SlideShare a Scribd company logo
1 of 9
Download to read offline
STUDENT INDUSTRIAL WORK EXPERIENCE
SCHEME
A PRESENTATION
BY : RIMAMCHIKA LAZARUS
TSU/FEN/CE/I8/2009
GENERAL NOTES
SETTING OUT FOR POSITION
 ALL POSITION OF STRUCTURAL ELEMENT ARE MARKED OUT USING TOTAL STATION (REFLECT0RLESS
OR 360 DEGREE REFLECTOR IN CASES OF CURVED BEAMS)
FORMWORK
 DOMINO SHUTTERING PANEL WAS USED ( PVC SHUTTERING BOARD ARE USED IN CASES OF CURVED
FORMS)
REINFORCEMENT
 VARIOUS REBARS ARE USED WITH RESPECT TO AREA OF STRUCTURAL ELEMENT
 30MM BISCUIT ARE TIED AROUND REBARS TO PROVIDE FOR CLEAR COVER
 BARS ARE TIED TO EACH OTHER WITH TIE WIRE
CONCRETING
 M40 GRADE OF CONCRETE ARE USED FOR ALL COLUMNS AND BEAMS
 M35 GRADE OF CONCRETE ARE USED FOR SLABS
 M15 GRADE OF CONCRETE ARE USED FOR BLINDING
 ANTI- ARE APPLIED ON ALL CONCRETE AFTER FORM REMOVAL
 EXPANDED POLYSTYRENE (EPS) ARE PLACE WHERE TWO SLAB MEET , AS EXPANSION JOINT
CONSTRUCTION OF COLUMNS SLAB AND BEAMS
COLUMN:
DEFINITION: RCC (Reinforced Cement Cement Concrete) column is a structural
member of RCC framed structured building. Its vertical member which accepts or
carries load from slab and beam directly to the foundation.
MATERIALS USED IN CONSTRUCTION OF COLUMNS:
Cement
Coarse aggregate
Fine aggregate
Steel bar
Water
Shuttering panel
Tie rod and wing knot
wedges
SETTING OUT OF COLUMN POSITION
In this stage of works, the location
Of the columns are determined
Practically in Field. It is done by laying rope according to grids
shown in the drawing and then mark the location of columns
related rope.
For neck columns extended through slabs, form panel are
places beside extended reinforcement, where reinforcement
and form work are adjusted with respect to reflector less
reading from total station.
COLUMN REINFORCEMENT WORK
After marking the column locations, we then start
to place reinforcement as instructed in the
structural drawing.
This is described in the drawing as
(C1-12y16mm@200mm c/c)
COLUMN FORMWORK
Column formwork is a term used for structures
that are used to support forms or moulds for
poured concrete. Here,
Domino panel is place beside reinforcement.
Column alignment is done using a total station.
Concrete biscuit of 30mm is tied on rebar to
allow for clear cover to reinforcement.
CASTING OF CONCRETE ELEMENTS
Concrete are mixed at batching plant
with various mix design/ratio for various
concrete grade (C10, C15, C20, C30, C35,
C40, C50 etc.)
C40 and C35 column grade was used for
our structural columns. `
SLAB
Concrete slab is a structural element which is constructed to create flat and
useful surfaces such as floors. They are commonly supported by beams,
columns, walls or the ground.
FORMWORK
Formwork are created to provide support to the wet concrete until it has gained
sufficient strength.
1) Acrow-prop are placed, arranged and adjusted to designed level
2) Domino shuttering board are placed over the form girder toe retain wet
concrete and give fine smooth finish look.
3) Form girders are placed over them as platform for shuttering panel to be laid
over
4) Oil where applied over domino board for easy formwork removal.
ARRANGEMENT/SPACING OF STEEL BARS
Steel bars diameter and its spacing in the RCC slab is
calculated by designing the slab according to load and span
of the slab. In general
Reinforcing steel bars are placed within the formwork and then
the concrete is poured.
Rebar chairs and biscuit are used to hold the reinforcing steel
bars away from the bottom and sides of the form-work, so that
when the concrete sets it completely envelops the
reinforcement.
LAYING OF CONCRETE/CURING
Wet concrete mixed at batch plant with respect to
mix design are transported in concrete bucket and
carried by stationary crane to place where concrete is
laid. The mix is mechanically mixed and vibrated using
the poker vibrator after laying on the slab.
Curing is done after laying the RCC slab, for full
strength.
BEAM
A beam is a structural element that is capable of withstanding load primarily by resisting against bending. The bending
force induced into the material of the beam as a result of the external loads, self-load, span and external reactions to
these loads, is called bending moment.
According to work arrangement, laying of RCC beam can be done in 4 stages
Formwork
Bending and binding steel bar
Laying of cement concrete
FORMWORK
Formwork is to retain concrete, therefore formwork and shuttering is
required.
1) Domino shuttering board are used to create mould for concrete.
2) Woods are nailed to the board to serve as wedges.
3) Tie rod and wing knot are used to hold shuttering board together from
both ends
4) Woods are placed at 300mm interval to avoid board from breaking
when wet concretes are laid.
BENDING, BINDING AND ARRANGEMENT OF
STEEL BAR
At the time of designing the slab, it is
considered that concrete is strong in
compressive strength but weak in tensile
strength, so therefore to make the structure
safe against tensile stress, steel bars are
provided.
LAYING OF CEMENT CONCRETE
concrete mixed at batch plant with
respect to mix design and ratio are
been transported with the help of the
crane using concrete bucket to place
where concrete is laid. The mix is
mechanically mixed and vibrated
using the poker vibrator after laying on
the beam.
Curing is done after laying the RCC
slab, for full strength

