SlideShare a Scribd company logo
1 of 29
Download to read offline
US Army Corps of Engineers
BUILDING STRONG®
Renewable Energy Development for a
Military Training Complex in
Afghanistan
William Stein
Benjamin Barnes
US Army ERDC-CERL
Energy, Utility & Environment Conference
(EUEC 2012), Session K-3
Phoenix AZ USA
31 January 2012
Distribution Statement A - Approved for public
release; distribution is unlimited.
BUILDING STRONG®
Outline
• Information collected after feasibility study
• Results from discussion with SSA
• Assessment plan
• Wind
• Solar PV
• Solar Hot Water + Diesel/Propane Boilers
• Lighting retrofit
• Reflective roofs
• Window retrofit
• Waste water treatment potentials
• WTE
• Phases II and III
• Acknowledgements
2
BUILDING STRONG®
Information collected after feasibility study
The 3 X cost multiplier does not capture in sufficient detail the site conditions
• Logistical difficulties:
• 1 MW turbine requires a 300 ton crane
• Largest section to move by truck is 35m long
• Multiple contractors around Kabul verify that the
largest crane available is 125 tons.
• Theft and vandalism are issues.
• Lack of technical capacity available for
operation and maintenance.
• USAID failures in micro-hydro caused them to
recommend: “In the short-term, make every effort
to slow developments to match the capacity by
downsizing planned government and donor
programs … to accommodate sustainable
development.”
• Rough terrain, insufficient
roads.
Eastern ridge of ANSU site, typical terrain.
Photo credit: Ben Barnes, CERL
3
BUILDING STRONG®
Results From In-Brief with the Senior Science
Advisor (SSA) to the Commander
GO-AHEAD GIVEN TO:
• Reduce the size and increase
the number of wind turbines.
Five 10-12 kW units tentatively
approved; potential for more.
• Install 50 kW PV in multiple small
systems.
• Consider efficiency and low-tech
RE for RFP.
• Cancel complex WTE plant.
• Cancel complex anaerobic
digester.
EMPHASIS ON:
• Social value: demonstrating that
RE can work here, showing the
public that we’re trying things
that work.
• Five-year paybacks are preferred
• Waste and waste-water sludge
both still require trucking off the
installation, which presents a
security issue. If possible, SSA
would still like recommendations
on these items.
4
BUILDING STRONG®
Renewable Energy
• 10-12 kW wind turbines
• 50 kW PV in multiple small systems.
• Solar hot water (potentially with diesel or propane
boiler)
• Transpired solar walls on the few buildings with
makeup air
Energy Efficiency
• Lighting retrofit
• Window retrofit
• Reflective roof coatings
Assessment Plan
Technologies Considered
5
BUILDING STRONG®
• Met with Renewable Energy Enterprises (REE), an
Afghan-owned company with a permanent
presence in Kabul.
• Exchanged emails with and reviewed the work of
Sustainable Energy Services Afghanistan (SESA),
a company installing systems and training Afghan
technicians in Kabul.
• Concluded that qualified, local companies exist,
both with experience in the technologies we are
considering.
Assessment Plan
Verify Availability of Technology/Contractors
6
BUILDING STRONG®
Wind Power
Installing a 1MW wind turbine is impossible at worst, risky at best
The limitations mentioned above
make a 1 MW turbine risky at best.
Even if it could be installed and
maintained, it is an unrealistically
large investment for a site with no
detailed wind study.
Furthermore, multiple small
resources increases resiliency in a
difficult maintenance environment;
failed turbines represent a smaller
percentage of the overall capacity,
and can be cannibalized for parts if
necessary.
http://www.brighterenergy.org/wp-
content/uploads/2010/05/nordic.jpg
7
BUILDING STRONG®
Wind Power
Contractors in Kabul have the capacity to install and maintain small turbines
Panjshir Valley wind power
project, SES Afghanistan (using
10 kW Bergey)
http://sesa.af/projects/panjshir-valley/gallery/panjshir-windpower-
small-2/
22 Bunkers ERDC Partnership:
Wind and Solar Project by IHFD
(partner of REE).
WWW.IHFDLLC.COM
The expected payback period (very roughly estimated) of the
new, smaller wind turbines is 20 years, or about 2.5 times
that predicted for the larger turbine.
8
BUILDING STRONG®
Wind Power
Site Determination
Wind data from the
Kabul airport (~8 mi.
East) indicate a
predominantly N and NW
wind. Monthly data
suggest that this flow is
largely dependent on
immediate solar
radiation, as it decreases
substantially in the
Winter.
9
BUILDING STRONG®
Wind Power
Site Determination
LIDAR data from the Intelligence Fusion Cell assisted in
understanding large scale features likely to change the speed
and prevailing direction of the wind.
10
BUILDING STRONG®
Wind Power
Site Determination
Site observations on different days and times helped verify
assumptions on wind behavior and assess constructability.
GPS data and observations recorded for each potential site.
Observing wind walking from peak to saddle on
NW ridge. Photo credit: Ben Barnes, CERL
Bill Stein observing wind at NW peak at
ANSU site. Photo credit: Ben Barnes, CERL
11
BUILDING STRONG®
Wind Power
Site Determination
Proposed locations.
12
BUILDING STRONG®
Wind Power
Site Determination
Proposed locations – East Ridgeline.
13
BUILDING STRONG®
Wind Power
Site Determination
Proposed locations – Northeast Ridgeline.
14
BUILDING STRONG®
Wind Power
Site Determination
Proposed locations – Northwest Ridgeline.
15
BUILDING STRONG®
Wind Power
Future Potential
After two or more years, the
10 kW turbines will indicate
which wind sites are the
best, paving the way for
installation of a larger 275
kW Vergnet, which is the
largest tilt-up wind turbine
available. It can be installed
or maintained with a 20 ton
crane.
www.vergnet.com
16
BUILDING STRONG®
Photovoltaics
