SlideShare a Scribd company logo
1 of 36
6 MONTH INTERNSHIP AT
MADE BY - ADITYA THOMBARE
SYMBIOSIS INSTITUTE OF TECHNOLOGY
PRN- 1700121158
INSIGHT OF THE COMPANY
 KIRLOSKAR BROTHERS LTD, (KBL) incorporated in 1920 is a acknowledged
leader in fluid handling and largest manufacturer and exporter of pumps in
India.
 The company's product range includes a wide range of Centrifugal Pumps
for Agriculture, Domestic, Industrial process , general applications , large
vertical pumps , concrete volute pumps for Power Projects, Water Supply
and Irrigation schemes ranging from Domestic Pumps of 0.375 Kw to
concrete volute pumps of 4500Kw.
 KBL’s Global Network includes Regional Offices in all the major cities in
India and offices and representatives posted in various countries in Europe,
Middle East and South East Asia.
 Its products and services are exported to over 70 countries across five
continents. On both the national and international fronts.
DEPARTMENTS WITHIN THE COMPANY
HRMC
PATTERN
SHOP
FOUNDRY
MACHINE
SHOP
PUMP
TESTING
PACKING
DISPATCH
DEPARTMENT DETAILS
CENTRAL PATTERN MANUFACTURING
CAD CAM
PROCESS DETAILS
 IT STARTS WITH THE DESIGN DEPARTMENT providing the drawing of the related
pump with all details , then the CAD engineer analyses and produces the pattern
and necessary core for making a casting.
 The Manufacturing of a pattern is also decided on the basis of how frequently
they would be utilised-
 Temporary- Thermacol pattern
 Few castings- Wood
 Large requirement – Aluminium
 Besides even dies(Aluminium) are made for making highly finished castings.
 These patterns after their use are stored in pattern store where they can be
reproduced as in when the customer order is generated.
INSIGHT OF THE PATTERN PROCESS
 A casting is made from 2 basic things = Pattern + Core box
 The cores are separated as per convenience for easy casting
removal.
PROJECT DETAILS
The company assigned 3 projects which included :
 Pattern Management System ( Material Management)
 Angular Drilling machine stand (Jig to guide the drill in any angle)
 Reverse Engineering of a impeller
Out of which :
 Pattern Management System took about-- 3 months
 Drilling machine stand took about -- 2 months
 And reverse Engineering project – 1 month
All the 3 project had different impact providing knowledge of various works of
Mechanical Engineering.
PATTERN MANAGEMENT SYSTEM
NEED FOR MANAGEMENT-
 Patterns and Core boxes form the basics of manufacturing a simple casting.
They both are developed on the basis of the requirement or order placed
by the consumer. Pattern along with the core box made is sent to the
foundry for making a casting.
 These patterns and core boxes need to be maintained with proper care so
that they can be re-used when required again. If not maintained, they
further have to be made again which is not at all cost efficient. Thus
maintaining a pattern and its core box is very essential as it is a major asset
to the company, which can cause a great deal of loss.
 Further if not kept at the right place or in a right manner it becomes very
difficult to search or find the necessary pattern when needed. This leads to
panic or dependency of the company to a particular person or authority. To
avoid all such problems, a proper systematic arrangement or a management
is necessary which guides every related employee of the company to search
the required equipment when in need. (Equipment= patter +core box)
SOLUTION PROVIDED
 To avoid all above problems a project of pattern
management was adopted to minimize the effort
 Initially layouts of the stores containing the patterns
were drawn to know the area well and to plan and
utilize the space efficiently
 These storage areas were given particular names and
rack system was adopted to simplify the problem
LAYOUT OF THE EXISTING STORE
 Besides the details of the racks were calculated including
dimensions and giving names to all of them.
 Also in order to create a database of the patterns and core
boxes the equipments were counted manually along with the
name, material, size, date of manufacturing of the pump.
 On the basis of noted data an excel database of about 4000
pieces of both patterns and core boxes were found
 With help of such database the patterns came to be sorted out
on the basis of condition of it.
 After all the data collection the used and unused patterns were
separated and the unused were disposed to the scrap yard and
all the frequently used ones were collected together.
 It was decided to arrange them in the racks on the basis of their sizes
and need.
 Each of the top and bottom and their core boxes were arranged in such a
way that all the work could be done by coming into one store.
 The top were kept in one rack their other half i.e. its bottom was kept in
the rack in front of the earlier rack and their core boxes were kept
below the racks for their easy removal.
 Besides color coding system was to be adopted to recognize particular
equipment.
 So on the basis of series decided the patterns were colored with specific
colors along with their core boxes and a signboard indicating the color
code was put up at the entrance of the pattern store.
Some of the images here describe the related work :
On the basis of color coding a layout containing the
equipments was made to easily guide any related person
