SlideShare a Scribd company logo
1 of 48
Note: See the text itself for full citations.
Copyright 2018 Schwalbe Publishing 2
 Describe the importance of creating plans to guide
project execution
 List several planning processes and outputs for
project integration and scope management
 Discuss the project integration management planning
process and explain the purpose and contents of a
project management plan
 Describe the project scope management planning
processes
Copyright 2018 Schwalbe Publishing 3
 Explain the purpose and contents of a scope
management plan and requirements management plan
 Discuss different ways to collect project
requirements
 Create a scope statement to define project scope
 Develop a work breakdown structure (WBS) and a
WBS dictionary to clearly describe all of the work
required for a project
3
Copyright 2018 Schwalbe Publishing 4
 Many people have heard the following sayings:
◦ If you fail to plan, you plan to fail.
◦ If you don’t know where you’re going, any road will take you
there.
◦ What gets measured gets managed.
 Successful project managers know how important it is
to develop, refine, and follow plans to meet project
goals
 People are more likely to perform well if they know
what they are supposed to do and when
4
Copyright 2018 Schwalbe Publishing 5
 Planning is often the most difficult and unappreciated
process in project management
 Often, people do not want to take the time to plan
well, but theory and practice show that good planning
is crucial to good execution
 The main purpose of project planning is to guide
project execution, so project plans must be realistic
and useful
5
Copyright 2018 Schwalbe Publishing 6
 Many people make great plans, but they don’t realize the importance of using those plans as their roadmap. For
example, a transplant nurse, Sally (BSN, MSN), had moved up to the position as the lead technical person in her
department and was named the project manager for a new transplant implementation. Because of her
inexperience managing projects, the PMO Director, Mike “Mikey” Matthews, was asked to help her plan the
project. Mikey set up a meeting with the Sally for the following week, and she studied everything she could find
about project management over the weekend.
 The following week Mikey and Sally sat down with her team and developed a project management plan,
including schedules, budgets, and other required documents. It seemed like a great start. Sally thanked Mikey,
and he went back to his other projects while Sally’s project chugged along, appearing in status reports to be
doing fine. After about three months someone approached Mikey and asked if he would attend an upcoming
transplant project meeting.
 The meeting started off great, with each team member giving their updates. One by one they each told
the nurse project manager of obstacles, setbacks, lack of stakeholder participation, and unclear requirements
from users. Sally listened to each person intently, jotted notes, and then said, “That’s great. Thanks everyone.
I’ll see you next week!” The meeting ended. Just like that! After the room cleared Mikey asked Sally how the
project was going, and after a slight pause, she replied that it was going very well. Mikey then asked where they
were in the schedule. Sally paused again, this time for what seemed like minutes, looking back at Mikey blankly.
He then rephrased the question, “What activity are you working on right now, as a team? Are you ahead of
schedule? Behind schedule? You know, compared to the schedule we laid out three months ago.” After another
slight pause, Sally replied with a very simple and honest reply: “You didn’t say that we needed to use that
schedule again.”
 Sally had never considered the plan to be her roadmap, and as a result the project ended up being 100%
over schedule and nearly that much over budget.
Copyright 2018 Schwalbe Publishing 7
 Planning is often the most difficult and unappreciated
process in project management
 Often, people do not want to take the time to plan
well, but theory and practice show that good planning
is crucial to good execution
 The main purpose of project planning is to guide
project execution, so project plans must be realistic
and useful
7
Copyright 2018 Schwalbe Publishing 8
 Top managers often require a plan, but then no one
tracks whether the plan was followed
 One project manager said he would meet with each
project team leader within two months to review their
project plans. Two months later, the project manager
had still not met with over half of the project team
leaders
 Why should project team members feel obligated to
follow their own plans when the project manager
obviously does not follow his?
8
Copyright 2018 Schwalbe Publishing 99
Knowledge area Planning process Outputs
Project
integration
management
Develop project
management plan
Project management plan
Project scope
management
Plan scope
management
Collect requirements
Define scope
Create WBS
Scope management plan
Requirements management
plan
Requirements documentation
Requirements traceability
matrix
Project scope statement
Project documents updates
Scope baseline
Project documents updates
Copyright 2018 Schwalbe Publishing 10
 Project integration management involves coordinating
all the project management knowledge areas
throughout a project’s life span
 The main planning output is a project management plan
10
Copyright 2018 Schwalbe Publishing 11
 A project management plan is a document used to integrate and
coordinate all project planning documents and to help guide a
project’s execution, monitoring and control, and closure
 Plans created in the other knowledge areas are subsidiary parts
of the overall project management plan and provide more detailed
information about that knowledge area
 Project management plans facilitate communication among
stakeholders and provide a baseline for progress measurement
and project control
◦ A baseline is a starting point, a measurement, or an observation that
is documented so that it can be used for future comparison
11
Copyright 2018 Schwalbe Publishing 12
 The Berlin Brandenburg Airport was supposed to become the busiest airport in Germany. It
was projected to have 45 million passengers traveling through annually. The preplanning phase
took 15 years and the approved budget for the airport was €5.4 billion. Construction began in
2006 and it was scheduled to take 5 years to build. The opening day was set for October 30,
2011, but 6 years later the airport is still not open. The project is over budget with the latest
estimate totaling €7.9 billion.
 There are several reasons why that this project got off track. Correct information about the
project were not communicated. The city’s mayor, and project sponsor, was accused of
ignoring the problems during construction and acting as if the project was going as planned. In
2013, two years after the project’s scheduled finish date, the mayor was removed from his
position.
 Another reason this project was not finished on-time was due to the scope changes and the
unfortunate scope creep. One of the key stakeholders wanted to increase the size of the
airport. There were numerous quality issues that were found as well. Of the 66,500 defects
that were found, 34,000 were found to be “significant” and 5,845 were “critical”. These critical
defects were issues such as an alarm system that wasn’t built to appropriate building code.
 All of these factors have pushed this project’s timeline back further and further. As a project
manager it is important to ensure proper communication, prevent scope creep, and confirm
quality checks
Copyright 2018 Schwalbe Publishing 13•1
Source: Project Management Institute, Inc., A Guide to the Project
Management Body of Knowledge (PMBOK Guide) – Sixth Edition (2017).
Project Management Plan Project Documents
1. Scope management plan
2. Requirements management plan
3. Schedule management plan
4. Cost management plan
5. Quality management plan
6. Resource management plan
7. Communications management
plan
8. Risk management plan
9. Procurement management plan
10. Stakeholder engagement plan
11. Change management plan
12. Configuration management plan
13. Scope baseline
14. Schedule baseline
15. Cost baseline
16. Performance measurement
baseline
17. Project life cycle description
18. Development approach
1. Activity attributes
2. Activity list
3. Assumption log
4. Basis of estimates
5. Change log
6. Cost estimates
7. Cost forecasts
8. Duration estimates
9. Issue log
10. Lessons learned register
11. Milestone list
12. Physical resource
assignments
13. Project calendars
14. Project communications
15. Project schedule
16. Project schedule network
diagram
17. Project scope statement
18. Quality control
measurements
19. Quality metrics
1. Quality report
2. Requirements
documentation
3. Requirements
traceability matrix
4. Resource
assignments
5. Resource breakdown
structure
6. Resource calendars
7. Resource
requirements
8. Risk register
9. Risk report
10. Schedule data
11. Schedule forecasts
12. Stakeholder register
13. Team charter
14. Team resource
assignments
15. Test and evaluation
documents
Copyright 2018 Schwalbe Publishing 14
 Project management plans should be dynamic, flexible, and
receptive to change when the environment or project changes
 Just as projects are unique, so are project plans.
◦ For a small project involving a few people over a couple of months, a
project charter, team contract, scope statement, and Gantt chart
might be the only project planning documents needed; there would
not be a need for a separate project management plan
◦ A large project involving 100 people over three years would benefit
from having a detailed project management plan and separate plans
for each knowledge area
 It is important to tailor all planning documentation to fit the
needs of specific projects
14
