SlideShare a Scribd company logo
1 of 18
PACMAN
Simulation II
PACMAN
Chief Engineer
Peiyi Huo
Chief Operations Manager
Chirag Agarwal
Chief Architect
Abide Masaraure
Team Strategy: Identify the enemies, befriend them and then stealthily attack .
● Overview 1 & 2
● Choosing the Contract
● Ordering machines
● Choosing the safety stock
● Selecting the reorder point
● Selecting the order quantity I and II
● Maintaining contracts
● The unmanned spacecraft
● Lessons Learned
● Acknowledgment and thanks
Agenda
● This was an exciting and a highly contested simulation
Our goals were to:
● increase the team revenue with minimal risk
● increase our team position in the overall standings
●learn more about purchasing, lot sizing and how to
maintain supplier contracts
Overview 1
gg
pacman
maniacs
ads123
kgs
ideaco csuite
Closing cash balance $2 406 931
Overview 2- Changes Summary
● Switched to contact 2 on Day 54
● Contract 2 offered better revenues compared
to contract 1
Choosing the contracts
● Machines were ordered the same day
we entered into Contract 2
● We had enough cash to purchase the machines
● One more machine was added to each of
the three stations
Ordering machines
Safety Stock
● (Max Daily Usage − Avg Daily Usage) × Lead Time* Service Factor
● Used the safety stock to calculate the optimal order
quantity
Determining safety stock
● Point was changed on day 55
● Job queues were increasing because the inventory
was out of stock
Choosing the reorder point
● Calculated the optimal order quantity to
minimize costs
● On day 63 order quantity was changed to
14400 kits by doubling current order quantity
Selecting the order quantity I
Selecting the order quantity II
● The optimal solution is was to order for 3 times in the next 81 days.
● So the order quantity was be changed to 12.5*27=337.5338batches=20280 kits
● Utilization station under each station was well under 0.5
● This enabled us to choose contract three which
paid $1250 per job
●Contracts were interchanged between 2 and 3
according to the changes in queue sizes through the
rest of the simulation
Maintaining the contracts
● Ceased to use contract 1 and 2 after
day 132
● Revenue averaged 1200 from day
80 using contract three
Revenue Analysis
● On day 70 scheduling rule of station 2 was set to priority step 4
● This was due to a number of jobs queuing on station 1
● 2 days later priority was changed back to FIFO and the queue size of station 1
was well close to 0.1 in the next coming days
Scheduling Analysis
Station 2 QueueStation 1 Queue Station 3 Queue
● Last 50 days in space - Getting the right fuel
The unmanned Spacecraft
● Accurately forecasting demand
● Calculating the the reorder point
● Determining the reorder quantity
● Minimizing inventory costs
● Maintaining supplier and service contracts
Lessons Learned
● Thanks to the Professor for her efforts in delivering the course.
● Thanks to the PACMAN team for your hard work.
● To the MBE class…. It was fun to be in the program with you.
● And thumbs up to our enemy, team gg.
Acknowledgment and thanks
Question and Answer Session

More Related Content

Viewers also liked

Littlefield Simulation
Littlefield Simulation Littlefield Simulation
Littlefield Simulation Kamal Gelya
 
Pacman
PacmanPacman
PacmanJeroen
 
Pacman para scratch
Pacman para scratchPacman para scratch
Pacman para scratchAna Zyanya
 
Creative Teaching with Scratch
Creative Teaching with ScratchCreative Teaching with Scratch
Creative Teaching with ScratchDouglas Kiang
 
Southeast asian music grade 8 first quarter
Southeast asian music grade 8 first quarterSoutheast asian music grade 8 first quarter
Southeast asian music grade 8 first quarterElmer Llames
 
Music of the mangyan mindoro
Music of the mangyan mindoroMusic of the mangyan mindoro
Music of the mangyan mindoroArniel Salinasal
 
How I got 2.5 Million views on Slideshare (by @nickdemey - Board of Innovation)
How I got 2.5 Million views on Slideshare (by @nickdemey - Board of Innovation)How I got 2.5 Million views on Slideshare (by @nickdemey - Board of Innovation)
How I got 2.5 Million views on Slideshare (by @nickdemey - Board of Innovation)Board of Innovation
 
The Seven Deadly Social Media Sins
The Seven Deadly Social Media SinsThe Seven Deadly Social Media Sins
The Seven Deadly Social Media SinsXPLAIN
 
Five Killer Ways to Design The Same Slide
Five Killer Ways to Design The Same SlideFive Killer Ways to Design The Same Slide
Five Killer Ways to Design The Same SlideCrispy Presentations
 
How People Really Hold and Touch (their Phones)
How People Really Hold and Touch (their Phones)How People Really Hold and Touch (their Phones)
How People Really Hold and Touch (their Phones)Steven Hoober
 
Upworthy: 10 Ways To Win The Internets
Upworthy: 10 Ways To Win The InternetsUpworthy: 10 Ways To Win The Internets
Upworthy: 10 Ways To Win The InternetsUpworthy
 
What 33 Successful Entrepreneurs Learned From Failure
What 33 Successful Entrepreneurs Learned From FailureWhat 33 Successful Entrepreneurs Learned From Failure
What 33 Successful Entrepreneurs Learned From FailureReferralCandy
 
Why Content Marketing Fails
Why Content Marketing FailsWhy Content Marketing Fails
Why Content Marketing FailsRand Fishkin
 

Viewers also liked (20)

Littlefield Simulation
Littlefield Simulation Littlefield Simulation
Littlefield Simulation
 
Pacman
PacmanPacman
Pacman
 
Pacman
PacmanPacman
Pacman
 
PacMan Rebourn
PacMan RebournPacMan Rebourn
PacMan Rebourn
 
Pacman animacion
Pacman animacionPacman animacion
Pacman animacion
 
Pacman para scratch
Pacman para scratchPacman para scratch
Pacman para scratch
 
Creative Teaching with Scratch
Creative Teaching with ScratchCreative Teaching with Scratch
Creative Teaching with Scratch
 
Southeast asian music grade 8 first quarter
Southeast asian music grade 8 first quarterSoutheast asian music grade 8 first quarter
Southeast asian music grade 8 first quarter
 
Music of palawan
Music of palawanMusic of palawan
Music of palawan
 
Music History
Music HistoryMusic History
Music History
 
Music of the mangyan mindoro
Music of the mangyan mindoroMusic of the mangyan mindoro
Music of the mangyan mindoro
 
The Minimum Loveable Product
The Minimum Loveable ProductThe Minimum Loveable Product
The Minimum Loveable Product
 
How I got 2.5 Million views on Slideshare (by @nickdemey - Board of Innovation)
How I got 2.5 Million views on Slideshare (by @nickdemey - Board of Innovation)How I got 2.5 Million views on Slideshare (by @nickdemey - Board of Innovation)
How I got 2.5 Million views on Slideshare (by @nickdemey - Board of Innovation)
 
The Seven Deadly Social Media Sins
The Seven Deadly Social Media SinsThe Seven Deadly Social Media Sins
The Seven Deadly Social Media Sins
 
Five Killer Ways to Design The Same Slide
Five Killer Ways to Design The Same SlideFive Killer Ways to Design The Same Slide
Five Killer Ways to Design The Same Slide
 
How People Really Hold and Touch (their Phones)
How People Really Hold and Touch (their Phones)How People Really Hold and Touch (their Phones)
How People Really Hold and Touch (their Phones)
 
Upworthy: 10 Ways To Win The Internets
Upworthy: 10 Ways To Win The InternetsUpworthy: 10 Ways To Win The Internets
Upworthy: 10 Ways To Win The Internets
 
What 33 Successful Entrepreneurs Learned From Failure
What 33 Successful Entrepreneurs Learned From FailureWhat 33 Successful Entrepreneurs Learned From Failure
What 33 Successful Entrepreneurs Learned From Failure
 
Design Your Career 2018
Design Your Career 2018Design Your Career 2018
Design Your Career 2018
 
Why Content Marketing Fails
Why Content Marketing FailsWhy Content Marketing Fails
Why Content Marketing Fails
 

Similar to PACMAN Simulation 2 Report

OM II_Group 9_MRF.pptx
OM II_Group 9_MRF.pptxOM II_Group 9_MRF.pptx
OM II_Group 9_MRF.pptxArpitaMandal22
 
Cost calculation of cnc machining operation
Cost calculation of cnc machining operationCost calculation of cnc machining operation
Cost calculation of cnc machining operationAbdul Kader
 
CV_Ananta_Halder_Stnd.
CV_Ananta_Halder_Stnd.CV_Ananta_Halder_Stnd.
CV_Ananta_Halder_Stnd.Ananta Halder
 
Sanjeewa_CV updated on 16.05.2014
Sanjeewa_CV  updated on 16.05.2014Sanjeewa_CV  updated on 16.05.2014
Sanjeewa_CV updated on 16.05.2014Sanjeewa Mahawedage
 
Schneider Case Study Challenge
Schneider Case Study ChallengeSchneider Case Study Challenge
Schneider Case Study ChallengeNikhil Kejriwal
 
Track Software -- Shell presentation
Track Software -- Shell presentationTrack Software -- Shell presentation
Track Software -- Shell presentationtracksoftware
 
Mapotempo - ISMP 2018 : Modelling the Periodic Vehicle Routing Problem in an ...
Mapotempo - ISMP 2018 : Modelling the Periodic Vehicle Routing Problem in an ...Mapotempo - ISMP 2018 : Modelling the Periodic Vehicle Routing Problem in an ...
Mapotempo - ISMP 2018 : Modelling the Periodic Vehicle Routing Problem in an ...Manon Bouly
 
manufacturing resource planning
manufacturing resource planningmanufacturing resource planning
manufacturing resource planningDinesh Nikam
 
Agile Development with Agile Contract
Agile Development with Agile ContractAgile Development with Agile Contract
Agile Development with Agile ContractNUS-ISS
 
Know how to oversee building services work
Know how to oversee building services workKnow how to oversee building services work
Know how to oversee building services workcatherinelindsay
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Processarpantripathi2
 
Quick Start to Field Service Lightning, Paweł Dobrzynski
Quick Start to Field Service Lightning, Paweł DobrzynskiQuick Start to Field Service Lightning, Paweł Dobrzynski
Quick Start to Field Service Lightning, Paweł DobrzynskiCzechDreamin
 
Transmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesTransmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesMANTHAN CHAUHAN
 

Similar to PACMAN Simulation 2 Report (20)

OM II_Group 9_MRF.pptx
OM II_Group 9_MRF.pptxOM II_Group 9_MRF.pptx
OM II_Group 9_MRF.pptx
 
Iy3416321635
Iy3416321635Iy3416321635
Iy3416321635
 
Cost calculation of cnc machining operation
Cost calculation of cnc machining operationCost calculation of cnc machining operation
Cost calculation of cnc machining operation
 
CV_Ananta_Halder_Stnd.
CV_Ananta_Halder_Stnd.CV_Ananta_Halder_Stnd.
CV_Ananta_Halder_Stnd.
 
Sanjeewa_CV updated on 16.05.2014
Sanjeewa_CV  updated on 16.05.2014Sanjeewa_CV  updated on 16.05.2014
Sanjeewa_CV updated on 16.05.2014
 
DonnerCompany
DonnerCompanyDonnerCompany
DonnerCompany
 
Smart factory Presentation
Smart factory PresentationSmart factory Presentation
Smart factory Presentation
 
Schneider Case Study Challenge
Schneider Case Study ChallengeSchneider Case Study Challenge
Schneider Case Study Challenge
 
Agile contracts
Agile contractsAgile contracts
Agile contracts
 
Track Software -- Shell presentation
Track Software -- Shell presentationTrack Software -- Shell presentation
Track Software -- Shell presentation
 
Resume
ResumeResume
Resume
 
Mapotempo - ISMP 2018 : Modelling the Periodic Vehicle Routing Problem in an ...
Mapotempo - ISMP 2018 : Modelling the Periodic Vehicle Routing Problem in an ...Mapotempo - ISMP 2018 : Modelling the Periodic Vehicle Routing Problem in an ...
Mapotempo - ISMP 2018 : Modelling the Periodic Vehicle Routing Problem in an ...
 
manufacturing resource planning
manufacturing resource planningmanufacturing resource planning
manufacturing resource planning
 
Agile Development with Agile Contract
Agile Development with Agile ContractAgile Development with Agile Contract
Agile Development with Agile Contract
 
Know how to oversee building services work
Know how to oversee building services workKnow how to oversee building services work
Know how to oversee building services work
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Process
 
Om2
Om2Om2
Om2
 
Nec3 introduction
Nec3 introductionNec3 introduction
Nec3 introduction
 
Quick Start to Field Service Lightning, Paweł Dobrzynski
Quick Start to Field Service Lightning, Paweł DobrzynskiQuick Start to Field Service Lightning, Paweł Dobrzynski
Quick Start to Field Service Lightning, Paweł Dobrzynski
 
Transmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesTransmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission Lines
 

PACMAN Simulation 2 Report

  • 2. PACMAN Chief Engineer Peiyi Huo Chief Operations Manager Chirag Agarwal Chief Architect Abide Masaraure Team Strategy: Identify the enemies, befriend them and then stealthily attack .
  • 3. ● Overview 1 & 2 ● Choosing the Contract ● Ordering machines ● Choosing the safety stock ● Selecting the reorder point ● Selecting the order quantity I and II ● Maintaining contracts ● The unmanned spacecraft ● Lessons Learned ● Acknowledgment and thanks Agenda
  • 4. ● This was an exciting and a highly contested simulation Our goals were to: ● increase the team revenue with minimal risk ● increase our team position in the overall standings ●learn more about purchasing, lot sizing and how to maintain supplier contracts Overview 1 gg pacman maniacs ads123 kgs ideaco csuite Closing cash balance $2 406 931
  • 6. ● Switched to contact 2 on Day 54 ● Contract 2 offered better revenues compared to contract 1 Choosing the contracts
  • 7. ● Machines were ordered the same day we entered into Contract 2 ● We had enough cash to purchase the machines ● One more machine was added to each of the three stations Ordering machines
  • 8. Safety Stock ● (Max Daily Usage − Avg Daily Usage) × Lead Time* Service Factor ● Used the safety stock to calculate the optimal order quantity Determining safety stock
  • 9. ● Point was changed on day 55 ● Job queues were increasing because the inventory was out of stock Choosing the reorder point
  • 10. ● Calculated the optimal order quantity to minimize costs ● On day 63 order quantity was changed to 14400 kits by doubling current order quantity Selecting the order quantity I
  • 11. Selecting the order quantity II ● The optimal solution is was to order for 3 times in the next 81 days. ● So the order quantity was be changed to 12.5*27=337.5338batches=20280 kits
  • 12. ● Utilization station under each station was well under 0.5 ● This enabled us to choose contract three which paid $1250 per job ●Contracts were interchanged between 2 and 3 according to the changes in queue sizes through the rest of the simulation Maintaining the contracts
  • 13. ● Ceased to use contract 1 and 2 after day 132 ● Revenue averaged 1200 from day 80 using contract three Revenue Analysis
  • 14. ● On day 70 scheduling rule of station 2 was set to priority step 4 ● This was due to a number of jobs queuing on station 1 ● 2 days later priority was changed back to FIFO and the queue size of station 1 was well close to 0.1 in the next coming days Scheduling Analysis Station 2 QueueStation 1 Queue Station 3 Queue
  • 15. ● Last 50 days in space - Getting the right fuel The unmanned Spacecraft
  • 16. ● Accurately forecasting demand ● Calculating the the reorder point ● Determining the reorder quantity ● Minimizing inventory costs ● Maintaining supplier and service contracts Lessons Learned
  • 17. ● Thanks to the Professor for her efforts in delivering the course. ● Thanks to the PACMAN team for your hard work. ● To the MBE class…. It was fun to be in the program with you. ● And thumbs up to our enemy, team gg. Acknowledgment and thanks