SlideShare a Scribd company logo
1 of 33
Electrical Distribution System
Name of the Faculty : Adithya Ballaji
School of Electrical and Electronics Engineering
Unit 3: System Planning and Reliability
School of Electrical and Electronics Engineering, REVA
University
Syllabus
β€’ Planning process, planning criteria, system developers, dispersed generation, distribution systems,
economics and finance, mapping. Load Characteristics - Basic definition, relation between load
and load factor, load growth.
β€’ Reliability-Basic reliability concept –Cost verses system Reliability –Reliability planning
procedure–Mathematical concept.
School of Electrical and Electronics Engineering, REVA
University
Introduction
β€’ Planning is the process of taking careful decision. The main input in planning
is quality and systematic thought.
β€’ It involves selecting the first a vision, values, mission and objective and deciding what should be
done to attain them.
β€’ The main objective of distribution planning is to provide satisfactory service at lowest possible
cost.
β€’ In power utility, the planning process is used to identify the best schedule of future resources and
actions to achieve the utility goal.
β€’ Planning is driven by two inputs:
1. Future Needs
2. Time needed to fulfil these needs with defined master plan.
β€’ Long term planning (5-10 years) determines the power energy forecasts and optimum network
arrangements.
β€’ A short term planning involves the planning for current year and next year annual plans, and
subsequent years.
School of Electrical and Electronics Engineering, REVA
University
Steps involved in Planning Process
β€’ Feasibility studies are carried out to identify, evaluate and finalize the best plan.
1. Define the problem
2. Find the alternative
3. Evaluate the alternative
4. Select the best one
β€’ Project report for long, medium, short term works along with the action plan/pert chart/bar chart
for each activity/ work is prepared and dates are set for milestones.
β€’ Final approval is taken after financial and economic appraisal.
β€’ Once the best plan is selected the next stage of process is inititated.
School of Electrical and Electronics Engineering, REVA
University
Flow chart of Planning Process
School of Electrical and Electronics Engineering, REVA
University
Planning Actions
School of Electrical and Electronics Engineering, REVA
University
Planning Criteria and Standards
β€’ Criteria and standards together form a set of requirements against which the planning process can
compare alternatives in the evaluation and final choice.
β€’ A distribution plan must provided with least cost and also satisfy various criteria and standards.
β€’ Criteria are rules or procedures.
β€’ Standards are specifications to ensure that the system is built with compatible equipment that will
fit and function together when installed and maintained in an economical manner.
β€’ Standards and criteria and their application to the planning process depends upon vision, mission
and the value system of the utility.
β€’ Criteria and standards convey direction in the master plan.
β€’ Planning standards exists for reasons of efficiency and to achieve the reduced investment
β€’ The system may use various Indian standards, Indian Electricity Rules, Rural Electrification
Corporation Standards, IEC, ISO and electricity act 2003.
β€’ These criteria and standards are used for better and improved power utility their by to achieve its
objective.
School of Electrical and Electronics Engineering, REVA
University
Typical Criteria for Planning
The following are the typical criteria for planning:
β€’ A prospective plan for the next 15 years to meet the anticipated load growth and forecast load
centers.
β€’ The plan should be reviewed yearly on the basis of annual plans with respect to the targets
achieved.
β€’ Detailed project reports be framed to identify the system strengthening works on long term and
short term bases.
β€’ Demand side management projects reports be prepared to achieve tangible reduction in demand
and energy consumption on the planned year.
β€’ Security of supply is one of the important factors for planning, for example, In industrial cities
supply to be provide using sub transmission open circuit of 33 or 66 or 132 or 220kV, 11kV open
ring main circuit for all urban area, and separate independent feeders to be provided for major
industrial consumers and rural areas.
β€’ Power utility needs to use and create load research facilities to study and identify load profiles in
the particular area.
School of Electrical and Electronics Engineering, REVA
University
Typical Criteria for Planning
β€’ The number of 11kV outgoing feeders at distribution station should not exceed 15.
β€’ The length of 11kV outgoing feeder emanating from substation up-to tail end not to be more than
12km.
β€’ Improved metering, that is to provide electronic meters to all the consumers.
β€’ Total harmonic distortion at any voltage level should be within 5 per cent.
School of Electrical and Electronics Engineering, REVA
University
Types of planning standards
β€’ Development of standard cost structure for material and labour rates for different voltages
to be used in the estimation.
β€’ Use of standard system voltages as per Indian standards and voltage regulation as per IE Rules.
β€’ The load growth of at least 10 years will considered to prepare new or system improvement
schemes.
β€’ Shunt capacitor fixed / switched type shall be installed in distribution system to improve the power
factor and voltage profile there by reducing transmission and distribution losses.
β€’ Fixed LT capacitor should be installed on the distribution transformers.
School of Electrical and Electronics Engineering, REVA
University
Distribution system Economics and Finance
β€’ Economic analysis is carried out to determine the lo cost plan among various alternatives.
β€’ Financial analysis determines the rate of return and risk involved on the investment to be made on
the plan.
β€’ The investment to carry out a planned distribution is either:
1. Annual expenses : Obtained from operating revenue
2. Capital expenditure : obtained from financing, reinvested reserve etc.
3. Both annual expenses and capital expenditure
Following methods are used for Investment decision :
1. Minimum Revenue Requirement
β€’ Time value money
β€’ Revenue Requirement of Investment
2. Financial Method
β€’ Benefit/Cost Ration
β€’ Internal Rate of Return( IRR)
School of Electrical and Electronics Engineering, REVA
University
Minimum Revenue Requirement
β€’ In this type of method choice is made on the basis of the present value of all future
annual costs.
β€’ The economic choice is made based on the one with lowest present value of all the future cost.
β€’ The economic comparison is done based on two steps:
1. Estimating the annual cost of each year
2. If the annual costs are not uniform, calculate their present value.
Time Value Money:
β€’ Here money has time value and interest on its use has to be paid. The rate of interest is determined
by the reserve Bank of India according to economic condition at the time.
