SlideShare a Scribd company logo
1 of 11
Download to read offline
WWW.HIMALAYAL.COM.CN
T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL
info@himalayal.com Page:1 All right reserved.
How to Conduct the Test on the Linearity of
Impulse Voltage Divider
Long Zhaozhi, Liu Shaobo, et al
HIMALAYAL - SHANGHAI - CHINA
Abstract: In the process of tracing the impulse voltage measuring system,
low-voltage DC source or impulse voltage calibrator is utilized to measure the
scale factor of voltage divider. Therefore, the effect of linearity of voltage divider
on uncertainty of measuring system must be taken into account. Given that the
national standard has not been established, an experimental method is put
forward in the paper for measuring the linearity of voltage divider. The resistor
divider R200S is made use of to obtain the linearity of impulse voltage generator;
DC divider is adopted to measure the charge voltage of generator and the ratio of
HCR600 indication value to charge voltage; then the linearity of amended
generator is obtained. The results show that the linearity of HCR600 decreases
from +0.4% to ﹣0.8%; the maximum difference between positive polarity and
negative polarity is 0.14%; the linearity of negative polarity is superior to that of
positive polarity. Moreover, the linearity of 500kV resistor divider with known
linearity is used to be compared with that of HCR600. The results show that two
curves match basically, and the maximum difference is 0.15% at the same voltage.
That means that this method can be used to correctly measure the linearity of
measuring divider. In addition, this method can also be applicable to verify the
test during the establishment of national standards. If the generator equipment
meets some requirements, the method can also be used to calibrate the UHV
impulse equipment.
Key words: linearity, impulse voltage generator, impulse voltage divider,
efficiency deviation, comparison calibration; scale factor, charge voltage
1. Introduction
With continuous development of UHV
transmission technology and the
improvement of transmission line
voltage stage, voltage stage of impulse
voltage generator and measuring
device also improves a lot in order to
meet the requirements of impulse
voltage withstand test about
transformer, current transformer and
capacitor etc. The nationwide electric
power research institutes establish
measuring system of 3600kV impulse
voltage test, UHVAV test base, UHVDC
test base and high altitude base, even
up to 7200kV impulse voltage
measuring system. Correct
high-voltage impulse test results have
a direct influence on the safety and
economy of electric equipment. The
traceability of value is one of effective
methods for ensuring correct and
consistent value. In other words,
WWW.HIMALAYAL.COM.CN
T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL
info@himalayal.com Page:2 All right reserved.
measuring results are traceable to
national or international standards by
means of uninterrupted chains. Hence,
companies at home and abroad pay
more attention to value traceability
and calibrate the equipment on a
regular basis.
America, Australia, German and Japan
has improved impulse standard
measuring system and established
500kV and below impulse voltage
standard measuring system with 0.5%
uncertainty. The physikalisch
technische bundesanstalt (PTB) in
German has established 1500kV
impulse voltage standard device. At
present, the calibration of impulse
voltage measuring device is still at the
theoretical analysis stage, and
measuring standards and regulations
have not yet been established.
Given that voltage stage of impulse
voltage test system reaches several MV,
but voltage stage of standard
measuring system is less than 1000kV,
linearity test on the voltage divider
must be conducted as a necessary
item to ensure the precision of scale
coefficient calibration. According to
IEC 60060-2, GB/T 16927-2010 and
DL/T992-2006 Detailed
Implementation Guide for Impulse
Voltage Measurement, 200kV resistor
divider R200S is used to measure
scale coefficient and linearity of
under-damping voltage divider HCR
600 .
2. Method Analysis
The IEC standards stipulate that
measuring system must conduct the
linearity test. The scale coefficient of
conversion device (voltage divider) is
measured under maximum value,
minimum value and three equal value
within the range of system voltage.
The variation should not be more than
±1% of average value. The test can be
conducted on conversion device or
measuring system. The test waveform
is lightning full wave and operation
wave. However, in most cases, the
standard system is the resistor divider.
The lightning full wave dominates due
to heating and the polarity is positive
and negative polarity.
1) Standard method
The standard measuring system is
adopted to measure the scale
coefficient and its linearity of voltage
system.
2) Alternative methods
No.1 Replace the standard measuring
system by measuring system, which
passes through linearity test via
standard method. Because voltage
stage of standard system is not
enough, this method is not suitable.
No.2 Adopt the sphere gap
measurement to measure the input
voltage of testing voltage divider,
which is shown in Fig.1. The scale
factor can be calculated through the
ratio of measured input voltage to
output voltage of voltage-divided
system. The variation is observed
under five amplitudes of regulated
impulse test voltage. The device for
measuring the sphere gap should
conform to GB/T 311.6-2005.
Moreover, the discharge spark is used
as light and the test should be finished
within a short time. By doing so, it is
not necessary to adjust discharge
voltage used to measure the sphere
WWW.HIMALAYAL.COM.CN
T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL
info@himalayal.com Page:3 All right reserved.
gap according to the environment and
its deviation can be within ±1%. The
difficulties by applying this method
are as follows: ① The linearity of
voltage-divided system via
measurement contains the sphere
gap’s linearity. Even though the
deviation is greater than 1%, that
cannot illustrate that the linearity of
voltage-divided system does not meet
the requirements of standards; ②
Now, only a few universities and
research institutes have sphere gaps
with large-diameter; ③ When the
diameter of sphere gap remains the
same, the higher voltage stage is, the
larger sphere gap distance becomes.
When the distance increases to a
certain degree, the electric field
between sphere gaps changes from
even electric field to uneven field, and
the dispersibility of discharge voltage
is great. Hence, this method does not
work.
G -- Impulse voltage generator
S -- measuring sphere gap
D -- testing voltage system
M -- testing instrument
Fig.1 Linearity test with sphere gap
No.3 Adopt electric field strength
tester to measure the linearity of
voltage-divided system and calculate
the ratio of output voltage of divided
voltage system to corresponding
electric field strength. Because stray
parameter does not have impact on
the electric field sensor, the electric
field does not distort without corona,
and the electric field is proportional to
voltage; the electric field sensor uses
optical fiber to measure the output
signal and there is no interference. In
2009, Tsinghua University cooperated
with China Electric Power Research
Institute to measure the operation
impulse voltage in a middle-phase
tower window of real cup-shaped
tower in the outdoor test base. The
sensor has good time domain
response for impulse voltage signal,
and the electric field waveform is in
consistent with voltage waveform
without corona; if the corona occurs,
the electric field distorts seriously,
and there is great deviation between
measuring value and calculation value.
Existing problems are as follows: ①
The precision of electric field tester is
low, only 1% or so; so is the imported
tester; ② The corona has a significant
influence on the electric field tester;
when the impulse voltage generator
generates MV high voltage, the corona
will happen. Hence, electric field
tester is only used as auxiliary device.
No.4 As for voltage-divided system
with many stages, the linearity test
can be conducted stage by stage. If
each unit of voltage divider passes the
linearity test, and the whole
assembled voltage divider has no
corona under the maximum voltage, it
means that the voltage-divided system
is linear. This method is suitable for
delivery and acceptance test and
regular calibration lab. However, in
most tests, the time is limited and it is
WWW.HIMALAYAL.COM.CN
T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL
info@himalayal.com Page:4 All right reserved.
difficult to assemble the voltage
divider. Moreover, the voltage-divided
system cannot ensure that there is no
corona under the maximum voltage.
No.5 Utilize impulse voltage
generator’s charge voltage to measure
the linearity of testing voltage-divided
system. During the test, charge
condition should be kept stable. With
five amplitudes of regulated impulse
test voltage, the ratio of output voltage
of voltage-divided system to
corresponding charge voltage is
calculated. If the ratio is within ±1%
of average value, this system is
regarded linear. This method was used
to measure the linearity in Indian UHV
lab. The Japanese expert Harada made
use of 700kV voltage divider with
known linearity and impulse voltage
generator to obtain the linearity of
standard voltage divider when he was
developing the standard resistor
divider. When Japan Science Institute
and the University of Tokyo were
setting the standard impulse
measuring system, they used impulse
generator to measure the linearity of
voltage divider, kept charge voltage
per stage the same, determined the
linearity of impulse voltage generator
by means of 300kV resistor divider
with known linearity, and finally get
the linearity of 1200kV voltage divider.
Advantages of this method are as
follows: ① There is no need to
disassemble the equipment and the
test time is short; ② At present, the
technology of control system is
mature. If the charge time is kept
certain, amplitude repeatability of
impulse voltage is less than 0.5% with
same stage and charge voltage; ③
The linearity of system measured by
this method often includes the
linearity of the generator. But, if there
exists the voltage-divided system with
above two linearities, the linearity of
the generator can be got. At this point,
the linearity of voltage-divider system
can be accurately measured.
The fifth method is adopted in the
paper to measure the linearity of
600kV under-damping voltage divider
HCR 600. 200kV resistor divider
R200S is used to rate the scale factor
of HCR600; remove the R200S and
keep charge time and generator body
stage the same; raise the voltage and
use the DC voltage divider to measure
the charge voltage of impulse
generator; the ratio of five voltage
divider indication values to charge
voltage is obtained. The variation of
the ratio is the linearity of HCR600.
3. Performance Test of Resistor
Divider R200S
3.1 DC voltage ratio
The test circuit is shown in Fig.2. The
KEITHLEY2410 DC source applies DC
voltage on 220kV impulse resistor
divider R200S. The Angilent 34401A
six and a half digital multi-meter is
adopted to measure the output
voltage of DC source and R200S
low-voltage arm. Then the ratio is
calculated under stable condition. The
DC voltage is raised from 50V to 500V.
The statistical diagram of scale factor
is shown in Fig.3. The value of each
point is the average value of three
measurements. Based on Fig.3, the
dispersibility of R200S’s stable scale
factor is small; its average is 108.985;
there is no distinction of positive and
negative polarity.
WWW.HIMALAYAL.COM.CN
T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL
info@himalayal.com Page:5 All right reserved.
Fig.2 Test circuit of measuring DC
ratio
Fig.3 DC scale ratio of the divider
3.2 Dynamic features
According to Fig.4, the circuit is set up
and step wave response waveform of
R200S is measured. There is square
wave source, and its output step wave
amplitude is 100V. Test result is
shown in Fig.5. In the Fig.5, waveform
of R200S step wave response is
represented by Ch1 while output
waveform of square wave source is
represented by Ch2. The partial
response time is about 10ns;
overshoot is 2.3%; stable time is 97ns.
Its dynamic features meet the
requirements of IEC 60060-2.
Fig.4 Circuit of step wave response
Fig.5 Waveform of step wave response
3.3 Impulse scale factor
The impulse scale factor of R200S can
be obtained by adopting the
comparison method, which is shown
in Fig.6. When the test is conducted,
please ensure that the included angle
between resistor divider and R200S is
90°. Both D1 cable end and Df cable
end are connected to measuring
system (oscilloscope and measuring
software) via the attenuator. Before
and after the test, some calibrator is
utilized to calibrate the scale factor of
attenuator in real-time. The scale
factor of R200S positive and negative
polarity is measured under 160kV. In
the Fig.7, the triangle represents
positive polarity and the square
represents negative polarity. From the
Fig.7, the dispersibility of R200S scale
factor is small; the positive polarity is
more than negative one; the average
scale factor of positive polarity is
109.25 while that of negative polarity
is 108.61. The deviation is 0.24% and
0.34%.
WWW.HIMALAYAL.COM.CN
T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL
info@himalayal.com Page:6 All right reserved.
G -- Impulse voltage generator
C-- Load capacitor (Under-damping
divider)
D1 --R200S
Df -- Standard resistor divider
Fig.6 Diagram of calibrating scale
factor of R200S
Fig.7 Repeatable test results of scale
factor
4. Test Proposal and Procedure
4.1 Measurement of impulse voltage
generator’s linearity
First of all, measure the linearity of
impulse voltage generator; adjust the
generator; use four-stage charge
capacitor and 200kV DC voltage
divider SGB-200 to monitor first-stage
charge voltage (measuring precision
is 0.1% and can trace back to national
DC standards); then R200S is
connected into the circuit; the
linearity of R200S is 0.12%, which can
be ignored. The equipment used in
this test is shown in Fig.8. The test is
conducted based on each stage charge
voltage (15, 23, 33, 42, 53kV) shown
in Fig.9. The output voltage of
generator rises from 50kV to 176kV;
the test is repeated 40 times at each
voltage point; charge time is 60s;
normal trigger per each time and the
environment is consistent (the
temperature is 20 ° and relative
humidity is 60%). The ratio of R200S
output voltage to charge voltage is
calculated, and the deviation between
this ratio and average value is also
obtained (shown in Fig.9 vertical
axis). Finally we get the variation
trend of the linearity of voltage
generator. Based on Fig.9, no special
law for the linearity of generator is
summarized; there is a great
discrepancy between the trend of
positive polarity and that of negative
polarity. Because the structure of each
generator or stray parameter of all
elements is different, the linearity of
each generator is unique.
WWW.HIMALAYAL.COM.CN
T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL
info@himalayal.com Page:7 All right reserved.
RD-- resistor divider
IVG-- Impulse voltage generator
Fig.8 Equipment used in the test
Fig.9 Test results of the linearity on
impulse generator
4.2 The scale factor of under-damping
divider HCR600 under 20% rated
voltage
R200S is utilized to measure the scale
factor of HCR600 under 160kV. The
repetition test result is shown in
Fig.10. The positive polarity is
represented by triangle while negative
polarity is denoted by square.
According to Fig.10, average scale
factor of positive polarity is 2026
while 2028 for negative polarity. The
dispersibility of negative polarity is
greater.
Fig.10 Scale factor calibration of
HCR600 with R200S
4.3 Measurement of HCR600 linearity
From then on, the generator should
have twelve stages and the
environment should keep consistent
(the temperature is 20 ℃ , relative
humidity is 60%). The impulse voltage
generator is connected with HCR600;
SGB-200 is used to measure charge
voltage of first-stage capacitance;
charge voltage of each stage is raised
based on 3.1 section (15, 23, 33, 42,
55kV); output voltage of the generator
is roughly equal to five voltage points
of HCR-600. Output voltage of
HCR600 and monitoring voltage of
SGB-200 are measured; the test is
repeated 40 times at each voltage
point under single polarity; charge
time per time is 60s and the sphere
gap should be triggered normally.
Before and after the test, impulse
voltage calibrator RIC422 is applied to
calibrate scale factor of the attenuator
in real-time and to amend the
influence of secondary attenuating
change on test results.
The ratio of HCR’s output voltage to
charge voltage is calculated. The
deviation between the ratio and its
average value is shown in Fig.11(a).
The test results are amended
according to Fig.9, which is shown in
Fig.11 (b). From Fig.11 (b), the
linearity of HCR-600 ranges from
+0.4% to ﹣ 0.8% and is inversely
proportional to the voltage; the
difference between positive polarity
and negative polarity under the same