Copyright 2018 Schwalbe Publishing 15
 Introduction/overview of the project
 Project organization
 Management and technical processes (including
project lifecycle description and development
approach, as applicable)
 Work to be performed (scope)
 Schedule information
 Budget information
 References to other project planning documents
15
Copyright 2018 Schwalbe Publishing 1616
PURPOSE
VAP costs AHS over $3.6M per year in costs, and puts our patients at risk for severe and sometimes fatal
consequences. VAP is considered preventable by CMS and has worked with the Institutes for Healthcare
Improvement (IHI) to develop a set of best practices that, if followed, has demonstrated a reduction of
VAP by 50% in other healthcare facilities. AHS will implement a system to collect and report compliance
with the best practices to better manage VAP.
PROJECT ORGANIZATION
The basic organization of the project is provided in Figure 1. The project sponsor, Marilyn Shoemaker, RN,
PhD, will have the final say on major decisions, with consultation from the project steering committee and
project champions, Casey Lidwell and Dr. Danielle Scheerer. The project sponsor should have time to
thoroughly review important project information and provide timely feedback to the project manager.
PROJECT GOVERNANCE
1. Management Review Process: The project steering committee will meet at least monthly to provide
inputs and review progress on this project.
2. Progress Measurement Process: The project steering committee will review project progress during
project review meetings, and they can also review information as needed by viewing reports on the
enterprise project management system.
3. Change Approval Process: See Attachment 1 based on AHS standards.
VAPR has been broken down into two phases. The first phase is a proof of concept and the data
collection/reporting system and will be managed by Jeff Birdwell, PMP from the PMO’s office. The second
phase will be managed by Pat Wager, RN from analytics.
Copyright 2018 Schwalbe Publishing 17
 Project scope management involves defining and
controlling what work is or is not included in a project
 The main planning tasks include planning scope
management, collecting requirements, defining scope,
and creating the WBS
 The main documents produced are requirements
documents, a requirements management plan, a
requirements traceability matrix, and a scope baseline,
which is composed of an approved scope statement, a
WBS, and a WBS dictionary
Copyright 2018 Schwalbe Publishing 18
 The purpose of the process of planning scope
management is to determine how the project scope
will be defined, validated, and controlled.
◦ Validation means formal acceptance of deliverables by the
customer and other identified stakeholders
◦ In contrast, verification (done as part of controlling quality)
means the deliverable complies with a regulation,
requirement, specification, or imposed condition
 Project teams usually have several meetings with key
stakeholders and experts to help them develop a
scope management plan and requirements
management plan.
Copyright 2018 Schwalbe Publishing 19
 Preparing a detailed project scope statement
 Creating, maintaining, and approving the WBS
 Obtaining acceptance of the completed project
deliverables
 Controlling how requests for changes to the project
scope statement will be processed
•1
Copyright 2018 Schwalbe Publishing 20
 The PMBOK® Guide – Sixth Edition, defines a
requirement as “a condition or capability that is
necessary to be present in a product, service, or
result to satisfy a business need.”
 A requirements management plan describes how
project requirements will be analyzed, documented,
and managed.
•2
Copyright 2018 Schwalbe Publishing 21
Requirements Management Plan
Version 1.0 May 29, 20xx
PROJECT TITLE: VENTILATOR ASSOCIATED PNEUMONIA (VAP) REDUCTION – “VAPR”
Planning, tracking, and reporting requirements
Information provided in the business case and project charter will provide valuable information
in determining requirements for this project, as will the IHI Ventilator Bundle itself. All
requirements will be documented within the project management system and will be reviewed
for progress weekly as part of the regular project meetings. Each requirement will be assigned a
customer owner, designated initially as the provider of the requirement, but in some cases as
the staff member who is considered the expert on the requirement itself.
Performing configuration management activities
Requirements can be identified through a variety of methods. Executive clinical leadership will
be interviewed individually, committees such as the Med Exec and Clinical Quality Improvement
Council will be asked for requirements through our sponsor, and our champions will conduct
focus groups with their peers and customers to gather input. Requirements will also be
extracted from the IHI Ventilator Bundle, and both CMS and Joint Commission measures will be
reviewed for additional requirements. Appropriate project stakeholders will analyze, authorize,
track, and report changes to requirements. The project manager must be informed in advance
of potential changes to requirements and be involved in the decision process to approve those
changes. Any change that will impact the project’s cost by more than 2% or extend the schedule
past the identified go live date must be approved by the project steering committee.
Copyright 2018 Schwalbe Publishing 22
 Emerging Health started using a tool by IBM called Rational
DOORS to help manage requirements. As a result, they saw a
69 percent reduction in the cost of test preparation, testing,
and rework in the software development process and a 25
percent reduction in the time it took to customize their
Clinical Looking Glass application for unique client
requirements.
 According to McCroskey, “Time to market is always a critical
benchmark, but especially so in the fast-paced healthcare
industry. Because our industry is so competitive, being able to
deliver the product faster enhances our reputation and the
confidence our customers have in us. Faster time to market is
vital to our success, and we’ve now achieved that with the
more responsive environment Rational DOORS has allowed us
to establish.”
•2
Copyright 2018 Schwalbe Publishing 23
Req
ID Name Category Source Status Comments
R26 Identify source
systems that
document
compliance
with the IHI
vent bundle
Technical Chief
Medical
Information
Officer
Complete Three sources were
identified: ClinDoc,
Pharmacy
Administration, and
RT Documentation.
R91 Online report
to indicate
compliance, by
patient, with IHI
bundle
Analytics Chief
Quality
Officer
Not
started
Data must be no
more than 6 hours
old.
R123 Design new
ventilator
protocol for
nursing
Clinical
Workflow
Chief
Nursing
Officer
Not
started
Must be reviewed
and approved by the
nursing oversight
committee.
Copyright 2018 Schwalbe Publishing 24
 Good scope definition is crucial to project success because it
◦ Helps improve the accuracy of time, cost, and resource estimates
◦ Defines a baseline for performance measurement and project control
◦ Aids in communicating clear work responsibilities
 The project charter, requirements documentation, and
organizational process assets (i.e. policies and procedures
related to project management, past project files, and lessons-
learned reports from previous, similar projects) are all inputs for
creating the initial scope statement
 Contents of a scope statement vary, but it should include a
product scope description, product user acceptance criteria, and
detailed information on all project deliverables
Copyright 2018 Schwalbe Publishing 25
 Good scope definition is crucial to project success because it
◦ Helps improve the accuracy of time, cost, and resource estimates
◦ Defines a baseline for performance measurement and project control
◦ Aids in communicating clear work responsibilities
 A project scope statement describes product characteristics and
requirements, user acceptance criteria, and deliverables.
 Work that is not included in the scope statement should not be
done, and you can explicitly state what is out of scope for the
project under a section called project exclusions.
Copyright 2018 Schwalbe Publishing 26
Product Characteristics and Requirements
This project will introduce the IHI Ventilator Bundle (best practices) into our AHS clinical
protocols and workflows. We must identify which, if any, AHS system currently collects data
that would indicate compliance with the five elements in the bundle. If the data is not currently
collected electronically at AHS, a data collection point must be identified. All data must be
integrated into a single online report so that they may correct the patient’s care during the
required time period. To minimize the amount of corrective actions required, the nursing and
respiratory therapy workflows will be modified to include the best practices, and the ventilator
protocols will be modified to automatically include orders for the bundle elements. The
following best practices are included in the IHI Ventilator Bundle:
 Patient Head of Bed (HOB) elevation, 30 to 45 degrees
 Sedation vacation every 24 hours
 Daily oral/mouth care with Chlorhexidine
 Venous Thrombosis Embolism (VTE) prophylaxis
 Peptic ulcer prophylaxis
Out of Scope
This project will not consider any other patient care, best practices, evidenced based medicine,
or other patient care improvements discovered during the project work. Any additional
potential patient care improvement projects will be submitted to the project request system
and reviewed, approved, and managed separately based on their own merits.
Copyright 2018 Schwalbe Publishing 27
Product User Acceptance Criteria
This project will be considered successful if the following measures are met:
 Project completed by the end of the next fiscal year (June 30)