β€’ There is a similar mechanism to determine the interest rate at the international level also.
β€’ The process of taking money and finding its equivalent value at some future date is called future
value calculation.
β€’ The process of finding the equivalent value at some earlier time is called present value
calculation.
School of Electrical and Electronics Engineering, REVA
University
Minimum Revenue Requirement
Revenue Requirement of Investment:
β€’ The total revenue requirement of investment is the sim of the annual charges extending over
the service life.
It includes:
1. Return on investment
2. Depreciation
3. Insurance expenses
4. Operating and Maintenance expenses
5. Interest on loan capital and working capital
6. Taxes etc.
The above charges can be conveniently estimated as a percentage of original investment. And three
methods to calculate the present value are:
1. Cumulative present worth method
2. Levelised Annual Cost Method
3. Uniform series present worth Method
School of Electrical and Electronics Engineering, REVA
University
Financial Analysis
It can be classified into :
1. Benefit / cost ratio
2. Internal Rate of Return ( IRR)
Benefit / cost ratio
β€’ This method ranks a project by the ratio of the present value of revenue and benefits earned to the
present value of the costs incurred.
β€’ System improvement works are generally evaluated on a benefit – cost basis by the rural
electrification corporation of India.
β€’ The central Electricity Authority (CEA) also uses this method for such schemes, based on lifecycle
(25-30 year period) cost benefits.
β€’ The works proposed for strengthening, upgradation and improvement of sub- transmission and
distribution helps in reducing technical and commercial losses by the year.
β€’ The financial analysis is usually done for the for lifetime of projects considering the year wise
costs including interest, depreciation, operation and maintenance charges.
School of Electrical and Electronics Engineering, REVA
University
Financial Analysis
Internal Rate of Return ( IRR)
β€’ The design and sustainability of the project should take into account the level of incentive for
undertaking and maintaining a project investment.
β€’ The financial incentive takes the form of increased income that the investment generates with the
execution of the project.
β€’ This method calculates the rate of interest needed for the present value of the returns to be the same
as the present value of the investment needed.
β€’ Rural Electrification Corporation specifies the IRR as 15 percent while sanctioning short term
( seven year repayment) loan scheme.
School of Electrical and Electronics Engineering, REVA
University
Mapping
β€’ Creating a geodatabase containing relevant information about assets in existing electrical
distribution system.
β€’ Types of Mapping:
β€’ Global Positioning System (GPS)
1. Back ground Maps
2. Digital Mapping
3. Automated Mapping (AM)/ Facilities Management (FM)/ Geographical Information System
(GIS)
4. Enterprise Resource Planning (ERP)
School of Electrical and Electronics Engineering, REVA
University
Mapping
Global Positioning System (GPS)
β€’ GPS is a system in which earth orbiting satellites provide precise information on time and position
enabling GPS receiving devices to compute position on earth.
β€’ Signals must be received from at least three satellites in order to establish the latitude and longitude
of receiver position.
β€’ A fourth satellite is required to calculate the altitude.
β€’ GPS technology is used to locate tap-off points, transformers and other facilities of power
distribution networks and consequently to map the system with an accuracy of up to one meter.
β€’ GPS can be used to capture data for 11kV and above voltage level distribution/sub transmission
lines and substations/distribution transformer for mapping.
β€’ For LT network each distribution transformer geographical maps on paper can be drawn based on
judgment and eye approximately.
β€’ The length of the feeder is generally fixed, based on estimates and pole to pole standard distances.
β€’ These maps can be prepared on survey of India sheets
School of Electrical and Electronics Engineering, REVA
University
Mapping
Digital Mapping
β€’ Digital mapping software can be used to create an integrated and automated facilities model
in which paper maps are first digitized and then suitably linked.
β€’ A digitizer board is used for digitizing nodes with respect to a reference point pre-fixed on the map.
β€’ One person can read co-ordinates on the digitized board and other can feed it into a computer.
β€’ Once digitization is complete, the software numbers the nodes, draws the network diagram and
calculates the lengths.
β€’ Network drawn with a computer then undergo field verification.
β€’ A computer processing centre will then issue a prescribed format to obtain electrical loading data
of feeders, transformer capacity, size/type of feeder for the concerned area.
School of Electrical and Electronics Engineering, REVA
University
Digital Mapping
The following steps should be taken to prepare the maps:
1. The complete area should be covered and duplication avoided.
2. The 132-33kV system be digitized first then followed by 11kV and finally the 400kV network.
3. Devices like GPS and VHF sets may be required for dense urban areas to capture attributes
accurately and ensuring high frequency digitized maps.
4. Oracle RDBMS is suitable for data storage. Digital mapping process is shown below:
School of Electrical and Electronics Engineering, REVA
University
Automated Mapping (AM) / Facilities Management (FM)/
Geographical Information System (GIS)
β€’ Every transaction whether it is a work order, billing, operation, system improvements or
maintenance is tied to a location.
β€’ AM and FM provide an integrated tool to create an automated facilities model and help to convert
paper maps to a digital environment where the system details and its changes are fed and stored in
a graphic and tabular database.
β€’ The graphic data is representation of the network and is the backbone of an AM/FM/GIS system
and the driving force for all the application.
β€’ FM software links the graphic network map to tabular and non-graphic data associated with the
databases, work order drawing etc.
β€’ GIS establishes the connection to these databases through a record server and provides the best
characteristics of AM and FM system to provide an integrated information system.
School of Electrical and Electronics Engineering, REVA
University
Role of Geographical Information System (GIS) and
its application
β€’ GIS is a system of mapping of complete electrical network including low voltage system
and consumer meter.
β€’ Database plays a central role in the operation of planning, where analysis programme form a part
of system supported by a database management system which stores, retrieves and modifies
various data on the distribution system.
β€’ The main role of GIS is to integrate the dynamic side of the operation with the relatively static side
