Smoke and environmental ventilation of multi-storey buildings using
shafts webinar Q&A
Here is a copy of the questions and answers from our recent
webinar on smoke and environmental ventilation of multi-storey
buildings using shafts, slightly edited for clarity.
Where planning conditions on projects in London apply,
where plant is to be mounted on the roof, is it
possible for smoke fans to be fitted within the
shaft?
Yes this is possible. There needs to be sufficient space between
the top of the shaft and the ceiling of the highest floor that you are
ventilating. If you are ventilating the top floor with a shaft, that limits the available distance for fans. These are
normally run and standby in series, so the required depth can be fairly great
To deal with this the top storey can be ventilated separately with a natural ventilator on the roof of the lobby or
corridor.
You won’t be able to provide day to day ventilation via the fans, because they will be too noisy as you won’t have
room to fit the necessary attenuation. You can only do this if you have a smoke-only system.
Is there a maximum distance from the shaft to the end of the communal corridor (i.e. dead end
distance), which if you exceeded you could not get the CFD to pass?
If you have an ADB compliant corridor, then you are allowed a 7.5m dead end anywhere. You can then put the
shaft anywhere you like.
If you have an extended corridor, then we would recommend that you place the shafts as close as possible to the
ends of the corridor.
The general guidance is that this distance should not exceed 7.5m of the end of the corridor, because there will
be area beyond the end of the shaft which will stay smokier for longer. The assumption is that if you have an ADB
compliant corridor, then you only have a 7.5m corridor which may well be smoky anyway, so that you won’t be
any worse in that 7.5m than you would be if it was a compliant corridor. While 7.5m is an absolute maximum, I
recommend that you make this distance as small as possible, as this will give you the best system.
Is the 3m2
shaft a geometric or aerodynamic free area?
It is the geometric area, the physical size of the shaft. The 1.5m2
shaft is also the geometric area, but the 1m2
or
1.5m2
for the ventilators or grilles etc. can be taken either as a geometric or aerodynamic free area, whichever is
the most advantageous.
What material should a shaft be constructed of?
© 2014 Colt International Licensing Ltd.
It needs to be fire rated, in just the same way as any riser passing through the building would, to protect against
the vertical spread of fire. It can be cast concrete, builders work / blockwork, plastered or fire board – so long as it
has the correct size, it is reasonably smooth, it provides the required fire resistance and it is reasonably smoke-
sealed.
Particularly where a mechanical system is installed into a relatively tall building, if the shaft is too leaky, you will
find that at the bottom of the shaft the extract rate falls off because of the leakage from the shaft.
What are the requirements for the maintenance of variable speed fans to check that they operate
within the required parameters?
This should comprise an annual test and check. This would involve running the fans, to check that they can run at
full speed with the doors open and that with the doors closed there is a pressure differential which is in the order
of around 15-30 Pa. It is a simple check.
What are the design requirements to ensure a high degree of reliability with inverters?
The run and standby fans should each have their own inverter. Normally a fire-fighter’s switch would be provided
as a bypass so that the fire-fighters can actually bypass the inverter to a direct contact to provide full speed. They
would do this once they have opened the door into the lobby or corridor, so that there is no issue with pressure
differentials because the door is open.
To what extent can the relative humidity be allowed to increase with the cooling of a corridor with
an evaporative cooling system?
There will be an increase of humidity but generally this won’t induce discomfort or mould etc. The actual allowable
value will depend on the location and the design of the system and this is always subject to a design on a project
by project basis.
What is the maximum temperature that the extract fans can tolerate? Is it possible not to supply
sprinklers for cooling purposes?
Such fans are normally rated at 300C and certainly sprinklers would not be required to protect the fans. The
reason for this is that we are not taking smoke directly from the plume; we taking smoke which has come from the
fire and which has been through a door and done a lot of mixing.
We have never had a situation where the CFD has shown that the temperature within the smoke extract shaft will
be 300C or higher. We normally get conditions around 50-200C. A 300C fan is perfectly acceptable and readily
available: anyway, this is the normal rating for fans used for smoke control in the UK.
Please explain the power supply requirements for mechanical extract systems
BS 8519 requires both a maintained primary and secondary supply with an automatic transfer switch between the
two that provides the maximum possible security for the supply to the units.
The type of secondary system depends on the application: for instance it can be a generator system or a second
mains supply system.
© 2014 Colt International Licensing Ltd.
What is the maximum allowable velocity in a ColtShaft?
We design on the pressure drop down the shaft, not the velocity, in such a way that we limit that pressure drop:
we should achieve a reasonable balance between the flow rate when we open the top damper and the flow rate
when we open the bottom damper. Because of this factor, the taller the shaft is, the lower the velocity we want.
What kind of air change rates is used to select a fan for summer overheating?
We do not design on an air change rate. We look at the heat generated by the pipes in the corridor and then
design to maintain a reasonable pressure differential.
What is the maximum allowance velocity for dampers in a ColtShaft system?
This depends on the product and system used. We tend size a conventional damper on 5 m/s for use with a
mechanical system such as ColtShaft.
What the maximum length of corridor we have designed for use with a mechanical extract
system?
We have designed systems up to 27m, though many are around 15-25m. Guidance suggests that 30m is the
maximum that would be accepted by Building Control. This is because where you have a corridor divided by fire
doors, then the maximum distance allowed between these is 30m, so this fairly well accepted. Technically I think
we could get a larger distance to work but it would not be approved.
What is the allowable maximum velocity in a pressurisation shaft?
This comes down to achieving a balance between the power that is needed in the fan and keeping the duct size
to a reasonable minimum. Typically 10 m/s might be the design velocity, but this will be influenced by the overall
design and priorities.
If smoke ventilation used for day to day ventilation, is inlet an issue as regards air quality?
Generally not, as air inlet and extract are normally at roof level, where the air quality is likely to be high. However
if a system has low level inlet, then this can indeed be a problem. If there are any dirty discharges from the rest of
the building then these do need to be kept a reasonable distance away from the inlets for the day to day
ventilation for the stairs or corridor.
What allowance should be made for leakage when determining the pressure regulation control for
leakage in the corridor itself and the control of the variable speed fan?
In this instance we are not making an allowance at all, because system just runs at whatever speed is necessary.
So if the corridor is very leaky, you may find that the fan may run at 40-50% of full speed; if the corridor is well
sealed, the fan may run at 5-10% of full speed. This happens automatically so there is no allowance in terms of
the design.
How do you make sure that opening and closing of doors do actually close so as to maintain the
negative pressure in the lobby?
© 2014 Colt International Licensing Ltd.
Door closers do the work of closing the door, but unfortunately they are variable in terms of the amount of power
they provide, depending on how they are set up, how big the door is and so on.
Although we design for a notional -25 Pa in the lobby, we adjust the lobby pressure at commissioning to allow us
to ensure that the doors will close under that negative pressure.
On occasions, where there are very large doors, we have had to get these adjusted to get the right balance
between the two. But the relative pressure is not a very critical value: if it goes too high, problems with door
opening and closing can occur, but it can go down to a low value without issues occurring.
If combining smoke and environmental control, do you need to supply independent fans in any
situation, i.e. one dedicated to smoke and the other to environmental control?
Yes, you can do this, but you do not have to. In general you can use a smoke control fan with an inverter to
reduce the volume flow rate and attenuators to keep the noise down and to reduce the power, or a separate
dedicated environmental fan. Which you use comes down to the geometry of the building, in particular what space
you have available.
What are the requirements for the periodic inspection and maintenance of AOVs?
Generally they should be maintained once a year. They should also have a weekly test to ensure that they are still
working, since they are life safety systems, normally along with the fire alarm test.
© 2014 Colt International Licensing Ltd.

