SlideShare a Scribd company logo
1 of 9
REPORT ON LTS REDUCTION
Prepared By: Gulfam Khalid
Shift Engineer
AMMONIA PLANT
Standard Operating Procedure FOR LTS reduction
Introduction
Fresh/Newly charged LTS catalyst has to be reduced before taken it into service, by this
procedure stable copper oxide component of the new catalyst is converted into reactive
copper metal. During reduction and operation its zinc oxide and alumina components remain
unchanged and act as support, which stabilize the copper metal crystals that act as reservoir
for poisons. Hydrogen is used as reducing agent. The reaction of catalyst with hydrogen is
exothermic as given below:
CuO + H2 ↔ Cu + H2O ∆H = -81 Kj/mol
KATALCO 83-3 catalyst is based on copper oxide supported on a matrix of zinc oxide and
alumina.
Catalyst type: KATALCO 83-3 (CuO)
Form: cylindrical pellets
Length: 3.0 mm
Diameter: 5.2 mm
Charged bulk density: 1.38 kg/L or 86 lb/ft3
Vendor: Johnson Matthy
Total volume of catalyst: 39.6 m3
Bulk density: 1380 kg/m3
Total weight: 54648 kg
CuO in catalyst: 51 wt%
Plant condition before reduction
Plant load: 50%
Air to secondary reformer: Not started yet
Source to H2 rich gas: 103F
Steam to carbon ratio: 5
Reduction circuit:
1. Prepare the reduction circuit of LTS as follows:
2. SFS 1132, SFS 1143, SFS 1144, SFS 1139, SFS 1167, SFS 1168, SFS 1171 and
their associated valves should be close.
3. SFS 1165, SFS 1170 and EMV 1165 should be close.
4. Keep close by pass valve of exchanger A-133C1 of line no. 6PF1119.
5. SFS 1133, SFS 1145, and SFS 1172 should be in open position.
6. Open isolation manual valves associated with SFS 1172 and SFS 1145, and block
valve of line no. 6PF1121.
7. Establish flow of desulphurised natural gas through LTS slowly at the rate of 15000
Nm3
/hr minimum to maintain space velocity at 300/hr minimum so that gas
distribution through the catalyst bed is uniform. Use FI-1140 to measure the N.Gas
flow to LTS.
8. Increase the catalyst bed temperature up to 130O
C by the by pass valve of the
exchanger A-133C1 at the rate of 50O
C/hr. keep LTS back pressure at 6.0kg/cm2
g
with its manual vent valve on line no.10V1115.
9. Check correct working of hydrogen flow meter F-1168/ F-1169 when catalyst bed
temperature reaches 120 ̴130O
C. During checking of flow meter do not increase the
bed temperature.
10. Install online hydrogen analyzer by connecting it with inlet / outlet sample points S-
1165B & S-1165C of LTS. Before making it online, confirm its accuracy with chemical
laboratory results.
11. Increase the top LTS bed temperature up to 180O
C.
Catalyst reduction
When catalyst inlet temperature reached to 180O
C, introduce H2 from 103F.
1. Open 103F outlet valve to 104DB fully and open u/s of FI-1169 valve slowly in steps.
Keep LTS inlet temperature at 180O
C.
2. Establish H2 gas flow at the rate of 30 Nm3/hr initially by opening 1-1/2 ‘’ needle
valve. Watch LTS catalyst bed temperature (T-1230 ̴ T-1232, T-1181 ̴ T-1182) for 5
minutes.
3. If catalyst temperatures are not rising by abnormal reaction, increase hydrogen
gradually in steps up to 100 m3
/hr. watch LTS bed temperature for 5 minutes after
each step.
4. Bed temperature will start increasing when hydrogen starts reacting with CuO
catalyst.
HPNG BC4 101D 102DA/DB 133C1 LTS /104-DB
103F (H2)
VENT
5. Keep on increasing hydrogen flow from 1% to 3% in the inlet Natural Gas gradually
by watching bed temperatures. Maintain hydrogen flow maximum till the bed
temperature stops rising.
6. Monitor LTS inlet and outlet H2 gas content with online analyzer continuously. Verify
these results with laboratory analysis after 1 ̴ 2 hrs. So special arrangements for H2
gas analysis is necessary during LTS catalyst reduction.
7. When 1st
bed temperature is coming down the reaction will start in 2nd
bed and its
temperature will rise. Control the temperature by controlling the hydrogen flow into
the N.Gas LTS inlet. Similar steps are to be followed for all the beds till the
temperature of the last bed starts decreasing after reaching to peak temperature.
8. Confirm hydrogen consumption which is more than 90% if 1st
bed temperature comes
down to 1st
bed inlet temperature (180O
C) one by one.
9. If H2 is not consumed more than 90%, increase inlet temperature of LTS 3O
C at every
step until 90% hydrogen is consumed. However maximum limit of inlet temperature is
215O
C.
10. If H2 is consumed more than 90%, keep that temperature and increase hydrogen
contents from 3% to 50% volume gradually. Increasing rate of H2 is 1.5 times of
existing hydrogen contents. That is 2% × 1.5 = 3%, 3% × 1.5 = 4.5%
11. During catalyst reduction, watch catalyst bed temperature carefully and if any
abnormal temperature rise is found cut H2 supply.
12. Under LTS inlet temperature 215O
C and inlet hydrogen contents 50%, if each bed
temperature is less than LTS inlet temperature (180O
C) and H2 consumption is
almost zero, LTS reduction has completed.
Soaking
When reduction of LTS catalyst completed soaking period started, for this gradually increase
the hydrogen concentration in the inlet gas up to 15% incrementally and watch very carefully
bed temperatures for 5 ̴10 minutes. Bed temperature neither allows increasing abruptly nor
exceeding to 230O