voltage is small; the biggest difference
(0.14%) appears at 42kV point; but as
a whole, the linearity of negative
polarity is superior to that of positive
polarity.
WWW.HIMALAYAL.COM.CN
T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL
info@himalayal.com Page:8 All right reserved.
Fig.11 Linearity test results of
HCR-600
5. Experimental Test
In order to verify whether the test
result presented in section 4.3 is
reasonable, standard voltage divider
SMR7.7/500ref is compared with
HCR600. Because the rated voltage of
standard voltage divider is 500kV,
only first four voltage points are
selected. The test condition is the
same as that described in section 4.3.
The compared results are amended by
SMR7.7/500ref, which is shown in
Fig.12. The positive polarity is
represented by triangle while square
for negative polarity. Through
comparing Fig.11 (b) and Fig. (12), as
for first four points, the two curves
decrease and the linearity of negative
polarity is superior to that of positive
polarity; the difference of positive
polarity is close to that of negative
polarity; the maximum difference
appears at 42kV point; the maximum
difference (0.15%) of both diagrams
appears at 33kV under the same
polarity. Results show that this
method presented in section 3.3 is
reasonable and can be used in the
tracing study of impulse voltage.
Only satisfying the following
requirements does the method can be
used in the calibration of impulse
voltage measuring system.
1) The test must be conducted
indoors. The indoor temperature and
humidity can be adjusted to reduce
the influence on the test result.
2) The used impulse voltage
generator can produce standard
lightning full wave without overshoot,
and control the charge time. Moreover,
the control software can monitor and
compensate the charge voltage in
real-time.
3) The generator can realize
self-trigger discharge after sphere gap
is well adjusted, avoiding
self-discharge in advance. The
precision of used DC voltage divider
should be more than 0.5%. It can
record the standard DC divider while
discharging at the same time.
4) During the repetition test,
measured output waveform amplitude,
wave front time and wave tail time
should not change greatly. If we
WWW.HIMALAYAL.COM.CN
T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL
info@himalayal.com Page:9 All right reserved.
conduct many tests, the resistance of
the generator may heat up, resulting
in the change of circuit parameters.
Hence, heat dissipation should be
done on a regular basis.
5) Because the capacitive voltage
divider can be affected by its own
position, please don’t move it during
the test. The lab should be empty to
reduce the stray capacitance that
voltage divider brings to other objects.
6) Owning to good stability and
repetition, resistor divider is
recommended.
6. Conclusions
1) The scale factor of positive polarity
impulse of resistor divider R200S is
109.25 while 108.61 for negative
polarity. The deviation is within ±
0.34%. Its partial response time is
10ns or so; the overshoot is 2.3%;
stable time is 97ns. Its features
conform to the regulations on
standard impulse divider of
IEC60060-2.
2) The linearity of one impulse
voltage generator is different from
others. The linearity variation of
impulse voltage generator used in the
lab is as follows: the positive polarity
is greatly different from negative
polarity; the change does not follow
any special law; as the voltage rises,
the linearity presents
non-monotonous change. The
linearity of amended HCR600 is in the
following: as the charge voltage
increases, the linearity decreases
monotonically between +0.4% and ﹣
0.8%; the maximum difference
(0.14%) appears at 42kV point; the
linearity of negative polarity is
superior to that of positive polarity.
3) The linearity variation of HCR600
can be obtained within 500kV by
comparing standard voltage divider
SMR7.7/500ref with HCR600. The
deviation of two test results is close;
the maximum difference at 33kV
positive polarity is 0.15%; the
variation trend is monotonic
decreasing. Hence, the method can be
used in the linearity measurement of
impulse voltage standard system.
When the test equipment meets the
requirement, this method can be
utilized in the calibration test of UHV
impulse measuring equipment.
REFERENCES
[1] Yang Yingjian, Hu Yi, Wu Xiong.
Construction of UHV AC test base of
SGCC [J]. High Voltage Engineering,
2007, 33(11): 6-9.
[2] Li Guangfan, Liao Weiming, Li
Qingfeng. Voltage output performance
of 7200kV/480kJ impulse voltage
generator [J]. Proceeding of the CSEE,
2008, 28(25): 1-7.
[3] He Huiwen, Gu Dingxie, Zhou
Peihong, et al. Simulating calculation
and analysis on time-to-crest of
switching impulse for test on Chinese
UHV AC pilot project[J]. High Voltage
Engineering, 2011, 37(9): 2156-2162.
[4] Wakimoto T, Ishii M. National
standard class measuring system for
impulse voltage in Japan [C]//15th
International Symposium on High
Voltage Engineering. Ljubljana,
Slovenia: [s.n], 2007:1-5.
WWW.HIMALAYAL.COM.CN
T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL
info@himalayal.com Page:10 All right
reserved.
[5] Hallstrom J, Aro M, Zhang Y, et al.
Progress of a worldwide Comparison
of LI measuring systems: round
1[C]//12th International Symposium
on High Voltage Engineering.
Bangalore, India: [s.n.], 2001:1-7.
[6] Harada T, Wakimoto T, Sato S, et al.
Development of national standard
class reference divider for impulse
voltage measurement [C]//11th
International Symposium on High
Voltage Engineering. London, England:
[s.n.], 1999: 13-16.
[7] Harada T, Wakamoto T, Saeki M, et
al. Development and performance test
of the reference divider for 300kV
lightning impulse voltage
measurement in Japan [C] //10th
International Symposium on High
Voltage Engineering. Montreal,
Canada: [s.n.], 1997: 303-306.
[8] Yu Cunyi, Xiong Yun, Yuan Meizhen.
The international comparison of
impulse voltage measurement [J].
High Voltage Engineering, 1992,18(3):
59-62.
[9] Huang Dexiang, Ren Wenzhu, Zhou
Huigao. The international comparison
of impulse voltage measurement [J].
High Voltage Apparatus, 1992,28(3):
3-10.
[10] Ren Wenzhu, Feng Jianhua, Ge
Zhen. 800kV standard impulse voltage
measuring system and the uncertainty
of evaluation[J]. Acta Metrologica
Sinica, 2008, 29(2): 153-157.
[11] He Yi, Li Yanming, Zhang
Xiaoyong. Experience of the
international comparison of impulse
voltage measuring systems [J]. High
Voltage Engineering, 2001, 27(5):
153-157.
[12] Yang Yingjian. Establishing of
impulse voltage reference device [J].
High Voltage Engineering, 2006,
27(5) : 54-56.
[13] Liu Zhen, Zhou Chunyu, Yu Fang.
Characteristics of the long fronted
switching impulse discharge [J]. High
Voltage Engineering, 2009, 35(10):
2401-2406.
[14] IEC 60060-1 High-voltage test
techniques, Part 1: general definitions
and test requirements [S], 2010.
[15] Huo Feng, Wan Qifa, Hu Wei. Long
wave-front impulse voltage test of
UHV air-gaps with multistage method
and result statistics [J]. High Voltage
Engineering, 2011, 37(9): 2171-2177.
[16] IEC 60060-2 High-voltage test
techniques, part 2: measuring systems
[S], 2010.
[17] DL/T 992-2006 Detailed
implementation guide for impulse
voltage measurement [M]. Beijing,
China: China Electric Power Press,
2006.
[18] Li Qingquan, Liu Jian, Li Yanming.
Spherical sensor for the measuring
transient electric fields based on
optical fiber [J]. Journal of Transducer
Technology, 2002, 21(3): 8-12.
[19] Fester K, Pfaff W. A potential free
spherical sensor for the measurement
of transient electric fields [J]. IEEE
Transactions on Power Apparatus and
Systems, 1984, 103 (10): 2904-2911.
[20] Chen Weiyuan, Zeng Rong, Liang
Xidong, et al. Design of an
WWW.HIMALAYAL.COM.CN
T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL
info@himalayal.com Page:11 All right
reserved.
electro-optic integrated electric field
sensor [J]. Journal of Tsinghua
University; Science and Technology,
2006, 46(10): 1641-1644.
[21] Niu Ben, Zeng Rong, Geng Yinan.
Electric field measurement of
switching impulse discharge in UHV
Tower [J]. High Voltage Engineering,
2009, 35(4): 731-736.
[22] Zhang Renyu, Chen Changyu,
Wang Changchang. High-voltage
testing technology [M]. Beijing, China:
Tsinghua University Press, 2003.
[23] Cao Jing, Wan Qifa, Zhang Qin.
Analysis on phase-to-phase switching
impulse discharge characteristic of
high altitude converter station [J].
High Voltage Engineering, 2010,
36(12): 2896-2901.
[24] Zhang Yixiu, Sun Wei, Fu
Zhengcai. Simulation and
experimental investigation of the
charging ununiformity of impulse
voltage generators [J]. Electrical
Engineering, 2009 (2): 34-37.

