SlideShare a Scribd company logo
1 of 21
The Caserones Project
October 2014
Mr. Héctor Sepúlveda O.
Services Manager
SCM Minera Lumina Copper Chile
Project location
• 575 km North of Santiago
• 162 km South-East of Copiapó
• 414 km south of Antofagasta
• 15 km from the Argentinean border
• 2,000 to 4,600 m above sea level
Caserones
• Open PitExtraction Method
• Pan Pacific Copper 78%
• Mitsui Trading 22%
Production Capacity
• Concentrate Cu (110 kt a 150 kt/yr)
• Concentrate Mo (3 kt/yr)
• Cathodes (30 - 36 mil toneladas)
Design Capacity
• 10.000 – 20.000 contractors employee (construction phase)
• 2,000 employee (operación phase – 500 own and 1,500 thirds).
Sttafing
• 1.047 millions tons of sulfur ore with an average of 0,34% Cu,
126 ppm of Mo and 296 millions ton of leached ore with an
average of 0,30% of Cut.
Reserves
Owners
Caserones Project
• Concentrate Cu (105 kt/day)
• Concentrate Mo (3 kt/yr)
• SX/EW Plant: (30 kt/yr)
• US$ 4,2B.Investment
• 28 yrs.Exploitation life
Water consumption
• 48 months, starting in April 2010.Construcción Period
• SX/EW Plant: March 2013
• Concentrate Plan: July 2014
Start-up
Caserones Project
• 518 lt/s.
Project progress
May
2006
PPC
purchases
the project
Oct 21st
2008
EIS filed
Jan 13th
2010
EIS
Approval
2012
Leaching
started
2013
1st Copper
Cathode
2033
End of
cathode
production
2010
Construction
begins
2008 – 2009
Feasibility
2007 – 2008
Prefeasibility
2014
Concentrator
Start up
2040
End of
concentrate
production
Not even
one flat m2
Tough climate and geography
MINIMUM WIND CHILL
(31|07|2011)
- 40 ⁰C
PLATAFORMA 4392 CURVA NEGRA
WIND
86 km/h
MAX 2013
TEMPERATURE
- 18 ⁰C
14,14 ⁰C
MIN & MAX 2013
SNOW
380 cm
TOTAL 2013
Construction history
2010 2011
2012 2013
Now
42 Mm3 earth movement 21,000 ton structural steel 200,000 m3 concrete
1,200 mechanical equipment 1,600 km electrical cable 282 km piping
85 millions of HH + 160 companies
Process
COPPER CATHODES
PORT
WATER
SLIMES
DEPOSIT
2,800 - 3,000 masl
SANDS
DEPOSIT
3,200 - 3,600 masl
FLOTATION
GRINDING
MOLY
PLANT
COPPER
CONCENTRATE
MOLYBDENUM
CONCENTRATE
PORT
MINE
4,600 masl
DUMP LEACH
4,000 masl
PRIMARY
CRUSHER
SX-EW
CONCENTRATOR
3,900- 4,100 masl
Mine Process
DRILLING
BLASTING
TRANSPORT
OXIDES TO
DUMP LEACH
SULPHIDES TO
CONCENTRATOR
WASTE
TO DUMP
LOADING
24 330-ton Komatsu trucks
2 electrical 73-yd3 shovels
1 hydraulic 56-yd3 shovel
3 33-yd3 front loaders
3 drilling machines
Dump Leach
• Initial Area = 1 million m2
• Final Area = 2 million m2
• Lined surface
• Irrigation rate: 2000 m3/hr
• Ore Capacity: 300 million tons
• 20 to 40 m benches
SX-EW Plant (Outotec)
First Cathode
March 13th, 2013
Primary Crusher - Concentrator
Grinding - Flotation - Moly Plant - Tailings
Tailings transport and disposal
HDPE 800 mm pipeline
Slimes dam
470 Mm3
Borrow wall
108 Mm3
Rapid
3.6 km long Tunnel
4.5 x 4.5 section
Sand deposit
360 Mm3
First Ton to SAG Mill
April 17th, 2014
First Concentrate Shipment
July 16th, 2014
July 29th, 2014
Secure stable copper / moly
supply, creating sustainable
value for our owners and
stakeholders:
3,4 mtf Copper in concentrate
449 ktf Copper cathodes
95 kt Molybdenum
Mission
What we want to achieve ....
Final Remarks
Successful transfer of a high altitude wetland
It´s been eight years of an on-going effort in an environment of extreme conditions
with thousands of people working with a common objective: To design and built the
Caserones project according to the highest social, environmental, safety,
engineering and construction standards.
It is an endeavour committed to a long term relationship with our stakeholders -
community, workers, suppliers, contractors and owners - with reserves that will
allow us to produce copper and molybdenum for at least 28 years through an
efficient and sustainable operation.
THANKS