Installing a 2 MW PV array is risky and expensive. Senior Science Advisor requested
smaller and approved a total of 50 kW in smaller systems.
The technical limitations
mentioned above make a 2
MW solar array risky. Theft
and vandalism remain and
issue at ANSU, so smaller,
roof mounted systems are
preferred.
The same small inverter size
throughout will increase
system resiliency and is
more within the capacity of
the available contractors.http://www.industcards.com/nellis-pv.jpg
17
BUILDING STRONG®
Sayed Karam solar power
project, Sustainable Energy
Service Afghainstan
http://sesa.af/projects/sayed-karam-solar-pv-
project/gallery/
22 Bunkers ERDC Partnership:
Wind and Solar Project by IHFD
(partner of REE).
WWW.IHFDLLC.COM
The expected payback period (very roughly estimated) of the
new, smaller solar systems is 24 years, or about 1.6 times
that predicted for the ground-mounted 2-MW system.
Photovoltaics
Multiple contractors in Kabul have the capacity to install and maintain small,
grid-tied solar systems
18
BUILDING STRONG®
The expected payback period (very roughly estimated) of
the SHW systems is 9.4 years.
Solar Hot Water
Multiple contractors in Kabul have the capacity to install and maintain domestic SHW
systems, which have a better payback than other renewables considered.
An REE affiliate manufactures
solar thermal panels in Kabul.
They also import and install
systems.
WWW.IHFDLLC.COM
Sustainable Energy Services
Afghanistan installs evacuated
tube collectors.
http://img.diytrade.com/
19
BUILDING STRONG®
Solar Hot Water
Multiple contractors in Kabul have the capacity to install and maintain domestic
SHW systems, which have a better payback than other renewables considered.
• The current hot water scheme is many electric
resistance tanks in every building.
• The assessment identified buildings with heaters
in the same general location, making
supplementing with solar hot water more feasible.
• Diesel boilers also have the potential to reduce
diesel consumption per Btu of hot water by a
factor of 3 or 4. Propane is also an option, as it will
be supplied to the DFACs for cooking.
20
BUILDING STRONG®
Solar Hot Water
Comparing a low-solar-fraction electric backup SHW system to a ordinary
diesel boiler.
A low solar fraction
with electric backup
can consume more
diesel than a simple
diesel boiler.
The “break-even” solar
fraction when
comparing these two
systems, is 69%.
(assuming a genset efficiency of 25%
and a diesel boiler efficiency of 80%)
21
BUILDING STRONG®
Solar Hot Water
Four options
• Use a high solar fraction solar system (>80%)
with the existing electric water heaters as
backup.
• Accept the added complexity of SHW with a
diesel or propane backup.
• Implement diesel or propane boiler alone.
• Heat pump water heaters with or without solar
backup (this option likely unavailable)
22
BUILDING STRONG®
Lighting Retrofit
The lighting load can be cut in half in most places.
Magnetic ballasts were used in Phase I because electronic ballasts are
difficult to get in Kabul. ANSU is large enough to justify importing a large
order from Dubai, however, and the high reliability of programmable start
electronic ballasts suggests that 10-15% spares should be adequate for
the foreseeable future.
Typical two-
lamp fixture
from Building
229 on ANSU.
Photo credit:
Ben Barnes
23
BUILDING STRONG®
The spaces are also over-lit. 6500K lamps are more common in Afghanistan than
in the US, and the light they provide is used more efficiently by the human eye.
The US-based designers might not have taken this into account when designing
the lighting; one lamp-fixtures in most locations would give adequate lighting.
Replacing with one-lamp fixtures with electronic ballasts will have a (roughly
estimated) 4.4 year payback.
6500K lamps
excessively
illuminating a
barracks corridor
at ANSU. Photo
Credit: Ben
Barnes
Lighting Retrofit
The lighting load can be cut in half in most places.
24
BUILDING STRONG®
The expected payback period (very roughly estimated) of the reflective
roof coatings is 5 years. This does not include the small contribution to
PV and SHW systems from the higher reflectivity roof.
Reflective Roof
Reflective roofs have the potential to increase comfort in most buildings and
reduce cooling energy in the air conditioned buildings.
Bill Stein inspects new ‘TC Ceramic®’ coating on a roof in
Baghdad in 2004. Photo Credit: Richard Kelly
Coated Bagdad roof next to uncoated roof. Photo Credit:
Richard Kelly
25
BUILDING STRONG®
Other Technologies Assessed
• Window Retrofits.
• Waste water biogas digester.
• Solid waste to energy
incineration (briquette
machine or electricity plant).
26
AwningwindowinANSUsupport
area.Photocredit:BillStein
http://business.inquirer.net/money/topstories/view/20110
312-325042/Garbage-in-briquettes-out
TheBiogas/BiofertilizerBusinessHandbook.
PeaceCorpsInformationCollectionand
Exchange
BUILDING STRONG®
• Feasibility determined for several
demonstration scale retrofit technologies
for Phase I and II.
• Recommendations made for Phase III to
avoid unnecessary retrofit.
Conclusions
27
BUILDING STRONG®
Acknowledgements
• CSTC-A, for sponsorship
• AMEC, for providing food, lodging, hospitality and
security at their site, traveling around with us and
providing information and recommendations in a timely
manner.
• MACTEC, for meeting with us, and entertaining a long
discussion about design changes.
• REE, for meeting with us and discussing their
experiences in Afghanistan.
• SESA, for exchanging emails with us and discussing
their experiences in Afghanistan.
• TAD Intelligence Fusion Cell, for supporting the effort
by promptly responding to requests for GIS
information.
28
BUILDING STRONG®
Questions and contact information
Bill Stein
Office phone 520-456-1377
E-mail william.j.stein@usace.army.mil
29