within the company -
ANGULAR DRILLING MACHINE STAND
REQIUREMENT :
 The Pattern shop along with manufacturing of Patterns and
Core Boxes also produces dies(Aluminium) for making
Thermacol patterns used for producing high finish castings.
 These dies are made of aluminium and have intricate parts
which are machined on the VMC by using programming.
 These dies need air passages for adding steam in the die to
fuse the Thermacol balls by using a process called REPLICAST
to generate a high finish casting.
 These air passages were manually drilled earlier.
 The parts of the dies have hydraulic shapes of the vane,
casing etc. On which manual drilling caused a lot of problems
like breaking of the drill ,change in the angle in which the
drill has to be drilled and much more.
 In order to overcome all these problems a concept of
making an angular drilling machine stand was generated in
the department which was to be fulfilled.
 With the guidance of the Sir Dhananjay Sankpal (Ass.Manager)
the concept was understood and the 3-D drawing of the concept
was made initially.
 A drawing of the 3-model is shown below-
 By help of this 3-D model a 2-D model was generated and
machining and other tolerances were added by the
MED(Manufacturing Engineering Division) division
 As the stand needed to be sturdy – steel was selected
as the material to be used (WBC)
 The material was searched through the scrap yard and
the material was re-used from the scrap out of which 2
parts were casted out in the ACS foundry by making
Thermacol pattern of each of them.
 All the collected parts were then started to be
machined by considering all the machining allowance
and tolerances.
Following were the manufacturing processes used –
 Facing
 Turning
 Parting
 Drilling
 Milling
 Key way slotting
 Welding
 Grinding
• After machining it was assembled together and a table having
T-slot was found from scrap yard and the assembly was
mounted on the table creating a fix position.
 Later, on testing it was found that modification was necessary
and thus use of linear bearings was done for the smooth
movement of the sliding arm holding the hand drilling machine.
COSTING -
 Approximate cost estimation of the project was done to
calculate the investment done in manufacturing and
show the savings.
This is the detailed costing of each part of the
assembly :
REVERSE ENGINEERING
 A systematic methodology for analyzing the design of an
existing device or system, either as an approach to study the
design or as a prerequisite for re-designs.
 The process of duplicating an existing component,
subassembly or product, without the aid of drawings,
documentation, or computer model is known as reverse
engineering.
Reverse engineering can be viewed as the process of
analyzing a system to:
 Identify the system's components and their
interrelationships.
 Create representations of the system in another form or
a higher level of abstraction.
 Create the physical representation of that system
Need of Reverse Engineering:
 Some bad features of a product need to be design out.
 To strengthen the good features of a product based on
long-term usage of the product.
 To analyze the good and bad features of the competitors
product. To explore new avenues to improve product
performance and features.
 To gain competitive benchmarking methods to
understand competitor's products and develop better
products.
Reverse Engineering is done in 4 stages:
 Stage 1: Evaluation and verification
 Stage 2: Technical data generation
 Stage 3; Design verification
 Stage 4: Project implementation
DATA CAPTURE DATA SEGMENTATION 3D CAD MODEL
AREAS IN WHICH REVERSE ENGINEERING IS APPLICABLE:
 Lost documentation: Reverse engineering often is done because the
documentation of a particular device has been lost (or was never written), and
the person who built it is no longer available. Integrated circuits often seem to
have been designed on obsolete, proprietary systems, which means that the
only way to incorporate the functionality into new technology is to reverse-
engineer the existing chip and then re-design it.
 Product analysis. To examine how a product works, what components it
consists of, estimate costs, and identify potential patent infringement.
 Digital update/correction. To update the digital version (e.g. CAD model) of an
object to match an "as-built" condition.
 Acquiring sensitive data by disassembling and analyzing the design of a system
component [3]
 Military or commercial espionage. Learning about an enemy's or competitor's
latest research by stealing or capturing a prototype and dismantling it.
 Creation of unlicensed/unapproved duplicates.
 Academic/learning purposes.
 Curiosity
 Competitive technical intelligence (understand what your competitor is
actually doing versus what they say they are doing)
 Learning: learn from others' mistakes. Do not make the same mistakes that
others have already made and subsequently corrected
STEPS IN REVERSE ENGINEERING
DATA ACQUISITION TECHNIQUES
THESE WERE THE METHODS FOLLOWED FOR
VERIFICATION OF A PARTICULAR DESIGN
 BESIDES THE PROJECTS GIVEN –THERE WERE SOME 5S
AND KAIZEN INITIATIVES TAKEN ON THE SHOP FLOOR
KAI ZEN
“Kai” in Japanese means
“Change” and “Zen” means
good.
The literary meaning of Kaizen
is
“change for good”
BEFORE/AFTER
BEFORE/AFTER
BEFORE/AFTER
THE END

