This document provides a status update on the construction of a 115km road from In-Ezzane to Col d'Anai in Algeria. It outlines the planned and actual durations and budgets for each phase of the project. The overall project is 35.26% complete, with an actual end date 12 days behind schedule but within the planned budget. Earthworks are 67.52% complete but 14 days behind schedule. Recharging is 46.42% complete but ahead of schedule and under budget. Treatment work is 27.72% complete and on schedule and budget.