Chapter 3:
Work study is a service that uses techniques such
as research methods and study time, to review the
effectiveness of each activity in a
        systematic work activities to produce an
          efficient and productive work.
   Minimize time
   Minimize cost
   Production based on ability raw material,
    equipment and skill of workers.
   Produce high-quality spending
   Maximize worker safety.
   High production costs of the ordinary.

   Production is not balanced in terms of quality.

   Too much work in progress (Work In Progress)

   The existence of the movement of
    people and material excess.
   Use of materials, equipment, machinery and
    labor is not satisfactory.

   Often requires overtime.

   There are works that have to much idle time.

   Production quality is not satisfactory.
Before starting any work study should take note
 of these two factors:

-   How much savings if a work is
    reviewed and new methods developed.

-   How much time is allocated for research work.
KAJIAN KERJA
                     (work Study)



 KAJIAN KAEDAH                       KAJIAN MASA
(Research Methods)                   (Time Methods)




MENINGKATKAN KECEKAPAN DAN
PRODUKTIVITI
       (Increase Efficency and Productivity)
   The study method is as a study to determine
    the various methods that can be usedfor a job.

   From these studies we can determine the
    best method to practiced in carrying outthe
    work.
   Detailed studies carried out to analyze the
    following areas:

     - purpose of this process is done
     - quality standards
    - layout of workplace equipment
    - cycle (work cycle)
    - work methods
   Improve production flow
   Effective use of labor
   Improve the plant layout and design
   Effective use of existing facilities
   Create a more comfortable working conditions
   Establish standards for the methods used
Flow Chart process describes in diagram
form on the activities that occurred from the
beginning raw materials are processed, they
tend to run the operation and inspection.
Flow chart process can devide to three such:

 Material types - shows that the movement of
  material being processed.

   Operator type that shows the movement done
    by the operator during the process.

   Equipment type - that shows the activities done
    to a device for the purpose of processing
SYMBOL        ACTIVITIES             PURPOSE (TUJUAN)

         Control              Process and Production
         (Pengendalian)
         Inspection           Inspect Quality and Quantity
         (Pemeriksaan)
         Transportation       Movement
         Pengangkutan

         Delay
         Kelewatan/simpanan   Delay / Interruption
         sementara
         Simpanan Tetap       Simpan
   Assembly / component opening
   Repair works
   Provide plant and equipment
   Change shape / condition of a material
   Chemical reaction
   command
   fill in the form
   Computation and others
   measure ingredients
   Mengkelas
   Check - measure, numbering.
 The motion of the hand, trucks, lorries and other
  transport devices.

 Movement through the pipe or tube

 Travel operators
   Operator / Material wait to lift / lifted

   Materials waiting for the next process

   Operator wait till material come.
   Alat/Bahan yang disimpan dalam stor
    sementara menanti untuk dihantar ke tempat
    lain.
   Maklumat yang disimpan
   Semua kelewatan atau simpanan sementara
    yang melebihi 24 jam.
Example 1

 Draw a Process Flow Chart to show
 the activities of laundry using the washing
 machine
2 minit                     1           kumpulkan pakaian kotor


 17 meter                                    1        bawa pakaian ke tempat cuci


                          5 minit                2       masukkan pakaian ke dalam
                  mesin

                             45 minit        1        tunggu sehingga mesin berhenti



15 meter      -                          2           bawa pakaian ke tempat jemuran


                              15 minit       3         sidai pakaian tersebut


                              120 minit 2 2            tunggu sehingga pakaian kering


  15 meter        -                          3         bawa pakaian ke tempat melipat


                             20 minit    4            lipat pakaian


  5 meter                     -              4         bawa pakaian ke tempat penyimpanan


                                             1         simpan pakai
   Time study is  a study that
    using specific techniques to determine the total
    time taken by the operator to complete an
    operation.
   The study time objectives are to :

    i. Determine the number of elements that an
    operation
    ii. Determine the level of difficulty of an
    operation
    iii. Determine the level of employee skills
    iv. Reduce production costs
    v. Determine the standard time for an
    operation
   Two techniques are commonly used;


    i.  Using the Stopwatch

    ii.  Movement Time
    System Set / Predetermined Motion Time Sys
    tem
Standard time is the goal to be achieved in
a time study using stopwatch. The standard
time is

total time taken to perform each element found
in a review of the work.

[Total Standard Time = Work + All rewards
given
   Peti-peti surat yang dibuat daripada kepingan logam galvanis untuk
    kegunaan Politeknik Sultan Haji Ahmad Shah dibuat di Bengkel
    Kepingan Logam. Lima kitaran Kajian Masa telah dilakukan oleh
    En Saaid ke atas seorang pelajar Kejuruteraan Mekanikal. Kajian
    bermula dari pukul 8.00 pagi dan berakhir hingga pukul 9.50 pagi.
    En.Saaid telah mendapat butiran seperti berikut :
 
Jumlah peratusan ganjaran :
   Unsur 1 =         20% MA
   Unsur 2 =         15% MA
   Unsur 3 =         10% MA
   Unsur 4 =         25% MA
MASA PEMERHATIAN
NO.                             UNSUR                    KADAR
                                                                      (MINIT)


                                                          90            6
                                                          95            7
      Memotong kepingan-kepingan logam galvanis           90            7
1.
      kepada saiz peti surat                              90            8
                                                          95            5

                                                          90            4
                                                          95            5
                                                          95            5
2.    Membentuk peti surat
                                                          80            5
                                                          90            4

                                                         105            5
                                                          95            6
      Mencantumkan kepingan-kepingan logam peti           90            6
3.
      surat                                               95            7
                                                          95            7

                                                          90            4
                                                         105            3
                                                          90            4
4.    Merivet peti surat
                                                          90            4
                                                         100            3

                                                          95            1
5.    Memeriksa Peti Surat (untuk setiap 2 peti surat)    90            2
   Time is measured in the study methods are: -

    i. The average time-which is the time for each
    element of its cycle.

    ii. CAS / rating, during a review, the observer also
    assesses the speed of current employees to
    work compare with normal speed.

     Masa Normal = Masa Purata + ( Masa Normal x Kadaran %)
   Time is stale-time employees'
    personal needs (eg go to the canteen, toilet,
    etc.), time to rest and time delays, such
    as damage to the machine and so on.
   Usually the value given in percentage (%).
   Standard time is calculated by the following
    means:

    Masa Piawai = Masa Normal + ( masa normal x
    masa basi )
Seorang Jurutera industri di Syarikat Biz Sdn Bhd.mengambil masa
piawai bagi suatu operasi dengan menggunakan teknik kajian masa.
Data dari jadual di bawah adalah masa yang diambil dengan
menggunakan jam randik secara ulangan.
                                Masa ( min )
           Unsur                                          Kadaran
                    Kitaran 1   Kitaran 2    Kitaran 3

             1          4.5         4.2          4.7        112
             2          3.0         3.2          2.8        112
             3          2.3         2.5          2.3        110

 Sekiranya di tetapkan jumlah kelegaan / basi peribadi, kelewatan dan
 kelesuan adalah 10 %, dapatkan:-
     1.Masa purata bagi setiap unsur
     2.Masa normal bagi setiap unsur
     3.Masa piawai bagi setiap unsur
     4.Masa piawai bagi keseluruhan
Seorang penyelia Syarikat Jeman Sdn. Bhd. dikehendaki membuat
kajian masa bagi satu operasi. Data dari jadual di bawah adalah masa
yang diambil dengan menggunakan jam randik secara ulangan.

                                 Masa ( min )
          Unsur                                             Kadaran
                     Kitaran 1    Kitaran 2     Kitaran 3

            A          0.30         0.35          0.50       100

            B          0.12         0.15          0.10       110

            C          0.41         0.43          0.45       110

            D          0.80         0.90          0.92        95


Diberi kelegaan peribadi 15%. Dapatkan masa piawai bagi proses tersebut.
END

More Related Content

Similar to Chapter 3 work study

IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
Karina Islam
 
ppt-project-final.ppt
ppt-project-final.pptppt-project-final.ppt
ppt-project-final.ppt
steel14
 
Ch5 process analysis
Ch5 process analysisCh5 process analysis
Ch5 process analysis
videoaakash15
 
Ch5 process+analysis
Ch5 process+analysisCh5 process+analysis
Ch5 process+analysis
videoaakash15
 

Similar to Chapter 3 work study (20)

Production planning and control
Production planning and controlProduction planning and control
Production planning and control
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
 
ppt-project-final.ppt
ppt-project-final.pptppt-project-final.ppt
ppt-project-final.ppt
 
Ch5 process analysis
Ch5 process analysisCh5 process analysis
Ch5 process analysis
 
Ch5 process+analysis
Ch5 process+analysisCh5 process+analysis
Ch5 process+analysis
 
Production planning and control 2019
Production planning and control 2019Production planning and control 2019
Production planning and control 2019
 
production planning and control
production planning and controlproduction planning and control
production planning and control
 
Motion and time study
Motion and time studyMotion and time study
Motion and time study
 
Work study manual
Work study manualWork study manual
Work study manual
 
Work measurement (1)
Work measurement (1)Work measurement (1)
Work measurement (1)
 
Plastop report
Plastop reportPlastop report
Plastop report
 
Line balancing and its formulation
Line balancing and its formulationLine balancing and its formulation
Line balancing and its formulation
 
Lean Management
Lean ManagementLean Management
Lean Management
 
All in 1 IE
All in 1 IEAll in 1 IE
All in 1 IE
 
Work measurement
Work measurementWork measurement
Work measurement
 
Work measurement
Work measurementWork measurement
Work measurement
 
POM.pptx
POM.pptxPOM.pptx
POM.pptx
 
Lean six sigma 3d
Lean six sigma 3dLean six sigma 3d
Lean six sigma 3d
 
PPC and functions of PPC.pptx
PPC and functions of PPC.pptxPPC and functions of PPC.pptx
PPC and functions of PPC.pptx
 
Work Measurement
Work MeasurementWork Measurement
Work Measurement
 

Chapter 3 work study

  • 2. Work study is a service that uses techniques such as research methods and study time, to review the effectiveness of each activity in a systematic work activities to produce an efficient and productive work.
  • 3. Minimize time  Minimize cost  Production based on ability raw material, equipment and skill of workers.  Produce high-quality spending  Maximize worker safety.
  • 4. High production costs of the ordinary.  Production is not balanced in terms of quality.  Too much work in progress (Work In Progress)  The existence of the movement of people and material excess.
  • 5. Use of materials, equipment, machinery and labor is not satisfactory.  Often requires overtime.  There are works that have to much idle time.  Production quality is not satisfactory.
  • 6. Before starting any work study should take note of these two factors: - How much savings if a work is reviewed and new methods developed. - How much time is allocated for research work.
  • 7. KAJIAN KERJA (work Study) KAJIAN KAEDAH KAJIAN MASA (Research Methods) (Time Methods) MENINGKATKAN KECEKAPAN DAN PRODUKTIVITI (Increase Efficency and Productivity)
  • 8. The study method is as a study to determine the various methods that can be usedfor a job.  From these studies we can determine the best method to practiced in carrying outthe work.
  • 9. Detailed studies carried out to analyze the following areas: - purpose of this process is done - quality standards - layout of workplace equipment - cycle (work cycle) - work methods
  • 10. Improve production flow  Effective use of labor  Improve the plant layout and design  Effective use of existing facilities  Create a more comfortable working conditions  Establish standards for the methods used
  • 11. Flow Chart process describes in diagram form on the activities that occurred from the beginning raw materials are processed, they tend to run the operation and inspection.
  • 12. Flow chart process can devide to three such:  Material types - shows that the movement of material being processed.  Operator type that shows the movement done by the operator during the process.  Equipment type - that shows the activities done to a device for the purpose of processing
  • 13. SYMBOL ACTIVITIES PURPOSE (TUJUAN) Control Process and Production (Pengendalian) Inspection Inspect Quality and Quantity (Pemeriksaan) Transportation Movement Pengangkutan Delay Kelewatan/simpanan Delay / Interruption sementara Simpanan Tetap Simpan
  • 14. Assembly / component opening  Repair works  Provide plant and equipment  Change shape / condition of a material  Chemical reaction  command  fill in the form  Computation and others
  • 15. measure ingredients  Mengkelas  Check - measure, numbering.
  • 16.  The motion of the hand, trucks, lorries and other transport devices.  Movement through the pipe or tube  Travel operators
  • 17. Operator / Material wait to lift / lifted  Materials waiting for the next process  Operator wait till material come.
  • 18. Alat/Bahan yang disimpan dalam stor sementara menanti untuk dihantar ke tempat lain.  Maklumat yang disimpan  Semua kelewatan atau simpanan sementara yang melebihi 24 jam.
  • 19. Example 1 Draw a Process Flow Chart to show the activities of laundry using the washing machine
  • 20. 2 minit 1 kumpulkan pakaian kotor 17 meter 1 bawa pakaian ke tempat cuci 5 minit 2 masukkan pakaian ke dalam mesin 45 minit 1 tunggu sehingga mesin berhenti 15 meter - 2 bawa pakaian ke tempat jemuran 15 minit 3 sidai pakaian tersebut 120 minit 2 2 tunggu sehingga pakaian kering 15 meter - 3 bawa pakaian ke tempat melipat 20 minit 4 lipat pakaian 5 meter - 4 bawa pakaian ke tempat penyimpanan 1 simpan pakai
  • 21. Time study is  a study that using specific techniques to determine the total time taken by the operator to complete an operation.
  • 22. The study time objectives are to : i. Determine the number of elements that an operation ii. Determine the level of difficulty of an operation iii. Determine the level of employee skills iv. Reduce production costs v. Determine the standard time for an operation
  • 23. Two techniques are commonly used;  i.  Using the Stopwatch ii.  Movement Time System Set / Predetermined Motion Time Sys tem
  • 24. Standard time is the goal to be achieved in a time study using stopwatch. The standard time is total time taken to perform each element found in a review of the work. [Total Standard Time = Work + All rewards given
  • 25. Peti-peti surat yang dibuat daripada kepingan logam galvanis untuk kegunaan Politeknik Sultan Haji Ahmad Shah dibuat di Bengkel Kepingan Logam. Lima kitaran Kajian Masa telah dilakukan oleh En Saaid ke atas seorang pelajar Kejuruteraan Mekanikal. Kajian bermula dari pukul 8.00 pagi dan berakhir hingga pukul 9.50 pagi. En.Saaid telah mendapat butiran seperti berikut :   Jumlah peratusan ganjaran : Unsur 1 = 20% MA Unsur 2 = 15% MA Unsur 3 = 10% MA Unsur 4 = 25% MA
  • 26. MASA PEMERHATIAN NO. UNSUR KADAR (MINIT) 90 6 95 7 Memotong kepingan-kepingan logam galvanis 90 7 1. kepada saiz peti surat 90 8 95 5 90 4 95 5 95 5 2. Membentuk peti surat 80 5 90 4 105 5 95 6 Mencantumkan kepingan-kepingan logam peti 90 6 3. surat 95 7 95 7 90 4 105 3 90 4 4. Merivet peti surat 90 4 100 3 95 1 5. Memeriksa Peti Surat (untuk setiap 2 peti surat) 90 2
  • 27. Time is measured in the study methods are: - i. The average time-which is the time for each element of its cycle. ii. CAS / rating, during a review, the observer also assesses the speed of current employees to work compare with normal speed. Masa Normal = Masa Purata + ( Masa Normal x Kadaran %)
  • 28. Time is stale-time employees' personal needs (eg go to the canteen, toilet, etc.), time to rest and time delays, such as damage to the machine and so on.  Usually the value given in percentage (%).
  • 29. Standard time is calculated by the following means: Masa Piawai = Masa Normal + ( masa normal x masa basi )
  • 30. Seorang Jurutera industri di Syarikat Biz Sdn Bhd.mengambil masa piawai bagi suatu operasi dengan menggunakan teknik kajian masa. Data dari jadual di bawah adalah masa yang diambil dengan menggunakan jam randik secara ulangan. Masa ( min ) Unsur Kadaran Kitaran 1 Kitaran 2 Kitaran 3 1 4.5 4.2 4.7 112 2 3.0 3.2 2.8 112 3 2.3 2.5 2.3 110 Sekiranya di tetapkan jumlah kelegaan / basi peribadi, kelewatan dan kelesuan adalah 10 %, dapatkan:- 1.Masa purata bagi setiap unsur 2.Masa normal bagi setiap unsur 3.Masa piawai bagi setiap unsur 4.Masa piawai bagi keseluruhan
  • 31. Seorang penyelia Syarikat Jeman Sdn. Bhd. dikehendaki membuat kajian masa bagi satu operasi. Data dari jadual di bawah adalah masa yang diambil dengan menggunakan jam randik secara ulangan. Masa ( min ) Unsur Kadaran Kitaran 1 Kitaran 2 Kitaran 3 A 0.30 0.35 0.50 100 B 0.12 0.15 0.10 110 C 0.41 0.43 0.45 110 D 0.80 0.90 0.92 95 Diberi kelegaan peribadi 15%. Dapatkan masa piawai bagi proses tersebut.
  • 32. END