SlideShare a Scribd company logo
1 of 54
Wagdy Ahmed Moustafa Mansour
Electrical and Electronics Engineering Department
Universiti Teknologi PETRONAS
Supervisor: Ir Mohd Faris Bin Abdullah
Final Year Project Viva
“Technical-Economic Analysis in the Application of
Series Capacitor Compensation for Distribution
Networks”
Project
Background
Problem
Statement
Objectives
Literature
Review
Methodology
Results and
Discussion
Recommendations
Conclusion
Q & A
PRESENTATION FLOW:
OUTLINE:
Project
Background
Problem
Statement
Objectives
Literature
Review
Methodology
Results and
Discussion
Recommendations
Conclusion
Q & A
PROJECT BACKGROUND:
• The use of Series capacitors is widely common for compensating losses
on current carrying lines.
• How it works ?
• Series Compensation is achieved by reducing the reactance value on the
line between the supply bus and load.
• An injected value of the capacitor negative reactance will eliminate the
huge amount of the line positive reactance and as a result the line
impedance is reduced in total.
• Main Application: Electric Grid Lines Compensation
Fig.1: Concept of Series Compensation
• A network consists of various
electrical equipment for
delivering electricity from
suppliers to consumers[10].
Transmission Lines:
• High-voltage current carrying
cables that carry power from
distant sources to demand centers.
• Long Distance (80 Km and Above)
• High Rated Voltage Levels (33,
132, 275, 500 KV)
Distribution Networks:
• Distribution networks that connect
individual customers.
• Shorter Distance (Not more than
50 Km)
• Lower Rated Voltage Levels (33,
22, 11, 6.6 KV and 400/230 V)
 ELECTRIC GRID:
Fig.2: Typical Power System
• The concept is to add a voltage in series with the lines to maintain a fixed
voltage value at the load side despite any load variations. And so, any voltage
drops in the line can be compensated [1].
• By doing that, the voltage profile will be greatly improved and at the same time,
the line losses are reduced [2].
• An important factor - the degree of compensation (𝑲) – which is the ratio of
line reactance to be compensated in order to enhance the overall performance of
the line.
• K is chosen to be in the range of 25 % to 75 % to avoid overcompensation
which increases the risk of ferroresonance.
Fig.3: Series Capacitor Compensated Distribution Lines
• When K = 75 % , the line will be electrically shorter by 50 % and 75 % respectively
which means that only a part of the line will be affecting the transmission process.
Uncompensated line
Compensated line K = 75 %
Compensated line K = 50 %
• A typical series capacitor unit is not just a capacitor in series with the
line.
• For proper functioning, series compensation requires control,
protection and monitoring to enable it to perform as an integrated part
of a power system.
• Also, since the series capacitor is working at the same voltage level as
the rest of the system, it needs to be fully insulated to ground.
 SERIES CAPACITOR COMPENSATION UNIT:
• Capacitor Bank
Consists of capacitor units connected
in series and parallel to obtain the
required total Mvar ratings
(Compensation Percentage).
• Metal Oxide Varistor
Protect series capacitor against over-
voltages caused by faults in the
surrounding network.
• Damping Circuit
Limit and damp the discharge current
caused by spark gap operation or
closing the bypass breaker.
• Bypass Breaker
Allow the series capacitor to be
bypassed In cases of internal faults
and reinsert the faulted line after fault
is cleared[8].
Fig.5: ABB MiniCap Internal Structure
(Single Line)
 INTERNAL STRUCTURE:
OUTLINE:
Project
Background
Problem
Statement
Objectives
Literature
Review
Methodology
Results
Discussion
Recommendations
Conclusion
Q & A
1. Series Capacitor Compensation is not widely used in distribution
systems due to unfamiliarity in the design, operation, negative
effects.
2. There are no recent studies analyzing the technical effects along with
the economic effects of applying series capacitor compensation
method in distribution networks with respect to:
• Reduction in Reactive Power input from the grid system.
• Enhancement in voltage profile
• The ability to increase Power Transfer Capability of the system.
PROBLEM STATEMENT:
OUTLINE:
Project
Background
Problem
Statement
Objectives
Literature
Review
Methodology
Results
Discussion
Recommendations
Conclusion
Q & A
 To Compare two proposed alternatives for increasing Power Transfer
Capability in a typical distribution system. The two alternatives are;
Series Capacitor Compensation and New line construction.
 To analyze possible reduction in reactive power input to the grid.
 To Determine the optimum location on the distribution network for
applying series capacitor compensation.
OBJECTIVES:
OUTLINE:
Project
Background
Problem
Statement
Objectives
Literature
Review
Methodology
Results
Discussion
Recommendations
Conclusion
Q & A
LITERATURE REVIEW:
Voltage Profile and Power Transfer Capability:
• In distribution networks, voltage fluctuations are caused by switching
of heavy loads, starting of large motors and transformer energizing[11].
• This results in an instantaneous voltage drop which usually lasts for a
few seconds until the motor reaches the operating speed[3].
• This may trigger the operation of voltage sensitive controls (Under
Voltage), leading to extensive disconnection of loads and thus
adversely affecting consumers and company Revenues.[11]
• In addition, the power transfer capability of a line is a fixed value
and is identified by the design standards and line ratings.
• Increasing the PTC might be crucial in times of economical growth.
• Alternatives can be proposed such as uprating the feeder voltage,
constructing a parallel feeder, and constructing a new substation [3].
• When considering any of the alternatives, big investments should be
made to cover the expenses needed.
• That’s why an accurate cost optimization should be made to confirm
if the alternative is economically justified or not.
 Series Compensation as an Alternative:
• A case study performed by ABB Sweden was
analyzed to evaluate some of the proposed
alternatives. In the study, An existing 1300
MW transmission system using two parallel
500 kV lines is to be upgraded to a 2000 MW
system.
• The options are to series compensate the two
existing lines or build a third parallel line[4].
• The Cost Analysis showed that the total investment for compensating the two
existing lines will be approximately 10 percent of building a third, parallel line.
• The study proved series capacitor compensation as a proper, cost effective and
environmentally acceptable solution to help enhance the voltage profile and PTC.
Economic Evaluation of Alternatives:
Investments in the energy sector are usually managed by the government because of the
high criticality on the country’s economy.
