SlideShare a Scribd company logo
1 of 32
The Kansas
City Hyatt
Regency
Walkway
Collapse
“The Worst Structural
Disaster In the United States”
BY:
Arpit Modh
(16BCH035)
B.Tech Chemical
Nirma University,
Ahmedabad.
WHERE: Kansas City, Missouri
DATE: July 17, 1981
3rd
Floor Walkway Still Intact
• Two Walkways
Collapsed
• 114 People Lost
Their Life
• Failure of Hanger
Rod Connection
(4th Floor)
Kansas City Hyatt
July 17, 1981
Hotel Features
• The hotel had a grand lobby which featured a multistory
atrium crossed by three concrete walkways on the second,
third and fourth floors
• The hotel advertised to have many parties and events
Entrance to Hotel and Atrium
Kansas City Hyatt
Entranc
e
Hyatt General Layout
Background Of Walkway
• July 1980 – Most Modern Hotel in Kansas City finished.
• Consisted of 3 Buildings, 2 were connected by 3 walkways.
Tea-Dance Party Leads to
Disaster
• A party was held in the lobby
• Over 2,000 people were in attendance
• People crowded the walkways and the lobby below to watch the
dance competition
• The excess weight caused the fourth floor walkway to fall onto the
second floor walkway and both walkways collapsed onto the
crowded first floor
• The collapse left 114 dead and more than 200 injured
• This was the United States’ most devastating structural failure of the
time
Design Problems
• Havens proposed the modified design to simplify the assembly task
and to eliminate the need to thread the entire length of the rods
• However, the change in the design doubled the stress put forth on
the nut which was under the fourth floor beam and with the
change the nut had to support the weight of two walkways
instead of just one
• “The ultimate capacity actually available using the original
connection detail would have been approximately 60% of that
expected of a connection designed in accordance with AISC
Specifications” according to the National Building Specifications
On a preliminary design a note was made that the
hanging rods needed to have strength of 413MPa
but that was left out of the final design and so the
fabricator used hanger rods with only 248MPa pf
strength.
Walkway’s Original Design
beams as intermediate supports
hole at both ends of Flanges
aded single rod
Hanger for 2nd
and 4th
floor walkways (3rd
floor
alkway was separate entity)
Walkway as Constructed
•4th
floor box beams:
-Ends had 2 holes
-Outer hole connected to ceiling
-2 lower rods went through
inner holes to support second
floor walkway
Original Design Modified Design (was used)
The 2nd
and 4th
floor
walkways were
originally supposed to be
suspended
from the same rod and
held in place by nuts
The fabricator had
modified the design to use
two hanging rods and the
engineers approved the
change without checking
it
The hanger rod threads, washer andThe hanger rod threads, washer and
supporting nutsupporting nut
Note: the deformation in the washer caused the beam to slipNote: the deformation in the washer caused the beam to slip
CLOSE-UPS OF
SOME OF
THE 4TH
FLOOR
BEAMS
Why Did It Happen?
Combination of :Personnel
Errors
A. Design Deficiencies
B. Inadequate Oversight &
Review Process
C. Missed opportunities to
discover error
D. Poor Communication
Factors That Contributed to the
Collapse
• Fast Track Process
 Architectural design changes & conceptual re-designs
 Drafting Errors
 Checking errors-Shop Drawings
 Invalid initial design concept of hanger
Senior engineer personnel changes
 Phone changes w/o follow-up by detailer or engineer in writing
•Fabricators in-house engineer transferred fabricator’s partial shop
dwgs to outside firm who assumed connection was designed
•Engineers technician, checked piece size but not connection. (Not
Drawn or submitted)
•Outside Peer Review didn’t check
shop dwg
Factors (Continued)
•“Design Check” questions answers not verified
•In-house design check questions following atrium collapse were
not verified. No Follow Up
•Poor Testing & Inspection
Factors (Continued)
•No Structural Site Representation (Refused several times)
•Engineer Relied (ASSUMED) based on past projects on design of
connections by Fabricator, w/no follow-up by Project Manager
Factors (Continued)
Other Factors
• Resonating vibrations from dancing and music
• Greatly increased stress on box beams.
• Kansas City Building Code required for walkway:
• 100lbs/ft2
or 72,000 lbs for each walkway
• Actual load day of tragedy
• 9450 lbs (63 people @150lbs each)
• Design Lacked Redundancy
Procedures must be implemented that assure that allProcedures must be implemented that assure that all
connections are designed by a competent professionalconnections are designed by a competent professional
Peer reviews and design checks should include a review ofPeer reviews and design checks should include a review of
shop drawingsshop drawings
Lessons Learned
When questions come up look at surrounding issues for related
problems
EOR should be retained to provide full inspection during
construction of structure
Owner needs on site qualified representation
Lessons Learned
Design and construction is a collaborativeDesign and construction is a collaborative
process that requires professional integrity,process that requires professional integrity,
judgment, and integrity on the part of alljudgment, and integrity on the part of all
participantsparticipants
We have not yet clearly defined the nature ofWe have not yet clearly defined the nature of
the design and construction process and thethe design and construction process and the
information flow that is required for success ininformation flow that is required for success in
all respectsall respects
We have not learned to respect and teach theWe have not learned to respect and teach the
history of the profession and fully disseminatehistory of the profession and fully disseminate
information of problems that occurinformation of problems that occur
Lessons Not Learned
“It wasn’t a matter of doing something wrong, they just never did it at
all. Nobody ever did any calculations…. It got built without anybody
figuring out if it would be strong enough.”
• Patrick McLarny, attorney representing state of MO.
In Conclusion
• The two structural engineers lost their Professional Engineering
licenses and are no longer able to practice in the states of Missouri
and Texas
• Both are now practicing in other states
• A number of firms were bankrupt
• Many expensive legal suits were settled out of court
The kansas city hyatt regency walkway collapse