C. However, for small duration increase is not harmful for the catalyst.
Actual Operating Procedure
LTS catalyst blowing
To remove entrapped dust particles from catalyst bed, catalyst is blown with desulphurized
natural gas for 3 to 4 hours. It was done to avoid increase in pressure drop along the bed
and these dust particles cause foaming problem in the CO2 removal system.
Circuit for LTS blowing
Heating
Desulphurized natural gas is used for heating of LTS catalyst. Established the flow of N.Gas
to heat the bed up to 130O
C at the rate of 50O
C per hour and keep the back pressure 5-6
kg/cm2
g. Ensure that both the hydrogen flow meter and analyzer are operating satisfactorily
as the temperature approaches 130O
C. Continue heating the catalyst until top of bed is at
180O
C. The temperature of the gas should not exceed 210O
C during the initial heating if
natural gas space velocity is less than recommended more care is necessary as there can
be poor gas distribution which can lead to localized overheating. Start recording the bed
temperature during warm up to confirm that the gas is well distributed through the bed.
Circuit for heating
 SFS 1132, SFS 1143, SFS 1144, SFS 1167, SFS 1168, SFS 1171 and their
associated valves were close.
 SFS 1165, SFS 1170 and EMV 1165 should be close.
 Used A-133C1 by pass route for heating of LTS.
 SFS 1133, SFS 1145, SFS 1177, and SFS 1172 should be open.
102 DA,DB A-133C1 by pass A-104DB
Vent
H2 injection
1st
bed reduction
When the temperature of top 3rd
bed reached 159O
C introduced hydrogen through FI 1169 at
the rate of 65 Nm3
/hr. To maintain the inlet temperature of N.Gas 180O
C at the inlet increase
the H2 flow 65 ̴100 Nm3
/hr then 100 ̴160 Nm3
/hr, 16 ̴ 220 Nm3
/hr, 220 ̴ 280 Nm3
/hr within 4.5
hours of reduction started when the hydrogen concentration at online analyzer reached 7.6%
first bed reduction completed and exotherm of first bed was at 224O
C, at its peak. Actually
hydrogen concentrations at online analyzer 7.6% was more than expectations, the reason
was that hydrogen analyzer was giving the results of HTS out let combined, later on analyzer
position was changed, HTS outlet blinded, and so H2 analyzer concentrations came to
normal.
2nd
bed reduction
Reduction of 2nd
bed completed within 10.5 hours of reduction started, H2 concentration at
online analyzer was 2.09% and temperature of 2nd
bed was 208O
C at that time.
150
160
170
180
190
200
210
220
230
0 2 4 6 8
H2 ConcVS 1st bed temperature
1stbedtemperatures
H2 concentration
200
205
210
215
220
225
2 2.5 3 3.5 4 4.5 5 5.5 6 6.5 7
H2 concentration
2ndbedtemperatures
3rd
bed reduction
Reduction of 3rd
bed completed within 17 hours of reduction started, H2 concentration at
online analyzer was 2.40% and temperature of 3rd
bed was 206O
C at that time.
4th
bed reduction
Reduction of 4th
bed completed within 27.5 hours of reduction started, H2 concentration at
online analyzer was 2.40% and temperature of 3rd
bed was 215O
C at that time.
150
160
170
180
190
200
210
220
230
2.15 2.2 2.25 2.3 2.35 2.4 2.45 2.5
H2 ConcentrationVs 3rd bed temperatures
H2 Concentration
3rdbedtemperatures
214
214.5
215
215.5
216
216.5
217
2 2.05 2.1 2.15 2.2 2.25 2.3 2.35 2.4 2.45 2.5 2.55 2.6 2.65 2.7
H2 ConcentrationVs 4th bed temperatures
H2 Concentration
4thbedtemperatures
5th
bed reduction
Reduction of 5th
bed completed within 29 hours of reduction started, H2 concentration at
online analyzer was 2.54% and temperature of 3rd
bed was 213O
C at that time.
Soaking
At 34 hours of reduction started temperature 1st
,2nd
,3rd
,4th
,and 5th
bed were
191.5,192,192.4,192.2 and 197 respectively then H2 soaking started for this gradually
increase the inlet H2 concentration up to 19.08% at that time temperature of inlet gas and all
the beds were 219, 219.6, 220.6, 221.5, 223 and 221.8 respectively, since all the beds now
were almost same temperature then H2 flow to LTS restricted to zero inlet concentration at
LTS inlet and hold for 3.5 hours and after this isolated LTS and hold up it at 30 kg/cm2
g all
this activity took 41 hours. At 39 hours of reduction front end load increase started and air to
secondary reformer fed at 50% plant load to achieve the desired composition of HTS outlet
for taking LTS in service.
Circuit for LTS reduction
 SFS 1132, SFS 1143, SFS 1144, SFS 1167, SFS 1168, SFS 1171 and their
associated valves were close.
 SFS 1165, SFS 1170 and EMV 1165 should be close.
 Used A-133C1 for LTS reduction.
 SFS 1133, SFS 1145, SFS 1177, and SFS 1172 should be open.
 H2 flow for reduction was maintained through FI 1169 and later through both FI 1169
and 1168
196
198
200
202
204
206
208
210
212
214
216
2.1 2.2 2.3 2.4 2.5 2.6 2.7
H2 ConcentrationVs 5th bed temperatures
H2 Concentration
5thbedtemperatures
LTS in service
When LTS took in service then temperatures of all the beds shooted abruptly after 12
minutes of taken it into service temperature of 1st
bed was 216◦C at its peak, after 15
minutes of service temperature of 2nd
bed was 256◦C, after 17 minutes of service
temperature of 3rd
bed was 287.4◦C, after 23 minutes of service temperature of 4th
bed was
300◦C, and after 26 minutes of service temperature of 5th
bed was 297◦C. And after that
temperatures of all the bed started to come down.