 Project completed for $980,000 or less
 VAP incidence is reduced by 25% within 90 days of go live
 VAP incidence rate is reduced by 35% within 180 days of go live
 VAP incidence rate is reduced by 50% within 270 days of go live
Product-Oriented Deliverables
1. Data Interfaces from source systems, including registration, bed management, clinical
documentation, and respiratory therapy documentation systems.
2. Database to store IHI bundle data elements collected on AHS patients.
3. Online report to present IHI bundle compliance to caregivers using standard AHS
reporting tools.
4. Convenient and timely report delivery method, including availability on mobile devices.
5. Modified clinical workflows to integrate IHI Ventilator Bundle best practices.
Modified ventilator protocols to integrate IHI Ventilator Bundle best practices.
Copyright 2018 Schwalbe Publishing 28
 The project team should update the project scope
statement as new information becomes available
 Name different iterations of the scope statement
Version 1.0, Version 2.0, etc.
 A good, up-to-date scope statement helps prevent
scope creep, which is the tendency for project scope
to continually increase
Copyright 2018 Schwalbe Publishing 29
Copyright 2018 Schwalbe Publishing 30
 A work breakdown structure (WBS) is a deliverable-
oriented grouping of the work involved in a project
that defines the total scope of the project
 The WBS is a document that breaks all the work
required for the project into discrete deliverables,
and groups them into a logical hierarchy
 Often shown in two different forms:
◦ Graphical or chart form
◦ Tabular or list form
Copyright 2018 Schwalbe Publishing 31
 A work package is a deliverable at the lowest level of the
WBS, where it can be appropriately assigned to and
managed by a single accountable person
 Each work package should be defined in enough detail to
estimate what it would cost and how long it would take to
create
 Each work package is part of a control account, a
management control point for performance measurement
where scope, budget, and schedule are integrated and
compared to the earned value (see Chapter 8 for detailed
on earned value)
Copyright 2018 Schwalbe Publishing 32
 Foundation document in project management
because it provides the basis for planning and
managing project schedules, costs, resources, and
changes
 The WBS contains 100% of the deliverables (often
called “work”) of the project—not 95%, not 102%, but
100%
 Often depicted in a graphical format, similar to an
organizational chart; can also be shown in tabular
form as an indented list of elements
•3
Copyright 2018 Schwalbe Publishing 33
Copyright 2018 Schwalbe Publishing 34
Copyright 2018 Schwalbe Publishing 35
Copyright 2018 Schwalbe Publishing 36
Copyright 2018 Schwalbe Publishing 37
 If you look closely at the WBS examples shown you will
notice that there are no verbs, as verbs represent action,
and a WBS is not about action, but rather about
deliverables. As the definition of a WBS has fluctuated over
the decades, sometimes you may still come across a
definition that shows activities on the WBS.
 However, it is incorrect to show activities on the WBS,
according to PMI, so try to consistently use deliverables on
your WBS. Activities should be shown on the schedule and
not on the WBS itself.
 Several project management software packages use the
WBS to create the activities, which may also cause some
confusion. Use your judgment to decide the best way to
create a WBS and the wording on it.
•3
Copyright 2018 Schwalbe Publishing 38
 It is difficult to create a good WBS
 The project manager and the project team must decide as a
group how to organize the work and how many levels to
include in the WBS
 It is often better to focus on getting the top levels of the
WBS done well to avoid being distracted by too much detail
 Many people confuse tasks on a WBS with specifications or
think it must reflect a sequential list of steps
 You should focus on what work needs to be delivered, not
when or exactly how it will be done
Copyright 2018 Schwalbe Publishing 39
Copyright 2018 Schwalbe Publishing 40
 A WBS dictionary is a document that describes the
deliverables on the WBS in more detail
 The format can vary based on project needs
 It may also include who owns the work package,
estimated cost and schedule information, contract
information if outsourced, specific quality
requirements, technical and performance
requirements, etc.
Copyright 2018 Schwalbe Publishing 41
 Using guidelines or templates: Some organizations, like
the DOD, provide guidelines or templates for preparing
WBSs
 The analogy approach: Review WBSs of similar
projects and tailor to your project
 The top-down approach: Start with the largest items
of the project and break them down
 The bottom-up approach: Start with the specific tasks
and roll them up
 Mind-mapping approach: Mind mapping is a technique
that uses branches radiating out from a core idea to
structure thoughts and ideas
Copyright 2018 Schwalbe Publishing 42
 Healthcare projects can come in many forms. For example, a bike company, Holy
Spokes, is getting noticed in Charleston, SC. Holy Spokes along with the city of
Charleston, Medical University of South Carolina (MUSC), and The Gotcha Group
operate bikes that allow people to rent by the hour or through monthly payments.
The stakeholders were involved with approving the details for these city-share bikes.
One of the requirements was to ensure that these bikes included details specific to
Charleston.
 The project launched in May 2017. Within five months these bikes have been used
over 10,000 times just by MUSC employees and students alone. These MUSC
employees and students represent 42% of the users.
 The bikes were designed to incorporate the local culture through the pretty blue
color to the logo and even the name. Each bike is built to withstand the normal wear
and tear, and include software with live GPS tracking, solar panels, and a cost
savings application. The City wanted to promote biking as an alternative to driving to
reduce traffic, and MUSC wanted to encourage biking to improve the health of its
employees and visitors.
 The City of Charleston and MUSC are working hard to live up to their label as the
destination of choice for travelers, and having a bike-friendly city is part of that.
Although having cities with bike rental programs is not new, joint venture projects
between cities and healthcare providers such as this are uncommon.
Copyright 2018 Schwalbe Publishing 43
Copyright 2018 Schwalbe Publishing 44
Copyright 2018 Schwalbe Publishing 45
 MindView software allows you to create a WBS with a mind map. You
can access a 30-day trial of their software at www.matchware.com. You
can also watch several videos about creating a WBS using a mind map
from Matchware’s site or others. For example, Jim Franklin shows how
to use Mindview to create a WBS for a solar panel project. Jim has also
created a site called pmmapping.com with more information on using
mind maps in project management.
 Andy Kaufman, host of PeopleAndProjectsPodcast.com,
demonstrates how to engage people in creating a WBS for a vacation by
using sticky notes. Jennifer Bridges of projectmanager.com explains how
to plan projects with your team and provides tips to perfect the project
planning process by using a simple white board. See the companion site
for this text at www.intropm.com for links to these and other video
highlights.
Copyright 2018 Schwalbe Publishing 46
Copyright 2018 Schwalbe Publishing 47
WBS Item Number: 2.3.1
WBS Item Name: Compliance Policy
Requirement Trace: R12 – Enforce VAP Best Practices
Responsible Person: Danielle Scheerer, MD, Chief Quality Officer
Estimated Cost: $0, executive leadership costs not charged to the project
Estimated Duration: 3 months, due to committee schedules and approvals required
Resource Requirements: Executive Quality Oversight Committee (CQO, CNO, CMO, CMIO,
CNIO), Compliance Officer
Description: Caregivers treat patients based on their own experiences,
education, and research. However, there are many best-practices that have
been proven to be superior to those based on individual judgment as they take
into account large numbers of patients studied over extended periods of time.
Although these best practices are proven, the organizations who publish these
practices are not sitting in front of the patient and therefore do not understand
the patient as a whole. A policy must be created that encourages and holds
accountable physicians and nurses for complying with the IHI Ventilator Bundle
that has been designed and proven to reduce the incidence of VAP. The policy
must include the ability to deviate from the best practices if the caregiver
believes it is in the best interest of the patient’s health, but the policy should
also require that the caregiver documents the deviation and reasoning so that
AHS may study the patient outcomes of these patients compared to those who
follow the best practices. The policy must be co-issued by the highest level
clinicians (Chief Medical Officer and Chief Nursing Officer) and communicated,
supported, and enforced by clinical leadership.
Copyright 2018 Schwalbe Publishing 48
 Planning for integration management includes developing a project
management plan. Plans in the other knowledge areas are considered to
be subsidiary parts of the project management plan.
 Planning processes for scope management include planning scope
management, collecting requirements, defining scope, and creating a WBS
 Approaches for developing a WBS include using guidelines or templates, an
analogy approach, a top-down approach, a bottom-up approach, and mind
mapping. A WBS dictionary provides more detail on WBS items
 Samples of several planning documents are provided for the VAPR project
•4