More Related Content

What's hot

Tacoma Narrows Suspension Bridge
Tacoma Narrows Suspension BridgeTacoma Narrows Suspension Bridge
Tacoma Narrows Suspension BridgeMuhammad Warraich
 
Quebec Bridge Collapse - A Case Study
Quebec Bridge Collapse - A Case StudyQuebec Bridge Collapse - A Case Study
Quebec Bridge Collapse - A Case StudyThings Simplified
 
Tacoma narrows bridge
Tacoma narrows bridgeTacoma narrows bridge
Tacoma narrows bridgesunnarsan
 
Structural systems in high rise building and analysis methods
Structural systems in high rise building and analysis methodsStructural systems in high rise building and analysis methods
Structural systems in high rise building and analysis methodsDP NITHIN
 
Tacoma Narrows Bridge - 1940
Tacoma Narrows Bridge - 1940Tacoma Narrows Bridge - 1940
Tacoma Narrows Bridge - 1940Nicole Grubb
 
case study for leaning tower of pisa ,infinity tower, dam failure
case study for leaning tower of pisa ,infinity tower, dam failurecase study for leaning tower of pisa ,infinity tower, dam failure
case study for leaning tower of pisa ,infinity tower, dam failureJainam Shah
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road constructionSatish Kambaliya
 
Leaning tower of Pisa
Leaning tower of PisaLeaning tower of Pisa
Leaning tower of PisaSumit Shokeen
 
What is post tensioning
What is post tensioningWhat is post tensioning
What is post tensioningCharlie Gupta
 
Polavaram project
Polavaram projectPolavaram project
Polavaram projectHari Harish
 
Case studies for strengthening of existing structures
Case studies for strengthening of existing structuresCase studies for strengthening of existing structures
Case studies for strengthening of existing structuresParamaAthmeka
 
Schoharie Creek Bridge Collapse - Case Study
Schoharie Creek Bridge Collapse - Case StudySchoharie Creek Bridge Collapse - Case Study
Schoharie Creek Bridge Collapse - Case StudyThings Simplified
 

What's hot (20)

Tacoma Narrows Suspension Bridge
Tacoma Narrows Suspension BridgeTacoma Narrows Suspension Bridge
Tacoma Narrows Suspension Bridge
 