More Related Content

What's hot

Solar Water Heating System Installation
Solar Water Heating System InstallationSolar Water Heating System Installation
Solar Water Heating System Installationdrcmarx
 
building services
building servicesbuilding services
building servicesszelun
 
CPD Presentation: Car Park Ventilation
CPD Presentation: Car Park VentilationCPD Presentation: Car Park Ventilation
CPD Presentation: Car Park VentilationColt UK
 
Fighting Fires in Sprinklered Buildings
Fighting Fires in Sprinklered BuildingsFighting Fires in Sprinklered Buildings
Fighting Fires in Sprinklered BuildingsAaron Johnson
 
Basics of building fire protection design
Basics of building fire protection designBasics of building fire protection design
Basics of building fire protection designMostafa Al Wakeel
 
Design and demonstration of heat pipe based waste heat recovery system
Design and demonstration of heat pipe based waste heat recovery systemDesign and demonstration of heat pipe based waste heat recovery system
Design and demonstration of heat pipe based waste heat recovery systemIRJET Journal
 
Energy efficientventilationsystembs
Energy efficientventilationsystembsEnergy efficientventilationsystembs
Energy efficientventilationsystembslohwenjun
 
Ventilation system of building
Ventilation system of buildingVentilation system of building
Ventilation system of buildingSulieman KOHISTANI
 
Building Services 1 Report
Building Services 1 ReportBuilding Services 1 Report
Building Services 1 ReportMelvin Lim
 
Fire Fighting "A Complete Handbook"
Fire Fighting "A Complete Handbook"Fire Fighting "A Complete Handbook"
Fire Fighting "A Complete Handbook"EzazulHaqueSiddique
 
Underground car parking ventilation system
Underground car parking ventilation systemUnderground car parking ventilation system
Underground car parking ventilation systemMohamed Hashish
 
Introduction To Mechanical Smoke Control CPD Presentation
Introduction To Mechanical Smoke Control CPD PresentationIntroduction To Mechanical Smoke Control CPD Presentation
Introduction To Mechanical Smoke Control CPD PresentationAxair Fan (UK) Ltd.
 

