SlideShare a Scribd company logo
1 of 15
Project Phase 1
Value stream mapping of Pilot plant
by
Schawan Kunupakaphun
Srividya Sharvankumar
Rushi Patel
Content
What is Pilot Plant?
Process Flow for Pilot Plant
External and Internal customer Requirements
Work time
Process information
Value Stream Mapping
Area of improvement
Pilot Plant Trial for a New Product
● Pilot plant runs trial for various compound that are developed in an R&D
● The compound is tested for the feasibility of its commercial production
● Provides sample of the product to the expected customers for them to test
the product in their facility.
● On time delivery of samples to the customer is critical. As the sample will let
the customer to provide us the commercial scale production order if the
material passes their specifications.
● pilot plant aims at testing the process within the existing facility available at
the pilot plant
● The value stream for the pilot run in this project is related to a single product
Process Flow for Pilot Trial
● Upon the arrival of the order for a sample production following are the series of
event followed:
● Decide the operation philosophy for the process.
● Execute the modifications.
● Checking of the changes
● Information to operating team
● Conduct the run
● Data compilation
● Product packaging
● Discussion on findings of batch with the design team
● Dispatch of material to customer
● Two suppliers involved:- Process chemical supplier( supplier 1) and Starting Mat.
supplier(Supplier 2)
● Lead time for obtaining both material is two weeks by 2 shipment every week.
External Customer Requirements
● 50kg of pyrazole acid per month
● Specification for the final product is provided to the production control team.
● Customer order to produce 150 kg within 3 months.
● 3kg material in PTFE cans
● Weekly shipment
● Pharmaceutical company requires orders to come 30 days before shipment.
Internal Customer Requirements
● Weekly updates regarding the product dispatch
● Weekly progress from the production team about the new findings and issues in
the operation.
● Weekly process data collected in all the operations during all the shifts.
Work Time
● 330 days per year
● Three shifts in all production department.
● 8.5 hrs every shift with 30 mins break during each shift.
● Manual process stops during breaks.
● 30mins of lapover time between each shift.
Process Information - Reaction
● Batch process with 2 operators per shift.
● Number of shifts: 3
● Cycle time : 8hrs
● Changeover Time : 4hrs
● Changeover Frequency : 2 per day
● Observed Inventory:
o 10 days of unreacted raw materials
o 1 day of reacted material.
● Uptime: 67%
● Yield : 100%
Process Information - Filtration
● Batch process with 1 operators per shift.
● Number of Shifts: 3
● Cycle time : 10hrs
● Changeover Time : 3hrs
● Changeover Frequency : 2 per day
● Observed Inventory:
o 4 days of filtered material.
● Uptime: 83%
● Yield : 90%
Process Information - Distillation
● Batch process with 2 operators per shift.
● Number of shifts : 3
● Cycle time : 12hrs
● Changeover Time : 12hrs
● Changeover Frequency : 1 per day
● Observed Inventory:
o 1 day of final product
● Uptime: 50%
● Yield : 98%
Process Information - Packaging
● Manual process with 1 operators per shift.
● Number of Shifts: 1
● Cycle time : 3hrs
● Changeover Time : 1hr
● Changeover Frequency : 2 per day
● Observed Inventory:
o 7 days of packed product
● Uptime: 75%
Value Stream Mapping
Pilot plant
Customer 2
Engineering Design
30 days2 weeks
Supplier 2
(Catalyst and
starting materials)
Supplier 1
(Process Chemicals)
Receiving
I
10 days
Production
Control
1 day
C/T = 8 hr
C/O = 4 hr
CoF = 2/day
Upt = 67%
Yield = 100%
Shift = 3
Reaction
(O) 2
I
1days
C/T = 10 hr
C/O = 3 hr
CoF = 2/day
Upt = 83%
Yield = 90%
Shift = 3
Filtration
(O) 1
I
10hrs
I
1 day
C/T = 3hr
C/O = 1 hr
Upt = 75%
Shift = 1
Packaging
(O) 1
2* week
Production Supervisor
Weekly
12hrs 3hrs
8hrs
10 days 1 days 4 days 1 days 7 days
Total LT = 23days
Total VA time = 33hrs
Weekly
updates
Engineering
design
1 day
Modification
7 days
50 Kg/mo
PTFE Can = 3kg
Product Dispatch
I
7 days4 days
Weekly Progress
Customer 1
Daily Schedule
Checking Modification
2 days
C/T = 12 hr
C/O = 12 hr
CoF = 1/day
Upt = 50%
Yield = 98%
Shift = 3
Distillation
(O) 2
Takt Time
Total available working hours in a month = 27.5 * 24
= 660 hrs
Total Quantity to be produced per month = 50 kg
Takt Time = Time Available/ Qty Required
= 660/50 = 13.2 hrs/kg
Overall Cycle time => 33hrs to produce 3 kg
= 11 hrs/ Kg
Hence the overall cycle time for the process < Takt time
(O) 2
C/T = 12 hr
C/O = 12 hr
CoF = 1/day
Upt = 50%
Yield = 98%
Shift = 3
Value Stream Mapping
Pilot plant
Customer 2
Engineering Design
30 days2 weeks
Supplier 2
(Catalyst and
starting materials)
Supplier 1
(Process Chemicals)
Receiving
I
10 days
Production
Control
1 day
C/T = 8 hr
C/O = 4 hr
CoF = 2/day
Upt = 67%
Yield = 100%
Shift = 3
Reaction
I
1days
C/T = 10 hr
C/O = 3 hr
CoF = 2/day
Upt = 83%
Yield = 90%
Shift = 3
Filtration
(O) 1
I
10hrs
I
1 day
C/T = 3hr
C/O = 1 hr
Upt = 75%
Shift = 1
Packaging
(O) 1
2* week
Production Supervisor
Weekly
12hrs 3hrs
8hrs
10 days 1 days 4 days 1 days 7 days
Total LT = 23days
Total VA time = 33hrs
Engineering
design
1 day
50 Kg/mo
PTFE Can = 3kg
Product Dispatch
I
7 days4 days
Customer 1
Daily Schedule
Checking Modification
2 days
Distillation
(O) 2
Area of improvement
● The raw material stays in the warehouse for 10 days before the process is
started which needs to be reduced.
● There is holdover for all the intermediate material with the intermediate after
filtration to be as high as 4 days.
● The finished product stays in the warehouse for 7 days before the customer
pulls it.
● Product stays in inventory for 7 days therefore no.of shift is high.
● Staffing for the reaction and distillation has high number of operator.
● The uptime is very low for the reaction and distillation steps.
● The changeover time is high for all the processes.
Thank You