More Related Content

What's hot

Smart Cities presentation at the Renewable Energy Conference at Eilat Eilot
Smart Cities presentation at the Renewable Energy Conference at Eilat EilotSmart Cities presentation at the Renewable Energy Conference at Eilat Eilot
Smart Cities presentation at the Renewable Energy Conference at Eilat EilotHaim R. Branisteanu
 
Rural electrification by Lakshmi.Nidoni-seminar ppt
Rural electrification by Lakshmi.Nidoni-seminar pptRural electrification by Lakshmi.Nidoni-seminar ppt
Rural electrification by Lakshmi.Nidoni-seminar pptlakshmi nidoni
 
rural electrification
rural electrificationrural electrification
rural electrificationanudeep123
 
GRAPHENE USES IN ENERGY STORAGE
GRAPHENE USES IN ENERGY STORAGEGRAPHENE USES IN ENERGY STORAGE
GRAPHENE USES IN ENERGY STORAGESagar Gadhethariya
 
Future of solar power
Future of solar powerFuture of solar power
Future of solar powerShahed Babu
 
" Overview on Solar energy "
" Overview on Solar energy "" Overview on Solar energy "
" Overview on Solar energy "Virendra Uppalwar
 
Roof top solar project
Roof top solar projectRoof top solar project
Roof top solar projectSumit Sharma
 
Graphene and its applications in electrical devices(batteries ,
Graphene  and its applications in electrical devices(batteries ,Graphene  and its applications in electrical devices(batteries ,
Graphene and its applications in electrical devices(batteries ,mohdabuzar5
 
Aoil floating solar power plant ppt 2015
Aoil floating solar power plant ppt 2015Aoil floating solar power plant ppt 2015
Aoil floating solar power plant ppt 2015Abhay Ocean India ltd.
 
Session 3A - Samuel Sanchez
Session 3A - Samuel SanchezSession 3A - Samuel Sanchez
Session 3A - Samuel SanchezReenergize
 
HYBRID POWER GENERATION SYSTEM From KMP College
HYBRID POWER  GENERATION SYSTEM From KMP CollegeHYBRID POWER  GENERATION SYSTEM From KMP College
HYBRID POWER GENERATION SYSTEM From KMP CollegeHIGHVOLTEEE
 
Renewable Energy, 07 29 09
Renewable Energy, 07 29 09Renewable Energy, 07 29 09
Renewable Energy, 07 29 09James Jurgensen
 
The big green future of energy storage systems
The big green future of energy storage systemsThe big green future of energy storage systems
The big green future of energy storage systemsFSP Technology Inc.
 
1. Paper on Floating Solar Photovoltaic System An Emerging Technology
1. Paper on Floating Solar Photovoltaic System An Emerging Technology1. Paper on Floating Solar Photovoltaic System An Emerging Technology
1. Paper on Floating Solar Photovoltaic System An Emerging TechnologyMd Shahabuddin
 
Electric Energy Storage Systems
Electric Energy Storage SystemsElectric Energy Storage Systems
Electric Energy Storage SystemsHussein Kassem
 
Greenway self park building, Chicago
Greenway self park building, ChicagoGreenway self park building, Chicago
Greenway self park building, ChicagoPragyaGoswami1
 
EMERGING TRENDS IN ELECTRICAL ENGINEERING
EMERGING TRENDS IN ELECTRICAL ENGINEERING EMERGING TRENDS IN ELECTRICAL ENGINEERING
EMERGING TRENDS IN ELECTRICAL ENGINEERING ANANT VYAS
 
GreenStudio - Chapter 4 5 4 Photovoltaics
GreenStudio - Chapter 4 5 4 PhotovoltaicsGreenStudio - Chapter 4 5 4 Photovoltaics
GreenStudio - Chapter 4 5 4 PhotovoltaicsGalala University
 