Quebec Bridge Collapse - A Case Study
Quebec Bridge Collapse - A Case StudyQuebec Bridge Collapse - A Case Study
Quebec Bridge Collapse - A Case Study
 
Tacoma narrows bridge
Tacoma narrows bridgeTacoma narrows bridge
Tacoma narrows bridge
 
Structural systems in high rise building and analysis methods
Structural systems in high rise building and analysis methodsStructural systems in high rise building and analysis methods
Structural systems in high rise building and analysis methods
 
Tacoma Narrows Bridge - 1940
Tacoma Narrows Bridge - 1940Tacoma Narrows Bridge - 1940
Tacoma Narrows Bridge - 1940
 
case study for leaning tower of pisa ,infinity tower, dam failure
case study for leaning tower of pisa ,infinity tower, dam failurecase study for leaning tower of pisa ,infinity tower, dam failure
case study for leaning tower of pisa ,infinity tower, dam failure
 
Casting yard
Casting yardCasting yard
Casting yard
 
golden gate bridge
golden gate bridgegolden gate bridge
golden gate bridge
 
Is 1343 2012
Is 1343   2012Is 1343   2012
Is 1343 2012
 
Golden gate bridge
Golden gate bridgeGolden gate bridge
Golden gate bridge
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road construction
 
Kansai airport ppt
Kansai airport pptKansai airport ppt
Kansai airport ppt
 
Leaning tower of Pisa
Leaning tower of PisaLeaning tower of Pisa
Leaning tower of Pisa
 
What is post tensioning
What is post tensioningWhat is post tensioning
What is post tensioning
 
Special structure
Special structureSpecial structure
Special structure
 
Retrofitting
RetrofittingRetrofitting
Retrofitting
 
Polavaram project
Polavaram projectPolavaram project
Polavaram project
 
the millau viaduct
the millau viaductthe millau viaduct
the millau viaduct
 
Case studies for strengthening of existing structures
Case studies for strengthening of existing structuresCase studies for strengthening of existing structures
Case studies for strengthening of existing structures
 
Schoharie Creek Bridge Collapse - Case Study
Schoharie Creek Bridge Collapse - Case StudySchoharie Creek Bridge Collapse - Case Study
Schoharie Creek Bridge Collapse - Case Study
 

Viewers also liked

Kansas City Collapse
Kansas City CollapseKansas City Collapse
Kansas City CollapseDon W. Lewis
 
(PART1/2)COLLAPSE OF THE HYATT REGENCY WALKWAYS 1981
(PART1/2)COLLAPSE OF THE HYATT REGENCY WALKWAYS 1981(PART1/2)COLLAPSE OF THE HYATT REGENCY WALKWAYS 1981
(PART1/2)COLLAPSE OF THE HYATT REGENCY WALKWAYS 1981Ali Faizan Wattoo
 
(Part 2/2)COLLAPSE OF THE HYATT REGENCY WALKWAYS 1981
(Part 2/2)COLLAPSE OF THE HYATT REGENCY WALKWAYS 1981(Part 2/2)COLLAPSE OF THE HYATT REGENCY WALKWAYS 1981
(Part 2/2)COLLAPSE OF THE HYATT REGENCY WALKWAYS 1981Ali Faizan Wattoo
 
walkway collapse analysis
walkway collapse analysiswalkway collapse analysis
walkway collapse analysisMeng Lu
 
HOTEL CASESTUDY - HYATT REGENCY, PUNE
HOTEL CASESTUDY - HYATT REGENCY, PUNEHOTEL CASESTUDY - HYATT REGENCY, PUNE
HOTEL CASESTUDY - HYATT REGENCY, PUNEjagrutib22
 
Case study on whistleblowing
Case study on whistleblowingCase study on whistleblowing
Case study on whistleblowingParveen Bano
 
What Makes Great Infographics
What Makes Great InfographicsWhat Makes Great Infographics
What Makes Great InfographicsSlideShare
 