More Related Content

What's hot

7 QC Tools training presentation
7 QC Tools training presentation7 QC Tools training presentation
7 QC Tools training presentationPRASHANT KSHIRSAGAR
 
Advanced Product Quality Planning presentation
Advanced Product Quality Planning presentationAdvanced Product Quality Planning presentation
Advanced Product Quality Planning presentationPRASHANT KSHIRSAGAR
 
Lean Manufacturing Tools
Lean Manufacturing ToolsLean Manufacturing Tools
Lean Manufacturing ToolsJagriti Prasad
 
Quality circle presentation by yusuff
Quality circle presentation by yusuffQuality circle presentation by yusuff
Quality circle presentation by yusuffMohamed Yusuff
 
Cost of-poor-quality - juran institute
Cost of-poor-quality - juran instituteCost of-poor-quality - juran institute
Cost of-poor-quality - juran instituteManish Chaurasia
 
Quality control circle presentation
Quality control circle presentationQuality control circle presentation
Quality control circle presentationGanesh Murugan
 
7 qc tools training material[1]
7 qc tools training material[1]7 qc tools training material[1]
7 qc tools training material[1]gurmukh singh
 
Equipment reliability l1
Equipment reliability l1Equipment reliability l1
Equipment reliability l1Matthew Clemens
 
Root cause analysis - tools and process
Root cause analysis - tools and processRoot cause analysis - tools and process
Root cause analysis - tools and processCharles Cotter, PhD
 