It reflects not only investment costs but also other items –operational costs,
deprecations, reducing of costs of supply interruptions and the time value of the money
[11].
In the analysis, there are two main terms to be introduced which are present worth, and
annual worth [12]. The present worth is the value of an expected income flow
determined as of the date of the project’s appraisal and it can be calculated as in
Equation 2.0.
P = AW(P/A, i %, n) Equation (2.0)
As for the annual worth, it is defined as the yearly cost of owning and operating an asset
over its entire lifespan and can be calculated by Equation 2.1.
A = PW(A/P, i %, n) Equation (2.0)
Where;
i is the rate of return
n is the lifespan
As a public sector project, there are significant differences in its characteristics
comparing to private sector alternatives.
• Size of investment will demand large initial investments.
• Project’s life estimates is important as public projects often have long lifespans.
• Low interest rate.
• Publicly owned projects have costs that are paid mostly by the government unit.
• A main aim of benefiting the citizens.
Alternative Selection using Incremental Benefit-Cost Ratio Analysis:
• The incremental benefit-cost analysis is used to choose the best option from a list
of mutually exclusive alternatives [15] .
• Mutually exclusive alternatives can be defined as the business proposals of a
certain project where only one of these proposals can be selected.
• Applicable for all types of investment projects with a main aim of improving the
current business schemes.
• The examples of this improvement may vary from a simple replacement in a
certain project to the full construction of new plants or factories.
OUTLINE:
Project
Background
Problem
Statement
Objectives
Literature
Review
Methodology
Results and
Discussion
Recommendations
Conclusion
Q & A
METHODOLOGY:
Project's first activity (Proof of Concept)
Project’s second activity (Location Based Compensation)
Project's third activity (Distribution Network Series Capacitor
Compensation)
Analysis and evaluation of the data obtained.
Project’s fourth activity (Economic evaluation of proposed alternatives)
Project 1st activity:
To prove the technical concept of series capacitor compensation in
enhancing transmission efficiency
Generator Load
Transmission Line
Bus 1 Bus 2 Step-down
TransformerStep –up
Transformer
• Different degrees of compensation (K)
• Capacitor Unit is placed at the midpoint between bus 1 and 2
• Measurements:
 Voltage profile at the receiving end of the line (load side)
 The reactive power input to the system
 The power transfer capability
Generator Load
Transmission LineBus 1 Bus 2 Step-down
TransformerStep –up
Transformer
L/2 L/2
K = 25 %
K = 75 %K = 40 % K = 60 %
Project 2nd activity:
Generator Load
Transmission Line
Bus 1 Bus 2 Step-down
TransformerStep –up
Transformer
To determine the location where the capacitor unit should be positioned to
give its highest performance
• Different degrees of compensation (K)
• Different locations (D) - the total length of the line is divided into twelve (12)
sections.
• Measurements:
 Voltage profile at the receiving end of the line (load side)
 The reactive power input to the system
 The power transfer capability
K = 25 %
K = 75 %K = 40 % K = 60 %
Project 3rd activity:
To investigate application of series compensation on an electrical
distribution network
L = 10 km L = 30 km L = 50 km
K = 75 %K = 40 %
• The compensation is applied for the line with the highest reactance.
• Two degrees of compensation K = 40 %, K = 75 %
• Three different locations at 𝐷 = 1/2, 𝐷 = 3/4, 𝐷 = 2/3 of the total line’s
length.
• Three different line lengths are assumed; 10 km, 30 km and 50 km.
Project 4th activity:
To economically justify the most suitable alternative for an electrical
distribution network
• Justify the two alternatives technically regarding their abilities in
enhancing transmission efficiency.
• The incremental benefit cost ratio is implemented to compare the overall
cost of applying either of the alternatives.
• Determine the equivalent total costs for both alternatives.
• Order the alternatives by equivalent total cost: first smaller, then larger.
Calculate the incremental cost (∆C) for the larger-cost alternative. This is
the denominator in ∆B/C.
• Calculate the equivalent total benefits.
• Calculate the incremental benefits (∆B) for the larger-cost alternative.
• Calculate the ∆B/ ∆C ratio.
• Use the selection guideline to select the lower-cost alternative if ∆B/ ∆C <
1.0
OUTLINE:
Project
Background
Problem
Statement
Objectives
Literature
Review
Methodology
Results and
Discussion
Recommendations
Conclusion
Q & A
Project 1st activity:
Project 2nd activity:
Vr
• An increase in voltage magnitude by increasing K
• An increase in voltage magnitude by reducing the distance between the load
and the capacitor unit D
• Voltage magnitude must not exceed +,- 5 % of its nominal value
Ps
• A significant increase in
PTC by increasing K
• An increase in PTC by
reducing the distance
between the load and
the capacitor unit D
• Positive impact
• The limit depends on
line rating and its
ability to transfer active
power
Qs
• A decrease in reactive power input to the network by increasing K
• An increase in reactive power input to the network by reducing the distance between
the load and the capacitor unit D
• A suitable location must be chosen to get the least Qs without affecting other
transmission parameters
• A compensation degree of K = 75 % which has been proven as the most suitable for
enhancing the transmission efficiency.
• The series capacitor unit’s location is estimated at a distance of 𝐷 = 2/3 or 𝐷 =
3/4 of the total length of the line.
• For 250 km line, the most suitable location for implementing series compensation
will be at 200 km or 225 km from the line’s sending end.
Project 3rd activity:
0.92 0.94 0.96 0.98 1 1.02 1.04
No
Compensation
40%
Compensation
75%
Compensation
Voltage (pu)
VR at L = 10 km
VR at D =
3/4
VR at D =
2/3
VR at D =
1/2
0.93
0.94
0.95
0.96
0.97
0.98
0.99
1
1.01
1.02
1.03
No Compensation 40% Compensation 75% Compensation
Voltage(pu)
VR at L = 30 km
VR at D = 1/2
VR at D = 2/3
VR at D = 3/4
0.9
0.95
1
1.05
1.1
No
Compensation
40%
Compensation
75%
Compensation
Voltage (pu)
VR at L = 50 km
VR at D = 3/4
VR at D = 2/3
VR at D = 1/2
• An overall enhancement in the receiving end voltage profile with
K = 75 %
• No significant impact on the voltage profile when changing the
capacitor unit’s location along the line.
0
0.5
1
1.5
2
2.5
3
3.5
No Compensation
40%
Compensation 75%
Compensation
Power(pu)
PS at L = 10 km
PS at D = 3/4
PS at D = 2/3
PS at D = 1/2
0
0.5 1
1.5
2
2.5
No Compensation
40% Compensation
75% Compensation
Power (pu)
PS at L = 30 km
PS at D = 1/2
PS at D = 2/3
PS at D = 3/4
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
No
Compensation 40%
