2. Project location
• 575 km North of Santiago
• 162 km South-East of Copiapó
• 414 km south of Antofagasta
• 15 km from the Argentinean border
• 2,000 to 4,600 m above sea level
Caserones
3. • Open PitExtraction Method
• Pan Pacific Copper 78%
• Mitsui Trading 22%
Production Capacity
• Concentrate Cu (110 kt a 150 kt/yr)
• Concentrate Mo (3 kt/yr)
• Cathodes (30 - 36 mil toneladas)
Design Capacity
• 10.000 – 20.000 contractors employee (construction phase)
• 2,000 employee (operación phase – 500 own and 1,500 thirds).
Sttafing
• 1.047 millions tons of sulfur ore with an average of 0,34% Cu,
126 ppm of Mo and 296 millions ton of leached ore with an
average of 0,30% of Cut.
Reserves
Owners
Caserones Project
• Concentrate Cu (105 kt/day)
• Concentrate Mo (3 kt/yr)
• SX/EW Plant: (30 kt/yr)
4. • US$ 4,2B.Investment
• 28 yrs.Exploitation life
Water consumption
• 48 months, starting in April 2010.Construcción Period
• SX/EW Plant: March 2013
• Concentrate Plan: July 2014
Start-up
Caserones Project
• 518 lt/s.
5. Project progress
May
2006
PPC
purchases
the project
Oct 21st
2008
EIS filed
Jan 13th
2010
EIS
Approval
2012
Leaching
started
2013
1st Copper
Cathode
2033
End of
cathode
production
2010
Construction
begins
2008 – 2009
Feasibility
2007 – 2008
Prefeasibility
2014
Concentrator
Start up
2040
End of
concentrate
production
6. Not even
one flat m2
Tough climate and geography
MINIMUM WIND CHILL
(31|07|2011)
- 40 ⁰C
PLATAFORMA 4392 CURVA NEGRA
WIND
86 km/h
MAX 2013
TEMPERATURE
- 18 ⁰C
14,14 ⁰C
MIN & MAX 2013
SNOW
380 cm
TOTAL 2013
8. Now
42 Mm3 earth movement 21,000 ton structural steel 200,000 m3 concrete
1,200 mechanical equipment 1,600 km electrical cable 282 km piping
85 millions of HH + 160 companies
10. Mine Process
DRILLING
BLASTING
TRANSPORT
OXIDES TO
DUMP LEACH
SULPHIDES TO
CONCENTRATOR
WASTE
TO DUMP
LOADING
24 330-ton Komatsu trucks
2 electrical 73-yd3 shovels
1 hydraulic 56-yd3 shovel
3 33-yd3 front loaders
3 drilling machines
11. Dump Leach
• Initial Area = 1 million m2
• Final Area = 2 million m2
• Lined surface
• Irrigation rate: 2000 m3/hr
• Ore Capacity: 300 million tons
• 20 to 40 m benches
16. Tailings transport and disposal
HDPE 800 mm pipeline
Slimes dam
470 Mm3
Borrow wall
108 Mm3
Rapid
3.6 km long Tunnel
4.5 x 4.5 section
Sand deposit
360 Mm3
19. Secure stable copper / moly
supply, creating sustainable
value for our owners and
stakeholders:
3,4 mtf Copper in concentrate
449 ktf Copper cathodes
95 kt Molybdenum
Mission
What we want to achieve ....
20. Final Remarks
Successful transfer of a high altitude wetland
It´s been eight years of an on-going effort in an environment of extreme conditions
with thousands of people working with a common objective: To design and built the
Caserones project according to the highest social, environmental, safety,
engineering and construction standards.
It is an endeavour committed to a long term relationship with our stakeholders -
community, workers, suppliers, contractors and owners - with reserves that will
allow us to produce copper and molybdenum for at least 28 years through an
efficient and sustainable operation.