Value Stream Mapping -The Concept
Value Stream Mapping -The ConceptValue Stream Mapping -The Concept
Value Stream Mapping -The ConceptSubhrajyoti Parida
 
Value stream mapping study with example
Value stream mapping study with exampleValue stream mapping study with example
Value stream mapping study with exampleMouhcine Nahal
 
Ppap training-presentation
Ppap training-presentationPpap training-presentation
Ppap training-presentationRanvijay Akela
 
Failure Mode & Effect Analysis
Failure Mode & Effect AnalysisFailure Mode & Effect Analysis
Failure Mode & Effect AnalysisNafis Ahmad
 
2006 pfmea presentation
2006 pfmea presentation2006 pfmea presentation
2006 pfmea presentationilker kayar
 
VSM - Value Stream Mapping for made-to-order manufacturing
VSM - Value Stream Mapping for made-to-order manufacturingVSM - Value Stream Mapping for made-to-order manufacturing
VSM - Value Stream Mapping for made-to-order manufacturingJessica Mitchell
 

What's hot (20)

7 QC Tools training presentation
7 QC Tools training presentation7 QC Tools training presentation
7 QC Tools training presentation
 
Advanced Product Quality Planning presentation
Advanced Product Quality Planning presentationAdvanced Product Quality Planning presentation
Advanced Product Quality Planning presentation
 
Lean Manufacturing Tools
Lean Manufacturing ToolsLean Manufacturing Tools
Lean Manufacturing Tools
 
Quality circle presentation by yusuff
Quality circle presentation by yusuffQuality circle presentation by yusuff
Quality circle presentation by yusuff
 
Cost of-poor-quality - juran institute
Cost of-poor-quality - juran instituteCost of-poor-quality - juran institute
Cost of-poor-quality - juran institute
 
Quality control circle presentation
Quality control circle presentationQuality control circle presentation
Quality control circle presentation
 
7 qc tools training material[1]
7 qc tools training material[1]7 qc tools training material[1]
7 qc tools training material[1]
 
Equipment reliability l1
Equipment reliability l1Equipment reliability l1
Equipment reliability l1
 
Root cause analysis - tools and process
Root cause analysis - tools and processRoot cause analysis - tools and process
Root cause analysis - tools and process
 
Apqp ppt
Apqp pptApqp ppt
Apqp ppt
 
Value Stream Mapping -The Concept
Value Stream Mapping -The ConceptValue Stream Mapping -The Concept
Value Stream Mapping -The Concept
 
TQM TPM
TQM TPMTQM TPM
TQM TPM
 
Value stream mapping study with example
Value stream mapping study with exampleValue stream mapping study with example
Value stream mapping study with example
 
Ppap training-presentation
Ppap training-presentationPpap training-presentation
Ppap training-presentation
 
Failure Mode & Effect Analysis
Failure Mode & Effect AnalysisFailure Mode & Effect Analysis
Failure Mode & Effect Analysis
 
8D analysis presentation
8D analysis presentation8D analysis presentation
8D analysis presentation
 
APQP
APQPAPQP
APQP
 
2006 pfmea presentation
2006 pfmea presentation2006 pfmea presentation
2006 pfmea presentation
 
Quality Awareness Training
Quality Awareness TrainingQuality Awareness Training
Quality Awareness Training
 
VSM - Value Stream Mapping for made-to-order manufacturing
VSM - Value Stream Mapping for made-to-order manufacturingVSM - Value Stream Mapping for made-to-order manufacturing
VSM - Value Stream Mapping for made-to-order manufacturing
 

Viewers also liked

Value stream mapping- lean manufacturing tool
Value stream mapping- lean manufacturing toolValue stream mapping- lean manufacturing tool
Value stream mapping- lean manufacturing toolbhanutomar
 
Introduction to lean six sigma
Introduction to lean six sigmaIntroduction to lean six sigma
Introduction to lean six sigmaSteve Carleysmith
 
Improvement Kata Roles & Structure
Improvement Kata Roles & StructureImprovement Kata Roles & Structure
Improvement Kata Roles & StructureTyson Ortiz
 