of the utility facility record for effective utilization by all functional departments and personnel.
β€’ The various roles include:
1. Detailed space representation of the facilities and network linked to the related data.
2. Integrated facility database and its management with multi user access.
3. Management of different stages of the facility’s life cycle.
4. Optimum data for facility application.
School of Electrical and Electronics Engineering, REVA
University
Role of Geographical Information System (GIS) and
its application
β€’ Applications:
1. The planning department will be needing field data of land records, load growth based on
population growth and demand, existing network layout.
2. The data is required for feeder layout/routing and network planning, load flow analysis,
protective devices locations.
3. Estimation and Costing
4. Management reports
5. Design / operational logistics
6. Maintenance
7. Troubleshooting School of Electrical and Electronics Engineering, REVA
University
Load Characteristics
Basic Definitions
Demand
β€’ The demand of an installation or system is the load at the receiving terminals averaged over a
specified interval of time. Here the load may be given in kilowatts, kilovars, kilovolt amperes, kilo
amperes or amperes
Demand interval
β€’ It is the period over which the load is averaged. This selected βˆ†t period may be 15min, 30min or
even longer.
Maximum Demand
β€’ The maximum demand of an installation or system is the greatest of all demands which have
occurred during the specified period of time. The maximum demand statement should also express
the demand interval used to measure it. For example, the specific demand might be the maximum
of all demands such as daily, weekly, monthly or annual.
School of Electrical and Electronics Engineering, REVA
University
Daily Demand variation curve
School of Electrical and Electronics Engineering, REVA
University
Basic Definitions
Utilization Factor
β€’ It is the ratio of maximum demand of the system to the rated capacity of the system. Thus
utilization factor is denoted as 𝑭 𝒖
𝑭 𝒖 =
π‘΄π’‚π’™π’Šπ’Žπ’–π’Ž π‘«π’†π’Žπ’‚π’π’…
𝑹𝒂𝒕𝒆𝒅 π‘Ίπ’šπ’”π’•π’†π’Ž π‘ͺπ’‚π’‘π’‚π’„π’Šπ’•π’š
Plant Factor
β€’ It is the ratio of the total actual energy produced or served over a designated period of time to the
energy that would have been produced or served of the plant had operated continuously at
maximum rating. It is also known as capacity factor or use factor.
𝑷𝒍𝒂𝒏𝒕 𝑭𝒂𝒄𝒕𝒐𝒓 =
𝑨𝒄𝒕𝒖𝒂𝒍 π’†π’π’†π’“π’ˆπ’š 𝒑𝒓𝒐𝒅𝒖𝒄𝒆𝒅 𝒐𝒓 𝒔𝒆𝒓𝒗𝒆𝒅 Γ— 𝑻
π‘΄π’‚π’™π’Šπ’Žπ’–π’Ž 𝑷𝒍𝒂𝒏𝒕 π’“π’‚π’•π’Šπ’π’ˆ Γ— 𝑻
Where T is the time in days, weeks, months or years.
School of Electrical and Electronics Engineering, REVA
University
Basic Definitions
Load Factor
β€’ It is the ratio of the average load over a designated period of time to the peak load occurring on that
period. Therefore load factor FLD
𝑭 𝑳𝑫 =
π‘¨π’—π’†π’“π’‚π’ˆπ’† 𝑳𝒐𝒂𝒅
π‘·π’†π’‚π’Œ 𝑳𝒐𝒂𝒅
𝑭 𝑳𝑫 =
π‘¨π’—π’†π’“π’‚π’ˆπ’† 𝑳𝒐𝒂𝒅 Γ— 𝑻
π‘·π’†π’‚π’Œ 𝑳𝒐𝒂𝒅 Γ— 𝑻
=
π‘Όπ’π’Šπ’•π’” 𝒔𝒆𝒓𝒗𝒆𝒅
π‘·π’†π’‚π’Œ 𝒍𝒐𝒂𝒅 Γ— 𝑻
Where T is the time in days, weeks, months or years.
School of Electrical and Electronics Engineering, REVA
University
Problem
School of Electrical and Electronics Engineering, REVA
University
β€’ Assume that the Yelahanka distribution substation of KPTCL supplying to Vinayakanagar, a small place,
β€’ experiences an annual peak load of 3500 Kw. The total annual energy supplied to the primary feeder
β€’ circuits is 10,000,000 kWh. The peak demand occurs in July or august and is due to air – conditioning load.
(i) Find the annual average power demand.
(ii) Find the annual load factor
Assume the monthly load curve as shown below:
Solution
(i) The annual average power demand is
π΄π‘›π‘›π‘’π‘Žπ‘™ π‘ƒπ‘Žπ‘£ =
π‘‡π‘œπ‘‘π‘Žπ‘™ π‘Žπ‘›π‘›π‘’π‘Žπ‘™ π‘’π‘›π‘’π‘Ÿπ‘”π‘¦
π‘Œπ‘’π‘Žπ‘Ÿ
=
107 π‘˜π‘Šβ„Ž/π‘¦π‘’π‘Žπ‘Ÿ
8760β„Ž/π‘¦π‘’π‘Žπ‘Ÿ
= 1141kW
(II) Annual load factor is given by,
𝐹𝐿𝐷 =
π΄π‘›π‘›π‘’π‘Žπ‘™ π΄π‘£π‘’π‘Ÿπ‘Žπ‘”π‘’ πΏπ‘œπ‘Žπ‘‘
π΄π‘›π‘›π‘’π‘Žπ‘™ π‘ƒπ‘’π‘Žπ‘˜ π·π‘’π‘šπ‘Žπ‘›π‘‘
=
1141π‘˜π‘Š
3500π‘˜π‘Š
= 0.326
School of Electrical and Electronics Engineering, REVA
University
Distribution System Reliability
β€’ Reliability is the probability of a device or system performing its purpose adequately for the period
of time intended under the operating conditions encountered.
β€’ A measure of the ability of the system to perform its intended function
Basic Definition
Outage
β€’ Describes the state of a component when it is not available to perform its intended function due to
some event directly associated with that component. An outage may or may not cause an
interruption of service to consumers depending on the system.
β€’ Types of outages:
1. Forced Outage
2. Scheduled Outage
3. Partial Outage
4. Transient Forced Outage
5. Persistent forced Outage School of Electrical and Electronics Engineering, REVA
University
Basic Definitions
Forced Outage
β€’ An outage caused by emergency conditions directly associated with a component that require the
component to be taken out of service immediately, either automatically or as soon as switching
operations can be performed, or an outage caused by improper operation of equipment or human
error.
Scheduled error
β€’ An outage that results when a component is deliberately taken out of service at a selected time,
usually for the purpose of construction, preventive maintenance or repair.
Partial Outage
β€’ Describes an component state where the capacity of the component toperform its function is
reduced but not completely eliminated.
School of Electrical and Electronics Engineering, REVA
University
Basic Definitions
Transient Forced Outage
β€’ A component outage where the cause or the reason for outage is immediately self clearing so that
the affected component can be restored to service either automatically or as soon as a switch or
circuit breaker can be reclosed or a fuse is replaced.
For example: Outage due to lightning flash over
Persistent forced Outage
β€’ A component outage where the cause or the reason for outage is not immediately self clearing but
must be cleared by eliminating the hazard or by repairing or replacing the effected line or
component before the line can be energized.
For example: a lightning flashover which shatters the insulators there by disabling the component
until it is replaced.
School of Electrical and Electronics Engineering, REVA
University
Cost vs Reliability
School of Electrical and Electronics Engineering, REVA
University
β€’ By increasing the reliability level, leads to new investments for the utility, while
the economic consequences for the customers decreases.
β€’ The opposite happens if the utilities decreases the system reliability level, which leads to fewer
investments, and thereby a reduced cost.
β€’ But this will on the other hand increase the economic consequences for the customers, which might
be unsatisfactory.
β€’ A global minimum at the total cost curve exists, which may be the aim for utilities, in order to
keep the costs and satisfied customers at a certain level
Thank You
School of Electrical and Electronics Engineering, REVA
University