More Related Content

What's hot

Electronics measurements and instrumentation basics
Electronics measurements and instrumentation basicsElectronics measurements and instrumentation basics
Electronics measurements and instrumentation basicsAbhishek Thakkar
 
Electrical measuring instruments
Electrical measuring instrumentsElectrical measuring instruments
Electrical measuring instrumentsVinod Adakkaputhur
 
Electrical Measurement, Instrumentation and Sensors
Electrical Measurement, Instrumentation and SensorsElectrical Measurement, Instrumentation and Sensors
Electrical Measurement, Instrumentation and SensorsRidwanul Hoque
 
ELECTRICAL AND ELECTRONICS MEASUREMENT
ELECTRICAL AND ELECTRONICS MEASUREMENT ELECTRICAL AND ELECTRONICS MEASUREMENT
ELECTRICAL AND ELECTRONICS MEASUREMENT Dinesh Sharma
 
Electrical measurement & measuring instruments [emmi (nee-302) -unit-3]
Electrical measurement & measuring instruments [emmi  (nee-302) -unit-3]Electrical measurement & measuring instruments [emmi  (nee-302) -unit-3]
Electrical measurement & measuring instruments [emmi (nee-302) -unit-3]Md Irshad Ahmad
 
A 1 maintain electrical system installation of mechatronics system
A 1  maintain electrical system installation of  mechatronics systemA 1  maintain electrical system installation of  mechatronics system
A 1 maintain electrical system installation of mechatronics systemSyyed Ali
 
Outcome 2.3 identify appropriate electrical instruments for the measurement...
Outcome 2.3   identify appropriate electrical instruments for the measurement...Outcome 2.3   identify appropriate electrical instruments for the measurement...
Outcome 2.3 identify appropriate electrical instruments for the measurement...sanewton
 
What is test method of impulse limiting voltage on signal SPD (impulse voltag...
What is test method of impulse limiting voltage on signal SPD (impulse voltag...What is test method of impulse limiting voltage on signal SPD (impulse voltag...
What is test method of impulse limiting voltage on signal SPD (impulse voltag...Fang Sam
 
Nebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and Admittance
Nebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and AdmittanceNebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and Admittance
Nebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and AdmittanceTESCO - The Eastern Specialty Company
 
instruments and measurements
instruments and measurementsinstruments and measurements
instruments and measurementsadnanqayum
 
Electrical measuring instruments
Electrical measuring instrumentsElectrical measuring instruments
Electrical measuring instrumentsMinka Grdesic
 
Electrical measurements - Sultan LeMarc
Electrical measurements - Sultan LeMarcElectrical measurements - Sultan LeMarc
Electrical measurements - Sultan LeMarcslemarc
 
Electrical measurements unit-1-measuring instruments
Electrical measurements unit-1-measuring instrumentsElectrical measurements unit-1-measuring instruments
Electrical measurements unit-1-measuring instrumentsRAGHU ENGINEERING COLLEGE
 

What's hot (20)

TESCO Tuesday: Ratio, Burden and Admittance
TESCO Tuesday: Ratio, Burden and AdmittanceTESCO Tuesday: Ratio, Burden and Admittance
TESCO Tuesday: Ratio, Burden and Admittance
 
Electronics measurements and instrumentation basics
Electronics measurements and instrumentation basicsElectronics measurements and instrumentation basics
Electronics measurements and instrumentation basics
 
Electrical measuring instruments
Electrical measuring instrumentsElectrical measuring instruments
Electrical measuring instruments
 
Electrical Measurement, Instrumentation and Sensors
Electrical Measurement, Instrumentation and SensorsElectrical Measurement, Instrumentation and Sensors
Electrical Measurement, Instrumentation and Sensors
 
Complete Site Testing
Complete Site TestingComplete Site Testing
Complete Site Testing
 
ELECTRICAL AND ELECTRONICS MEASUREMENT
ELECTRICAL AND ELECTRONICS MEASUREMENT ELECTRICAL AND ELECTRONICS MEASUREMENT
ELECTRICAL AND ELECTRONICS MEASUREMENT
 
Communicating to Your Meters
Communicating to Your MetersCommunicating to Your Meters
Communicating to Your Meters
 
Electrical measurement & measuring instruments [emmi (nee-302) -unit-3]
Electrical measurement & measuring instruments [emmi  (nee-302) -unit-3]Electrical measurement & measuring instruments [emmi  (nee-302) -unit-3]
Electrical measurement & measuring instruments [emmi (nee-302) -unit-3]
 
A 1 maintain electrical system installation of mechatronics system
A 1  maintain electrical system installation of  mechatronics systemA 1  maintain electrical system installation of  mechatronics system
A 1 maintain electrical system installation of mechatronics system
 
Outcome 2.3 identify appropriate electrical instruments for the measurement...
Outcome 2.3   identify appropriate electrical instruments for the measurement...Outcome 2.3   identify appropriate electrical instruments for the measurement...
Outcome 2.3 identify appropriate electrical instruments for the measurement...
 
What is test method of impulse limiting voltage on signal SPD (impulse voltag...
What is test method of impulse limiting voltage on signal SPD (impulse voltag...What is test method of impulse limiting voltage on signal SPD (impulse voltag...
What is test method of impulse limiting voltage on signal SPD (impulse voltag...
 
Transformer Rated Metering 09.27.17
Transformer Rated Metering 09.27.17Transformer Rated Metering 09.27.17
Transformer Rated Metering 09.27.17
 
Nebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and Admittance
Nebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and AdmittanceNebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and Admittance
Nebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and Admittance
 
instruments and measurements
instruments and measurementsinstruments and measurements
instruments and measurements
 
Electrical measuring instruments
Electrical measuring instrumentsElectrical measuring instruments
Electrical measuring instruments
 
Introduction to Transformer Rated Metering
Introduction to Transformer Rated MeteringIntroduction to Transformer Rated Metering
Introduction to Transformer Rated Metering
 
Four Quadrant Metering
Four Quadrant MeteringFour Quadrant Metering
Four Quadrant Metering
 
Electrical measurements - Sultan LeMarc
Electrical measurements - Sultan LeMarcElectrical measurements - Sultan LeMarc
Electrical measurements - Sultan LeMarc
 
DC Metering and Traceability
DC Metering and TraceabilityDC Metering and Traceability
DC Metering and Traceability
 
Electrical measurements unit-1-measuring instruments
Electrical measurements unit-1-measuring instrumentsElectrical measurements unit-1-measuring instruments
Electrical measurements unit-1-measuring instruments
 

Viewers also liked

WEIDMANN Integrated Services
WEIDMANN Integrated ServicesWEIDMANN Integrated Services
WEIDMANN Integrated Servicespontetto
 
1 hvdc systems_in_india
1 hvdc systems_in_india1 hvdc systems_in_india
1 hvdc systems_in_indiaganesh g
 
T 1 transformer insulation oil sensing system
T 1  transformer insulation oil sensing systemT 1  transformer insulation oil sensing system
T 1 transformer insulation oil sensing systemChung Da-woon
 
High Voltage Direct Current Transmission System
High Voltage Direct Current Transmission SystemHigh Voltage Direct Current Transmission System
High Voltage Direct Current Transmission SystemNadeem Khilji
 
POWER TRANSFORMER INSULATION REVITALIZATION
POWER TRANSFORMER INSULATION REVITALIZATIONPOWER TRANSFORMER INSULATION REVITALIZATION
POWER TRANSFORMER INSULATION REVITALIZATIONDejan Pantić
 
Трансформатор с керамической изоляцией
Трансформатор с керамической изоляциейТрансформатор с керамической изоляцией
Трансформатор с керамической изоляциейStartupvillage2015
 
Design, Modeling and control of modular multilevel converters (MMC) based hvd...
Design, Modeling and control of modular multilevel converters (MMC) based hvd...Design, Modeling and control of modular multilevel converters (MMC) based hvd...
Design, Modeling and control of modular multilevel converters (MMC) based hvd...Ghazal Falahi
 
6654882 presentation-on-insulation-co ordination
6654882 presentation-on-insulation-co ordination6654882 presentation-on-insulation-co ordination
6654882 presentation-on-insulation-co ordinationRui Zhang
 
High Voltage Dc (HVDC) transmission
High Voltage Dc (HVDC) transmissionHigh Voltage Dc (HVDC) transmission
High Voltage Dc (HVDC) transmissionZunAib Ali
 

Viewers also liked (19)

WEIDMANN Integrated Services
WEIDMANN Integrated ServicesWEIDMANN Integrated Services
WEIDMANN Integrated Services
 
10.1.1.125.8882
10.1.1.125.888210.1.1.125.8882
10.1.1.125.8882
 
1 hvdc systems_in_india
1 hvdc systems_in_india1 hvdc systems_in_india
1 hvdc systems_in_india
 
Edited hvdc2222upload
Edited hvdc2222uploadEdited hvdc2222upload
Edited hvdc2222upload
 
Insulation
InsulationInsulation
Insulation
 
T 1 transformer insulation oil sensing system
T 1  transformer insulation oil sensing systemT 1  transformer insulation oil sensing system
T 1 transformer insulation oil sensing system
 
Hvdc
HvdcHvdc
Hvdc
 
High Voltage Direct Current Transmission System
High Voltage Direct Current Transmission SystemHigh Voltage Direct Current Transmission System
High Voltage Direct Current Transmission System
 
POWER TRANSFORMER INSULATION REVITALIZATION
POWER TRANSFORMER INSULATION REVITALIZATIONPOWER TRANSFORMER INSULATION REVITALIZATION
POWER TRANSFORMER INSULATION REVITALIZATION
 
Трансформатор с керамической изоляцией
Трансформатор с керамической изоляциейТрансформатор с керамической изоляцией
Трансформатор с керамической изоляцией
 
Insulation coordination
Insulation coordinationInsulation coordination
Insulation coordination
 
HVDC benefits and types
HVDC benefits and typesHVDC benefits and types
HVDC benefits and types
 
Design, Modeling and control of modular multilevel converters (MMC) based hvd...
Design, Modeling and control of modular multilevel converters (MMC) based hvd...Design, Modeling and control of modular multilevel converters (MMC) based hvd...
Design, Modeling and control of modular multilevel converters (MMC) based hvd...
 