Panduan umum sistem jaminan halal lppom mui
Panduan umum  sistem jaminan halal lppom muiPanduan umum  sistem jaminan halal lppom mui
Panduan umum sistem jaminan halal lppom muiGuide_Consulting
 
How to Use VSM Correctly
How to Use VSM CorrectlyHow to Use VSM Correctly
How to Use VSM CorrectlyMike Rother
 

Viewers also liked (6)

Value stream mapping- lean manufacturing tool
Value stream mapping- lean manufacturing toolValue stream mapping- lean manufacturing tool
Value stream mapping- lean manufacturing tool
 
Introduction to lean six sigma
Introduction to lean six sigmaIntroduction to lean six sigma
Introduction to lean six sigma
 
Improvement Kata Roles & Structure
Improvement Kata Roles & StructureImprovement Kata Roles & Structure
Improvement Kata Roles & Structure
 
Panduan umum sistem jaminan halal lppom mui
Panduan umum  sistem jaminan halal lppom muiPanduan umum  sistem jaminan halal lppom mui
Panduan umum sistem jaminan halal lppom mui
 
Maruti
MarutiMaruti
Maruti
 
How to Use VSM Correctly
How to Use VSM CorrectlyHow to Use VSM Correctly
How to Use VSM Correctly
 

Similar to Lean Value Stream Mapping Project

ch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptxch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptxMukhtarMohamedAbdila
 
Ch5 process analysis
Ch5 process analysisCh5 process analysis
Ch5 process analysisvideoaakash15
 
Ch5 process+analysis
Ch5 process+analysisCh5 process+analysis
Ch5 process+analysisvideoaakash15
 
Batch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous FlowBatch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous FlowJulian Kalac P.Eng
 
Ukesh Simulation Project
Ukesh Simulation ProjectUkesh Simulation Project
Ukesh Simulation ProjectChawal Ukesh
 
Case study electronics industry
Case study   electronics industryCase study   electronics industry
Case study electronics industryGanesh TN
 
Value Stream Mapping: Beyond the Mechanics - Part 3 (Executing the Transforma...
Value Stream Mapping: Beyond the Mechanics - Part 3 (Executing the Transforma...Value Stream Mapping: Beyond the Mechanics - Part 3 (Executing the Transforma...
Value Stream Mapping: Beyond the Mechanics - Part 3 (Executing the Transforma...TKMG, Inc.
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)MohammedLahssaini1
 
Production planning
Production planningProduction planning
Production planningDavid Jaison
 
Litttle knowledge of lean concept helps
Litttle knowledge of lean  concept helpsLitttle knowledge of lean  concept helps
Litttle knowledge of lean concept helpsSF Lau
 
A case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringA case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringIJECSJournal
 
Motion and time study english
Motion and time study englishMotion and time study english
Motion and time study englishNorhan Abd Elaziz
 
SCORE implimentation (Blue Nile PP bag).pptx
SCORE implimentation (Blue Nile PP bag).pptxSCORE implimentation (Blue Nile PP bag).pptx
SCORE implimentation (Blue Nile PP bag).pptxmolla17
 
Chapter 5 operation management
Chapter 5   operation managementChapter 5   operation management
Chapter 5 operation managementIzah Asmadi
 
Schneider Case Study Challenge
Schneider Case Study ChallengeSchneider Case Study Challenge
Schneider Case Study ChallengeNikhil Kejriwal
 

Similar to Lean Value Stream Mapping Project (20)

ch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptxch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptx
 
Ch5 process analysis
Ch5 process analysisCh5 process analysis
Ch5 process analysis
 
Ch5 process+analysis
Ch5 process+analysisCh5 process+analysis
Ch5 process+analysis
 
MyPGDMM_MS_Chap12_TQM (1).pdf
MyPGDMM_MS_Chap12_TQM (1).pdfMyPGDMM_MS_Chap12_TQM (1).pdf
MyPGDMM_MS_Chap12_TQM (1).pdf
 
Batch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous FlowBatch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous Flow
 
Ukesh Simulation Project
Ukesh Simulation ProjectUkesh Simulation Project
Ukesh Simulation Project
 