Compensation 75%
Compensation
Power(pu)
PS at L = 50 km
PS at D = 3/4
PS at D = 2/3
PS at D = 1/2
• A significant increase in the power transfer capability along the line with
K = 75 %
• No significant impact on the PTC when changing the capacitor unit’s
location along the line.
Project 4th activity:
Case Study:
 Line rating: 33 kv
 Total length: 30 km
 Power transfer capability: 117 MVA
 Line reactance: 0.7 + j2.901 MΩ / per km
Proposed Alternatives to increase PTC:
 Alternative 1: Compensating the existing line with capacitor unit (series
capacitor compensation)
 Alternative 2: Construction of a new line.
Alternative Comparison (Technical):
0.92
0.94
0.96
0.98
1
1.02
75%
Compensation
New Line
No
Compensation
Voltage (pu)
Alternatives Comparison (VR)
VR
0
0.5
1
1.5
2
2.5
75% Compensation New Line No Compensation
Power(pu)
Alternatives Comparison (PTC)
75% Compensation
New Line
No Compensation
• An overall enhancement in the receiving end voltage profile with K = 75 %
• A significant increase in the power transfer capability by 93 % (1.09 pu) along the
line with K = 75 % (Alternative 1) comparing to 18 % (0.22 pu) (Alternative 2).
• Alternative 1 has been technically justified.
Alternative Comparison (Economic):
Price
per
Mwh MW
Hourly
Benefits Daily Benefits
Annual
Benefits
Initial
investment
Annual Cost
(O&M)
Alternative 1 50 109 5450 130800 47742000 480000 48000
Alternative 2 50 22 1100 26400 9636000 5400000 540000
PW1C = initial cost 1 + pw of
(O&M1) 641880 1121880
PW1B = present worth of annually
estimated benefits 3105617.1
PW2C = initial cost 2 + pw of
(O&M2) 7221150 12621150
PW2B = present worth of annually
estimated benefits 626821.8
ΔC 11499270
ΔB 2478795.3
ΔB/ΔC 0.215 As ΔB/ΔC < 1 ∴ Alternative 1 is justified
 Benefits: an increase in PTC by 1.09 pu (119
MVA) at base power of 100 MVA.
 Estimated annual value of benefits = 47742000
USD per year at MW/h price of 50 USD.
 Capacitor reactance = Total line reactance * 0.75
= 87 * 0.75 = 65.25 MVAR
 Suggested capacitor unit: ABB MiniCap (12
MVAR per unit)
 N = 65.25 / 12 = 6 units
 Unit price = 70000 USD
 Shipping and installation cost = 10000 USD
 Total initial cost = 70000 * 6 + 10000 * 6 =
480000 USD
 Maintenance and operation per year = 10 % of
total cost = 48000 USD per year
Alternative 1:
ABB MiniCap – 3 Phase Series
Capacitor Unit
Alternative 2:
 Benefits: an increase in PTC by 0.22 pu (22 MVA) at base power of 100 MVA.
 Estimated annual value of benefits = 9636000 USD per year at MW/h price of 50
USD.
 Construction cost per km = 180000 USD
 Total initial cost = 180000 * 30 = 5400000 USD
 Maintenance and operation per year = 540000 USD per year
 PROJECT KEY MILESTONE:
No. Item/Week 1 2 3 4 5 6 7 8 9 10 11 12 13 14
1 Preparing the
Progress
Report
2 Submission of
Progress
Report
3 Poster
Presentation
4 Submission
Final Report’s
Draft
5 Submission of
Final Report
 PROJECT TIMELINE STUDY PLAN:
No. Item/Week 1 2 3 4 5 6 7 8 9 10 11 12 13 14
1 Analysis of
Project’s First
Activity Data
2 Project’s
Second
Activity
3 Analysis of
Project’s
Second
Activity Data
4 Project’s Third
Activity
5 Analysis of
Project’s Third
Activity Data
6 Project’s
fourth Activity
OUTLINE:
Project
Background
Problem
Statement
Objectives
Literature
Review
Methodology
Results and
Discussion
Recommendations
Conclusion
Q & A
RECOMMENDATIONS:
• Series capacitors are most effective for load variations involving a high
reactive content.
• Overcompensation should be avoided. K = 100 % is not advised for
compensating the line.
• The possibility of oscillations with the downstream loads and transformers
can be reduced by bypassing the capacitor bank prior to the
energizing or reclosing of the distribution circuit.
• The protection of the capacitor bank must be ensured by the use of
overvoltage protective schemes.
•
OUTLINE:
Project
Background
Problem
Statement
Objectives
Literature
Review
Methodology
Results and
Discussion
Recommendations
Conclusion
Q & A
• In this study, the use of series capacitor compensation method in
distribution networks is suggested to reduce line losses, enhance voltage
profile and gain the ability to increase power transfer capability through
the network.
• The analysis done on simulation basis proved that the technique can
increase the power transfer capability and enhance voltage profile as the
technique has shown high efficiency by the simulation results for the 14
Bus Electrical distribution network.
• The series capacitor unit’s location impact has been proven to be slight
regarding short distance lines and will not have an important impact on
the network.
• Economically, the technique has been justified by the use of incremental
benefit cost ratio analysis associated with public sector projects.
CONCLUSION:
OUTLINE:
Project
Background
Problem
Statement
Objectives
Literature
Review
Methodology
Results and
Discussion
Recommendations
Conclusion
Q & A
Q&A
1. T. F. Orchi, M. J. Hossain, H. R. Pota, and M. S. Rahman, "Impact of distributed
generation and series compensation on distribution network," in Industrial Electronics
and Applications (ICIEA), 2013 8th IEEE Conference on, 2013, pp. 854-859.
2. S. Das and D. Das, "Series capacitor compensation for radial distribution networks," in
Innovative Smart Grid Technologies - India (ISGT India), 2011 IEEE PES, 2011, pp.
178-182.
3. L. Morgan, J. M. Barcus, and S. Ihara, "Distribution series capacitor with high-energy
varistor protection," Power Delivery, IEEE Transactions on, vol. 8, pp. 1413-1419,
1993.
4. A. Sweden, "Series Compensation - Boosting transmission capacity," ed, 2005.
5. N. K. R. Wamkeue , J. East , Y.Boisclair, "Series Compensation for a Hydro-Quebec
Long Distribution Line."
6. I. C. Report", "READER'S GUIDE TO SUBSYNCHRONOUS RESONANCE,"
IEEE1992.
REFERENCES:
7. G. C. Baker, "Reconductoring power lines- an example exercise in conductor
selection," in Rural Electric Power Conference, 2001, 2001, pp. D1/1-D1/6.
8. J. S. Hedin and L. H. Paulsson, "Application and evaluation of a new concept for
compact series compensation for distribution networks," in Electricity Distribution,
1993. CIRED. 12th International Conference on, 1993, pp. 1.22/1-1.22/5 vol.1.
9. M. Couvreur, E. De Jaeger, P. Goossens, and A. Robert, "The concept of short-circuit
power and the assessment of the flicker emission level," in Electricity Distribution,
2001. Part 1: Contributions. CIRED. 16th International Conference and Exhibition
on (IEE Conf. Publ No. 482), 2001, p. 7 pp. vol.2.
10. Kaplan, S. M. (2009). Smart Grid. Electrical Power Transmission: Background and
Policy Issues. The Capital.Net, Government Series. Pp. 1-42.
11. H. A. Arun Pachori , Vikendra Moranya , Associat Professor, "Static VAR
Compensation Technique for IEEE 14-bus System," International Journal of
Emerging Technology and Advanced Engineering, vol. Volume 3, August 2013.
REFERENCES:

More Related Content

What's hot

Modern power system planning new
Modern power system planning newModern power system planning new
Modern power system planning newBayu imadul Bilad
 
IRJET- Simulation and Experimental Verification of Single Phase Unity Power F...
IRJET- Simulation and Experimental Verification of Single Phase Unity Power F...IRJET- Simulation and Experimental Verification of Single Phase Unity Power F...
IRJET- Simulation and Experimental Verification of Single Phase Unity Power F...IRJET Journal
 
Impact of dynamic demand response in the load frequency control
Impact of dynamic demand response in the load frequency controlImpact of dynamic demand response in the load frequency control
Impact of dynamic demand response in the load frequency controlIRJET Journal
 
Power System Planning
Power System PlanningPower System Planning
Power System Planninglinsstalex
 
Design methodology of smart photovoltaic plant
Design methodology of smart photovoltaic plant Design methodology of smart photovoltaic plant
Design methodology of smart photovoltaic plant IJECEIAES
 
S 8 final-report-april-2003
S 8 final-report-april-2003S 8 final-report-april-2003
S 8 final-report-april-2003Vara Prasad
 
Distribution System Planning and Design
Distribution System Planning and DesignDistribution System Planning and Design
Distribution System Planning and DesignAdithya Ballaji
 
IRJET- Assessment of Voltage Stability in a Power System Network and its Impr...
IRJET- Assessment of Voltage Stability in a Power System Network and its Impr...IRJET- Assessment of Voltage Stability in a Power System Network and its Impr...
IRJET- Assessment of Voltage Stability in a Power System Network and its Impr...IRJET Journal
 
Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]Sifan Welisa
 
Congestion issues and its related management
Congestion issues and its related managementCongestion issues and its related management
Congestion issues and its related managementalpna1808
 
Available transfer capability (atc) sbw ppt
Available transfer capability (atc) sbw pptAvailable transfer capability (atc) sbw ppt
Available transfer capability (atc) sbw pptRavi Sekpure
 
A Pilot Experience for the Integration of Distributed Generation in Active Di...
A Pilot Experience for the Integration of Distributed Generation in Active Di...A Pilot Experience for the Integration of Distributed Generation in Active Di...
A Pilot Experience for the Integration of Distributed Generation in Active Di...davidtrebolle
 
Available transfer capability computations in the indian southern e.h.v power...
Available transfer capability computations in the indian southern e.h.v power...Available transfer capability computations in the indian southern e.h.v power...
Available transfer capability computations in the indian southern e.h.v power...eSAT Publishing House
 
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...IRJET Journal
 
A New approach for controlling the power flow in a transmission system using ...
A New approach for controlling the power flow in a transmission system using ...A New approach for controlling the power flow in a transmission system using ...
A New approach for controlling the power flow in a transmission system using ...IJMER
 
Centralized voltage control in medium voltage distribution networks with dist...
Centralized voltage control in medium voltage distribution networks with dist...Centralized voltage control in medium voltage distribution networks with dist...
Centralized voltage control in medium voltage distribution networks with dist...davidtrebolle
 
Guidelines and best practices for the commissioning and operation of controll...
Guidelines and best practices for the commissioning and operation of controll...Guidelines and best practices for the commissioning and operation of controll...
Guidelines and best practices for the commissioning and operation of controll...Power System Operation
 

What's hot (20)

Modern power system planning new
Modern power system planning newModern power system planning new
Modern power system planning new
 
IRJET- Simulation and Experimental Verification of Single Phase Unity Power F...
IRJET- Simulation and Experimental Verification of Single Phase Unity Power F...IRJET- Simulation and Experimental Verification of Single Phase Unity Power F...
IRJET- Simulation and Experimental Verification of Single Phase Unity Power F...
 
Impact of dynamic demand response in the load frequency control
Impact of dynamic demand response in the load frequency controlImpact of dynamic demand response in the load frequency control
Impact of dynamic demand response in the load frequency control
 
Power System Planning
Power System PlanningPower System Planning
Power System Planning
 
ijess_paper7
ijess_paper7ijess_paper7
ijess_paper7
 
Design methodology of smart photovoltaic plant
Design methodology of smart photovoltaic plant Design methodology of smart photovoltaic plant
Design methodology of smart photovoltaic plant
 
S 8 final-report-april-2003
S 8 final-report-april-2003S 8 final-report-april-2003
S 8 final-report-april-2003
 
Distribution System Planning and Design
Distribution System Planning and DesignDistribution System Planning and Design
Distribution System Planning and Design
 
IRJET- Assessment of Voltage Stability in a Power System Network and its Impr...
IRJET- Assessment of Voltage Stability in a Power System Network and its Impr...IRJET- Assessment of Voltage Stability in a Power System Network and its Impr...
IRJET- Assessment of Voltage Stability in a Power System Network and its Impr...
 
Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]
 
Final ppt
Final pptFinal ppt
Final ppt
 
Congestion issues and its related management
Congestion issues and its related managementCongestion issues and its related management
Congestion issues and its related management
 
Available transfer capability (atc) sbw ppt
Available transfer capability (atc) sbw pptAvailable transfer capability (atc) sbw ppt
Available transfer capability (atc) sbw ppt
 
A Pilot Experience for the Integration of Distributed Generation in Active Di...
A Pilot Experience for the Integration of Distributed Generation in Active Di...A Pilot Experience for the Integration of Distributed Generation in Active Di...
A Pilot Experience for the Integration of Distributed Generation in Active Di...
 
Available transfer capability computations in the indian southern e.h.v power...
Available transfer capability computations in the indian southern e.h.v power...Available transfer capability computations in the indian southern e.h.v power...
Available transfer capability computations in the indian southern e.h.v power...
 
Electric Utility Solutions: Basics of Load Allocation
Electric Utility Solutions: Basics of Load AllocationElectric Utility Solutions: Basics of Load Allocation
Electric Utility Solutions: Basics of Load Allocation
 
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
 
A New approach for controlling the power flow in a transmission system using ...
A New approach for controlling the power flow in a transmission system using ...A New approach for controlling the power flow in a transmission system using ...
A New approach for controlling the power flow in a transmission system using ...
 
Centralized voltage control in medium voltage distribution networks with dist...
Centralized voltage control in medium voltage distribution networks with dist...Centralized voltage control in medium voltage distribution networks with dist...
Centralized voltage control in medium voltage distribution networks with dist...
 
Guidelines and best practices for the commissioning and operation of controll...
Guidelines and best practices for the commissioning and operation of controll...Guidelines and best practices for the commissioning and operation of controll...
Guidelines and best practices for the commissioning and operation of controll...
 

Similar to Viva

Energy Efficiency in Electrical Systems.pptx
Energy  Efficiency in Electrical Systems.pptxEnergy  Efficiency in Electrical Systems.pptx
Energy Efficiency in Electrical Systems.pptxPoojaAnupGarg
 
OptimizationMethodsApplicationtoOptimalPowerFlowinElectricPowerSystems.pdf
OptimizationMethodsApplicationtoOptimalPowerFlowinElectricPowerSystems.pdfOptimizationMethodsApplicationtoOptimalPowerFlowinElectricPowerSystems.pdf
OptimizationMethodsApplicationtoOptimalPowerFlowinElectricPowerSystems.pdfSAli656322
 
Reconfiguración de redes eléctricas - Sistemas de Redes de distribución de en...
Reconfiguración de redes eléctricas - Sistemas de Redes de distribución de en...Reconfiguración de redes eléctricas - Sistemas de Redes de distribución de en...
Reconfiguración de redes eléctricas - Sistemas de Redes de distribución de en...JOe Torres Palomino
 