6654882 presentation-on-insulation-co ordination
6654882 presentation-on-insulation-co ordination6654882 presentation-on-insulation-co ordination
6654882 presentation-on-insulation-co ordination
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
HVDC
HVDC HVDC
HVDC
 
HVDC vs HVAC ppt
HVDC vs HVAC pptHVDC vs HVAC ppt
HVDC vs HVAC ppt
 
HVDC presentation
HVDC presentationHVDC presentation
HVDC presentation
 
High Voltage Dc (HVDC) transmission
High Voltage Dc (HVDC) transmissionHigh Voltage Dc (HVDC) transmission
High Voltage Dc (HVDC) transmission
 

Similar to How to conduct the test on the linearity of impulse voltage divider? (www.himalayal.com-impulse voltage generator)

Best transformer-test-procedures-en
Best transformer-test-procedures-enBest transformer-test-procedures-en
Best transformer-test-procedures-enSuresh Patil
 
Relay operation principles
Relay operation principlesRelay operation principles
Relay operation principlesAmmar Al Hakeim
 
Power grid synopsis
Power grid synopsisPower grid synopsis
Power grid synopsisParveen Jaat
 
DC potentiometers
DC potentiometersDC potentiometers
DC potentiometerstadi1padma
 
EmI Unit-2.pptx
EmI Unit-2.pptxEmI Unit-2.pptx
EmI Unit-2.pptxMamthaMam1
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
283481961-POWER-SYSTEM-FAULTS-ppt.ppt
283481961-POWER-SYSTEM-FAULTS-ppt.ppt283481961-POWER-SYSTEM-FAULTS-ppt.ppt
283481961-POWER-SYSTEM-FAULTS-ppt.pptAshaLatha456489
 
A High-Performance SPWM Controller for Three-Phase UPS Systems Operating Unde...
A High-Performance SPWM Controller for Three-Phase UPS Systems Operating Unde...A High-Performance SPWM Controller for Three-Phase UPS Systems Operating Unde...
A High-Performance SPWM Controller for Three-Phase UPS Systems Operating Unde...ijiert bestjournal
 
06 current -__voltage_transformers
06 current -__voltage_transformers06 current -__voltage_transformers
06 current -__voltage_transformersKrishna Das
 
Grid fault Control Scheme for Peak Current Reduction in Photovoltaic Inverte...
Grid fault Control Scheme for Peak Current Reduction in  Photovoltaic Inverte...Grid fault Control Scheme for Peak Current Reduction in  Photovoltaic Inverte...
Grid fault Control Scheme for Peak Current Reduction in Photovoltaic Inverte...IJMER
 
Final Project Paper
Final Project PaperFinal Project Paper
Final Project PaperAhmed Hashem
 
Summary Presentation on PMU Based Transmission Line Protection Scheme
Summary Presentation on PMU Based Transmission Line Protection Scheme Summary Presentation on PMU Based Transmission Line Protection Scheme
Summary Presentation on PMU Based Transmission Line Protection Scheme Samuel Okhuegbe
 
Power quality improvement by series active power filter- a review
Power quality improvement by series active power filter- a reviewPower quality improvement by series active power filter- a review
Power quality improvement by series active power filter- a reviewIRJET Journal
 
Microsoft PowerPoint - Unit II.pdf
Microsoft PowerPoint - Unit II.pdfMicrosoft PowerPoint - Unit II.pdf
Microsoft PowerPoint - Unit II.pdfsrevathiap
 
Impulse testing of transformer
Impulse testing of transformerImpulse testing of transformer
Impulse testing of transformerPreet_patel
 

Similar to How to conduct the test on the linearity of impulse voltage divider? (www.himalayal.com-impulse voltage generator) (20)

Best transformer-test-procedures-en
Best transformer-test-procedures-enBest transformer-test-procedures-en
Best transformer-test-procedures-en
 
PPT.pptx
PPT.pptxPPT.pptx
PPT.pptx
 
Relay operation principles
Relay operation principlesRelay operation principles
Relay operation principles
 
Power grid synopsis
Power grid synopsisPower grid synopsis
Power grid synopsis
 
eem-2020309.pdf
eem-2020309.pdfeem-2020309.pdf
eem-2020309.pdf
 
DC potentiometers
DC potentiometersDC potentiometers
DC potentiometers
 
Kf3517721775
Kf3517721775Kf3517721775
Kf3517721775
 
EmI Unit-2.pptx
EmI Unit-2.pptxEmI Unit-2.pptx
EmI Unit-2.pptx
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
283481961-POWER-SYSTEM-FAULTS-ppt.ppt
283481961-POWER-SYSTEM-FAULTS-ppt.ppt283481961-POWER-SYSTEM-FAULTS-ppt.ppt
283481961-POWER-SYSTEM-FAULTS-ppt.ppt
 
A High-Performance SPWM Controller for Three-Phase UPS Systems Operating Unde...
A High-Performance SPWM Controller for Three-Phase UPS Systems Operating Unde...A High-Performance SPWM Controller for Three-Phase UPS Systems Operating Unde...
A High-Performance SPWM Controller for Three-Phase UPS Systems Operating Unde...
 
06 current -__voltage_transformers
06 current -__voltage_transformers06 current -__voltage_transformers
06 current -__voltage_transformers
 
Grid fault Control Scheme for Peak Current Reduction in Photovoltaic Inverte...
Grid fault Control Scheme for Peak Current Reduction in  Photovoltaic Inverte...Grid fault Control Scheme for Peak Current Reduction in  Photovoltaic Inverte...
Grid fault Control Scheme for Peak Current Reduction in Photovoltaic Inverte...
 
Final Project Paper
Final Project PaperFinal Project Paper
Final Project Paper
 
Summary Presentation on PMU Based Transmission Line Protection Scheme
Summary Presentation on PMU Based Transmission Line Protection Scheme Summary Presentation on PMU Based Transmission Line Protection Scheme
Summary Presentation on PMU Based Transmission Line Protection Scheme
 
Power quality improvement by series active power filter- a review
Power quality improvement by series active power filter- a reviewPower quality improvement by series active power filter- a review
Power quality improvement by series active power filter- a review
 
Microsoft PowerPoint - Unit II.pdf
Microsoft PowerPoint - Unit II.pdfMicrosoft PowerPoint - Unit II.pdf
Microsoft PowerPoint - Unit II.pdf
 
presentation.pptx
presentation.pptxpresentation.pptx
presentation.pptx
 
presentation.pptx
presentation.pptxpresentation.pptx
presentation.pptx
 
Impulse testing of transformer
Impulse testing of transformerImpulse testing of transformer
Impulse testing of transformer
 

More from Fang Sam

HSC Gas Insulated Standard Capacitor
HSC Gas Insulated Standard CapacitorHSC Gas Insulated Standard Capacitor
HSC Gas Insulated Standard CapacitorFang Sam
 
Impulse-Voltage-Generator-Test-System
Impulse-Voltage-Generator-Test-SystemImpulse-Voltage-Generator-Test-System
Impulse-Voltage-Generator-Test-SystemFang Sam
 
Himalayal-AC-Resonant-Test-System
Himalayal-AC-Resonant-Test-SystemHimalayal-AC-Resonant-Test-System
Himalayal-AC-Resonant-Test-SystemFang Sam
 