GreenStudio - Chapter 4 5 4 Photovoltaics2
GreenStudio - Chapter 4 5 4 Photovoltaics2GreenStudio - Chapter 4 5 4 Photovoltaics2
GreenStudio - Chapter 4 5 4 Photovoltaics2Galala University
 

What's hot (20)

Smart Cities presentation at the Renewable Energy Conference at Eilat Eilot
Smart Cities presentation at the Renewable Energy Conference at Eilat EilotSmart Cities presentation at the Renewable Energy Conference at Eilat Eilot
Smart Cities presentation at the Renewable Energy Conference at Eilat Eilot
 
Rural electrification by Lakshmi.Nidoni-seminar ppt
Rural electrification by Lakshmi.Nidoni-seminar pptRural electrification by Lakshmi.Nidoni-seminar ppt
Rural electrification by Lakshmi.Nidoni-seminar ppt
 
Solar Panel
Solar PanelSolar Panel
Solar Panel
 
rural electrification
rural electrificationrural electrification
rural electrification
 
GRAPHENE USES IN ENERGY STORAGE
GRAPHENE USES IN ENERGY STORAGEGRAPHENE USES IN ENERGY STORAGE
GRAPHENE USES IN ENERGY STORAGE
 
Future of solar power
Future of solar powerFuture of solar power
Future of solar power
 
" Overview on Solar energy "
" Overview on Solar energy "" Overview on Solar energy "
" Overview on Solar energy "
 
Roof top solar project
Roof top solar projectRoof top solar project
Roof top solar project
 
Graphene and its applications in electrical devices(batteries ,
Graphene  and its applications in electrical devices(batteries ,Graphene  and its applications in electrical devices(batteries ,
Graphene and its applications in electrical devices(batteries ,
 
Aoil floating solar power plant ppt 2015
Aoil floating solar power plant ppt 2015Aoil floating solar power plant ppt 2015
Aoil floating solar power plant ppt 2015
 
Session 3A - Samuel Sanchez
Session 3A - Samuel SanchezSession 3A - Samuel Sanchez
Session 3A - Samuel Sanchez
 
HYBRID POWER GENERATION SYSTEM From KMP College
HYBRID POWER  GENERATION SYSTEM From KMP CollegeHYBRID POWER  GENERATION SYSTEM From KMP College
HYBRID POWER GENERATION SYSTEM From KMP College
 
Renewable Energy, 07 29 09
Renewable Energy, 07 29 09Renewable Energy, 07 29 09
Renewable Energy, 07 29 09
 
The big green future of energy storage systems
The big green future of energy storage systemsThe big green future of energy storage systems
The big green future of energy storage systems
 
1. Paper on Floating Solar Photovoltaic System An Emerging Technology
1. Paper on Floating Solar Photovoltaic System An Emerging Technology1. Paper on Floating Solar Photovoltaic System An Emerging Technology
1. Paper on Floating Solar Photovoltaic System An Emerging Technology
 
Electric Energy Storage Systems
Electric Energy Storage SystemsElectric Energy Storage Systems
Electric Energy Storage Systems
 
Greenway self park building, Chicago
Greenway self park building, ChicagoGreenway self park building, Chicago
Greenway self park building, Chicago
 
EMERGING TRENDS IN ELECTRICAL ENGINEERING
EMERGING TRENDS IN ELECTRICAL ENGINEERING EMERGING TRENDS IN ELECTRICAL ENGINEERING
EMERGING TRENDS IN ELECTRICAL ENGINEERING
 
GreenStudio - Chapter 4 5 4 Photovoltaics
GreenStudio - Chapter 4 5 4 PhotovoltaicsGreenStudio - Chapter 4 5 4 Photovoltaics
GreenStudio - Chapter 4 5 4 Photovoltaics
 
GreenStudio - Chapter 4 5 4 Photovoltaics2
GreenStudio - Chapter 4 5 4 Photovoltaics2GreenStudio - Chapter 4 5 4 Photovoltaics2
GreenStudio - Chapter 4 5 4 Photovoltaics2
 

Viewers also liked

Updated AREU Presentation 1
Updated AREU Presentation 1Updated AREU Presentation 1
Updated AREU Presentation 1AREU Afghanistan
 
Conservation of energy
Conservation of energyConservation of energy
Conservation of energySameer Nawab
 
Mineral Resources of Afghanistan
Mineral Resources of AfghanistanMineral Resources of Afghanistan
Mineral Resources of AfghanistanPierre Memheld
 
An Introduction to Petroleum & Mineral Resources of Afghanistan
An Introduction to  Petroleum & Mineral Resources of AfghanistanAn Introduction to  Petroleum & Mineral Resources of Afghanistan
An Introduction to Petroleum & Mineral Resources of AfghanistanIPPAI
 
Renewable Energy Resourses
Renewable Energy ResoursesRenewable Energy Resourses
Renewable Energy Resoursesshalini2093
 

Viewers also liked (7)