More Related Content

What's hot

Introduction about Power System Planning in the Presence of Uncertainties
Introduction about  Power System Planning in the Presence of Uncertainties Introduction about  Power System Planning in the Presence of Uncertainties
Introduction about Power System Planning in the Presence of Uncertainties ahmedgoun
Β 
Power system transmission issues and effects
Power system transmission issues and effectsPower system transmission issues and effects
Power system transmission issues and effectsAnand Azad
Β 
Power System Planning
Power System PlanningPower System Planning
Power System Planninglinsstalex
Β 
Modern power system planning new
Modern power system planning newModern power system planning new
Modern power system planning newBayu imadul Bilad
Β 
EDS Unit 1 (Part 1).pptx
EDS Unit 1 (Part 1).pptxEDS Unit 1 (Part 1).pptx
EDS Unit 1 (Part 1).pptxDr. Rohit Babu
Β 
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...IRJET Journal
Β 
Adequacy Analysis and Security Reliability Evaluation of Bulk Power System
Adequacy Analysis and Security Reliability Evaluation of Bulk Power SystemAdequacy Analysis and Security Reliability Evaluation of Bulk Power System
Adequacy Analysis and Security Reliability Evaluation of Bulk Power SystemIOSR Journals
Β 
Available transfer capability computations in the indian southern e.h.v power...
Available transfer capability computations in the indian southern e.h.v power...Available transfer capability computations in the indian southern e.h.v power...
Available transfer capability computations in the indian southern e.h.v power...eSAT Publishing House
Β 
11.optimization of loss minimization using facts in deregulated power systems
11.optimization of loss minimization using facts in deregulated power systems11.optimization of loss minimization using facts in deregulated power systems
11.optimization of loss minimization using facts in deregulated power systemsAlexander Decker
Β 
Optimization of loss minimization using facts in deregulated power systems
Optimization of loss minimization using facts in deregulated power systemsOptimization of loss minimization using facts in deregulated power systems
Optimization of loss minimization using facts in deregulated power systemsAlexander Decker
Β 
Design methodology of smart photovoltaic plant
Design methodology of smart photovoltaic plant Design methodology of smart photovoltaic plant
Design methodology of smart photovoltaic plant IJECEIAES
Β 
POWER SYSTEM OPERATION AND CONTROL. load forecasting - introduction, methodo...
POWER SYSTEM OPERATION AND CONTROL. load forecasting -  introduction, methodo...POWER SYSTEM OPERATION AND CONTROL. load forecasting -  introduction, methodo...
POWER SYSTEM OPERATION AND CONTROL. load forecasting - introduction, methodo...Jobin Abraham
Β 
CV ENGLISH Feb2016 - Copy
CV ENGLISH Feb2016 - CopyCV ENGLISH Feb2016 - Copy
CV ENGLISH Feb2016 - Copyshraf eldin sati
Β 
Load Forecasting
Load ForecastingLoad Forecasting
Load Forecastinglinsstalex
Β 
Congestion issues and its related management
Congestion issues and its related managementCongestion issues and its related management
Congestion issues and its related managementalpna1808
Β 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)IJERD Editor
Β 
S 8 final-report-april-2003
S 8 final-report-april-2003S 8 final-report-april-2003
S 8 final-report-april-2003Vara Prasad
Β 
A Review on Energy Consumption Monitoring and Analysis System
A Review on Energy Consumption Monitoring and Analysis SystemA Review on Energy Consumption Monitoring and Analysis System
A Review on Energy Consumption Monitoring and Analysis SystemIRJET Journal
Β 

What's hot (20)

Smart optimization techniques for virtual power plants
Smart optimization techniques for virtual power plants Smart optimization techniques for virtual power plants
Smart optimization techniques for virtual power plants
Β 
Introduction about Power System Planning in the Presence of Uncertainties
Introduction about  Power System Planning in the Presence of Uncertainties Introduction about  Power System Planning in the Presence of Uncertainties
Introduction about Power System Planning in the Presence of Uncertainties
Β 
Power system transmission issues and effects
Power system transmission issues and effectsPower system transmission issues and effects
Power system transmission issues and effects
Β 
Power System Planning
Power System PlanningPower System Planning
Power System Planning
Β 
Modern power system planning new
Modern power system planning newModern power system planning new
Modern power system planning new
Β 
EDS Unit 1 (Part 1).pptx
EDS Unit 1 (Part 1).pptxEDS Unit 1 (Part 1).pptx
EDS Unit 1 (Part 1).pptx
Β 
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
Β 
Adequacy Analysis and Security Reliability Evaluation of Bulk Power System
Adequacy Analysis and Security Reliability Evaluation of Bulk Power SystemAdequacy Analysis and Security Reliability Evaluation of Bulk Power System
Adequacy Analysis and Security Reliability Evaluation of Bulk Power System
Β 
Available transfer capability computations in the indian southern e.h.v power...
Available transfer capability computations in the indian southern e.h.v power...Available transfer capability computations in the indian southern e.h.v power...
Available transfer capability computations in the indian southern e.h.v power...
Β 
11.optimization of loss minimization using facts in deregulated power systems
11.optimization of loss minimization using facts in deregulated power systems11.optimization of loss minimization using facts in deregulated power systems
11.optimization of loss minimization using facts in deregulated power systems
Β 
Optimization of loss minimization using facts in deregulated power systems
Optimization of loss minimization using facts in deregulated power systemsOptimization of loss minimization using facts in deregulated power systems
Optimization of loss minimization using facts in deregulated power systems
Β 
Design methodology of smart photovoltaic plant
Design methodology of smart photovoltaic plant Design methodology of smart photovoltaic plant
Design methodology of smart photovoltaic plant
Β 
POWER SYSTEM OPERATION AND CONTROL. load forecasting - introduction, methodo...
POWER SYSTEM OPERATION AND CONTROL. load forecasting -  introduction, methodo...POWER SYSTEM OPERATION AND CONTROL. load forecasting -  introduction, methodo...
POWER SYSTEM OPERATION AND CONTROL. load forecasting - introduction, methodo...
Β 
CV ENGLISH Feb2016 - Copy
CV ENGLISH Feb2016 - CopyCV ENGLISH Feb2016 - Copy
CV ENGLISH Feb2016 - Copy
Β 
Load Forecasting
Load ForecastingLoad Forecasting
Load Forecasting
Β 
Congestion issues and its related management
Congestion issues and its related managementCongestion issues and its related management
Congestion issues and its related management
Β 
amr CV
amr CVamr CV
amr CV
Β 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
Β 
S 8 final-report-april-2003
S 8 final-report-april-2003S 8 final-report-april-2003
S 8 final-report-april-2003
Β 
A Review on Energy Consumption Monitoring and Analysis System
A Review on Energy Consumption Monitoring and Analysis SystemA Review on Energy Consumption Monitoring and Analysis System
A Review on Energy Consumption Monitoring and Analysis System
Β 