The Voltage Fed Series Compensation Based ZVZCS Topology and Its Tuning Metho...
The Voltage Fed Series Compensation Based ZVZCS Topology and Its Tuning Metho...The Voltage Fed Series Compensation Based ZVZCS Topology and Its Tuning Metho...
The Voltage Fed Series Compensation Based ZVZCS Topology and Its Tuning Metho...IRJET Journal
 
Planning and modern trends in hvdc
Planning and modern trends in hvdcPlanning and modern trends in hvdc
Planning and modern trends in hvdcjawaharramaya
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)IJERD Editor
 
IRJET - Design and Analysis of a SEPIC Integrated Boost (SIB) Converter using...
IRJET - Design and Analysis of a SEPIC Integrated Boost (SIB) Converter using...IRJET - Design and Analysis of a SEPIC Integrated Boost (SIB) Converter using...
IRJET - Design and Analysis of a SEPIC Integrated Boost (SIB) Converter using...IRJET Journal
 
Briefing: Understanding and De-Risking EV Charging Power Delivery
Briefing: Understanding and De-Risking EV Charging Power DeliveryBriefing: Understanding and De-Risking EV Charging Power Delivery
Briefing: Understanding and De-Risking EV Charging Power DeliveryBlack & Veatch
 
when a coil is rotated or turned under a magnetic field, there occurs a force...
when a coil is rotated or turned under a magnetic field, there occurs a force...when a coil is rotated or turned under a magnetic field, there occurs a force...
when a coil is rotated or turned under a magnetic field, there occurs a force...theijes
 
Reconfiguration and Capacitor Placement in Najaf Distribution Networks Sector...
Reconfiguration and Capacitor Placement in Najaf Distribution Networks Sector...Reconfiguration and Capacitor Placement in Najaf Distribution Networks Sector...
Reconfiguration and Capacitor Placement in Najaf Distribution Networks Sector...IRJET Journal
 
Optimal placement and sizing of ht shunt capacitors for transmission loss min...
Optimal placement and sizing of ht shunt capacitors for transmission loss min...Optimal placement and sizing of ht shunt capacitors for transmission loss min...
Optimal placement and sizing of ht shunt capacitors for transmission loss min...IAEME Publication
 
A Review of Analysis and Modeling of Grid Connected Three Phase Multilevel Un...
A Review of Analysis and Modeling of Grid Connected Three Phase Multilevel Un...A Review of Analysis and Modeling of Grid Connected Three Phase Multilevel Un...
A Review of Analysis and Modeling of Grid Connected Three Phase Multilevel Un...IRJET Journal
 
Presentation on DC-DC converter for EV
Presentation on DC-DC converter for EVPresentation on DC-DC converter for EV
Presentation on DC-DC converter for EVUdayaKumar120822
 
SIMULATION AND ANALYSIS OF TIBC FOR INDUCTION MOTOR DRIVE
SIMULATION AND ANALYSIS OF TIBC FOR INDUCTION MOTOR DRIVESIMULATION AND ANALYSIS OF TIBC FOR INDUCTION MOTOR DRIVE
SIMULATION AND ANALYSIS OF TIBC FOR INDUCTION MOTOR DRIVEEditor IJMTER
 
Implementation of a grid-tied emergency back-up power supply for medium and l...
Implementation of a grid-tied emergency back-up power supply for medium and l...Implementation of a grid-tied emergency back-up power supply for medium and l...
Implementation of a grid-tied emergency back-up power supply for medium and l...IJECEIAES
 
Congestion Management in Deregulated Power System by Using FACTS Devices
Congestion Management in Deregulated Power System by Using FACTS DevicesCongestion Management in Deregulated Power System by Using FACTS Devices
Congestion Management in Deregulated Power System by Using FACTS DevicesIRJET Journal
 
IRJET- A Novel Modified Switched Capacitor Nine Level Inverter Topology with ...
IRJET- A Novel Modified Switched Capacitor Nine Level Inverter Topology with ...IRJET- A Novel Modified Switched Capacitor Nine Level Inverter Topology with ...
IRJET- A Novel Modified Switched Capacitor Nine Level Inverter Topology with ...IRJET Journal
 
A DC-DC Converter with Ripple Current Cancellation Based On Duty Cycle Selection
A DC-DC Converter with Ripple Current Cancellation Based On Duty Cycle SelectionA DC-DC Converter with Ripple Current Cancellation Based On Duty Cycle Selection
A DC-DC Converter with Ripple Current Cancellation Based On Duty Cycle SelectionIJMER
 

Similar to Viva (20)

Energy Efficiency in Electrical Systems.pptx
Energy  Efficiency in Electrical Systems.pptxEnergy  Efficiency in Electrical Systems.pptx
Energy Efficiency in Electrical Systems.pptx
 
Demand side management
Demand side managementDemand side management
Demand side management
 
OptimizationMethodsApplicationtoOptimalPowerFlowinElectricPowerSystems.pdf
OptimizationMethodsApplicationtoOptimalPowerFlowinElectricPowerSystems.pdfOptimizationMethodsApplicationtoOptimalPowerFlowinElectricPowerSystems.pdf
OptimizationMethodsApplicationtoOptimalPowerFlowinElectricPowerSystems.pdf
 
Reconfiguración de redes eléctricas - Sistemas de Redes de distribución de en...
Reconfiguración de redes eléctricas - Sistemas de Redes de distribución de en...Reconfiguración de redes eléctricas - Sistemas de Redes de distribución de en...
Reconfiguración de redes eléctricas - Sistemas de Redes de distribución de en...
 
The Voltage Fed Series Compensation Based ZVZCS Topology and Its Tuning Metho...
The Voltage Fed Series Compensation Based ZVZCS Topology and Its Tuning Metho...The Voltage Fed Series Compensation Based ZVZCS Topology and Its Tuning Metho...
The Voltage Fed Series Compensation Based ZVZCS Topology and Its Tuning Metho...
 
Planning and modern trends in hvdc
Planning and modern trends in hvdcPlanning and modern trends in hvdc
Planning and modern trends in hvdc
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 
IRJET - Design and Analysis of a SEPIC Integrated Boost (SIB) Converter using...
IRJET - Design and Analysis of a SEPIC Integrated Boost (SIB) Converter using...IRJET - Design and Analysis of a SEPIC Integrated Boost (SIB) Converter using...
IRJET - Design and Analysis of a SEPIC Integrated Boost (SIB) Converter using...
 
Briefing: Understanding and De-Risking EV Charging Power Delivery
Briefing: Understanding and De-Risking EV Charging Power DeliveryBriefing: Understanding and De-Risking EV Charging Power Delivery
Briefing: Understanding and De-Risking EV Charging Power Delivery
 
when a coil is rotated or turned under a magnetic field, there occurs a force...
when a coil is rotated or turned under a magnetic field, there occurs a force...when a coil is rotated or turned under a magnetic field, there occurs a force...
when a coil is rotated or turned under a magnetic field, there occurs a force...
 
Reconfiguration and Capacitor Placement in Najaf Distribution Networks Sector...
Reconfiguration and Capacitor Placement in Najaf Distribution Networks Sector...Reconfiguration and Capacitor Placement in Najaf Distribution Networks Sector...
Reconfiguration and Capacitor Placement in Najaf Distribution Networks Sector...
 