What's hot (20)

Chapter 05
Chapter 05Chapter 05
Chapter 05
 
Solar Water Heating System Installation
Solar Water Heating System InstallationSolar Water Heating System Installation
Solar Water Heating System Installation
 
building services
building servicesbuilding services
building services
 
Radiator Valve_
Radiator Valve_Radiator Valve_
Radiator Valve_
 
CPD Presentation: Car Park Ventilation
CPD Presentation: Car Park VentilationCPD Presentation: Car Park Ventilation
CPD Presentation: Car Park Ventilation
 
Final Portfolio
Final PortfolioFinal Portfolio
Final Portfolio
 
Fighting Fires in Sprinklered Buildings
Fighting Fires in Sprinklered BuildingsFighting Fires in Sprinklered Buildings
Fighting Fires in Sprinklered Buildings
 
Fire fighting -1 By Er. Ezaz
Fire fighting -1 By Er. EzazFire fighting -1 By Er. Ezaz
Fire fighting -1 By Er. Ezaz
 
Basics of building fire protection design
Basics of building fire protection designBasics of building fire protection design
Basics of building fire protection design
 
Fire smokedampers
Fire smokedampersFire smokedampers
Fire smokedampers
 
Design and demonstration of heat pipe based waste heat recovery system
Design and demonstration of heat pipe based waste heat recovery systemDesign and demonstration of heat pipe based waste heat recovery system
Design and demonstration of heat pipe based waste heat recovery system
 
Air Duct Leakage
Air Duct LeakageAir Duct Leakage
Air Duct Leakage
 
Energy efficientventilationsystembs
Energy efficientventilationsystembsEnergy efficientventilationsystembs
Energy efficientventilationsystembs
 
Ventilation system of building
Ventilation system of buildingVentilation system of building
Ventilation system of building
 
Ventilation
VentilationVentilation
Ventilation
 
Building Services 1 Report
Building Services 1 ReportBuilding Services 1 Report
Building Services 1 Report
 
Ventilation Systems
Ventilation SystemsVentilation Systems
Ventilation Systems
 
Fire Fighting "A Complete Handbook"
Fire Fighting "A Complete Handbook"Fire Fighting "A Complete Handbook"
Fire Fighting "A Complete Handbook"
 
Underground car parking ventilation system
Underground car parking ventilation systemUnderground car parking ventilation system
Underground car parking ventilation system
 
Introduction To Mechanical Smoke Control CPD Presentation
Introduction To Mechanical Smoke Control CPD PresentationIntroduction To Mechanical Smoke Control CPD Presentation
Introduction To Mechanical Smoke Control CPD Presentation
 

Similar to Smoke and environmental ventilation of multi-storey buildings using shafts webinar Q&A

Questions and answers from Paul Compton's pressurisation webinar
Questions and answers from Paul Compton's pressurisation webinar Questions and answers from Paul Compton's pressurisation webinar
Questions and answers from Paul Compton's pressurisation webinar Colt UK
 
S3 Supply Air Duct System Assignment
S3 Supply Air Duct System AssignmentS3 Supply Air Duct System Assignment
S3 Supply Air Duct System Assignmentno suhaila
 
How To Install A Flexible Air Duct-mmihomeimprovement.com
How To Install A Flexible Air Duct-mmihomeimprovement.comHow To Install A Flexible Air Duct-mmihomeimprovement.com
How To Install A Flexible Air Duct-mmihomeimprovement.comangelinarobert1
 
LECTURE 6 ZONING IN HVAC.ppt
LECTURE  6 ZONING IN HVAC.pptLECTURE  6 ZONING IN HVAC.ppt
LECTURE 6 ZONING IN HVAC.pptBhaskarBhatia2
 
kitchen.services-Your ultimate guide on Range Hood backdraft damper.pdf
kitchen.services-Your ultimate guide on Range Hood backdraft damper.pdfkitchen.services-Your ultimate guide on Range Hood backdraft damper.pdf
kitchen.services-Your ultimate guide on Range Hood backdraft damper.pdfAhmad Affan
 
Sizing vent n exhaust fans
Sizing vent n exhaust fansSizing vent n exhaust fans
Sizing vent n exhaust fansKim Pham
 
A Guide To Fume Extraction Systems & Components
A Guide To Fume Extraction Systems & ComponentsA Guide To Fume Extraction Systems & Components
A Guide To Fume Extraction Systems & ComponentsAxair Fan (UK) Ltd.
 