More Related Content

What's hot

Information Technology Project Management - part 11
Information Technology Project Management - part 11Information Technology Project Management - part 11
Information Technology Project Management - part 11Rizwan Khurram
 
Basic Principles of Project Management
Basic Principles of Project ManagementBasic Principles of Project Management
Basic Principles of Project Managementdanieljohn810
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementMauro Jasse
 
Standard For Program Management Changes
Standard For Program Management ChangesStandard For Program Management Changes
Standard For Program Management Changesgryasam
 
Project time management
Project time managementProject time management
Project time managementJivan Nepali
 
Project Management Methodologies and Project Governance
Project Management Methodologies and Project GovernanceProject Management Methodologies and Project Governance
Project Management Methodologies and Project GovernancePMIUKChapter
 
Project integration management
Project integration managementProject integration management
Project integration managementEhsan Ullah
 
Project Benefits Realisation G Byatt
Project Benefits Realisation G ByattProject Benefits Realisation G Byatt
Project Benefits Realisation G ByattGareth Byatt
 
Introduction to Project Management & Planning
Introduction to Project Management & PlanningIntroduction to Project Management & Planning
Introduction to Project Management & PlanningShikhaj Jakhete
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overruneSAT Journals
 
Program management - Fundamentals
Program management   - FundamentalsProgram management   - Fundamentals
Program management - FundamentalsJulen Mohanty
 
Project management
Project managementProject management
Project managementJay Raval
 
Role and Responsibilities of Project Manager
Role and Responsibilities of Project ManagerRole and Responsibilities of Project Manager
Role and Responsibilities of Project Managerkanti choudhary
 
Project management
Project managementProject management
Project managementAhmed Said
 

What's hot (20)

Information Technology Project Management - part 11
Information Technology Project Management - part 11Information Technology Project Management - part 11
Information Technology Project Management - part 11
 
1. project integration management
1. project integration management1. project integration management
1. project integration management
 
Basic Principles of Project Management
Basic Principles of Project ManagementBasic Principles of Project Management
Basic Principles of Project Management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Standard For Program Management Changes
Standard For Program Management ChangesStandard For Program Management Changes
Standard For Program Management Changes
 
Project closeout-report
Project closeout-reportProject closeout-report
Project closeout-report
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project management
 
Project time management
Project time managementProject time management
Project time management
 
Project Management Methodologies and Project Governance
Project Management Methodologies and Project GovernanceProject Management Methodologies and Project Governance
Project Management Methodologies and Project Governance
 
Project integration management
Project integration managementProject integration management
Project integration management
 
Project Benefits Realisation G Byatt
Project Benefits Realisation G ByattProject Benefits Realisation G Byatt
Project Benefits Realisation G Byatt
 
Introduction to Project Management & Planning
Introduction to Project Management & PlanningIntroduction to Project Management & Planning
Introduction to Project Management & Planning
 
Project Charter Guide
Project Charter GuideProject Charter Guide
Project Charter Guide
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
Program management - Fundamentals
Program management   - FundamentalsProgram management   - Fundamentals
Program management - Fundamentals
 
How to do a Project Audit
How to do a Project AuditHow to do a Project Audit
How to do a Project Audit
 
Project Implementation.pptx
Project Implementation.pptxProject Implementation.pptx
Project Implementation.pptx
 
Project management
Project managementProject management
Project management
 
Role and Responsibilities of Project Manager
Role and Responsibilities of Project ManagerRole and Responsibilities of Project Manager
Role and Responsibilities of Project Manager
 
Project management
Project managementProject management
Project management
 

Similar to HM 418 2e hcpm04 (1)

م.58-مبادرة#تواصل_تطوير-د.وليد محفوظ-إدارة مشاركة المعنيين في مشاريع وبرامج ا...
م.58-مبادرة#تواصل_تطوير-د.وليد محفوظ-إدارة مشاركة المعنيين في مشاريع وبرامج ا...م.58-مبادرة#تواصل_تطوير-د.وليد محفوظ-إدارة مشاركة المعنيين في مشاريع وبرامج ا...
م.58-مبادرة#تواصل_تطوير-د.وليد محفوظ-إدارة مشاركة المعنيين في مشاريع وبرامج ا...Egyptian Engineers Association
 
Running Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docx
Running Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docxRunning Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docx
Running Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docxtodd581
 
UNIT-01_Fundamentals_ Project management
UNIT-01_Fundamentals_ Project managementUNIT-01_Fundamentals_ Project management
UNIT-01_Fundamentals_ Project managementsdbhosale860
 
10 Project Management Mistakes
10 Project Management Mistakes10 Project Management Mistakes
10 Project Management MistakesOrangescrum
 
Module Three Project Scope, Planning, and Time Management.docx
Module Three Project Scope, Planning, and Time Management.docxModule Three Project Scope, Planning, and Time Management.docx
Module Three Project Scope, Planning, and Time Management.docxgilpinleeanna
 
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docx
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docxPROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docx
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docxwkyra78
 
Engineering Project Management
Engineering Project Management Engineering Project Management
Engineering Project Management Nzar Braim
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Renee Jones
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1Imoh Etuk
 
4. Proper planning of a software project unless the project is trivia.pdf
4. Proper planning of a software project unless the project is trivia.pdf4. Proper planning of a software project unless the project is trivia.pdf
4. Proper planning of a software project unless the project is trivia.pdfeyevisioncare1
 
Project Life Cycle final.pptx
Project Life Cycle final.pptxProject Life Cycle final.pptx
Project Life Cycle final.pptxPranshiGoyal2
 
Successful Project Planning - Drasvin
Successful Project Planning - DrasvinSuccessful Project Planning - Drasvin
Successful Project Planning - DrasvinDrasvin Cheowtirakul
 
Project management practices the criteria for success or failure
Project management practices the criteria for success or failureProject management practices the criteria for success or failure
Project management practices the criteria for success or failureTa Ngoc
 
5-PHASE PROJECT MANAGEMENT
5-PHASE PROJECT MANAGEMENT5-PHASE PROJECT MANAGEMENT
5-PHASE PROJECT MANAGEMENTClaire Webber
 
Planning process group
Planning process groupPlanning process group
Planning process groupMudassir Iqbal
 