More Related Content

Similar to IT PPT(0).pdf

REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURESREVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURESIRJET Journal
 
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...Deepak Verma
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxtoddr4
 
Experimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabExperimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabIRJET Journal
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesSayedaAmrin
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shutteringKishor Ade
 
Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3Prasanth Dasu
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete constructionJenilPatel22
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)AJAY SHAHU
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concreteMylene Delmoro
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concreteMylene Delmoro
 
Formwork seminar 2
Formwork seminar 2Formwork seminar 2
Formwork seminar 2Gali Suresh
 

Similar to IT PPT(0).pdf (20)

Rigid pavements
Rigid pavements Rigid pavements
Rigid pavements
 
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURESREVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
 
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
 
Experimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabExperimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor Slab
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examples
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
 
Micropiles
Micropiles Micropiles
Micropiles
 
Acm assignment
Acm assignmentAcm assignment
Acm assignment
 
Ppt
PptPpt
Ppt
 
Formwork
FormworkFormwork
Formwork
 
Various elements of building
Various elements of buildingVarious elements of building
Various elements of building
 
Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 
Formwork seminar 2
Formwork seminar 2Formwork seminar 2
Formwork seminar 2
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 

Recently uploaded (20)

MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 

IT PPT(0).pdf

  • 1. STUDENT INDUSTRIAL WORK EXPERIENCE SCHEME A PRESENTATION BY : RIMAMCHIKA LAZARUS TSU/FEN/CE/I8/2009
  • 2. GENERAL NOTES SETTING OUT FOR POSITION  ALL POSITION OF STRUCTURAL ELEMENT ARE MARKED OUT USING TOTAL STATION (REFLECT0RLESS OR 360 DEGREE REFLECTOR IN CASES OF CURVED BEAMS) FORMWORK  DOMINO SHUTTERING PANEL WAS USED ( PVC SHUTTERING BOARD ARE USED IN CASES OF CURVED FORMS) REINFORCEMENT  VARIOUS REBARS ARE USED WITH RESPECT TO AREA OF STRUCTURAL ELEMENT  30MM BISCUIT ARE TIED AROUND REBARS TO PROVIDE FOR CLEAR COVER  BARS ARE TIED TO EACH OTHER WITH TIE WIRE CONCRETING  M40 GRADE OF CONCRETE ARE USED FOR ALL COLUMNS AND BEAMS  M35 GRADE OF CONCRETE ARE USED FOR SLABS  M15 GRADE OF CONCRETE ARE USED FOR BLINDING  ANTI- ARE APPLIED ON ALL CONCRETE AFTER FORM REMOVAL  EXPANDED POLYSTYRENE (EPS) ARE PLACE WHERE TWO SLAB MEET , AS EXPANSION JOINT
  • 3. CONSTRUCTION OF COLUMNS SLAB AND BEAMS COLUMN: DEFINITION: RCC (Reinforced Cement Cement Concrete) column is a structural member of RCC framed structured building. Its vertical member which accepts or carries load from slab and beam directly to the foundation. MATERIALS USED IN CONSTRUCTION OF COLUMNS: Cement Coarse aggregate Fine aggregate Steel bar Water Shuttering panel Tie rod and wing knot wedges
  • 4. SETTING OUT OF COLUMN POSITION In this stage of works, the location Of the columns are determined Practically in Field. It is done by laying rope according to grids shown in the drawing and then mark the location of columns related rope. For neck columns extended through slabs, form panel are places beside extended reinforcement, where reinforcement and form work are adjusted with respect to reflector less reading from total station. COLUMN REINFORCEMENT WORK After marking the column locations, we then start to place reinforcement as instructed in the structural drawing. This is described in the drawing as (C1-12y16mm@200mm c/c)