Similar to Electrical Distribution System Planning

2: Introduction to Energy Audit Methods in Water Supply
2: Introduction to Energy Audit Methods in Water Supply2: Introduction to Energy Audit Methods in Water Supply
2: Introduction to Energy Audit Methods in Water SupplyAlliance To Save Energy
Β 
Energy Audit in water supply and use in public places.pptx
Energy Audit in water supply and use in public places.pptxEnergy Audit in water supply and use in public places.pptx
Energy Audit in water supply and use in public places.pptxJawaharlal37
Β 
IRJET- Life Cycle Cost Analysis of a Residential Building
IRJET-  	  Life Cycle Cost Analysis of a Residential BuildingIRJET-  	  Life Cycle Cost Analysis of a Residential Building
IRJET- Life Cycle Cost Analysis of a Residential BuildingIRJET Journal
Β 
Usgbc leed
Usgbc leedUsgbc leed
Usgbc leedRakhi Ghosh
Β 
Energy Audit Report Presentation
Energy Audit Report PresentationEnergy Audit Report Presentation
Energy Audit Report PresentationFurqan Ullah Mir
Β 
Retrofitting Buildings to Achieve Energy Efficiency
Retrofitting Buildings to Achieve Energy EfficiencyRetrofitting Buildings to Achieve Energy Efficiency
Retrofitting Buildings to Achieve Energy EfficiencyDivya Kothari
Β 
Financial and economic analysis
Financial and economic analysisFinancial and economic analysis
Financial and economic analysisSiladitya Bag
Β 
Boris SučiΔ‡, JoΕΎef Stefan Institute, Ljubljana, Slovenia.
Boris SučiΔ‡, JoΕΎef Stefan Institute, Ljubljana, Slovenia.Boris SučiΔ‡, JoΕΎef Stefan Institute, Ljubljana, Slovenia.
Boris SučiΔ‡, JoΕΎef Stefan Institute, Ljubljana, Slovenia.ARC research group
Β 
Methodology for a Cost-Benefit Analysis of RES-E, Eoin clifford eirgrid
Methodology for a Cost-Benefit Analysis of RES-E, Eoin clifford eirgridMethodology for a Cost-Benefit Analysis of RES-E, Eoin clifford eirgrid
Methodology for a Cost-Benefit Analysis of RES-E, Eoin clifford eirgridSustainableEnergyAut
Β 
ODOEPresentation
ODOEPresentationODOEPresentation
ODOEPresentationMatthew Bragg
Β 
cost-benefit-analysis (1).pdf
cost-benefit-analysis (1).pdfcost-benefit-analysis (1).pdf
cost-benefit-analysis (1).pdfSACHINMAURYA57
Β 
PP_lect1.pptx
PP_lect1.pptxPP_lect1.pptx
PP_lect1.pptxnazarbaloch1
Β 
Energy efficiency project financing in india
Energy efficiency project financing in indiaEnergy efficiency project financing in india
Energy efficiency project financing in indiaJayant Sinha
Β 
Eng. Osama Aly Ahmed - Energy Efficiency Management
Eng. Osama Aly Ahmed - Energy Efficiency ManagementEng. Osama Aly Ahmed - Energy Efficiency Management
Eng. Osama Aly Ahmed - Energy Efficiency ManagementThe i-Capital Africa Institute
Β 

Similar to Electrical Distribution System Planning (20)

2: Introduction to Energy Audit Methods in Water Supply
2: Introduction to Energy Audit Methods in Water Supply2: Introduction to Energy Audit Methods in Water Supply
2: Introduction to Energy Audit Methods in Water Supply
Β 
EAM-PPT-converted.pdf
EAM-PPT-converted.pdfEAM-PPT-converted.pdf
EAM-PPT-converted.pdf
Β 
Energy Audit in water supply and use in public places.pptx
Energy Audit in water supply and use in public places.pptxEnergy Audit in water supply and use in public places.pptx
Energy Audit in water supply and use in public places.pptx
Β 
IRJET- Life Cycle Cost Analysis of a Residential Building
IRJET-  	  Life Cycle Cost Analysis of a Residential BuildingIRJET-  	  Life Cycle Cost Analysis of a Residential Building
IRJET- Life Cycle Cost Analysis of a Residential Building
Β 
Usgbc leed
Usgbc leedUsgbc leed
Usgbc leed
Β 
Energy Audit Report Presentation
Energy Audit Report PresentationEnergy Audit Report Presentation
Energy Audit Report Presentation
Β 
Panel 2: Utility Presentation
Panel 2: Utility PresentationPanel 2: Utility Presentation
Panel 2: Utility Presentation
Β 
Energy Audit.pptx
Energy Audit.pptxEnergy Audit.pptx
Energy Audit.pptx
Β 
Retrofitting Buildings to Achieve Energy Efficiency
Retrofitting Buildings to Achieve Energy EfficiencyRetrofitting Buildings to Achieve Energy Efficiency
Retrofitting Buildings to Achieve Energy Efficiency
Β 
Financial and economic analysis
Financial and economic analysisFinancial and economic analysis
Financial and economic analysis
Β 
Boris SučiΔ‡, JoΕΎef Stefan Institute, Ljubljana, Slovenia.
Boris SučiΔ‡, JoΕΎef Stefan Institute, Ljubljana, Slovenia.Boris SučiΔ‡, JoΕΎef Stefan Institute, Ljubljana, Slovenia.
Boris SučiΔ‡, JoΕΎef Stefan Institute, Ljubljana, Slovenia.
Β 
Energy management
Energy managementEnergy management
Energy management
Β 
Methodology for a Cost-Benefit Analysis of RES-E, Eoin clifford eirgrid
Methodology for a Cost-Benefit Analysis of RES-E, Eoin clifford eirgridMethodology for a Cost-Benefit Analysis of RES-E, Eoin clifford eirgrid
Methodology for a Cost-Benefit Analysis of RES-E, Eoin clifford eirgrid
Β 
Dr.pptx1
Dr.pptx1Dr.pptx1
Dr.pptx1
Β 
ODOEPresentation
ODOEPresentationODOEPresentation
ODOEPresentation
Β 
cost-benefit-analysis (1).pdf
cost-benefit-analysis (1).pdfcost-benefit-analysis (1).pdf
cost-benefit-analysis (1).pdf
Β 
PP_lect1.pptx
PP_lect1.pptxPP_lect1.pptx
PP_lect1.pptx
Β 
Energy efficiency project financing in india
Energy efficiency project financing in indiaEnergy efficiency project financing in india
Energy efficiency project financing in india
Β 
Eng. Osama Aly Ahmed - Energy Efficiency Management
Eng. Osama Aly Ahmed - Energy Efficiency ManagementEng. Osama Aly Ahmed - Energy Efficiency Management
Eng. Osama Aly Ahmed - Energy Efficiency Management
Β 
Load forecasting
Load forecastingLoad forecasting
Load forecasting
Β 

Recently uploaded

Model Call Girl in Narela Delhi reach out to us at πŸ”8264348440πŸ”
Model Call Girl in Narela Delhi reach out to us at πŸ”8264348440πŸ”Model Call Girl in Narela Delhi reach out to us at πŸ”8264348440πŸ”
Model Call Girl in Narela Delhi reach out to us at πŸ”8264348440πŸ”soniya singh
Β 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
Β 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
Β 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
Β 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
Β 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
Β 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
Β 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
Β 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
Β 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
Β 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
Β 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
Β 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
Β 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
Β 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
Β 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
Β 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
Β 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
Β 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
Β 

