1. The document provides steps to start up a new gas turbine compressor (GTC) system, including pressurizing the system, starting up two GTC trains, and shifting process gas flow from the bypass line into the GTC system.
2. It outlines pressing the inlet separator and delivering gas to perform testing on the inlet cooler.
3. The steps also include depressurizing the suction header and opening/closing various valves to start up the two GTC trains and deliver a total gas flowrate of 170 MMSCFD through the system.
1. START UP
1. Power Up New System
2. Pressurize New System
3. Start Up 2 train GTC
4. Shifting Process Gas Flow from Bypass line into GTC System
2. Power Up New System
Start EDG-406
Energize PCR 3, UPS,
PCS/SIS
Energize New IA/UA
System
Energize Purge Gas fro
New Flare and Closed
Drain
Pressurize New Fuel
and Seal Gas Package
Running New Fuel Gas
Heater in one stage
Supply Fuel Gas to new
GTG-404 and 405
Synchronize all power
then shutdown EDG-
406
Operate New Fuel Gas
Heater in Normal Mode