Optimal placement and sizing of ht shunt capacitors for transmission loss min...
Optimal placement and sizing of ht shunt capacitors for transmission loss min...Optimal placement and sizing of ht shunt capacitors for transmission loss min...
Optimal placement and sizing of ht shunt capacitors for transmission loss min...
 
A Review of Analysis and Modeling of Grid Connected Three Phase Multilevel Un...
A Review of Analysis and Modeling of Grid Connected Three Phase Multilevel Un...A Review of Analysis and Modeling of Grid Connected Three Phase Multilevel Un...
A Review of Analysis and Modeling of Grid Connected Three Phase Multilevel Un...
 
Presentation on DC-DC converter for EV
Presentation on DC-DC converter for EVPresentation on DC-DC converter for EV
Presentation on DC-DC converter for EV
 
Economic_Dispatch_in_power_systems.pdf
Economic_Dispatch_in_power_systems.pdfEconomic_Dispatch_in_power_systems.pdf
Economic_Dispatch_in_power_systems.pdf
 
SIMULATION AND ANALYSIS OF TIBC FOR INDUCTION MOTOR DRIVE
SIMULATION AND ANALYSIS OF TIBC FOR INDUCTION MOTOR DRIVESIMULATION AND ANALYSIS OF TIBC FOR INDUCTION MOTOR DRIVE
SIMULATION AND ANALYSIS OF TIBC FOR INDUCTION MOTOR DRIVE
 
Implementation of a grid-tied emergency back-up power supply for medium and l...
Implementation of a grid-tied emergency back-up power supply for medium and l...Implementation of a grid-tied emergency back-up power supply for medium and l...
Implementation of a grid-tied emergency back-up power supply for medium and l...
 
Congestion Management in Deregulated Power System by Using FACTS Devices
Congestion Management in Deregulated Power System by Using FACTS DevicesCongestion Management in Deregulated Power System by Using FACTS Devices
Congestion Management in Deregulated Power System by Using FACTS Devices
 
IRJET- A Novel Modified Switched Capacitor Nine Level Inverter Topology with ...
IRJET- A Novel Modified Switched Capacitor Nine Level Inverter Topology with ...IRJET- A Novel Modified Switched Capacitor Nine Level Inverter Topology with ...
IRJET- A Novel Modified Switched Capacitor Nine Level Inverter Topology with ...
 
A DC-DC Converter with Ripple Current Cancellation Based On Duty Cycle Selection
A DC-DC Converter with Ripple Current Cancellation Based On Duty Cycle SelectionA DC-DC Converter with Ripple Current Cancellation Based On Duty Cycle Selection
A DC-DC Converter with Ripple Current Cancellation Based On Duty Cycle Selection
 