Case study electronics industry
Case study   electronics industryCase study   electronics industry
Case study electronics industry
 
Process analysis
Process analysisProcess analysis
Process analysis
 
Value Stream Mapping: Beyond the Mechanics - Part 3 (Executing the Transforma...
Value Stream Mapping: Beyond the Mechanics - Part 3 (Executing the Transforma...Value Stream Mapping: Beyond the Mechanics - Part 3 (Executing the Transforma...
Value Stream Mapping: Beyond the Mechanics - Part 3 (Executing the Transforma...
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)
 
Production planning
Production planningProduction planning
Production planning
 
Litttle knowledge of lean concept helps
Litttle knowledge of lean  concept helpsLitttle knowledge of lean  concept helps
Litttle knowledge of lean concept helps
 
A case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringA case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ring
 
Motion and time study english
Motion and time study englishMotion and time study english
Motion and time study english
 
product-review.ppt
product-review.pptproduct-review.ppt
product-review.ppt
 
Value stream mapping
Value stream mappingValue stream mapping
Value stream mapping
 
Resume Suresh Patel
Resume Suresh PatelResume Suresh Patel
Resume Suresh Patel
 
SCORE implimentation (Blue Nile PP bag).pptx
SCORE implimentation (Blue Nile PP bag).pptxSCORE implimentation (Blue Nile PP bag).pptx
SCORE implimentation (Blue Nile PP bag).pptx
 
Chapter 5 operation management
Chapter 5   operation managementChapter 5   operation management
Chapter 5 operation management
 
Schneider Case Study Challenge
Schneider Case Study ChallengeSchneider Case Study Challenge
Schneider Case Study Challenge
 