Afghanistan Country Presentation at ACEF 2014
Afghanistan Country Presentation at ACEF 2014Afghanistan Country Presentation at ACEF 2014
Afghanistan Country Presentation at ACEF 2014
 
Updated AREU Presentation 1
Updated AREU Presentation 1Updated AREU Presentation 1
Updated AREU Presentation 1
 
Conservation of energy
Conservation of energyConservation of energy
Conservation of energy
 
Mineral Resources of Afghanistan
Mineral Resources of AfghanistanMineral Resources of Afghanistan
Mineral Resources of Afghanistan
 
An Introduction to Petroleum & Mineral Resources of Afghanistan
An Introduction to  Petroleum & Mineral Resources of AfghanistanAn Introduction to  Petroleum & Mineral Resources of Afghanistan
An Introduction to Petroleum & Mineral Resources of Afghanistan
 
Renewable Energy Resourses
Renewable Energy ResoursesRenewable Energy Resourses
Renewable Energy Resourses
 
Afghanistan .
Afghanistan .Afghanistan .
Afghanistan .
 

Similar to Renewable Energy Development for the Afghanistan National Security University by Bill Stein 31 jan 2012

A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.Saurabh Biswas
 
Wind energy applications, ams short course, august 1, 2010, keystone, co
Wind energy applications, ams short course, august 1, 2010, keystone, coWind energy applications, ams short course, august 1, 2010, keystone, co
Wind energy applications, ams short course, august 1, 2010, keystone, condkelley
 
Colgreen North Shore presentation-7.26.12
Colgreen North Shore presentation-7.26.12Colgreen North Shore presentation-7.26.12
Colgreen North Shore presentation-7.26.12Graeme Donaldson
 
Chris dowe-synergy’s-renewable-energy-integration
Chris dowe-synergy’s-renewable-energy-integrationChris dowe-synergy’s-renewable-energy-integration
Chris dowe-synergy’s-renewable-energy-integrationjames hamilton
 
Ece464 power electronics assignment solution
Ece464 power electronics assignment solutionEce464 power electronics assignment solution
Ece464 power electronics assignment solutionOZ Assignment help
 
Infrastructure Seminar | B9 Energy | David Surplus | Case Study
Infrastructure Seminar | B9 Energy | David Surplus | Case StudyInfrastructure Seminar | B9 Energy | David Surplus | Case Study
Infrastructure Seminar | B9 Energy | David Surplus | Case StudyInvest Northern Ireland
 
Enterprise Europe Network | STORY CAES Demo | David Surplus
Enterprise Europe Network | STORY CAES Demo | David SurplusEnterprise Europe Network | STORY CAES Demo | David Surplus
Enterprise Europe Network | STORY CAES Demo | David SurplusInvest Northern Ireland
 
Solar PV on Dry Lakebed Soil
Solar PV on Dry Lakebed SoilSolar PV on Dry Lakebed Soil
Solar PV on Dry Lakebed SoilYamen Nanne
 
SILVESTER-PRESENTION.pptx
SILVESTER-PRESENTION.pptxSILVESTER-PRESENTION.pptx
SILVESTER-PRESENTION.pptxAntonyGeo1
 
Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power
Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable PowerFeasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power
Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable PowerClean Energy Canada
 
Colgreen North Shore presentation-1.8a.13
Colgreen North Shore presentation-1.8a.13Colgreen North Shore presentation-1.8a.13
Colgreen North Shore presentation-1.8a.13Graeme Donaldson
 
Rebecca mills-securing-the-n ts-energy-future
Rebecca mills-securing-the-n ts-energy-futureRebecca mills-securing-the-n ts-energy-future
Rebecca mills-securing-the-n ts-energy-futurejames hamilton
 
Technology review
Technology reviewTechnology review
Technology reviewCPWF Mekong
 
AEP texas project edison award winner
AEP texas project edison award winnerAEP texas project edison award winner
AEP texas project edison award winnerDave Bryant
 
PVN SOQ Presentation 2016 Final
PVN SOQ Presentation 2016 FinalPVN SOQ Presentation 2016 Final
PVN SOQ Presentation 2016 FinalRobert Potter
 
Energy Storage Systems and Technology
Energy Storage Systems and TechnologyEnergy Storage Systems and Technology
Energy Storage Systems and TechnologyBushveld Energy
 
Wind Energy Project Analysis
Wind Energy Project AnalysisWind Energy Project Analysis
Wind Energy Project AnalysisLeonardo ENERGY
 
Nwtc seminar overview of the impact of turbulence on turbine dynamics, sept...
Nwtc seminar   overview of the impact of turbulence on turbine dynamics, sept...Nwtc seminar   overview of the impact of turbulence on turbine dynamics, sept...
Nwtc seminar overview of the impact of turbulence on turbine dynamics, sept...ndkelley
 
Byron Washom's Microgrid Guest Lecture
Byron Washom's Microgrid Guest LectureByron Washom's Microgrid Guest Lecture
Byron Washom's Microgrid Guest LectureUCSD-Strategic-Energy
 

Similar to Renewable Energy Development for the Afghanistan National Security University by Bill Stein 31 jan 2012 (20)

A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.
 