More Related Content

What's hot

02 apron feeder pans
02 apron feeder pans02 apron feeder pans
02 apron feeder pans
Fernando Zhang
 

What's hot (20)

Sistema de fijación hilti hva has
Sistema de fijación hilti hva hasSistema de fijación hilti hva has
Sistema de fijación hilti hva has
 
Manual de rendimiento de maquinaria caterpillar
Manual de rendimiento de maquinaria caterpillarManual de rendimiento de maquinaria caterpillar
Manual de rendimiento de maquinaria caterpillar
 
Catalogo rolmax ucr 200
Catalogo rolmax ucr 200Catalogo rolmax ucr 200
Catalogo rolmax ucr 200
 
Texto guia sap2000 v9
Texto guia sap2000 v9Texto guia sap2000 v9
Texto guia sap2000 v9
 
Eurocodigo une en 1990=2003-bases para el calculo estructuras
Eurocodigo une en 1990=2003-bases para el calculo estructurasEurocodigo une en 1990=2003-bases para el calculo estructuras
Eurocodigo une en 1990=2003-bases para el calculo estructuras
 
caracteristicas de los métales
caracteristicas de los métalescaracteristicas de los métales
caracteristicas de los métales
 
Astm a53 53 m-12.en.es
Astm a53 53 m-12.en.esAstm a53 53 m-12.en.es
Astm a53 53 m-12.en.es
 
Costos estimación
Costos   estimaciónCostos   estimación
Costos estimación
 
Catalogo aceros otero
Catalogo aceros oteroCatalogo aceros otero
Catalogo aceros otero
 
Presentación proyecto puente segmental 300m
Presentación proyecto puente segmental 300mPresentación proyecto puente segmental 300m
Presentación proyecto puente segmental 300m
 
Calculo puentes
Calculo   puentesCalculo   puentes
Calculo puentes
 
Pesos específico,s
Pesos específico,sPesos específico,s
Pesos específico,s
 
doblado de tubería
doblado de tubería doblado de tubería
doblado de tubería
 
CATALOGO - SCOOPTRAMS R-2900G CAT - (Español) www..oroscocat.com
CATALOGO - SCOOPTRAMS  R-2900G CAT - (Español) www..oroscocat.comCATALOGO - SCOOPTRAMS  R-2900G CAT - (Español) www..oroscocat.com
CATALOGO - SCOOPTRAMS R-2900G CAT - (Español) www..oroscocat.com
 
Catalogo de barras de cobre
Catalogo de barras de cobreCatalogo de barras de cobre
Catalogo de barras de cobre
 
Norma cmaa 70
Norma cmaa 70Norma cmaa 70
Norma cmaa 70
 
02 apron feeder pans
02 apron feeder pans02 apron feeder pans
02 apron feeder pans
 
Tuneladoras
TuneladorasTuneladoras
Tuneladoras
 
194256167 retroexcavadora-cat-420 d-420d-it
194256167 retroexcavadora-cat-420 d-420d-it194256167 retroexcavadora-cat-420 d-420d-it
194256167 retroexcavadora-cat-420 d-420d-it
 
6. ventiladores
6.  ventiladores6.  ventiladores
6. ventiladores
 

Similar to The caserones project

Longwall - China & India
Longwall - China & IndiaLongwall - China & India
Longwall - China & India
VR M
 
Pwc basics-of-mining-2-som-mining-methods
Pwc basics-of-mining-2-som-mining-methodsPwc basics-of-mining-2-som-mining-methods
Pwc basics-of-mining-2-som-mining-methods
Azzuhry Smallville
 
Valgma backfilling technologies for estonian oil shale mines(2)
Valgma backfilling technologies for estonian oil shale mines(2)Valgma backfilling technologies for estonian oil shale mines(2)
Valgma backfilling technologies for estonian oil shale mines(2)
Ingo Valgma
 
