SlideShare a Scribd company logo
1 of 49
Download to read offline
Construction
                 of
         Telecom Towers-
      Quality and Productivity
           Improvement
                 Final Presentation
BTP Guide:                            Presented By:
Prof. K N Satyanarayana               N S B Syam
Dept. of Civil Engineering            CE05B038
Introduction
• In the next three to four years, telecom companies
  (Telco's) will need another 100,000 towers and the
  industry estimates that at least 60 per cent of this
  will be built by independent operators.

• The development of the Infrastructure segment in
  our country is associated with many issues like poor
  quality, lack of safety concerns, cost overruns and
  project delays due to inefficient project planning and
  control.

                                                           2
• Prominent telecom infrastructure companies -
  Reliance Communications, Bharti/Airtel, Vodafone,
  Idea Cellular, Aircel Ltd, MTNL, BSNL, VSNL etc.

• Independent telecom infrastructure companies -Tata,
  ATC (American Tower Corp), Indus Towers, Quippo
  Telecom and GTL Infra Ltd.




                                                      3
Objectives
• Basic study on contracting procedures, quality, cost, time,
  and productivity issues in telecom tower construction
  industry.

• Suggesting productivity improvement methods using
  logistics in terms of supply chain management and
  process mapping of the whole construction process.

• Identifying the underlying issues and suggestions for
  quality in the construction of communication towers.



                                                          4
Scope
• The study is limited only to address the construction
  related issues. Design related issues are not in the scope
  of the study.

• The study is limited to construction of telecom towers in
  and around Chennai.

• The study is focused on contracting procedures, quality
  problems, cost overruns, project delays in the
  construction of telecom towers and developing a logistics
  model in terms of supply chain management.

                                                               5
Methodology
• Discussions with experts in telecom towers construction
  industry.

• Interviews of client representatives, contractor
  representatives and site supervisors.

• Study and analysis of data collected from the on-going
  projects.

• Developing a Logistics model to map the construction
  process in terms of the supply chain management.
                                                            6
• Study required extensive site visits, to collect data from
  the concerned personnel and to identify the key issues
  prevalent in the construction of telecom towers.

• Fifteen sites were visited as a part of this project.

• Three main types of issues identified:
   • Quality of the construction process
   • Schedule of the construction process.
   • Productivity of the construction process



                                                               7
Quality Issues
Broadly classified into 7 categories based on site
data and interviews conducted

   –   Material/Equipment Availability
   –   Formwork/Reinforcement
   –   Geotechnical Issues
   –   Issues related to Concrete
   –   Structural Issues
   –   Labor Issues
   –   Site Management Issues

                                                     8
Issues Vs. No. of sites

                                    RTT         GBT
                    Issues        (Total:8)   (Total:7)

Material/Equipment Availability      2           3
Formwork/Reinforcement               7           7
Geotechnical Issues                   -          4
Concrete related Issues              8           7
Structural Issues                    4           3
Labor Issues                         8           7
Site Management Issues               5           7




                                                          9
Material/Equipment Availability
• Aggregates, Sand, Cement

• Steel for reinforcement

• Labor

• Pump for water pumping

• Vibrator for concrete

• Pulleys and bolts for tower erection

• Rubber soling to prevent seepage of water from underneath the
  foundation


                                                                  10
Formwork/Reinforcement
•       Quality of shuttering material
•       Irregularity of Foundation bolts
•       Leveling of formwork
•       Inadequate development lengths for column
        extension
    •    Required Ld is 200mm but available length was 75mm.

• Congested Reinforcement
• Early removal of formwork
                                                               11
12
13
14
15
Geotechnical Issues
• Soil Investigations
  • IS 6403- Code of Practice for determining Bearing Capacity of
    Shallow Foundation
  • Sufficient number of undisturbed samples of 40-100mm ø are
    required for testing
  • Budget for soil test on a 6mx12m site is Rs.8000

• Lack of laboratory in vicinity

• Achieving required depth for foundation
  • IS 1080-1985- Code of Practice foe Design and Construction of
    Shallow Foundation in Soils
  • Min. required foundation depth is 3m

• Validity of the soil test report when compared to
  the actual conditions
                                                                    16
17
Concrete
• Proper mix design
   – IS 10262: Code of Practice for Concrete Mix Design

• Concrete cover for bolts/members
   – Min. cover in Chennai not less than 45mm

• Improper Maintenance/Finishing

• Segregation & Honeycombing
   – Honeycombing noticed in all the sites visited

• Lack of proper cube testing for checking concrete strength
   – IS 4031-1968 – 28 day compressive strength( Appendix C, Clause 3.8) M20
     Grade
   – IS 9013-1978 – Accelerated curing method for determination of compressive
     strength
                                                                           18
19
20
21
Structural Inadequacies –Constructability issues

  • Missing Bracings/Fasteners
    – IS 204 (Part 1) :1991- Tower Bolts Specifications


  • Movement of foundation

  • Ad hock site modifications

  • Template Setting
                                                          22
23
24
25
Labor
• Poor skill of labor

• Safety rules not followed at sites
  – SP 70:2001 Handbook on Construction Safety Practices


• Lack of coordination among labor



                                                           26
Site Management Issues
• Supervision at sites

• Drawings/reports of tests

• Poor Handling & Storage of materials

• Accessing the site

                                         27
Scheduling Issues
 Labor

 Unavailability of supervisors

 Timely availability of material/equipment

 Weather

 Holidays

 No written work schedule

                                              28
Average Schedule of a 15m RTT-34 days duration




                                                 29
Slowest Completed Schedule of a 15m RTT-56 days duration




                                                           30
Fastest Completed Schedule of a 15m RTT-22 days duration




                                                           31
Analysis of RTT schedules
• 30 days difference between slowest and
  fastest completed towers
  – Delay of 18-21 days due to material availability
  – Delay of 3-4 days due to the delay between the installation
    of the tower equipment after the tower framework is
    erected
  – Delay of 2-3 days is caused due to the prolonged
    installation period of the telecom equipment
  – Delay of 2-3 days is caused in between the tower
    installation and the tower being on air

                                                             32
Average Schedule of a 30m GBT-47 days duration




                                                 33
Slowest Completed Schedule of a 30m GBT-65 days duration




                                                           34
Fastest Completed Schedule of a 30m GBT-34 days duration




                                                           35
Analysis of GBT schedules
• Difference of 31 days between the fastest and
  the slowest completed towers
  – Delay of 19-21 days caused due to supply of construction
    material, tower material and the telecom equipment
  – Delay of 2-3 days between each of the foundation levels
  – Delay of 5-7 days between the installation of the tower
    and the completion of the tower foundation




                                                               36
Process Mapping
1. What is Process Mapping?

2. Why are we applying Process Mapping?

3. How is it useful in this project?




                                          37
Process Mapping is a powerful tool that offers an in-depth
understanding of any given process, finds effective ways for that
process to be more successful, and ensures that true value is
being provided to the client/customer.