Wind energy applications, ams short course, august 1, 2010, keystone, co
Wind energy applications, ams short course, august 1, 2010, keystone, coWind energy applications, ams short course, august 1, 2010, keystone, co
Wind energy applications, ams short course, august 1, 2010, keystone, co
 
Colgreen North Shore presentation-7.26.12
Colgreen North Shore presentation-7.26.12Colgreen North Shore presentation-7.26.12
Colgreen North Shore presentation-7.26.12
 
EESS 2018 Day 2 - Mark Mills
EESS 2018 Day 2 - Mark MillsEESS 2018 Day 2 - Mark Mills
EESS 2018 Day 2 - Mark Mills
 
Chris dowe-synergy’s-renewable-energy-integration
Chris dowe-synergy’s-renewable-energy-integrationChris dowe-synergy’s-renewable-energy-integration
Chris dowe-synergy’s-renewable-energy-integration
 
Ece464 power electronics assignment solution
Ece464 power electronics assignment solutionEce464 power electronics assignment solution
Ece464 power electronics assignment solution
 
Infrastructure Seminar | B9 Energy | David Surplus | Case Study
Infrastructure Seminar | B9 Energy | David Surplus | Case StudyInfrastructure Seminar | B9 Energy | David Surplus | Case Study
Infrastructure Seminar | B9 Energy | David Surplus | Case Study
 
Enterprise Europe Network | STORY CAES Demo | David Surplus
Enterprise Europe Network | STORY CAES Demo | David SurplusEnterprise Europe Network | STORY CAES Demo | David Surplus
Enterprise Europe Network | STORY CAES Demo | David Surplus
 
Solar PV on Dry Lakebed Soil
Solar PV on Dry Lakebed SoilSolar PV on Dry Lakebed Soil
Solar PV on Dry Lakebed Soil
 
SILVESTER-PRESENTION.pptx
SILVESTER-PRESENTION.pptxSILVESTER-PRESENTION.pptx
SILVESTER-PRESENTION.pptx
 
Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power
Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable PowerFeasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power
Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power
 
Colgreen North Shore presentation-1.8a.13
Colgreen North Shore presentation-1.8a.13Colgreen North Shore presentation-1.8a.13
Colgreen North Shore presentation-1.8a.13
 
Rebecca mills-securing-the-n ts-energy-future
Rebecca mills-securing-the-n ts-energy-futureRebecca mills-securing-the-n ts-energy-future
Rebecca mills-securing-the-n ts-energy-future
 
Technology review
Technology reviewTechnology review
Technology review
 
AEP texas project edison award winner
AEP texas project edison award winnerAEP texas project edison award winner
AEP texas project edison award winner
 
PVN SOQ Presentation 2016 Final
PVN SOQ Presentation 2016 FinalPVN SOQ Presentation 2016 Final
PVN SOQ Presentation 2016 Final
 
Energy Storage Systems and Technology
Energy Storage Systems and TechnologyEnergy Storage Systems and Technology
Energy Storage Systems and Technology
 
Wind Energy Project Analysis
Wind Energy Project AnalysisWind Energy Project Analysis
Wind Energy Project Analysis
 
Nwtc seminar overview of the impact of turbulence on turbine dynamics, sept...
Nwtc seminar   overview of the impact of turbulence on turbine dynamics, sept...Nwtc seminar   overview of the impact of turbulence on turbine dynamics, sept...
Nwtc seminar overview of the impact of turbulence on turbine dynamics, sept...
 
Byron Washom's Microgrid Guest Lecture
Byron Washom's Microgrid Guest LectureByron Washom's Microgrid Guest Lecture
Byron Washom's Microgrid Guest Lecture
 

Recently uploaded

Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
Rums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfRums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfsmsksolar
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxmaisarahman1
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Air Compressor reciprocating single stage
Air Compressor reciprocating single stageAir Compressor reciprocating single stage
Air Compressor reciprocating single stageAbc194748
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...HenryBriggs2
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersMairaAshraf6
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086anil_gaur
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 

Recently uploaded (20)

Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Rums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfRums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdf
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Air Compressor reciprocating single stage
Air Compressor reciprocating single stageAir Compressor reciprocating single stage
Air Compressor reciprocating single stage
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 

Renewable Energy Development for the Afghanistan National Security University by Bill Stein 31 jan 2012

