SAP Production Planning & Execution
Understanding Production Order
Time Elements
1. Analyzing the Production Planned Order time
elements.
2. Check the inputs that affects calculation for the
time elements for the Planned Production Order.
3. PIR requirement date and Production Machine
Time.
4. Planned Order dates verification.
5. Convert Planned Order to Production Order.
6. Summary o the Time Elements for Production
Order schedule dates.
Plan Production Order
created from the MRP
run
PIR qty is 200
Let's analyze
all these
time elements
1. Analyzing the Production Planned Order time
elements.
2. Check the inputs that affects calculation for
the time elements for the Planned Production
Order.
3. PIR requirement date and Production Machine
Time.
4. Planned Order dates verification.
5. Convert Planned Order to Production Order.
6. Summary o the Time Elements for Production
Order schedule dates.
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Scheduling Margin Key
(Material Master MRP2 view)
1) Opening period
2) Float before Production
3) Release Period
4) Float after Production
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
(Material Master MRP2
view)
10) Goods Receipt
Processing Time
Operation 10
Routing
5) Queue Time
6) Machine Time
7) Move Time
Operation 20
Routing
8) Machine Time
9) Wait Time
Material Master
MRP2 view
stores the
GR Processing Time &
Scheduling Margin Key
Scheduling Margin Key
(Material Master MRP2 view)
1) Opening period
2) Float before Production
3) Release Period
4) Float after Production
(Material Master MRP2 view)
10) Goods Receipt Processing
Time
Scheduling Margin Key
(Material Master MRP2 view)
1) Opening period
2) Float before Production
3) Release Period
4) Float after Production
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
Operation 10 Operation 20
Queue
Time
MoveT
ime
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
(Material Master MRP2
view)
10) Goods Receipt
Processing Time
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
2 Work Centers in the Routing
Work Center ZWC1 and ZWC2
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
2 Work Centers in the Routing
Operation 10 Work Center ZWC1
Operation 20 Work Center ZWC2
2 Work Centers in the Routing
Operation 10 Work Center ZWC1
Operation 20 Work Center ZWC2
2 Work Centers in the Routing
Operation 10 Work Center ZWC1
Operation 20 Work Center ZWC2
1. Analyzing the Production Planned Order time
elements.
2. Check the inputs that affects calculation for the
time elements for the Planned Production Order.
3. PIR requirement date and Production Machine
Time.
4. Planned Order dates verification.
5. Convert Planned Order to Production Order.
6. Summary o the Time Elements for Production
Order schedule dates.
PIR qty is 200
10pcs / 60min
200/10 x 60
= 1200min
= 2.9 days for each
Operation Machine
Times
Requirement date
01.12.2021
PIR qty is 200
10pcs / 60min
200/10 x 60
= 1200min
= 2.9 days for each
Operation Machine
Times
1. Analyzing the Production Planned Order time
elements.
2. Check the inputs that affects calculation for the
time elements for the Planned Production Order.
3. PIR requirement date and Production Machine
Time.
4. Planned Order dates verification.
5. Convert Planned Order to Production Order.
6. Summary o the Time Elements for Production
Order schedule dates.
From Opening date 29.10.2021
to Available date 01.12.2021
the Factory calendar show
1 holiday on 01.11.2021 and all Saturday
and Sundays are non-working days
200pcs
stock available date 01.12.2021
gr processing time 2 days
basic finish date 29.11.2021
float after production 3 days
schedule finish date 23.11.2021
opr20:wait time 2 days 2 days
opr20:zwc2 (7hr) 10pcs/1hour > 20 hours 2.9 days
opr10:move time 1 day 1 days
opr10:zwc2 (7hr) 10pcs/1hour > 20 hours 2.9 days
opr10:queue time 1 day 1 days
schedule start date 12.11.2021
float before production 3 days
basic start date 09.11.2021
release period 2 days
release period 2 days 10.11.2021
opening period 5 days
opening date 02.11.2021
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
Stock Available Date
01.12.2021
Basic Finish Date
29.11.2021
Schedule Finish Date
23.11.2021
Schedule Start Date
12.11.2021
Basic Start Date
09.11.2021
Opening date
02.11.2021
Production Times
Operation 10 Queue time + Machine time + Move time
= 1 day + 2.9 days + 1 day = 4.9 days
Operation 20 Machine time + Wait time
= 2.9 days + 2 days = 4.9 days
Total = 4.9 days + 4.9 days = 9.8 days
1. Analyzing the Production Planned Order time
elements.
2. Check the inputs that affects calculation for the
time elements for the Planned Production Order.
3. PIR requirement date and Production Machine
Time.
4. Planned Order dates verification.
5. Convert Planned Order to Production Order.
6. Summary o the Time Elements for Production
Order schedule dates.
Convert the
Planned Order to
Production Order
Planned Orders
Basic Start/Finish dates
Schedule Start/Finish dates
are copied to the
Production Order
Schedule Start date 12.11.2021
- 2 days (Release Period)
=
Release date 10.11.2021
Schedule Start date 12.11.2021
- 2 days (Release Period)
=
Release date 10.11.2021
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
Earliest Start
Time
Latest Start
Time
Earliest Finish
Time
Latest Finish
Time
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
Earliest Start Time + Queue Time (1 day)
= Latest Start Times
Latest Start
Time
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
Earliest Start Time + Queue Time (1 day)
= Latest Start Times
Earliest tear down time means
exclude Queue TIme
12.11.2021 09:17:08 to
17.11.2021 08:08:34
is just the Machine time of 1200min
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