Recently uploaded (20)

Model Call Girl in Narela Delhi reach out to us at πŸ”8264348440πŸ”
Model Call Girl in Narela Delhi reach out to us at πŸ”8264348440πŸ”Model Call Girl in Narela Delhi reach out to us at πŸ”8264348440πŸ”
Model Call Girl in Narela Delhi reach out to us at πŸ”8264348440πŸ”
Β 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
Β 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
Β 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Β 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
Β 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
Β 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
Β 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Β 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
Β 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
Β 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
Β 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
Β 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
Β 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
Β 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
Β 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
Β 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
Β 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
Β 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
Β 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Β 

Electrical Distribution System Planning

  • 1. Electrical Distribution System Name of the Faculty : Adithya Ballaji School of Electrical and Electronics Engineering Unit 3: System Planning and Reliability School of Electrical and Electronics Engineering, REVA University
  • 2. Syllabus β€’ Planning process, planning criteria, system developers, dispersed generation, distribution systems, economics and finance, mapping. Load Characteristics - Basic definition, relation between load and load factor, load growth. β€’ Reliability-Basic reliability concept –Cost verses system Reliability –Reliability planning procedure–Mathematical concept. School of Electrical and Electronics Engineering, REVA University
  • 3. Introduction β€’ Planning is the process of taking careful decision. The main input in planning is quality and systematic thought. β€’ It involves selecting the first a vision, values, mission and objective and deciding what should be done to attain them. β€’ The main objective of distribution planning is to provide satisfactory service at lowest possible cost. β€’ In power utility, the planning process is used to identify the best schedule of future resources and actions to achieve the utility goal. β€’ Planning is driven by two inputs: 1. Future Needs 2. Time needed to fulfil these needs with defined master plan. β€’ Long term planning (5-10 years) determines the power energy forecasts and optimum network arrangements. β€’ A short term planning involves the planning for current year and next year annual plans, and subsequent years. School of Electrical and Electronics Engineering, REVA University
  • 4. Steps involved in Planning Process β€’ Feasibility studies are carried out to identify, evaluate and finalize the best plan. 1. Define the problem 2. Find the alternative 3. Evaluate the alternative 4. Select the best one β€’ Project report for long, medium, short term works along with the action plan/pert chart/bar chart for each activity/ work is prepared and dates are set for milestones. β€’ Final approval is taken after financial and economic appraisal. β€’ Once the best plan is selected the next stage of process is inititated. School of Electrical and Electronics Engineering, REVA University
  • 5. Flow chart of Planning Process School of Electrical and Electronics Engineering, REVA University
  • 6. Planning Actions School of Electrical and Electronics Engineering, REVA University
  • 7. Planning Criteria and Standards β€’ Criteria and standards together form a set of requirements against which the planning process can compare alternatives in the evaluation and final choice. β€’ A distribution plan must provided with least cost and also satisfy various criteria and standards. β€’ Criteria are rules or procedures. β€’ Standards are specifications to ensure that the system is built with compatible equipment that will fit and function together when installed and maintained in an economical manner. β€’ Standards and criteria and their application to the planning process depends upon vision, mission and the value system of the utility. β€’ Criteria and standards convey direction in the master plan. β€’ Planning standards exists for reasons of efficiency and to achieve the reduced investment β€’ The system may use various Indian standards, Indian Electricity Rules, Rural Electrification Corporation Standards, IEC, ISO and electricity act 2003. β€’ These criteria and standards are used for better and improved power utility their by to achieve its objective. School of Electrical and Electronics Engineering, REVA University
  • 8. Typical Criteria for Planning The following are the typical criteria for planning: β€’ A prospective plan for the next 15 years to meet the anticipated load growth and forecast load centers. β€’ The plan should be reviewed yearly on the basis of annual plans with respect to the targets achieved. β€’ Detailed project reports be framed to identify the system strengthening works on long term and short term bases. β€’ Demand side management projects reports be prepared to achieve tangible reduction in demand and energy consumption on the planned year. β€’ Security of supply is one of the important factors for planning, for example, In industrial cities supply to be provide using sub transmission open circuit of 33 or 66 or 132 or 220kV, 11kV open ring main circuit for all urban area, and separate independent feeders to be provided for major industrial consumers and rural areas. β€’ Power utility needs to use and create load research facilities to study and identify load profiles in the particular area. School of Electrical and Electronics Engineering, REVA University
  • 9. Typical Criteria for Planning β€’ The number of 11kV outgoing feeders at distribution station should not exceed 15. β€’ The length of 11kV outgoing feeder emanating from substation up-to tail end not to be more than 12km. β€’ Improved metering, that is to provide electronic meters to all the consumers. β€’ Total harmonic distortion at any voltage level should be within 5 per cent. School of Electrical and Electronics Engineering, REVA University
  • 10. Types of planning standards β€’ Development of standard cost structure for material and labour rates for different voltages to be used in the estimation. β€’ Use of standard system voltages as per Indian standards and voltage regulation as per IE Rules. β€’ The load growth of at least 10 years will considered to prepare new or system improvement schemes. β€’ Shunt capacitor fixed / switched type shall be installed in distribution system to improve the power factor and voltage profile there by reducing transmission and distribution losses. β€’ Fixed LT capacitor should be installed on the distribution transformers. School of Electrical and Electronics Engineering, REVA University
  • 11. Distribution system Economics and Finance β€’ Economic analysis is carried out to determine the lo cost plan among various alternatives. β€’ Financial analysis determines the rate of return and risk involved on the investment to be made on the plan. β€’ The investment to carry out a planned distribution is either: 1. Annual expenses : Obtained from operating revenue 2. Capital expenditure : obtained from financing, reinvested reserve etc. 3. Both annual expenses and capital expenditure Following methods are used for Investment decision : 1. Minimum Revenue Requirement β€’ Time value money β€’ Revenue Requirement of Investment 2. Financial Method β€’ Benefit/Cost Ration β€’ Internal Rate of Return( IRR) School of Electrical and Electronics Engineering, REVA University