More Related Content

What's hot

Amine Gas Treating Unit - Best Practices - Troubleshooting Guide
Amine Gas Treating Unit  - Best Practices - Troubleshooting Guide Amine Gas Treating Unit  - Best Practices - Troubleshooting Guide
Amine Gas Treating Unit - Best Practices - Troubleshooting Guide Gerard B. Hawkins
 
Steam Reforming - Types of Reformer Design
Steam Reforming - Types of Reformer DesignSteam Reforming - Types of Reformer Design
Steam Reforming - Types of Reformer DesignGerard B. Hawkins
 
Feedstock Purfication in Hydrogen Plants
Feedstock Purfication in Hydrogen PlantsFeedstock Purfication in Hydrogen Plants
Feedstock Purfication in Hydrogen PlantsGerard B. Hawkins
 
DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS
DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS
DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS Gerard B. Hawkins
 
In-Situ Oxidation Procedure for High and Low Temperature Shift Catalysts
In-Situ Oxidation Procedure for High and Low Temperature Shift CatalystsIn-Situ Oxidation Procedure for High and Low Temperature Shift Catalysts
In-Situ Oxidation Procedure for High and Low Temperature Shift CatalystsGerard B. Hawkins
 
Principles of Pre-reforming Technology
Principles of Pre-reforming TechnologyPrinciples of Pre-reforming Technology
Principles of Pre-reforming TechnologyGerard B. Hawkins
 
Heater operation
Heater operationHeater operation
Heater operationJOMON M.C
 
(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview
(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview
(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev OverviewGerard B. Hawkins
 
A presentation on reformer new
A presentation on reformer newA presentation on reformer new
A presentation on reformer newGowri Shankar
 
Methanol Loop Start Up and Shut Down
Methanol Loop Start Up and Shut DownMethanol Loop Start Up and Shut Down
Methanol Loop Start Up and Shut DownGerard B. Hawkins
 
Steam Reforming - A Comprehensive Review
Steam Reforming - A Comprehensive ReviewSteam Reforming - A Comprehensive Review
Steam Reforming - A Comprehensive ReviewGerard B. Hawkins
 