CH-2.2 Developing Project Charter and Baseline Project Plan.ppt
CH-2.2 Developing Project Charter and Baseline Project Plan.pptCH-2.2 Developing Project Charter and Baseline Project Plan.ppt
CH-2.2 Developing Project Charter and Baseline Project Plan.pptamanuel236786
 
MODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptxMODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptxMdAliMujawar1
 
romi-pm-03-process-april2013.pptx
romi-pm-03-process-april2013.pptxromi-pm-03-process-april2013.pptx
romi-pm-03-process-april2013.pptxummi1206
 

Similar to HM 418 2e hcpm04 (1) (20)

م.58-مبادرة#تواصل_تطوير-د.وليد محفوظ-إدارة مشاركة المعنيين في مشاريع وبرامج ا...
م.58-مبادرة#تواصل_تطوير-د.وليد محفوظ-إدارة مشاركة المعنيين في مشاريع وبرامج ا...م.58-مبادرة#تواصل_تطوير-د.وليد محفوظ-إدارة مشاركة المعنيين في مشاريع وبرامج ا...
م.58-مبادرة#تواصل_تطوير-د.وليد محفوظ-إدارة مشاركة المعنيين في مشاريع وبرامج ا...
 
Running Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docx
Running Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docxRunning Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docx
Running Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docx
 
HM 418 2e hcpm09
HM 418 2e hcpm09HM 418 2e hcpm09
HM 418 2e hcpm09
 
UNIT-01_Fundamentals_ Project management
UNIT-01_Fundamentals_ Project managementUNIT-01_Fundamentals_ Project management
UNIT-01_Fundamentals_ Project management
 
10 Project Management Mistakes
10 Project Management Mistakes10 Project Management Mistakes
10 Project Management Mistakes
 
Module Three Project Scope, Planning, and Time Management.docx
Module Three Project Scope, Planning, and Time Management.docxModule Three Project Scope, Planning, and Time Management.docx
Module Three Project Scope, Planning, and Time Management.docx
 
APM-BoK.pdf
APM-BoK.pdfAPM-BoK.pdf
APM-BoK.pdf
 
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docx
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docxPROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docx
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docx
 
Engineering Project Management
Engineering Project Management Engineering Project Management
Engineering Project Management
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1
 
4. Proper planning of a software project unless the project is trivia.pdf
4. Proper planning of a software project unless the project is trivia.pdf4. Proper planning of a software project unless the project is trivia.pdf
4. Proper planning of a software project unless the project is trivia.pdf
 
Project Life Cycle final.pptx
Project Life Cycle final.pptxProject Life Cycle final.pptx
Project Life Cycle final.pptx
 
Successful Project Planning - Drasvin
Successful Project Planning - DrasvinSuccessful Project Planning - Drasvin
Successful Project Planning - Drasvin
 
Project management practices the criteria for success or failure
Project management practices the criteria for success or failureProject management practices the criteria for success or failure
Project management practices the criteria for success or failure
 
5-PHASE PROJECT MANAGEMENT
5-PHASE PROJECT MANAGEMENT5-PHASE PROJECT MANAGEMENT
5-PHASE PROJECT MANAGEMENT
 
Planning process group
Planning process groupPlanning process group
Planning process group
 
CH-2.2 Developing Project Charter and Baseline Project Plan.ppt
CH-2.2 Developing Project Charter and Baseline Project Plan.pptCH-2.2 Developing Project Charter and Baseline Project Plan.ppt
CH-2.2 Developing Project Charter and Baseline Project Plan.ppt
 
MODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptxMODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptx
 
romi-pm-03-process-april2013.pptx
romi-pm-03-process-april2013.pptxromi-pm-03-process-april2013.pptx
romi-pm-03-process-april2013.pptx
 

More from BealCollegeOnline (20)

BA650 Week 3 Chapter 3 "Why Change? contemporary drivers and pressures
BA650 Week 3 Chapter 3 "Why Change? contemporary drivers and pressuresBA650 Week 3 Chapter 3 "Why Change? contemporary drivers and pressures
BA650 Week 3 Chapter 3 "Why Change? contemporary drivers and pressures
 
BIO420 Chapter 25
BIO420 Chapter 25BIO420 Chapter 25
BIO420 Chapter 25
 
BIO420 Chapter 24
BIO420 Chapter 24BIO420 Chapter 24
BIO420 Chapter 24
 
BIO420 Chapter 23
BIO420 Chapter 23BIO420 Chapter 23
BIO420 Chapter 23
 
BIO420 Chapter 20
BIO420 Chapter 20BIO420 Chapter 20
BIO420 Chapter 20
 
BIO420 Chapter 18
BIO420 Chapter 18BIO420 Chapter 18
BIO420 Chapter 18
 
BIO420 Chapter 17
BIO420 Chapter 17BIO420 Chapter 17
BIO420 Chapter 17
 
BIO420 Chapter 16
BIO420 Chapter 16BIO420 Chapter 16
BIO420 Chapter 16
 
BIO420 Chapter 13
BIO420 Chapter 13BIO420 Chapter 13
BIO420 Chapter 13
 
BIO420 Chapter 12
BIO420 Chapter 12BIO420 Chapter 12
BIO420 Chapter 12
 
BIO420 Chapter 09
BIO420 Chapter 09BIO420 Chapter 09
BIO420 Chapter 09
 
BIO420 Chapter 08
BIO420 Chapter 08BIO420 Chapter 08
BIO420 Chapter 08
 
BIO420 Chapter 06
BIO420 Chapter 06BIO420 Chapter 06
BIO420 Chapter 06
 
BIO420 Chapter 05
BIO420 Chapter 05BIO420 Chapter 05
BIO420 Chapter 05
 
BIO420 Chapter 04
BIO420 Chapter 04BIO420 Chapter 04
BIO420 Chapter 04
 
BIO420 Chapter 03
BIO420 Chapter 03BIO420 Chapter 03
BIO420 Chapter 03
 
BIO420 Chapter 01
BIO420 Chapter 01BIO420 Chapter 01
BIO420 Chapter 01
 
BA350 Katz esb 6e_chap018_ppt
BA350 Katz esb 6e_chap018_pptBA350 Katz esb 6e_chap018_ppt
BA350 Katz esb 6e_chap018_ppt
 
BA350 Katz esb 6e_chap017_ppt
BA350 Katz esb 6e_chap017_pptBA350 Katz esb 6e_chap017_ppt
BA350 Katz esb 6e_chap017_ppt
 
BA350 Katz esb 6e_chap016_ppt
BA350 Katz esb 6e_chap016_pptBA350 Katz esb 6e_chap016_ppt
BA350 Katz esb 6e_chap016_ppt
 

Recently uploaded

Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfadityarao40181
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxJiesonDelaCerna
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 

Recently uploaded (20)

Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdf
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptx
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 

HM 418 2e hcpm04 (1)