  • 12. Minimum Revenue Requirement β€’ In this type of method choice is made on the basis of the present value of all future annual costs. β€’ The economic choice is made based on the one with lowest present value of all the future cost. β€’ The economic comparison is done based on two steps: 1. Estimating the annual cost of each year 2. If the annual costs are not uniform, calculate their present value. Time Value Money: β€’ Here money has time value and interest on its use has to be paid. The rate of interest is determined by the reserve Bank of India according to economic condition at the time. β€’ There is a similar mechanism to determine the interest rate at the international level also. β€’ The process of taking money and finding its equivalent value at some future date is called future value calculation. β€’ The process of finding the equivalent value at some earlier time is called present value calculation. School of Electrical and Electronics Engineering, REVA University
  • 13. Minimum Revenue Requirement Revenue Requirement of Investment: β€’ The total revenue requirement of investment is the sim of the annual charges extending over the service life. It includes: 1. Return on investment 2. Depreciation 3. Insurance expenses 4. Operating and Maintenance expenses 5. Interest on loan capital and working capital 6. Taxes etc. The above charges can be conveniently estimated as a percentage of original investment. And three methods to calculate the present value are: 1. Cumulative present worth method 2. Levelised Annual Cost Method 3. Uniform series present worth Method School of Electrical and Electronics Engineering, REVA University
  • 14. Financial Analysis It can be classified into : 1. Benefit / cost ratio 2. Internal Rate of Return ( IRR) Benefit / cost ratio β€’ This method ranks a project by the ratio of the present value of revenue and benefits earned to the present value of the costs incurred. β€’ System improvement works are generally evaluated on a benefit – cost basis by the rural electrification corporation of India. β€’ The central Electricity Authority (CEA) also uses this method for such schemes, based on lifecycle (25-30 year period) cost benefits. β€’ The works proposed for strengthening, upgradation and improvement of sub- transmission and distribution helps in reducing technical and commercial losses by the year. β€’ The financial analysis is usually done for the for lifetime of projects considering the year wise costs including interest, depreciation, operation and maintenance charges. School of Electrical and Electronics Engineering, REVA University
  • 15. Financial Analysis Internal Rate of Return ( IRR) β€’ The design and sustainability of the project should take into account the level of incentive for undertaking and maintaining a project investment. β€’ The financial incentive takes the form of increased income that the investment generates with the execution of the project. β€’ This method calculates the rate of interest needed for the present value of the returns to be the same as the present value of the investment needed. β€’ Rural Electrification Corporation specifies the IRR as 15 percent while sanctioning short term ( seven year repayment) loan scheme. School of Electrical and Electronics Engineering, REVA University
  • 16. Mapping β€’ Creating a geodatabase containing relevant information about assets in existing electrical distribution system. β€’ Types of Mapping: β€’ Global Positioning System (GPS) 1. Back ground Maps 2. Digital Mapping 3. Automated Mapping (AM)/ Facilities Management (FM)/ Geographical Information System (GIS) 4. Enterprise Resource Planning (ERP) School of Electrical and Electronics Engineering, REVA University
  • 17. Mapping Global Positioning System (GPS) β€’ GPS is a system in which earth orbiting satellites provide precise information on time and position enabling GPS receiving devices to compute position on earth. β€’ Signals must be received from at least three satellites in order to establish the latitude and longitude of receiver position. β€’ A fourth satellite is required to calculate the altitude. β€’ GPS technology is used to locate tap-off points, transformers and other facilities of power distribution networks and consequently to map the system with an accuracy of up to one meter. β€’ GPS can be used to capture data for 11kV and above voltage level distribution/sub transmission lines and substations/distribution transformer for mapping. β€’ For LT network each distribution transformer geographical maps on paper can be drawn based on judgment and eye approximately. β€’ The length of the feeder is generally fixed, based on estimates and pole to pole standard distances. β€’ These maps can be prepared on survey of India sheets School of Electrical and Electronics Engineering, REVA University
  • 18. Mapping Digital Mapping β€’ Digital mapping software can be used to create an integrated and automated facilities model in which paper maps are first digitized and then suitably linked. β€’ A digitizer board is used for digitizing nodes with respect to a reference point pre-fixed on the map. β€’ One person can read co-ordinates on the digitized board and other can feed it into a computer. β€’ Once digitization is complete, the software numbers the nodes, draws the network diagram and calculates the lengths. β€’ Network drawn with a computer then undergo field verification. β€’ A computer processing centre will then issue a prescribed format to obtain electrical loading data of feeders, transformer capacity, size/type of feeder for the concerned area. School of Electrical and Electronics Engineering, REVA University
  • 19. Digital Mapping The following steps should be taken to prepare the maps: 1. The complete area should be covered and duplication avoided. 2. The 132-33kV system be digitized first then followed by 11kV and finally the 400kV network. 3. Devices like GPS and VHF sets may be required for dense urban areas to capture attributes accurately and ensuring high frequency digitized maps. 4. Oracle RDBMS is suitable for data storage. Digital mapping process is shown below: School of Electrical and Electronics Engineering, REVA University
  • 20. Automated Mapping (AM) / Facilities Management (FM)/ Geographical Information System (GIS) β€’ Every transaction whether it is a work order, billing, operation, system improvements or maintenance is tied to a location. β€’ AM and FM provide an integrated tool to create an automated facilities model and help to convert paper maps to a digital environment where the system details and its changes are fed and stored in a graphic and tabular database. β€’ The graphic data is representation of the network and is the backbone of an AM/FM/GIS system and the driving force for all the application. β€’ FM software links the graphic network map to tabular and non-graphic data associated with the databases, work order drawing etc. β€’ GIS establishes the connection to these databases through a record server and provides the best characteristics of AM and FM system to provide an integrated information system. School of Electrical and Electronics Engineering, REVA University
  • 21. Role of Geographical Information System (GIS) and its application β€’ GIS is a system of mapping of complete electrical network including low voltage system and consumer meter. β€’ Database plays a central role in the operation of planning, where analysis programme form a part of system supported by a database management system which stores, retrieves and modifies various data on the distribution system. β€’ The main role of GIS is to integrate the dynamic side of the operation with the relatively static side of the utility facility record for effective utilization by all functional departments and personnel. β€’ The various roles include: 1. Detailed space representation of the facilities and network linked to the related data. 2. Integrated facility database and its management with multi user access. 3. Management of different stages of the facility’s life cycle. 4. Optimum data for facility application. School of Electrical and Electronics Engineering, REVA University
  • 22. Role of Geographical Information System (GIS) and its application β€’ Applications: 1. The planning department will be needing field data of land records, load growth based on population growth and demand, existing network layout. 2. The data is required for feeder layout/routing and network planning, load flow analysis, protective devices locations. 3. Estimation and Costing 4. Management reports 5. Design / operational logistics 6. Maintenance 7. Troubleshooting School of Electrical and Electronics Engineering, REVA University
  • 23. Load Characteristics Basic Definitions Demand β€’ The demand of an installation or system is the load at the receiving terminals averaged over a specified interval of time. Here the load may be given in kilowatts, kilovars, kilovolt amperes, kilo amperes or amperes Demand interval β€’ It is the period over which the load is averaged. This selected βˆ†t period may be 15min, 30min or even longer. Maximum Demand β€’ The maximum demand of an installation or system is the greatest of all demands which have occurred during the specified period of time. The maximum demand statement should also express the demand interval used to measure it. For example, the specific demand might be the maximum of all demands such as daily, weekly, monthly or annual. School of Electrical and Electronics Engineering, REVA University
  • 24. Daily Demand variation curve School of Electrical and Electronics Engineering, REVA University
  • 25. Basic Definitions Utilization Factor β€’ It is the ratio of maximum demand of the system to the rated capacity of the system. Thus utilization factor is denoted as 𝑭 𝒖 𝑭 𝒖 = π‘΄π’‚π’™π’Šπ’Žπ’–π’Ž π‘«π’†π’Žπ’‚π’π’… 𝑹𝒂𝒕𝒆𝒅 π‘Ίπ’šπ’”π’•π’†π’Ž π‘ͺπ’‚π’‘π’‚π’„π’Šπ’•π’š Plant Factor β€’ It is the ratio of the total actual energy produced or served over a designated period of time to the energy that would have been produced or served of the plant had operated continuously at maximum rating. It is also known as capacity factor or use factor. 𝑷𝒍𝒂𝒏𝒕 𝑭𝒂𝒄𝒕𝒐𝒓 = 𝑨𝒄𝒕𝒖𝒂𝒍 π’†π’π’†π’“π’ˆπ’š 𝒑𝒓𝒐𝒅𝒖𝒄𝒆𝒅 𝒐𝒓 𝒔𝒆𝒓𝒗𝒆𝒅 Γ— 𝑻 π‘΄π’‚π’™π’Šπ’Žπ’–π’Ž 𝑷𝒍𝒂𝒏𝒕 π’“π’‚π’•π’Šπ’π’ˆ Γ— 𝑻 Where T is the time in days, weeks, months or years. School of Electrical and Electronics Engineering, REVA University
  • 26. Basic Definitions Load Factor β€’ It is the ratio of the average load over a designated period of time to the peak load occurring on that period. Therefore load factor FLD 𝑭 𝑳𝑫 = π‘¨π’—π’†π’“π’‚π’ˆπ’† 𝑳𝒐𝒂𝒅 π‘·π’†π’‚π’Œ 𝑳𝒐𝒂𝒅 𝑭 𝑳𝑫 = π‘¨π’—π’†π’“π’‚π’ˆπ’† 𝑳𝒐𝒂𝒅 Γ— 𝑻 π‘·π’†π’‚π’Œ 𝑳𝒐𝒂𝒅 Γ— 𝑻 = π‘Όπ’π’Šπ’•π’” 𝒔𝒆𝒓𝒗𝒆𝒅 π‘·π’†π’‚π’Œ 𝒍𝒐𝒂𝒅 Γ— 𝑻 Where T is the time in days, weeks, months or years. School of Electrical and Electronics Engineering, REVA University
  • 27. Problem School of Electrical and Electronics Engineering, REVA University β€’ Assume that the Yelahanka distribution substation of KPTCL supplying to Vinayakanagar, a small place, β€’ experiences an annual peak load of 3500 Kw. The total annual energy supplied to the primary feeder β€’ circuits is 10,000,000 kWh. The peak demand occurs in July or august and is due to air – conditioning load. (i) Find the annual average power demand. (ii) Find the annual load factor Assume the monthly load curve as shown below:
  • 28. Solution (i) The annual average power demand is π΄π‘›π‘›π‘’π‘Žπ‘™ π‘ƒπ‘Žπ‘£ = π‘‡π‘œπ‘‘π‘Žπ‘™ π‘Žπ‘›π‘›π‘’π‘Žπ‘™ π‘’π‘›π‘’π‘Ÿπ‘”π‘¦ π‘Œπ‘’π‘Žπ‘Ÿ = 107 π‘˜π‘Šβ„Ž/π‘¦π‘’π‘Žπ‘Ÿ 8760β„Ž/π‘¦π‘’π‘Žπ‘Ÿ = 1141kW (II) Annual load factor is given by, 𝐹𝐿𝐷 = π΄π‘›π‘›π‘’π‘Žπ‘™ π΄π‘£π‘’π‘Ÿπ‘Žπ‘”π‘’ πΏπ‘œπ‘Žπ‘‘ π΄π‘›π‘›π‘’π‘Žπ‘™ π‘ƒπ‘’π‘Žπ‘˜ π·π‘’π‘šπ‘Žπ‘›π‘‘ = 1141π‘˜π‘Š 3500π‘˜π‘Š = 0.326 School of Electrical and Electronics Engineering, REVA University
  • 29. Distribution System Reliability β€’ Reliability is the probability of a device or system performing its purpose adequately for the period of time intended under the operating conditions encountered. β€’ A measure of the ability of the system to perform its intended function Basic Definition Outage β€’ Describes the state of a component when it is not available to perform its intended function due to some event directly associated with that component. An outage may or may not cause an interruption of service to consumers depending on the system. β€’ Types of outages: 1. Forced Outage 2. Scheduled Outage 3. Partial Outage 4. Transient Forced Outage 5. Persistent forced Outage School of Electrical and Electronics Engineering, REVA University
  • 30. Basic Definitions Forced Outage β€’ An outage caused by emergency conditions directly associated with a component that require the component to be taken out of service immediately, either automatically or as soon as switching operations can be performed, or an outage caused by improper operation of equipment or human error. Scheduled error β€’ An outage that results when a component is deliberately taken out of service at a selected time, usually for the purpose of construction, preventive maintenance or repair. Partial Outage β€’ Describes an component state where the capacity of the component toperform its function is reduced but not completely eliminated. School of Electrical and Electronics Engineering, REVA University
  • 31. Basic Definitions Transient Forced Outage β€’ A component outage where the cause or the reason for outage is immediately self clearing so that the affected component can be restored to service either automatically or as soon as a switch or circuit breaker can be reclosed or a fuse is replaced. For example: Outage due to lightning flash over Persistent forced Outage β€’ A component outage where the cause or the reason for outage is not immediately self clearing but must be cleared by eliminating the hazard or by repairing or replacing the effected line or component before the line can be energized. For example: a lightning flashover which shatters the insulators there by disabling the component until it is replaced. School of Electrical and Electronics Engineering, REVA University
  • 32. Cost vs Reliability School of Electrical and Electronics Engineering, REVA University β€’ By increasing the reliability level, leads to new investments for the utility, while the economic consequences for the customers decreases. β€’ The opposite happens if the utilities decreases the system reliability level, which leads to fewer investments, and thereby a reduced cost. β€’ But this will on the other hand increase the economic consequences for the customers, which might be unsatisfactory. β€’ A global minimum at the total cost curve exists, which may be the aim for utilities, in order to keep the costs and satisfied customers at a certain level
  • 33. Thank You School of Electrical and Electronics Engineering, REVA University