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...Gerard B. Hawkins
 
Steam Reforming - Tube Design
Steam Reforming - Tube DesignSteam Reforming - Tube Design
Steam Reforming - Tube DesignGerard B. Hawkins
 
Steam Reforming - Common Problems
Steam Reforming - Common ProblemsSteam Reforming - Common Problems
Steam Reforming - Common ProblemsGerard B. Hawkins
 
Gas Heated Reforming - An Overview
Gas Heated Reforming - An OverviewGas Heated Reforming - An Overview
Gas Heated Reforming - An OverviewGerard B. Hawkins
 

What's hot (20)

Amine Gas Treating Unit - Best Practices - Troubleshooting Guide
Amine Gas Treating Unit  - Best Practices - Troubleshooting Guide Amine Gas Treating Unit  - Best Practices - Troubleshooting Guide
Amine Gas Treating Unit - Best Practices - Troubleshooting Guide
 
Steam Reforming - Types of Reformer Design
Steam Reforming - Types of Reformer DesignSteam Reforming - Types of Reformer Design
Steam Reforming - Types of Reformer Design
 
Feedstock Purfication in Hydrogen Plants
Feedstock Purfication in Hydrogen PlantsFeedstock Purfication in Hydrogen Plants
Feedstock Purfication in Hydrogen Plants
 
DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS
DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS
DESIGN OF VENT GAS COLLECTION AND DESTRUCTION SYSTEMS
 
In-Situ Oxidation Procedure for High and Low Temperature Shift Catalysts
In-Situ Oxidation Procedure for High and Low Temperature Shift CatalystsIn-Situ Oxidation Procedure for High and Low Temperature Shift Catalysts
In-Situ Oxidation Procedure for High and Low Temperature Shift Catalysts
 
Principles of Pre-reforming Technology
Principles of Pre-reforming TechnologyPrinciples of Pre-reforming Technology
Principles of Pre-reforming Technology
 
Heater operation
Heater operationHeater operation
Heater operation
 
(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview
(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview
(HTS) High Temperature Shift Catalyst (VSG-F101) - Comprehensiev Overview
 
A presentation on reformer new
A presentation on reformer newA presentation on reformer new
A presentation on reformer new
 
Methanol Loop Start Up and Shut Down
Methanol Loop Start Up and Shut DownMethanol Loop Start Up and Shut Down
Methanol Loop Start Up and Shut Down
 
Steam Reforming - Poisons
Steam Reforming - PoisonsSteam Reforming - Poisons
Steam Reforming - Poisons
 
Steam Reforming - A Comprehensive Review
Steam Reforming - A Comprehensive ReviewSteam Reforming - A Comprehensive Review
Steam Reforming - A Comprehensive Review
 
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
 
Ammonia CO2 Removal Systems
Ammonia CO2 Removal SystemsAmmonia CO2 Removal Systems
Ammonia CO2 Removal Systems
 
Steam Reforming - Tube Design
Steam Reforming - Tube DesignSteam Reforming - Tube Design
Steam Reforming - Tube Design
 
Graphite Heat Exchangers
Graphite Heat ExchangersGraphite Heat Exchangers
Graphite Heat Exchangers
 
API STD 521
API STD 521API STD 521
API STD 521
 
Activated MDEA solution(aMDEA)
Activated MDEA solution(aMDEA)Activated MDEA solution(aMDEA)
Activated MDEA solution(aMDEA)
 
Steam Reforming - Common Problems
Steam Reforming - Common ProblemsSteam Reforming - Common Problems
Steam Reforming - Common Problems
 
Gas Heated Reforming - An Overview
Gas Heated Reforming - An OverviewGas Heated Reforming - An Overview
Gas Heated Reforming - An Overview
 

Similar to Report on Low temperature shift converter Catalyst reduction

Some fact about Ammonia Production by Prem Baboo.pdf
Some fact about Ammonia Production by Prem Baboo.pdfSome fact about Ammonia Production by Prem Baboo.pdf
Some fact about Ammonia Production by Prem Baboo.pdfPremBaboo4
 
Bidirectional syngas generator TSW work on advanced large scale non steady st...
Bidirectional syngas generator TSW work on advanced large scale non steady st...Bidirectional syngas generator TSW work on advanced large scale non steady st...
Bidirectional syngas generator TSW work on advanced large scale non steady st...Steve Wittrig
 
Gas laws in anaesthesia
Gas laws in anaesthesiaGas laws in anaesthesia
Gas laws in anaesthesiaDavis Kurian
 