More Related Content

What's hot

Verification Engineer - Opportunities and Career Path
Verification Engineer - Opportunities and Career PathVerification Engineer - Opportunities and Career Path
Verification Engineer - Opportunities and Career PathRamdas Mozhikunnath
 
Reverse Engineering of Software Architecture
Reverse Engineering of Software ArchitectureReverse Engineering of Software Architecture
Reverse Engineering of Software ArchitectureDharmalingam Ganesan
 
Bristol 2009 q1_eder_kersten
Bristol 2009 q1_eder_kerstenBristol 2009 q1_eder_kersten
Bristol 2009 q1_eder_kerstenObsidian Software
 
Resume_VenkataRakeshGudipalli Master - Copy
Resume_VenkataRakeshGudipalli Master - CopyResume_VenkataRakeshGudipalli Master - Copy
Resume_VenkataRakeshGudipalli Master - CopyVenkata Rakesh Gudipalli
 
SOC Verification using SystemVerilog
SOC Verification using SystemVerilog SOC Verification using SystemVerilog
SOC Verification using SystemVerilog Ramdas Mozhikunnath
 
Static code analysis
Static code analysisStatic code analysis
Static code analysisRune Sundling
 
Ecd302 unit 01(investigate ecad systems)
Ecd302 unit 01(investigate ecad systems)Ecd302 unit 01(investigate ecad systems)
Ecd302 unit 01(investigate ecad systems)Xi Qiu
 
About dfx engineering
About dfx engineeringAbout dfx engineering
About dfx engineeringitzikb
 
No liftoff, touchdown, or heartbeat shall miss because of a software failure
No liftoff, touchdown, or heartbeat shall miss because of a software failureNo liftoff, touchdown, or heartbeat shall miss because of a software failure
No liftoff, touchdown, or heartbeat shall miss because of a software failureRogue Wave Software
 
A comprehensive formal verification solution for ARM based SOC design
A comprehensive formal verification solution for ARM based SOC design A comprehensive formal verification solution for ARM based SOC design
A comprehensive formal verification solution for ARM based SOC design chiportal
 
Classic Formal Methods Model Checking
Classic Formal Methods Model CheckingClassic Formal Methods Model Checking
Classic Formal Methods Model Checkingtyramisu
 
Interface-Implementation Contract Checking
Interface-Implementation Contract CheckingInterface-Implementation Contract Checking
Interface-Implementation Contract CheckingDharmalingam Ganesan
 
Design for testability as a way to good coding (SOLID and IoC)
Design for testability as a way to good coding (SOLID and IoC)Design for testability as a way to good coding (SOLID and IoC)
Design for testability as a way to good coding (SOLID and IoC)Simone Chiaretta
 
HIS 2015: Neil White - Advances in Practical Techniques for Critical Developm...
HIS 2015: Neil White - Advances in Practical Techniques for Critical Developm...HIS 2015: Neil White - Advances in Practical Techniques for Critical Developm...
HIS 2015: Neil White - Advances in Practical Techniques for Critical Developm...AdaCore
 

What's hot (20)

Verification Engineer - Opportunities and Career Path
Verification Engineer - Opportunities and Career PathVerification Engineer - Opportunities and Career Path
Verification Engineer - Opportunities and Career Path
 
Bangalore march07
Bangalore march07Bangalore march07
Bangalore march07
 
Reverse Engineering of Software Architecture
Reverse Engineering of Software ArchitectureReverse Engineering of Software Architecture
Reverse Engineering of Software Architecture
 
Bristol 2009 q1_eder_kersten
Bristol 2009 q1_eder_kerstenBristol 2009 q1_eder_kersten
Bristol 2009 q1_eder_kersten
 
Resume_VenkataRakeshGudipalli Master - Copy
Resume_VenkataRakeshGudipalli Master - CopyResume_VenkataRakeshGudipalli Master - Copy
Resume_VenkataRakeshGudipalli Master - Copy
 