Gas Flare Stack Process
Gas Flare Stack ProcessGas Flare Stack Process
Gas Flare Stack ProcessShad Ibrahim
 
Management of Poultry House Ventilation by Dr.Muhammad Ashiq Toor
Management of Poultry House Ventilation  by Dr.Muhammad Ashiq ToorManagement of Poultry House Ventilation  by Dr.Muhammad Ashiq Toor
Management of Poultry House Ventilation by Dr.Muhammad Ashiq ToorAshiq Toor
 
S3 Duct System Design Consideration
S3 Duct System Design ConsiderationS3 Duct System Design Consideration
S3 Duct System Design Considerationno suhaila
 
Duct sizing methods and filter types
Duct sizing methods and filter typesDuct sizing methods and filter types
Duct sizing methods and filter typesSANKA_SILVA
 
Heating Air Curtain Installation Method
Heating Air Curtain Installation MethodHeating Air Curtain Installation Method
Heating Air Curtain Installation MethodNanyoo Vents
 

Similar to Smoke and environmental ventilation of multi-storey buildings using shafts webinar Q&A (20)

Questions and answers from Paul Compton's pressurisation webinar
Questions and answers from Paul Compton's pressurisation webinar Questions and answers from Paul Compton's pressurisation webinar
Questions and answers from Paul Compton's pressurisation webinar
 
S3 Supply Air Duct System Assignment
S3 Supply Air Duct System AssignmentS3 Supply Air Duct System Assignment
S3 Supply Air Duct System Assignment
 
How To Install A Flexible Air Duct-mmihomeimprovement.com
How To Install A Flexible Air Duct-mmihomeimprovement.comHow To Install A Flexible Air Duct-mmihomeimprovement.com
How To Install A Flexible Air Duct-mmihomeimprovement.com
 
LECTURE 6 ZONING IN HVAC.ppt
LECTURE  6 ZONING IN HVAC.pptLECTURE  6 ZONING IN HVAC.ppt
LECTURE 6 ZONING IN HVAC.ppt
 
kitchen.services-Your ultimate guide on Range Hood backdraft damper.pdf
kitchen.services-Your ultimate guide on Range Hood backdraft damper.pdfkitchen.services-Your ultimate guide on Range Hood backdraft damper.pdf
kitchen.services-Your ultimate guide on Range Hood backdraft damper.pdf
 
Designing an HVAC System
Designing an HVAC SystemDesigning an HVAC System
Designing an HVAC System
 
Sizing vent n exhaust fans
Sizing vent n exhaust fansSizing vent n exhaust fans
Sizing vent n exhaust fans
 
A Guide To Fume Extraction Systems & Components
A Guide To Fume Extraction Systems & ComponentsA Guide To Fume Extraction Systems & Components
A Guide To Fume Extraction Systems & Components
 
All Energy Exhibition & Conference, Glasgow, May 2017
All Energy Exhibition & Conference, Glasgow, May 2017All Energy Exhibition & Conference, Glasgow, May 2017
All Energy Exhibition & Conference, Glasgow, May 2017
 
Garazi
GaraziGarazi
Garazi
 
Air distribution Product
Air distribution ProductAir distribution Product
Air distribution Product
 
analysis-of-uniformity-and-energy-consumption.pdf
analysis-of-uniformity-and-energy-consumption.pdfanalysis-of-uniformity-and-energy-consumption.pdf
analysis-of-uniformity-and-energy-consumption.pdf
 
Gas Flare Stack Process
Gas Flare Stack ProcessGas Flare Stack Process
Gas Flare Stack Process
 
Management of Poultry House Ventilation by Dr.Muhammad Ashiq Toor
Management of Poultry House Ventilation  by Dr.Muhammad Ashiq ToorManagement of Poultry House Ventilation  by Dr.Muhammad Ashiq Toor
Management of Poultry House Ventilation by Dr.Muhammad Ashiq Toor
 
3071irr.pdf
3071irr.pdf3071irr.pdf
3071irr.pdf
 
urr.pdf
urr.pdfurr.pdf
urr.pdf
 
S3 Duct System Design Consideration
S3 Duct System Design ConsiderationS3 Duct System Design Consideration
S3 Duct System Design Consideration
 
Steam Blow
Steam BlowSteam Blow
Steam Blow
 
Duct sizing methods and filter types
Duct sizing methods and filter typesDuct sizing methods and filter types
Duct sizing methods and filter types
 
Heating Air Curtain Installation Method
Heating Air Curtain Installation MethodHeating Air Curtain Installation Method
Heating Air Curtain Installation Method
 

More from Colt UK

Seven good practices for pressurisation systems
Seven good practices for pressurisation systemsSeven good practices for pressurisation systems
Seven good practices for pressurisation systemsColt UK
 
Can car park ventilation schemes be more energy efficient? Yes – and they sho...
Can car park ventilation schemes be more energy efficient? Yes – and they sho...Can car park ventilation schemes be more energy efficient? Yes – and they sho...
Can car park ventilation schemes be more energy efficient? Yes – and they sho...Colt UK
 
Q&A from Dr John H Klotes webinar on design fires for smoke control
Q&A from Dr John H Klotes webinar on design fires for smoke controlQ&A from Dr John H Klotes webinar on design fires for smoke control
Q&A from Dr John H Klotes webinar on design fires for smoke controlColt UK
 