Ammonia Presentation On the Urea Ammonia Plant
Ammonia Presentation On the Urea Ammonia PlantAmmonia Presentation On the Urea Ammonia Plant
Ammonia Presentation On the Urea Ammonia PlantMuradAli619307
 
Modified gas laws
Modified gas lawsModified gas laws
Modified gas lawsHossam atef
 
Gas dehydration using solid bed
Gas dehydration using solid bed Gas dehydration using solid bed
Gas dehydration using solid bed Mohamed Bedair
 
Anaesthesia Vaporizers
Anaesthesia VaporizersAnaesthesia Vaporizers
Anaesthesia VaporizersRahul Varshney
 
Styrene methods 2520of-2520-production
Styrene methods 2520of-2520-productionStyrene methods 2520of-2520-production
Styrene methods 2520of-2520-productionkioaudi
 
Anaesthesia Vaporizers by Dr shailendra
Anaesthesia Vaporizers by Dr shailendraAnaesthesia Vaporizers by Dr shailendra
Anaesthesia Vaporizers by Dr shailendraShailendra Satpute
 
Catalyst Screening- Single Process Furfural Decarbonylation and Hydrogenation
Catalyst Screening- Single Process Furfural Decarbonylation and HydrogenationCatalyst Screening- Single Process Furfural Decarbonylation and Hydrogenation
Catalyst Screening- Single Process Furfural Decarbonylation and HydrogenationTrent Simonetti
 
Design Project Presentation
Design Project PresentationDesign Project Presentation
Design Project PresentationRobert Cote
 
Hrsg startup proceudre
Hrsg startup proceudreHrsg startup proceudre
Hrsg startup proceudrekamaraprasad
 
Surging & blow out of loop seals in a CFBC boiler
Surging & blow out of loop seals in a CFBC boilerSurging & blow out of loop seals in a CFBC boiler
Surging & blow out of loop seals in a CFBC boilerVENUS ENERGY AUDIT SYSTEM
 
PERFORMANCE ENHANCEMENT OF HOUSEHOLD REFRIGERATOR BY USING TiO2 NANO LUBRICAN...
PERFORMANCE ENHANCEMENT OF HOUSEHOLD REFRIGERATOR BY USING TiO2 NANO LUBRICAN...PERFORMANCE ENHANCEMENT OF HOUSEHOLD REFRIGERATOR BY USING TiO2 NANO LUBRICAN...
PERFORMANCE ENHANCEMENT OF HOUSEHOLD REFRIGERATOR BY USING TiO2 NANO LUBRICAN...Niyas PP
 
Industrial manufacturing of Nitric acid
Industrial manufacturing of Nitric acidIndustrial manufacturing of Nitric acid
Industrial manufacturing of Nitric acidTaha Siddiqui
 
Cfbc boiler startup and shutdown
Cfbc boiler startup and shutdownCfbc boiler startup and shutdown
Cfbc boiler startup and shutdownAshvani Shukla
 
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptxrajneeshjauhari2
 
Key lessons to optimise ammonia plant
Key lessons to optimise ammonia plantKey lessons to optimise ammonia plant
Key lessons to optimise ammonia plantPRAVEEN SINGH
 

Similar to Report on Low temperature shift converter Catalyst reduction (20)

Some fact about Ammonia Production by Prem Baboo.pdf
Some fact about Ammonia Production by Prem Baboo.pdfSome fact about Ammonia Production by Prem Baboo.pdf
Some fact about Ammonia Production by Prem Baboo.pdf
 
Bidirectional syngas generator TSW work on advanced large scale non steady st...
Bidirectional syngas generator TSW work on advanced large scale non steady st...Bidirectional syngas generator TSW work on advanced large scale non steady st...
Bidirectional syngas generator TSW work on advanced large scale non steady st...
 
Gas laws in anaesthesia
Gas laws in anaesthesiaGas laws in anaesthesia
Gas laws in anaesthesia
 
Ammonia Presentation On the Urea Ammonia Plant
Ammonia Presentation On the Urea Ammonia PlantAmmonia Presentation On the Urea Ammonia Plant
Ammonia Presentation On the Urea Ammonia Plant
 
5.pdf
5.pdf5.pdf
5.pdf
 
Modified gas laws
Modified gas lawsModified gas laws
Modified gas laws
 
Gas dehydration using solid bed
Gas dehydration using solid bed Gas dehydration using solid bed
Gas dehydration using solid bed
 
Anaesthesia Vaporizers
Anaesthesia VaporizersAnaesthesia Vaporizers
Anaesthesia Vaporizers
 
Vaporizers in Anaesthesia
Vaporizers in AnaesthesiaVaporizers in Anaesthesia
Vaporizers in Anaesthesia
 