Shivani_Saklani
Shivani_SaklaniShivani_Saklani
Shivani_Saklani
 
SOC Verification using SystemVerilog
SOC Verification using SystemVerilog SOC Verification using SystemVerilog
SOC Verification using SystemVerilog
 
Design For Testability
Design For TestabilityDesign For Testability
Design For Testability
 
Static code analysis
Static code analysisStatic code analysis
Static code analysis
 
Firstenberg q207
Firstenberg q207Firstenberg q207
Firstenberg q207
 
Ecd302 unit 01(investigate ecad systems)
Ecd302 unit 01(investigate ecad systems)Ecd302 unit 01(investigate ecad systems)
Ecd302 unit 01(investigate ecad systems)
 
About dfx engineering
About dfx engineeringAbout dfx engineering
About dfx engineering
 
VLSI testing and analysis
VLSI testing and analysisVLSI testing and analysis
VLSI testing and analysis
 
No liftoff, touchdown, or heartbeat shall miss because of a software failure
No liftoff, touchdown, or heartbeat shall miss because of a software failureNo liftoff, touchdown, or heartbeat shall miss because of a software failure
No liftoff, touchdown, or heartbeat shall miss because of a software failure
 
A comprehensive formal verification solution for ARM based SOC design
A comprehensive formal verification solution for ARM based SOC design A comprehensive formal verification solution for ARM based SOC design
A comprehensive formal verification solution for ARM based SOC design
 
Classic Formal Methods Model Checking
Classic Formal Methods Model CheckingClassic Formal Methods Model Checking
Classic Formal Methods Model Checking
 
Interface-Implementation Contract Checking
Interface-Implementation Contract CheckingInterface-Implementation Contract Checking
Interface-Implementation Contract Checking
 
Resume-06-13-2016
Resume-06-13-2016Resume-06-13-2016
Resume-06-13-2016
 
Design for testability as a way to good coding (SOLID and IoC)
Design for testability as a way to good coding (SOLID and IoC)Design for testability as a way to good coding (SOLID and IoC)
Design for testability as a way to good coding (SOLID and IoC)
 
HIS 2015: Neil White - Advances in Practical Techniques for Critical Developm...
HIS 2015: Neil White - Advances in Practical Techniques for Critical Developm...HIS 2015: Neil White - Advances in Practical Techniques for Critical Developm...
HIS 2015: Neil White - Advances in Practical Techniques for Critical Developm...
 

Viewers also liked

summer training Certificate
summer training Certificatesummer training Certificate
summer training CertificateAjay Kumar
 
Project Report on Industrial Summer Training at NTPC Simhadri
 Project Report on Industrial Summer Training at NTPC Simhadri Project Report on Industrial Summer Training at NTPC Simhadri
Project Report on Industrial Summer Training at NTPC SimhadriAshish Uppu
 
TRRAIN: Internship certificate
TRRAIN: Internship certificateTRRAIN: Internship certificate
TRRAIN: Internship certificateNeil Merchant
 
Internship Project Power Point Presentation
Internship Project Power Point PresentationInternship Project Power Point Presentation
Internship Project Power Point PresentationDavid Mugerwa
 
Internship Certificate
Internship CertificateInternship Certificate
Internship Certificatengoswami
 
Final Year Project Presentation
Final Year Project PresentationFinal Year Project Presentation
Final Year Project PresentationSyed Absar
 
Presentation on project report
Presentation on project reportPresentation on project report
Presentation on project reportramesh_x
 
Summer internship report L&T
Summer internship report L&TSummer internship report L&T
Summer internship report L&TUmed Paliwal
 
Internship Report on Building Construction
Internship Report on Building ConstructionInternship Report on Building Construction
Internship Report on Building ConstructionEsmael Aragaw
 

Viewers also liked (9)

summer training Certificate
summer training Certificatesummer training Certificate
summer training Certificate
 
Project Report on Industrial Summer Training at NTPC Simhadri
 Project Report on Industrial Summer Training at NTPC Simhadri Project Report on Industrial Summer Training at NTPC Simhadri
Project Report on Industrial Summer Training at NTPC Simhadri
 
TRRAIN: Internship certificate
TRRAIN: Internship certificateTRRAIN: Internship certificate
TRRAIN: Internship certificate
 
Internship Project Power Point Presentation
Internship Project Power Point PresentationInternship Project Power Point Presentation
Internship Project Power Point Presentation
 