CPD Presentation Evaporative cooling in data centres
CPD Presentation   Evaporative cooling in data centresCPD Presentation   Evaporative cooling in data centres
CPD Presentation Evaporative cooling in data centresColt UK
 
The top three considerations when specifying glass louvred ventilators
The top three considerations when specifying glass louvred ventilatorsThe top three considerations when specifying glass louvred ventilators
The top three considerations when specifying glass louvred ventilatorsColt UK
 
CPD Presentation - Smoke control and environmental ventilation in residential...
CPD Presentation - Smoke control and environmental ventilation in residential...CPD Presentation - Smoke control and environmental ventilation in residential...
CPD Presentation - Smoke control and environmental ventilation in residential...Colt UK
 
CPD Presentation: Smoke curtains and fire curtains
CPD Presentation: Smoke curtains and fire curtainsCPD Presentation: Smoke curtains and fire curtains
CPD Presentation: Smoke curtains and fire curtainsColt UK
 
CPD Presentation: Key considerations when specifying weather louvres
CPD Presentation: Key considerations when specifying weather louvresCPD Presentation: Key considerations when specifying weather louvres
CPD Presentation: Key considerations when specifying weather louvresColt UK
 
People feel better in colt conditions
People feel better in colt conditions People feel better in colt conditions
People feel better in colt conditions Colt UK
 
CPD Presentation: Pressurisation
CPD Presentation: PressurisationCPD Presentation: Pressurisation
CPD Presentation: PressurisationColt UK
 
CPD Presentation: Smoke Ventilation using Shafts
CPD Presentation: Smoke Ventilation using ShaftsCPD Presentation: Smoke Ventilation using Shafts
CPD Presentation: Smoke Ventilation using ShaftsColt UK
 
CPD Presentation: General Principles of Smoke Control
CPD Presentation: General Principles of Smoke ControlCPD Presentation: General Principles of Smoke Control
CPD Presentation: General Principles of Smoke ControlColt UK
 
You want to improve your factory’s productivity: what’s next?
You want to improve your factory’s productivity: what’s next?You want to improve your factory’s productivity: what’s next?
You want to improve your factory’s productivity: what’s next?Colt UK
 
Can your factory be more productive?
Can your factory be more productive?Can your factory be more productive?
Can your factory be more productive?Colt UK
 
Are you sure your natural ventilation system is really energy efficient?
Are you sure your natural ventilation system is really energy efficient?Are you sure your natural ventilation system is really energy efficient?
Are you sure your natural ventilation system is really energy efficient?Colt UK
 
When is a U value real?
When is a U value real?When is a U value real?
When is a U value real?Colt UK
 
The Lakanal House inquest and Local Authority tower blocks
The Lakanal House inquest and Local Authority tower blocksThe Lakanal House inquest and Local Authority tower blocks
The Lakanal House inquest and Local Authority tower blocksColt UK
 
Not all “Class A” weather louvres are equal
Not all “Class A” weather louvres are equalNot all “Class A” weather louvres are equal
Not all “Class A” weather louvres are equalColt UK
 
Green micro-algae façade becomes reality in Hamburg
Green micro-algae façade becomes reality in HamburgGreen micro-algae façade becomes reality in Hamburg
Green micro-algae façade becomes reality in HamburgColt UK
 
The CPR and mandatory CE marking: what is changing and what will it mean for you
The CPR and mandatory CE marking: what is changing and what will it mean for youThe CPR and mandatory CE marking: what is changing and what will it mean for you
The CPR and mandatory CE marking: what is changing and what will it mean for youColt UK
 

More from Colt UK (20)

Seven good practices for pressurisation systems
Seven good practices for pressurisation systemsSeven good practices for pressurisation systems
Seven good practices for pressurisation systems
 
Can car park ventilation schemes be more energy efficient? Yes – and they sho...
Can car park ventilation schemes be more energy efficient? Yes – and they sho...Can car park ventilation schemes be more energy efficient? Yes – and they sho...
Can car park ventilation schemes be more energy efficient? Yes – and they sho...
 
Q&A from Dr John H Klotes webinar on design fires for smoke control
Q&A from Dr John H Klotes webinar on design fires for smoke controlQ&A from Dr John H Klotes webinar on design fires for smoke control
Q&A from Dr John H Klotes webinar on design fires for smoke control
 
CPD Presentation Evaporative cooling in data centres
CPD Presentation   Evaporative cooling in data centresCPD Presentation   Evaporative cooling in data centres
CPD Presentation Evaporative cooling in data centres
 
The top three considerations when specifying glass louvred ventilators
The top three considerations when specifying glass louvred ventilatorsThe top three considerations when specifying glass louvred ventilators
The top three considerations when specifying glass louvred ventilators
 
CPD Presentation - Smoke control and environmental ventilation in residential...
CPD Presentation - Smoke control and environmental ventilation in residential...CPD Presentation - Smoke control and environmental ventilation in residential...
CPD Presentation - Smoke control and environmental ventilation in residential...
 