Himalayal-Alternative-Current-AC-Dielectric-Test-System
Himalayal-Alternative-Current-AC-Dielectric-Test-SystemHimalayal-Alternative-Current-AC-Dielectric-Test-System
Himalayal-Alternative-Current-AC-Dielectric-Test-SystemFang Sam
 
Research on typical discharge mode of power transformer (www.himalayal.com)
Research on typical discharge mode of power transformer (www.himalayal.com)Research on typical discharge mode of power transformer (www.himalayal.com)
Research on typical discharge mode of power transformer (www.himalayal.com)Fang Sam
 
How to conduct the lightning impulse withstand test on 550kv GIS?
How to conduct the lightning impulse withstand test on 550kv GIS?How to conduct the lightning impulse withstand test on 550kv GIS?
How to conduct the lightning impulse withstand test on 550kv GIS?Fang Sam
 

More from Fang Sam (6)

HSC Gas Insulated Standard Capacitor
HSC Gas Insulated Standard CapacitorHSC Gas Insulated Standard Capacitor
HSC Gas Insulated Standard Capacitor
 
Impulse-Voltage-Generator-Test-System
Impulse-Voltage-Generator-Test-SystemImpulse-Voltage-Generator-Test-System
Impulse-Voltage-Generator-Test-System
 
Himalayal-AC-Resonant-Test-System
Himalayal-AC-Resonant-Test-SystemHimalayal-AC-Resonant-Test-System
Himalayal-AC-Resonant-Test-System
 
Himalayal-Alternative-Current-AC-Dielectric-Test-System
Himalayal-Alternative-Current-AC-Dielectric-Test-SystemHimalayal-Alternative-Current-AC-Dielectric-Test-System
Himalayal-Alternative-Current-AC-Dielectric-Test-System
 
Research on typical discharge mode of power transformer (www.himalayal.com)
Research on typical discharge mode of power transformer (www.himalayal.com)Research on typical discharge mode of power transformer (www.himalayal.com)
Research on typical discharge mode of power transformer (www.himalayal.com)
 
How to conduct the lightning impulse withstand test on 550kv GIS?
How to conduct the lightning impulse withstand test on 550kv GIS?How to conduct the lightning impulse withstand test on 550kv GIS?
How to conduct the lightning impulse withstand test on 550kv GIS?
 

Recently uploaded

main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 

Recently uploaded (20)

main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 

How to conduct the test on the linearity of impulse voltage divider? (www.himalayal.com-impulse voltage generator)

