- The document is a progress report on a construction project showing planned vs actual quantities and progress percentages for various tasks in June and July 2016.
- Overall project completion is reported at 63.88% with a remaining available budget of $436,824,167.
- Key tasks like opening the airport runway are 79.57% complete while others like clearing debris in rocky terrain are fully completed.
- Earthworks like laying down foundation layers are between 46-57% complete while treating the foundation layer is only 46.7% done.
- The largest individual remaining budgets are for treating the base layer at $105 million and clearing debris at $28.35 million.