Internship Certificate
Internship CertificateInternship Certificate
Internship Certificate
 
Final Year Project Presentation
Final Year Project PresentationFinal Year Project Presentation
Final Year Project Presentation
 
Presentation on project report
Presentation on project reportPresentation on project report
Presentation on project report
 
Summer internship report L&T
Summer internship report L&TSummer internship report L&T
Summer internship report L&T
 
Internship Report on Building Construction
Internship Report on Building ConstructionInternship Report on Building Construction
Internship Report on Building Construction
 

Similar to 6 MONTH INTERNSHIP AT

OPTIMIZED MANUFACTURING PROCESSES FOR COOLER TANK
OPTIMIZED MANUFACTURING PROCESSES FOR COOLER TANKOPTIMIZED MANUFACTURING PROCESSES FOR COOLER TANK
OPTIMIZED MANUFACTURING PROCESSES FOR COOLER TANKIjripublishers Ijri
 
OPTIMIZED MANUFACTURING PROCESSES FOR COOLER TANK
OPTIMIZED MANUFACTURING PROCESSES FOR COOLER TANKOPTIMIZED MANUFACTURING PROCESSES FOR COOLER TANK
OPTIMIZED MANUFACTURING PROCESSES FOR COOLER TANKIjripublishers Ijri
 
Introduction of design of machine element
Introduction of design of machine elementIntroduction of design of machine element
Introduction of design of machine elementyamini champaneri
 
1 a. Introduction design of machine element
1 a. Introduction   design of machine element1 a. Introduction   design of machine element
1 a. Introduction design of machine elementDr.R. SELVAM
 
Karl Zemlin resume 2017
Karl Zemlin resume 2017Karl Zemlin resume 2017
Karl Zemlin resume 2017Karl Zemlin
 
Unit 5 design for manufacturing
Unit 5 design for manufacturing Unit 5 design for manufacturing
Unit 5 design for manufacturing arivumani ravanan
 
Computer Aided Design - Unit I Introduction
Computer Aided Design - Unit I IntroductionComputer Aided Design - Unit I Introduction
Computer Aided Design - Unit I IntroductionJayavendhanJ
 
Preliminary Study of an Assembling Plant
Preliminary Study of an Assembling Plant Preliminary Study of an Assembling Plant
Preliminary Study of an Assembling Plant MustafaElAkkad
 
OPTIMIZED DIE STRUCTURE DESIGN OF PLASTIC INJECTION MOULD USING FEM TECHNIQUE
OPTIMIZED DIE STRUCTURE DESIGN OF PLASTIC INJECTION MOULD USING FEM TECHNIQUEOPTIMIZED DIE STRUCTURE DESIGN OF PLASTIC INJECTION MOULD USING FEM TECHNIQUE
OPTIMIZED DIE STRUCTURE DESIGN OF PLASTIC INJECTION MOULD USING FEM TECHNIQUEIjripublishers Ijri
 
OPTIMIZED DIE STRUCTURE DESIGN OF PLASTIC INJECTION MOULD USING FEM TECHNIQUE
OPTIMIZED DIE STRUCTURE DESIGN OF PLASTIC INJECTION MOULD USING FEM TECHNIQUEOPTIMIZED DIE STRUCTURE DESIGN OF PLASTIC INJECTION MOULD USING FEM TECHNIQUE
OPTIMIZED DIE STRUCTURE DESIGN OF PLASTIC INJECTION MOULD USING FEM TECHNIQUEIjripublishers Ijri
 
SIMUL8 User Group - Visual8 Case Study - Plywood Manufacturing.
SIMUL8 User Group - Visual8 Case Study - Plywood Manufacturing. SIMUL8 User Group - Visual8 Case Study - Plywood Manufacturing.
SIMUL8 User Group - Visual8 Case Study - Plywood Manufacturing. SIMUL8 Corporation
 
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh AroraIntroduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh AroraADD VALUE CONSULTING Inc
 
Reverse engineering & its application
Reverse engineering & its applicationReverse engineering & its application
Reverse engineering & its applicationmapqrs
 
Emgineering Design Portfolio
Emgineering Design PortfolioEmgineering Design Portfolio
Emgineering Design PortfolioTsuyoshi Yokoyama
 
Company Presentation 2015
Company Presentation 2015Company Presentation 2015
Company Presentation 2015Mach Cao Xuan
 