  • 1. WWW.HIMALAYAL.COM.CN T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL info@himalayal.com Page:1 All right reserved. How to Conduct the Test on the Linearity of Impulse Voltage Divider Long Zhaozhi, Liu Shaobo, et al HIMALAYAL - SHANGHAI - CHINA Abstract: In the process of tracing the impulse voltage measuring system, low-voltage DC source or impulse voltage calibrator is utilized to measure the scale factor of voltage divider. Therefore, the effect of linearity of voltage divider on uncertainty of measuring system must be taken into account. Given that the national standard has not been established, an experimental method is put forward in the paper for measuring the linearity of voltage divider. The resistor divider R200S is made use of to obtain the linearity of impulse voltage generator; DC divider is adopted to measure the charge voltage of generator and the ratio of HCR600 indication value to charge voltage; then the linearity of amended generator is obtained. The results show that the linearity of HCR600 decreases from +0.4% to ﹣0.8%; the maximum difference between positive polarity and negative polarity is 0.14%; the linearity of negative polarity is superior to that of positive polarity. Moreover, the linearity of 500kV resistor divider with known linearity is used to be compared with that of HCR600. The results show that two curves match basically, and the maximum difference is 0.15% at the same voltage. That means that this method can be used to correctly measure the linearity of measuring divider. In addition, this method can also be applicable to verify the test during the establishment of national standards. If the generator equipment meets some requirements, the method can also be used to calibrate the UHV impulse equipment. Key words: linearity, impulse voltage generator, impulse voltage divider, efficiency deviation, comparison calibration; scale factor, charge voltage 1. Introduction With continuous development of UHV transmission technology and the improvement of transmission line voltage stage, voltage stage of impulse voltage generator and measuring device also improves a lot in order to meet the requirements of impulse voltage withstand test about transformer, current transformer and capacitor etc. The nationwide electric power research institutes establish measuring system of 3600kV impulse voltage test, UHVAV test base, UHVDC test base and high altitude base, even up to 7200kV impulse voltage measuring system. Correct high-voltage impulse test results have a direct influence on the safety and economy of electric equipment. The traceability of value is one of effective methods for ensuring correct and consistent value. In other words,
  • 2. WWW.HIMALAYAL.COM.CN T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL info@himalayal.com Page:2 All right reserved. measuring results are traceable to national or international standards by means of uninterrupted chains. Hence, companies at home and abroad pay more attention to value traceability and calibrate the equipment on a regular basis. America, Australia, German and Japan has improved impulse standard measuring system and established 500kV and below impulse voltage standard measuring system with 0.5% uncertainty. The physikalisch technische bundesanstalt (PTB) in German has established 1500kV impulse voltage standard device. At present, the calibration of impulse voltage measuring device is still at the theoretical analysis stage, and measuring standards and regulations have not yet been established. Given that voltage stage of impulse voltage test system reaches several MV, but voltage stage of standard measuring system is less than 1000kV, linearity test on the voltage divider must be conducted as a necessary item to ensure the precision of scale coefficient calibration. According to IEC 60060-2, GB/T 16927-2010 and DL/T992-2006 Detailed Implementation Guide for Impulse Voltage Measurement, 200kV resistor divider R200S is used to measure scale coefficient and linearity of under-damping voltage divider HCR 600 . 2. Method Analysis The IEC standards stipulate that measuring system must conduct the linearity test. The scale coefficient of conversion device (voltage divider) is measured under maximum value, minimum value and three equal value within the range of system voltage. The variation should not be more than ±1% of average value. The test can be conducted on conversion device or measuring system. The test waveform is lightning full wave and operation wave. However, in most cases, the standard system is the resistor divider. The lightning full wave dominates due to heating and the polarity is positive and negative polarity. 1) Standard method The standard measuring system is adopted to measure the scale coefficient and its linearity of voltage system. 2) Alternative methods No.1 Replace the standard measuring system by measuring system, which passes through linearity test via standard method. Because voltage stage of standard system is not enough, this method is not suitable. No.2 Adopt the sphere gap measurement to measure the input voltage of testing voltage divider, which is shown in Fig.1. The scale factor can be calculated through the ratio of measured input voltage to output voltage of voltage-divided system. The variation is observed under five amplitudes of regulated impulse test voltage. The device for measuring the sphere gap should conform to GB/T 311.6-2005. Moreover, the discharge spark is used as light and the test should be finished within a short time. By doing so, it is not necessary to adjust discharge voltage used to measure the sphere
  • 3. WWW.HIMALAYAL.COM.CN T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL info@himalayal.com Page:3 All right reserved. gap according to the environment and its deviation can be within ±1%. The difficulties by applying this method are as follows: ① The linearity of voltage-divided system via measurement contains the sphere gap’s linearity. Even though the deviation is greater than 1%, that cannot illustrate that the linearity of voltage-divided system does not meet the requirements of standards; ② Now, only a few universities and research institutes have sphere gaps with large-diameter; ③ When the diameter of sphere gap remains the same, the higher voltage stage is, the larger sphere gap distance becomes. When the distance increases to a certain degree, the electric field between sphere gaps changes from even electric field to uneven field, and the dispersibility of discharge voltage is great. Hence, this method does not work. G -- Impulse voltage generator S -- measuring sphere gap D -- testing voltage system M -- testing instrument Fig.1 Linearity test with sphere gap No.3 Adopt electric field strength tester to measure the linearity of voltage-divided system and calculate the ratio of output voltage of divided voltage system to corresponding electric field strength. Because stray parameter does not have impact on the electric field sensor, the electric field does not distort without corona, and the electric field is proportional to voltage; the electric field sensor uses optical fiber to measure the output signal and there is no interference. In 2009, Tsinghua University cooperated with China Electric Power Research Institute to measure the operation impulse voltage in a middle-phase tower window of real cup-shaped tower in the outdoor test base. The sensor has good time domain response for impulse voltage signal, and the electric field waveform is in consistent with voltage waveform without corona; if the corona occurs, the electric field distorts seriously, and there is great deviation between measuring value and calculation value. Existing problems are as follows: ① The precision of electric field tester is low, only 1% or so; so is the imported tester; ② The corona has a significant influence on the electric field tester; when the impulse voltage generator generates MV high voltage, the corona will happen. Hence, electric field tester is only used as auxiliary device. No.4 As for voltage-divided system with many stages, the linearity test can be conducted stage by stage. If each unit of voltage divider passes the linearity test, and the whole assembled voltage divider has no corona under the maximum voltage, it means that the voltage-divided system is linear. This method is suitable for delivery and acceptance test and regular calibration lab. However, in most tests, the time is limited and it is
  • 4. WWW.HIMALAYAL.COM.CN T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL info@himalayal.com Page:4 All right reserved. difficult to assemble the voltage divider. Moreover, the voltage-divided system cannot ensure that there is no corona under the maximum voltage. No.5 Utilize impulse voltage generator’s charge voltage to measure the linearity of testing voltage-divided system. During the test, charge condition should be kept stable. With five amplitudes of regulated impulse test voltage, the ratio of output voltage of voltage-divided system to corresponding charge voltage is calculated. If the ratio is within ±1% of average value, this system is regarded linear. This method was used to measure the linearity in Indian UHV lab. The Japanese expert Harada made use of 700kV voltage divider with known linearity and impulse voltage generator to obtain the linearity of standard voltage divider when he was developing the standard resistor divider. When Japan Science Institute and the University of Tokyo were setting the standard impulse measuring system, they used impulse generator to measure the linearity of voltage divider, kept charge voltage per stage the same, determined the linearity of impulse voltage generator by means of 300kV resistor divider with known linearity, and finally get the linearity of 1200kV voltage divider. Advantages of this method are as follows: ① There is no need to disassemble the equipment and the test time is short; ② At present, the technology of control system is mature. If the charge time is kept certain, amplitude repeatability of impulse voltage is less than 0.5% with same stage and charge voltage; ③ The linearity of system measured by this method often includes the linearity of the generator. But, if there exists the voltage-divided system with above two linearities, the linearity of the generator can be got. At this point, the linearity of voltage-divider system can be accurately measured. The fifth method is adopted in the paper to measure the linearity of 600kV under-damping voltage divider HCR 600. 200kV resistor divider R200S is used to rate the scale factor of HCR600; remove the R200S and keep charge time and generator body stage the same; raise the voltage and use the DC voltage divider to measure the charge voltage of impulse generator; the ratio of five voltage divider indication values to charge voltage is obtained. The variation of the ratio is the linearity of HCR600. 3. Performance Test of Resistor Divider R200S 3.1 DC voltage ratio The test circuit is shown in Fig.2. The KEITHLEY2410 DC source applies DC voltage on 220kV impulse resistor divider R200S. The Angilent 34401A six and a half digital multi-meter is adopted to measure the output voltage of DC source and R200S low-voltage arm. Then the ratio is calculated under stable condition. The DC voltage is raised from 50V to 500V. The statistical diagram of scale factor is shown in Fig.3. The value of each point is the average value of three measurements. Based on Fig.3, the dispersibility of R200S’s stable scale factor is small; its average is 108.985; there is no distinction of positive and negative polarity.
  • 5. WWW.HIMALAYAL.COM.CN T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL info@himalayal.com Page:5 All right reserved. Fig.2 Test circuit of measuring DC ratio Fig.3 DC scale ratio of the divider 3.2 Dynamic features According to Fig.4, the circuit is set up and step wave response waveform of R200S is measured. There is square wave source, and its output step wave amplitude is 100V. Test result is shown in Fig.5. In the Fig.5, waveform of R200S step wave response is represented by Ch1 while output waveform of square wave source is represented by Ch2. The partial response time is about 10ns; overshoot is 2.3%; stable time is 97ns. Its dynamic features meet the requirements of IEC 60060-2. Fig.4 Circuit of step wave response Fig.5 Waveform of step wave response 3.3 Impulse scale factor The impulse scale factor of R200S can be obtained by adopting the comparison method, which is shown in Fig.6. When the test is conducted, please ensure that the included angle between resistor divider and R200S is 90°. Both D1 cable end and Df cable end are connected to measuring system (oscilloscope and measuring software) via the attenuator. Before and after the test, some calibrator is utilized to calibrate the scale factor of attenuator in real-time. The scale factor of R200S positive and negative polarity is measured under 160kV. In the Fig.7, the triangle represents positive polarity and the square represents negative polarity. From the Fig.7, the dispersibility of R200S scale factor is small; the positive polarity is more than negative one; the average scale factor of positive polarity is 109.25 while that of negative polarity is 108.61. The deviation is 0.24% and 0.34%.