There are four major steps of Process Mapping
   – Process identification – attaining a full understanding of all the steps
     of a process.
   – Information gathering – identifying objectives, risks and key controls in
     a process.
   – Interviewing and mapping – understanding the point of view of
     individuals in the process and designing actual maps.
   – Analysis – utilizing tools and approaches to make the process run
     more effectively and efficiently.

Back

                                                                            38
• Process Mapping is used in this project to identify the different
  processes that constitute the telecom tower construction.

• Helps in increasing the productivity of the overall process by
  focusing on the processes that need rework for their improvement.

• Telecom tower construction consists of a lot of processes ranging
  from Radio Frequency survey to the handing over of the completed
  tower on air.

• It allows all the individuals working on the project to gain a better
  understanding of that process with a simple, yet powerful approach
  that anyone can utilize.


Back


                                                                      39
Area of business being reviewed: Telecom tower construction
                                                   Trigger Events                                       Process Name
                 Growth of mobile phone users in the country. Need for better networking and RF Survey
                 hence construction of telecom towers. Survey done to locate the right
                 locations for the tower constructions.
                 Optimal location of tower site for better reach of customers.                   Site Identification/ Land
                                                                                                 Acquisition
                 Drawings for the construction of towers.                                        Layout Plans
   Process       Type of foundation needed for GBTs for the construction. The structural
                 stability of the existing structure for RTTs.
                                                                                                 Soil Investigation/
                                                                                                 Structural Stability
Identification   Protection and to prevent trespassing and misuse of the tower, fencing and      Fencing, Compound wall,
                 guard room to be constructed. Safety and protection of tower.                   Guard Room, DG Slab,
 Worksheet                                                                                       Shelter Foundation
                 Construction materials like, steel, sand, cement, aggregates for the tower      Tower Supply & Erection
                 foundation construction, tower fabrication set for tower material and
                 equipment like vibrator, pulleys for tower erection.
                 Diesel Generator set installation which is the key component of the tower       DG set installation
                 construction.
                 Shelter for the security guard and to store maintenance parts for emergency     Shelter Supply & Erection
                 replacement of parts of the tower.
                 Earthing to prevent damage by lighting and electrical works in order to ensure Electrical- Indoor, Outdoor
                 proper functioning of the antennae.                                             and Earthing
                 Backup power options for the transmission of signals.                           AC installation, Battery,
                                                                                                 PIU
                 Need for a base station to receive and transmit signals.                        Installation of BTS
                 Need for the transmission of signals.                                           Antennae Installation
                 Connections of antennae to the electrical systems for proper functioning of the RF Cable Routing
                 system.

                                                                                                                      40
Comprehensive Business Time Line Worksheet
Telecom Tower Construction



                                              Site Identification/Land
                                               Site Identification/Land
       Surveying




                            RF Survey
      Surveying




                             RF Survey               Acquisition
                                                      Acquisition

                             Tender 1-
                                              Tender 2- Company D
                            Company C
       Civil Works
      Civil Works




                                                   Soil Investigation/Structural Stability
                                                    Soil Investigation/Structural Stability   Fencing/Compound Wall, DG Slab, Shelter
                                                                                               Fencing/Compound Wall, DG Slab, Shelter     Tower
                              Layout Plans
                               Layout Plans                       Analysis
                                                                   Analysis                                Foundation
                                                                                                            Foundation                   Foundation

                                                                                    Tender 3 – Company A
  Electrical & Mechanical
 Electrical & Mechanical




                               Tower Supply &
                                Tower Supply &            Shelter Supply &
                                                           Shelter Supply &         Electrical- Indoor, Outdoor and
                                                                                     Electrical- Indoor, Outdoor and
                                  Erection
                                   Erection                  Erection
                                                               Erection                          Earthing
                                                                                                  Earthing
            Works
          Works




                                                               Tender 3 – Company A
       Telecom Works
      Telecom Works




                               AC Installation,
                                AC Installation,      Installation of
                                                       Installation of       Antennae
                                                                              Antennae          RF Cable
                                                                                                 RF Cable         Wi-max
                                                                                                                   Wi-max
                                Battery, PIU
                                 Battery, PIU              BTS
                                                            BTS             Installation
                                                                             Installation        Routing
                                                                                                  Routing       Installation
                                                                                                                 Installation

                                                             Tender 4 – OEMs – Company B




                                                                                                                                                      41
Process Name and Number                             Process Owner
                  RF survey : 1                                       Principal Companies/Telecom Companies
                  Description :
                  The ultimate goal of a RF site survey is to supply enough information to determine the number and
                  placement of access points that provides adequate coverage throughout the facility. In most
                  implementations, "adequate coverage" means support of a minimum data rate. A RF site survey also
                  detects the presence of interference coming from other sources that could degrade the performance of the
                  wireless LAN.
                  Triggers

Process Profile   Event Beginning: Call for tenders for RF surveying.
                  Event Ending Process: Document findings of the sites best suitable for telecom tower construction.

  Worksheet       Additional Events: Call for tenders for more than 1 company to save time. For 100 sites to be RF
                  surveyed, 10 companies could finish the survey in 10 times less time than the survey being done by a
                  single company.
                  Inputs – Items and Sources
                  Surveying equipment like Theodolite, GPS, Satellites
                  Outputs – Items and Sources
                  Optimal location of sites for the construction of telecom towers
                  Process Units                                       Process Unit Owners
                  Obtain a site facility diagram                      Telecommunication Companies
                  Visually inspect the site facility
                  Identify cellular phone user areas
                  Determine preliminary site access point locations
                  Verify site access point

                  Business Objectives                                 Business Risks
                  Location of sites which offer better transmission   Time consuming and tiring process. A slight change
                  of signals and networking                           in the site location may not yield transmission signals.
                                                                      Accuracy is very important.
                  Key Controls                                        Measure of Success
                  Skilled usage of GPS systems and accuracy of        Best fit site which can ideally transmit and receive
                  the instruments.                                    signals with maximum efficiency.               42
Tower Construction
    Initiation            Site Identification/                              Structural Stability
                                                  Type of Tower       RTT
                          Land Acquisition                                       Analysis



                                                       GBT
    RF survey

                          Negotiations with
                                                 Soil Investigation
                     No      the owner



  Obtain an area
  facility diagram

                             Successful                                                                   Tower and Shelter
     Visually                Negotiation                                                                   Material Supply
                                                  Common Civil
     inspect                                         works
        the
      facility                   Yes
       area
                           Land acquired for
                          tower construction
      Identify                                                                                                Formwork and
      cellular                                        Guard                                                   Reinforcement
       phone                                          Room
        user                                        foundation
       areas


                            Layout Plans                                                                       Concreting

     Determine                                       Fencing
preliminary access
  point locations


                                                                                                    Tower
                                                                                                     and
                                                                                                                            DG set
                                                                                                   Shelter
      Verify                                      Superstructure
                                                                                                   Erection
      access                                       of the guard
      points                                           room




                                                                                                                   A


                                                                                                                                     43
Telecom
                                              Installations
                    A




                                               Antennae
                Electrical                    Installation




                                        GSM                   Microwave
  Indoor                     Outdoor




                                              Installation
                             Routing            of PIU,
Installation
                               of               power
  of RBS
                             cables             backup




                                              Site on air
 Fixing of
   cable                     Clamping
  ladder




Installation
 of rectifier                Ground/
and battery                  Earthing
    bank




                                                                          44
Suggestions
•   Prior stacking of materials at the job site
•   Adequate supervision
•   More labor compared to peak labor requirement
•   Use of process charts and work schedules
•   Safety equipment
•   Use of vibrator and other equipment to prevent segregation
    and honeycombing
•   Use of system formwork
•   Grouting of bolts
•   Leveling of beams, columns and template settings
•   Centralized warehouse catering the needs of each
    construction site
                                                                 45
References
•   Dileep R. S, 2001, Logistics of Facility Location and Allocation, United States of America, Marcel Dekker, Inc.
•   Jacka, M J., 2002, Business Process Mapping, United States of America, John Wiley & Sons, Inc.
•   LakshmiNag P (2006), Productivity Issues in Construction of Steel Communication Towers, Bachelor of Technology Thesis,
    Indian Institute of Technology Madras, Chennai
•   Kumar S, 2006-Types and Design of Steel Towers, Structural Steel Design, Indian Institute of Technology, Madras,
    http://nptel.iitm.ac.in/courses/IIT-MADRAS/Design_Steel_Structures_II, (accessed May 2006)
•   IS 204 Part 2 :1992 – Tower Bolts Specifications
•   IS 456 (2000) – Plain and Reinforced Concrete-Code of Practice
•   IS 800 (2007) - General Construction in Steel–Code of Practice
•   IS 802 (Part 1/Sec 2): 1992 – Use of Structural Steel in Overhead Transmission Line Towers- Code of Practice
•   IS 806: 1988 - Code of Practice for use of Steel Tubes in General Building Construction
•   IS 10262 – Recommended Guidelines for Concrete Mix Design
•   IS 875 Part 3: 1987 – Code of Practice for Design Loads for Buildings and Structures
•   IS 4091-1979 – Code of Practice for Design and Construction of Transmission Lines and Poles
•   Chetan, 2007, Civil Construction Issues, Proceedings of workshop conducted for M/s GTL Infra Ltd., Indian Institute of
    Techology Madras, Chennai, Nov 3rd 2007
•   Gandhi S R, 2007, Geotechnical Issues related to Telecommunication Tower Construction, Proceedings of workshop
    conducted for M/s GTL Infra Ltd., Indian Institute of Techology Madras, Chennai, Nov 3rd 2007



                                                                                                                       46
•   Gettu R, 2007, Concrete Properties, Proceedings of workshop conducted for M/s GTL Infra Ltd., Indian Institute of
    Techology Madras, Chennai, Nov 2nd 2007
•   Kalyanraman, 2007, A Review of Steel Tower Skeleton System, Proceedings of workshop conducted for M/s GTL Infra Ltd.,
    Indian Institute of Techology Madras, Chennai, Nov 3rd 2007
•   Menon, 2007, Fixing of Ground Based and Roof Top Towers-Structural Issues, Proceedings of workshop conducted for M/s
    GTL Infra Ltd., Indian Institute of Techology Madras, Chennai, Nov 2nd 2007
•   Advantages and disadvantages of tubular and angular towers, http://www.monsterfm.com/tech/tower/towerspecs.htm#top
    (accessed April 2009)
•   Estimate of Cell sites construction 2007, http://www.airtel.in/wps/wcm/connect/ (accessed January 2009)
•   Indian Telecom Sector Analysis (2006-2007), http://www.rncos.com/Report/IM073.htm (accessed November 2008)
•   ITU World Telecommunication base indicator 2007, www.itu.int (accessed October,2008)
•   Site Installation, http://www.topcomco.com/civil_work.htm (accessed March 2009)
•   Site Survey, http://www.topcomco.com/site_survey.htm (accessed January 2009)
•   Structural changes in the Indian Steel Industry 2003, http://jpcindiansteel.nic.in/structure.asp (accessed December 2008)
•   Tower design specifications, http://www.rajessh.com/towerdesignspecifications (accessed February 2009)
•   Tower materials, http://www.topcomco.com/ti.htm (accessed April 2009)
•   Tower specifications, http://www.monsterfm.com/tech/tower/towerspecs.htm (accessed January 2009)
•   Why cell tower business is booming?, www.financialexpress.com/news/whys-cell-tower-business-booming/407427/
    (accessed April 2009)




                                                                                                                                47
THANK YOU

            48
Back
       49

More Related Content

What's hot

Construction EHV Transmission Line
Construction EHV Transmission LineConstruction EHV Transmission Line
Construction EHV Transmission LineSURESH GOPAL
 
Construction Material Management
Construction Material ManagementConstruction Material Management
Construction Material ManagementPriya Ramaraj
 
Electrical Transmission Tower: Types, Design and Parts
Electrical Transmission Tower: Types, Design and  PartsElectrical Transmission Tower: Types, Design and  Parts
Electrical Transmission Tower: Types, Design and PartsDr.Raja R
 
Pre qualification stages and tender selection
Pre qualification stages and tender selectionPre qualification stages and tender selection
Pre qualification stages and tender selectionanojan kanagarathnam
 
Microwave Tower Presentation.ppt
Microwave Tower Presentation.pptMicrowave Tower Presentation.ppt
Microwave Tower Presentation.pptRuturajJadhav25
 
EDUARDO H. PARE CV - CIRCA - 04.07.2021
EDUARDO H. PARE CV - CIRCA - 04.07.2021EDUARDO H. PARE CV - CIRCA - 04.07.2021
EDUARDO H. PARE CV - CIRCA - 04.07.2021Eduardo H. Pare
 
Inspection & Test Plan - Electrical Power Distribution System - Q1447-CS-PCP-...
Inspection & Test Plan - Electrical Power Distribution System - Q1447-CS-PCP-...Inspection & Test Plan - Electrical Power Distribution System - Q1447-CS-PCP-...
Inspection & Test Plan - Electrical Power Distribution System - Q1447-CS-PCP-...Gary Hayes
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 
QAQC MEP HVAC INSPECTOR
QAQC MEP HVAC INSPECTORQAQC MEP HVAC INSPECTOR
QAQC MEP HVAC INSPECTORMurugan Pillai
 
CV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerCV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerSankar Sundaram PMP
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
PROJECTS-RELAIBILITY-MAINTENANCE CV
PROJECTS-RELAIBILITY-MAINTENANCE CVPROJECTS-RELAIBILITY-MAINTENANCE CV
PROJECTS-RELAIBILITY-MAINTENANCE CVMAHMOOD AHMED
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & EquipmentsGAURAV. H .TANDON
 
Civil Engineer & Inspector
Civil Engineer & InspectorCivil Engineer & Inspector
Civil Engineer & InspectorMOHAMED RASHEED
 
Hossam(civil structural engineer) cover letter+cv-resume-3-09-2015
Hossam(civil structural engineer) cover letter+cv-resume-3-09-2015Hossam(civil structural engineer) cover letter+cv-resume-3-09-2015
Hossam(civil structural engineer) cover letter+cv-resume-3-09-2015Hossameldin Ahmed
 
HV tower design 3
HV tower design 3HV tower design 3
HV tower design 3Thy Khy
 

What's hot (20)

Construction EHV Transmission Line
Construction EHV Transmission LineConstruction EHV Transmission Line
Construction EHV Transmission Line
 
Cv Piping Engineer
Cv Piping EngineerCv Piping Engineer
Cv Piping Engineer
 
Construction Material Management
Construction Material ManagementConstruction Material Management
Construction Material Management
 
Electrical Transmission Tower: Types, Design and Parts
Electrical Transmission Tower: Types, Design and  PartsElectrical Transmission Tower: Types, Design and  Parts
Electrical Transmission Tower: Types, Design and Parts
 
Pre qualification stages and tender selection
Pre qualification stages and tender selectionPre qualification stages and tender selection
Pre qualification stages and tender selection
 
Microwave Tower Presentation.ppt
Microwave Tower Presentation.pptMicrowave Tower Presentation.ppt
Microwave Tower Presentation.ppt
 
EDUARDO H. PARE CV - CIRCA - 04.07.2021
EDUARDO H. PARE CV - CIRCA - 04.07.2021EDUARDO H. PARE CV - CIRCA - 04.07.2021
EDUARDO H. PARE CV - CIRCA - 04.07.2021
 
Inspection & Test Plan - Electrical Power Distribution System - Q1447-CS-PCP-...
Inspection & Test Plan - Electrical Power Distribution System - Q1447-CS-PCP-...Inspection & Test Plan - Electrical Power Distribution System - Q1447-CS-PCP-...
Inspection & Test Plan - Electrical Power Distribution System - Q1447-CS-PCP-...
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
QAQC MEP HVAC INSPECTOR
QAQC MEP HVAC INSPECTORQAQC MEP HVAC INSPECTOR
QAQC MEP HVAC INSPECTOR
 
Construction Supervising Site Engineer - Duties & Responsibilities
Construction Supervising Site Engineer - Duties & ResponsibilitiesConstruction Supervising Site Engineer - Duties & Responsibilities
Construction Supervising Site Engineer - Duties & Responsibilities
 
CV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerCV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning Engineer
 
Construction contract
Construction contract Construction contract
Construction contract
 
PROJECTS-RELAIBILITY-MAINTENANCE CV
PROJECTS-RELAIBILITY-MAINTENANCE CVPROJECTS-RELAIBILITY-MAINTENANCE CV
PROJECTS-RELAIBILITY-MAINTENANCE CV
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & Equipments
 
Project Planning & Control Engineer
Project Planning & Control EngineerProject Planning & Control Engineer
Project Planning & Control Engineer
 
Types of-tower
Types of-towerTypes of-tower
Types of-tower
 
Civil Engineer & Inspector
Civil Engineer & InspectorCivil Engineer & Inspector
Civil Engineer & Inspector
 
Hossam(civil structural engineer) cover letter+cv-resume-3-09-2015
Hossam(civil structural engineer) cover letter+cv-resume-3-09-2015Hossam(civil structural engineer) cover letter+cv-resume-3-09-2015
Hossam(civil structural engineer) cover letter+cv-resume-3-09-2015
 
HV tower design 3
HV tower design 3HV tower design 3
HV tower design 3
 

Viewers also liked

analysis and design of telecommunication tower
analysis and design of telecommunication toweranalysis and design of telecommunication tower
analysis and design of telecommunication towerRohithasangaraju
 
Cell tower, BTS & antennas
Cell tower, BTS & antennasCell tower, BTS & antennas
Cell tower, BTS & antennasnimay1
 
Project ManagementOf Telecom Project A Case Study
Project ManagementOf Telecom Project A Case StudyProject ManagementOf Telecom Project A Case Study
Project ManagementOf Telecom Project A Case StudyDjadja Sardjana
 
Bts installation & commisioning.ppt
Bts installation & commisioning.pptBts installation & commisioning.ppt
Bts installation & commisioning.pptAIRTEL
 
Telecommunication Tower
Telecommunication TowerTelecommunication Tower
Telecommunication Towerayishairshad
 
Bts-site-installation
 Bts-site-installation Bts-site-installation
Bts-site-installationAli Usman
 

Viewers also liked (6)

analysis and design of telecommunication tower
analysis and design of telecommunication toweranalysis and design of telecommunication tower
analysis and design of telecommunication tower
 
Cell tower, BTS & antennas
Cell tower, BTS & antennasCell tower, BTS & antennas
Cell tower, BTS & antennas
 
Project ManagementOf Telecom Project A Case Study
Project ManagementOf Telecom Project A Case StudyProject ManagementOf Telecom Project A Case Study
Project ManagementOf Telecom Project A Case Study
 
Bts installation & commisioning.ppt
Bts installation & commisioning.pptBts installation & commisioning.ppt
Bts installation & commisioning.ppt
 
Telecommunication Tower
Telecommunication TowerTelecommunication Tower
Telecommunication Tower
 
Bts-site-installation
 Bts-site-installation Bts-site-installation
Bts-site-installation
 

Similar to Construction of telecommunication towers

Management Control System- Delhi Metro_10042016
Management Control System- Delhi Metro_10042016Management Control System- Delhi Metro_10042016
Management Control System- Delhi Metro_10042016Anil Kumar Gupta
 
ETDP 2015 D1 The Digitally Enabling Electrification Project - Atkins & Laing ...
ETDP 2015 D1 The Digitally Enabling Electrification Project - Atkins & Laing ...ETDP 2015 D1 The Digitally Enabling Electrification Project - Atkins & Laing ...
ETDP 2015 D1 The Digitally Enabling Electrification Project - Atkins & Laing ...Comit Projects Ltd
 
Summer Internship in Jaypee Group
Summer Internship in Jaypee Group Summer Internship in Jaypee Group
Summer Internship in Jaypee Group Abhimanyu Saraswat
 
Mouyadin moumin abdillahi.pptx
Mouyadin moumin abdillahi.pptxMouyadin moumin abdillahi.pptx
Mouyadin moumin abdillahi.pptxZakaria156221
 
Constructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportConstructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportDivyesh Mungara
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System ashleyyeap
 
Rapid construction techniques
Rapid construction techniques Rapid construction techniques
Rapid construction techniques Deepak Pradhan
 
Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphbhlksd
 
Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zachary Maddox
 
Why 3D Laser Scanning Technology Lowers Brownfield Capital Construction Costs
Why 3D Laser Scanning Technology Lowers Brownfield Capital Construction CostsWhy 3D Laser Scanning Technology Lowers Brownfield Capital Construction Costs
Why 3D Laser Scanning Technology Lowers Brownfield Capital Construction CostsAVEVA Group plc
 
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi LabbanFiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi LabbanCCT International
 
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSISFORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSISIRJET Journal
 
Muthukumar Civil engineer resume UPDATED (1).pdf
Muthukumar Civil engineer resume UPDATED (1).pdfMuthukumar Civil engineer resume UPDATED (1).pdf
Muthukumar Civil engineer resume UPDATED (1).pdfMUTHUKUMAR428109
 
A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...
A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...
A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...Shabaz Khan
 
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...IRJET Journal
 
CV_PARTHA_PRATIM_GORAIN_18th_dec_2015
CV_PARTHA_PRATIM_GORAIN_18th_dec_2015CV_PARTHA_PRATIM_GORAIN_18th_dec_2015
CV_PARTHA_PRATIM_GORAIN_18th_dec_2015Partha Gorain
 

Similar to Construction of telecommunication towers (20)

Management Control System- Delhi Metro_10042016
Management Control System- Delhi Metro_10042016Management Control System- Delhi Metro_10042016
Management Control System- Delhi Metro_10042016
 
AH15019
AH15019AH15019
AH15019
 
ETDP 2015 D1 The Digitally Enabling Electrification Project - Atkins & Laing ...
ETDP 2015 D1 The Digitally Enabling Electrification Project - Atkins & Laing ...ETDP 2015 D1 The Digitally Enabling Electrification Project - Atkins & Laing ...
ETDP 2015 D1 The Digitally Enabling Electrification Project - Atkins & Laing ...
 
Katleho P LETELE CV with picture
Katleho P LETELE CV with pictureKatleho P LETELE CV with picture
Katleho P LETELE CV with picture
 
Summer Internship in Jaypee Group
Summer Internship in Jaypee Group Summer Internship in Jaypee Group
Summer Internship in Jaypee Group
 
Mouyadin moumin abdillahi.pptx
Mouyadin moumin abdillahi.pptxMouyadin moumin abdillahi.pptx
Mouyadin moumin abdillahi.pptx
 
Constructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportConstructionmethodologyandprojectmanagementreport
Constructionmethodologyandprojectmanagementreport
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
Site report
Site reportSite report
Site report
 
Rapid construction techniques
Rapid construction techniques Rapid construction techniques
Rapid construction techniques
 
Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphb
 
Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01
 
Why 3D Laser Scanning Technology Lowers Brownfield Capital Construction Costs
Why 3D Laser Scanning Technology Lowers Brownfield Capital Construction CostsWhy 3D Laser Scanning Technology Lowers Brownfield Capital Construction Costs
Why 3D Laser Scanning Technology Lowers Brownfield Capital Construction Costs
 
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi LabbanFiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
 
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSISFORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
FORMWORK TECHNOLOGY IN HIGH-RISE BUILDING ITS COST AND QUALITY ANALYSIS
 
Muthukumar Civil engineer resume UPDATED (1).pdf
Muthukumar Civil engineer resume UPDATED (1).pdfMuthukumar Civil engineer resume UPDATED (1).pdf
Muthukumar Civil engineer resume UPDATED (1).pdf
 
CV
CVCV
CV
 
A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...
A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...
A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...
 
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
 
CV_PARTHA_PRATIM_GORAIN_18th_dec_2015
CV_PARTHA_PRATIM_GORAIN_18th_dec_2015CV_PARTHA_PRATIM_GORAIN_18th_dec_2015
CV_PARTHA_PRATIM_GORAIN_18th_dec_2015
 

More from snookala

Membrane Enhanced Biological Phosphorous Removal
Membrane Enhanced Biological Phosphorous RemovalMembrane Enhanced Biological Phosphorous Removal
Membrane Enhanced Biological Phosphorous Removalsnookala
 
Oil Recovery And Disaster Strategies
Oil Recovery And Disaster StrategiesOil Recovery And Disaster Strategies
Oil Recovery And Disaster Strategiessnookala
 
VAR in Construction
VAR in ConstructionVAR in Construction
VAR in Constructionsnookala
 
GIS in Construction
GIS in ConstructionGIS in Construction
GIS in Constructionsnookala
 
Composite material
Composite materialComposite material
Composite materialsnookala
 
Construction Simulation
Construction SimulationConstruction Simulation
Construction Simulationsnookala
 
Innovation Capacity in India
Innovation Capacity in IndiaInnovation Capacity in India
Innovation Capacity in Indiasnookala
 

More from snookala (7)

Membrane Enhanced Biological Phosphorous Removal
Membrane Enhanced Biological Phosphorous RemovalMembrane Enhanced Biological Phosphorous Removal
Membrane Enhanced Biological Phosphorous Removal
 
Oil Recovery And Disaster Strategies
Oil Recovery And Disaster StrategiesOil Recovery And Disaster Strategies
Oil Recovery And Disaster Strategies
 
VAR in Construction
VAR in ConstructionVAR in Construction
VAR in Construction
 
GIS in Construction
GIS in ConstructionGIS in Construction
GIS in Construction
 
Composite material
Composite materialComposite material
Composite material
 
Construction Simulation
Construction SimulationConstruction Simulation
Construction Simulation
 
Innovation Capacity in India
Innovation Capacity in IndiaInnovation Capacity in India
Innovation Capacity in India
 

Construction of telecommunication towers

  • 1. Construction of Telecom Towers- Quality and Productivity Improvement Final Presentation BTP Guide: Presented By: Prof. K N Satyanarayana N S B Syam Dept. of Civil Engineering CE05B038
  • 2. Introduction • In the next three to four years, telecom companies (Telco's) will need another 100,000 towers and the industry estimates that at least 60 per cent of this will be built by independent operators. • The development of the Infrastructure segment in our country is associated with many issues like poor quality, lack of safety concerns, cost overruns and project delays due to inefficient project planning and control. 2
  • 3. • Prominent telecom infrastructure companies - Reliance Communications, Bharti/Airtel, Vodafone, Idea Cellular, Aircel Ltd, MTNL, BSNL, VSNL etc. • Independent telecom infrastructure companies -Tata, ATC (American Tower Corp), Indus Towers, Quippo Telecom and GTL Infra Ltd. 3
  • 4. Objectives • Basic study on contracting procedures, quality, cost, time, and productivity issues in telecom tower construction industry. • Suggesting productivity improvement methods using logistics in terms of supply chain management and process mapping of the whole construction process. • Identifying the underlying issues and suggestions for quality in the construction of communication towers. 4
  • 5. Scope • The study is limited only to address the construction related issues. Design related issues are not in the scope of the study. • The study is limited to construction of telecom towers in and around Chennai. • The study is focused on contracting procedures, quality problems, cost overruns, project delays in the construction of telecom towers and developing a logistics model in terms of supply chain management. 5
  • 6. Methodology • Discussions with experts in telecom towers construction industry. • Interviews of client representatives, contractor representatives and site supervisors. • Study and analysis of data collected from the on-going projects. • Developing a Logistics model to map the construction process in terms of the supply chain management. 6
  • 7. • Study required extensive site visits, to collect data from the concerned personnel and to identify the key issues prevalent in the construction of telecom towers. • Fifteen sites were visited as a part of this project. • Three main types of issues identified: • Quality of the construction process • Schedule of the construction process. • Productivity of the construction process 7
  • 8. Quality Issues Broadly classified into 7 categories based on site data and interviews conducted – Material/Equipment Availability – Formwork/Reinforcement – Geotechnical Issues – Issues related to Concrete – Structural Issues – Labor Issues – Site Management Issues 8
  • 9. Issues Vs. No. of sites RTT GBT Issues (Total:8) (Total:7) Material/Equipment Availability 2 3 Formwork/Reinforcement 7 7 Geotechnical Issues - 4 Concrete related Issues 8 7 Structural Issues 4 3 Labor Issues 8 7 Site Management Issues 5 7 9
  • 10. Material/Equipment Availability • Aggregates, Sand, Cement • Steel for reinforcement • Labor • Pump for water pumping • Vibrator for concrete • Pulleys and bolts for tower erection • Rubber soling to prevent seepage of water from underneath the foundation 10
  • 11. Formwork/Reinforcement • Quality of shuttering material • Irregularity of Foundation bolts • Leveling of formwork • Inadequate development lengths for column extension • Required Ld is 200mm but available length was 75mm. • Congested Reinforcement • Early removal of formwork 11
  • 12. 12
  • 13. 13
  • 14. 14
  • 15. 15
  • 16. Geotechnical Issues • Soil Investigations • IS 6403- Code of Practice for determining Bearing Capacity of Shallow Foundation • Sufficient number of undisturbed samples of 40-100mm ø are required for testing • Budget for soil test on a 6mx12m site is Rs.8000 • Lack of laboratory in vicinity • Achieving required depth for foundation • IS 1080-1985- Code of Practice foe Design and Construction of Shallow Foundation in Soils • Min. required foundation depth is 3m • Validity of the soil test report when compared to the actual conditions 16
  • 17. 17
  • 18. Concrete • Proper mix design – IS 10262: Code of Practice for Concrete Mix Design • Concrete cover for bolts/members – Min. cover in Chennai not less than 45mm • Improper Maintenance/Finishing • Segregation & Honeycombing – Honeycombing noticed in all the sites visited • Lack of proper cube testing for checking concrete strength – IS 4031-1968 – 28 day compressive strength( Appendix C, Clause 3.8) M20 Grade – IS 9013-1978 – Accelerated curing method for determination of compressive strength 18
  • 19. 19
  • 20. 20
  • 21. 21
  • 22. Structural Inadequacies –Constructability issues • Missing Bracings/Fasteners – IS 204 (Part 1) :1991- Tower Bolts Specifications • Movement of foundation • Ad hock site modifications • Template Setting 22
  • 23. 23
  • 24. 24
  • 25. 25
  • 26. Labor • Poor skill of labor • Safety rules not followed at sites – SP 70:2001 Handbook on Construction Safety Practices • Lack of coordination among labor 26
  • 27. Site Management Issues • Supervision at sites • Drawings/reports of tests • Poor Handling & Storage of materials • Accessing the site 27
  • 28. Scheduling Issues  Labor  Unavailability of supervisors  Timely availability of material/equipment  Weather  Holidays  No written work schedule 28
  • 29. Average Schedule of a 15m RTT-34 days duration 29
  • 30. Slowest Completed Schedule of a 15m RTT-56 days duration 30
  • 31. Fastest Completed Schedule of a 15m RTT-22 days duration 31
  • 32. Analysis of RTT schedules • 30 days difference between slowest and fastest completed towers – Delay of 18-21 days due to material availability – Delay of 3-4 days due to the delay between the installation of the tower equipment after the tower framework is erected – Delay of 2-3 days is caused due to the prolonged installation period of the telecom equipment – Delay of 2-3 days is caused in between the tower installation and the tower being on air 32
  • 33. Average Schedule of a 30m GBT-47 days duration 33
  • 34. Slowest Completed Schedule of a 30m GBT-65 days duration 34
  • 35. Fastest Completed Schedule of a 30m GBT-34 days duration 35
  • 36. Analysis of GBT schedules • Difference of 31 days between the fastest and the slowest completed towers – Delay of 19-21 days caused due to supply of construction material, tower material and the telecom equipment – Delay of 2-3 days between each of the foundation levels – Delay of 5-7 days between the installation of the tower and the completion of the tower foundation 36
  • 37. Process Mapping 1. What is Process Mapping? 2. Why are we applying Process Mapping? 3. How is it useful in this project? 37
  • 38. Process Mapping is a powerful tool that offers an in-depth understanding of any given process, finds effective ways for that process to be more successful, and ensures that true value is being provided to the client/customer. There are four major steps of Process Mapping – Process identification – attaining a full understanding of all the steps of a process. – Information gathering – identifying objectives, risks and key controls in a process. – Interviewing and mapping – understanding the point of view of individuals in the process and designing actual maps. – Analysis – utilizing tools and approaches to make the process run more effectively and efficiently. Back 38
  • 39. • Process Mapping is used in this project to identify the different processes that constitute the telecom tower construction. • Helps in increasing the productivity of the overall process by focusing on the processes that need rework for their improvement. • Telecom tower construction consists of a lot of processes ranging from Radio Frequency survey to the handing over of the completed tower on air. • It allows all the individuals working on the project to gain a better understanding of that process with a simple, yet powerful approach that anyone can utilize. Back 39
  • 40. Area of business being reviewed: Telecom tower construction Trigger Events Process Name Growth of mobile phone users in the country. Need for better networking and RF Survey hence construction of telecom towers. Survey done to locate the right locations for the tower constructions. Optimal location of tower site for better reach of customers. Site Identification/ Land Acquisition Drawings for the construction of towers. Layout Plans Process Type of foundation needed for GBTs for the construction. The structural stability of the existing structure for RTTs. Soil Investigation/ Structural Stability Identification Protection and to prevent trespassing and misuse of the tower, fencing and Fencing, Compound wall, guard room to be constructed. Safety and protection of tower. Guard Room, DG Slab, Worksheet Shelter Foundation Construction materials like, steel, sand, cement, aggregates for the tower Tower Supply & Erection foundation construction, tower fabrication set for tower material and equipment like vibrator, pulleys for tower erection. Diesel Generator set installation which is the key component of the tower DG set installation construction. Shelter for the security guard and to store maintenance parts for emergency Shelter Supply & Erection replacement of parts of the tower. Earthing to prevent damage by lighting and electrical works in order to ensure Electrical- Indoor, Outdoor proper functioning of the antennae. and Earthing Backup power options for the transmission of signals. AC installation, Battery, PIU Need for a base station to receive and transmit signals. Installation of BTS Need for the transmission of signals. Antennae Installation Connections of antennae to the electrical systems for proper functioning of the RF Cable Routing system. 40
  • 41. Comprehensive Business Time Line Worksheet Telecom Tower Construction Site Identification/Land Site Identification/Land Surveying RF Survey Surveying RF Survey Acquisition Acquisition Tender 1- Tender 2- Company D Company C Civil Works Civil Works Soil Investigation/Structural Stability Soil Investigation/Structural Stability Fencing/Compound Wall, DG Slab, Shelter Fencing/Compound Wall, DG Slab, Shelter Tower Layout Plans Layout Plans Analysis Analysis Foundation Foundation Foundation Tender 3 – Company A Electrical & Mechanical Electrical & Mechanical Tower Supply & Tower Supply & Shelter Supply & Shelter Supply & Electrical- Indoor, Outdoor and Electrical- Indoor, Outdoor and Erection Erection Erection Erection Earthing Earthing Works Works Tender 3 – Company A Telecom Works Telecom Works AC Installation, AC Installation, Installation of Installation of Antennae Antennae RF Cable RF Cable Wi-max Wi-max Battery, PIU Battery, PIU BTS BTS Installation Installation Routing Routing Installation Installation Tender 4 – OEMs – Company B 41
  • 42. Process Name and Number Process Owner RF survey : 1 Principal Companies/Telecom Companies Description : The ultimate goal of a RF site survey is to supply enough information to determine the number and placement of access points that provides adequate coverage throughout the facility. In most implementations, "adequate coverage" means support of a minimum data rate. A RF site survey also detects the presence of interference coming from other sources that could degrade the performance of the wireless LAN. Triggers Process Profile Event Beginning: Call for tenders for RF surveying. Event Ending Process: Document findings of the sites best suitable for telecom tower construction. Worksheet Additional Events: Call for tenders for more than 1 company to save time. For 100 sites to be RF surveyed, 10 companies could finish the survey in 10 times less time than the survey being done by a single company. Inputs – Items and Sources Surveying equipment like Theodolite, GPS, Satellites Outputs – Items and Sources Optimal location of sites for the construction of telecom towers Process Units Process Unit Owners Obtain a site facility diagram Telecommunication Companies Visually inspect the site facility Identify cellular phone user areas Determine preliminary site access point locations Verify site access point Business Objectives Business Risks Location of sites which offer better transmission Time consuming and tiring process. A slight change of signals and networking in the site location may not yield transmission signals. Accuracy is very important. Key Controls Measure of Success Skilled usage of GPS systems and accuracy of Best fit site which can ideally transmit and receive the instruments. signals with maximum efficiency. 42
  • 43. Tower Construction Initiation Site Identification/ Structural Stability Type of Tower RTT Land Acquisition Analysis GBT RF survey Negotiations with Soil Investigation No the owner Obtain an area facility diagram Successful Tower and Shelter Visually Negotiation Material Supply Common Civil inspect works the facility Yes area Land acquired for tower construction Identify Formwork and cellular Guard Reinforcement phone Room user foundation areas Layout Plans Concreting Determine Fencing preliminary access point locations Tower and DG set Shelter Verify Superstructure Erection access of the guard points room A 43
  • 44. Telecom Installations A Antennae Electrical Installation GSM Microwave Indoor Outdoor Installation Routing of PIU, Installation of power of RBS cables backup Site on air Fixing of cable Clamping ladder Installation of rectifier Ground/ and battery Earthing bank 44
  • 45. Suggestions • Prior stacking of materials at the job site • Adequate supervision • More labor compared to peak labor requirement • Use of process charts and work schedules • Safety equipment • Use of vibrator and other equipment to prevent segregation and honeycombing • Use of system formwork • Grouting of bolts • Leveling of beams, columns and template settings • Centralized warehouse catering the needs of each construction site 45
  • 46. References • Dileep R. S, 2001, Logistics of Facility Location and Allocation, United States of America, Marcel Dekker, Inc. • Jacka, M J., 2002, Business Process Mapping, United States of America, John Wiley & Sons, Inc. • LakshmiNag P (2006), Productivity Issues in Construction of Steel Communication Towers, Bachelor of Technology Thesis, Indian Institute of Technology Madras, Chennai • Kumar S, 2006-Types and Design of Steel Towers, Structural Steel Design, Indian Institute of Technology, Madras, http://nptel.iitm.ac.in/courses/IIT-MADRAS/Design_Steel_Structures_II, (accessed May 2006) • IS 204 Part 2 :1992 – Tower Bolts Specifications • IS 456 (2000) – Plain and Reinforced Concrete-Code of Practice • IS 800 (2007) - General Construction in Steel–Code of Practice • IS 802 (Part 1/Sec 2): 1992 – Use of Structural Steel in Overhead Transmission Line Towers- Code of Practice • IS 806: 1988 - Code of Practice for use of Steel Tubes in General Building Construction • IS 10262 – Recommended Guidelines for Concrete Mix Design • IS 875 Part 3: 1987 – Code of Practice for Design Loads for Buildings and Structures • IS 4091-1979 – Code of Practice for Design and Construction of Transmission Lines and Poles • Chetan, 2007, Civil Construction Issues, Proceedings of workshop conducted for M/s GTL Infra Ltd., Indian Institute of Techology Madras, Chennai, Nov 3rd 2007 • Gandhi S R, 2007, Geotechnical Issues related to Telecommunication Tower Construction, Proceedings of workshop conducted for M/s GTL Infra Ltd., Indian Institute of Techology Madras, Chennai, Nov 3rd 2007 46
  • 47. Gettu R, 2007, Concrete Properties, Proceedings of workshop conducted for M/s GTL Infra Ltd., Indian Institute of Techology Madras, Chennai, Nov 2nd 2007 • Kalyanraman, 2007, A Review of Steel Tower Skeleton System, Proceedings of workshop conducted for M/s GTL Infra Ltd., Indian Institute of Techology Madras, Chennai, Nov 3rd 2007 • Menon, 2007, Fixing of Ground Based and Roof Top Towers-Structural Issues, Proceedings of workshop conducted for M/s GTL Infra Ltd., Indian Institute of Techology Madras, Chennai, Nov 2nd 2007 • Advantages and disadvantages of tubular and angular towers, http://www.monsterfm.com/tech/tower/towerspecs.htm#top (accessed April 2009) • Estimate of Cell sites construction 2007, http://www.airtel.in/wps/wcm/connect/ (accessed January 2009) • Indian Telecom Sector Analysis (2006-2007), http://www.rncos.com/Report/IM073.htm (accessed November 2008) • ITU World Telecommunication base indicator 2007, www.itu.int (accessed October,2008) • Site Installation, http://www.topcomco.com/civil_work.htm (accessed March 2009) • Site Survey, http://www.topcomco.com/site_survey.htm (accessed January 2009) • Structural changes in the Indian Steel Industry 2003, http://jpcindiansteel.nic.in/structure.asp (accessed December 2008) • Tower design specifications, http://www.rajessh.com/towerdesignspecifications (accessed February 2009) • Tower materials, http://www.topcomco.com/ti.htm (accessed April 2009) • Tower specifications, http://www.monsterfm.com/tech/tower/towerspecs.htm (accessed January 2009) • Why cell tower business is booming?, www.financialexpress.com/news/whys-cell-tower-business-booming/407427/ (accessed April 2009) 47
  • 48. THANK YOU 48
  • 49. Back 49