  • 1. US Army Corps of Engineers BUILDING STRONG® Renewable Energy Development for a Military Training Complex in Afghanistan William Stein Benjamin Barnes US Army ERDC-CERL Energy, Utility & Environment Conference (EUEC 2012), Session K-3 Phoenix AZ USA 31 January 2012 Distribution Statement A - Approved for public release; distribution is unlimited.
  • 2. BUILDING STRONG® Outline • Information collected after feasibility study • Results from discussion with SSA • Assessment plan • Wind • Solar PV • Solar Hot Water + Diesel/Propane Boilers • Lighting retrofit • Reflective roofs • Window retrofit • Waste water treatment potentials • WTE • Phases II and III • Acknowledgements 2
  • 3. BUILDING STRONG® Information collected after feasibility study The 3 X cost multiplier does not capture in sufficient detail the site conditions • Logistical difficulties: • 1 MW turbine requires a 300 ton crane • Largest section to move by truck is 35m long • Multiple contractors around Kabul verify that the largest crane available is 125 tons. • Theft and vandalism are issues. • Lack of technical capacity available for operation and maintenance. • USAID failures in micro-hydro caused them to recommend: “In the short-term, make every effort to slow developments to match the capacity by downsizing planned government and donor programs … to accommodate sustainable development.” • Rough terrain, insufficient roads. Eastern ridge of ANSU site, typical terrain. Photo credit: Ben Barnes, CERL 3
  • 4. BUILDING STRONG® Results From In-Brief with the Senior Science Advisor (SSA) to the Commander GO-AHEAD GIVEN TO: • Reduce the size and increase the number of wind turbines. Five 10-12 kW units tentatively approved; potential for more. • Install 50 kW PV in multiple small systems. • Consider efficiency and low-tech RE for RFP. • Cancel complex WTE plant. • Cancel complex anaerobic digester. EMPHASIS ON: • Social value: demonstrating that RE can work here, showing the public that we’re trying things that work. • Five-year paybacks are preferred • Waste and waste-water sludge both still require trucking off the installation, which presents a security issue. If possible, SSA would still like recommendations on these items. 4
  • 5. BUILDING STRONG® Renewable Energy • 10-12 kW wind turbines • 50 kW PV in multiple small systems. • Solar hot water (potentially with diesel or propane boiler) • Transpired solar walls on the few buildings with makeup air Energy Efficiency • Lighting retrofit • Window retrofit • Reflective roof coatings Assessment Plan Technologies Considered 5
  • 6. BUILDING STRONG® • Met with Renewable Energy Enterprises (REE), an Afghan-owned company with a permanent presence in Kabul. • Exchanged emails with and reviewed the work of Sustainable Energy Services Afghanistan (SESA), a company installing systems and training Afghan technicians in Kabul. • Concluded that qualified, local companies exist, both with experience in the technologies we are considering. Assessment Plan Verify Availability of Technology/Contractors 6
  • 7. BUILDING STRONG® Wind Power Installing a 1MW wind turbine is impossible at worst, risky at best The limitations mentioned above make a 1 MW turbine risky at best. Even if it could be installed and maintained, it is an unrealistically large investment for a site with no detailed wind study. Furthermore, multiple small resources increases resiliency in a difficult maintenance environment; failed turbines represent a smaller percentage of the overall capacity, and can be cannibalized for parts if necessary. http://www.brighterenergy.org/wp- content/uploads/2010/05/nordic.jpg 7
  • 8. BUILDING STRONG® Wind Power Contractors in Kabul have the capacity to install and maintain small turbines Panjshir Valley wind power project, SES Afghanistan (using 10 kW Bergey) http://sesa.af/projects/panjshir-valley/gallery/panjshir-windpower- small-2/ 22 Bunkers ERDC Partnership: Wind and Solar Project by IHFD (partner of REE). WWW.IHFDLLC.COM The expected payback period (very roughly estimated) of the new, smaller wind turbines is 20 years, or about 2.5 times that predicted for the larger turbine. 8
  • 9. BUILDING STRONG® Wind Power Site Determination Wind data from the Kabul airport (~8 mi. East) indicate a predominantly N and NW wind. Monthly data suggest that this flow is largely dependent on immediate solar radiation, as it decreases substantially in the Winter. 9
  • 10. BUILDING STRONG® Wind Power Site Determination LIDAR data from the Intelligence Fusion Cell assisted in understanding large scale features likely to change the speed and prevailing direction of the wind. 10
  • 11. BUILDING STRONG® Wind Power Site Determination Site observations on different days and times helped verify assumptions on wind behavior and assess constructability. GPS data and observations recorded for each potential site. Observing wind walking from peak to saddle on NW ridge. Photo credit: Ben Barnes, CERL Bill Stein observing wind at NW peak at ANSU site. Photo credit: Ben Barnes, CERL 11
  • 12. BUILDING STRONG® Wind Power Site Determination Proposed locations. 12
  • 13. BUILDING STRONG® Wind Power Site Determination Proposed locations – East Ridgeline. 13
  • 14. BUILDING STRONG® Wind Power Site Determination Proposed locations – Northeast Ridgeline. 14
  • 15. BUILDING STRONG® Wind Power Site Determination Proposed locations – Northwest Ridgeline. 15
  • 16. BUILDING STRONG® Wind Power Future Potential After two or more years, the 10 kW turbines will indicate which wind sites are the best, paving the way for installation of a larger 275 kW Vergnet, which is the largest tilt-up wind turbine available. It can be installed or maintained with a 20 ton crane. www.vergnet.com 16