  • 1. Note: See the text itself for full citations.
  • 2. Copyright 2018 Schwalbe Publishing 2  Describe the importance of creating plans to guide project execution  List several planning processes and outputs for project integration and scope management  Discuss the project integration management planning process and explain the purpose and contents of a project management plan  Describe the project scope management planning processes
  • 3. Copyright 2018 Schwalbe Publishing 3  Explain the purpose and contents of a scope management plan and requirements management plan  Discuss different ways to collect project requirements  Create a scope statement to define project scope  Develop a work breakdown structure (WBS) and a WBS dictionary to clearly describe all of the work required for a project 3
  • 4. Copyright 2018 Schwalbe Publishing 4  Many people have heard the following sayings: ◦ If you fail to plan, you plan to fail. ◦ If you don’t know where you’re going, any road will take you there. ◦ What gets measured gets managed.  Successful project managers know how important it is to develop, refine, and follow plans to meet project goals  People are more likely to perform well if they know what they are supposed to do and when 4
  • 5. Copyright 2018 Schwalbe Publishing 5  Planning is often the most difficult and unappreciated process in project management  Often, people do not want to take the time to plan well, but theory and practice show that good planning is crucial to good execution  The main purpose of project planning is to guide project execution, so project plans must be realistic and useful 5
  • 6. Copyright 2018 Schwalbe Publishing 6  Many people make great plans, but they don’t realize the importance of using those plans as their roadmap. For example, a transplant nurse, Sally (BSN, MSN), had moved up to the position as the lead technical person in her department and was named the project manager for a new transplant implementation. Because of her inexperience managing projects, the PMO Director, Mike “Mikey” Matthews, was asked to help her plan the project. Mikey set up a meeting with the Sally for the following week, and she studied everything she could find about project management over the weekend.  The following week Mikey and Sally sat down with her team and developed a project management plan, including schedules, budgets, and other required documents. It seemed like a great start. Sally thanked Mikey, and he went back to his other projects while Sally’s project chugged along, appearing in status reports to be doing fine. After about three months someone approached Mikey and asked if he would attend an upcoming transplant project meeting.  The meeting started off great, with each team member giving their updates. One by one they each told the nurse project manager of obstacles, setbacks, lack of stakeholder participation, and unclear requirements from users. Sally listened to each person intently, jotted notes, and then said, “That’s great. Thanks everyone. I’ll see you next week!” The meeting ended. Just like that! After the room cleared Mikey asked Sally how the project was going, and after a slight pause, she replied that it was going very well. Mikey then asked where they were in the schedule. Sally paused again, this time for what seemed like minutes, looking back at Mikey blankly. He then rephrased the question, “What activity are you working on right now, as a team? Are you ahead of schedule? Behind schedule? You know, compared to the schedule we laid out three months ago.” After another slight pause, Sally replied with a very simple and honest reply: “You didn’t say that we needed to use that schedule again.”  Sally had never considered the plan to be her roadmap, and as a result the project ended up being 100% over schedule and nearly that much over budget.
  • 7. Copyright 2018 Schwalbe Publishing 7  Planning is often the most difficult and unappreciated process in project management  Often, people do not want to take the time to plan well, but theory and practice show that good planning is crucial to good execution  The main purpose of project planning is to guide project execution, so project plans must be realistic and useful 7
  • 8. Copyright 2018 Schwalbe Publishing 8  Top managers often require a plan, but then no one tracks whether the plan was followed  One project manager said he would meet with each project team leader within two months to review their project plans. Two months later, the project manager had still not met with over half of the project team leaders  Why should project team members feel obligated to follow their own plans when the project manager obviously does not follow his? 8
  • 9. Copyright 2018 Schwalbe Publishing 99 Knowledge area Planning process Outputs Project integration management Develop project management plan Project management plan Project scope management Plan scope management Collect requirements Define scope Create WBS Scope management plan Requirements management plan Requirements documentation Requirements traceability matrix Project scope statement Project documents updates Scope baseline Project documents updates
  • 10. Copyright 2018 Schwalbe Publishing 10  Project integration management involves coordinating all the project management knowledge areas throughout a project’s life span  The main planning output is a project management plan 10
  • 11. Copyright 2018 Schwalbe Publishing 11  A project management plan is a document used to integrate and coordinate all project planning documents and to help guide a project’s execution, monitoring and control, and closure  Plans created in the other knowledge areas are subsidiary parts of the overall project management plan and provide more detailed information about that knowledge area  Project management plans facilitate communication among stakeholders and provide a baseline for progress measurement and project control ◦ A baseline is a starting point, a measurement, or an observation that is documented so that it can be used for future comparison 11
  • 12. Copyright 2018 Schwalbe Publishing 12  The Berlin Brandenburg Airport was supposed to become the busiest airport in Germany. It was projected to have 45 million passengers traveling through annually. The preplanning phase took 15 years and the approved budget for the airport was €5.4 billion. Construction began in 2006 and it was scheduled to take 5 years to build. The opening day was set for October 30, 2011, but 6 years later the airport is still not open. The project is over budget with the latest estimate totaling €7.9 billion.  There are several reasons why that this project got off track. Correct information about the project were not communicated. The city’s mayor, and project sponsor, was accused of ignoring the problems during construction and acting as if the project was going as planned. In 2013, two years after the project’s scheduled finish date, the mayor was removed from his position.  Another reason this project was not finished on-time was due to the scope changes and the unfortunate scope creep. One of the key stakeholders wanted to increase the size of the airport. There were numerous quality issues that were found as well. Of the 66,500 defects that were found, 34,000 were found to be “significant” and 5,845 were “critical”. These critical defects were issues such as an alarm system that wasn’t built to appropriate building code.  All of these factors have pushed this project’s timeline back further and further. As a project manager it is important to ensure proper communication, prevent scope creep, and confirm quality checks
  • 13. Copyright 2018 Schwalbe Publishing 13•1 Source: Project Management Institute, Inc., A Guide to the Project Management Body of Knowledge (PMBOK Guide) – Sixth Edition (2017). Project Management Plan Project Documents 1. Scope management plan 2. Requirements management plan 3. Schedule management plan 4. Cost management plan 5. Quality management plan 6. Resource management plan 7. Communications management plan 8. Risk management plan 9. Procurement management plan 10. Stakeholder engagement plan 11. Change management plan 12. Configuration management plan 13. Scope baseline 14. Schedule baseline 15. Cost baseline 16. Performance measurement baseline 17. Project life cycle description 18. Development approach 1. Activity attributes 2. Activity list 3. Assumption log 4. Basis of estimates 5. Change log 6. Cost estimates 7. Cost forecasts 8. Duration estimates 9. Issue log 10. Lessons learned register 11. Milestone list 12. Physical resource assignments 13. Project calendars 14. Project communications 15. Project schedule 16. Project schedule network diagram 17. Project scope statement 18. Quality control measurements 19. Quality metrics 1. Quality report 2. Requirements documentation 3. Requirements traceability matrix 4. Resource assignments 5. Resource breakdown structure 6. Resource calendars 7. Resource requirements 8. Risk register 9. Risk report 10. Schedule data 11. Schedule forecasts 12. Stakeholder register 13. Team charter 14. Team resource assignments 15. Test and evaluation documents
  • 14. Copyright 2018 Schwalbe Publishing 14  Project management plans should be dynamic, flexible, and receptive to change when the environment or project changes  Just as projects are unique, so are project plans. ◦ For a small project involving a few people over a couple of months, a project charter, team contract, scope statement, and Gantt chart might be the only project planning documents needed; there would not be a need for a separate project management plan ◦ A large project involving 100 people over three years would benefit from having a detailed project management plan and separate plans for each knowledge area  It is important to tailor all planning documentation to fit the needs of specific projects 14
