This document summarizes the coal loading operation from the pit stock pile through the hauling road to the Pelindo stock pile and loading onto barges. It involves:
1) Coal getting from the pit stock pile and loading onto dump trucks for hauling.
2) Hauling the coal over 80km of road to the Pelindo stock pile for stocking and crushing.
3) Loading the crushed coal onto barges using conveyors with a capacity of 2,000 tons per hour for transport.
Engineering studies were also conducted for the river, loading jetty and stockpile areas. Responsibilities for developing the Pelindo stockpile facilities are outlined.
1. Coal Loading Operation from Pit Stock Pile
through hauling road and dump to Pelindo Stock
Pile and Loading to Barge
BLACK GOLD ENERGY INDONESIA
MINING OPERATION AT RENGAT
INDRAGIRI HULU
RIAU-INDONESIA
6. Effective operating hours coal getting to pit stock pile receciving = 360 hours
Effective operating hours loading to DT at pit stock pile = 360 hours
Effective operating hauling from pit stock pile to Pelindo = 360
hours
Hauling distance from Primanusa to Pelindo is 80 Km
Coal charasteristics :
Bulk density : 0,85T/M3
Boulder size : 400 to 300 mm
Crush Coal size : 0-50 mm
Stock Pile requirements
Pit Stock Pile estimate for 7 days minimum
Pelindo stock pile expected to received 60,000 mt as Standby Stock Pile.
Loading operational 4 hours/ each 7,000 DWT barges
Working hours 20 hours/day
Jetty Operational
7. River SURVEY /BED – BASIC ENGINEERING DESIGN
Bathy metri, 35 km a long of river from Kuala Cenaku to Tembilhan
Monitoring of water level at three points of area for 15 days
Hydrometrics – Check water elevation
Current meter
Sedimentation check
Weather Station – measure wind speed and rain leverages
Cross section of river surrounding of loading jetty
Hydrology
Loading Jetty/Stock Pile and Coal Handling System – Sub structure – Basic Engineering Design
Topography for 12 Ha of area
Bathymetry Survey
Soil Investigation : deep bore hole and sondir and laboratories test for soil for total of 12 point
Conceptual design – Civil- for Sub structure and Loading Jetty, mechanical refer to Coal Handling
Design
Utilities building
Reclamation and soil improvement study and calculation for Pressure load of stock pile up to
60,000 MT
Barging Study from Kuala Cenaku up to Mother Vessel
Survey and Engineering Study
15. Flow of coal Laoding at Pelindo Stock Pile
1 2
3 4
16. Weight bridge
Stockpile no.1
Stockpile no.2
Hauling truck entering
Pelindo stock pile
Raw Coal number 1 and 2
with 30,000 MT
Capacity/each total of
60,000 MT
20. Land clearing and dozing 11 ha area to be used – Pelindo or BGE
Reclamation and soil stabilization for stock pile – Pelindo or BGE
Fencing all Pelindo property Pelindo or BGE
Permit for Constrction for Jetty/CHF Pelindo or BGE
If new Amdal need to be done Pelindo or BGE
Construction of all facilities,stock pile,CHF,Jetty
Soil protection at edges of river
Scope of Responsibility for Pelindo Stock Pile Development
21. Autocad drawing by : Ir. Aan Pujiandi
Animation by : Robby Kurniawan S.Kom
Flow diagram by : Ir.Adi Sumanto