  • 6. WWW.HIMALAYAL.COM.CN T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL info@himalayal.com Page:6 All right reserved. G -- Impulse voltage generator C-- Load capacitor (Under-damping divider) D1 --R200S Df -- Standard resistor divider Fig.6 Diagram of calibrating scale factor of R200S Fig.7 Repeatable test results of scale factor 4. Test Proposal and Procedure 4.1 Measurement of impulse voltage generator’s linearity First of all, measure the linearity of impulse voltage generator; adjust the generator; use four-stage charge capacitor and 200kV DC voltage divider SGB-200 to monitor first-stage charge voltage (measuring precision is 0.1% and can trace back to national DC standards); then R200S is connected into the circuit; the linearity of R200S is 0.12%, which can be ignored. The equipment used in this test is shown in Fig.8. The test is conducted based on each stage charge voltage (15, 23, 33, 42, 53kV) shown in Fig.9. The output voltage of generator rises from 50kV to 176kV; the test is repeated 40 times at each voltage point; charge time is 60s; normal trigger per each time and the environment is consistent (the temperature is 20 ° and relative humidity is 60%). The ratio of R200S output voltage to charge voltage is calculated, and the deviation between this ratio and average value is also obtained (shown in Fig.9 vertical axis). Finally we get the variation trend of the linearity of voltage generator. Based on Fig.9, no special law for the linearity of generator is summarized; there is a great discrepancy between the trend of positive polarity and that of negative polarity. Because the structure of each generator or stray parameter of all elements is different, the linearity of each generator is unique.
  • 7. WWW.HIMALAYAL.COM.CN T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL info@himalayal.com Page:7 All right reserved. RD-- resistor divider IVG-- Impulse voltage generator Fig.8 Equipment used in the test Fig.9 Test results of the linearity on impulse generator 4.2 The scale factor of under-damping divider HCR600 under 20% rated voltage R200S is utilized to measure the scale factor of HCR600 under 160kV. The repetition test result is shown in Fig.10. The positive polarity is represented by triangle while negative polarity is denoted by square. According to Fig.10, average scale factor of positive polarity is 2026 while 2028 for negative polarity. The dispersibility of negative polarity is greater. Fig.10 Scale factor calibration of HCR600 with R200S 4.3 Measurement of HCR600 linearity From then on, the generator should have twelve stages and the environment should keep consistent (the temperature is 20 ℃ , relative humidity is 60%). The impulse voltage generator is connected with HCR600; SGB-200 is used to measure charge voltage of first-stage capacitance; charge voltage of each stage is raised based on 3.1 section (15, 23, 33, 42, 55kV); output voltage of the generator is roughly equal to five voltage points of HCR-600. Output voltage of HCR600 and monitoring voltage of SGB-200 are measured; the test is repeated 40 times at each voltage point under single polarity; charge time per time is 60s and the sphere gap should be triggered normally. Before and after the test, impulse voltage calibrator RIC422 is applied to calibrate scale factor of the attenuator in real-time and to amend the influence of secondary attenuating change on test results. The ratio of HCR’s output voltage to charge voltage is calculated. The deviation between the ratio and its average value is shown in Fig.11(a). The test results are amended according to Fig.9, which is shown in Fig.11 (b). From Fig.11 (b), the linearity of HCR-600 ranges from +0.4% to ﹣ 0.8% and is inversely proportional to the voltage; the difference between positive polarity and negative polarity under the same voltage is small; the biggest difference (0.14%) appears at 42kV point; but as a whole, the linearity of negative polarity is superior to that of positive polarity.
  • 8. WWW.HIMALAYAL.COM.CN T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL info@himalayal.com Page:8 All right reserved. Fig.11 Linearity test results of HCR-600 5. Experimental Test In order to verify whether the test result presented in section 4.3 is reasonable, standard voltage divider SMR7.7/500ref is compared with HCR600. Because the rated voltage of standard voltage divider is 500kV, only first four voltage points are selected. The test condition is the same as that described in section 4.3. The compared results are amended by SMR7.7/500ref, which is shown in Fig.12. The positive polarity is represented by triangle while square for negative polarity. Through comparing Fig.11 (b) and Fig. (12), as for first four points, the two curves decrease and the linearity of negative polarity is superior to that of positive polarity; the difference of positive polarity is close to that of negative polarity; the maximum difference appears at 42kV point; the maximum difference (0.15%) of both diagrams appears at 33kV under the same polarity. Results show that this method presented in section 3.3 is reasonable and can be used in the tracing study of impulse voltage. Only satisfying the following requirements does the method can be used in the calibration of impulse voltage measuring system. 1) The test must be conducted indoors. The indoor temperature and humidity can be adjusted to reduce the influence on the test result. 2) The used impulse voltage generator can produce standard lightning full wave without overshoot, and control the charge time. Moreover, the control software can monitor and compensate the charge voltage in real-time. 3) The generator can realize self-trigger discharge after sphere gap is well adjusted, avoiding self-discharge in advance. The precision of used DC voltage divider should be more than 0.5%. It can record the standard DC divider while discharging at the same time. 4) During the repetition test, measured output waveform amplitude, wave front time and wave tail time should not change greatly. If we
  • 9. WWW.HIMALAYAL.COM.CN T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL info@himalayal.com Page:9 All right reserved. conduct many tests, the resistance of the generator may heat up, resulting in the change of circuit parameters. Hence, heat dissipation should be done on a regular basis. 5) Because the capacitive voltage divider can be affected by its own position, please don’t move it during the test. The lab should be empty to reduce the stray capacitance that voltage divider brings to other objects. 6) Owning to good stability and repetition, resistor divider is recommended. 6. Conclusions 1) The scale factor of positive polarity impulse of resistor divider R200S is 109.25 while 108.61 for negative polarity. The deviation is within ± 0.34%. Its partial response time is 10ns or so; the overshoot is 2.3%; stable time is 97ns. Its features conform to the regulations on standard impulse divider of IEC60060-2. 2) The linearity of one impulse voltage generator is different from others. The linearity variation of impulse voltage generator used in the lab is as follows: the positive polarity is greatly different from negative polarity; the change does not follow any special law; as the voltage rises, the linearity presents non-monotonous change. The linearity of amended HCR600 is in the following: as the charge voltage increases, the linearity decreases monotonically between +0.4% and ﹣ 0.8%; the maximum difference (0.14%) appears at 42kV point; the linearity of negative polarity is superior to that of positive polarity. 3) The linearity variation of HCR600 can be obtained within 500kV by comparing standard voltage divider SMR7.7/500ref with HCR600. The deviation of two test results is close; the maximum difference at 33kV positive polarity is 0.15%; the variation trend is monotonic decreasing. Hence, the method can be used in the linearity measurement of impulse voltage standard system. When the test equipment meets the requirement, this method can be utilized in the calibration test of UHV impulse measuring equipment. REFERENCES [1] Yang Yingjian, Hu Yi, Wu Xiong. Construction of UHV AC test base of SGCC [J]. High Voltage Engineering, 2007, 33(11): 6-9. [2] Li Guangfan, Liao Weiming, Li Qingfeng. Voltage output performance of 7200kV/480kJ impulse voltage generator [J]. Proceeding of the CSEE, 2008, 28(25): 1-7. [3] He Huiwen, Gu Dingxie, Zhou Peihong, et al. Simulating calculation and analysis on time-to-crest of switching impulse for test on Chinese UHV AC pilot project[J]. High Voltage Engineering, 2011, 37(9): 2156-2162. [4] Wakimoto T, Ishii M. National standard class measuring system for impulse voltage in Japan [C]//15th International Symposium on High Voltage Engineering. Ljubljana, Slovenia: [s.n], 2007:1-5.
  • 10. WWW.HIMALAYAL.COM.CN T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL info@himalayal.com Page:10 All right reserved. [5] Hallstrom J, Aro M, Zhang Y, et al. Progress of a worldwide Comparison of LI measuring systems: round 1[C]//12th International Symposium on High Voltage Engineering. Bangalore, India: [s.n.], 2001:1-7. [6] Harada T, Wakimoto T, Sato S, et al. Development of national standard class reference divider for impulse voltage measurement [C]//11th International Symposium on High Voltage Engineering. London, England: [s.n.], 1999: 13-16. [7] Harada T, Wakamoto T, Saeki M, et al. Development and performance test of the reference divider for 300kV lightning impulse voltage measurement in Japan [C] //10th International Symposium on High Voltage Engineering. Montreal, Canada: [s.n.], 1997: 303-306. [8] Yu Cunyi, Xiong Yun, Yuan Meizhen. The international comparison of impulse voltage measurement [J]. High Voltage Engineering, 1992,18(3): 59-62. [9] Huang Dexiang, Ren Wenzhu, Zhou Huigao. The international comparison of impulse voltage measurement [J]. High Voltage Apparatus, 1992,28(3): 3-10. [10] Ren Wenzhu, Feng Jianhua, Ge Zhen. 800kV standard impulse voltage measuring system and the uncertainty of evaluation[J]. Acta Metrologica Sinica, 2008, 29(2): 153-157. [11] He Yi, Li Yanming, Zhang Xiaoyong. Experience of the international comparison of impulse voltage measuring systems [J]. High Voltage Engineering, 2001, 27(5): 153-157. [12] Yang Yingjian. Establishing of impulse voltage reference device [J]. High Voltage Engineering, 2006, 27(5) : 54-56. [13] Liu Zhen, Zhou Chunyu, Yu Fang. Characteristics of the long fronted switching impulse discharge [J]. High Voltage Engineering, 2009, 35(10): 2401-2406. [14] IEC 60060-1 High-voltage test techniques, Part 1: general definitions and test requirements [S], 2010. [15] Huo Feng, Wan Qifa, Hu Wei. Long wave-front impulse voltage test of UHV air-gaps with multistage method and result statistics [J]. High Voltage Engineering, 2011, 37(9): 2171-2177. [16] IEC 60060-2 High-voltage test techniques, part 2: measuring systems [S], 2010. [17] DL/T 992-2006 Detailed implementation guide for impulse voltage measurement [M]. Beijing, China: China Electric Power Press, 2006. [18] Li Qingquan, Liu Jian, Li Yanming. Spherical sensor for the measuring transient electric fields based on optical fiber [J]. Journal of Transducer Technology, 2002, 21(3): 8-12. [19] Fester K, Pfaff W. A potential free spherical sensor for the measurement of transient electric fields [J]. IEEE Transactions on Power Apparatus and Systems, 1984, 103 (10): 2904-2911. [20] Chen Weiyuan, Zeng Rong, Liang Xidong, et al. Design of an
  • 11. WWW.HIMALAYAL.COM.CN T: 86 21 61016212 Himalayal, always by your side. Copy right © HIMALAYAL info@himalayal.com Page:11 All right reserved. electro-optic integrated electric field sensor [J]. Journal of Tsinghua University; Science and Technology, 2006, 46(10): 1641-1644. [21] Niu Ben, Zeng Rong, Geng Yinan. Electric field measurement of switching impulse discharge in UHV Tower [J]. High Voltage Engineering, 2009, 35(4): 731-736. [22] Zhang Renyu, Chen Changyu, Wang Changchang. High-voltage testing technology [M]. Beijing, China: Tsinghua University Press, 2003. [23] Cao Jing, Wan Qifa, Zhang Qin. Analysis on phase-to-phase switching impulse discharge characteristic of high altitude converter station [J]. High Voltage Engineering, 2010, 36(12): 2896-2901. [24] Zhang Yixiu, Sun Wei, Fu Zhengcai. Simulation and experimental investigation of the charging ununiformity of impulse voltage generators [J]. Electrical Engineering, 2009 (2): 34-37.