Earliest Start Time + Queue Time (1 day)
= Latest Start Times
Latest tear down time means
include Queue TIme
Earliest Process time
12.11.2021 09:17:08 + Machine time of 1200min + 1 day
Queue Time
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
for the Operation 20
note
Operation 10 latest teardown time + 1 day move time
= Operation 20 earliest start time
18.11.2021 08:08:34 + 1 day
= 19.11.2021 08:08:34
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
Since there is no Queue Time for Operation 20
the
Earliest start time = Latest start time
Operation 10
Queue time 1 day
Move time 1 day
1. Analyzing the Production Planned Order time
elements.
2. Check the inputs that affects calculation for the
time elements for the Planned Production Order.
3. PIR requirement date and Production Machine
Time.
4. Planned Order dates verification.
5. Convert Planned Order to Production Order.
6. Summary o the Time Elements for Production
Order schedule dates.
200pcs
stock available date 01.12.2021
gr processing time 2 days
basic finish date 29.11.2021
float after production 3 days
schedule finish date 23.11.2021
opr20:wait time 2 days 2 days
opr20:zwc2 (7hr) 10pcs/1hour > 20 hours 2.9 days
opr10:move time 1 day 1 days
opr10:zwc2 (7hr) 10pcs/1hour > 20 hours 2.9 days
opr10:queue time 1 day 1 days
schedule start date 12.11.2021
float before production 3 days
basic start date 09.11.2021
release period 2 days
release period 2 days 10.11.2021
opening period 5 days
opening date 02.11.2021
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
Stock Available Date
01.12.2021
Basic Finish Date
29.11.2021
Schedule Finish Date
23.11.2021
Schedule Start Date
12.11.2021
Basic Start Date
09.11.2021
Opening date
02.11.2021
These are the lead times for the
Planned Production Order
and Production Order
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
Stock Available Date
01.12.2021
Basic Finish Date
29.11.2021
Schedule Finish Date
23.11.2021
Schedule Start Date
12.11.2021
Basic Start Date
09.11.2021
Opening date
02.11.2021
Opening date + Opering Period = Basic Start Date
Opening Period
is the time given to the Planner to Convert the
Planned Order to Production Order
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
Stock Available Date
01.12.2021
Basic Finish Date
29.11.2021
Schedule Finish Date
23.11.2021
Schedule Start Date
12.11.2021
Basic Start Date
09.11.2021
Opening date
02.11.2021
Basic Start Date + Float before Prod = Schedule start date
Float before Prod is
the time given to the Scheduler to prepare the Production
inclduing check materials, check jig, check drawing etc
+ the Release Period
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
Stock Available Date
01.12.2021
Basic Finish Date
29.11.2021
Schedule Finish Date
23.11.2021
Schedule Start Date
12.11.2021
Basic Start Date
09.11.2021
Opening date
02.11.2021
Schedule start date - Release Period = Release Date
Release period is
the time required for preparation of materials for picking and
material staged to the shop floor ready for Production
Release Date
10.11.2021
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
Stock Available Date
01.12.2021
Basic Finish Date
29.11.2021
Schedule Finish Date
23.11.2021
Schedule Start Date
12.11.2021
Basic Start Date
09.11.2021
Opening date
02.11.2021
Queue time is
the Average time a Production Order has to
wait before it can start, due to several
Production Orders Queuing to start the JOB.
Release Date
10.11.2021
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
Stock Available Date
01.12.2021
Basic Finish Date
29.11.2021
Schedule Finish Date
23.11.2021
Schedule Start Date
12.11.2021
Basic Start Date
09.11.2021
Opening date
02.11.2021
Move time is
Production finish in Operation
10 takes how long to move the
WIP from Operation 10 to
Operation 20
Release Date
10.11.2021
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
Stock Available Date
01.12.2021
Basic Finish Date
29.11.2021
Schedule Finish Date
23.11.2021
Schedule Start Date
12.11.2021
Basic Start Date
09.11.2021
Opening date
02.11.2021
Release Date
10.11.2021
Wait Time is
Operation 20 completed will have to Wait how
long before it can moved to the next Operation or
next step (example waiting for the Paint to dry)
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
Stock Available Date
01.12.2021
Basic Finish Date
29.11.2021
Schedule Finish Date
23.11.2021
Schedule Start Date
12.11.2021
Basic Start Date
09.11.2021
Opening date
02.11.2021
Release Date
10.11.2021
Schedule Start time + the Operation times
= Schedule Finish Date
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
Stock Available Date
01.12.2021
Basic Finish Date
29.11.2021
Schedule Finish Date
23.11.2021
Schedule Start Date
12.11.2021
Basic Start Date
09.11.2021
Opening date
02.11.2021
Release Date
10.11.2021
Schedule Finish Date + Float after Production
= Basic Finish date
Float after Production is
a BUFFER in case production delay
Operation 10 Operation 20
Queue
Time
Move
Time
Wait
Time
Float
After
Prod
Float
Before
Prod Release
Period
Opening
Period
5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days
10pcs / hr
or 60min
10pcs / hr
or 60min
200pcs
means
1200 min
200pcs
means
1200 min
7 hrs/day
work time
7 hrs/day
work time
= 2.9 days = 2.9 days
Goods
Receipt
Process
Time
2 Days
1 2 3 4 10
5
6
7
8
9
Stock Available Date
01.12.2021
Basic Finish Date
29.11.2021
Schedule Finish Date
23.11.2021
Schedule Start Date
12.11.2021
Basic Start Date
09.11.2021
Opening date
02.11.2021
Release Date
10.11.2021
Basic Finish Date + Goods Receipt Processing Time
= Stock Available Date
GR Processing Time is
the time required for QA and Storage to Warehouse