  • 15. Copyright 2018 Schwalbe Publishing 15  Introduction/overview of the project  Project organization  Management and technical processes (including project lifecycle description and development approach, as applicable)  Work to be performed (scope)  Schedule information  Budget information  References to other project planning documents 15
  • 16. Copyright 2018 Schwalbe Publishing 1616 PURPOSE VAP costs AHS over $3.6M per year in costs, and puts our patients at risk for severe and sometimes fatal consequences. VAP is considered preventable by CMS and has worked with the Institutes for Healthcare Improvement (IHI) to develop a set of best practices that, if followed, has demonstrated a reduction of VAP by 50% in other healthcare facilities. AHS will implement a system to collect and report compliance with the best practices to better manage VAP. PROJECT ORGANIZATION The basic organization of the project is provided in Figure 1. The project sponsor, Marilyn Shoemaker, RN, PhD, will have the final say on major decisions, with consultation from the project steering committee and project champions, Casey Lidwell and Dr. Danielle Scheerer. The project sponsor should have time to thoroughly review important project information and provide timely feedback to the project manager. PROJECT GOVERNANCE 1. Management Review Process: The project steering committee will meet at least monthly to provide inputs and review progress on this project. 2. Progress Measurement Process: The project steering committee will review project progress during project review meetings, and they can also review information as needed by viewing reports on the enterprise project management system. 3. Change Approval Process: See Attachment 1 based on AHS standards. VAPR has been broken down into two phases. The first phase is a proof of concept and the data collection/reporting system and will be managed by Jeff Birdwell, PMP from the PMO’s office. The second phase will be managed by Pat Wager, RN from analytics.
  • 17. Copyright 2018 Schwalbe Publishing 17  Project scope management involves defining and controlling what work is or is not included in a project  The main planning tasks include planning scope management, collecting requirements, defining scope, and creating the WBS  The main documents produced are requirements documents, a requirements management plan, a requirements traceability matrix, and a scope baseline, which is composed of an approved scope statement, a WBS, and a WBS dictionary
  • 18. Copyright 2018 Schwalbe Publishing 18  The purpose of the process of planning scope management is to determine how the project scope will be defined, validated, and controlled. ◦ Validation means formal acceptance of deliverables by the customer and other identified stakeholders ◦ In contrast, verification (done as part of controlling quality) means the deliverable complies with a regulation, requirement, specification, or imposed condition  Project teams usually have several meetings with key stakeholders and experts to help them develop a scope management plan and requirements management plan.
  • 19. Copyright 2018 Schwalbe Publishing 19  Preparing a detailed project scope statement  Creating, maintaining, and approving the WBS  Obtaining acceptance of the completed project deliverables  Controlling how requests for changes to the project scope statement will be processed •1
  • 20. Copyright 2018 Schwalbe Publishing 20  The PMBOK® Guide – Sixth Edition, defines a requirement as “a condition or capability that is necessary to be present in a product, service, or result to satisfy a business need.”  A requirements management plan describes how project requirements will be analyzed, documented, and managed. •2
  • 21. Copyright 2018 Schwalbe Publishing 21 Requirements Management Plan Version 1.0 May 29, 20xx PROJECT TITLE: VENTILATOR ASSOCIATED PNEUMONIA (VAP) REDUCTION – “VAPR” Planning, tracking, and reporting requirements Information provided in the business case and project charter will provide valuable information in determining requirements for this project, as will the IHI Ventilator Bundle itself. All requirements will be documented within the project management system and will be reviewed for progress weekly as part of the regular project meetings. Each requirement will be assigned a customer owner, designated initially as the provider of the requirement, but in some cases as the staff member who is considered the expert on the requirement itself. Performing configuration management activities Requirements can be identified through a variety of methods. Executive clinical leadership will be interviewed individually, committees such as the Med Exec and Clinical Quality Improvement Council will be asked for requirements through our sponsor, and our champions will conduct focus groups with their peers and customers to gather input. Requirements will also be extracted from the IHI Ventilator Bundle, and both CMS and Joint Commission measures will be reviewed for additional requirements. Appropriate project stakeholders will analyze, authorize, track, and report changes to requirements. The project manager must be informed in advance of potential changes to requirements and be involved in the decision process to approve those changes. Any change that will impact the project’s cost by more than 2% or extend the schedule past the identified go live date must be approved by the project steering committee.
  • 22. Copyright 2018 Schwalbe Publishing 22  Emerging Health started using a tool by IBM called Rational DOORS to help manage requirements. As a result, they saw a 69 percent reduction in the cost of test preparation, testing, and rework in the software development process and a 25 percent reduction in the time it took to customize their Clinical Looking Glass application for unique client requirements.  According to McCroskey, “Time to market is always a critical benchmark, but especially so in the fast-paced healthcare industry. Because our industry is so competitive, being able to deliver the product faster enhances our reputation and the confidence our customers have in us. Faster time to market is vital to our success, and we’ve now achieved that with the more responsive environment Rational DOORS has allowed us to establish.” •2
  • 23. Copyright 2018 Schwalbe Publishing 23 Req ID Name Category Source Status Comments R26 Identify source systems that document compliance with the IHI vent bundle Technical Chief Medical Information Officer Complete Three sources were identified: ClinDoc, Pharmacy Administration, and RT Documentation. R91 Online report to indicate compliance, by patient, with IHI bundle Analytics Chief Quality Officer Not started Data must be no more than 6 hours old. R123 Design new ventilator protocol for nursing Clinical Workflow Chief Nursing Officer Not started Must be reviewed and approved by the nursing oversight committee.
  • 24. Copyright 2018 Schwalbe Publishing 24  Good scope definition is crucial to project success because it ◦ Helps improve the accuracy of time, cost, and resource estimates ◦ Defines a baseline for performance measurement and project control ◦ Aids in communicating clear work responsibilities  The project charter, requirements documentation, and organizational process assets (i.e. policies and procedures related to project management, past project files, and lessons- learned reports from previous, similar projects) are all inputs for creating the initial scope statement  Contents of a scope statement vary, but it should include a product scope description, product user acceptance criteria, and detailed information on all project deliverables
  • 25. Copyright 2018 Schwalbe Publishing 25  Good scope definition is crucial to project success because it ◦ Helps improve the accuracy of time, cost, and resource estimates ◦ Defines a baseline for performance measurement and project control ◦ Aids in communicating clear work responsibilities  A project scope statement describes product characteristics and requirements, user acceptance criteria, and deliverables.  Work that is not included in the scope statement should not be done, and you can explicitly state what is out of scope for the project under a section called project exclusions.
  • 26. Copyright 2018 Schwalbe Publishing 26 Product Characteristics and Requirements This project will introduce the IHI Ventilator Bundle (best practices) into our AHS clinical protocols and workflows. We must identify which, if any, AHS system currently collects data that would indicate compliance with the five elements in the bundle. If the data is not currently collected electronically at AHS, a data collection point must be identified. All data must be integrated into a single online report so that they may correct the patient’s care during the required time period. To minimize the amount of corrective actions required, the nursing and respiratory therapy workflows will be modified to include the best practices, and the ventilator protocols will be modified to automatically include orders for the bundle elements. The following best practices are included in the IHI Ventilator Bundle:  Patient Head of Bed (HOB) elevation, 30 to 45 degrees  Sedation vacation every 24 hours  Daily oral/mouth care with Chlorhexidine  Venous Thrombosis Embolism (VTE) prophylaxis  Peptic ulcer prophylaxis Out of Scope This project will not consider any other patient care, best practices, evidenced based medicine, or other patient care improvements discovered during the project work. Any additional potential patient care improvement projects will be submitted to the project request system and reviewed, approved, and managed separately based on their own merits.