Group technology ppt @ bec doms
Group technology ppt @ bec domsGroup technology ppt @ bec doms
Group technology ppt @ bec domsBabasab Patil
 
Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Chris Baichoo
 

Similar to 6 MONTH INTERNSHIP AT (20)

OPTIMIZED MANUFACTURING PROCESSES FOR COOLER TANK
OPTIMIZED MANUFACTURING PROCESSES FOR COOLER TANKOPTIMIZED MANUFACTURING PROCESSES FOR COOLER TANK
OPTIMIZED MANUFACTURING PROCESSES FOR COOLER TANK
 
OPTIMIZED MANUFACTURING PROCESSES FOR COOLER TANK
OPTIMIZED MANUFACTURING PROCESSES FOR COOLER TANKOPTIMIZED MANUFACTURING PROCESSES FOR COOLER TANK
OPTIMIZED MANUFACTURING PROCESSES FOR COOLER TANK
 
Introduction of design of machine element
Introduction of design of machine elementIntroduction of design of machine element
Introduction of design of machine element
 
1 a. Introduction design of machine element
1 a. Introduction   design of machine element1 a. Introduction   design of machine element
1 a. Introduction design of machine element
 
Karl Zemlin resume 2017
Karl Zemlin resume 2017Karl Zemlin resume 2017
Karl Zemlin resume 2017
 
Unit 5 design for manufacturing
Unit 5 design for manufacturing Unit 5 design for manufacturing
Unit 5 design for manufacturing
 
Portfolio 2016
Portfolio 2016Portfolio 2016
Portfolio 2016
 
Computer Aided Design - Unit I Introduction
Computer Aided Design - Unit I IntroductionComputer Aided Design - Unit I Introduction
Computer Aided Design - Unit I Introduction
 
Preliminary Study of an Assembling Plant
Preliminary Study of an Assembling Plant Preliminary Study of an Assembling Plant
Preliminary Study of an Assembling Plant
 
OPTIMIZED DIE STRUCTURE DESIGN OF PLASTIC INJECTION MOULD USING FEM TECHNIQUE
OPTIMIZED DIE STRUCTURE DESIGN OF PLASTIC INJECTION MOULD USING FEM TECHNIQUEOPTIMIZED DIE STRUCTURE DESIGN OF PLASTIC INJECTION MOULD USING FEM TECHNIQUE
OPTIMIZED DIE STRUCTURE DESIGN OF PLASTIC INJECTION MOULD USING FEM TECHNIQUE
 
OPTIMIZED DIE STRUCTURE DESIGN OF PLASTIC INJECTION MOULD USING FEM TECHNIQUE
OPTIMIZED DIE STRUCTURE DESIGN OF PLASTIC INJECTION MOULD USING FEM TECHNIQUEOPTIMIZED DIE STRUCTURE DESIGN OF PLASTIC INJECTION MOULD USING FEM TECHNIQUE
OPTIMIZED DIE STRUCTURE DESIGN OF PLASTIC INJECTION MOULD USING FEM TECHNIQUE
 
Group Technology
Group TechnologyGroup Technology
Group Technology
 
CAD _ UNIT 1.pptx
CAD _ UNIT 1.pptxCAD _ UNIT 1.pptx
CAD _ UNIT 1.pptx
 
SIMUL8 User Group - Visual8 Case Study - Plywood Manufacturing.
SIMUL8 User Group - Visual8 Case Study - Plywood Manufacturing. SIMUL8 User Group - Visual8 Case Study - Plywood Manufacturing.
SIMUL8 User Group - Visual8 Case Study - Plywood Manufacturing.
 
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh AroraIntroduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
 
Reverse engineering & its application
Reverse engineering & its applicationReverse engineering & its application
Reverse engineering & its application
 
Emgineering Design Portfolio
Emgineering Design PortfolioEmgineering Design Portfolio
Emgineering Design Portfolio
 
Company Presentation 2015
Company Presentation 2015Company Presentation 2015
Company Presentation 2015
 
Group technology ppt @ bec doms
Group technology ppt @ bec domsGroup technology ppt @ bec doms
Group technology ppt @ bec doms
 
Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006
 

6 MONTH INTERNSHIP AT

  • 1. 6 MONTH INTERNSHIP AT MADE BY - ADITYA THOMBARE SYMBIOSIS INSTITUTE OF TECHNOLOGY PRN- 1700121158
  • 2. INSIGHT OF THE COMPANY  KIRLOSKAR BROTHERS LTD, (KBL) incorporated in 1920 is a acknowledged leader in fluid handling and largest manufacturer and exporter of pumps in India.  The company's product range includes a wide range of Centrifugal Pumps for Agriculture, Domestic, Industrial process , general applications , large vertical pumps , concrete volute pumps for Power Projects, Water Supply and Irrigation schemes ranging from Domestic Pumps of 0.375 Kw to concrete volute pumps of 4500Kw.  KBL’s Global Network includes Regional Offices in all the major cities in India and offices and representatives posted in various countries in Europe, Middle East and South East Asia.  Its products and services are exported to over 70 countries across five continents. On both the national and international fronts.
  • 3. DEPARTMENTS WITHIN THE COMPANY HRMC PATTERN SHOP FOUNDRY MACHINE SHOP PUMP TESTING PACKING DISPATCH
  • 4. DEPARTMENT DETAILS CENTRAL PATTERN MANUFACTURING CAD CAM
  • 5. PROCESS DETAILS  IT STARTS WITH THE DESIGN DEPARTMENT providing the drawing of the related pump with all details , then the CAD engineer analyses and produces the pattern and necessary core for making a casting.  The Manufacturing of a pattern is also decided on the basis of how frequently they would be utilised-  Temporary- Thermacol pattern  Few castings- Wood  Large requirement – Aluminium  Besides even dies(Aluminium) are made for making highly finished castings.  These patterns after their use are stored in pattern store where they can be reproduced as in when the customer order is generated.
  • 6. INSIGHT OF THE PATTERN PROCESS  A casting is made from 2 basic things = Pattern + Core box  The cores are separated as per convenience for easy casting removal.
  • 7. PROJECT DETAILS The company assigned 3 projects which included :  Pattern Management System ( Material Management)  Angular Drilling machine stand (Jig to guide the drill in any angle)  Reverse Engineering of a impeller Out of which :  Pattern Management System took about-- 3 months  Drilling machine stand took about -- 2 months  And reverse Engineering project – 1 month All the 3 project had different impact providing knowledge of various works of Mechanical Engineering.
  • 8. PATTERN MANAGEMENT SYSTEM NEED FOR MANAGEMENT-  Patterns and Core boxes form the basics of manufacturing a simple casting. They both are developed on the basis of the requirement or order placed by the consumer. Pattern along with the core box made is sent to the foundry for making a casting.  These patterns and core boxes need to be maintained with proper care so that they can be re-used when required again. If not maintained, they further have to be made again which is not at all cost efficient. Thus maintaining a pattern and its core box is very essential as it is a major asset to the company, which can cause a great deal of loss.  Further if not kept at the right place or in a right manner it becomes very difficult to search or find the necessary pattern when needed. This leads to panic or dependency of the company to a particular person or authority. To avoid all such problems, a proper systematic arrangement or a management is necessary which guides every related employee of the company to search the required equipment when in need. (Equipment= patter +core box)
  • 9. SOLUTION PROVIDED  To avoid all above problems a project of pattern management was adopted to minimize the effort  Initially layouts of the stores containing the patterns were drawn to know the area well and to plan and utilize the space efficiently  These storage areas were given particular names and rack system was adopted to simplify the problem
  • 10. LAYOUT OF THE EXISTING STORE
  • 11.  Besides the details of the racks were calculated including dimensions and giving names to all of them.
  • 12.  Also in order to create a database of the patterns and core boxes the equipments were counted manually along with the name, material, size, date of manufacturing of the pump.  On the basis of noted data an excel database of about 4000 pieces of both patterns and core boxes were found  With help of such database the patterns came to be sorted out on the basis of condition of it.  After all the data collection the used and unused patterns were separated and the unused were disposed to the scrap yard and all the frequently used ones were collected together.
  • 13.  It was decided to arrange them in the racks on the basis of their sizes and need.  Each of the top and bottom and their core boxes were arranged in such a way that all the work could be done by coming into one store.  The top were kept in one rack their other half i.e. its bottom was kept in the rack in front of the earlier rack and their core boxes were kept below the racks for their easy removal.  Besides color coding system was to be adopted to recognize particular equipment.  So on the basis of series decided the patterns were colored with specific colors along with their core boxes and a signboard indicating the color code was put up at the entrance of the pattern store.
  • 14. Some of the images here describe the related work :
  • 15. On the basis of color coding a layout containing the equipments was made to easily guide any related person within the company -
  • 16. ANGULAR DRILLING MACHINE STAND REQIUREMENT :  The Pattern shop along with manufacturing of Patterns and Core Boxes also produces dies(Aluminium) for making Thermacol patterns used for producing high finish castings.
  • 17.  These dies are made of aluminium and have intricate parts which are machined on the VMC by using programming.  These dies need air passages for adding steam in the die to fuse the Thermacol balls by using a process called REPLICAST to generate a high finish casting.  These air passages were manually drilled earlier.  The parts of the dies have hydraulic shapes of the vane, casing etc. On which manual drilling caused a lot of problems like breaking of the drill ,change in the angle in which the drill has to be drilled and much more.  In order to overcome all these problems a concept of making an angular drilling machine stand was generated in the department which was to be fulfilled.
  • 18.  With the guidance of the Sir Dhananjay Sankpal (Ass.Manager) the concept was understood and the 3-D drawing of the concept was made initially.  A drawing of the 3-model is shown below-
  • 19.  By help of this 3-D model a 2-D model was generated and machining and other tolerances were added by the MED(Manufacturing Engineering Division) division
  • 20.  As the stand needed to be sturdy – steel was selected as the material to be used (WBC)  The material was searched through the scrap yard and the material was re-used from the scrap out of which 2 parts were casted out in the ACS foundry by making Thermacol pattern of each of them.  All the collected parts were then started to be machined by considering all the machining allowance and tolerances.
  • 21. Following were the manufacturing processes used –  Facing  Turning  Parting  Drilling  Milling  Key way slotting  Welding  Grinding
  • 22. • After machining it was assembled together and a table having T-slot was found from scrap yard and the assembly was mounted on the table creating a fix position.
  • 23.  Later, on testing it was found that modification was necessary and thus use of linear bearings was done for the smooth movement of the sliding arm holding the hand drilling machine.
  • 24. COSTING -  Approximate cost estimation of the project was done to calculate the investment done in manufacturing and show the savings.
  • 25. This is the detailed costing of each part of the assembly :
  • 26. REVERSE ENGINEERING  A systematic methodology for analyzing the design of an existing device or system, either as an approach to study the design or as a prerequisite for re-designs.  The process of duplicating an existing component, subassembly or product, without the aid of drawings, documentation, or computer model is known as reverse engineering. Reverse engineering can be viewed as the process of analyzing a system to:  Identify the system's components and their interrelationships.  Create representations of the system in another form or a higher level of abstraction.  Create the physical representation of that system
  • 27. Need of Reverse Engineering:  Some bad features of a product need to be design out.  To strengthen the good features of a product based on long-term usage of the product.  To analyze the good and bad features of the competitors product. To explore new avenues to improve product performance and features.  To gain competitive benchmarking methods to understand competitor's products and develop better products.
  • 28. Reverse Engineering is done in 4 stages:  Stage 1: Evaluation and verification  Stage 2: Technical data generation  Stage 3; Design verification  Stage 4: Project implementation DATA CAPTURE DATA SEGMENTATION 3D CAD MODEL
  • 29. AREAS IN WHICH REVERSE ENGINEERING IS APPLICABLE:  Lost documentation: Reverse engineering often is done because the documentation of a particular device has been lost (or was never written), and the person who built it is no longer available. Integrated circuits often seem to have been designed on obsolete, proprietary systems, which means that the only way to incorporate the functionality into new technology is to reverse- engineer the existing chip and then re-design it.  Product analysis. To examine how a product works, what components it consists of, estimate costs, and identify potential patent infringement.  Digital update/correction. To update the digital version (e.g. CAD model) of an object to match an "as-built" condition.  Acquiring sensitive data by disassembling and analyzing the design of a system component [3]  Military or commercial espionage. Learning about an enemy's or competitor's latest research by stealing or capturing a prototype and dismantling it.  Creation of unlicensed/unapproved duplicates.  Academic/learning purposes.  Curiosity  Competitive technical intelligence (understand what your competitor is actually doing versus what they say they are doing)  Learning: learn from others' mistakes. Do not make the same mistakes that others have already made and subsequently corrected
  • 30. STEPS IN REVERSE ENGINEERING
  • 32. THESE WERE THE METHODS FOLLOWED FOR VERIFICATION OF A PARTICULAR DESIGN
  • 33.  BESIDES THE PROJECTS GIVEN –THERE WERE SOME 5S AND KAIZEN INITIATIVES TAKEN ON THE SHOP FLOOR KAI ZEN “Kai” in Japanese means “Change” and “Zen” means good. The literary meaning of Kaizen is “change for good”
  • 34.