Styrene methods 2520of-2520-production
Styrene methods 2520of-2520-productionStyrene methods 2520of-2520-production
Styrene methods 2520of-2520-production
 
Anaesthesia Vaporizers by Dr shailendra
Anaesthesia Vaporizers by Dr shailendraAnaesthesia Vaporizers by Dr shailendra
Anaesthesia Vaporizers by Dr shailendra
 
Catalyst Screening- Single Process Furfural Decarbonylation and Hydrogenation
Catalyst Screening- Single Process Furfural Decarbonylation and HydrogenationCatalyst Screening- Single Process Furfural Decarbonylation and Hydrogenation
Catalyst Screening- Single Process Furfural Decarbonylation and Hydrogenation
 
Design Project Presentation
Design Project PresentationDesign Project Presentation
Design Project Presentation
 
Hrsg startup proceudre
Hrsg startup proceudreHrsg startup proceudre
Hrsg startup proceudre
 
Surging & blow out of loop seals in a CFBC boiler
Surging & blow out of loop seals in a CFBC boilerSurging & blow out of loop seals in a CFBC boiler
Surging & blow out of loop seals in a CFBC boiler
 
PERFORMANCE ENHANCEMENT OF HOUSEHOLD REFRIGERATOR BY USING TiO2 NANO LUBRICAN...
PERFORMANCE ENHANCEMENT OF HOUSEHOLD REFRIGERATOR BY USING TiO2 NANO LUBRICAN...PERFORMANCE ENHANCEMENT OF HOUSEHOLD REFRIGERATOR BY USING TiO2 NANO LUBRICAN...
PERFORMANCE ENHANCEMENT OF HOUSEHOLD REFRIGERATOR BY USING TiO2 NANO LUBRICAN...
 
Industrial manufacturing of Nitric acid
Industrial manufacturing of Nitric acidIndustrial manufacturing of Nitric acid
Industrial manufacturing of Nitric acid
 
Cfbc boiler startup and shutdown
Cfbc boiler startup and shutdownCfbc boiler startup and shutdown
Cfbc boiler startup and shutdown
 
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
194309386-LESSON-LEARNT-FROM-AICHE-PAPER-S.pptx
 
Key lessons to optimise ammonia plant
Key lessons to optimise ammonia plantKey lessons to optimise ammonia plant
Key lessons to optimise ammonia plant
 

Recently uploaded

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 

Recently uploaded (20)