Viva

  • 1. Wagdy Ahmed Moustafa Mansour Electrical and Electronics Engineering Department Universiti Teknologi PETRONAS Supervisor: Ir Mohd Faris Bin Abdullah Final Year Project Viva “Technical-Economic Analysis in the Application of Series Capacitor Compensation for Distribution Networks”
  • 4. PROJECT BACKGROUND: • The use of Series capacitors is widely common for compensating losses on current carrying lines. • How it works ? • Series Compensation is achieved by reducing the reactance value on the line between the supply bus and load. • An injected value of the capacitor negative reactance will eliminate the huge amount of the line positive reactance and as a result the line impedance is reduced in total. • Main Application: Electric Grid Lines Compensation Fig.1: Concept of Series Compensation
  • 5. • A network consists of various electrical equipment for delivering electricity from suppliers to consumers[10]. Transmission Lines: • High-voltage current carrying cables that carry power from distant sources to demand centers. • Long Distance (80 Km and Above) • High Rated Voltage Levels (33, 132, 275, 500 KV) Distribution Networks: • Distribution networks that connect individual customers. • Shorter Distance (Not more than 50 Km) • Lower Rated Voltage Levels (33, 22, 11, 6.6 KV and 400/230 V)  ELECTRIC GRID: Fig.2: Typical Power System
  • 6. • The concept is to add a voltage in series with the lines to maintain a fixed voltage value at the load side despite any load variations. And so, any voltage drops in the line can be compensated [1]. • By doing that, the voltage profile will be greatly improved and at the same time, the line losses are reduced [2]. • An important factor - the degree of compensation (𝑲) – which is the ratio of line reactance to be compensated in order to enhance the overall performance of the line. • K is chosen to be in the range of 25 % to 75 % to avoid overcompensation which increases the risk of ferroresonance. Fig.3: Series Capacitor Compensated Distribution Lines
  • 7. • When K = 75 % , the line will be electrically shorter by 50 % and 75 % respectively which means that only a part of the line will be affecting the transmission process. Uncompensated line Compensated line K = 75 % Compensated line K = 50 %
  • 8. • A typical series capacitor unit is not just a capacitor in series with the line. • For proper functioning, series compensation requires control, protection and monitoring to enable it to perform as an integrated part of a power system. • Also, since the series capacitor is working at the same voltage level as the rest of the system, it needs to be fully insulated to ground.  SERIES CAPACITOR COMPENSATION UNIT:
  • 9. • Capacitor Bank Consists of capacitor units connected in series and parallel to obtain the required total Mvar ratings (Compensation Percentage). • Metal Oxide Varistor Protect series capacitor against over- voltages caused by faults in the surrounding network. • Damping Circuit Limit and damp the discharge current caused by spark gap operation or closing the bypass breaker. • Bypass Breaker Allow the series capacitor to be bypassed In cases of internal faults and reinsert the faulted line after fault is cleared[8]. Fig.5: ABB MiniCap Internal Structure (Single Line)  INTERNAL STRUCTURE:
  • 11. 1. Series Capacitor Compensation is not widely used in distribution systems due to unfamiliarity in the design, operation, negative effects. 2. There are no recent studies analyzing the technical effects along with the economic effects of applying series capacitor compensation method in distribution networks with respect to: • Reduction in Reactive Power input from the grid system. • Enhancement in voltage profile • The ability to increase Power Transfer Capability of the system. PROBLEM STATEMENT:
  • 13.  To Compare two proposed alternatives for increasing Power Transfer Capability in a typical distribution system. The two alternatives are; Series Capacitor Compensation and New line construction.  To analyze possible reduction in reactive power input to the grid.  To Determine the optimum location on the distribution network for applying series capacitor compensation. OBJECTIVES:
  • 15. LITERATURE REVIEW: Voltage Profile and Power Transfer Capability: • In distribution networks, voltage fluctuations are caused by switching of heavy loads, starting of large motors and transformer energizing[11]. • This results in an instantaneous voltage drop which usually lasts for a few seconds until the motor reaches the operating speed[3]. • This may trigger the operation of voltage sensitive controls (Under Voltage), leading to extensive disconnection of loads and thus adversely affecting consumers and company Revenues.[11]
  • 16. • In addition, the power transfer capability of a line is a fixed value and is identified by the design standards and line ratings. • Increasing the PTC might be crucial in times of economical growth. • Alternatives can be proposed such as uprating the feeder voltage, constructing a parallel feeder, and constructing a new substation [3]. • When considering any of the alternatives, big investments should be made to cover the expenses needed. • That’s why an accurate cost optimization should be made to confirm if the alternative is economically justified or not.
  • 17.  Series Compensation as an Alternative: • A case study performed by ABB Sweden was analyzed to evaluate some of the proposed alternatives. In the study, An existing 1300 MW transmission system using two parallel 500 kV lines is to be upgraded to a 2000 MW system. • The options are to series compensate the two existing lines or build a third parallel line[4]. • The Cost Analysis showed that the total investment for compensating the two existing lines will be approximately 10 percent of building a third, parallel line. • The study proved series capacitor compensation as a proper, cost effective and environmentally acceptable solution to help enhance the voltage profile and PTC.
  • 18. Economic Evaluation of Alternatives: Investments in the energy sector are usually managed by the government because of the high criticality on the country’s economy. It reflects not only investment costs but also other items –operational costs, deprecations, reducing of costs of supply interruptions and the time value of the money [11]. In the analysis, there are two main terms to be introduced which are present worth, and annual worth [12]. The present worth is the value of an expected income flow determined as of the date of the project’s appraisal and it can be calculated as in Equation 2.0. P = AW(P/A, i %, n) Equation (2.0) As for the annual worth, it is defined as the yearly cost of owning and operating an asset over its entire lifespan and can be calculated by Equation 2.1. A = PW(A/P, i %, n) Equation (2.0) Where; i is the rate of return n is the lifespan
  • 19. As a public sector project, there are significant differences in its characteristics comparing to private sector alternatives. • Size of investment will demand large initial investments. • Project’s life estimates is important as public projects often have long lifespans. • Low interest rate. • Publicly owned projects have costs that are paid mostly by the government unit. • A main aim of benefiting the citizens.
  • 20. Alternative Selection using Incremental Benefit-Cost Ratio Analysis: • The incremental benefit-cost analysis is used to choose the best option from a list of mutually exclusive alternatives [15] . • Mutually exclusive alternatives can be defined as the business proposals of a certain project where only one of these proposals can be selected. • Applicable for all types of investment projects with a main aim of improving the current business schemes. • The examples of this improvement may vary from a simple replacement in a certain project to the full construction of new plants or factories.
  • 22. METHODOLOGY: Project's first activity (Proof of Concept) Project’s second activity (Location Based Compensation) Project's third activity (Distribution Network Series Capacitor Compensation) Analysis and evaluation of the data obtained. Project’s fourth activity (Economic evaluation of proposed alternatives)
  • 23. Project 1st activity: To prove the technical concept of series capacitor compensation in enhancing transmission efficiency Generator Load Transmission Line Bus 1 Bus 2 Step-down TransformerStep –up Transformer • Different degrees of compensation (K) • Capacitor Unit is placed at the midpoint between bus 1 and 2 • Measurements:  Voltage profile at the receiving end of the line (load side)  The reactive power input to the system  The power transfer capability
  • 24. Generator Load Transmission LineBus 1 Bus 2 Step-down TransformerStep –up Transformer L/2 L/2 K = 25 % K = 75 %K = 40 % K = 60 %
  • 25. Project 2nd activity: Generator Load Transmission Line Bus 1 Bus 2 Step-down TransformerStep –up Transformer To determine the location where the capacitor unit should be positioned to give its highest performance • Different degrees of compensation (K) • Different locations (D) - the total length of the line is divided into twelve (12) sections. • Measurements:  Voltage profile at the receiving end of the line (load side)  The reactive power input to the system  The power transfer capability
  • 26. K = 25 % K = 75 %K = 40 % K = 60 %
  • 27. Project 3rd activity: To investigate application of series compensation on an electrical distribution network
  • 28. L = 10 km L = 30 km L = 50 km K = 75 %K = 40 % • The compensation is applied for the line with the highest reactance. • Two degrees of compensation K = 40 %, K = 75 % • Three different locations at 𝐷 = 1/2, 𝐷 = 3/4, 𝐷 = 2/3 of the total line’s length. • Three different line lengths are assumed; 10 km, 30 km and 50 km.