TEDx Manchester: AI & The Future of Work
TEDx Manchester: AI & The Future of WorkTEDx Manchester: AI & The Future of Work
TEDx Manchester: AI & The Future of WorkVolker Hirsch
 
Masters of SlideShare
Masters of SlideShareMasters of SlideShare
Masters of SlideShareKapost
 
STOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
STOP! VIEW THIS! 10-Step Checklist When Uploading to SlideshareSTOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
STOP! VIEW THIS! 10-Step Checklist When Uploading to SlideshareEmpowered Presentations
 
10 Ways to Win at SlideShare SEO & Presentation Optimization
10 Ways to Win at SlideShare SEO & Presentation Optimization10 Ways to Win at SlideShare SEO & Presentation Optimization
10 Ways to Win at SlideShare SEO & Presentation OptimizationOneupweb
 
How To Get More From SlideShare - Super-Simple Tips For Content Marketing
How To Get More From SlideShare - Super-Simple Tips For Content MarketingHow To Get More From SlideShare - Super-Simple Tips For Content Marketing
How To Get More From SlideShare - Super-Simple Tips For Content MarketingContent Marketing Institute
 
How to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksHow to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksSlideShare
 

Viewers also liked (17)

Kansas City Collapse
Kansas City CollapseKansas City Collapse
Kansas City Collapse
 
(PART1/2)COLLAPSE OF THE HYATT REGENCY WALKWAYS 1981
(PART1/2)COLLAPSE OF THE HYATT REGENCY WALKWAYS 1981(PART1/2)COLLAPSE OF THE HYATT REGENCY WALKWAYS 1981
(PART1/2)COLLAPSE OF THE HYATT REGENCY WALKWAYS 1981
 
(Part 2/2)COLLAPSE OF THE HYATT REGENCY WALKWAYS 1981
(Part 2/2)COLLAPSE OF THE HYATT REGENCY WALKWAYS 1981(Part 2/2)COLLAPSE OF THE HYATT REGENCY WALKWAYS 1981
(Part 2/2)COLLAPSE OF THE HYATT REGENCY WALKWAYS 1981
 
walkway collapse analysis
walkway collapse analysiswalkway collapse analysis
walkway collapse analysis
 
HOTEL CASESTUDY - HYATT REGENCY, PUNE
HOTEL CASESTUDY - HYATT REGENCY, PUNEHOTEL CASESTUDY - HYATT REGENCY, PUNE
HOTEL CASESTUDY - HYATT REGENCY, PUNE
 
2015_MST15_PPT_MIC Final
2015_MST15_PPT_MIC Final2015_MST15_PPT_MIC Final
2015_MST15_PPT_MIC Final
 
Senses of engineering ethics1
Senses of engineering ethics1Senses of engineering ethics1
Senses of engineering ethics1
 
Case study on whistleblowing
Case study on whistleblowingCase study on whistleblowing
Case study on whistleblowing
 
SlideShare 101
SlideShare 101SlideShare 101
SlideShare 101
 
What Makes Great Infographics
What Makes Great InfographicsWhat Makes Great Infographics
What Makes Great Infographics
 
TEDx Manchester: AI & The Future of Work
TEDx Manchester: AI & The Future of WorkTEDx Manchester: AI & The Future of Work
TEDx Manchester: AI & The Future of Work
 
Masters of SlideShare
Masters of SlideShareMasters of SlideShare
Masters of SlideShare
 
STOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
STOP! VIEW THIS! 10-Step Checklist When Uploading to SlideshareSTOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
STOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
 
You Suck At PowerPoint!
You Suck At PowerPoint!You Suck At PowerPoint!
You Suck At PowerPoint!
 
10 Ways to Win at SlideShare SEO & Presentation Optimization
10 Ways to Win at SlideShare SEO & Presentation Optimization10 Ways to Win at SlideShare SEO & Presentation Optimization
10 Ways to Win at SlideShare SEO & Presentation Optimization
 
How To Get More From SlideShare - Super-Simple Tips For Content Marketing
How To Get More From SlideShare - Super-Simple Tips For Content MarketingHow To Get More From SlideShare - Super-Simple Tips For Content Marketing
How To Get More From SlideShare - Super-Simple Tips For Content Marketing
 
How to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksHow to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & Tricks
 

Similar to The kansas city hyatt regency walkway collapse

Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiKrystian Gnysinski
 
Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09zaff69
 
case study on failed construction projects
case study on failed construction projectscase study on failed construction projects
case study on failed construction projectsSULAKSHYA GAUR
 
St James Presentation short
St James Presentation shortSt James Presentation short
St James Presentation shortDamien Brennan
 
Armtec Engineering's Top Picks - Case Studies and Design Review
Armtec Engineering's Top Picks - Case Studies and Design ReviewArmtec Engineering's Top Picks - Case Studies and Design Review
Armtec Engineering's Top Picks - Case Studies and Design ReviewCommunications Branding
 
Non-Residential PowerPoint
Non-Residential PowerPointNon-Residential PowerPoint
Non-Residential PowerPointbermanwright
 
Benefits of Mathematical Simulation
Benefits of Mathematical SimulationBenefits of Mathematical Simulation
Benefits of Mathematical SimulationBill ODonnell
 
Nu Flow Presentation Eric VA and YMCA
Nu Flow Presentation Eric VA and YMCANu Flow Presentation Eric VA and YMCA
Nu Flow Presentation Eric VA and YMCAEric Hopkins
 
No 1 Licensed structural auditor in Mumbai CSR consultant and associates
No 1 Licensed structural auditor in Mumbai CSR consultant and associatesNo 1 Licensed structural auditor in Mumbai CSR consultant and associates
No 1 Licensed structural auditor in Mumbai CSR consultant and associatesCSR Consultant and Associates
 
INTODUCTION TO CIVIL ENGINEERING
INTODUCTION TO CIVIL ENGINEERINGINTODUCTION TO CIVIL ENGINEERING
INTODUCTION TO CIVIL ENGINEERINGHafiz JUNAID
 
Washinton State University/Manchester Fuel Depot Senior Project
Washinton State University/Manchester Fuel Depot Senior ProjectWashinton State University/Manchester Fuel Depot Senior Project
Washinton State University/Manchester Fuel Depot Senior ProjectWSUME_2013_A-TEAM
 
WilliamHarkabusResume
WilliamHarkabusResumeWilliamHarkabusResume
WilliamHarkabusResumeBill Harkabus
 
April 2016 PM Magazine - Ken Neyer Plumbing
April 2016 PM Magazine - Ken Neyer PlumbingApril 2016 PM Magazine - Ken Neyer Plumbing
April 2016 PM Magazine - Ken Neyer PlumbingJim Mercer
 
Precast Prestressed Hollowcore Slabs Seminar - Armtec
Precast Prestressed Hollowcore Slabs Seminar - ArmtecPrecast Prestressed Hollowcore Slabs Seminar - Armtec
Precast Prestressed Hollowcore Slabs Seminar - ArmtecCommunications Branding
 
Construction portfolio (manvi)
Construction portfolio (manvi)Construction portfolio (manvi)
Construction portfolio (manvi)ManviVarshney2
 
Trusted BIM: Accurate As-Builts for Project Coordination
Trusted BIM: Accurate As-Builts for Project CoordinationTrusted BIM: Accurate As-Builts for Project Coordination
Trusted BIM: Accurate As-Builts for Project CoordinationClearEdge3D Inc
 

Similar to The kansas city hyatt regency walkway collapse (20)

Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian Gnysinski
 
Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09Ralls ncc meeting-san_antonio_04-01-09
Ralls ncc meeting-san_antonio_04-01-09
 
case study on failed construction projects
case study on failed construction projectscase study on failed construction projects
case study on failed construction projects
 
St James Presentation short
St James Presentation shortSt James Presentation short
St James Presentation short
 
Armtec Engineering's Top Picks - Case Studies and Design Review
Armtec Engineering's Top Picks - Case Studies and Design ReviewArmtec Engineering's Top Picks - Case Studies and Design Review
Armtec Engineering's Top Picks - Case Studies and Design Review
 
Non-Residential PowerPoint
Non-Residential PowerPointNon-Residential PowerPoint
Non-Residential PowerPoint
 
Expert Witness Presentation
Expert Witness PresentationExpert Witness Presentation
Expert Witness Presentation
 
Benefits of Mathematical Simulation
Benefits of Mathematical SimulationBenefits of Mathematical Simulation
Benefits of Mathematical Simulation
 
Presentation10.pptx
Presentation10.pptxPresentation10.pptx
Presentation10.pptx
 
citigroupcenter.pptx
citigroupcenter.pptxcitigroupcenter.pptx
citigroupcenter.pptx
 
Nu Flow Presentation Eric VA and YMCA
Nu Flow Presentation Eric VA and YMCANu Flow Presentation Eric VA and YMCA
Nu Flow Presentation Eric VA and YMCA
 
No 1 Licensed structural auditor in Mumbai CSR consultant and associates
No 1 Licensed structural auditor in Mumbai CSR consultant and associatesNo 1 Licensed structural auditor in Mumbai CSR consultant and associates
No 1 Licensed structural auditor in Mumbai CSR consultant and associates
 
INTODUCTION TO CIVIL ENGINEERING
INTODUCTION TO CIVIL ENGINEERINGINTODUCTION TO CIVIL ENGINEERING
INTODUCTION TO CIVIL ENGINEERING
 
Washinton State University/Manchester Fuel Depot Senior Project
Washinton State University/Manchester Fuel Depot Senior ProjectWashinton State University/Manchester Fuel Depot Senior Project
Washinton State University/Manchester Fuel Depot Senior Project
 
WilliamHarkabusResume
WilliamHarkabusResumeWilliamHarkabusResume
WilliamHarkabusResume
 
ASCE Utility Standards
ASCE Utility StandardsASCE Utility Standards
ASCE Utility Standards
 
April 2016 PM Magazine - Ken Neyer Plumbing
April 2016 PM Magazine - Ken Neyer PlumbingApril 2016 PM Magazine - Ken Neyer Plumbing
April 2016 PM Magazine - Ken Neyer Plumbing
 
Precast Prestressed Hollowcore Slabs Seminar - Armtec
Precast Prestressed Hollowcore Slabs Seminar - ArmtecPrecast Prestressed Hollowcore Slabs Seminar - Armtec
Precast Prestressed Hollowcore Slabs Seminar - Armtec
 
Construction portfolio (manvi)
Construction portfolio (manvi)Construction portfolio (manvi)
Construction portfolio (manvi)
 
Trusted BIM: Accurate As-Builts for Project Coordination
Trusted BIM: Accurate As-Builts for Project CoordinationTrusted BIM: Accurate As-Builts for Project Coordination
Trusted BIM: Accurate As-Builts for Project Coordination
 

More from Arpit Modh

Cryogenic grinding
Cryogenic grindingCryogenic grinding
Cryogenic grindingArpit Modh
 
Organizational change
Organizational changeOrganizational change
Organizational changeArpit Modh
 
Intellectual property rights
Intellectual property rightsIntellectual property rights
Intellectual property rightsArpit Modh
 
Green synthesis of gold nano particles
Green synthesis of gold nano particlesGreen synthesis of gold nano particles
Green synthesis of gold nano particlesArpit Modh
 
Pulp industries
Pulp industriesPulp industries
Pulp industriesArpit Modh
 
Wireless power transmission
Wireless power transmissionWireless power transmission
Wireless power transmissionArpit Modh
 
Maxima & Minima of Calculus
Maxima & Minima of CalculusMaxima & Minima of Calculus
Maxima & Minima of CalculusArpit Modh
 
Communication skills
Communication skillsCommunication skills
Communication skillsArpit Modh
 
Boiler Introduction & Classification
Boiler Introduction & ClassificationBoiler Introduction & Classification
Boiler Introduction & ClassificationArpit Modh
 

More from Arpit Modh (17)