CPD Presentation: Smoke curtains and fire curtains
CPD Presentation: Smoke curtains and fire curtainsCPD Presentation: Smoke curtains and fire curtains
CPD Presentation: Smoke curtains and fire curtains
 
CPD Presentation: Key considerations when specifying weather louvres
CPD Presentation: Key considerations when specifying weather louvresCPD Presentation: Key considerations when specifying weather louvres
CPD Presentation: Key considerations when specifying weather louvres
 
People feel better in colt conditions
People feel better in colt conditions People feel better in colt conditions
People feel better in colt conditions
 
CPD Presentation: Pressurisation
CPD Presentation: PressurisationCPD Presentation: Pressurisation
CPD Presentation: Pressurisation
 
CPD Presentation: Smoke Ventilation using Shafts
CPD Presentation: Smoke Ventilation using ShaftsCPD Presentation: Smoke Ventilation using Shafts
CPD Presentation: Smoke Ventilation using Shafts
 
CPD Presentation: General Principles of Smoke Control
CPD Presentation: General Principles of Smoke ControlCPD Presentation: General Principles of Smoke Control
CPD Presentation: General Principles of Smoke Control
 
You want to improve your factory’s productivity: what’s next?
You want to improve your factory’s productivity: what’s next?You want to improve your factory’s productivity: what’s next?
You want to improve your factory’s productivity: what’s next?
 
Can your factory be more productive?
Can your factory be more productive?Can your factory be more productive?
Can your factory be more productive?
 
Are you sure your natural ventilation system is really energy efficient?
Are you sure your natural ventilation system is really energy efficient?Are you sure your natural ventilation system is really energy efficient?
Are you sure your natural ventilation system is really energy efficient?
 
When is a U value real?
When is a U value real?When is a U value real?
When is a U value real?
 
The Lakanal House inquest and Local Authority tower blocks
The Lakanal House inquest and Local Authority tower blocksThe Lakanal House inquest and Local Authority tower blocks
The Lakanal House inquest and Local Authority tower blocks
 
Not all “Class A” weather louvres are equal
Not all “Class A” weather louvres are equalNot all “Class A” weather louvres are equal
Not all “Class A” weather louvres are equal
 
Green micro-algae façade becomes reality in Hamburg
Green micro-algae façade becomes reality in HamburgGreen micro-algae façade becomes reality in Hamburg
Green micro-algae façade becomes reality in Hamburg
 
The CPR and mandatory CE marking: what is changing and what will it mean for you
The CPR and mandatory CE marking: what is changing and what will it mean for youThe CPR and mandatory CE marking: what is changing and what will it mean for you
The CPR and mandatory CE marking: what is changing and what will it mean for you
 

Recently uploaded

NATA 2024 SYLLABUS, full syllabus explained in detail
NATA 2024 SYLLABUS, full syllabus explained in detailNATA 2024 SYLLABUS, full syllabus explained in detail
NATA 2024 SYLLABUS, full syllabus explained in detailDesigntroIntroducing
 
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一F dds
 
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130Suhani Kapoor
 
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一Fi L
 
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
PORTAFOLIO   2024_  ANASTASIYA  KUDINOVAPORTAFOLIO   2024_  ANASTASIYA  KUDINOVA
PORTAFOLIO 2024_ ANASTASIYA KUDINOVAAnastasiya Kudinova
 
VIP Call Girls Service Bhagyanagar Hyderabad Call +91-8250192130
VIP Call Girls Service Bhagyanagar Hyderabad Call +91-8250192130VIP Call Girls Service Bhagyanagar Hyderabad Call +91-8250192130
VIP Call Girls Service Bhagyanagar Hyderabad Call +91-8250192130Suhani Kapoor
 
Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`
Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`
Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`dajasot375
 
办理学位证(NTU证书)新加坡南洋理工大学毕业证成绩单原版一比一
办理学位证(NTU证书)新加坡南洋理工大学毕业证成绩单原版一比一办理学位证(NTU证书)新加坡南洋理工大学毕业证成绩单原版一比一
办理学位证(NTU证书)新加坡南洋理工大学毕业证成绩单原版一比一A SSS
 
Kindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUpKindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUpmainac1
 
Passbook project document_april_21__.pdf
Passbook project document_april_21__.pdfPassbook project document_april_21__.pdf
Passbook project document_april_21__.pdfvaibhavkanaujia
 
Call Girls Satellite 7397865700 Ridhima Hire Me Full Night
Call Girls Satellite 7397865700 Ridhima Hire Me Full NightCall Girls Satellite 7397865700 Ridhima Hire Me Full Night
Call Girls Satellite 7397865700 Ridhima Hire Me Full Nightssuser7cb4ff
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Rndexperts
 