  • 5. COLUMN FORMWORK Column formwork is a term used for structures that are used to support forms or moulds for poured concrete. Here, Domino panel is place beside reinforcement. Column alignment is done using a total station. Concrete biscuit of 30mm is tied on rebar to allow for clear cover to reinforcement. CASTING OF CONCRETE ELEMENTS Concrete are mixed at batching plant with various mix design/ratio for various concrete grade (C10, C15, C20, C30, C35, C40, C50 etc.) C40 and C35 column grade was used for our structural columns. `
  • 6. SLAB Concrete slab is a structural element which is constructed to create flat and useful surfaces such as floors. They are commonly supported by beams, columns, walls or the ground. FORMWORK Formwork are created to provide support to the wet concrete until it has gained sufficient strength. 1) Acrow-prop are placed, arranged and adjusted to designed level 2) Domino shuttering board are placed over the form girder toe retain wet concrete and give fine smooth finish look. 3) Form girders are placed over them as platform for shuttering panel to be laid over 4) Oil where applied over domino board for easy formwork removal. ARRANGEMENT/SPACING OF STEEL BARS Steel bars diameter and its spacing in the RCC slab is calculated by designing the slab according to load and span of the slab. In general Reinforcing steel bars are placed within the formwork and then the concrete is poured. Rebar chairs and biscuit are used to hold the reinforcing steel bars away from the bottom and sides of the form-work, so that when the concrete sets it completely envelops the reinforcement.
  • 7. LAYING OF CONCRETE/CURING Wet concrete mixed at batch plant with respect to mix design are transported in concrete bucket and carried by stationary crane to place where concrete is laid. The mix is mechanically mixed and vibrated using the poker vibrator after laying on the slab. Curing is done after laying the RCC slab, for full strength.
  • 8. BEAM A beam is a structural element that is capable of withstanding load primarily by resisting against bending. The bending force induced into the material of the beam as a result of the external loads, self-load, span and external reactions to these loads, is called bending moment. According to work arrangement, laying of RCC beam can be done in 4 stages Formwork Bending and binding steel bar Laying of cement concrete FORMWORK Formwork is to retain concrete, therefore formwork and shuttering is required. 1) Domino shuttering board are used to create mould for concrete. 2) Woods are nailed to the board to serve as wedges. 3) Tie rod and wing knot are used to hold shuttering board together from both ends 4) Woods are placed at 300mm interval to avoid board from breaking when wet concretes are laid.
  • 9. BENDING, BINDING AND ARRANGEMENT OF STEEL BAR At the time of designing the slab, it is considered that concrete is strong in compressive strength but weak in tensile strength, so therefore to make the structure safe against tensile stress, steel bars are provided. LAYING OF CEMENT CONCRETE concrete mixed at batch plant with respect to mix design and ratio are been transported with the help of the crane using concrete bucket to place where concrete is laid. The mix is mechanically mixed and vibrated using the poker vibrator after laying on the beam. Curing is done after laying the RCC slab, for full strength