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 

Report on Low temperature shift converter Catalyst reduction

  • 1. REPORT ON LTS REDUCTION Prepared By: Gulfam Khalid Shift Engineer AMMONIA PLANT
  • 2. Standard Operating Procedure FOR LTS reduction Introduction Fresh/Newly charged LTS catalyst has to be reduced before taken it into service, by this procedure stable copper oxide component of the new catalyst is converted into reactive copper metal. During reduction and operation its zinc oxide and alumina components remain unchanged and act as support, which stabilize the copper metal crystals that act as reservoir for poisons. Hydrogen is used as reducing agent. The reaction of catalyst with hydrogen is exothermic as given below: CuO + H2 ↔ Cu + H2O ∆H = -81 Kj/mol KATALCO 83-3 catalyst is based on copper oxide supported on a matrix of zinc oxide and alumina. Catalyst type: KATALCO 83-3 (CuO) Form: cylindrical pellets Length: 3.0 mm Diameter: 5.2 mm Charged bulk density: 1.38 kg/L or 86 lb/ft3 Vendor: Johnson Matthy Total volume of catalyst: 39.6 m3 Bulk density: 1380 kg/m3 Total weight: 54648 kg CuO in catalyst: 51 wt% Plant condition before reduction Plant load: 50% Air to secondary reformer: Not started yet Source to H2 rich gas: 103F Steam to carbon ratio: 5
  • 3. Reduction circuit: 1. Prepare the reduction circuit of LTS as follows: 2. SFS 1132, SFS 1143, SFS 1144, SFS 1139, SFS 1167, SFS 1168, SFS 1171 and their associated valves should be close. 3. SFS 1165, SFS 1170 and EMV 1165 should be close. 4. Keep close by pass valve of exchanger A-133C1 of line no. 6PF1119. 5. SFS 1133, SFS 1145, and SFS 1172 should be in open position. 6. Open isolation manual valves associated with SFS 1172 and SFS 1145, and block valve of line no. 6PF1121. 7. Establish flow of desulphurised natural gas through LTS slowly at the rate of 15000 Nm3 /hr minimum to maintain space velocity at 300/hr minimum so that gas distribution through the catalyst bed is uniform. Use FI-1140 to measure the N.Gas flow to LTS. 8. Increase the catalyst bed temperature up to 130O C by the by pass valve of the exchanger A-133C1 at the rate of 50O C/hr. keep LTS back pressure at 6.0kg/cm2 g with its manual vent valve on line no.10V1115. 9. Check correct working of hydrogen flow meter F-1168/ F-1169 when catalyst bed temperature reaches 120 ̴130O C. During checking of flow meter do not increase the bed temperature. 10. Install online hydrogen analyzer by connecting it with inlet / outlet sample points S- 1165B & S-1165C of LTS. Before making it online, confirm its accuracy with chemical laboratory results. 11. Increase the top LTS bed temperature up to 180O C. Catalyst reduction When catalyst inlet temperature reached to 180O C, introduce H2 from 103F. 1. Open 103F outlet valve to 104DB fully and open u/s of FI-1169 valve slowly in steps. Keep LTS inlet temperature at 180O C. 2. Establish H2 gas flow at the rate of 30 Nm3/hr initially by opening 1-1/2 ‘’ needle valve. Watch LTS catalyst bed temperature (T-1230 ̴ T-1232, T-1181 ̴ T-1182) for 5 minutes. 3. If catalyst temperatures are not rising by abnormal reaction, increase hydrogen gradually in steps up to 100 m3 /hr. watch LTS bed temperature for 5 minutes after each step. 4. Bed temperature will start increasing when hydrogen starts reacting with CuO catalyst. HPNG BC4 101D 102DA/DB 133C1 LTS /104-DB 103F (H2) VENT
  • 4. 5. Keep on increasing hydrogen flow from 1% to 3% in the inlet Natural Gas gradually by watching bed temperatures. Maintain hydrogen flow maximum till the bed temperature stops rising. 6. Monitor LTS inlet and outlet H2 gas content with online analyzer continuously. Verify these results with laboratory analysis after 1 ̴ 2 hrs. So special arrangements for H2 gas analysis is necessary during LTS catalyst reduction. 7. When 1st bed temperature is coming down the reaction will start in 2nd bed and its temperature will rise. Control the temperature by controlling the hydrogen flow into the N.Gas LTS inlet. Similar steps are to be followed for all the beds till the temperature of the last bed starts decreasing after reaching to peak temperature. 8. Confirm hydrogen consumption which is more than 90% if 1st bed temperature comes down to 1st bed inlet temperature (180O C) one by one. 9. If H2 is not consumed more than 90%, increase inlet temperature of LTS 3O C at every step until 90% hydrogen is consumed. However maximum limit of inlet temperature is 215O C. 10. If H2 is consumed more than 90%, keep that temperature and increase hydrogen contents from 3% to 50% volume gradually. Increasing rate of H2 is 1.5 times of existing hydrogen contents. That is 2% × 1.5 = 3%, 3% × 1.5 = 4.5% 11. During catalyst reduction, watch catalyst bed temperature carefully and if any abnormal temperature rise is found cut H2 supply. 12. Under LTS inlet temperature 215O C and inlet hydrogen contents 50%, if each bed temperature is less than LTS inlet temperature (180O C) and H2 consumption is almost zero, LTS reduction has completed. Soaking When reduction of LTS catalyst completed soaking period started, for this gradually increase the hydrogen concentration in the inlet gas up to 15% incrementally and watch very carefully bed temperatures for 5 ̴10 minutes. Bed temperature neither allows increasing abruptly nor exceeding to 230O C. However, for small duration increase is not harmful for the catalyst.