Demzy's Presentation on HDD
Demzy's Presentation on HDDDemzy's Presentation on HDD
Demzy's Presentation on HDD
Demzy George
 
61904252-ONGC-ANKLESHWAR-ASSET.pptx
61904252-ONGC-ANKLESHWAR-ASSET.pptx61904252-ONGC-ANKLESHWAR-ASSET.pptx
61904252-ONGC-ANKLESHWAR-ASSET.pptx
Vevietpomata
 

Similar to The caserones project (20)

Massive Advantage in Mining - Using Scrapers for Efficient Material Transport...
Massive Advantage in Mining - Using Scrapers for Efficient Material Transport...Massive Advantage in Mining - Using Scrapers for Efficient Material Transport...
Massive Advantage in Mining - Using Scrapers for Efficient Material Transport...
 
Gold mine Mialy in Kazakhstan[821].pptx
Gold mine Mialy in Kazakhstan[821].pptxGold mine Mialy in Kazakhstan[821].pptx
Gold mine Mialy in Kazakhstan[821].pptx
 
Longwall - China & India
Longwall - China & IndiaLongwall - China & India
Longwall - China & India
 
Extending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningExtending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine Planning
 
Tipong report
Tipong report Tipong report
Tipong report
 
training and excursion
training and excursiontraining and excursion
training and excursion
 
Jonathan Mulosa ET'Al
Jonathan Mulosa ET'AlJonathan Mulosa ET'Al
Jonathan Mulosa ET'Al
 
Pwc basics-of-mining-2-som-mining-methods
Pwc basics-of-mining-2-som-mining-methodsPwc basics-of-mining-2-som-mining-methods
Pwc basics-of-mining-2-som-mining-methods
 
Innovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngInnovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellng
 
Valgma backfilling technologies for estonian oil shale mines(2)
Valgma backfilling technologies for estonian oil shale mines(2)Valgma backfilling technologies for estonian oil shale mines(2)
Valgma backfilling technologies for estonian oil shale mines(2)
 
THERMAL POWER PLANT AND COAL HANDLING
THERMAL POWER PLANT AND COAL HANDLING THERMAL POWER PLANT AND COAL HANDLING
THERMAL POWER PLANT AND COAL HANDLING
 
attcofinal
attcofinalattcofinal
attcofinal
 
Coal Lectures Series Mining Technology Presentation
Coal Lectures Series   Mining Technology PresentationCoal Lectures Series   Mining Technology Presentation
Coal Lectures Series Mining Technology Presentation
 
Coal Lectures Series Mining Technology
Coal Lectures Series   Mining TechnologyCoal Lectures Series   Mining Technology
Coal Lectures Series Mining Technology
 
Demzy's Presentation on HDD
Demzy's Presentation on HDDDemzy's Presentation on HDD
Demzy's Presentation on HDD
 
International Montoro Resources, Fact Sheet April 2014
International Montoro Resources, Fact Sheet April 2014International Montoro Resources, Fact Sheet April 2014
International Montoro Resources, Fact Sheet April 2014
 
61904252-ONGC-ANKLESHWAR-ASSET.pptx
61904252-ONGC-ANKLESHWAR-ASSET.pptx61904252-ONGC-ANKLESHWAR-ASSET.pptx
61904252-ONGC-ANKLESHWAR-ASSET.pptx
 
The university of zambia presentation (immanuel 2016)
The university of zambia presentation (immanuel 2016)The university of zambia presentation (immanuel 2016)
The university of zambia presentation (immanuel 2016)
 
Takraf ipcc 2014_compressed
Takraf ipcc 2014_compressedTakraf ipcc 2014_compressed
Takraf ipcc 2014_compressed
 
Coal mine Presentation (1).pptx
Coal mine Presentation (1).pptxCoal mine Presentation (1).pptx
Coal mine Presentation (1).pptx
 

Recently uploaded

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 

Recently uploaded (20)

Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic Marks
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086
 