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts ServiceCall Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Servicejennyeacort
 
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一diploma 1
 
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCRdollysharma2066
 
Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...
Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...
Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...narwatsonia7
 
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一F La
 
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一z xss
 

Recently uploaded (20)

NATA 2024 SYLLABUS, full syllabus explained in detail
NATA 2024 SYLLABUS, full syllabus explained in detailNATA 2024 SYLLABUS, full syllabus explained in detail
NATA 2024 SYLLABUS, full syllabus explained in detail
 
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
 
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130
 
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
 
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk GurgaonCheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
 
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
PORTAFOLIO   2024_  ANASTASIYA  KUDINOVAPORTAFOLIO   2024_  ANASTASIYA  KUDINOVA
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
 
VIP Call Girls Service Bhagyanagar Hyderabad Call +91-8250192130
VIP Call Girls Service Bhagyanagar Hyderabad Call +91-8250192130VIP Call Girls Service Bhagyanagar Hyderabad Call +91-8250192130
VIP Call Girls Service Bhagyanagar Hyderabad Call +91-8250192130
 
Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`
Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`
Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`
 
办理学位证(NTU证书)新加坡南洋理工大学毕业证成绩单原版一比一
办理学位证(NTU证书)新加坡南洋理工大学毕业证成绩单原版一比一办理学位证(NTU证书)新加坡南洋理工大学毕业证成绩单原版一比一
办理学位证(NTU证书)新加坡南洋理工大学毕业证成绩单原版一比一
 
Kindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUpKindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUp
 
Passbook project document_april_21__.pdf
Passbook project document_april_21__.pdfPassbook project document_april_21__.pdf
Passbook project document_april_21__.pdf
 
Call Girls Satellite 7397865700 Ridhima Hire Me Full Night
Call Girls Satellite 7397865700 Ridhima Hire Me Full NightCall Girls Satellite 7397865700 Ridhima Hire Me Full Night
Call Girls Satellite 7397865700 Ridhima Hire Me Full Night
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025
 
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts ServiceCall Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
 
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
 
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
 
Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...
Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...
Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...
 
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
 
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一
 

Smoke and environmental ventilation of multi-storey buildings using shafts webinar Q&A

