyster a217 (n30 fr) forklift service repair manual
Hyster a217 (n30 fr) forklift service repair manual
 

Recently uploaded

SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 

Recently uploaded (20)

SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 

Gantry girder Analyse & design

  • 2. GANTRY GIRDER  Gantry girders are laterally unsupported beams to carry heavy loads from place to place at the construction sites, mostly these are of steel material. 2
  • 3. INTRODUCTION TO THE GANTRY GIRDER  Profiles used for Gantry Girder 3
  • 4.  Wheel Base  Wheel base means the distance between the two wheels resting on one gantry girder.  This depends upon the span of the crane across the shop. The wheel base may be taken as follows. 4
  • 5.  Support Gantry girders may be supported on brackets attached to columns or stepped columns or on a separate column set on the inner side of the main columns. 5
  • 6.  Allowances for Impact of Wheel Loads The following allowances are made to cover all forces caused by vibration, shock from slipping of slings, kinetic action of acceleration and retardation and impact of wheel loads. 6
  • 7.  Load on Gantry Girder  Vertical loads transmitted by the crane.  Lateral forces transmitted due to sudden stopping or starting of the crab on the crane.  Longitudinal forces transmitted due to sudden stopping or starting of the crane. 7
  • 8. DESIGN PROCEDURES FOR GANTRY GIRDER 1. Determination of the Maximum Wheel Load 2. Determine Maximum vertical shear force and maximum vertical bending moment for the gantry girder 3. Determine Corresponding to the wheel loads the appropriate lateral forces 4. Analysis of the Selected Girder Section 5. Checking 8
  • 9. PROBLEM Design a gantry girder to be used in an industrial building carrying a manual operated travelling crane for the following data: • Crane capacity: 200 KN • Self-weight of the crane girder excluding trolley: 200 KN • Self-weight of the trolley etc.: 40 KN • Approximate minimum approach of the crane hook: 1.2m • Wheel base: 3.5m • Distance between gantry rails: 36m • Distance between the columns: 8m • Self-weight of rail section: 300N/m • Diameter of crane wheel: 150mm 9
  • 10. STEP (1): PARTIAL SAFETY FACTORS 10
  • 11. STEP (2): DESIGN FORCES  Maximum Wheel Load Maximum concentrated load on crane: Maximum factored load on crane: Factored uniform distributed load: 11 200 40 240KN  240 1.5 360KN  200 1.5 8.33 36 KN 
  • 12. Taking moment about (B) Load on each wheel: • Total weight of Sections: I section + Channel section + rail section • Factored load = 12 8.33 36 36 * 36 360 (36 1.2) 498 2 * 161.88 RA RA KN RB KN           498 249 2 KN 1432.4 351.2 300 2.3KN m   ; 1.5 2.3 3.45KN m  
  • 13. 13 * 8 249 (8 1.375) 249 (3.125) 303.46 * 8 249 (1.375) 249 (4.875) 194.5 3.125 * 194 3.125 3.45 3.125 591 2 RC Rc KN RD Rc KN Moment KN m                       
  • 14.  Maximum Shear Taking moment about (D) 14 8 249 8 249 4.5 389.06RC Rc KN      
  • 15.  Impact load Vertical force to rails • Machine operated 25% of wheel load • Hand operated 10% of wheel load • Total Moment = 15 10 249 24.9 100 KN  * ' 8 24.9 6.25 24.9 3.125 ' 30.34 * ' 8 2 24.9 30.34 ' 19.46 * 19.46 3.125 60.81 RC RC KN RD RD KN Moment KN m                  591 60.81 651.81KN m  