  • 5. Actual Operating Procedure LTS catalyst blowing To remove entrapped dust particles from catalyst bed, catalyst is blown with desulphurized natural gas for 3 to 4 hours. It was done to avoid increase in pressure drop along the bed and these dust particles cause foaming problem in the CO2 removal system. Circuit for LTS blowing Heating Desulphurized natural gas is used for heating of LTS catalyst. Established the flow of N.Gas to heat the bed up to 130O C at the rate of 50O C per hour and keep the back pressure 5-6 kg/cm2 g. Ensure that both the hydrogen flow meter and analyzer are operating satisfactorily as the temperature approaches 130O C. Continue heating the catalyst until top of bed is at 180O C. The temperature of the gas should not exceed 210O C during the initial heating if natural gas space velocity is less than recommended more care is necessary as there can be poor gas distribution which can lead to localized overheating. Start recording the bed temperature during warm up to confirm that the gas is well distributed through the bed. Circuit for heating  SFS 1132, SFS 1143, SFS 1144, SFS 1167, SFS 1168, SFS 1171 and their associated valves were close.  SFS 1165, SFS 1170 and EMV 1165 should be close.  Used A-133C1 by pass route for heating of LTS.  SFS 1133, SFS 1145, SFS 1177, and SFS 1172 should be open. 102 DA,DB A-133C1 by pass A-104DB Vent
  • 6. H2 injection 1st bed reduction When the temperature of top 3rd bed reached 159O C introduced hydrogen through FI 1169 at the rate of 65 Nm3 /hr. To maintain the inlet temperature of N.Gas 180O C at the inlet increase the H2 flow 65 ̴100 Nm3 /hr then 100 ̴160 Nm3 /hr, 16 ̴ 220 Nm3 /hr, 220 ̴ 280 Nm3 /hr within 4.5 hours of reduction started when the hydrogen concentration at online analyzer reached 7.6% first bed reduction completed and exotherm of first bed was at 224O C, at its peak. Actually hydrogen concentrations at online analyzer 7.6% was more than expectations, the reason was that hydrogen analyzer was giving the results of HTS out let combined, later on analyzer position was changed, HTS outlet blinded, and so H2 analyzer concentrations came to normal. 2nd bed reduction Reduction of 2nd bed completed within 10.5 hours of reduction started, H2 concentration at online analyzer was 2.09% and temperature of 2nd bed was 208O C at that time. 150 160 170 180 190 200 210 220 230 0 2 4 6 8 H2 ConcVS 1st bed temperature 1stbedtemperatures H2 concentration 200 205 210 215 220 225 2 2.5 3 3.5 4 4.5 5 5.5 6 6.5 7 H2 concentration 2ndbedtemperatures
  • 7. 3rd bed reduction Reduction of 3rd bed completed within 17 hours of reduction started, H2 concentration at online analyzer was 2.40% and temperature of 3rd bed was 206O C at that time. 4th bed reduction Reduction of 4th bed completed within 27.5 hours of reduction started, H2 concentration at online analyzer was 2.40% and temperature of 3rd bed was 215O C at that time. 150 160 170 180 190 200 210 220 230 2.15 2.2 2.25 2.3 2.35 2.4 2.45 2.5 H2 ConcentrationVs 3rd bed temperatures H2 Concentration 3rdbedtemperatures 214 214.5 215 215.5 216 216.5 217 2 2.05 2.1 2.15 2.2 2.25 2.3 2.35 2.4 2.45 2.5 2.55 2.6 2.65 2.7 H2 ConcentrationVs 4th bed temperatures H2 Concentration 4thbedtemperatures
  • 8. 5th bed reduction Reduction of 5th bed completed within 29 hours of reduction started, H2 concentration at online analyzer was 2.54% and temperature of 3rd bed was 213O C at that time. Soaking At 34 hours of reduction started temperature 1st ,2nd ,3rd ,4th ,and 5th bed were 191.5,192,192.4,192.2 and 197 respectively then H2 soaking started for this gradually increase the inlet H2 concentration up to 19.08% at that time temperature of inlet gas and all the beds were 219, 219.6, 220.6, 221.5, 223 and 221.8 respectively, since all the beds now were almost same temperature then H2 flow to LTS restricted to zero inlet concentration at LTS inlet and hold for 3.5 hours and after this isolated LTS and hold up it at 30 kg/cm2 g all this activity took 41 hours. At 39 hours of reduction front end load increase started and air to secondary reformer fed at 50% plant load to achieve the desired composition of HTS outlet for taking LTS in service. Circuit for LTS reduction  SFS 1132, SFS 1143, SFS 1144, SFS 1167, SFS 1168, SFS 1171 and their associated valves were close.  SFS 1165, SFS 1170 and EMV 1165 should be close.  Used A-133C1 for LTS reduction.  SFS 1133, SFS 1145, SFS 1177, and SFS 1172 should be open.  H2 flow for reduction was maintained through FI 1169 and later through both FI 1169 and 1168 196 198 200 202 204 206 208 210 212 214 216 2.1 2.2 2.3 2.4 2.5 2.6 2.7 H2 ConcentrationVs 5th bed temperatures H2 Concentration 5thbedtemperatures
  • 9. LTS in service When LTS took in service then temperatures of all the beds shooted abruptly after 12 minutes of taken it into service temperature of 1st bed was 216◦C at its peak, after 15 minutes of service temperature of 2nd bed was 256◦C, after 17 minutes of service temperature of 3rd bed was 287.4◦C, after 23 minutes of service temperature of 4th bed was 300◦C, and after 26 minutes of service temperature of 5th bed was 297◦C. And after that temperatures of all the bed started to come down.