  • 27. Copyright 2018 Schwalbe Publishing 27 Product User Acceptance Criteria This project will be considered successful if the following measures are met:  Project completed by the end of the next fiscal year (June 30)  Project completed for $980,000 or less  VAP incidence is reduced by 25% within 90 days of go live  VAP incidence rate is reduced by 35% within 180 days of go live  VAP incidence rate is reduced by 50% within 270 days of go live Product-Oriented Deliverables 1. Data Interfaces from source systems, including registration, bed management, clinical documentation, and respiratory therapy documentation systems. 2. Database to store IHI bundle data elements collected on AHS patients. 3. Online report to present IHI bundle compliance to caregivers using standard AHS reporting tools. 4. Convenient and timely report delivery method, including availability on mobile devices. 5. Modified clinical workflows to integrate IHI Ventilator Bundle best practices. Modified ventilator protocols to integrate IHI Ventilator Bundle best practices.
  • 28. Copyright 2018 Schwalbe Publishing 28  The project team should update the project scope statement as new information becomes available  Name different iterations of the scope statement Version 1.0, Version 2.0, etc.  A good, up-to-date scope statement helps prevent scope creep, which is the tendency for project scope to continually increase
  • 29. Copyright 2018 Schwalbe Publishing 29
  • 30. Copyright 2018 Schwalbe Publishing 30  A work breakdown structure (WBS) is a deliverable- oriented grouping of the work involved in a project that defines the total scope of the project  The WBS is a document that breaks all the work required for the project into discrete deliverables, and groups them into a logical hierarchy  Often shown in two different forms: ◦ Graphical or chart form ◦ Tabular or list form
  • 31. Copyright 2018 Schwalbe Publishing 31  A work package is a deliverable at the lowest level of the WBS, where it can be appropriately assigned to and managed by a single accountable person  Each work package should be defined in enough detail to estimate what it would cost and how long it would take to create  Each work package is part of a control account, a management control point for performance measurement where scope, budget, and schedule are integrated and compared to the earned value (see Chapter 8 for detailed on earned value)
  • 32. Copyright 2018 Schwalbe Publishing 32  Foundation document in project management because it provides the basis for planning and managing project schedules, costs, resources, and changes  The WBS contains 100% of the deliverables (often called “work”) of the project—not 95%, not 102%, but 100%  Often depicted in a graphical format, similar to an organizational chart; can also be shown in tabular form as an indented list of elements •3
  • 33. Copyright 2018 Schwalbe Publishing 33
  • 34. Copyright 2018 Schwalbe Publishing 34
  • 35. Copyright 2018 Schwalbe Publishing 35
  • 36. Copyright 2018 Schwalbe Publishing 36
  • 37. Copyright 2018 Schwalbe Publishing 37  If you look closely at the WBS examples shown you will notice that there are no verbs, as verbs represent action, and a WBS is not about action, but rather about deliverables. As the definition of a WBS has fluctuated over the decades, sometimes you may still come across a definition that shows activities on the WBS.  However, it is incorrect to show activities on the WBS, according to PMI, so try to consistently use deliverables on your WBS. Activities should be shown on the schedule and not on the WBS itself.  Several project management software packages use the WBS to create the activities, which may also cause some confusion. Use your judgment to decide the best way to create a WBS and the wording on it. •3
  • 38. Copyright 2018 Schwalbe Publishing 38  It is difficult to create a good WBS  The project manager and the project team must decide as a group how to organize the work and how many levels to include in the WBS  It is often better to focus on getting the top levels of the WBS done well to avoid being distracted by too much detail  Many people confuse tasks on a WBS with specifications or think it must reflect a sequential list of steps  You should focus on what work needs to be delivered, not when or exactly how it will be done
  • 39. Copyright 2018 Schwalbe Publishing 39
  • 40. Copyright 2018 Schwalbe Publishing 40  A WBS dictionary is a document that describes the deliverables on the WBS in more detail  The format can vary based on project needs  It may also include who owns the work package, estimated cost and schedule information, contract information if outsourced, specific quality requirements, technical and performance requirements, etc.
  • 41. Copyright 2018 Schwalbe Publishing 41  Using guidelines or templates: Some organizations, like the DOD, provide guidelines or templates for preparing WBSs  The analogy approach: Review WBSs of similar projects and tailor to your project  The top-down approach: Start with the largest items of the project and break them down  The bottom-up approach: Start with the specific tasks and roll them up  Mind-mapping approach: Mind mapping is a technique that uses branches radiating out from a core idea to structure thoughts and ideas
  • 42. Copyright 2018 Schwalbe Publishing 42  Healthcare projects can come in many forms. For example, a bike company, Holy Spokes, is getting noticed in Charleston, SC. Holy Spokes along with the city of Charleston, Medical University of South Carolina (MUSC), and The Gotcha Group operate bikes that allow people to rent by the hour or through monthly payments. The stakeholders were involved with approving the details for these city-share bikes. One of the requirements was to ensure that these bikes included details specific to Charleston.  The project launched in May 2017. Within five months these bikes have been used over 10,000 times just by MUSC employees and students alone. These MUSC employees and students represent 42% of the users.  The bikes were designed to incorporate the local culture through the pretty blue color to the logo and even the name. Each bike is built to withstand the normal wear and tear, and include software with live GPS tracking, solar panels, and a cost savings application. The City wanted to promote biking as an alternative to driving to reduce traffic, and MUSC wanted to encourage biking to improve the health of its employees and visitors.  The City of Charleston and MUSC are working hard to live up to their label as the destination of choice for travelers, and having a bike-friendly city is part of that. Although having cities with bike rental programs is not new, joint venture projects between cities and healthcare providers such as this are uncommon.
  • 43. Copyright 2018 Schwalbe Publishing 43
  • 44. Copyright 2018 Schwalbe Publishing 44
  • 45. Copyright 2018 Schwalbe Publishing 45  MindView software allows you to create a WBS with a mind map. You can access a 30-day trial of their software at www.matchware.com. You can also watch several videos about creating a WBS using a mind map from Matchware’s site or others. For example, Jim Franklin shows how to use Mindview to create a WBS for a solar panel project. Jim has also created a site called pmmapping.com with more information on using mind maps in project management.  Andy Kaufman, host of PeopleAndProjectsPodcast.com, demonstrates how to engage people in creating a WBS for a vacation by using sticky notes. Jennifer Bridges of projectmanager.com explains how to plan projects with your team and provides tips to perfect the project planning process by using a simple white board. See the companion site for this text at www.intropm.com for links to these and other video highlights.
  • 46. Copyright 2018 Schwalbe Publishing 46
  • 47. Copyright 2018 Schwalbe Publishing 47 WBS Item Number: 2.3.1 WBS Item Name: Compliance Policy Requirement Trace: R12 – Enforce VAP Best Practices Responsible Person: Danielle Scheerer, MD, Chief Quality Officer Estimated Cost: $0, executive leadership costs not charged to the project Estimated Duration: 3 months, due to committee schedules and approvals required Resource Requirements: Executive Quality Oversight Committee (CQO, CNO, CMO, CMIO, CNIO), Compliance Officer Description: Caregivers treat patients based on their own experiences, education, and research. However, there are many best-practices that have been proven to be superior to those based on individual judgment as they take into account large numbers of patients studied over extended periods of time. Although these best practices are proven, the organizations who publish these practices are not sitting in front of the patient and therefore do not understand the patient as a whole. A policy must be created that encourages and holds accountable physicians and nurses for complying with the IHI Ventilator Bundle that has been designed and proven to reduce the incidence of VAP. The policy must include the ability to deviate from the best practices if the caregiver believes it is in the best interest of the patient’s health, but the policy should also require that the caregiver documents the deviation and reasoning so that AHS may study the patient outcomes of these patients compared to those who follow the best practices. The policy must be co-issued by the highest level clinicians (Chief Medical Officer and Chief Nursing Officer) and communicated, supported, and enforced by clinical leadership.
  • 48. Copyright 2018 Schwalbe Publishing 48  Planning for integration management includes developing a project management plan. Plans in the other knowledge areas are considered to be subsidiary parts of the project management plan.  Planning processes for scope management include planning scope management, collecting requirements, defining scope, and creating a WBS  Approaches for developing a WBS include using guidelines or templates, an analogy approach, a top-down approach, a bottom-up approach, and mind mapping. A WBS dictionary provides more detail on WBS items  Samples of several planning documents are provided for the VAPR project •4