More Related Content

What's hot

Co product costing detailed trng
Co product costing detailed trngCo product costing detailed trng
Co product costing detailed trng
Venkat Reddy
 
Sap procurement process flow
Sap procurement process flowSap procurement process flow
Sap procurement process flow
Keennary Pungyera
 
SAP Automatic batch determination
SAP Automatic batch determinationSAP Automatic batch determination
SAP Automatic batch determination
Amit Pandey
 

What's hot (20)

80467542 asset-closing-in-sap-fico
80467542 asset-closing-in-sap-fico80467542 asset-closing-in-sap-fico
80467542 asset-closing-in-sap-fico
 
SAP PS - system statuses maintenance
SAP PS - system statuses maintenanceSAP PS - system statuses maintenance
SAP PS - system statuses maintenance
 
How to teco the production orders - Murali Krishna Nookella
How to teco the production orders - Murali Krishna NookellaHow to teco the production orders - Murali Krishna Nookella
How to teco the production orders - Murali Krishna Nookella
 
Ps user manual
Ps user manualPs user manual
Ps user manual
 
Dip profiles-documentation
Dip profiles-documentationDip profiles-documentation
Dip profiles-documentation
 
Co product costing detailed trng
Co product costing detailed trngCo product costing detailed trng
Co product costing detailed trng
 
MRP Live on S/4 HANA
MRP Live on S/4 HANAMRP Live on S/4 HANA
MRP Live on S/4 HANA
 
Case study material ledger implementation lessons learned
Case study  material ledger implementation lessons learnedCase study  material ledger implementation lessons learned
Case study material ledger implementation lessons learned
 
CO-PA SAP
CO-PA SAPCO-PA SAP
CO-PA SAP
 
SAP PS Certification Overview (mindmap edition)
SAP PS Certification Overview (mindmap edition)SAP PS Certification Overview (mindmap edition)
SAP PS Certification Overview (mindmap edition)
 
SAP S4 HANA MM 1709 Overview (mindmap edition) Final
SAP S4 HANA MM 1709 Overview (mindmap edition) FinalSAP S4 HANA MM 1709 Overview (mindmap edition) Final
SAP S4 HANA MM 1709 Overview (mindmap edition) Final
 
SAP MM Business Scenarios
SAP MM  Business ScenariosSAP MM  Business Scenarios
SAP MM Business Scenarios
 
SAP HANA Product Costing / Cost center accounting
SAP HANA Product Costing / Cost center accountingSAP HANA Product Costing / Cost center accounting
SAP HANA Product Costing / Cost center accounting
 
Sap procurement process flow
Sap procurement process flowSap procurement process flow
Sap procurement process flow
 
SAP Automatic batch determination
SAP Automatic batch determinationSAP Automatic batch determination
SAP Automatic batch determination
 
Sap mm configuration document ramesh kamishetty
Sap mm  configuration document ramesh kamishettySap mm  configuration document ramesh kamishetty
Sap mm configuration document ramesh kamishetty
 
7358948 questionnaire-mm
7358948 questionnaire-mm7358948 questionnaire-mm
7358948 questionnaire-mm
 
Sap pp tutorial
Sap pp tutorialSap pp tutorial
Sap pp tutorial
 
SAP CO step by step config guide & user manual part 1
SAP CO step by step config guide & user manual part 1SAP CO step by step config guide & user manual part 1
SAP CO step by step config guide & user manual part 1
 
Parametrage magasin wm sap s4 hana
Parametrage magasin wm sap s4 hanaParametrage magasin wm sap s4 hana
Parametrage magasin wm sap s4 hana
 

Similar to SAP PP Production Order Understanding Time Elements.pdf

Ch5 process analysis
Ch5 process analysisCh5 process analysis
Ch5 process analysis
videoaakash15
 
Ch5 process+analysis
Ch5 process+analysisCh5 process+analysis
Ch5 process+analysis
videoaakash15
 
ch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptxch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptx
MukhtarMohamedAbdila
 
Chapter 3 work study
Chapter 3 work studyChapter 3 work study
Chapter 3 work study
ctsan
 
Ukesh Simulation Project
Ukesh Simulation ProjectUkesh Simulation Project
Ukesh Simulation Project
Chawal Ukesh
 
Chapter 5 operation management
Chapter 5   operation managementChapter 5   operation management
Chapter 5 operation management
Izah Asmadi
 

Similar to SAP PP Production Order Understanding Time Elements.pdf (20)

Value stream map
Value stream mapValue stream map
Value stream map
 
Value stream mapping
Value stream mappingValue stream mapping
Value stream mapping
 
Ch5 process analysis
Ch5 process analysisCh5 process analysis
Ch5 process analysis
 
Ch5 process+analysis
Ch5 process+analysisCh5 process+analysis
Ch5 process+analysis
 
ch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptxch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptx
 
Bakery Production Using Arena Simulation
Bakery Production Using Arena SimulationBakery Production Using Arena Simulation
Bakery Production Using Arena Simulation
 
DonnerCompany
DonnerCompanyDonnerCompany
DonnerCompany
 
Bakery Production Using Arena Simulation
Bakery Production Using Arena SimulationBakery Production Using Arena Simulation
Bakery Production Using Arena Simulation
 
Chapter 3 work study
Chapter 3 work studyChapter 3 work study
Chapter 3 work study
 
Improving processes
Improving processesImproving processes
Improving processes
 
Lean Value Stream Mapping Project
Lean Value Stream Mapping ProjectLean Value Stream Mapping Project
Lean Value Stream Mapping Project
 
How to build a hardware in one day v0.9
How to build a hardware in one day v0.9How to build a hardware in one day v0.9
How to build a hardware in one day v0.9
 
Ukesh Simulation Project
Ukesh Simulation ProjectUkesh Simulation Project
Ukesh Simulation Project
 
Case study furniture industry
Case study   furniture industryCase study   furniture industry
Case study furniture industry
 
BRUSNSWICK MOTORS, INC
BRUSNSWICK MOTORS, INCBRUSNSWICK MOTORS, INC
BRUSNSWICK MOTORS, INC
 
Brunswick motors, inc
Brunswick motors, incBrunswick motors, inc
Brunswick motors, inc
 
Brunswick motors, inc
Brunswick motors, incBrunswick motors, inc
Brunswick motors, inc
 
Frepple-Odoo integration - Odoo experience days 2016
Frepple-Odoo integration - Odoo experience days 2016Frepple-Odoo integration - Odoo experience days 2016
Frepple-Odoo integration - Odoo experience days 2016
 
Chapter 5 operation management
Chapter 5   operation managementChapter 5   operation management
Chapter 5 operation management
 
MRP and ERP
MRP and ERPMRP and ERP
MRP and ERP
 

Recently uploaded

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Dr.Costas Sachpazis
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
rknatarajan
 

Recently uploaded (20)

UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 

SAP PP Production Order Understanding Time Elements.pdf

  • 1. SAP Production Planning & Execution Understanding Production Order Time Elements
  • 2. 1. Analyzing the Production Planned Order time elements. 2. Check the inputs that affects calculation for the time elements for the Planned Production Order. 3. PIR requirement date and Production Machine Time. 4. Planned Order dates verification. 5. Convert Planned Order to Production Order. 6. Summary o the Time Elements for Production Order schedule dates.
  • 3. Plan Production Order created from the MRP run PIR qty is 200
  • 5. 1. Analyzing the Production Planned Order time elements. 2. Check the inputs that affects calculation for the time elements for the Planned Production Order. 3. PIR requirement date and Production Machine Time. 4. Planned Order dates verification. 5. Convert Planned Order to Production Order. 6. Summary o the Time Elements for Production Order schedule dates.
  • 6. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9
  • 7. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Scheduling Margin Key (Material Master MRP2 view) 1) Opening period 2) Float before Production 3) Release Period 4) Float after Production Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 (Material Master MRP2 view) 10) Goods Receipt Processing Time Operation 10 Routing 5) Queue Time 6) Machine Time 7) Move Time Operation 20 Routing 8) Machine Time 9) Wait Time
  • 8. Material Master MRP2 view stores the GR Processing Time & Scheduling Margin Key Scheduling Margin Key (Material Master MRP2 view) 1) Opening period 2) Float before Production 3) Release Period 4) Float after Production (Material Master MRP2 view) 10) Goods Receipt Processing Time
  • 9. Scheduling Margin Key (Material Master MRP2 view) 1) Opening period 2) Float before Production 3) Release Period 4) Float after Production Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9
  • 10. Operation 10 Operation 20 Queue Time MoveT ime Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 (Material Master MRP2 view) 10) Goods Receipt Processing Time
  • 11. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 2 Work Centers in the Routing Work Center ZWC1 and ZWC2
  • 12.
  • 13.
  • 14.
  • 15.
  • 16. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 2 Work Centers in the Routing Operation 10 Work Center ZWC1 Operation 20 Work Center ZWC2
  • 17. 2 Work Centers in the Routing Operation 10 Work Center ZWC1 Operation 20 Work Center ZWC2
  • 18. 2 Work Centers in the Routing Operation 10 Work Center ZWC1 Operation 20 Work Center ZWC2
  • 19. 1. Analyzing the Production Planned Order time elements. 2. Check the inputs that affects calculation for the time elements for the Planned Production Order. 3. PIR requirement date and Production Machine Time. 4. Planned Order dates verification. 5. Convert Planned Order to Production Order. 6. Summary o the Time Elements for Production Order schedule dates.
  • 20. PIR qty is 200 10pcs / 60min 200/10 x 60 = 1200min = 2.9 days for each Operation Machine Times
  • 21. Requirement date 01.12.2021 PIR qty is 200 10pcs / 60min 200/10 x 60 = 1200min = 2.9 days for each Operation Machine Times
  • 22. 1. Analyzing the Production Planned Order time elements. 2. Check the inputs that affects calculation for the time elements for the Planned Production Order. 3. PIR requirement date and Production Machine Time. 4. Planned Order dates verification. 5. Convert Planned Order to Production Order. 6. Summary o the Time Elements for Production Order schedule dates.
  • 23. From Opening date 29.10.2021 to Available date 01.12.2021 the Factory calendar show 1 holiday on 01.11.2021 and all Saturday and Sundays are non-working days
  • 24. 200pcs stock available date 01.12.2021 gr processing time 2 days basic finish date 29.11.2021 float after production 3 days schedule finish date 23.11.2021 opr20:wait time 2 days 2 days opr20:zwc2 (7hr) 10pcs/1hour > 20 hours 2.9 days opr10:move time 1 day 1 days opr10:zwc2 (7hr) 10pcs/1hour > 20 hours 2.9 days opr10:queue time 1 day 1 days schedule start date 12.11.2021 float before production 3 days basic start date 09.11.2021 release period 2 days release period 2 days 10.11.2021 opening period 5 days opening date 02.11.2021
  • 25. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 Stock Available Date 01.12.2021 Basic Finish Date 29.11.2021 Schedule Finish Date 23.11.2021 Schedule Start Date 12.11.2021 Basic Start Date 09.11.2021 Opening date 02.11.2021 Production Times Operation 10 Queue time + Machine time + Move time = 1 day + 2.9 days + 1 day = 4.9 days Operation 20 Machine time + Wait time = 2.9 days + 2 days = 4.9 days Total = 4.9 days + 4.9 days = 9.8 days
  • 26. 1. Analyzing the Production Planned Order time elements. 2. Check the inputs that affects calculation for the time elements for the Planned Production Order. 3. PIR requirement date and Production Machine Time. 4. Planned Order dates verification. 5. Convert Planned Order to Production Order. 6. Summary o the Time Elements for Production Order schedule dates.
  • 27. Convert the Planned Order to Production Order
  • 28. Planned Orders Basic Start/Finish dates Schedule Start/Finish dates are copied to the Production Order
  • 29. Schedule Start date 12.11.2021 - 2 days (Release Period) = Release date 10.11.2021
  • 30. Schedule Start date 12.11.2021 - 2 days (Release Period) = Release date 10.11.2021 Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9
  • 31. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 Earliest Start Time Latest Start Time Earliest Finish Time Latest Finish Time
  • 32. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 Earliest Start Time + Queue Time (1 day) = Latest Start Times Latest Start Time
  • 33. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 Earliest Start Time + Queue Time (1 day) = Latest Start Times Earliest tear down time means exclude Queue TIme 12.11.2021 09:17:08 to 17.11.2021 08:08:34 is just the Machine time of 1200min
  • 34. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 Earliest Start Time + Queue Time (1 day) = Latest Start Times Latest tear down time means include Queue TIme Earliest Process time 12.11.2021 09:17:08 + Machine time of 1200min + 1 day Queue Time
  • 35. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 for the Operation 20 note Operation 10 latest teardown time + 1 day move time = Operation 20 earliest start time 18.11.2021 08:08:34 + 1 day = 19.11.2021 08:08:34
  • 36. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 Since there is no Queue Time for Operation 20 the Earliest start time = Latest start time
  • 37. Operation 10 Queue time 1 day Move time 1 day
  • 38. 1. Analyzing the Production Planned Order time elements. 2. Check the inputs that affects calculation for the time elements for the Planned Production Order. 3. PIR requirement date and Production Machine Time. 4. Planned Order dates verification. 5. Convert Planned Order to Production Order. 6. Summary o the Time Elements for Production Order schedule dates.
  • 39. 200pcs stock available date 01.12.2021 gr processing time 2 days basic finish date 29.11.2021 float after production 3 days schedule finish date 23.11.2021 opr20:wait time 2 days 2 days opr20:zwc2 (7hr) 10pcs/1hour > 20 hours 2.9 days opr10:move time 1 day 1 days opr10:zwc2 (7hr) 10pcs/1hour > 20 hours 2.9 days opr10:queue time 1 day 1 days schedule start date 12.11.2021 float before production 3 days basic start date 09.11.2021 release period 2 days release period 2 days 10.11.2021 opening period 5 days opening date 02.11.2021
  • 40. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 Stock Available Date 01.12.2021 Basic Finish Date 29.11.2021 Schedule Finish Date 23.11.2021 Schedule Start Date 12.11.2021 Basic Start Date 09.11.2021 Opening date 02.11.2021 These are the lead times for the Planned Production Order and Production Order
  • 41. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 Stock Available Date 01.12.2021 Basic Finish Date 29.11.2021 Schedule Finish Date 23.11.2021 Schedule Start Date 12.11.2021 Basic Start Date 09.11.2021 Opening date 02.11.2021 Opening date + Opering Period = Basic Start Date Opening Period is the time given to the Planner to Convert the Planned Order to Production Order
  • 42. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 Stock Available Date 01.12.2021 Basic Finish Date 29.11.2021 Schedule Finish Date 23.11.2021 Schedule Start Date 12.11.2021 Basic Start Date 09.11.2021 Opening date 02.11.2021 Basic Start Date + Float before Prod = Schedule start date Float before Prod is the time given to the Scheduler to prepare the Production inclduing check materials, check jig, check drawing etc + the Release Period
  • 43. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 Stock Available Date 01.12.2021 Basic Finish Date 29.11.2021 Schedule Finish Date 23.11.2021 Schedule Start Date 12.11.2021 Basic Start Date 09.11.2021 Opening date 02.11.2021 Schedule start date - Release Period = Release Date Release period is the time required for preparation of materials for picking and material staged to the shop floor ready for Production Release Date 10.11.2021
  • 44. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 Stock Available Date 01.12.2021 Basic Finish Date 29.11.2021 Schedule Finish Date 23.11.2021 Schedule Start Date 12.11.2021 Basic Start Date 09.11.2021 Opening date 02.11.2021 Queue time is the Average time a Production Order has to wait before it can start, due to several Production Orders Queuing to start the JOB. Release Date 10.11.2021
  • 45. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 Stock Available Date 01.12.2021 Basic Finish Date 29.11.2021 Schedule Finish Date 23.11.2021 Schedule Start Date 12.11.2021 Basic Start Date 09.11.2021 Opening date 02.11.2021 Move time is Production finish in Operation 10 takes how long to move the WIP from Operation 10 to Operation 20 Release Date 10.11.2021
  • 46. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 Stock Available Date 01.12.2021 Basic Finish Date 29.11.2021 Schedule Finish Date 23.11.2021 Schedule Start Date 12.11.2021 Basic Start Date 09.11.2021 Opening date 02.11.2021 Release Date 10.11.2021 Wait Time is Operation 20 completed will have to Wait how long before it can moved to the next Operation or next step (example waiting for the Paint to dry)
  • 47. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 Stock Available Date 01.12.2021 Basic Finish Date 29.11.2021 Schedule Finish Date 23.11.2021 Schedule Start Date 12.11.2021 Basic Start Date 09.11.2021 Opening date 02.11.2021 Release Date 10.11.2021 Schedule Start time + the Operation times = Schedule Finish Date
  • 48. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 Stock Available Date 01.12.2021 Basic Finish Date 29.11.2021 Schedule Finish Date 23.11.2021 Schedule Start Date 12.11.2021 Basic Start Date 09.11.2021 Opening date 02.11.2021 Release Date 10.11.2021 Schedule Finish Date + Float after Production = Basic Finish date Float after Production is a BUFFER in case production delay
  • 49. Operation 10 Operation 20 Queue Time Move Time Wait Time Float After Prod Float Before Prod Release Period Opening Period 5 Days 3 Days 2 Days 1 Day 1 Day 2 Days 3 Days 10pcs / hr or 60min 10pcs / hr or 60min 200pcs means 1200 min 200pcs means 1200 min 7 hrs/day work time 7 hrs/day work time = 2.9 days = 2.9 days Goods Receipt Process Time 2 Days 1 2 3 4 10 5 6 7 8 9 Stock Available Date 01.12.2021 Basic Finish Date 29.11.2021 Schedule Finish Date 23.11.2021 Schedule Start Date 12.11.2021 Basic Start Date 09.11.2021 Opening date 02.11.2021 Release Date 10.11.2021 Basic Finish Date + Goods Receipt Processing Time = Stock Available Date GR Processing Time is the time required for QA and Storage to Warehouse