Cryogenic grinding
Cryogenic grindingCryogenic grinding
Cryogenic grinding
 
Values
ValuesValues
Values
 
Personality
PersonalityPersonality
Personality
 
Motivation
MotivationMotivation
Motivation
 
Organizational change
Organizational changeOrganizational change
Organizational change
 
Intellectual property rights
Intellectual property rightsIntellectual property rights
Intellectual property rights
 
Green synthesis of gold nano particles
Green synthesis of gold nano particlesGreen synthesis of gold nano particles
Green synthesis of gold nano particles
 
Acetone
AcetoneAcetone
Acetone
 
Pulp industries
Pulp industriesPulp industries
Pulp industries
 
Spectroscopy
SpectroscopySpectroscopy
Spectroscopy
 
Wireless power transmission
Wireless power transmissionWireless power transmission
Wireless power transmission
 
Nuclear waste
Nuclear wasteNuclear waste
Nuclear waste
 
Maxima & Minima of Calculus
Maxima & Minima of CalculusMaxima & Minima of Calculus
Maxima & Minima of Calculus
 
Functions
FunctionsFunctions
Functions
 
Communication skills
Communication skillsCommunication skills
Communication skills
 
Antarctica
AntarcticaAntarctica
Antarctica
 
Boiler Introduction & Classification
Boiler Introduction & ClassificationBoiler Introduction & Classification
Boiler Introduction & Classification
 

Recently uploaded

A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086anil_gaur
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf203318pmpc
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 

Recently uploaded (20)