  • 17. BUILDING STRONG® Photovoltaics Installing a 2 MW PV array is risky and expensive. Senior Science Advisor requested smaller and approved a total of 50 kW in smaller systems. The technical limitations mentioned above make a 2 MW solar array risky. Theft and vandalism remain and issue at ANSU, so smaller, roof mounted systems are preferred. The same small inverter size throughout will increase system resiliency and is more within the capacity of the available contractors.http://www.industcards.com/nellis-pv.jpg 17
  • 18. BUILDING STRONG® Sayed Karam solar power project, Sustainable Energy Service Afghainstan http://sesa.af/projects/sayed-karam-solar-pv- project/gallery/ 22 Bunkers ERDC Partnership: Wind and Solar Project by IHFD (partner of REE). WWW.IHFDLLC.COM The expected payback period (very roughly estimated) of the new, smaller solar systems is 24 years, or about 1.6 times that predicted for the ground-mounted 2-MW system. Photovoltaics Multiple contractors in Kabul have the capacity to install and maintain small, grid-tied solar systems 18
  • 19. BUILDING STRONG® The expected payback period (very roughly estimated) of the SHW systems is 9.4 years. Solar Hot Water Multiple contractors in Kabul have the capacity to install and maintain domestic SHW systems, which have a better payback than other renewables considered. An REE affiliate manufactures solar thermal panels in Kabul. They also import and install systems. WWW.IHFDLLC.COM Sustainable Energy Services Afghanistan installs evacuated tube collectors. http://img.diytrade.com/ 19
  • 20. BUILDING STRONG® Solar Hot Water Multiple contractors in Kabul have the capacity to install and maintain domestic SHW systems, which have a better payback than other renewables considered. • The current hot water scheme is many electric resistance tanks in every building. • The assessment identified buildings with heaters in the same general location, making supplementing with solar hot water more feasible. • Diesel boilers also have the potential to reduce diesel consumption per Btu of hot water by a factor of 3 or 4. Propane is also an option, as it will be supplied to the DFACs for cooking. 20
  • 21. BUILDING STRONG® Solar Hot Water Comparing a low-solar-fraction electric backup SHW system to a ordinary diesel boiler. A low solar fraction with electric backup can consume more diesel than a simple diesel boiler. The “break-even” solar fraction when comparing these two systems, is 69%. (assuming a genset efficiency of 25% and a diesel boiler efficiency of 80%) 21
  • 22. BUILDING STRONG® Solar Hot Water Four options • Use a high solar fraction solar system (>80%) with the existing electric water heaters as backup. • Accept the added complexity of SHW with a diesel or propane backup. • Implement diesel or propane boiler alone. • Heat pump water heaters with or without solar backup (this option likely unavailable) 22
  • 23. BUILDING STRONG® Lighting Retrofit The lighting load can be cut in half in most places. Magnetic ballasts were used in Phase I because electronic ballasts are difficult to get in Kabul. ANSU is large enough to justify importing a large order from Dubai, however, and the high reliability of programmable start electronic ballasts suggests that 10-15% spares should be adequate for the foreseeable future. Typical two- lamp fixture from Building 229 on ANSU. Photo credit: Ben Barnes 23
  • 24. BUILDING STRONG® The spaces are also over-lit. 6500K lamps are more common in Afghanistan than in the US, and the light they provide is used more efficiently by the human eye. The US-based designers might not have taken this into account when designing the lighting; one lamp-fixtures in most locations would give adequate lighting. Replacing with one-lamp fixtures with electronic ballasts will have a (roughly estimated) 4.4 year payback. 6500K lamps excessively illuminating a barracks corridor at ANSU. Photo Credit: Ben Barnes Lighting Retrofit The lighting load can be cut in half in most places. 24
  • 25. BUILDING STRONG® The expected payback period (very roughly estimated) of the reflective roof coatings is 5 years. This does not include the small contribution to PV and SHW systems from the higher reflectivity roof. Reflective Roof Reflective roofs have the potential to increase comfort in most buildings and reduce cooling energy in the air conditioned buildings. Bill Stein inspects new ‘TC Ceramic®’ coating on a roof in Baghdad in 2004. Photo Credit: Richard Kelly Coated Bagdad roof next to uncoated roof. Photo Credit: Richard Kelly 25
  • 26. BUILDING STRONG® Other Technologies Assessed • Window Retrofits. • Waste water biogas digester. • Solid waste to energy incineration (briquette machine or electricity plant). 26 AwningwindowinANSUsupport area.Photocredit:BillStein http://business.inquirer.net/money/topstories/view/20110 312-325042/Garbage-in-briquettes-out TheBiogas/BiofertilizerBusinessHandbook. PeaceCorpsInformationCollectionand Exchange
  • 27. BUILDING STRONG® • Feasibility determined for several demonstration scale retrofit technologies for Phase I and II. • Recommendations made for Phase III to avoid unnecessary retrofit. Conclusions 27
  • 28. BUILDING STRONG® Acknowledgements • CSTC-A, for sponsorship • AMEC, for providing food, lodging, hospitality and security at their site, traveling around with us and providing information and recommendations in a timely manner. • MACTEC, for meeting with us, and entertaining a long discussion about design changes. • REE, for meeting with us and discussing their experiences in Afghanistan. • SESA, for exchanging emails with us and discussing their experiences in Afghanistan. • TAD Intelligence Fusion Cell, for supporting the effort by promptly responding to requests for GIS information. 28
  • 29. BUILDING STRONG® Questions and contact information Bill Stein Office phone 520-456-1377 E-mail william.j.stein@usace.army.mil 29