  • 16. Horizontal Force to rail Factored lateral force: Lateral force on each wheel: Maximum B.M due to lateral force by proportion: 16 5 240 12 100 KN  5 240 1.5 12 100 KN   18 9 2 KN 9 60.81 2.2 249 KNm   3 3 1.2 1 824.76 10 250 1.2 800.4 10 250 1.1 1.1 187.44 218.29 y y z o o z Zp f Ze f Md m m Md KNm KNm                  
  • 17. STEP (3): PRELIMINARY TRIAL SECTION According IS 800:2007 (Table 46), I select ISWB 600 with 17 6 31.4 651.81 10 1.4 (3650.136 ) 250 Mz Zp cm fy      3 3986.66Zp cm ISWB 600@133.7 Kg/m ISMC 300@351N/m bf 250mm 90mm tf 21.3mm 13.6mm tw 11.2mm 7.6mm R1 17 13 Ixx 106198.5cm^4 6362.6cm^4 Iyy 4702.5cm^4 310.8cm^4 Area 17038mm^2 4564mm^2
  • 18. 18
  • 19.  Moment Inertia of Gantry Girder  Izz gross = I beam + I channel 19 17038 (300 7.6) 4564 23.6 247.59 4564 17038 AY y mm A           106198.5 × 104 + 17038 × 307.6 − 247.59 2 + 310.8 × 104 + 4564 × 274.59 − 23.6 2 = 135543 × 104 𝑚𝑚4
  • 20. • A1+A2+A3+A4=A5+A6 • Equal Area Axis 20 (250 21.3) (300 7.6) (90 7.6 13.6) 2 (557.4 ) 11.2 ( 11.2) (250 21.3) ( 480.83 ) t t t mm                 600 2 21.3 480.83 76.57mm   
  • 21.  Plastic Modulus of Section 21 3 7.6 * 300 7.6 (76.57 21.3 ) 2 90 7.6 2 13.6 (90 7.6) (76.57 21.3 7.6 ( 7.6) 2 21.3 250 21.3 (76.57 ) 2 76.57 76.57 11.2 2 480.83 480.83 11.2 2 21.3 250 21.3 (480.83 ) 2 4767935.97 z z Zp Zp mm                                3 31356033064 * 3766.98 10 600 7.6 247.59 Iz Ze mm y      
  • 22. CLASSIFICATION OF SECTION  Outstanding of flange of I-Section, b=bf/2<8.4ꜫ  Outstanding flange of channel section, b=bf – tw/tf <8.4 ꜫ  Web of I section d/tw 22 125 5.86 8.4 2   90 7.6 6.05 8.4 13.6     2( 1) 600 2(21.3 17) 46.73 84 11.2 f w D t R t         Hence, the entire section is plastic.
  • 23.  Check for moment capacity Hence, moment capacity of the section  Combined check for local Moment 23 3 3 1.2 1 824.76 10 250 1.2 800.4 10 250 1.1 1.1 1083.63 1026.81 y y z o o z Zp f Ze f Md m m Md KNm KNm                   1026.81 651.81zMd KNm KNm  1 651.81 2.2 0.64 1....... 1026.81 187.44 My Mz Mdy Mdz ok     
  • 24.  Buckling Resistance Check 24 0.5 2 2 2 4 4 5 4 2 5 1 1 ( ) 2 20 8000 607.6 21.3 7.6 28.9 4702.5 10 6362.6 10 1106.51 10 17038 4564 21602 1106.5 10 71.56 21602 LT y f f L y f cr h tLT LT f f y y EI h M L L mm h t mm I mm A mm Iy A                              0.5 2 5 4 2 6 2 8000 2 10 11065.1 10 607.6 1 71.561 ( ) 1610.78 10 607.62 8000 20 28.9 crM Nmm                    
  • 25.  Non Dimensional Slender ratio  Design Bending Compressive Stress 25 3 6 2 2 2 2 0.5 2 2 0.5 1 4767.977 10 250 0.86 1610 10 0.5 1 ( 0.2) 0.5 1 0.21 (0.86 0.2) 0.86 0.93 1 ( ) 1 0.77 0.93 (0.93 0.86 ) b pz y LT cr LT LT LT LT LT LT LT LT Z f M                                         2 0.77 250 175 1.1 LT y bd o f N f m mm       
  • 26.  Design Bending Strength 26 3 1 4767.977 10 175 834.39 dz b pz bd dz M Z f M KNm         So 834.39 > 651.81 ………………………………………ok
  • 27. STEP (4): CHECKING  Shear Capacity Check Maximum shear force due to wheel load= 389.06 KN Impact Load= Design Shear force= 389.06+38.90 = 427.96KN So 881.77 > 427.96 ……………………….............ok 27 0.1 389.06 38.90KN  600 11.2 250 881.77 3 3 1.1 w y d mo h t f V KNm          
  • 28.  Web Bearing Check So 626.18 > 427.96 ………………………………ok 28 2 2 1 ( 1 ) * 1 (100 150) * 2.5( ) 2.5(21.3 17) 96 (150 96) 11.2 250 626.18 1.1 w y w o f w b n t f F m b n t R F KN                 
  • 29. ANALYZE AND DESIGN BY STAAD PRO 29
  • 30. 30
  • 31. 31