A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 

The kansas city hyatt regency walkway collapse

  • 1. The Kansas City Hyatt Regency Walkway Collapse “The Worst Structural Disaster In the United States” BY: Arpit Modh (16BCH035) B.Tech Chemical Nirma University, Ahmedabad.
  • 2. WHERE: Kansas City, Missouri DATE: July 17, 1981 3rd Floor Walkway Still Intact
  • 3. • Two Walkways Collapsed • 114 People Lost Their Life • Failure of Hanger Rod Connection (4th Floor) Kansas City Hyatt July 17, 1981
  • 4.
  • 5. Hotel Features • The hotel had a grand lobby which featured a multistory atrium crossed by three concrete walkways on the second, third and fourth floors • The hotel advertised to have many parties and events
  • 6. Entrance to Hotel and Atrium Kansas City Hyatt
  • 8. Background Of Walkway • July 1980 – Most Modern Hotel in Kansas City finished. • Consisted of 3 Buildings, 2 were connected by 3 walkways.
  • 9. Tea-Dance Party Leads to Disaster • A party was held in the lobby • Over 2,000 people were in attendance • People crowded the walkways and the lobby below to watch the dance competition • The excess weight caused the fourth floor walkway to fall onto the second floor walkway and both walkways collapsed onto the crowded first floor • The collapse left 114 dead and more than 200 injured • This was the United States’ most devastating structural failure of the time
  • 10. Design Problems • Havens proposed the modified design to simplify the assembly task and to eliminate the need to thread the entire length of the rods • However, the change in the design doubled the stress put forth on the nut which was under the fourth floor beam and with the change the nut had to support the weight of two walkways instead of just one • “The ultimate capacity actually available using the original connection detail would have been approximately 60% of that expected of a connection designed in accordance with AISC Specifications” according to the National Building Specifications
  • 11. On a preliminary design a note was made that the hanging rods needed to have strength of 413MPa but that was left out of the final design and so the fabricator used hanger rods with only 248MPa pf strength.
  • 12. Walkway’s Original Design beams as intermediate supports hole at both ends of Flanges aded single rod Hanger for 2nd and 4th floor walkways (3rd floor alkway was separate entity)
  • 13. Walkway as Constructed •4th floor box beams: -Ends had 2 holes -Outer hole connected to ceiling -2 lower rods went through inner holes to support second floor walkway
  • 14. Original Design Modified Design (was used) The 2nd and 4th floor walkways were originally supposed to be suspended from the same rod and held in place by nuts The fabricator had modified the design to use two hanging rods and the engineers approved the change without checking it
  • 15. The hanger rod threads, washer andThe hanger rod threads, washer and supporting nutsupporting nut Note: the deformation in the washer caused the beam to slipNote: the deformation in the washer caused the beam to slip
  • 16. CLOSE-UPS OF SOME OF THE 4TH FLOOR BEAMS
  • 17. Why Did It Happen? Combination of :Personnel Errors A. Design Deficiencies B. Inadequate Oversight & Review Process C. Missed opportunities to discover error D. Poor Communication
  • 18. Factors That Contributed to the Collapse • Fast Track Process  Architectural design changes & conceptual re-designs  Drafting Errors  Checking errors-Shop Drawings  Invalid initial design concept of hanger Senior engineer personnel changes  Phone changes w/o follow-up by detailer or engineer in writing
  • 19. •Fabricators in-house engineer transferred fabricator’s partial shop dwgs to outside firm who assumed connection was designed •Engineers technician, checked piece size but not connection. (Not Drawn or submitted) •Outside Peer Review didn’t check shop dwg Factors (Continued)
  • 20. •“Design Check” questions answers not verified •In-house design check questions following atrium collapse were not verified. No Follow Up •Poor Testing & Inspection Factors (Continued)
  • 21. •No Structural Site Representation (Refused several times) •Engineer Relied (ASSUMED) based on past projects on design of connections by Fabricator, w/no follow-up by Project Manager Factors (Continued)
  • 22. Other Factors • Resonating vibrations from dancing and music • Greatly increased stress on box beams. • Kansas City Building Code required for walkway: • 100lbs/ft2 or 72,000 lbs for each walkway • Actual load day of tragedy • 9450 lbs (63 people @150lbs each) • Design Lacked Redundancy
  • 23.
  • 24.
  • 25.
  • 26.
  • 27. Procedures must be implemented that assure that allProcedures must be implemented that assure that all connections are designed by a competent professionalconnections are designed by a competent professional Peer reviews and design checks should include a review ofPeer reviews and design checks should include a review of shop drawingsshop drawings Lessons Learned
  • 28. When questions come up look at surrounding issues for related problems EOR should be retained to provide full inspection during construction of structure Owner needs on site qualified representation Lessons Learned
  • 29. Design and construction is a collaborativeDesign and construction is a collaborative process that requires professional integrity,process that requires professional integrity, judgment, and integrity on the part of alljudgment, and integrity on the part of all participantsparticipants We have not yet clearly defined the nature ofWe have not yet clearly defined the nature of the design and construction process and thethe design and construction process and the information flow that is required for success ininformation flow that is required for success in all respectsall respects We have not learned to respect and teach theWe have not learned to respect and teach the history of the profession and fully disseminatehistory of the profession and fully disseminate information of problems that occurinformation of problems that occur Lessons Not Learned
  • 30. “It wasn’t a matter of doing something wrong, they just never did it at all. Nobody ever did any calculations…. It got built without anybody figuring out if it would be strong enough.” • Patrick McLarny, attorney representing state of MO.
  • 31. In Conclusion • The two structural engineers lost their Professional Engineering licenses and are no longer able to practice in the states of Missouri and Texas • Both are now practicing in other states • A number of firms were bankrupt • Many expensive legal suits were settled out of court

Editor's Notes

  1. Looking North- West Function Block in Immediate Foreground Entrance,Screen Wall and Atrium , Sandwiched back and between Tower and Function Block 35 Story, 750 Concrete Guest Tower on the North and Topped by a Steel Revolving Restaurant Four Story Function Block on the South Separated by a 4 Story Column Free Atruium Bed Tower connected to the Function Block by Three Bridges hung from the Atrium Roof , which in turn was connected to the Glass Entry Wall and Sun Screen
  2. Hotel Name: ??? Indoor Atrium with walkways connecting floors 2, 3, & 4 Failure at walkways connecting floors 2 & 4
  3. USE NOTES FOLLOWING THIS FOR DISCUSSION (NEXT PAGE……………)