  • 1. Smoke and environmental ventilation of multi-storey buildings using shafts webinar Q&A Here is a copy of the questions and answers from our recent webinar on smoke and environmental ventilation of multi-storey buildings using shafts, slightly edited for clarity. Where planning conditions on projects in London apply, where plant is to be mounted on the roof, is it possible for smoke fans to be fitted within the shaft? Yes this is possible. There needs to be sufficient space between the top of the shaft and the ceiling of the highest floor that you are ventilating. If you are ventilating the top floor with a shaft, that limits the available distance for fans. These are normally run and standby in series, so the required depth can be fairly great To deal with this the top storey can be ventilated separately with a natural ventilator on the roof of the lobby or corridor. You won’t be able to provide day to day ventilation via the fans, because they will be too noisy as you won’t have room to fit the necessary attenuation. You can only do this if you have a smoke-only system. Is there a maximum distance from the shaft to the end of the communal corridor (i.e. dead end distance), which if you exceeded you could not get the CFD to pass? If you have an ADB compliant corridor, then you are allowed a 7.5m dead end anywhere. You can then put the shaft anywhere you like. If you have an extended corridor, then we would recommend that you place the shafts as close as possible to the ends of the corridor. The general guidance is that this distance should not exceed 7.5m of the end of the corridor, because there will be area beyond the end of the shaft which will stay smokier for longer. The assumption is that if you have an ADB compliant corridor, then you only have a 7.5m corridor which may well be smoky anyway, so that you won’t be any worse in that 7.5m than you would be if it was a compliant corridor. While 7.5m is an absolute maximum, I recommend that you make this distance as small as possible, as this will give you the best system. Is the 3m2 shaft a geometric or aerodynamic free area? It is the geometric area, the physical size of the shaft. The 1.5m2 shaft is also the geometric area, but the 1m2 or 1.5m2 for the ventilators or grilles etc. can be taken either as a geometric or aerodynamic free area, whichever is the most advantageous. What material should a shaft be constructed of? © 2014 Colt International Licensing Ltd.
  • 2. It needs to be fire rated, in just the same way as any riser passing through the building would, to protect against the vertical spread of fire. It can be cast concrete, builders work / blockwork, plastered or fire board – so long as it has the correct size, it is reasonably smooth, it provides the required fire resistance and it is reasonably smoke- sealed. Particularly where a mechanical system is installed into a relatively tall building, if the shaft is too leaky, you will find that at the bottom of the shaft the extract rate falls off because of the leakage from the shaft. What are the requirements for the maintenance of variable speed fans to check that they operate within the required parameters? This should comprise an annual test and check. This would involve running the fans, to check that they can run at full speed with the doors open and that with the doors closed there is a pressure differential which is in the order of around 15-30 Pa. It is a simple check. What are the design requirements to ensure a high degree of reliability with inverters? The run and standby fans should each have their own inverter. Normally a fire-fighter’s switch would be provided as a bypass so that the fire-fighters can actually bypass the inverter to a direct contact to provide full speed. They would do this once they have opened the door into the lobby or corridor, so that there is no issue with pressure differentials because the door is open. To what extent can the relative humidity be allowed to increase with the cooling of a corridor with an evaporative cooling system? There will be an increase of humidity but generally this won’t induce discomfort or mould etc. The actual allowable value will depend on the location and the design of the system and this is always subject to a design on a project by project basis. What is the maximum temperature that the extract fans can tolerate? Is it possible not to supply sprinklers for cooling purposes? Such fans are normally rated at 300C and certainly sprinklers would not be required to protect the fans. The reason for this is that we are not taking smoke directly from the plume; we taking smoke which has come from the fire and which has been through a door and done a lot of mixing. We have never had a situation where the CFD has shown that the temperature within the smoke extract shaft will be 300C or higher. We normally get conditions around 50-200C. A 300C fan is perfectly acceptable and readily available: anyway, this is the normal rating for fans used for smoke control in the UK. Please explain the power supply requirements for mechanical extract systems BS 8519 requires both a maintained primary and secondary supply with an automatic transfer switch between the two that provides the maximum possible security for the supply to the units. The type of secondary system depends on the application: for instance it can be a generator system or a second mains supply system. © 2014 Colt International Licensing Ltd.
  • 3. What is the maximum allowable velocity in a ColtShaft? We design on the pressure drop down the shaft, not the velocity, in such a way that we limit that pressure drop: we should achieve a reasonable balance between the flow rate when we open the top damper and the flow rate when we open the bottom damper. Because of this factor, the taller the shaft is, the lower the velocity we want. What kind of air change rates is used to select a fan for summer overheating? We do not design on an air change rate. We look at the heat generated by the pipes in the corridor and then design to maintain a reasonable pressure differential. What is the maximum allowance velocity for dampers in a ColtShaft system? This depends on the product and system used. We tend size a conventional damper on 5 m/s for use with a mechanical system such as ColtShaft. What the maximum length of corridor we have designed for use with a mechanical extract system? We have designed systems up to 27m, though many are around 15-25m. Guidance suggests that 30m is the maximum that would be accepted by Building Control. This is because where you have a corridor divided by fire doors, then the maximum distance allowed between these is 30m, so this fairly well accepted. Technically I think we could get a larger distance to work but it would not be approved. What is the allowable maximum velocity in a pressurisation shaft? This comes down to achieving a balance between the power that is needed in the fan and keeping the duct size to a reasonable minimum. Typically 10 m/s might be the design velocity, but this will be influenced by the overall design and priorities. If smoke ventilation used for day to day ventilation, is inlet an issue as regards air quality? Generally not, as air inlet and extract are normally at roof level, where the air quality is likely to be high. However if a system has low level inlet, then this can indeed be a problem. If there are any dirty discharges from the rest of the building then these do need to be kept a reasonable distance away from the inlets for the day to day ventilation for the stairs or corridor. What allowance should be made for leakage when determining the pressure regulation control for leakage in the corridor itself and the control of the variable speed fan? In this instance we are not making an allowance at all, because system just runs at whatever speed is necessary. So if the corridor is very leaky, you may find that the fan may run at 40-50% of full speed; if the corridor is well sealed, the fan may run at 5-10% of full speed. This happens automatically so there is no allowance in terms of the design. How do you make sure that opening and closing of doors do actually close so as to maintain the negative pressure in the lobby? © 2014 Colt International Licensing Ltd.
  • 4. Door closers do the work of closing the door, but unfortunately they are variable in terms of the amount of power they provide, depending on how they are set up, how big the door is and so on. Although we design for a notional -25 Pa in the lobby, we adjust the lobby pressure at commissioning to allow us to ensure that the doors will close under that negative pressure. On occasions, where there are very large doors, we have had to get these adjusted to get the right balance between the two. But the relative pressure is not a very critical value: if it goes too high, problems with door opening and closing can occur, but it can go down to a low value without issues occurring. If combining smoke and environmental control, do you need to supply independent fans in any situation, i.e. one dedicated to smoke and the other to environmental control? Yes, you can do this, but you do not have to. In general you can use a smoke control fan with an inverter to reduce the volume flow rate and attenuators to keep the noise down and to reduce the power, or a separate dedicated environmental fan. Which you use comes down to the geometry of the building, in particular what space you have available. What are the requirements for the periodic inspection and maintenance of AOVs? Generally they should be maintained once a year. They should also have a weekly test to ensure that they are still working, since they are life safety systems, normally along with the fire alarm test. © 2014 Colt International Licensing Ltd.