The caserones project

  • 1. The Caserones Project October 2014 Mr. Héctor Sepúlveda O. Services Manager SCM Minera Lumina Copper Chile
  • 2. Project location • 575 km North of Santiago • 162 km South-East of Copiapó • 414 km south of Antofagasta • 15 km from the Argentinean border • 2,000 to 4,600 m above sea level Caserones
  • 3. • Open PitExtraction Method • Pan Pacific Copper 78% • Mitsui Trading 22% Production Capacity • Concentrate Cu (110 kt a 150 kt/yr) • Concentrate Mo (3 kt/yr) • Cathodes (30 - 36 mil toneladas) Design Capacity • 10.000 – 20.000 contractors employee (construction phase) • 2,000 employee (operación phase – 500 own and 1,500 thirds). Sttafing • 1.047 millions tons of sulfur ore with an average of 0,34% Cu, 126 ppm of Mo and 296 millions ton of leached ore with an average of 0,30% of Cut. Reserves Owners Caserones Project • Concentrate Cu (105 kt/day) • Concentrate Mo (3 kt/yr) • SX/EW Plant: (30 kt/yr)
  • 4. • US$ 4,2B.Investment • 28 yrs.Exploitation life Water consumption • 48 months, starting in April 2010.Construcción Period • SX/EW Plant: March 2013 • Concentrate Plan: July 2014 Start-up Caserones Project • 518 lt/s.
  • 5. Project progress May 2006 PPC purchases the project Oct 21st 2008 EIS filed Jan 13th 2010 EIS Approval 2012 Leaching started 2013 1st Copper Cathode 2033 End of cathode production 2010 Construction begins 2008 – 2009 Feasibility 2007 – 2008 Prefeasibility 2014 Concentrator Start up 2040 End of concentrate production
  • 6. Not even one flat m2 Tough climate and geography MINIMUM WIND CHILL (31|07|2011) - 40 ⁰C PLATAFORMA 4392 CURVA NEGRA WIND 86 km/h MAX 2013 TEMPERATURE - 18 ⁰C 14,14 ⁰C MIN & MAX 2013 SNOW 380 cm TOTAL 2013
  • 8. Now 42 Mm3 earth movement 21,000 ton structural steel 200,000 m3 concrete 1,200 mechanical equipment 1,600 km electrical cable 282 km piping 85 millions of HH + 160 companies
  • 9. Process COPPER CATHODES PORT WATER SLIMES DEPOSIT 2,800 - 3,000 masl SANDS DEPOSIT 3,200 - 3,600 masl FLOTATION GRINDING MOLY PLANT COPPER CONCENTRATE MOLYBDENUM CONCENTRATE PORT MINE 4,600 masl DUMP LEACH 4,000 masl PRIMARY CRUSHER SX-EW CONCENTRATOR 3,900- 4,100 masl
  • 10. Mine Process DRILLING BLASTING TRANSPORT OXIDES TO DUMP LEACH SULPHIDES TO CONCENTRATOR WASTE TO DUMP LOADING 24 330-ton Komatsu trucks 2 electrical 73-yd3 shovels 1 hydraulic 56-yd3 shovel 3 33-yd3 front loaders 3 drilling machines
  • 11. Dump Leach • Initial Area = 1 million m2 • Final Area = 2 million m2 • Lined surface • Irrigation rate: 2000 m3/hr • Ore Capacity: 300 million tons • 20 to 40 m benches
  • 14. Primary Crusher - Concentrator
  • 15. Grinding - Flotation - Moly Plant - Tailings
  • 16. Tailings transport and disposal HDPE 800 mm pipeline Slimes dam 470 Mm3 Borrow wall 108 Mm3 Rapid 3.6 km long Tunnel 4.5 x 4.5 section Sand deposit 360 Mm3
  • 17. First Ton to SAG Mill April 17th, 2014
  • 18. First Concentrate Shipment July 16th, 2014 July 29th, 2014
  • 19. Secure stable copper / moly supply, creating sustainable value for our owners and stakeholders: 3,4 mtf Copper in concentrate 449 ktf Copper cathodes 95 kt Molybdenum Mission What we want to achieve ....
  • 20. Final Remarks Successful transfer of a high altitude wetland It´s been eight years of an on-going effort in an environment of extreme conditions with thousands of people working with a common objective: To design and built the Caserones project according to the highest social, environmental, safety, engineering and construction standards. It is an endeavour committed to a long term relationship with our stakeholders - community, workers, suppliers, contractors and owners - with reserves that will allow us to produce copper and molybdenum for at least 28 years through an efficient and sustainable operation.

Editor's Notes

  1. <number>
  2. <number>
  3. <number>
  4. <number>
  5. <number>
  6. <number>
  7. <number>