Lean Value Stream Mapping Project

  • 1. Project Phase 1 Value stream mapping of Pilot plant by Schawan Kunupakaphun Srividya Sharvankumar Rushi Patel
  • 2. Content What is Pilot Plant? Process Flow for Pilot Plant External and Internal customer Requirements Work time Process information Value Stream Mapping Area of improvement
  • 3. Pilot Plant Trial for a New Product ● Pilot plant runs trial for various compound that are developed in an R&D ● The compound is tested for the feasibility of its commercial production ● Provides sample of the product to the expected customers for them to test the product in their facility. ● On time delivery of samples to the customer is critical. As the sample will let the customer to provide us the commercial scale production order if the material passes their specifications. ● pilot plant aims at testing the process within the existing facility available at the pilot plant ● The value stream for the pilot run in this project is related to a single product
  • 4. Process Flow for Pilot Trial ● Upon the arrival of the order for a sample production following are the series of event followed: ● Decide the operation philosophy for the process. ● Execute the modifications. ● Checking of the changes ● Information to operating team ● Conduct the run ● Data compilation ● Product packaging ● Discussion on findings of batch with the design team ● Dispatch of material to customer ● Two suppliers involved:- Process chemical supplier( supplier 1) and Starting Mat. supplier(Supplier 2) ● Lead time for obtaining both material is two weeks by 2 shipment every week.
  • 5. External Customer Requirements ● 50kg of pyrazole acid per month ● Specification for the final product is provided to the production control team. ● Customer order to produce 150 kg within 3 months. ● 3kg material in PTFE cans ● Weekly shipment ● Pharmaceutical company requires orders to come 30 days before shipment. Internal Customer Requirements ● Weekly updates regarding the product dispatch ● Weekly progress from the production team about the new findings and issues in the operation. ● Weekly process data collected in all the operations during all the shifts.
  • 6. Work Time ● 330 days per year ● Three shifts in all production department. ● 8.5 hrs every shift with 30 mins break during each shift. ● Manual process stops during breaks. ● 30mins of lapover time between each shift.
  • 7. Process Information - Reaction ● Batch process with 2 operators per shift. ● Number of shifts: 3 ● Cycle time : 8hrs ● Changeover Time : 4hrs ● Changeover Frequency : 2 per day ● Observed Inventory: o 10 days of unreacted raw materials o 1 day of reacted material. ● Uptime: 67% ● Yield : 100%
  • 8. Process Information - Filtration ● Batch process with 1 operators per shift. ● Number of Shifts: 3 ● Cycle time : 10hrs ● Changeover Time : 3hrs ● Changeover Frequency : 2 per day ● Observed Inventory: o 4 days of filtered material. ● Uptime: 83% ● Yield : 90%
  • 9. Process Information - Distillation ● Batch process with 2 operators per shift. ● Number of shifts : 3 ● Cycle time : 12hrs ● Changeover Time : 12hrs ● Changeover Frequency : 1 per day ● Observed Inventory: o 1 day of final product ● Uptime: 50% ● Yield : 98%
  • 10. Process Information - Packaging ● Manual process with 1 operators per shift. ● Number of Shifts: 1 ● Cycle time : 3hrs ● Changeover Time : 1hr ● Changeover Frequency : 2 per day ● Observed Inventory: o 7 days of packed product ● Uptime: 75%
  • 11. Value Stream Mapping Pilot plant Customer 2 Engineering Design 30 days2 weeks Supplier 2 (Catalyst and starting materials) Supplier 1 (Process Chemicals) Receiving I 10 days Production Control 1 day C/T = 8 hr C/O = 4 hr CoF = 2/day Upt = 67% Yield = 100% Shift = 3 Reaction (O) 2 I 1days C/T = 10 hr C/O = 3 hr CoF = 2/day Upt = 83% Yield = 90% Shift = 3 Filtration (O) 1 I 10hrs I 1 day C/T = 3hr C/O = 1 hr Upt = 75% Shift = 1 Packaging (O) 1 2* week Production Supervisor Weekly 12hrs 3hrs 8hrs 10 days 1 days 4 days 1 days 7 days Total LT = 23days Total VA time = 33hrs Weekly updates Engineering design 1 day Modification 7 days 50 Kg/mo PTFE Can = 3kg Product Dispatch I 7 days4 days Weekly Progress Customer 1 Daily Schedule Checking Modification 2 days C/T = 12 hr C/O = 12 hr CoF = 1/day Upt = 50% Yield = 98% Shift = 3 Distillation (O) 2
  • 12. Takt Time Total available working hours in a month = 27.5 * 24 = 660 hrs Total Quantity to be produced per month = 50 kg Takt Time = Time Available/ Qty Required = 660/50 = 13.2 hrs/kg Overall Cycle time => 33hrs to produce 3 kg = 11 hrs/ Kg Hence the overall cycle time for the process < Takt time
  • 13. (O) 2 C/T = 12 hr C/O = 12 hr CoF = 1/day Upt = 50% Yield = 98% Shift = 3 Value Stream Mapping Pilot plant Customer 2 Engineering Design 30 days2 weeks Supplier 2 (Catalyst and starting materials) Supplier 1 (Process Chemicals) Receiving I 10 days Production Control 1 day C/T = 8 hr C/O = 4 hr CoF = 2/day Upt = 67% Yield = 100% Shift = 3 Reaction I 1days C/T = 10 hr C/O = 3 hr CoF = 2/day Upt = 83% Yield = 90% Shift = 3 Filtration (O) 1 I 10hrs I 1 day C/T = 3hr C/O = 1 hr Upt = 75% Shift = 1 Packaging (O) 1 2* week Production Supervisor Weekly 12hrs 3hrs 8hrs 10 days 1 days 4 days 1 days 7 days Total LT = 23days Total VA time = 33hrs Engineering design 1 day 50 Kg/mo PTFE Can = 3kg Product Dispatch I 7 days4 days Customer 1 Daily Schedule Checking Modification 2 days Distillation (O) 2
  • 14. Area of improvement ● The raw material stays in the warehouse for 10 days before the process is started which needs to be reduced. ● There is holdover for all the intermediate material with the intermediate after filtration to be as high as 4 days. ● The finished product stays in the warehouse for 7 days before the customer pulls it. ● Product stays in inventory for 7 days therefore no.of shift is high. ● Staffing for the reaction and distillation has high number of operator. ● The uptime is very low for the reaction and distillation steps. ● The changeover time is high for all the processes.