  • 29. Project 4th activity: To economically justify the most suitable alternative for an electrical distribution network • Justify the two alternatives technically regarding their abilities in enhancing transmission efficiency. • The incremental benefit cost ratio is implemented to compare the overall cost of applying either of the alternatives. • Determine the equivalent total costs for both alternatives. • Order the alternatives by equivalent total cost: first smaller, then larger. Calculate the incremental cost (∆C) for the larger-cost alternative. This is the denominator in ∆B/C. • Calculate the equivalent total benefits. • Calculate the incremental benefits (∆B) for the larger-cost alternative. • Calculate the ∆B/ ∆C ratio. • Use the selection guideline to select the lower-cost alternative if ∆B/ ∆C < 1.0
  • 32. Project 2nd activity: Vr • An increase in voltage magnitude by increasing K • An increase in voltage magnitude by reducing the distance between the load and the capacitor unit D • Voltage magnitude must not exceed +,- 5 % of its nominal value
  • 33. Ps • A significant increase in PTC by increasing K • An increase in PTC by reducing the distance between the load and the capacitor unit D • Positive impact • The limit depends on line rating and its ability to transfer active power
  • 34. Qs • A decrease in reactive power input to the network by increasing K • An increase in reactive power input to the network by reducing the distance between the load and the capacitor unit D • A suitable location must be chosen to get the least Qs without affecting other transmission parameters
  • 35. • A compensation degree of K = 75 % which has been proven as the most suitable for enhancing the transmission efficiency. • The series capacitor unit’s location is estimated at a distance of 𝐷 = 2/3 or 𝐷 = 3/4 of the total length of the line. • For 250 km line, the most suitable location for implementing series compensation will be at 200 km or 225 km from the line’s sending end.
  • 36. Project 3rd activity: 0.92 0.94 0.96 0.98 1 1.02 1.04 No Compensation 40% Compensation 75% Compensation Voltage (pu) VR at L = 10 km VR at D = 3/4 VR at D = 2/3 VR at D = 1/2 0.93 0.94 0.95 0.96 0.97 0.98 0.99 1 1.01 1.02 1.03 No Compensation 40% Compensation 75% Compensation Voltage(pu) VR at L = 30 km VR at D = 1/2 VR at D = 2/3 VR at D = 3/4
  • 37. 0.9 0.95 1 1.05 1.1 No Compensation 40% Compensation 75% Compensation Voltage (pu) VR at L = 50 km VR at D = 3/4 VR at D = 2/3 VR at D = 1/2 • An overall enhancement in the receiving end voltage profile with K = 75 % • No significant impact on the voltage profile when changing the capacitor unit’s location along the line.
  • 38. 0 0.5 1 1.5 2 2.5 3 3.5 No Compensation 40% Compensation 75% Compensation Power(pu) PS at L = 10 km PS at D = 3/4 PS at D = 2/3 PS at D = 1/2 0 0.5 1 1.5 2 2.5 No Compensation 40% Compensation 75% Compensation Power (pu) PS at L = 30 km PS at D = 1/2 PS at D = 2/3 PS at D = 3/4
  • 39. 0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 No Compensation 40% Compensation 75% Compensation Power(pu) PS at L = 50 km PS at D = 3/4 PS at D = 2/3 PS at D = 1/2 • A significant increase in the power transfer capability along the line with K = 75 % • No significant impact on the PTC when changing the capacitor unit’s location along the line.
  • 40. Project 4th activity: Case Study:  Line rating: 33 kv  Total length: 30 km  Power transfer capability: 117 MVA  Line reactance: 0.7 + j2.901 MΩ / per km Proposed Alternatives to increase PTC:  Alternative 1: Compensating the existing line with capacitor unit (series capacitor compensation)  Alternative 2: Construction of a new line.
  • 41. Alternative Comparison (Technical): 0.92 0.94 0.96 0.98 1 1.02 75% Compensation New Line No Compensation Voltage (pu) Alternatives Comparison (VR) VR 0 0.5 1 1.5 2 2.5 75% Compensation New Line No Compensation Power(pu) Alternatives Comparison (PTC) 75% Compensation New Line No Compensation
  • 42. • An overall enhancement in the receiving end voltage profile with K = 75 % • A significant increase in the power transfer capability by 93 % (1.09 pu) along the line with K = 75 % (Alternative 1) comparing to 18 % (0.22 pu) (Alternative 2). • Alternative 1 has been technically justified. Alternative Comparison (Economic): Price per Mwh MW Hourly Benefits Daily Benefits Annual Benefits Initial investment Annual Cost (O&M) Alternative 1 50 109 5450 130800 47742000 480000 48000 Alternative 2 50 22 1100 26400 9636000 5400000 540000 PW1C = initial cost 1 + pw of (O&M1) 641880 1121880 PW1B = present worth of annually estimated benefits 3105617.1 PW2C = initial cost 2 + pw of (O&M2) 7221150 12621150 PW2B = present worth of annually estimated benefits 626821.8 ΔC 11499270 ΔB 2478795.3 ΔB/ΔC 0.215 As ΔB/ΔC < 1 ∴ Alternative 1 is justified
  • 43.  Benefits: an increase in PTC by 1.09 pu (119 MVA) at base power of 100 MVA.  Estimated annual value of benefits = 47742000 USD per year at MW/h price of 50 USD.  Capacitor reactance = Total line reactance * 0.75 = 87 * 0.75 = 65.25 MVAR  Suggested capacitor unit: ABB MiniCap (12 MVAR per unit)  N = 65.25 / 12 = 6 units  Unit price = 70000 USD  Shipping and installation cost = 10000 USD  Total initial cost = 70000 * 6 + 10000 * 6 = 480000 USD  Maintenance and operation per year = 10 % of total cost = 48000 USD per year Alternative 1: ABB MiniCap – 3 Phase Series Capacitor Unit
  • 44. Alternative 2:  Benefits: an increase in PTC by 0.22 pu (22 MVA) at base power of 100 MVA.  Estimated annual value of benefits = 9636000 USD per year at MW/h price of 50 USD.  Construction cost per km = 180000 USD  Total initial cost = 180000 * 30 = 5400000 USD  Maintenance and operation per year = 540000 USD per year
  • 45.  PROJECT KEY MILESTONE: No. Item/Week 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1 Preparing the Progress Report 2 Submission of Progress Report 3 Poster Presentation 4 Submission Final Report’s Draft 5 Submission of Final Report
  • 46.  PROJECT TIMELINE STUDY PLAN: No. Item/Week 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1 Analysis of Project’s First Activity Data 2 Project’s Second Activity 3 Analysis of Project’s Second Activity Data 4 Project’s Third Activity 5 Analysis of Project’s Third Activity Data 6 Project’s fourth Activity
  • 48. RECOMMENDATIONS: • Series capacitors are most effective for load variations involving a high reactive content. • Overcompensation should be avoided. K = 100 % is not advised for compensating the line. • The possibility of oscillations with the downstream loads and transformers can be reduced by bypassing the capacitor bank prior to the energizing or reclosing of the distribution circuit. • The protection of the capacitor bank must be ensured by the use of overvoltage protective schemes. •
  • 50. • In this study, the use of series capacitor compensation method in distribution networks is suggested to reduce line losses, enhance voltage profile and gain the ability to increase power transfer capability through the network. • The analysis done on simulation basis proved that the technique can increase the power transfer capability and enhance voltage profile as the technique has shown high efficiency by the simulation results for the 14 Bus Electrical distribution network. • The series capacitor unit’s location impact has been proven to be slight regarding short distance lines and will not have an important impact on the network. • Economically, the technique has been justified by the use of incremental benefit cost ratio analysis associated with public sector projects. CONCLUSION:
  • 52. Q&A
  • 53. 1. T. F. Orchi, M. J. Hossain, H. R. Pota, and M. S. Rahman, "Impact of distributed generation and series compensation on distribution network," in Industrial Electronics and Applications (ICIEA), 2013 8th IEEE Conference on, 2013, pp. 854-859. 2. S. Das and D. Das, "Series capacitor compensation for radial distribution networks," in Innovative Smart Grid Technologies - India (ISGT India), 2011 IEEE PES, 2011, pp. 178-182. 3. L. Morgan, J. M. Barcus, and S. Ihara, "Distribution series capacitor with high-energy varistor protection," Power Delivery, IEEE Transactions on, vol. 8, pp. 1413-1419, 1993. 4. A. Sweden, "Series Compensation - Boosting transmission capacity," ed, 2005. 5. N. K. R. Wamkeue , J. East , Y.Boisclair, "Series Compensation for a Hydro-Quebec Long Distribution Line." 6. I. C. Report", "READER'S GUIDE TO SUBSYNCHRONOUS RESONANCE," IEEE1992. REFERENCES:
  • 54. 7. G. C. Baker, "Reconductoring power lines- an example exercise in conductor selection," in Rural Electric Power Conference, 2001, 2001, pp. D1/1-D1/6. 8. J. S. Hedin and L. H. Paulsson, "Application and evaluation of a new concept for compact series compensation for distribution networks," in Electricity Distribution, 1993. CIRED. 12th International Conference on, 1993, pp. 1.22/1-1.22/5 vol.1. 9. M. Couvreur, E. De Jaeger, P. Goossens, and A. Robert, "The concept of short-circuit power and the assessment of the flicker emission level," in Electricity Distribution, 2001. Part 1: Contributions. CIRED. 16th International Conference and Exhibition on (IEE Conf. Publ No. 482), 2001, p. 7 pp. vol.2. 10. Kaplan, S. M. (2009). Smart Grid. Electrical Power Transmission: Background and Policy Issues. The Capital.Net, Government Series. Pp. 1-42. 11. H. A. Arun Pachori , Vikendra Moranya , Associat Professor, "Static VAR Compensation Technique for IEEE 14-bus System," International Journal of Emerging Technology and Advanced Engineering, vol. Volume 3, August 2013. REFERENCES: